Change Order No. 01-015-002
C H A N G E 0 ROE R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-015-002
To Contractor: SANDY HARK
5721 NE SECOND AVE.
MIAMI, FL
Change Order Date: 08/05/93
Architect's Project #:
33137
Contract For:
LAUNDRY EQUIPMENT
Contract Date:
04/22/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 068 - POMCO DELAY
In accordance with the April 9, 1993 updated master schedule and Paragraph 8.3.1 of the Contract
supplementary General Conditions, the Contract Substantial Completion Date is extended to November
1, 1993 at no additional cost, due to project delays resulting from the fabrication and erection of
the precast concrete.
--;0
\Ci
\...oJ
"'1
u
:z:
-.,.,
::-: r
(/.l
C!:!
'.....
.."
.-.:J
N
CO
'"'-'~
-7"
\0
J::,;.
N
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 0.00 and 123 days.
The Original Contract Amount was ....... ........... ........... ....................................... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Value of this Change Order is ............ ...... ........ ..... ..................................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time will change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
160,955.98
-4,739.00
156,216.98
0.00
156,216.98
123 days
11/01/93
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
~~
B /
'--
~,'~
o te,
:~~NSEN ~~~ND l ~:Y!ER e.
Or a l 8 -3866
I~
By \
9/'23/7 ~
Date
Agreed to by Contractor:
Authorized by Owner:
By
~
f"-,t...tJ
Date
County Commissioners
Date
Approved As To
By
st: D~ Kolhage, Clerk
By Ol~ C. ~ ~~.-e;..
Deputy Clerk -
Date
Date
,,9- t:'J' f' .3
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.