Loading...
Change Order No. KJ-001-014 C H A N G E 0 R D E R Project: KJ - NEW DETENTION FACILITY Change Order Number: 01-001-014 To Contractor: TOPPINO'S, INC. P.O. Box 787 Key West, FL Change Order Date: 06/04/93 Architect's Project #: 33041 Contract For: SITEWORK & CAISSONS Contract Date: 07/17/91 You are directed to make the following changes in this contract; all other provisions of the contract shall, except as specifically changed herein, remain in full force and effect. Issue: 228 - CLEAN-UP SERVICES Provide general labor clean-up services during regular working hours on an as needed basis at a rate of $25.00 per manhour for a not-to-exceed amount of $75,000.00. The rate of $25.00 is an all inclusive rate (i.e. includes overhead, profit, insurance, bond, safety equipment, miscellaneous small tools and supplies, etc.). The laborers shall work under the direct supervision of the Construction Manager. Daily Force Account sheets shall be initialled by a representative of the Construction Manager and shall accompany all invoices. -"T \0 Lv -11 L) :z: "1 ~~- c:.... c:: ::?: "-1 V1 -' Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra wor~'and all r~ted i~acts due to this contract change for the LUMP SUM AMOUNT of $ 75,000.00 and 0 days. , d The Original Contract Amount was........ ..................... ....................................... $ Net Change by Previously Authorized Change Orders .................................................... $ The Contract Amount prior to this Change was ......................................................... $ The Va lue of th i s Change Order is.................................................................... $ The New Contract Amount including this Change Order will be .......................................... $ The Contract Time will change by ..................................................................... The Date of Substantial Completion as of the Date of this Change Order is ............................ 1,261,096.25 -30,635.02 1,230,461.23 75,000.00 1,305,461.23 o days 06/20/92 Recommended by Construction Manager: Approved by Architect: Morrison-Knudsen/Gerrits 5090 College Road ~,st' F~ By '4~y 1>ate HANSEN LIND MEYER 8~MagnOlia Av~e. o la ~ 32 3- 866 By l '"(j - L-J4'~3 , Da e Agreed to by Contractor: Authorized by Owner: TOPPINO'S, INC. P.O. Box 787 Key wes~ 33041 ~ ~--4 By 6-~-93 Date County Commissioners B By Danny L. Kolhage, Clerk .Q~C. ~~ Deputy Clerk ' Date o""/~' 1.3 Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.