Change Order No. 01-014-003
C H A N G E 0 R D E R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-014-003
To Contractor: NATIONAL OETENTION GROUP, INC.
6091 JOHNS ROAD
TAMPA, FL
Change Order Date: 08/05/93
33634
Architect's Project #:
Contract For:
METALS, DOORS & GLAZING
Contract Date:
04/22/92
You are directed to make the following changes in this contract; aLl other provisions of the contract shalL, except as
specifically changed herein, remain in full force and effect.
Issue: 068 - POMCO DELAY
In accordance with the ApriL 9, 1993 updated master schedule and Paragraph 8.3.1 of the Contract
Supplementary General Conditions, the Contract Substantial Completion Date is extended to November
1, 1993 at no additional cost, due to project delays resulting from the fabrication and:irection of~
the precast concrete. ~ ~
~X'
~ Tl
{./J
r::
-0
;-,.,
::::J
'"'
N
CC
\0
~
-
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and aLL related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 0.00 and 123 days.
The OriginaL Contract Amount was ...... ....................... .... ................................ ... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Value of this Change Order is .................................................................... $
The New Contract Amount incLuding this Change Order will be .......................................... $
The Contract Time wi II change by .....................................................................
The Oate of Substantial CompLetion as of the Date of this Change Order is ............................
1,994,050.00
-22,973.00
1,971,077 .00
0.00
1,971,077.00
123 days
11/01/93
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
~~
#7
By
Agreed to by Contractor:
Authorized by Owner:
INC.
Monroe County Board of County Commissioners
500 Whitehead Street
Key West, FLa 33040
By
Mayor/Chairman
Date
Attest:
By
Not vaLid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, incLuding any and alL adjustments in Contract Sum and/or Contract Time.