Change Order No. KJ-001-010
C H A N G E 0 R D E R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-001-010
To Contractor: TOPPINO'S, INC.
P.O. Box 787
Key West, FL
Change Order Date: 06/15/92
33041
Architects Project #:
Contract For:
SITEWORK & CAISSONS
Contract Date:
07/17/91
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 024 - ASI 7 - ENTRANCE ROAD MODIFICATIONS
Per Architect's Supplemental Instruction No.7, dated April 3, 1992, and in accordance with
Toppino's written quotation dated April 24, 1992, revise the alignment and drainage of the entrance
road to the site.
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 2,456.70 and 0 days.
The Origninal Contract Amount was...................................... .......... ....................
Net Change by Previously Authorized Change Orders ....................................................
The Contract Amount prior to this Change was .........................................................
The Value of this Change Order is ................................... .................................
The New Contract Amount including this Change Order will be ..........................................
The Contract Time wi II change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
$ 1,261,096.25
$ -60,055.18
$ 1,201,041.07
$ 2,456.70
$ 1,203,497.77
o days
06/20/92
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
jE;tLA 1iL
By
l.. If.., Z-
Date
L..
:L.
Agreed to by Contractor:
Authorized by Owner:
TOPPINO'S, INC.
P.O. Box 787
KeY~1
~~~
By
~ - ~ "- ?'J...
Date
Monroe County Board of County Commissioners
500 Whitehead Street
K~., Fla 33040 ~\
~~. e ""^:: . "'-~
By
Mayor/Chairman
~~
B
By
Attest:
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.
TOPPINO'S, INC.
P.O. Box 787 . KEY WEST, FLORIDA 33041 . (305) 296-5606
SUBJECT: New Monroe County Detention Facility
KJ-01 Site Grading and Caissons
Change Order REquest for Revised Entrance Roadway.
MK/G 3310
INCOMING
[)1ST. .l A R
PIoi I V.J /
I""" r V/
111M h .. ,.,.
IPS
,..~r6E
,. 00
8B) /
.1,"" ...
. ~
IORIO I .. 9. I 7,,)
FILE W
,:-'>-."
'"
,...
April 21, 1992
Morrison, Knudsen/Gerrits
ATTN: Mr. Doug Fuller
Project Manager
P.O. Box 5283
Key West, FL 33041
RE: Morrison, Knudsen/Gerrits A/B Letter dated April 9, 1992
Serial # KJ-OC01-082
Dear Mr. Fuller,
The revised drawings in question changing the location of the entrance
roadway does affect our contract. A complete breakdown of the changes
is attached.
The cost to execute this additive change order to our contract is $2,256.70.
Our office is available to answer any questions that may arise is the
expedient approval of this change order.
Sincerely,
~A~~
Edward Toppino, Sr.
Secretary/Treasurer
ENCL: Letter KJ-OC01-082
Change Order Breakdown
TOPPINO'S, INC.
..,,-"'-.'-~~,.~~ .k'..;.7'."....,:...~:"1".'I~..fVnl..".,....""."'~
~ft!IIt J1IlaSll:Wlt ....IIllI"1" Ill'
4~~..=I':~B.<l!''''__~...'Woi~rw..q~,~~.~.
P.O. Box 787 . KEY WEST, FLORIDA 33041 . (305) 296-5606
April 20, 1992
NEW MONROE COUNTY DETENTION FACILITY
SITE GRADING AND CAISSON
CHANGE ORDER REQUEST WORKSHEET
ENTRANCE ROAD PER MORRISON, KNUDSEN/GERRITS LETTER KJ-oCOI-o82
1) To layout revised limits of entrance road
8.0 hrs @ $137.50 per hr
1,100.00
2) To finish grade additional road, base rock
38.0 sy @ $4.50 per sy
171. 00
3) To place additional asphalt to revised entrance roadway
38.0 sy @ $7.50 per sy
285.00
4) To backfill and compact reclaimed retention pond
1.0 LS @ $456.00
456.00
5) Finish grade slopes and sorround of reclaimed retention pond
1.0 LS @ $220.00 220.00
6) To supply and lay 12" RCP Class V Storm Sewer Pipe
10 LF @ $22.47 224.70
total
2,456.70
~MORRISON/~RRITS
~KNUDSEN ~ ,
A JOINT VENTURE
P.O, BOX 5283
KEY WEST, FLORIDA 33045-5283
TELEPHONE: (305) 292-7845
FAX: (305) 292-9697
April 9, 1992
Serial No.
KJ-OC01-082
Toppino's, Inc.
P.O. Box 787
Key West, FL 33041
Attention:
Subject:
Mr. Ed Toppino, Sr.
Architect's Supplemental Instruction No. 7
Contract No. KJ-01, site Grading & Caissons
New Monroe County Detention Facility
Monroe County Capital Improvements Program
Reference:
ASI No.7, attached.
Schedule of Drawings, dated 04/08/92, attached.
Dear Mr. Toppino:
The following revised drawings were handed to your site
superintendent, Jim Risk, for incorporation into your contract
drawings, and for construction:
Sheet 1. 03, rev. 3/04-03-92
Sheet 1.04, rev. 3/04-03-92
Sheet 1. 06, rev. 5/04-03-92
Sheet 1. 07 , rev. 5/04-03-92
Sheet 1.08, rev. 3/04-03-92
In accordance with the Architect's Supplemental Instructions No.
7, modify site access road as shown on the revised drawings.
Acknowledge receipt of these drawings by signing and dating below.
In addition, indicate whether the changes made on the subject
drawings affect your contract work. If paragraph 'B' is so noted,
then attach a complete explanation of the particular changes.
Drawing. 1.09, rev. 4/10-15-91, (2) copies were handed to you
previously. This A/B letter is to confirm incorporation of drawing
1.09. Included in the previous revised drawings with sheet 1.09,
were sheets 1. 04, rev. 2/10-15-91 and 1. 07, rev. 4/10-15-91,
although they are now void due to this Architect's Supplemental
Instructions No.7.
'A'
The changes made on the attached revised drawings
Do Not affect my contract (check)
~MORRISON/~.. RRrTS
~KNUDSEN ,,~
A JOINT VENTURE
Mr. Edward Toppino, Sr.
April 9, 1992
KJ-OC01-082
Page 2
'B'
The changes made on the attached revised drawings
Affect my contract. I ~av~attached an explanation
of the modifications ~ (check)
Signed: eLl ~~ .~
.L "') D - oL
Date: (- .>{ '7
Attached is a revised Schedule of Drawings, dated 04/08/92.
review this list and make sure that you are in receipt
current revision level of all contract drawings. If you
find any discrepancies, please notify us immediately.
Please
of the
should
Your prompt response to this A/.B letter would be appreciated.
If you have any question, please contact this office.
Sincerely,
MORRISON/KNUDSEN-GERRITS
A Joint Venture
J L A I 1/L
Dou;Jas A. Fuller
Project Manager
SBT/dk
Enclosure
13-5 KJ-024