Change Order No. KJ-001-013
C H A N G E 0 R D E R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-001-013
Change Order Date: 01/08/93
To Contractor: TOPPINO'S, INC.
P.O. Box 787
Key West, FL
Architect's Project #:
33041
Contract For:
SITEWORK & CAISSONS
Contract Date:
07/17/91
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 143 - UNSUITABLE FILL Q MISC. LOCATIONS
;>:
In accordance with Toppino's letter(KJ-IC01-043) dated October 6, 1992, remove and dispose O!!-sit~
at the Contract unit price of $6.00 per cy, 180 cy of unsuitable fill material from the fill:, )?'
stockpi le located in Zone F............................................................. .$1,f980.nn z
il ~7
1-<.
In accordance with.TOpp!nO's letter(KJ-IC01-047) dated Nov~r 9,.1992, r~ve and dis~se o1~-fft~
at the Contract umt prIce of $6.00 per cy, 175 cy of unsuItable fIll materIal from varIous:: 0 .
locations on the site............................. ............... ...................... ..$1,0~j)'_oe-; 7~
-\ :-"-'
In accordance with Toppino's letter(KJ-IC01-048) dated November 12, 1992, over-excavate, remove:a~ .
dispose off-site at the Contract unit price of $6.00 per cy, 84 cyof unsuitable fill material at -'
the Zone F parking area and backfill the same at the Contract unit price of $21.14 per '
cy...................................................................................... .$2,279.76
c..o
(J.J
""3
:::P
~:t,)
-...'\
co
. 1
, }
: 'l
:~
,""
o
o
:;0
CJ
-0
:3
r-'
(?
~:n
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 4,409.76 and 0 days.
The Original Contract Amount was........... ......................................................... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Va l ue of th is Change Order is.................................................................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time will change by ................................... ..................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
jtt;t Fl. 33040
A1dL
By
,. .,.."
Date
Agreed to by Contractor:
Authorized by Owner:
TOPPINO'S, INC.
P.O. Box 787
~3041
By ~
Monroe County Board of County Commissioners
500 Whitehead Street
Key West, Fla 33040
~
/ - I/-- if j
Date
By
Mayor/Chairman
1,261,096.25
-35,044.78
1,226,051.47
4,409.76
1,230,461.23
o days
06/20/92
I-/~- 93
Date
Date
By
D~~ge, Clerk
By iJod4Lc, A1tv~
Deputy Cr'erk
Attest:
Date
()/ -3.~ -- '1,J
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.