Change Order No. 01-016-003
C H A N G E 0 R D E R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: D1-016-003
Change Order Date: 08/05/93
To Contractor: D.L. PORTER CONSTRUCTION, INC
1100 GILLESPIE AVE
SARASOTA, FL
Architect's Project #:
34236
Contract For:
MASONRY
Contract Date:
06/10/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 068 - POMCO DELAY
In accordance with the April 9, 1993 updated master schedule and Paragraph 8.3.1 of the Contract
Supplementary General Conditions, the Contract Substantial Completion Date is extended t~ov~r
1, 1993 at no additional cost, due to project delays resulting from the fabrication and ~ct~n of
the precast concrete. ~r
\Ci -Tl
LV ~_.
;"T1
V) 0
rr1
-"'(}
N ..
0::
:D ')
'-0
:~ ".J
N
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 0.00 and 123 days.
The Original Contract Amount was .................................................................... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Value of this Change Order is .............. ..... ........... ....... ............................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time will change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
1,059,416.00
10,617.00
1,070,033.00
0.00
1,070,033.00
123 days
11/08/93
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
~~
..;dcf7
HANS
800
Orl
By
Agreed to by Contractor:
Authorized by Owner:
D.L. PORTER CONSTRUCTION, INC
1100 GILLESPIE AVE
SARASOT1' F~ 34236 /
By C'. \.-c:::I~ ~ ~Llfo/q.:J
By
Date
Approved As Sufficiency: A
Date
st: Danny L. Kolhage, Clerk
By ~ c. AL,~.......:4...0'
Deputy Clerk ,
tf) ~-ol-' 3
Date
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.