Change Order No. 01-013-003 C H A N G E 0 R D E R - Droject: KJ - NEW DETENTION FACILITY To Contractor: NORMENT IND./G.B.MANCHESTER 3224 MOBILE HIGHWAY MONTGOMERY, AL - Change Order Number: 01-013-003 Change Order Date: 08/05/93 Architect's Project #: 36108-4400 Contract For: SECURITY SYSTEMS Contract Date: 04/01/92 You are directed to make the following changes in this contract; aLL other provisions of the contract shaLl, except as specifically changed herein, remain in fuLL force and effect. Issue: 068 - POMCO DELAY In accordance with the April 9, 1993 updated master schedule and Paragraph 8.3.1 of the Contract Supplementary General Conditions, the Contract Substantial CompLetion Date is extended to November 1, 1993 at no additional cost, due to project deLays resulting from the fabrication and erection of the precast concrete. . ~...., z w % ~c \.C5 v; c::J c-: -\ ~:J --..; :r .-- \0 .:..:. \.51 Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work 'and alL related impacts due to this contract change for the LUMP SUM AMOUNT of $ 0.00 and 123 days. The Original Contract Amount was .................... ......................... .... ................... $ Net Change by Previously Authorized Change Orders .................................................... $ The Contract Amount prior to this Change was ......................................................... $ The Va l ue of th i s Change Order is.................................................................... $ The New Contract Amount including this Change Order wiLL be .......................................... $ The Contract Time wi II change by ..................................................................... The Date of Substantial Completion as of the Date of this Change Order is ............................ 1,471,000.00 119,145.00 1,590,145.00 0.00 1,590,145.00 123 days 11/01/93 Recommended by Construction Manager: Approved by Architect: Morrison-Knudsen/Gerrits 5090 College Road Key West, Fl 3304 HAN EN LIND MEYER 80 Magnolia A~~ o l 0 ~ .32* ,866 By 7.J Agreed to by Contractor: Authorized by Owner: Approved As 01/f3 D e y Board of County Commissioners ad Stree ~ -- ~ " La ~ Date L Sufficiency: A t: D~':nCLerk By -~G,~~ Deputy Clerk/ By I 1 County A~,.torneyls Office ,~ ~r?~ ~_ f . " ,/ Date '5 l'-f+ ~I /tjq 3 , Date Not valid unless signed by the OWner, the Architect, and the Construction Manager. Signature of the Contractor indicates agreement herewith, incLuding any and aLl adjustments in Contract Sum and/or Contract Time.