06/10/1992 Contract
1!lann!, I. i\olbagt
BRANCH OFFICE
3117 OVERSEAS HIGHWAY
MARATHON, FLORIDA 33050
TEL. (305) 743-9036
CLERK OF THE CIRCUIT COURT
MONROE COUNTY
500 WHITEHEAD STREET
KEY WEST, FLORIDA 33040
TEL. (305) 294-4641
BRANCH OFFICE
P.O. BOX 379
PLANTATION KEY, FLORIDA 83070
TEL. (305) 852-9253
M E MaR AND U M
To: Douglas Fuller
Morrison-Knudsen/Gerrits
From: Rosalie L. Connolly, Deputy Clerk
Date: July 20, 1992
Subject: Contract No. KJ-021
Wentworth Plastering Company of Boca Raton
Gypsum Board, Lath & Plaster
New County Detention Facility
On June 10, 1992, the Board of County Commissioners approved
and authorized execution of a Contract with Wentworth
Plastering Company of Boc~ Raton for Gypsum Board, Lath &
Plaster at the New County Detention Facility.
A duplicate original of the Contract, now executed and
sealed by all parties, is attached hereto for delivery to
the Contractor.
Rosalie L. onnolly
Deputy Clerk
Attachment
cc: County Attorney
County Administrator w/o document
Finance Director
File
New Detention Facility
CONTRACT KJ-021, Gypsum Board, Lath & Plaster
Wentworth Plastering Company of Boca Raton, Inc,
I.
II.
A
B.
e.
D.
E.
F.
G.
Form of Agreement
Public Construction Bond
Certificate of Insurance
Table of Contents
Schedule of Drawings
Scope of Work - Bid Package #34
Milestone Schedule
A
B.
D.
E.
F.
Proposal Form, pages 00134-1 through 00134-4 signed by bidder and dated June 4, 1992.
Bid Bond from Employers Insurance of Wausau, Wisconsin
Sworn Statement on Public Entity Crimes.
Lobbying and Conflict of Interest Clause.
Non-Collusion Affidavit.
III. Conditions of the Contract
A General Conditions
B. Supplementary Conditions
e. Project Safety and Health Plan
D, Contractor's Quality Control Plan
E. Substantial Completion & Owner's Acceptance
F. General Requirements
Application for Payment
Change Order Procedures
Security Project Procedures
Project Meetings
Submittals
Progress Schedules
Schedule of Values
Daily Construction Report
Document Clarification Requests
Testing Laboratory Services
Temporary Utilities
Construction Aids
Access Roads and Parking Areas
Temporary Controls
Project Identification and Signs
Field Offices and Sheds
Construction Cleaning
Material and Equipment
Post-Bid Substitutions
Starting of Systems
Systems Demonstrations
Contract Closeout
Final Cleaning
Project Record Documents
Operation and Maintenance Data
THE AMERICAN INSTITUTE OF ARCHITECTS
.
A/A Document A101/CM
CONSTRUCTION MANAGEMENT EDITION
Standard Form of Agreement Between
Owner and Contractor
where the basis of payment is a
STlPULA TED SUM
1980 EDITION
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH
AN ATTORNEY IS ENCOURAGED,
This document is intended to be used in conjunction with AlA Documents
A201/CM, 1980; B141/CM, 1980; and B801, 1980.
AGREEMENT
Contract No. KJ-021, Gypsum Board, Lath & Plaster
made as of the 29th
Hundred and Ninety-two
day of
(1992)
June
In the year of Nineteen
BETWEEN the Owner:
Monroe County Board of County Commissioners
500 Whitehead Street
Key West, FL 33040
and the Contractor:
Wentworth Plastering Company of Boca Raton, Inc.
4044 NE 7 Avenue
Fort Lauderdale, FL 33334-3098
(305) 564-8008
the Project:
New Monroe County Detention Facility
5501 College Road, Stock Island
Key West, FL 33040
the Construction Manager:
Morrison-Knudsen/Gerrits
the Architect:
Hansen Lind Meyer/Gonzalez
The Owner and the Contractor agree as set forth below.
Copyright 1975, @ 1980 by The American Institute of Architects, 1735 New York Avenue, N,W" Washington, D,C. 20006, Re-
production of the material herein or substantial quotation of its provisions without written permission of the AlA violates the
copyright laws of the United States and will be subject to legal prosecution.
AlA DOCUMENT Al0l/CM . OWNER-CONTRACTOR AGREEMENT . CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" N,W" WASHINGTON, D,C. 20006
A101/CM -1980 1
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution.
ARTICLE 1
THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, the Conditions of the Contract (General, Supplementary and
other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after
execution of this Agreement. These form the Contract, and all are as fully a part of the Contract as if attached to this
Agreement or repeated herein, An enumeration of the Contract Documents appears in Article 7.
ARTICLE 2
THE WORK
The Contractor shall perform all the Work required by the Contract Documents for
(Here insert the caption descriptive of the Work as used on other Contract Documents)
Bid Group 3, Bid Package No. 34, Gypsum Board, Lath & Plaster
ARTICLE 3
TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
The Work to be performed under this Contract shall be commenced on the date as established in the Notice to
Proceed,
and, subject to authorized adjustments, Substantial Completion of the Work shall be achieved not later than the time
(Here insert any special provisions lor liquidated damages relating to failure to complete on time,)
indicated in Section 00353 Milestone Schedule.
AlA DOCUMENT Al0l/CM . OWNER-CONTRACTOR AGREEMENT. CONSTRUCTION
MANAGEMENT EDITION. JUNE 1980 EDITION . AIN~ . @198O . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" N,W" WASHINGTON, D,C. 20006 A101/CM -1980 2
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution,
ARTICLE 4
CONTRACT SUM
The Owner shall pay the Contractor in current funds for the performance of the Work, subject to additions and
deductions by Change Order as provided in the Contract Documents, the Contract Sum of
Six Hundred Eighty One Thousand Dollars............................................... $681,000.00
The Contract Sum is determined as follows:
(State here the base bid or other lump sum amount, accepted alternates and unit prices. as applicable.)
Base Bid.............................................................................. $681,000.00
ARTICLE 5
PROGRESS PAYMENTS
Based upon Applications for Payment submitted to the Construction Manager by the Contractor and Project Certificates
for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the
Contractor as provided in the Contract Documents for the period ending the Twenty-fifth {25} .day' of each
month as follows: approxlmately
Not later than Thi rty (30) days following the end of the period covered by the Application for Payment,
Ninety percent ( 90 %) of the portion of the Contract Sum properly allocable to labor, materials and
equipment incorporated in the Work and Ninety percent (90 %) of the portion of the Contract
Sum properly allocable to materials and equipment suitably stored at the site or at some other location agreed upon
in writing, for the period covered by the Application for Payment, less the aggregate of previous payments made by
the Owner; and upon Substantial Completion of the Work, a sum sufficient to increase the total payments to
One Hundred percent ( 100 %) of the Contract Sum, less such amounts as the Architect shall determine for
all incomplete Work and unsettled claims as provided in the Contract Documents,
(II not covered elsewhere in the Contract Documents, here insert any provision (or limiting or reducing the amount retained alter the Work reaches a certain
stage 01 completion.!
Reference Section 00800 Substantial Completion and Owner Acceptance.
-Pa:)'F!leflt~ -<kI.e -a-Hd- ~~8 -Lm88 '" -liR8 -GQRt;r~-li ~ Q€~~~R \.!;-~.l. .boo.r-i.o.t€~s.t- f.r~ -the-4I.-li8 -pa>fR'l€+K -i~ -G~...J.t- ~ -fil ~
-entered- "e~ -or-m- t"'e~ t+tereof, -trt-t-he- ~-r'tl'te-~ I'e\"a1 hf'l~-ltt- th e-plttee-l'J'f -t-he- p,.o feet:-
-~ime-r'"....,.....,...!e-of..IO!~_~..,.,8ot11'..,..,;.
(Usury laws and requirements under the Federal Truth in Lending Act, similar state and local consumer credit laws and other regulations at the Owner's
and Contractor's principal places 01 business, the location 01 the Project and elsewhere may affect the validity 01 this provision, Specific legal advice should
be obtained with respect to deletion, modification or other requirements such as written disclosures or waivers.)
AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT. CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIM> . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" NW" WASHINGTON, D,C. 20006 A101/CM -1980 3
WARNING: Unlicensed photocopying violates U,S, copyright laws and is subject to legal prosecution,
ARTICLE 6
FINAL PAYMENT
Final payment, constituting the entire unpaid balance of the Contract Sum, shall be paid by the Owner to the
Contractor when the Work has been completed, the Contract fully performed, and the Architect has issued a Project
Certificate for Payment which approves the final payment due the Contractor.
ARTICLE 7
MISCELLANEOUS PROVISIONS
7,1 Terms used in this Agreement which are defined in the Conditions of the Contract shall have the meanings
designated in those Conditions.
7.2 The Contract Documents, which constitute the entire agreement between the Owner and the Contractor, are listed
in Article 1 and, except for Modifications issued after execution of this Agreement, are enumerated as follows:
(List below the Agreement, the Conditions 01 the Contract [General, Supplementary and other Conditions], the Drawings, the Specifications, and any Addenda
and accepted alternates, showing page or sheet numbers ;n all cases and dates where applicable,)
I. Bidding Documents
A. Bid Group 3 Bid Documents for New Monroe County Detention Facility, which include Bidding Documents,
Contract Documents, Conditions, Drawings, General Requirements and Technical Specifications, and
which are enumerated in the attached Table of Contents, contained in Bid Group 3, pages 00001-1
thru 00001-9, dated 03/24/92, and in the attached Schedule of Drawings contained in Bid Group 3,
pages 00993-1 thru 00993-19, dated 05/02/92, all as amended by the addenda listed below.
B. Addendum No. 1A dated November 26, 1991
Addendum No. 1B dated December 11, 1991
Addendum No. 1 dated December 20, 1991
Addendum No. 2A dated January 3, 1992
Addendum No.2 dated January 6, 1992
Addendum No. 3 dated January 9, 1992
Addendum No.4 dated January 13, 1992
Addendum No. 5 dated February 18, 1992
Addendum No. 6 dated March 4, 1992
Addendum No.7 dated March 10, 1992
Addendum No.8 dated March 25, 1992
Addendum No.9 dated April 3, 1992
Addendum No. 10 dated April 16, 1992
Addendum No. 11A dated April 21, 1992
Addendum No. lIB dated April 24, 1992
Addendum No. 11C dated May 1, 1992
Addendum No. 11 dated May 5, 1992
Addendum No. 12A dated May 8, 1992
Addendum No. 12B dated May 13, 1992
Addendum No. 12C dated May 15, 1992
Addendum No. 12 dated May 21, 1992
Addendum No. 13 dated June 1, 1992
II. Proposal Documents submitted by Wentworth Plastering Company of Boca Raton, Inc., on June 9, 1992:
A. Proposal Form, pages 00134-1 thru 00134-4, signed by bidder, and dated June 4, 1992.
B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin.
C. Sworn Statement on Public Entity Crimes.
D. Lobbying and Conflict of Interest Clause.
E. Non-Collusion Affidavit.
AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT. CONSTRUCTION
MANAGEMENT EDITION. JUNE 1980 EDITION. AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" N,W,. WASHINGTON, D,C. 20006 A101/CM -1980 4
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution.
7.3 Temporary facilities and services:
(Here insert temporary facilities and services which are different from or in addition to those included elsewhere in the Contract Documents.)
Reference the documents issued for bidding.
7.4 Working Conditions:
(Here list any special conditions affecting the Contract.)
Reference the documents issued for bidding.
(Sea 1)
Attest: Danny L. Kolhage, Clerk of the Court
"Approved as to Fonn and Legal Sufficiency"
By,/24D~
Date: ~ --I''''' ~
BY'~.
Attorn s Office
G - / 7- -)9 2--
Date:
This Agreement entered into as of the day and year first written above.
OWNER
CONTRACTOR
.~~~' ..~---.................~.....
ny of Boca Raton, Inc.
Monroe C~ Board of coun~ Commissioners
By, ~~', ~.I ..... ~ '...:.. ~ -.,,~
Its: C At.i.~Wl4"
By:
tiA.MP-{)
Its:
fJlJ
CAUTION: You should sign an original AlA document which has this caution printed in red.
An original assures that changes will not be obscured as may occur when documents are reproduced.
AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT. CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" N,W., WASHINGTON, D,C. 20006 A101/CM -1980 5
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution,
Bond No. 1450-23-088158
puaLIC CONSTRUCTION BONO
Wentworth Plastering Co.
BY THIS BOND, We of Boca Raton. Inc. , as Principal and EmR10vers
Ins~ra1)-ce of Wausa~ a corporation, as Surety, are bound to Monroe County Boarq of County
COmmlsslonffift-ein called Owner, in the sum of $ 681,000.00 for payment of
which we bind ourselves, our heirs, personal representatives,
successors, and assigns, jointly and severally.
THE CONDITION OF THIS BOND is that if Principal:
1. Performs the contract dated June 29 , 1911-, between
Principal and Owner for construction of ~lJt'Q~ CQPQty J)~tention FRril itlJ
the contract being made a part of this bond by reference, at the
times and in the manner prescribed in the contract; and
2. promptly makes payments to all claimants, as defined in
Section 255.05(1), Florida statutes, supplying principal with
labor, materials, or supplies, used directly or indirectly by
principal in the prosecution of the work provided for in the
contract; and
3. Pays Owner all losses, damages, expenses, costs, and
attorne~'s fees, including appellate proceedings, that ,Owner
sustains because of a default by principal under the contract;
. and
.'.
4. Performs the guarantee of all work and materials furnished
under the contract for the time specified in the contract, then
this bond is void; otherwise it remains in full force.
Any changes in or under the contract documents and compliance
with any formalities connected with the contract or the changes
does not affect Surety's obligation under this bond.
DATE ON 1-1~, 193,&.
BY
'1lf{if~
(AS TORNEY IN FACT)
Mary C. Aceves
Employers Insurance of Wausau
(NAME OF SURETY)
PUBLIC CONSTRUCTION BOND
00610 - 1
11/20/91
~
z
o
W
IT:
Z
IT:
<(
W
0..
0..
<(
I-
o
Z
(f)
w
o
o
I-
Z
w
~
w
G~
zt3
- (f)
7=r
t...u..
~~
IT:
o
~
u..
o
IT:
W
S
o
0..
o
...J
~
<(
I-
o
Z
(f)
(f)
I
I-
No. 214-147- 00295
ENtPlOVERS INSURANCE OF WAUSAlJ A Mutual Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS:
That the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company, a corporation duly organized and existing under
the laws of the State of Wisconsin, and having its principal office in the City of Wausau, County of Marathon, State of
Wisconsin, has made, constituted and appointed, and does by these presents make, constitute and appoint
CHARLES J. NIELSON, JACK E. FOWLER, MARY C. ACEVES, JOHN S. HARRIS
its true and lawful attorney-in-fact, with full power and authority hereby conferred in its name, place and stead, to execute,
seal. acknowledge and deliver ANY OR ALL BONDS, UNDERTAKINGS, RECOGNIZANCES OR OTHER WRITTEN
ORLIGATIONS IN THE NATURE THEREOF INCLUDING CONSENTS OF SURETY AND WAIVERS TO THE
CONDITIONS OF CONTRACTS. NOT TO EXCEED THE PENAL SUM OF TEN MILLION DOLLARS
($10,000,000). ~
and to hind the corporation therehy as fully and to the same extent as if such honds were signed hy the President, sealed with
thp corporate seal of the corporation and duly attested hy its secrptary herehy ratifying and confirming all that the said
attorney-in,faet may do in the premises.
This power of attorney is granted pursuant to the following resolution adopted by the Board of Directors of said Company at a
mepting duly call1'd and held on thp IRth day of May, I !.J7:I, which resolution is still in effect:
"RESOLVED, that the President and any Vice Prpsident - elpctivp or appointive - of EMPLOYERS INSURANCE OF
W A USA U A Mutual Company he, and that each of them herehy is, authorized to execute powers of attorney qualifying
the attorney naml'd in the given pOWl'r of attorney to execute on hehalf of EMPLOYERS INSURANCE OF W AUSAU A
Mutual Company honds, undl'rtakings and all contracts of suretyship; and that any secretary or assistant secretary be,
and that each or any of them herehy is, authorized to attl'st the eXl'cution of any such power of attorney, and to attach
thl'reto the sl'al of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company,"
"FURTHER RESOLVED, that thl' signaturl's of such officl'rs and thl' seal of EMPLOYERS INSURANCE OF W AUSAU
A Mutual Company may Ill' affixpd to any such power of attorney or to any certificate relating thereto hy facsimile, and
any such powpr of attornl'Y or cprtificatl' hparing such facsimilp signatures and facsimill' seal shall be valid and hinding
upon thp EMPLOYERS INSURANCE OF W AUSAU A Mutual Company whl'n so affixed and in the future with respect
to any hond, und{'[taking or contract of surptyship to which it is attached."
IN WITNESS WII EREOF, EMPLOYERS INSURANCE OF W AUSAU A Mutual Company has causpd these presents to he
signed by the senior vice president and attested by its assistant secretary, and its corporate seal to be hereto affixed this 18 t day
of ,TANTTARY , 19----.9.l,
(/;:::;~,;;~~~
~,SEAl/i
~-,~,;i,l
EMPLOYERS INSURANCE OF WAUSAU A Mutual Company
~CJ,~~
Bill D, Wymore
By
Executive Vice President
Attest: 4;J d L
?1J~~
R, J, Blsteman/
Assistant Secretary
STATE OF WISCONSIN )
) ss,
COUNTY OF MARATHON)
On this 18 t dav ot' JANUARY 19 91 h t' II
. , _, e ore me persona y came
Bill D, Wymore k h b' b '
, ",' ' to me nown, w 0 emg y me duly sworn, did depose
and say that he IS an execut!ve vice preSident ot the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company, the corporation described in
and which executed the a~ove mstrument:. that he knows the seal of said corporation; that the seal affixed to said instrument is such corporate
seal and that It was so atflxed hy order ot the Board ot Directors ot Said corporation and that he signed his name thereto by like order.
1:\ WITNESS WHFRFOF, 1 h'l\e hereunto sel mv hand and affixed mv official seal the day and year herein first above written,
~a,
l~
Patricia A, Kleman
NOTARY PUBLIC
STATE OF WISCONSIN ) STATE OF WISCONSIN
CITY OF WAUSAU ) ss, MY COMMISSION EXPIRES MAY 29,1994
COUNTY OF MARATHON) CERTIFICATE
I. tIll' undprsignl'd, assistant sl'eretary of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company, a Wisconsin
('orporatlOn, do hpn.h:.' ('ertlfy that the fon.going and atta('hl'd power of attornl'V, WHICH MUST CONTAIN A
V ALIDATING STATEMENT PRINTED IN THE MARGIN THEREOF IN REI) INK, remains in full force and has
not Ill'en n'\'okl'd: and furthermore that the rpsolution ofthl' Board ofl lirl'ctors sl'f forth in thl' power of attorney is still in force,
Signed and sl'aled in thp City of Wausau, Marathon County, Statp of Wisconsin, this _ day
of ________.__, 1!1_..
Notary Public
l;:~~:;;;::!~~~\
/':':-::~~::;0;
fico.'OIl",( ~
1 ~ -.- I \
~SEAl /i
~~~,J"'.."
Ad~
/ ./
Assistant Secretary
R, J. Besteman
NOTE IF YOl] HAVE ANY QUESTIONS REGARIlIN(; THE VALIDITY OR WORDING OF THIS POWER OF
ATTORN r: y, CALL TOLL FRE E (HO()) H~{)-llifi I, II N WISCONSI N, CALL iHO()) ,I i'2-0041 ),
A.~.tlll.~
CERTIFICATE OF INSURANCE
PRODUCER
Collinsworth, Alter, Nielson,
wIer & Dowling, Inc.
~ost O~~ice Box 9315
Miami Lakes, FL 33014-9315
INSURED
Wentworth Plastering
o~ Boca Raton, Inc.,
4044 N, E, 7th Avenue
Fort Lauderdale FL
Company
ETAL.
33334
ISSUE DATE (MMIDDIYY)
__.. 7/08/92,__
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND
CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE
DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE
POLICIES BELOW.
COMPANIES AFFORDING COVERAGE
f~T~~~NY A Marl,J land Casualty Co,
f~T~~~NY B Maryland Casualty Co,
f~T~~~NY C Norther'n Insurance Co
f~T~~NY D
~fl
Florida Home Builders-SIF
f~T~~NY E
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED, NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS,
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES, LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS,
CO
LTR
TYPE OF INSURANCE
POLICY NUMBER
AGE'NERALLi'ABlLi;:Y-------
EPA07416630
x
COMMERCIAL GENERAL LIABILITY
CLAIMS MADE)( OCCUR,
OWNER'S & CONTRACTOR'S PROT,
-<,,-~>--_.----.._- ~-,-- ~~..__._--.
B AUTOMOBILE LIABILITY
ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
X HIRED AUTOS
X NON-OWNED AUTOS
GARAGE LIABILITY
POLICY EFFECTIVE POLICY EXPIRATION
DATE (MMfDDIYY) DATE (MMIDDfYY)
LIMITS
8/01/91
8/01/92
GENERAL AGGREGATE $ 1. 000000
PRODUCTS-COMP/OP AGG, $ 1000000
PERSONAL & ADV. INJURY $ 1000000
EACH OCCURRENCE $ 1000000
FIRE DAMAGE (Anyone fire) $ 50000
MED, EXPENSE (Anyone person) $ . .,_5000.. ,
COMBINED SINGLE $ 1000000
LIMIT
"A""""___~_.,,'_'''___''-_____''____'-_>''_,~.,,__,,~_, ..~_."___..~__""~",...~_."_.__......".
ECA10604032 8/01/91
CE~ESS~C;-;;---"_.'--'-_._-'-'" UBA697981 07
X UMBRELLA FORM
OTHER THAN UMBRELLA FORM
D
WORKER'S COMPENSATION
AND
EMPLOYERS' LIABILITY
08392
OTHER
DESCRIPTION OF OPERATIONS/LOCATIONSIVEHICLES/SPECIAL ITEMS
8/01/92
BODILY INJURY
(Per person)
$
BODILY INJURY
(Per accident)
$
PROPERTY DAMAGE $
8/01/91
8/01/92 EACH OCCURRENCE
AGGREGATE
$ 5000000
$ 5000000
3/01/92 3/01/93 X
STATUTORY LIMITS
EACH ACCIDENT $
DISEASE-POLICY LIMIT $
DISEASE-EACH EMPLOYEE $
500000
500000
~OQ.Q..oQ
Certificate holder is added as additional
insured on all coverages except Workers Camp for operation performed
b y insured on the Monroe County Detent ion Fac i 1 i ty pro j ec;J:..:...__._...___________
CERTIFICA TE HOLDER CANCELLATION
nroe County Board of County
Lommissioners or Monroe County
c/o Morrison-Knudsen/Gerrits
P. O. Box 5283
Key West, Florida 33040
_~C~~I:) .3,5.:.s J7/9'?t.
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO
MAIL 60 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE
LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR
LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES,
AUTHORIZED REP~
't/ ~ORD CORPORATION 199.
c::.- 18
MK/G 3310
INCOMIN'3
DIST, I A R
(PM
PE
BM
PS
OE
OC
see
0RiG
FILE
--
TABLE OF CONTENTS
BID GROUP 3
1. Bidding Documents (Volume I)
03/24/92
section 00030
section 00050
section 00100
section 00113
section 00114
section 00115
section 00116
section 00117
section 00118
section 00119
section 00120
section 00121
section 00127
section 00128
Section 00129
section 00130
section 00131
section 00132
section 00133
section 00134
section 00135
section 00136
section 00137
section 00138
section 00139
section 00140
section 00141
section 00142
section 00148
section 00149
section 00143
section 00144
section 00145
section 00146
Notice of Calling for Bids
Project Summary
Instructions to Bidders
Proposal Forms:
Security Systems
Prime Electrical Contract Zones
A,B,C,D,E
Mechanical Process and HVAC
Prime Plumbing Contract Zones A,B,C,D,E
Fire Protection System
Food Service Equipment
Laundry Equipment
Loading Dock Equipment
Pneumatic Tube System
Metals-Doors-Glazing
Masonry
Concrete
Roofing
stairs & Miscellaneous Metals
sprayed Insulation
Sealants
Gypsum Board, Lath & Plaster
Carpentry
Special Flooring
Access Flooring, Resilient Flooring &
Carpet
Ceramic Tile
Acoustical Ceilings
Painting & Wallcovering
Fence & Gates
Asphaltic Concrete Paving
Wastewater Treatment Plant & utilities
Landscaping
Schedule of Unit Prices:
security systems
Prime Electrical Contract Zones
A,B,C,D,E
Mechanical Process and HVAC
Prime Plumbing Contract Zones A,B,C,D,E
TABLE OF CONTENTS (ADD. 8)
00001 - 1
03/24/92
section 00147
section 00157
section 00163
section 00220
section 00230
section 00303
section 00305
section 00307
Section 00309
Section 00310
section 00311
Section 00312
section 00313
section 00314
section 00315
section 00316
section 00317
Section 00318
Section 00319
section 00320
section 00321
section 00327
section 00328
section 00329
section 00330
section 00331
section 00332
section 00333
Section 00334
section 00335
section 00336
section 00337
section 00338
section 00339
section 00340
section 00341
section 00342
section 00343
section 00344
section 00353
Fire Protection System
Metals-Doors-Glazing
Pre-Bid Substitutions
Geotechnical Data
site survey
Scopes of Work for Reference (BG-l and
BG-2) :
site Electrical & Temporary Po~er
site Grading & Caissons
Concrete Foundations
site Plumbing
Precast Concrete
Hydraulic Elevators
Precast Embeds
Scopes of Work:
Security systems
Prime Electrical Contract Zor.es
A,B,C,D,E
Mechanical Process and HVAC
Prime Plumbing Contract Zones A,B,C,D,E
Fire Protection System
Food Service Equipment
Laundry Equipment
Loading Dock Equipment
Pneumatic Tube System
Metals-Doors-Glazing
Masonry
Concrete
Roofing
stairs & Miscellaneous Metals
sprayed Insulation
Sealants
Gypsum Board, Lath & Plaster
Carpentry
special Flooring
Access Flooring, Resilient Flooring &
Carpet
Ceramic Tile
Acoustical Ceilings
Painting & Wallcovering
Fence & Gates
Asphaltic Concrete Paving
Wastewater Treatment Plant & utilities
Landscaping
Milestone Schedule
TABLE OF COPTENTS (ADD. 8)
00001 - 2
section 00410 Bid Bond - AlA Docuoent A310, February
1970 edition
section 00420 Sworn statement on Public Entity Crimes
section 00425 Lobbying and Conflict of Interest Clause
section 00430 Non-Collusion Affidavit
section 00440 Proposed Subcontractor Listing
section 00450 Contractor's Qualification Statement -
AlA Document A305
2. Contract Documents (Volume I)
section 00500 Standard Form of Agreement Between Owner
and Contractor - AlA Document AI01/CM,
June 1980 edition
section 00610 Public Construction Bond
3. Conditions (Volume I)
section 00750 General Conditions, AlA Document
A201/CM, June 1980 edition
section 00800 Substantial Completion and Owner
Acceptance
section 00805 Supplementary General Conditions
section 00900 Application & certificate for Payment -
AlA Document G702/G703
section 00905 Contractor's Affidavit of Payment of
Debts and Claims
section 00908 Contractor's Affidavit of Release of
Liens
section 00910 Consent of surety to Final Payment - AlA
Document G707, April 1970 edition
section 00915 Affidavit and Partial Release of Lien
Section 00970 Project Safety and Health Plan
secticn 00930 Contractor Quality Control Plan
03/24/92
TABLE OF CONTENTS (ADD. 8)
00001 - 3
4. Drawings
section 00993 Schedule of Drawings, Bid Group 3
5. General Requirements (Volume I)
section 01027
section 01028
section 01130
section 01200
section 01301
section 01310
section 01370
section 01385
Section 01395
section 01410
Section 01510
section 01520
section 01550
section 01560
section 01580
section 01590
section 01595
section 01600
section 01630
section 01650
section 01670
section 01700
section 01710
section 01720
section 01730
Application for Payment
Change Order Procedures
security Project Procedures
Project Meetings
Submittals
Progress Schedules
Schedule of Values
Daily Construction Reports
Document Clarification Requests
Testing Laboratory Services
Temporary utilities
Construction Aids
Access Roads and Parking Areas
Temporary Controls
Project Identification and Signs
Field Offices and Sheds
Construction Cleaning
Material and Equipment
Post-Bid Substitutions
starting of Systems
Systems Demonstrations
Contract Closeout
Final Cleaning
Project Record Documents
Operation and Maintenance Data
03/24/92
00001 - 4
TABLE OF CONTENTS (ADD. 8)
6.
Technical specifications, Bid Group Three, (Volume II, dated
November 11, 1991)
ADDENDA
Addendum No. 1, section 00901, pages 00901-1 thru
00901-7.
Addendum No. 2, section 00902, pages 00901-1 thru
00902-7.
Addendum No. 3, section 0090) , pages 00903-1 thru
00903-7.
Addendum No. 5, section 00905, page 00905-1, with
Revisions to Contract Documents No. 1, pages 1 and 2.
Addendum No. 6, section 00906, page 00906-1, with
Revisions to Contract Documents No. 2, page 1.
Addendum No. 7, section 00907, page 00907-1.
DIVISION 2 - SITEWORK
section 02211
section 02215
section 02222
section 02226
section 02510
section 02518
section 02520
section 02580
section 02644
section 02721
section 02730
section 02732
section 02733
section 02800
section 02810
section 02830
section 02835
Section 02930
section 02950
Rough Grading
Finish Grading
Excavating, Backfilling And Compacting
For Structures
Excavating, Backfilling and Compacting
For utilities
Asphaltic Concrete Paving
Concrete unit Pavers
Portland Cement Concrete Paving
Pavement Marking
Water Mains
Sewer Structures
sanitary sewerage
sewage Force Mains
Sewage Pump station
site Improvements
Irrigation System
Fence And Gates
Barbed Tape
Lawns
Trees, Shrubs And Ground Cover
DIVISION 3 - CONCRETE
section 03100
section 03200
section 03300
section 03520
section 03600
Concrete Formwork
Concrete Reinforcement
cast-in-Place Concrete
Insulating Concrete Decks
Grout
03/2/,/92
00001 - 5
TABLE OF CONTENTS (ADD. 8)
DIVISION 4 - MASONRY'
section 04200 unit Masonry
DIVISION 5 - METALS
section 05180
section 05500
section 05510
section 05810
Miscellaneous Structural Steel
Metal Fabrications
Metal stairs
. Expansion Joint Covers Assemblies
DIVISION 6 - WOOD AND PLASTIC
section 06100
section 06200
Rough Carpentry
Finish Carpentry
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
section 07115
section 07210
section 07215
section 07272
section 07530
section 07730
section 07900
Sheet Waterproofing
Building Insulation
sprayed Insulation
Firestop And Penetration Sealing System
single Ply Roofing
Roof Accessories
Joint Sealers
DIVISION 8 - DOORS AND WINDOWS
section 08100
section 08211
section 08300
section 08305
section 08320
section 08410
section 08660
section 08710
section 08800
section 08842
section 08902
Metal Doors And Frames
Flush Wood Doors
Special Doors
Access Panels And Doors
Security Metal Doors And Frames
Aluminum Entrances
Security windows
Door Hardware
Glazing
Security Glazing
Aluminum Window Walls
DIVISION 9 - FINISHES
section 09110
section 09200
section 09250
section 09300
section 09510
section 09650
section 09680
section 09700
section 09800
Non-Load Bearing Wall Framing Systems
Lath and Plaster
Gypsum Board
Tile
Acoustical Ceilings
Resilient Flooring
Carpet
special Flooring
Special coatings
03/24/92
00001 - u
TABLE OF CONTENTS (ADD. 8)
DIVISION 9 - FINISHES, cont'd
section 09830
Section 09900
section 09950
Elastomeric coating
Painting
Wallcovering
DIVISION 10 - SPECIALTIES
section 10100
.Section 10160
section 10200
section 10270
Section 10350
section 10500
section 10520
section 10550
section 10606
section 10800
section 10900
Chalkboards And Tackboards
Solid Plastic Toilet Partitions
Louvers and Vents
Access Flooring
Flagpole
Steel Lockers
Fire Extinguisher Cabinets
Postal Specialties
Security Fencing Assembly
Toilet Accessories
Miscellaneous Specialties
DIVISION 11 - EQUIPMENT
section 11110
section 11160
section 11197
Section 11200
section 11202
section 11203
Section 11204
section 11205
section 11206
Section 11208
section 11211
section 11212
Section 11217
section 11218
section 11222
section 11224
section 11400
section 11480
section 11704
Laundry Equipment
Loading Dock Equipment
security/Detention Equipment
Basic Electronic Security Requirements
System Central Processing Unit
Fire Alarm Interface
Programmable Logic Controller
Address Panels
Relay Cabinets
Card Access Control
situation Man-Down Equipment
Closed circuit Video Equipment
Vehicle Loop Detection
operational Intercom system
Inmate/Attorney Telephones
Metal Detection Equipment
Food Service Equipment
Athletic Equipment
Ice Machines
DIVISION 13 - RADIATION PROTECTION
section 13090 Radiation Protection
DIVISION 14 - CONVEYING SYSTEMS
section 14700
section 14240
Pneumatic Tube System
Hydraulic Elevators
03/24/92
00001 - 7
TABLE OF CONTENTS (ADD. 8)
DIVISION 15 - MECHANICAL
Section 15000
section 15050
section 15060
section 15085
section 15100
section 15110
section 15130
section 15140
section 15160
section 15175
section 15242
section 15252
section 15290
section 15330
section 15403
section 15404
section 15408
section 15410
section 15430
section 15440
section 15460
section 15470
section 15490
section 15517
section 15540
section 15684
section 15714
section 15770
Section 15785
section 15855
section 15858
section 15880
section 15884
section 15885
section 15890
section 15894
section 15936
section 15950
section 15965
section 15992
section 15995
General provisions
Water Treatment
pipe and pipe Fittings
piping Identification
Valves
Heat Trace System
Thermometers and Gages
pipe Hangers And supports
Pumps
Variable Speed Motor Control for Fans
and Pumps
Vibration Isolation
Pipe And Equipment Insulation
Ductwork Insulation
Wet-Sprinkler System
Water Booster Pumps
Domestic Water Softener
Soil, Waste and Vent system
storm Drainage System
Plumbing Specialties
plumbing Fixtures and Accessories
Sump Pumps
Hot Water Storage Heater
Fuel storage And Dispensing Systems
Hydronic specialties
Emergency Generator Auxiliaries
Centrifugal Chillers
Blow Thru Cooling Tower
Make-Up Air Units
Fan Coil Units
Air Handling Units
Fans
Fire Dampers
Combination Smoke And Fire Dampers
Air Filters
Ductwork
Air Terminal Units
Grilles, Registers, Diffusers
Automatic Temperature Control Systems
Building Automation system
Tests - piping Systems
system Balancing and Testing
03/24/92
00001 - 8
TABLE OF CONTENTS (ADD. 8)
DIVISION 16 - ELECTRICAL
section 16010
Section 16111
section 16111
section 16120
section 16155
section 16161
section 16170
section 16199
section 16300
section 16351
section 16400
section 16425
Section 16450
section 16461
section 16470
section 16471
section 16472
section 16500
section 16601
section 16605
section 16660
section 16721
section 16781
section 16930
Electrical General Provisions
Conduit systems - Bid Group 3
Conduit Systems - Bid Group 2
Wire and Cable
Combination Motor Starters
Motor Control Centers
Disconnect switches
wiring Devices and Plates
Standby Power Generation
Uninterruptible Power supply
service and Power Distribution Systems
Main Service switchboard
Electrical Systems Grounding
Dry Type Distribution Transformers
Distribution panelboards - Circuit
Breaker Type
Feeder and Branch Circuits and Emergency
wiring
Branch Circuit Panelboards - circuit
Breaker Type
Lighting
Lightning Protection system
Transient Voltage/Surge Protection
wiring for Equipment Furnished by Others
Fire Alarm System
Telephone Conduit Systems
Lighting Control Equipment
03/24/92
00001 - 9
TABLE OF CONTENTS (ADD. 8)
SECTION 00993
SCHEDULE OF DRAWINGS
NUMBER
0.00
0.01
0.02A
0.03
0.04
0.05
1.00A
1.00B
1. OOC
1.01A
1.02A
1.03A
1.04A
1.05A
1. 06
1.06A
1.07A
1.08A
1.09A
DRAWING TITLE
DRAWING
LATEST
REVISION DATE
Rev 11/11/91
1 Rev 11/11/91
2 Rev 01/09/92
2 Rev 01/09/92
2 Rev 01/09/92
1 Rev 11/11/91
1 Rev 11/11/91
1 Rev 11/11/91
Cover
Index of Drawings
Symbols and Abbreviations (Architectural)
Life Safety Plan Ground Floor
Life Safety Plan First Floor
Life Safety Plan 2nd Floor
Existing Conditions North
Existing Conditions central
Existing Conditions South
Not Used
Not Used
Final site Layout Central
-2------Rcv .. 02 {9~
4..'Re'l HO~lg3/92
BG 3 10 jl--5j-9-l-
1 Rev04jOJ/92
Final site Layout and Grading South
Final Grading North
1 Rev 11/11/91
Rough Grading and Drainage
4 Rev 02/18/92
Final Grading and Drainage Central
-l Rcv 02/07/92
2 Rev 04/03/92
Not Used
Final Site Utilities Central
~-ev~-B:t-f~
3 Rev 04/03/92
Not Used
1.10 Entrance Enlarge~Ent
1 Rev 02/07/92
BG3 10/15/91
1.11 Landscape Plan North
1.12 Landscape Plan Central
1 Rev 02/07/92
05/02/92 BG-3 SCHEDULE OF DRA\HNGS (ADD. 11)
00993 - 1
1.13 Landscape Plan South
1. 14 Irrigation Plan North
1. 15 Irrigation Plan Central
1. 16 Irrigation Plan South
1. 17 Pump station Grinder Details
1. 18 Not used
1.19 Not Used
1. 20 site Details Fencing and Paving
1. 21 Landscape Irrigation Details
1. 22 civil Details
3.01 Not Used
3.02 Foundation Plan, Ground Floor Zone B
3.03 Not Used
3.04 Not Used
3.05 Not Used
3.06 Not Used
3.07 Framing Plan First Floor Zone A
3.08 Framing Plan First Floor Zone B
3.09 Framing Plan First Floor Zone C
3.10 Framing Plan First Floor Zone 0
3.11 Framing plan First Floor Zone E
3.12 Framing Plan First Floor Zone F Alternate
3,13 Framing Plan Second Floor Zone A
3.14 Framing plan Second Floor Zone B
3.15 Framing Plan Second Floor Zone C
BG3 10/15/91
BG3 10/15/S
1 Rev 02/07/92
BG3 10/15/91
1 Rev 11/11/91
~,,-!~~2-1-{H-f-.g-,;;
3 .8f2Y94/?8j92
BG3 10/15/91
BG3 10/15/91
1 Rev 02/18/92
3 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
6 Rev 02/07/92
6 Rev 02/07/92
BG3 11/11/91
5 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 2
3,16 Framing Plan Hezzanine Level Zone D 5 Rev 02/07/92
3.17 Framing plan Mezzanine Level Zone E 5 Rev 02/07/92
3.18 Framing Plan Mezzanine Floor Zone F BG3 11/11/91
Alternate
3.19 Framing Plan 11echanica 1 Plenum Zone D BG3 11/11/91
3.20 Framing Plan Mechanical Plenum Zone E BG3 11/11/91
3.21 Framing Plan Mechanical Plenum Zone F BG3 11/11/91
Alternate
3.22 Framing Plan Roof Level Zone A 4 Rev 02/07/92
3.23 Framing Plan Roof Level Zone B 3 Rev 02/07/92
3.24 Framing Plan Roof Level Zone C 3 Rev 02/07/92
3.25 Framing Plan Roof Level Zone D 5 Rev 02/07/92
3.26 Framing Plan Roof Level Zone E 5 Rev 02/07/92
3.27 Framing Plan Roof Level Zone F Alternate BG3 11/11/91
3.28 Not Used
3.29 Not Used
3.30 Not Used
3.31 Foundations, sections and Details 4 Rev 02/18/92
3.32 Typical Details 4 Rev 02/07/92
3.33 sections & Details 4 Rev 02/07/92
3.34 sections & Details 3 Rev 02/07/92
3.35 Precast h'all Schedule & Details 4 Rev 02/07/92
3.36 Precast Column Schedule & Details 4 Rev 02/07/92
3.37 General Notes & Abbreviations & Typical 4 Rev 02/07/92
Details
3.38 sections & Details 3 Rev 02/07/92
3.39 sections & Details 5 Rev 02/07/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 3
05/02/92
4.01 Exterior Building Plan Ground Floor Zone A 1 Rev 02/07/92
4.01A Building plan Ground Floor Zone A 1 Rev 02/0 )2
4.02 Exterior Building Plan Ground Floor Zone B BG3 11/11/91
4.02A Building Plan Ground Floor Zone B BG3 10/15/91
4.03 Exterior Building Plan Ground Floor Zone C BG3 11/11/91
4.03A Building Plan Ground Floor Zone C BG3 10/15/91
4.04 Exterior Building Plan Ground Floor Zone D BG3 11/11/91
4.04A Building Plan Ground Floor Zone D Housing BG3 10/15/91
4.05 Exterior Building Plan Ground Floor Zone E BG3 11/11/91
Housing
4.05A Building Plan Ground Floor Zone E Housing BG3 10/15/91
4.06 Exterior Building plan Ground Floor Zone F BG3 11/11/91
Housing Alternate
4.06A Building plan Ground Floor Zone F Housing BG3 10/15/91
Alternate
4.07 Exterior Building plan First Floor Zone A 1 Rev 02/07/92
4.08 Exterior Building Plan First Floor Zone B BG3 11/11/...-.1,
4.09 Exterior Building plan First Floor Zone C 4 Rev 02/07/92
4.10 Exterior Building Plan First Floor Zone D BG3 11/11/91
Housing
4.11 Exterior Building Plan First Floor Zone E BG3 11/11/91
Housing
4.12 Exterior Building Plan First Floor Zone F BG3 11/11/91
Housing Alternate
4.13 Exterior Building Plan Second Floor Zone A 4 Rev 02/07/92
4.14 Exterior Building plan Second Floor Zone B BG3 11/11/91
4.15 Exterior Building Plan Second Floor Zone C 3 Rev 02/07/92
4.16 Exterior Building plan 1'1ezzanine Level 4 Rev 04/03/92
Zone D Housing
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 4
05/02/92
4.17 Exterior Building Plan Mezzanine Level
Zone E Housing
4.18 Exterior Building Plan Mezzanine Level
Zone F Housing Alternate
4.19 Mechanical Plenu~ Plan Zone D
4.20 Mechanical Plenun Plan Zone E
4.21 Mechanical Plenun Plan Zone F Alternate
4.22 Building Plan Roof Level Zone A
4.23 Building Plan Roof Level Zone B
4.24 Building Plan Roof Level Zone C
4.25 Building plan Roof Level Zone D
4,26 Building Plan Roof Level Zone E
4.27 Building Plan Roof Level Zone F Alternate
4.28 Exterior Elevations
4.29 Exterior Elevations
4.30 Exterior Elevations
4.31 Exterior Elevations
4,32 Exterior Elevations
4.33 Exterior Elevations
4.33A Exterior Elevations
4.34 Wall sections
4.35 Wall sections
4.36 Wall Sections
4.37 Wall sections
4.38 Exterior Details
4.39 Exterior Details
4.40 Exterior Details
BG3 11/11/91
BG3 11/11/91
BG3 11/11/91
BG3 11/11/91
BG3 11/11/91
4 Rev 02/07/92
3 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
BG3 11/11/91
2 Rev 02/07/92
1 Rev 02/07/92
3 Rev 02/07/92
3 Rev 02/07/92
BG3 11/11/91
BG3 11/11/91
2 Rev 02/07/92
4 Rev 02/07/92
3 Rev 02/07/92
2 Rev 02/07/92
5 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
5 Rev 02/07/92
05/02/92 BG-3 SCHEDCLE OF DRAWINGS (ADD. 11)
00993 - 5
4.41
4.41A
4.41B
4.42
4.43
4.44
4.45
4.46
4.47
4.47A
4.48
4.49
4.50
4.51
4.52
4.53
4.54
4.55
4.56
4.57
4.58
4.59
4,60
4.61
05/02/92
Exterior Details
Exterior Details
Exterior Details
Metal Door & window Frame Elevations &
Details, Door Schedule
Not Csed
Not Used
Not Used
stair Plans & sections
stair Plans & sections
stair Plans & sections
stair Details
Elevator plans & sections
Elevator Details
Enlarged Cell - plans & Elevations
Not Used
Interior Building Plan First Floor Zone A
Interior Building Plan First Floor Zone B
Interior Building Plan First Floor Zone C
Interior Building plan First Floor Zone D
Housing
Interior Building Plan First Floor Zone E
Housing
Ir:terior Building plan first floor Zone F
Housing Alternate
Interior Building Plan Second Floor Zone A
Interior Building plan Second floor Zone B
Interior Building Plan Second Floor Zone C
BG3 11/11/91
BG3 11/11,
3 Rev 02/07/92
3 Rev 12/20/91
BG3 11/11/91
3 Rev 02/07/92
BG3 11/11/91
BG3 11/11/91
2 Rev 02/07/92
2 Rev 02/07/92
BG3 11/11/91
3 Rev 02/07/92
2 Rev 01/09/92
1 Rev 11/11/91
2 Rev 01/09/92
2 Rev 01/09/92
1 Rev 01/09/9'2
2 Rev 02/07/9'2
1 Rev 11/11/9:'
1 Rev 11/11/9:
00993 - f
BG-3 SCHEDULE OF DRPJ'HNGS (ADD. 11)
4.62
4.63
4.64
4.65
4.66
4.67
4.67A
4.68
4.69
4.70
4.71
4.72
4.73
4.74
4.75
4.76
4.77
4.78
4.79
4.79A
4.80
6.01
6.02
Interior Building Plan Mezzanine Level D
Housing
Interior Building Plan Mezzanine Level
Zone E Housing
Interior Building Plan Mezzanine Level
Zone F Housing Alternate
Building sections
Building sections
Not Used
Partition Types
Interior Details
Interior Details
Interior Details
Interior Details
Interior Details
Door Schedule
Door Schedule
Door Schedule
H.M. Elevations
Door and Window Details and Buck Types
Finish Schedule
Finish Schedule
Finish Schedule
Miscellaneous Details
Reflected ceiling Plan Ground Floor Zone A
Not Used
05/02/92
BG-3 SCHEDULE OF DRA\~INGS (ADD. 11)
00993 - 7
1 Rev 02/07/92
2 Rev 02/07/92
BG3 10/15/91
BG3 10/15/91
2 Rev 01/02/92
2 Rev 02/07/92
2 Rev 02/07/92
1 Rev 02/07/92
2 Rev 02/07/92
1 Rev 02/07/92
2 Rev 02/07/92
3 Rev 01/09/92
4 Rev 01/09/92
2 Rev 01/09/92
1 Rev 01/09/92
BG3 10/15/91
4 " C" r., 1-{J3+9~
..... .. '\",~
5 Rev 01,/28/92
4 ~cv O~-f03/92
5 Rev 01,/28/92
~~v~:r-f2--G-!..1H:
5Rev.O~J28/92
BG3 10/15/91
1 Rev 02/07/92
6.03
Reflected Ceiling Plan Ground Floor Zone C
6,04 Not Used
6,05
6.06
6.07
6.08
6.09
6.10
6.11
6.12
6.13
6.14
6.15
6.16
6.17
6.18
6.19
6,20
7.00
7.01
7.02
7.03
7,04
Not Used
Not Used
Reflected Ce il ing Plan First Floor Zone A
Reflected Ceiling Plan First Floor Zone B
Reflected Ceiling Plan First Floor Zone C
BG3 10/15/91
1 Rev 02/07/92
BG3 10/15/91
BG3 10/15/91
Reflected Ceiling Plan First Floor D Housing BG3 10/15/91
Reflected Ceiling Plan First Floor Zone E
Housing
Reflected Ceiling Plan First Floor Zone F
Housing Alternate
Reflected Ceiling Plan Second Floor Zone A
Reflected Ceiling Plan Second Floor Zone B
Reflected ceiling Plan Second Floor Zone C
Reflected Ceiling plan Mezzanine Level
Zone D Housing
Reflected Ceiling Plan Mezzanine Level
Zone E Housing
Reflected Ceiling Plan Mezzanine Level
Zone F Housing Alternate
Ceiling Details
Ceiling Details
standard Mounting Heights
Not uSEd
Not uSEd
Equip~Ent Plan Ground Floor Zone C
Not Used
BG3 10/15/91
BG3 10/15/91
1 Rev 02/07/92
1 Rev 12/20/91
BG3 10/15/91
1 Rev 02/0- 2
1 Rev 02/07/92
BG3 10/15/91
2 Rev 02/07/92
2 Rev 04/03/92
1 Rev 11/11/91
BG3 10/15/91
05/02/92
------------
BG-3 SCHEDULE OF DRP.\VINGS (ADD. 11)
00993 - 8
7.05
Not Used
7.06
Not Used
7.07 Equipment Plan First Floor Zone A
7.08 Equipment Plan First Floor Zone B
7.09 Equipment Plan First Floor Zone C
7.10 Equipment Plan First Floor Zone D Housing
7.11 Equipment Plan First Floor Zone E Housing
7.12 Equipment Plan First Floor Zone F Housing
Alternate
7.13 Equipment plan Second Floor Zone A
7.14 Equipment Plan Second Floor Zone B
7.15 Equipment Plan Second Floor Zone C
7.16 Equipment Plan Mezzanine Level Zone D
Housing
7.17 Equipment Plan Mezzanine Level Zone E
Housing
7.18 Equipment Plan Mezzanine Level Zone F
Housing Alternate
7.19 Enlarged Toilet/Shower Equipment Plan
7.20 Enlarged Plans
7.21 Millwork Elevations
7.22 Millwork Elevations
7.23 Millwork Elevations
7,24 Millwork Elevations
7.25 Millwork Details
7.26 Millwork Details
FS-1 Food Service Equipment Schedule
FS-2 Food Service Equipment Plan
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
1 Rev 11/11/91
BG3 10/15/91
BG3 10/15/91
1 Rev 11/11/91
1 Rev 11/11/91
1 Rev 11/11/91
1 Rev 04/03/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 02/07/92
1 Rev 02/07/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 01/02/92
BG3 10/15/91
BG3 10/15/91
00993 - 9
fS-3
Food Service Mechanical plan
fS-4
Food Service Electrical Plan
fS-5
Food Service PI~~bing Plan
fS-6
Food Service Equipment Details
FS-7
Food Service Equipment Details
L-1
Laundry Equipment Plan and Schedule
L-2
Laundry Mechanical Plan
L-3
Laundry Electrical Plan
L-4
Laundry Plumbing Plan
VQL~_
0.00
Cover
0.01
Index of Drawings
8.00
Plumbing Legend
8.00A
Plumbing Schedules
8.01
Plumbing Ground Floor Zone A
8.02 Plumbing Ground Floor Zone B
8.03 Plumbing Ground Floor Zone C
8.04 Plumbing Ground Floor Zone D Housing
8.05 Plumbing Ground Floor Zone E Housing
8.06 Plumbing Ground Floor Zone F Housing
Alternate
8.07 Plumbing First Floor Zone A
8.08 Plumbing First Floor Zone B
8.09 Plu~bing First Floor Zone C
8.10 Plumbing First Floor Zone D Housing
8.11 Plumbing First Floor Zone E Housing
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
BG3 10/15/91
BG3 10/15/9
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
Rev 11/11/91
BG3 10/15/91
1 Rev 12/20/91
3 Rev 02/0')2
BG3 10/15/91
3 Rev 01/02/92
2 Rev 01/09/92
BG3 10/15/91
1 Rev 11/11/91
2 Rev 02/07/92
BG3 10/15/91
1 Rev 01/02/92
2 Rev 01/09/92
1 Rev 12/20/91
00993 - 11"
8.12 PI ur,bing First Floor Zone F Housing 1 Rev 11/11/91
Alternate
8.13 PluE,bing Second Floor Zone A 1 Rev 01/09/92
8.14 pluBbing Second Floor Zone B BG3 10/15/91
8.15 Plunbing Second Floor Zone C 2 Rev 12/20/91
8.16 Plumbing :!ezzanine Level Zone D Housing 1 Rev 12/20/91
8.17 Plumbing ~!ezzanine Level Zone E Housing BG3 10/15/91
8.18 Plumbing Mezzanine Level Zone F Housing BG3 10/15/91
Alternate
8.19 Plumbing plenum Plan Zone D Housing 1 Rev 01/09/92
8.20 Plumbing Plenum Plan Zone E Housing BG3 10/15/91
8.21 Plumbing Plenum Plan Zone F Housing BG3 10/15/91
Alternate
8.22 Plumbing Schedules and Details 1 Rev 01/02/92
8.23 Plumbing Riser Diagram 2 Rev 02/07/92
8.24 Plumbing Riser Diagram 1 Rev 01/09/92
8.25 Plumbing Riser Diagram 1 Rev 01/09/92
8.26 Plumbing Riser Diagram BG3 10/15/91
8.27 Plumbing Riser Diagram BG3 10/15/91
8.28 Plur.,bing Riser Die.gram BG3 10/15/91
8.29 Plumbing Riser Diagram BG3 10/15/91
8.30 PlulT,bing Riser Diagram BG3 10/15/91
8.31 PI uT:'.bing Riser Diagram BG3 10/15/91
8.32 Plurbing Riser Die.gram 1 Rev 11/3 J /91
8.33 Plur:-~bing Riser Die.gram BG3 10/15/91
8.34 Plurbing Riser Die.gram BG3 10/15/91
8.35 Plunbing Kitchen Plan 1 Rev 01/02/92
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 11
8.36
9.01
9.02
9.03
9.04
9.05
9.06
9.07
9.08
9.09
9.10
9. II
9.12
9.13
9.14
9.15
9.16
9.17
9.18
9.19
9.20
9.21
9.22
10.01
10.02
05/02/92
Waste Handling system Details
Not Used
Not Used
Not Used
Not Used
Not used
Not Used
piping plan First Floor Zone A
piping Plan First Floor Zone B
piping plan First Floor Zone C
piping plan First Floor Zone D Housing
piping plan First Floor Zone E Housing
piping plan First Floor Zone F Housing
Alternate
piping plan Second Floor Zone A
piping Plan Second Floor Zone B
piping plan Second Floor Zone C
piping plan Mezzanine Level Zone D Housing
piping plan Mezzanine Level Zo~e E Housing
Piping plan Mezzanine Level Zone F Housing
Alternate
Not Used
Not used
Fuel oil Details
piping Diagrams
Not Used
HVAC plan Ground Floor Zone B
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
1 Rev 01/02/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/_J..
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
--~----------"---
00993 - )'"
10.03 HVJ..C plan Ground Floor Zone C -BG3 10/15/91
10.04 HVAC Plan Ground Floor Zone D Housing BG3 10/15/91
10.05 HVAC Plan Ground Floor Zone E Housing BG3 10/15/91
10.06 HVAC Plan Ground Floor Zone F Housing BG3 10/15/91
Alternate
10.07 HVAC Plan First Floor Zone A 1 Rev 02/07/92
10.08 HVAC plan First Floor Zone B BG3 10/15/91
10.09 HVAC plan First Floor Zone C BG3 10/15/91
10.10 HVAC Plan First Floor Zone D Housing 1 Rev 01/09/92
10.11 HVAC Plan First Floor Zone E Housing 1 Rev 01/09/92
10.12 HVAC Plan First Floor Zone F Housing 1 Rev 01/09/92
Alternate
10.13 HVAC Plan Second Floor Zone A 1 Rev 02/07/92
10.14 HVAC Plan Second Floor Zone B 1 Rev 12/20/91
10.15 HVAC Plan Second Floor Zone C 1 Rev 01/09/92
10.16 HVAC Plan Mezzanine Level Zone D Housing BG3 10/15/91
10.17 HVAC Plan Mezzanine Level Zone E Housing BG3 10/15/91
10.18 HVAC Plan Mezzanine Level Zone F Housing BG3 10/15/91
Alternate
10.19 HVAC Plenum Plan Zone D Housing BG3 10/15/91
10.20 HVAC Plenum Plan Zone E Housing BG3 10/15/91
10.21 HV;.C Ple:1um Plan Zone F Housing Alternate BG3 10/15/91
10.22 Not Used
10,23 Not Used
10.24 HVAC Plc:1 Roof Level Zone C 1 Rev 01/09/92
10.25 Not Used
10.26 Not Used
BG-3 SCEEDULE OF DRAWINGS (ADD. 11)
00993 - 13
05/02/92
10.27
10.28
10.29
10.30
10.31
10.32
10.33
10.34
10.35
10.36
10.37
11. 00
11.00A
11.01
11.02
11.03
11.04
11. 05
11.06
11.07
11.08
11.09
11.10
not Used
Enlarged Hechanical Room Plan
HVAC Details
HVAC Details
HVAC Details
HVAC Schedules
HVAC Schedules
HVAC Schedules
Central Plant Control Diagrams
HVAC Temperature Control
HVAC Smoke control
Electrical Symbols and Notes
Electrical site Lighting Plan
Power and Lighting Plan Ground Floor
Zone A
Power and Lighting Plan Ground Floor
Zone B
Power and Lighting Plan Ground floor
Zone C
po~er and Lighting plan Ground Floor
Zone D Housing
Power and Lighting Plan Ground Floor
Zone E Housing
power and Lighting Plan Ground Floor
Zone F Housing Alternate
power Plan first Floor Zone A
Lighting plan First Floor Zone A
po~er Plan First Floor Zone B
Lighting plan first floor Zone B
05/02/92
BG-3 SCHEDuLE OF DRA'iVINGS (ADD. 11)
BG3 10/15/
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
1 Rev 11/11/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
1 Rev 02/07/92
BG3 10/15/':>...
1 Rev 01/02/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 03/04/92
BG3 10/15/91
2 Rev 03/04/92
BG3 10/15/91
00993 - 1L1
11.11
11.12
11.13
11.14
11.15
11.16
11.17
11.18
11.19
11.20
11.21
11.22
11.23
11.24
11.25
11.26
11.27
11.28
11.29
11.30
Power Plan First Floor Zone C
Lighting Plan First Floor Zone C
Power Plan First Floor Zone D Housing
Lighting Plan First Floor Zone D Housing
Power Plan First Floor Zone E Housing
Lighting Plan First Floor Zone E Housing
Power Plan First Floor Zone F Housing
Alternate
Lighting Plan First Floor Zone F Housing
Alternate
Power Plan Second Floor Zone A
Lighting Plan Second Floor Zone A
Power Plan Second Floor Zone B
Lighting Plan Second Floor Zone B
Power Plan Second Floor Zone C
Lighting Plan Second Floor Zone C
Power Plan Mezzanine Level Zone D Housing
2 Rev 03/04/92
BG3 10/15/91
3 Rev 03/04/92
BG3 10/15/91
3 Rev 03/04/92
BG3 10/15/91
2 Rev 01/02/92
BG3 10/15/91
1 Rev 03/04/92
BG3 10/15/91
2 Rev 03/04/92
1 Rev 12/20/91
1 Rev 03/04/92
BG3 10/15/91
2 Rev 03/04/92
Power Plan Mezzanine Level Zone E Housing
Lighting Plan Mezzanine Level Zone D Housing BG3 10/15/91
2 Rev 03/04/92
Lighting Plan ~ezz2nine Level Zone E Housing BG3 10/15/91
Power plan Vezzanine Level Zone F Housing
Alternate
1 Rev 12/20/91
Lighting Plan Xezz2nine Level Zone F Housing BG3 10/15/91
Alternate
11.31 Power and Lighting Plan Plenum Plan Zone D
Housing
11.32 Power and Lighting Plan Plenum Plan Zone E
Housing
11.33 Power and Lighting Plan plenum Plan Zone F
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 15
11.34
11.35
11.36
11.37
11.38
11.39
11.40
11.4l
11.42
11.43
11.44
11.45
11.46
11.47
11.48
11,49
11. 50
11.51
11.52
Housing Alternate
Power plan Roof Level Zone A
Power Plan Roof Level Zone B
Power Plan Roof Level Zone C
Power Plan Roof level Zone D
Power Plan Roof level Zone E
power plan Roof Level Zone F Alternate
Electrical Enlarged Kitchen Plan
Electrical Enlarged Laundry plan
Lightning Protection Plan
Lightning Protection Plan Details
Electrical Riser Diagram Part 1
Electrical Riser Diagram Part 2
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Not Used
12.01 communicatic~s plan Ground Floor Zone A
12.02 communications plan Ground Floor Zone B
12.03 communications Flan Ground Floor Zone C
12.0~ Communications plan Ground Floor Zone D
Housing
12.05 communications Flan Ground Floor Zone E
Housing
05/02/92 BG-3 SCHEDCLE OF DRA\'HNGS (ADD. 11)
BG 3 1 0/ 15/
BG3 10/15/91
1 Rev 01/09/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 01/02/92
1 Rev 11/11/91
BG3 10/15/91
5 Rev 03/( 92
1 Rev 11/11/91
2 Rev 01/09/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
1 Rev 03/04/92
BG3 10/15/91
BG3 10/15/91
00993 - 1"'-
12.06
12.07
12.08
12.09
12.10
12.11
12.12
12.13
12.14
12.15
12.16
12.17
12.18
12.19
12.20
12.21
12.22
12,23
12,24
12,25
12,26
12.27
communications Plan Ground Floor Zone F
Housing Alternate
communications Plan First Floor Zone A
communications Plan First Floor Zone B
communications Plan First Floor Zone C
communications Plan First Floor Zone D
Housing
communications Plan First Floor Zone E
Housing
communications Plan First Floor Zone F
Housing Alternate
communications Plan Second Floor Zone A
communications plan Second Floor Zone B
Communications Plan Second Floor Zone C
Communications Plan Mezzanine Level Zone D
Housing
communications Plan Mezzanine Level Zone E
Housing
communications Plan Mezzanine Level Zone F
Housing Alternate
Fire Alarm Riser Diagram
Telephone Riser Diagram and Elevator
Fire Alarm System
Not Used
Not Used
Not Used
Security Plan Ground Floor Zone A
Security Plan Ground Floor Zone B
Security Plan Ground Floor Zone C
Security Plan Ground Floor Zone D Housing
BG3 10/15/91
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
BG3 10/15/91
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
BG3 10/15/91
BG3 10/15/91
1 Rev 12/20/91
1 Rev 12/20/91
1 Rev 12/20/91
1 Rev 12/20/91
1 Rev 12/20/91
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 17
12.28
Security Plan Ground Floor Zone E Housing
1 Rev 12/20/91
12.29
security Plan Ground Floor Zone F Housing
Alternate
1 Rev 12/2
) 1
12.30 Security Plan First Floor Zone A 3 Rev 03/04/92
12.31 Security Plan First Floor Zone B 3 Rev 03/04/92
12.32 security Plan First Floor Zone C 2 Rev 03/04/92
12.33 Security Plan First Floor Zone D Housing 3 Rev 03/04/92
12.34 security Plan First Floor Zone E Housing 3 Rev 03/04/92
12.35 security Plan First Floor Zone F Housing BG3 10/15/91
Alternate
12.36 security Plan Second Floor Zone A 5 Rev 03/04/92
12.37 Security Plan Second Floor Zone B 1 Rev 12/20/91
12.38 security Plan Second Floor Zone C 3 Rev 03/04/92
12.39 security Plan Mezzanine Level Zone 0 3 Rev 03/04/92
Housing
12.40 Security Plan Mezzanine Level Zone E 3 Rev 03/04/92
Housing
12.41 security Plan ~ezzanin Level Zone F 1 Rev 12/20/91
Housing Alternate
12.42 Security systems Riser Diagram 2 Rev 02/07/92
12.43 Details 1 Rev 02/07/92
12.44 Details 1 Rev 12/20/91
13.01 Fire Protection Ground Floor Zone A BG3 10/15/91
13.02 Fire Protection Ground Floor Zone B BGJ 10/15/91
13.03 Fire Protection Ground Floor Zone C BG3 10/15/91
13.04 Fire Protection Ground Floor Zone D Housing BG3 10/15/91
13.05 Fire Protection Ground Floor Zone E Housing BG3 10/15/91
13.06 Fire Protection Ground Floor Zone F Housing BG3 10/15/91
Alternate
05/02/92 BG-3 SCHEDULE OF DRA\'HNGS (ADD. 11) 00993 - P'
13.07 Fire Protection First Floor Zone A BG3 10/15/91
13.08 Fire Protection First Floor Zone B BG3 10/15/91
13.09 Fire Protection First Floor Zone C BG3 10/15/91
13.10 Fire Protection First Floor Zone D Housing BG3 10/15/91
13.11 Fire Protection First Floor Zone E Housing BG3 10/15/91
13.12 Fire Protection First Floor Zone F Housing BG3 10/15/91
Alternate
13.13 Fire Protection Second Floor Zone A BG3 10/15/91
13.14 Fire Protection Second Floor Zone B BG3 10/15/91
13.15 Fire Protection Second Floor Zone C BG3 10/15/91
13.16 Fire Protection Mezz. Level Zone 0 Housing BG3 10/15/91
13.17 Fire Protection Hezz. Level Zone E Housing BG3 10/15/91
13.18 Fire Protection Mezz. Level Zone F Housing BG3 10/15/91
Alternate
13.19 Not Used
13,20 Not Used
13.21 Not Used
13.22 Not Used
13.23 Not Used
13.24 Not Used
13.25 Not Used
13.26 Not Used
13.27 Not Used
13,28 Fire Protection Details BG3 10/15/91
13.29 Fire Protection Details BG3 10/15/91
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 19
SECTION 00334
SCOPE OF WORK
Bid Package No. 34
Gypsum Board, Lath & Plaster
1.1 General Scope
Provide all labor, supervision, engineering, materials,
supplies, equipment, tools, transportation, surveying and
layout, and protection, to install complete operating
systems, and proper execution and completion of all Work
specif ied on the drawings, in the bid package, and the
sections of the Specifications, which include, but are not
limited to the listing that follows. The bidder shall review
all drawings, and specification sections that are not
specifically listed, for any additional requirements in order
to complete the scope of work described herein.
Scecifications sections and Descriptions
05810
07210
08305
09110
09200
09250
L~090
Expansion Joint Cover Assemblies
Building Insulation
Access Panels and Doors
Non-Load Bearing Wall Framing Systems
Lath and Plaster
Gypsum Board
n~di~on Pro~cction
1.2 Special provisions
The following Special provisions are intended to clarify the
5cope of work, or highlight features of the work, or modify,
change, add to, or delete from the General Scope of this Bid
Package.
.1 All licenses required in order to perform the scope of
work in the specified location, shall be procured and
maintained by the contractor and his subcontractors.
Contractor shall submit copies to the Construction
Manager. Contractor shall be responsible for applying
for, and procuring the cO;lstruction Q?rni t as required by
the City of Key West; ho~ever, the Owner shall literally
pay the fee for the permit.
.2 Contractor shall :-:-,aintain As-Built drawings, (Record
Drawings per section 01720), of his work progression. A
50% progress of field work submittal, will be required.
05/04j92
GYPSUM BOARD SCOPE OF WORK (ADD. 11)
00334 - 1
.3 Provide, replace, and maintain any safety rails and
barricades as necessary during the process of *ork, or
during deliveries of materials or equipment.
.4 Contractor is to review Division 1 General Requirements
for additional responsibilities required in crder to
perform the work under this Bid Package.
Contractor shall pay particular attention to section
01710 Final Cleaning, which shall be performed as
scheduled by the CM, which will be at or r:.ear the
completion of the project.
.5 Access Panels and Doors - Install all access panels and
doors that are required to be installed in gypsum board
or plaster. Coordinate with other trade contractors for
locations. Access panels and doors will be furnished by
others.
The Access Panels and Doors Schedule, attached and
labelled Attachment 'B', represents those access panels
and doors that are not shown on the plans, but "'::Jich are
required by other trade contractors. The schedule shows
several types, and that they are to be installed in
various substrates. This schedule is to be used as a
guide, in order for this contractor to bid and understand
the requirements of this scope of work item. The
quantities are not absolute, and contractor shall be
require to make installations of all quantities that are
to be installed in ~um board or plaster.
.6 utility Routinq and Coordination of the Work
This contractor shall be responsible to coordinate his
work with other multiple prime contractors both in the
scheduling of field work activities and in the
integration of individually furnished items ir:.to final
composite installations.
.7 Furnish to, and receive from the appropria":e trade
contractor, for installation in precast concrete, non-
load bearing walls, masonry, and cast-in-place concrete,
a 11 frames, sleeves, anchors, weld plates 2.:Jd other
similar inserts or devices required to facil:tate and
coordinate the complete Work in this Bid Package. Submit
routing shop drawings showing wall elevation, :loor and
ceiling plans with requirerr.ents for location and size
suitable for field location and installation. C20rdinate
and verify correctness of installation as the work
progresses. Ver i fy pr ior to casting in form ',..'Ork, or
during line and grade installation of major feature
05/04/92
GYPSUM BOARD SCOPE OF HORK (ADD. 11)
C8334 - 2
progress.
This shall include this contractor's responsibility to
install all block ~g, anchors, inserts, and similar
fastenings, in \>"21 s, for other trades to attach their
work.
.8 All unfinished surfaces of materials or equipment
furnished or installed by this contractor, shall be
inspected for readi~ess by follow-on contractors and the
CM, prior to installation of follow-on work. This would
include bringing back to original condition, surfaces
disturbed by welding, burning, or other disfigurement,
which will need to be made ready for finish painting, or
other work. The Gypsum Board Contractor shall pay
particular attention to protect and clean floor surfaces,
(in compliance with floor covering installation).
.9 This contractor is responsible to coordinate and/or
provide all penetrations shown or not shown on drawings
which are necessary to facilitate the complete
installation of his work, and the work of others. Any
penetration after finish of assembly, shall be the
responsibility of the contractor requiring the
penetration.
It ~ill bc the :ull rcsponsibility of this
contr.:lctor to n~int..:lin gypsum bO.:lrd .:lnd pl.:lstcr
.:lsscr.,blics, or froperly seal in acce-r-eafK'C
rnanufacturcr I s recornIDcndations, as pcr scction
~estop and Pcnetration SC.:lling System.
trade
rated
T,J i th
07272
Anybu.ildirig insulation ..requIredHforgYPsl1m bc,ardarid
lat:l1 &H plaster partitions, Hshall be fuini~,hed and
installed by this contractor, and irfaccbrdancewith.
section 07210 Building InsulG\t:I?n.
.10 Materials and Equipment Furnished by Others All
materials furnisted by the Owner, other contractors for
the Owner, or by t~e CM for the Owner, for installation
by this contractor shall upon delivery, be unloaded,
transferred, stored and fully protected by the contractor
until installed. Any demurrage or similar charge
incurred due to failure of the contractor to promptly
unload the materials and equipment shall be the
responsibility of ~he contractor.
The contractor stall carefully examine all materials and
equipment furnished by the Owner, or any of his
designees, (other contractors or the eM). The contractor
shall complete receiving reports describing the quantity
05/04/92
GYPSUM BOARJ SCOPE OF WORK (ADD. 11)
00334 - 3
and condition of the materials or equipment. The
contractor shall be responsible for subsequent damage or
loss until installation is completed and accepted by the
O',,'ner.
Should the contractor fail to report any visible signs of
damage in the receiving report as indicated above, then
all parties may aSSGDe that the damage occurred while the
Ti,aterials and equipment were in the care, custody and
control of the receiving contractor.
Any material furnished by the Owner, at an off-site
location, on other than a charge basis in connection with
the contract, shall be deemed as held by the contractor
on consignment. All such materials not used in the
fabrication of materials or equipment required under the
contract shall be returned to the applicable party, as
directed, at their expense; and, if not accounted for or
so returned, shall be paid for by the contractor.
.11 P.Il incoming materials and equipment shall be coordinated
with other trades and the CM is to be notified, in order
that proper laydO\.m. staqinq and stockinq areas are
developed, prior to release for shipping. within the
building, areas shall be restricted and stocking areas
will be authorized in writing.
.12 If in the event of conflicting, or overlapping
requirements in any area of the bidding documents,
technical specif ications, or drawings, the most str ingent
condition shall be bid and constructed. Notify the eM in
any event, in order to not compromise the Owner's right
to make appropriate decisions.
.13 This contractor is reminded of inmate contact areas and
perimeters, and of the requirement for security devices,
fasteners I connectors, and any other work associated with
this bid package scope of work, in order that proper care
end construction is performed in accordance with the
stand2rds and guidelines set forth by the regulatory
agencies governing jails.
.14 poor~ Frames, Hard\o;are:
This contractor shall layout all metal stud walls,
ceilings and partitions, and coordinate and verify door
frame installation. Any errors in layout causing
:-:-covement after installation has begun, shall be corrected
at the expense of the wall contr2ctor and frame
installer.
05/04/92
GYPSUM BOARD SCOPE OF WORK (ADD. 11)
00334 - 4
The Gypsum Board Contractor shall be responsible for
arouting hollow metal frames that are attached to metal
stud system. Verify with Metals-Doors-Glazing
Contractor, that his door frame anchors are correct for
the Detal stud systeD being used.
.15 This contractor shall suitably mark ceilinq heights on
walls and columns in order for other trade contractors to
perform above ceiling rough-in work. This applies to all
areas where this contractor has metal stud or lath &
plaster work.
.16 scction 13090 R~d~~~~tcctiBB furni~ ~nd in8t~ll
lc~d l~min~ted gvpsun ~~llbo~rd ~nd in8t~11~tion
occc8sorie8. Coordin~te ~nd f~cilit~te inst~ll~t~n of
r~di~tion protection ..,-ork r~-i-r:cmcnt8 by others-.
.17 This contractor shall interface with spray-on insulation
installation, and schedule and coordinate gypsum board
and plaster work schedule with spray-on insulation work.
.18 This contractor shall notify the CM immediately of any
misalignments of any other trades work, (i.e., plumbing
stub-ups out of wall line, etc.).
.19 Furnish and install expansion joint cover assemblies in
accordance with section 05810, which are to be installed
in the work of this contractor.
.20
Furnish and
specified in
indicated.
install
section
sound attenuation blankets, as
09250 Gypsum Board, wherever
.21 Furnish and install acoustical sealant, where required
and specified, in accordance with section 09250 Gypsum
Board.
.22 Furnish and install wall tile base qypsum backing board,
where required and specified, in accordance with section
09250 Gypsum Board.
.23 furnish and install acoustical tile base gypsum backing
board, where required and specified, in accordance with
Section 09250 Gypsum Board.
.24 Vpon completion of taping and final_sanding of gypsum
board, inspect with follow-on contractor and eM, and
obtain acceptance.
05/04/92
GYPSUM BOARD SCOPE OF v;ORK (ADD. 11)
00334 - 5
.25 O'\.;ner option No. 34-01: Zone 'F' Gvpsum Board, Lath &
PJaster:
At the option of the Owner, furnish and install Zone IF'
Gypsum Board, Lath & Plaster, similar to Zones 'D' and
'[' .
This area is defined as the area bound by column lines G
to La, and 17 line to 24 line, as well as column lines 37
to X, and U line to 42 line.
.26 Owner option No. 34-02: Non-Security Fire Walls:
This bidder shall provide a price to ADD to his scope of
work, the furnishing and installing of wall partitions,
from 8" above ceiling, to underside of structure, as
shown in balloon on detail 4, on sheet 4.67A.
Thisinclude$/ l-11r. arid<2+HE.ratedpartit-i611s, vJith.
approPF.iate ....9Ypsum board<and. non-load bearIng wall
framing <details .< This owner option does hot > include
f irestopping<and ......f iresafin9.w()rktha tJ'\i1Y . .berequired..
Sea lantscont:ractor shall pexesponsibleforfl.restopping
and firesafing for this. QwnerOptiony if <option is
accept~qbyt-he OWner<< ..'
1.3 By Others
.1 Furnishing of access panels and doors.
05/04/92
GYPSUM BOF~D SCOPE OF WORK (ADD. 11)
00334 - 6
SECTION 00353
MILESTONE SCHEDULE
The bar chart and associated activity listing presented in
this section depicts the approximate duration, sequence, and
flow of ~ork of major work groups. Not all activities are
shown and groupings are subjective. Logic diagrans
generating the presented document are available for bidder
review in the office of the Construction Manager.
Contractors will be required to submit construction
schedules to meet the requirements of the presented
milestones and in accordance with the Master Project
Schedule.
The Contractors are to note the following special milestone
dates required for the project.
a. Building Temperature and Humidity
Controlled for Finishes & Follow-on
Work . . . . . .
..........
.11/15/92
b. start Contractor Completion Inspections.Ol/11/93
c.
start Prefinal Inspections . .
.03/02/93
d.
Project Completion . . .
. . . . . .
. .07/0LL2l
03/16/92
MILESTONE SCHEDULE (ADD. 8)
00353 - 1
I . .
~ j ~~Ji
I ,'.
~~;'i
! I J
~
~
i
~ ~
~ i
i1
z
""
-,
~
~ \1\
I! ,1:
, II ill
~ II \1 11:\
'! ,I i'l!
ii' ,j
~ illl
IJ
>-,'-
i i
I
I
\' l' _' ~I
, , . -I
~ ! ~ ~I
-: -: : ::1
~ " e ~
i..i_~c::J
~
..
~ 0
< 4
. C
- ~
';: : ~
~;~
~ :: t
. - 0
~ 5. 2 k
ilJ ~ L~
~
.
~
;;;
- I
.- - U a
~ I 15
~ !
~" I ..
~ !:
r ~
'1 I
-- S ~
, ~
v
c
.. . . . . . .. .. .. .. . . .. ... . .. .. .. .. .. .. .. ... .. ..... ... ... .. .. .. . .. .. ... .. .. ... .. .. . .. . . .. . .. . .. .. ... .. . ... . .. .. .. .. . .. .. .. .. . . . ... .. . .. . .. .. .. . .. .. . .. - .. . ... .. - .. .. . - . .. .. .. .. .. . .. - .. . . .. . ... .. . .. .. .. .. .. .. ... . . .. .. .. . . . . .. . .. .
'''Oroe COlnty. Florida
RT CATE 19OEC91 RUH~. 50
16:28
SCHED REPORT. line skip by &Ctivity code
PRl~~\~RA PROJECT PlA~NER
Monroe COlnty Detention Facility
Mooroe COU"'lty Detention Fadlity
SWH DATE 1""UG91 FIN DATE 1J
DA1A DATE 18~0V91 PAGE NO.
........ ....... ........ ..... . ..... ................. ..................................-........-....--.........................-....... ................ .............. .......-... -............ ..
ACTlVI TY
10
Sit e Ut it i \ I e5
5
H25
1330
1340
2000
2005
2010
2015
2020
2025
2030
2035
2040
2045
2050
3005
30'0
30'5
3020
3050
3055
5000
5005
5010
Caissons
'025
1030
1035
1040
1045
1050
'055
'060
1100
1150
'200
'250
1300
Colums
1105
1110
1115
1155
ORIG REM
DUR DUR
1
5
5
5
30
10
15
5
5
10
10
15
15
15
15
10
10
10
5
15
5
15
15
'5
x
ACTIVITY DESCRIPTION
SCHEDULED
START FINISH
................ ..-...........................................................................--.... -............ .............
o
5
5
5
5
10
'5
5
5
10
10
15
15
15
15
10
'0
10
5
15
5
15
'5
15
100
o
o
o
a3
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
10 0 100
10 0 100
40 0 100
'5 0 100
5 0 100
10 9 10
25 0 , 00
1 1 0
15 15 0
15 15 0
10 10 0
15 15 0
10 10 0
'5
5
20
'5
'5
5
20
15
o
o
o
o
HTP . Site Utilities
SW . Zone C . Sub-Slab Sanitary. loading Dock
SW . Zone C - Storm Drain (JB 28-0 & Upstream)
SW - Zone C . Storm Drain (Inlet 1-12 & Upstream
SW - Utilities - Underground Submittals
SW . Utilities' AlE Apvl of UIG Submittals
SW - Utilities - Install Outfall Structures
SW . Utilities' Instl UIG Terr~rary Pwr & Tele
SW - Utilitie5 - Sanitary Trunk line. ldg Dock
SW . Utilities - Remainder of Sanitary Trunk lln
SW - Utilities . El~trical Ductbank and Tele
SW - Utiliti~ - Instl Greywater line
SW - Utilities' Instl Domestic ~ater line
SW - Utilities' Instl Effluent line
SW - Utiliti~ . Instl Gas Line
SW - Entrance Read - Effluent line
SW - Entrance Read . Domestic/FW Main
SW - Entrance Read . Test/Flush/Disinfect D~/F~
SW - Entrance Road . Tie-in OU/F~ line to F(AA
SW - Utilities - OYerhe&d Power/Tel~one line
SW . Utilities - Temporary Pwr/Tele Startup
SW . Utilities' Storm Drain Trunk lines
SW - Utilities - SO laterials & Tr~h Drain
SW . Utiliti~ - Sanitary laterals
SW - Caisson load Test
SW - AlE Review of Caisson load Test Dati
SW . Caisson Rebar Submittals. Start
S~ - Caisson Rebar Submittals' Complete
SW . AlE Revi~ of Caisson Rebar Submittals
SW - Fabricate & Deliver Caisson Rebar
SW . uindl~ ~~;fication Pricing
SW - wee ~pvl of I/i ndl oad Chaf\ge
SW . Zone ~ - Caissons
SW . Zone D . Caissons
S~ . Zone B - Caissons
S~ . Zone E - Caissons
S~ - Zone C . Caissons
SW . Zone A . Columns & Mise Concrete
S~ . Zone A - Verify locations of Columns
SW . Zone A - Column Concrete Cure Period
SW . Zone D . Columns & Misc Concrete
9OCT91A 9OCT91A
4XAR92 10KAR92
4AAR92 10KAR92
4XAR92 10KAR92
13SEP91A 22~0V91
25NOV91 9OEC91
100EC91 31DEC91
100EC91 16OEC91
100EC91 16OEC91
17DEC91 310EC91
17DEC91 310EC91
2JAII92 22JAN92
2JAI<l92 22JAN92
2JAN92 22JAI/92
2JAI/92 22JAN92
'3JAN92 24JAN92
'3JAH92 24JAH92
27JAN92 7FEB92
10FEB92 14FEB92
13JAII92 31JAII92
3FEB92 7FEB92
17JUN92 8JUl92
17JUN92 8JUl92
17JUN92 8JUL92
7OCT91A 17OCT91A
18OCT91A 6N0V91A
13AUG91A bOCT9'A
7OCT91A 290CT91A
300cT91A 6N0V9'A
13N0V91A 29N0V9'
6OCT91A 13110V91A
20N0V91* 20~Ov91
~EC91 20DEC91
23OEC91 '4JA~92
1SJAN92 28JAN92
29JA~92 i8FEB92
19FEB92 3KAR92
230EC91
'SJAN92
15JA~92
1SJA~92
14JAN92
21JAII92
11FEB92
4fEB92
................. ~....... -..-....-...... -... ....-.... - -........... ..-.. ...... -- ....... ..--...... ..........-..............--.... ..............................- ............................... _.......~.. ..--..... ......-..
~r~ County, Florida
PRIKAVERA PROJECT PLAHHER
Monroe County Detention Fac11ity
REPORT DATE 190EC91 RUW NO. SO
16:28
SCHED REPORT' line skip by activity code
~onroe County Detention Facility
START CATE lAUG91 FIN CAJE 1 I
DATA DATE 1e~0Y91 PAGE
........ .... - .. .. .. .. . ... .. ..... - ... .. ............................. -............ .....-....................... - ................... - --... .. .. ... .. - ... .. ... ... . .. .... .. .. .. .. .. .. .. .. ..... ... . - . - .. .. - .. .'
AC1IVITY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 OUR OUR X START FINISH
......-.. .. .. ....... .. .. . .. .... .. .. .. ... ........... ............. ..-......... ....-....................-..................... - ..-.... ................. - .. ..... .. .. - .. ... .. .. .. ..... . .. .. .. .. .. .. .. .. .. . '
ColUTf"lS
, 1W 5 5 0 SiJ- Zone 0 - Verify locations of Columns SFE892 1 lFE892
,,65 20 20 0 SiJ- Zone D - Column Concrete Cure Period SFE892 3HAR92
1205 10 10 0 S'J- Zone 8 Columns & Mise Concrete 29JAH92 1lFEB92
1210 5 5 0 S'J- Zone 8 . Verify locations of Columns 12FEB92 18FEB92
1215 20 20 0 SiJ- Zone B - Column Concrete Cure Period 12FEB92 1 Ol".AR92
1255 15 15 0 SiJ- Zone E - Columns & Mise Concrete 19FEB92 10KAR92
12W 5 5 0 S'J- Zone E Verify locations of Columns 11MR92 1lXAR92
1265 20 20 0 SiJ . Zone E Column Concrete Cure Period l1KAR92 7APR92
nos 10 10 0 S\l- Zone C . Columns & Mise Concrete 4HAR92 1 lXAR92
1310 5 5 0 S'J- Z or-re C . Verify locations of Columns 1exAR92 24HAR92
1315 20 20 0 SiJ- Zone C . Column Concrete Cure Period 1 e.w.A R 92 HAPR92
1320 20 20 0 S\l- Zone C . F/R/P/C Concrete loading Dock 4AAR92 3 W.AR92
Er~tion Ora~ings
7020 15 15 0 Precast - Column Interfoce Details 21HOY91 12DEC91
7030 15 15 0 Pr~&st . Area A . Fr8tl\ing Drlrolings 21NOY91 1 20E C91
7040 10 10 0 Pr~ast - Area A . AlE Apvl of Fr&ming Drawings 13DEC91 27DEC91
7iOO 15 15 0 Precast - Areas B & 0 - Fr8tl\ing Drawings 13DEC91 6JAN92
7110 10 10 0 Precast. Areas B & D . A/E Apvl of Framing D~9S 7JAN92 20JAH92
noo 15 15 0 Pr~ast Areas C & E . Frbming Dra~ings 7JAN92 27JAII92
n10 10 '0 0 Pr~ast - Areas C & E - A/E Apvl of Framing D~9S 28JAH92 1 OfE B92
Utilities/Precast Coordination Effort
7005 10 0 100 Coordination Method Decision 1HOY91A 1SNOV91A
7050 20 20 0 Pr~ast . Area A . Utl/Pcst Coordination 1eNOY91 160EC91
7120 20 20 0 Pr~Bst . Areas B & D . Utl/Pest Coordination 17DEC91 lSJAN92
n20 15 15 0 Precast - Areas C & E . UtI/Pest Coordination 16JAN92 SFEB92
Deta i I Drawings
7060 15 1S 0 Pr~ast . Area A . Detail Drawings 300EC91 20JAN92
7070 10 10 0 Pr~ast Area A . AlE Apvl of Detail Dra~ings 21JAN92 3fEB92
7130 15 15 0 Precast Areas B & D - Detail Drawings 21 JAI/92 10FE692
7140 10 10 0 Pr~as t - Areas B & 0 . A/E Apvl of Detail D"'9s 1 HEB92 24FEB92
n30 15 15 0 Precast - Areas C & E Detai I Dra~il'\9s 1HE892 2KAR92
n40 10 10 0 Pr~ast - Areas C & E . A/E Apvl of Detail Dwgs 31':AR92 1t.KAR92
fabricBt ion
7080 20 20 0 Precast . Area A - F abr icat ion 4FEB92 2KAR92
7090 5 5 0 Precast - Area A . BE'9in ShiWing to Site 3KAR92 ~.AR92
7150 20 20 0 Pr~ast . Area B - Fabricat i on 25FEB92 23MAR92
71W 10 10 0 Pr~ast . Area B . Begin Shipping to Site 2t.~.AR92 6APR92
7170 40 40 0 Pr~ast . Area D . Fabrication 25FEB92 20APR92
71eo 10 10 0 Pr~ast . Area D - BE'9in Shipping to Site 21APR92 1.1'.,1.1'92
7250 25 25 0 Precast - Area C . Fabrication 2SKAR92 28APR92
nw 5 5 0 Pre<:ast - Area C - Begin Shipping to Site 29APR92 SKAY92
7270 40 40 0 Precast - Area E . fabrication 181".AR92 12HAY92
7280 5 5 0 Pr~ast Area E Begin Shippir-g to Site 131':AY92 1 9loIA Y92
. .......... ........... ....... ................-..... ........... ............. ......... ........... ...... .............. - ....-....--.. - .................. ...............- ...-.. -..... .......... ......--..........-..--...-........ ..............
&/onr~ COUlty, Fl or ida PRI~'V[RA PROJECT PL~~NER ~onroe COUlty Oetentlon Facility
~l DATE 190E(;91 RUN WOo 50 ~onroe County Detention Facility ST ART DATE ,....UG91 FIN DATE 1.-
16:28
SCMED REPORT . line s~lp by activity code OAT.... DATE l&lOW1 P....GE NO.
... .. .. . .... - .. . . . - . .. .. - - ... .. - .. .. .. ....-. ...- -... ....-.......-..... .............--...-..... -... - ..--....... -...... -............... .. .. - ...... - - .................. .. - .. .. -...... .'
....CTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 DUR OUR X START FINISH
........ ........- . . .. .. .. .. .. ....... ... ........-....-..-..-........-.......-....--.......--...........--........-....-- --......-..- .......-....- ...-.........- .. .. .. -.. -...
Pre<:ast Ere<:t ion
lOOOO 40 40 0 Pre<:ast - Area A . Erection lOOR92 4XAY92
20000 30 30 0 Precast . Area B - Erection 5101AY92 16JUN92
30000 30 30 0 Precast . Mea C - Erection 17JUN92 29JUl92
40000 30 30 0 Precast . Area 0 . Erect i on 5 IoIAY 92 l6JUN92
50000 30 30 0 P recas t - Area E . Erection 17 JUN92 29JUl92
Roof
lO050 10 10 0 Area A . Roof - Roofing 3JUN92 16JUN92
20050 10 10 0 Area B - Roof; ng 9JUl92 22JUl92
30050 10 10 0 Area C - Roofing 20AUG92 2SEP92
40050 10 10 0 Area D - Roofi ng 9JUl92 22JUl92
50050 10 10 0 Area E -Roofing 20AUG92 2SEP92
S tll i rs
lO010 5 5 0 Area A . Temporary AccesS Stairs 5KA Y92 1 lKAY92
20120 10 10 0 Area B . Erect Stairs 16JUl92 29JUl92
30080 10 10 0 Area C . Erect Stairs 27AUG92 10SEP92
40120 10 10 0 Area D . Erect Stairs '6JUl92 29JUl92
43050 15 15 0 Area 0 . 2nd f I . ~e2Z Handrails 6AUG92 26AUG92
43060 10 10 0 Area 0 . 1st Fl . Interior Stairs 6AUG92 19AUG92
50080 10 10 0 Area E . Ere<t Stairs 27AUGn 10SEP92
53050 15 15 0 Area E . 2nd F I . ~ezz Handrails leSEPn &x:192
53060 '0 10 0 Area E . 1st Fl . Interior Stairs 1eSEP92 1OC192
Ele-vetors
10100 15 l5 0 Aree A . Elevators - Rough-in 9JUL92 29JUL92
10110 5 5 0 Aree A - Elevators - Car & Platfonl 30JUln 5AUG'92
10120 5 5 0 Area A - Elevators . Doors & Frames 6AUG92 12AUG'92
10130 20 20 0 Area A . Elevators - Construct Cabs & T ri m- out 13AUG92 lOSEP92
Slab Ent>eds
11000 15 '5 0 Area A . 1st Fl . ~/E/P/S Slab Embeds 12AAY92 2JUN92
l2000 20 20 0 Area A . 2nd Fl . M/E/P/S Slab Embeds 12AAY92 9JUI\92
21000 10 lO 0 Area B . \stFl - ~/E/P/S Slab Embeds 17JUII92 30JU~92
22000 15 15 0 Area B - 2nd Fl M/E/P/S Slab Embeds '7 JUfl92 8JUl92
3'000 10 '0 0 Area C . l5tFl . M/E/P/S Slab Embeds 30JUl92 12AUG92
32000 15 '5 0 Area C . 2nd Fl . M/E/P/S Slab E~ 22JUl92 l1AUG'92
41000 15 '5 0 Area 0 . l5tFl . M/E/P/S Slab Embeds 17JU~92 8JUl92
42000 20 20 0 Area 0 . 2nd Fl . M/E/P/S Slab Errbeds 17 JUfl92 l5JUl92
5 1O00 15 '5 0 Area E . 1st Fl - M/E/P/S Slab Embeds 30JUl92 191;UG92
52000 20 20 0 Ar ea E - 2nd F I - M/E/P/S Slab Embeds 30JUL92 26AUG92
Slabs
10030 5 5 0 Area A Roof . Topping 1~Y92 26?'.AY92
"0'0 lO '0 0 Area A . 1st Fl . FlR/P /C Slab 3JUNn '6JUI\92
'2010 10 10 0 Area A . 2nd F I . F/R/P/C Slab l7JUN92 30JUII92
20020 5 5 0 Area 8 . Roof Topping 24JUII92 30JUI<I92
21010 lO 10 0 Area B - 1st FI . F/R/P/C Slab 1 JUl92 '5JUL92
~~- --... ....... ......... ~.........-..._...-.... ....-..... -.... -....... -..... -.............- ....-.....- -..... -.... ...-....... ...... -.. ............ ............... -....--... --.... ....... --.. ..... -.. --_..-.. -" -- ............. -.... -.
Konroe County, Florida
PRlKAVERA P~J~CT PLA~~ER
Konroe County Cetenti~ f&cility
RE~l CATE \90EC91 RUW WOo 50
16:28
SCH~D REPORT. lIne skip by activity code
Konroe COlY'Ity Detention F&Cility
START CAIE 1AUG91 Flk ~AIE 1J
CAIA DATE \e~0V91 P~GE
...-..-.. .....--.. .--.. -...-.. - -..- -....--..---- ......... - - - -.................... -.......... ..... --..... ....... -..... --....... -..- .. .. .. . -.. ..... .. - . - . - .. . ..............- -..Oo-..--..
ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 DUR CUR X START fllllSH
.. -..- --....-........... _......- -..................-....... ...... ...... -.. ........... - - -................. -.... -- ................ ... - .. - .. .. .. - ... .. .. .. .. . .,. .. - - - . .. . ... ..
Slabs
220\0 10 \0 0 Mea B . 2nd F I F/R/P/C Slab 16JUL92 29JUL92
22200 10 10 0 Area B . 2nd Fl . F/R/P/C Piers & Supports 30JUL92 12AUG92
22300 10 10 0 Mea B . 2nd Fl . Insulation Board & Slab ~ C\{f 16OCT92 290<:192
30020 5 5 0 Mea C . Roof Topping 6AUG92 12AUG92
31010 10 10 0 Area C . 1st Fl . F/R/P/C Slab 13AUG92 26AUG92
320\0 10 \0 0 Area C . 2nd Fl - F/R/P/C Slab 3SEP92 17sEP92
40020 5 5 0 Area 0 Roof Topping 24 JUJ.l92 30JUW92
4\010 10 10 0 Mea D 1st Fl - form & R~r for Slab 17JUII92 30JUW92
41020 10 10 0 Area 0 . 1st PI . Pour/Cure Slab 9JUL92 22JUL92
42010 10 10 0 Aree 0 . 2nd Fl - form & Rebar for Slab 17 JUII92 30JUk'92
42020 10 10 0 Area 0 . 2nd Fl . Pour/Cur~ Slab 23JUL92 5AUG92
42040 5 5 0 1>.ree 0 2rd fl . Pour Eq'J;p pads '3AUG92 19AUC;92
50020 5 5 0 Area E Roof Topping 6AUG92 12AUG92
510'0 10 10 0 Area E . 1st Fl . Form & Rebar for Slab 30JUL92 , ZAUG92
51020 10 10 0 Area E . 1st Fl . Pour/Cure Slab 20AUG92 2SEP92
52010 10 10 0 Area E . 2nd fl . Form & R~bar for Slab 30JUL92 12AUG92
52020 10 10 0 Area E . 2nd fl pour/Cure Slllb 3SEP92 17SEP92
52040 5 5 0 1>.rea E . 2nd Fl . Pour Equ; p pads 25SEP92 lOCT92
Masoory
11020 5 5 0 Area A . 1st Fl . layout Part/Set Fr~~s/Vnd ~al 17JUk'92 23JUH92
11040 15 15 0 1>.rea A 1st fl . Masoory ; Bathrooms 16JUL92 5AUG92
"050 35 35 0 1>.rea A . 1st fl Bathroom & Shower Tile 6AUG92 24SEP92
11070 20 20 0 1>.rea A . 1st Fl - Masonry. Offices & Dorm Areas 24 JUII92 22JUL92
'2020 5 5 0 Area A . 2nd F l . layout Partitions/Set rr&rr~s/W 1JUL92 8JUL92
12050 15 15 0 Area A 2rd Fl . Masonry 9JUL92 X'JUL92
'2210 '5 15 0 Area A - 2nd Fl . Ceramic Ti Ie 90C 192 ~T9Z
20100 10 10 0 1>.rea B . Masoory . Stairs 17JUII92 30JUN92
201'0 10 10 0 A rea B . Cure Kasoory . Stairs 1 JUl92 15JUL 92
2'020 5 5 0 1>.rea B . 1stH layout Part/Set F r a.:nes/\.Ind ....a l 16JUL92 22JUL92
21040 '0 '0 0 Area B . 1st Fl . Masoory . BR 6AUG9.Z 19AUG92
21050 10 10 0 Area B . 1st Fl . Ceramic Tile. BR 20AUG92 2SEP92
21070 20 20 0 Area B . 1st Fl . Masoory 23JUL 92 '9AUG92
22020 5 5 0 .'.rea B . 2nd F 1 . Lay-out Part/Set Door frarres/W 30JUL92 5AUG92
22040 10 10 0 Area 8 2nd Fl . Masonry. 8R 20AUG92 2SEP92
22050 15 1S 0 Area B - 2nd Fl Masoory Support Systern6 R~J9h. 6AUG92 26AUG92
22060 15 15 0 Area B . 2nd F 1 . Masonry 6AUG92 26AUG92
2221)() 10 '0 0 Area 8 . 2nd Fl . Complete E~terior Masonry 1SSEP92 10C192
30060 '0 10 0 Aree C - Masonry. Stairs 30JUL92 , 2.A.UG92
30070 10 '0 0 Area C . Cure Masonry. Stairs BAUG92 26AUG92
31020 5 5 0 Area C . 1st Fl lay-out Part/Set Dr fr0IT>2s/W 27AUG92 2SEP92
31040 '5 '5 0 Area C . 1st Fl . Masonry 3SEP92 24SEP92
32020 5 5 0 Area C 2nd Fl Layout Part/Set Frames/\.Ind \.Ial 'SSEP92 24SEP92
32040 15 'S 0 Are a C 2nd Fl - ~asonry 25SEP92 15OC192
1'I0000roe COU"Ity, Florida
............ ........ ....... ......................................... ........................ .................... ...- -- ..........-........- ................. ........-......... ............... .....-....... ......................-.......... ...................
Monroe County Detention facility
RT DAlE '9';)EC91 RUII NO. 50
'6:28
~~~tD REPORT. line SKip by actiyity code
PRI~'VERA PROJECT PLA~NER
Monroe COU"Ity Detention facility
SlART DATE lAUG91 fIN DATE 1JL
DATA DATE '~0V91 PAGE I/O. 5
........ ....... .. ....... .....-................. ..............................................-.................................................... --............- .................- ............--- ................. ...
ACTIVITY
ID
OR I G REM
OUR OUR
Masonry
40100 '0
40nO '0
41030 5
41050 15
41070 '0
1,2030 5
1,30'0 '0
43020 25
50060 '0
50070 10
5 \030 5
5'040 '5
5'050 '5
51070 10
52030 5
53010 '0
53020 25
Drywall
12030 25
'2200 '5
Spray-on Insulation
12070 '0
'2080 5
22080 '0
22090 5
32060 5
32070 5
43070 10
53070 '0
Utility Rough-in
'0020 5
'0040 5
'0060 10
"030 15
"060 20
'2040 25
12060 15
20010 5
20030 5
20040 '0
21030 '0
2'060 20
22030 10
x
ACTIVITY DESCRIPTION
SCHEDULED
START fiNISH
... ..-.. .--........--- .............--......................................................-....................- ......-..--- ....-....-.... -------.. ....--.......... ...-
'0
10
5
15
'0
5
10
25
'0
'0
5
'5
15
'0
5
'0
25
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
25
15
o
o
'0
5
10
5
5
5
'0
'0
o
o
o
o
o
o
o
o
5
5
'0
15
20
25
15
5
5
10
10
20
10
o
o
o
o
o
o
o
o
o
o
o
o
o
Area D . Masonry. Stairs
Area D . Cure Masonry. Stairs
Area D - 1st fl . layout Part/Set frames~nd ~al
Area D . 1st Fl - Masonry. 1st level walls
Area D - 1st Fl - Masonry. BR
Area D - 2nd fl - layout Part/Set rr&mes~nd ~al
Area D - 2nd Fl . ~asonry - 2nd level
Area D - 1st fl - High Bay ~asonry ~alls
Area E - Masonry. Stairs
Area E - Cure ~asonry . Stairs
Area E - 1st Fl - layout Part/Set frames/Vnd Val
Area E - 1st fl . Masonry Support Systems R/I
Area E . 1st Fl - Masonry. 1st level walls
Area E . 1st Fl . Masonry. BR
Area E - 2nd Fl . layout Part/Set Fr&mes~nd ~al
Area E . 2nd fl ~as6nry - 2nd leyel
Area E . 1st Fl - High Bay Masonry ~alls
Area A 2nd fl - Drywall fr~~ing
Area A . 2nd fl . Drywall/Tape/Plaster ~alls
Area A - 2nd Fl . Spray-on Insulation . Pr~
Area A - 2nd Fl - Spray-on Insulation. Spray
Area B . 2nd fl . Spray-on Insulation . Pr~
Area B . 2nd Fl . Spray-on Insulation
Area C - 2nd Fl . Spray-on Insulation Pr~
Area C . 2nd fl . Spray-on Insulation. Spray
Area D . 2nd Fl . Spray-on Insulation
Area E - 2nd Fl Spray-on Insulation
Area A . Roof. Penetrations & Roof Accessories
Area A - Roof . Curbs
Area A - Roof Roof Drainage
Area A . 1st Fl . Plumbing R/I . Bathrooms
Area A . 1st fl Masonry R/l Support (M/E/P/S)
Area A 2nd fl . Masonry R/I Support (M/E/P/S)
Area A . 2nd fl Ceiling Anchors & Hangars
Area B . Roof. PeDelrations & Roof Accessories
Area B - Roof Curbs
Area B - Roof Drainage
Area B . 1st fl - Plumbing Rough-in. BR
Area B . 1st Fl . Masonry Support, Systems R/I
Area B 2nd fl - Plumbing Rough-in. BR
17JUN92
1JUl92
23JUL92
30JUl92
20AUG92
6AUG92
3SEP92
bAUG92
30JUl92
13AUG92
3SEP92
" SEP92
11 SEP92
2SSEP92
1aSEP92
9OCl92
,aSEP92
30JUN92
'SJUL92
29JUl92
19AUG92
2SEP92
12AUG92
17SEP92
'OSEP92
1 2AUG92
26AUCi92
'OSEPn
1OCT92
1OCT92
80C T n
24SEP92
22OCT92
22OCT92
9JUl92 12AUG92
,aSEP92 8OC192
30JULn
13 AUen
bAUG92
27AUG92
9OCl92
160CTn
2OCT92
61/0V92
'2XAY92
27J.I.AY92
19l'.AY92
24JUN92
21, JUI/92
9JUl92
9JUl92
17JUI/92
1JUL92
24JUN92
23JUL92
23JUL92
6AUG92
12AUG92
19AUGn
19AUG92
2SEP92
1SOCl92
22OCl92
1SOCT92
19N0V92
1t'XAY92
2JUN92
2JUN92
1SJUl92
22JUL92
, 2AUG92
29JUl92
23JUI/92
8JUL92
8JUL92
SAUG92
19AUG92
'9Aue92
. ............... ..................... -.... -- -........... - -........ -...-...... -...................... -............... -.................... -......- - ........ -..- .............. -...-.......... ...-....... ................ ............... ............-
lI-::.nroe C"-S'lty, F lor Ida PRlKA\~RA PROJECT PLA~~ER Xonr~ County Cetent~~ Facility
REPORT DAlE 19DEC91 RUN NO. SO Xonroe County Detention Facility START DATE lAUG91 fill DATE 1~
16:28
SCHEC R[PORT - line skip by activity code DATA DATE 1S1iOV91 P.L:;C t
-.. .... . ...........- . - ..... - ..... ... .. - -.. ......... ..--...-....... ................... ........-.......... -... ......-.. ..............-. ..... .. .. . .. .. .. .. .. - .. . ... ... .. .................. ................. -,
ACTIYllY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 DUR DUR ~ START FINISK
.......... .. .. .. ... .- .. . ... .. ... .. ... ... - .. ............................. -..-... ....... .......-...... ............................. _........... .. ... .. - ... .. .. . ... ... .. .. .. .. - ... - .. .. ... -.. .. .. ................ - -
Utility Rough-In
30010 5 5 0 Area C . Roof - Penetration & Roof Accessor i es 30JUL92 5AUG92
30030 5 5 0 Area C Roof Curbs 13AUG92 19AUG92
30040 10 10 0 Area C . Roof Drainage 6AUG92 19AUG92
31030 15 15 0 "rea C . 1st fl f<(asonry Support - Systems R/1 3SEP92 24SEP92
31070 15 15 0 Area C - 1st fl Plumbing Rough-in; BR 3SEP92 24SEP92
32030 15 15 0 Area C - 2rd F l f<(asonry Support. Systems R/1 25SEP92 15OC192
32050 10 10 0 Area C - 2nd F l Ceiling Anchors & Hangers 25SEP92 80C T 92
32100 10 10 0 "rea C 2rd F l Plumbing Rough-in; BR 2SSEP92 80C T 92
40010 5 5 0 /..rea o - Roof - Penetrations & Roof Accessories 17JUil92 23JW.92
40030 5 5 0 "rea D - Roof Curbs 1 JUL92 8JUL92
40040 10 10 0 Mea D Roof Drainage 24JUl/92 8JUL92
41040 15 15 0 Area D . 1st Fl - f<(asonry Support Systems R/I 30JUL92 19AUG92
4 ~ 060 ~O ~O 0 Area D - 1st Fl . Plumbing Rough, in . Br 30JUL92 12).UG92
43000 10 10 0 Area D 2rd Fl - Masonry Support Systems R/I 3SEP92 17SEP92
43030 10 10 0 Area 0 . 2rd Fl - CeilingjPl~ Hangers & Sprts 18SEP92 1 OCT 92
50010 5 5 D Area E Roof . Penetrations & Roof Accessories 30JUL92 SAUG92
50030 5 5 0 Area E Roof Curbs 13AUG92 19AUG92
50040 ~O 10 0 Area E . Roof Drainage UUG92 19AUG92
51060 10 10 0 Area E - 1st Fl . Plumbing Rough-in. Br 11 SEP92 24SEP92
53000 10 10 0 Area E . 2rd Fl . ~asonry Support Syst~ R/I 90C T 92 22OCT92
53030 10 10 0 Area E . 2rd Fl . Ceiling/Plenum Hangers & Sprts 23OCT92 5~OV92
Bulk Installation of Ut i lit i es
11080 25 25 0 Area " . 1st Fl - KYAC Ductwork Bulk Instl 23JUL 92 26AUG92
11100 25 25 0 Area " . 1st Fl . HYAC Piping Bulk Instl 23JUL 92 26AUG92
11120 25 25 0 Area A . 1st Fl . Plumbing Bulk Instl 23JUL 92 26AUG92
11 140 25 25 0 Area A - 1st Fl - P~r/Lt9 Conduit Bulk Inst 23JUL92 26AU~2
11160 25 25 0 Area A 'st Fl seclComm Conduit Bulk Install 23JUL92 26AUG92
"'80 25 25 0 Area A - 1st Fl . Fire Protection Bulk lnstl 23JUL92 26AUG92
12090 20 20 0 Area A - 2nd F l KYAC Ductwork Bulk Instl 20AUG92 ~ 7SEP92
12100 15 15 0 Area " 2rd F l KYAC Piping Bulk Instl 2CAUG92 ~OSEP92
~2"0 15 15 0 Area A - 2rd Fl - Plumbing Bulk Instl 20AUG92 10SEP92
12120 15 15 0 Area A . 2rd Fl . P~r/Lts Conduit Bulk Instl 20AUG92 10SEP92
12130 15 '5 0 Area A - 2rd F l . SecurityjComm Conduit Bulk Ins 20AUG92 10SEP92
12'40 15 15 0 Area " . 2rd Fl - Fire Protection Bulk Instl 2C,t..UG92 10SEPn
2W80 15 15 0 Area B . 1st Fl KYAC Duct~rk . Bulk Install 20AUG92 10SEP92
2'1090 5 5 0 "rea B - 1st Fl - KVAC piping - Sulk Install 2CAUG92 26AUG92
21100 10 10 0 Area B . 1st Fl - Pluming. Bulk Install 20AUG92 2SEP92
2~"O 15 15 0 Area B - ht Fl Pwr/Ltg Conduit. Bulk Install 20AUC92 10SEP92
21120 10 ~O 0 Area B . 1st fl . Sec/Comm Conduit - Sulk Instal 20AUG92 2SEP92
21130 10 ~O 0 Area B - 1st Fl - fire Protection. Bulk Install 20AUG92 2SEP92
22100 10 ~O 0 Area B - 2rd Fl . HYAC Ductwork - Bulk Install 3SEP92 17SEP92
221~0 15 15 0 Area B - 2rd F l HYAC piping. Bulk Install 3SEP92 24SEP92
22~20 10 10 0 Area B - 2rd Fl . Pluming. Sulk Installation 3SEP92 ~ 7SEP92
......... .......... .........-.... ......... ....- ....-... --.. .......-.. ........ ....-.. ......--... ......-......- ". "..-..-........ ........ .....................- ..........-...... ......... ...-......... ..................... .........
Xonroe COV"lty. Florida
PRIKAYERA PROJECT PLA~WER
Monroe County Detention facility
U DATE 19DE~1 RUIl NO. SO
16:28
..rlED REPORT - l\~ s~ip by activity code
Monroe COV"lty Detention facility
START DATE 1AUG91 fIN CATE 1J
DATA DATE 18H0V91 PAGE ijO.
.. .. .. ... .. -.....-. .. ... .... ........ . . . - ... ..... ... ..... . ...-.. ..........-....... ...... .....-.. ........................... ...... ...... .............. ............... ........... ... .. - .. - .. .. .. .. .. . .. .. .. ..... -
ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 OUR OUR 1 START FINISH
.. ... . . .. .... ...... .. ...... ...... ........-........ .................. ............ .................-......... - -.. _..................- .. .. ... .. .. . .. ............. . ... . ... .. .. ... . ... .. .. .. ... ..
Bulk Installation of Utilities
22130 15 15 0 Area B . 2rd Fl - Pwr/Ltg Conduit - Bulk Install 3SEP92 24SEP92
22140 10 10 0 Area B - 2rd f I . Sec/C~~ Conduit - Bulk Instal 3SEP92 17SEP92
22150 10 10 0 Area B - 2rd F I . Fire Prot~tlon - Bulk Install 3SEP92 17SEP92
22310 15 15 0 Area B . 2rd Fl - Ancilllary Pipe 16OCT92 5H0V92
31050 15 15 0 Area C . 1st Fl - HVAC Ductwork Bulk Install 25SEP92 15OCT92
31060 5 5 0 Area C - 1st Fl . HVAC Piping' Bulk Install 2SSEP92 1OCT92
31080 15 15 0 Area C . 1st Fl - Plumbing' Bulk Install 25SEP92 15OCT92
31090 20 20 0 Area C . 1st Fl - Pwr/Ltg Conduit. Bulk Install 25SEP92 22OCT92
3 I 100 20 20 0 Area C - 1st Fl . S~/Comm Conduit - Bulk Instal 25SEP92 22OCT92
31110 15 15 0 Area C - 1st Fl . Fire Prot~tlon . Bulk Install 2SSEP92 15OCT92
32080 15 15 0 Area C . 2rd F I - HVAC Ductwork. Bulk Install 23OCT92 12H0V92
32090 10 10 0 Area C - 2rd Fl . HVAC Piping' Bulk Install 230CT92 5 HO,;,92
32110 10 10 0 Area C . 2rd F I . Plumbing' Bulk Install 230CT92 5 NO'>'92
32120 15 15 0 Area C . 2rd F I . Pwr/Ltg Conduit. Bulk Install 23-0CT 92 1210/0'0'92
32130 10 '0 0 Area C . 2rd F I . s~/Comm Conduit. Bulk Instal 230C T 92 5N0V92
32140 10 10 0 Area C . 2rd F I . Fire Protection' Bulk Install 23-0CT92 5H0V92
43100 15 15 0 Area 0 . 1st Fl HU Side A . vert chase uti l6OCT92 51<10V92
43110 15 15 0 ,Area D . 1st Fl - HU Side B . vert chase utI 6110'0'92 30N0V92
43120 15 15 0 Area D . 2rd fl . HU Side A - horlz chase utl 6NOV92 30H0V92
43130 15 15 0 Area D . 2rd Fl . HU 1 Side B . horiz chase uti lDEC92 21DE~2
43200 15 15 0 Area D . 1st Fl . HU 2 Side C - vert chase uti 16OCT92 5N0V92
43210 15 15 0 Area D . 1st Fl . HU 2 Side D - vert chase utI 6IIOV92 301ol0V92
43220 15 15 0 .&.r ea D . 2nd Fl. HU 2 Side C horiz chase uti 6II0V9 2 30H0V92
43230 15 15 0 Area D . 2rd Fl - HU 2 Side D - horiz chase utI 1DEC92 21DEC92
43300 30 30 0 Area D . 2nd Fl . Mechanical Room Utilities l6OC192 301olCV92
43330 20 20 0 Area D - Dayroom/Office Utilities 16OC192 , 2I/C".'92
53100 15 '5 0 Area E - 1st fl HU 3 Side E . vert chase utI 201<10\'92 14-DEC92
53110 15 15 0 Area E . 1st fl . HU 3 Side F . vert chase uti 15DEC92 6JAN93
53120 15 15 0 Area E . 2nd fl - HU 3 Side E . horiz chase uti 15DEC92 6JAN93
53130 15 15 0 Area E - 2nd Fl . HU 3 Side F horiz chase utl 7JAN93 27JA~93
53200 15 15 0 Area E - 1st Fl - HU 4 Side G vert chase uti 201/0V92 14DE~2
53210 15 15 0 Area E - 1st Fl - HU 4 Side K - vert chase utI 1 5DE C92 6JAII93
53220 15 15 0 Area E 2nd Fl . HU 4 Side G horiz chase utI 1SDEC92 6JAII93
53230 15 IS 0 Area E - 2nd fl - HU 4 Side H horiz chase uti 7JAN93 27 Jll/93
53300 30 30 0 Area E . 2nd Fl . Mechanical Room Utilities 20kOV92 6JAI/93
53330 20 20 0 Area E . Dayroom/Office Util 201/0V92 21DEC92
Ceiling Framing
11200 5 5 0 Area A . 1st fl - Ceiling framing in 1.1000 27AUG92 2SET'92
11210 5 5 0 Area A - 1st Fl - Ce i ling Framing in A1029 3SEP92 10SEP92
11220 5 5 0 Area A . 1st Fl - Ceiling Framing in 1.1039 11 SEP92 17SEP92
1 , 230 5 5 0 Area A . 1st fl . Ceiling Framing in A10i,9 18SEP92 24SEP92
12150 IS 15 0 Area A - 2nd f I Cei I ing Framing 18SEP92 8OCT92
21140 10 10 0 Area B . 1st fl . Ce i ling Framing 11 SEP92 24SEP92
.......... .......... ................ -......... -. --...-..... ......... ...... -.......... ..... -...... ........ ....--.........-....... ..... ......-.... .......................... ....... ........ ..............................................
Moor~ CO<.J"\ty, Florida
PRll'JYU:.A PROJECT PLAIiIlER
HOf'Ir~ COU1ty Cetentlon Fad lit)'
REPORT DATE 190EC91 RUN I/O. 50
16:28
SCKEO REPORT' line sKip by activity code
Mooroe County Detentton Facility
START DATE 1AUG91 FIN DATE 1J
DATA DATE 1Sk0V91 PAGE
........ .......... .-... ..-.. . . - . .. .. .. .. .. .. - .. . .. .. - .. .. .. .. .. .. .. .... - .. .. .... .. .. .. ... .. ... .. .. .. ... .. . - .. .. . .. .. . .. .. .. ... .. .. . .. .. .. .. ... .................... ................. ............... .................
ACT IVI T'l' ORIG REM ACTIVITY DESCRIPTION SCHEDULED
ID OUR CUR X START FINISH
.......... .. .. .... .. .. .. .. .. .. .. .. -... .. .."' ....-...... ............................ .......... ........ ..........-...... ........ -.-......- ................. -..... .. .. ... .. .. .... .. ... .. ........ ..........-.... -
Cei I ing FrblTiing
220ro 10 10 0 Area 8 . 2nd Ft Ceiling Anchors & Hangers 6AUG92 19AUG92
22160 5 5 0 Area 8 . 2nd Ft . Ceiling Framing 2SSEP92 1OCT92
31130 5 5 0 Area C . 1st Fl . Ceiling Framing . Start 2.3OC192 290CT92
3111,0 5 5 0 Area C . 1st Fl . Cei I ing Framing . Coop I ete 300cT92 SNOV92
32160 10 10 0 Area C . 2nd Fl . Ceili~ Framing 13N0V92 30NOV92
43340 10 10 0 Area D . Ceilin9 Framing 13NOV92 30NOV92
533-40 10 10 0 Area E . Ceilin9 Frcming 220EC92 6JAN93
System DrO?S I T es t i ng I PUf'lCh-out
"240 10 10 0 Area A . 1st Fl . Syst~ Drops . Start 3SEP92 17SEP92
11250 5 5 0 Area A - 1st Fl . Syst~ Crops . Complete 25SEP92 1OCT92
n260 5 5 0 Area A . 1st fl . Test Utility Piping Systems 2OC192 80C T 92
11270 5 5 0 1--rea A. . 1st Fl . Punch-out Above Ceiling ~ork YOC T 92 15OCT92
12160 15 15 0 1--rea A . 2nd Fl - Utility System Drops' Start 1BSEP92 8OCT92
12170 5 5 0 Area A . 2nd FI . Utility System Drops - Cpl 90<: T 92 1SOCT92
12180 5 5 0 Area A 2nd Fl . Test Utility Piping Systems 16O<:T92 22OCT92
12190 5 5 0 Area A 2nd Fl Punch-out Above Ceiling Vork 230C 192 29O<:T92
21150 10 10 0 Area 8 . 1st Fl. System Crops . Start 11 SEP92 24SEP92
21160 5 5 0 Area 8 . 1st Fl . Systems Drops . Complete 25SEP92 1OCT92
21170 5 5 0 '!'rea 8 . 1st fl Sy5 t e.ClS T es t 20c 1 92 8OCT92
21180 5 5 0 ,!.rea 8 - 1st Fl Punch-out 90C T 92 lSOCT92
22170 5 5 0 Area 8 . 2nd Fl Systems Drops 2OCT92 &xT 92
22~00 10 10 0 Area 8 . 2nd Fl . Systems Test ~OV92 191WV92
22410 5 5 0 A~ea 8 . 2nd F I . Punch- out 20NOV92 30NO\'92
31150 5 5 0 A~ea C . 1st Fl . Syst~ Crops' Start 300cT92 5N0V92
31160 5 5 0 ,!.rea C . 1st Fl - Systems Drops' Complete ~Ov92 12NOV92
31170 5 5 0 Aree C . 1st fl . Sys t e;1IS T es t 13 II ov92 19110\'92
31180 5 5 0 Area C . 1st Fl Sys t ~ PUf'lCh - out 20110\'92 30N0V92
32170 5 5 0 Area C 2nd FI System Crops . Start 13NOV92 191/0V92
32180 5 5 0 Area C 2nd F I . Syst~ Crops - Complete lDEC92 7tlEC92
32190 5 5 0 Area C 2nd FI . System test 8DEC92 14OEc92
32200 5 5 0 ,!.rea C 2nd F I . PiS'Ch-out 150EC92 210EC92
43310 5 5 0 ,!.;-ea D 2nd fl . Test Systems 22DEC92 29DEC92
43320 5 5 0 1--rea 0 2nd FI . P\.nCh - out 300E<:92 6JAN93
~3350 5 5 0 Area D . System Drops - both floors 1DEC92 7tlE c92
43360 5 5 0 ,l,rea 0 Systems Test. Dayrm/Off - both floors 8DEC92 1i.DEC92
43370 5 5 0 1rea D Punch'out - Oayrm/Off - both floors 150E<:92 21DE C92
53310 5 5 0 Area E - 2nd Fl . T es t S ys t ems 28JAli93 3FEB93
53320 5 5 0 Area E 2nd F I - Punch-out 4fES93 10fEB93
53350 5 5 0 Area E System Drops - both floors 7JAli93 13JAN93
53>60 5 5 0 .l.rea E Systems Test - Dayrm/Off . both floors 14.',1.).;93 20JA).;93
53370 5 5 0 .l.rea E Punch-out. Dayrm/Off - both floors 21JAN93 27JAW93
Ceilings
11280 20 20 0 Area A 1st Fl . Ceil;ng Board/Tape/Plaster 16OC192 121/0V92
...... ............... .-.. ...-....... -.. ..--........-........ ...... ................. ............. ........... -....... .......... ....-............................ -.... ..-................... - -.... .......... ....... ...........-.... .............
Konr~ County, Florida
P~I~'VERA PROJECT PLA~NER
~onroe County DetentIon Facilit
~T DATE 19OEC91
16:28
ww~ED REPORT' line
RUN NO. SO
~onroe County Detention Focility
START DATE
1 AUG91 FIN DATE
skip by activity code
DATA DATE
18N0V91 PAGE NO.
.....-... ..........- ... .. .. ....- - ................. .... -.. ....... ....-... ...... ........ ............ .........--......... ---......... .......... ...... .. .. .. .. - .. ... . ... .. - - . ... . .............. ..................
ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 DUR OUR X START FINISH
.....-- ........-- .....-......-.... .... -......-.. ..........................--... ...............--. ......-.... ....................... .. .. .. .. ... . .. - .. .. . .. .. - ..- .. .. .. ... ... - .. ... .. .. .. .. .. -... -
Finishes
434S0 15 15 0 Area 0 . Casework, both floors I.FEB93 24FE893
43490 15 15 0 Area 0 . Clazing . both floors 4fEB93 24fEB93
43500 15 15 0 Area 0 . Door Hardware' both floors 4fEB93 24fEB93
43510 15 15 0 Area 0 - Acoustical Ceiling - both floors 4fEB93 21.fEB93
43520 10 10 0 Area 0 . Floor prep - both floors I.FEB93 17FEB93
43530 10 10 0 Area 0 - Floor covering. both floors 25FEB93 10HAR93
53040 15 15 0 Area E . 1st Fl . Cell Furniture 20092 22OCT92
53045 10 10 0 Area E - 2nd Fl . Cell Furniture 23OCT92 5 N0V92
53400 20 20 0 Area E . Cell Doors & Door Fromes . both Floors 201<OV92 21DEC92
5310 10 10 10 0 Area E - Crout Cell Door Fr&mes - both floors 22'DEcn 6JAN93
534-40 5 5 0 Area E - Doors & Crilles . both floors i8FEB93 24FE893
534S0 15 15 0 Area E . Cas~rk - both floors 1iKAR93 3 i I'J..R93
5:>490 15 15 0 Area E - Glazing' both floors i iKAR93 3iKAR93
53500 15 15 0 Area E - Door Har~'are . both floors 1iKAR93 31~AR93
53510 15 15 0 Mea E - Acoustical Ceiling' both floors 1 iKAR93 31/'IAR93
53520 10 10 0 Area E . Floor prep' both floors 11/'IAR93 24KAR93
53530 10 10 0 Area E - Floor covering. both floors lAPR93 i4APR93
Et~trical Equipment
20350 15 15 0 Area B . Switchgear' Ce-ner ate P,O. 13JAN92 31.1.1.1192
20360 5 5 0 Area B - Switchgear. Selt{:t Vendor 3FEB92 7f[B92
20370 1 , 0 "'rea B . Switchgear. Issue PO iOFEB92 10FEB92
20:>80 70 70 0 Area B Switchgear . Fob & Delver 11FEB92 18XA,Y92
20400 15 15 0 "'rea B Emerll Ceo . Ger.erete P.O. 13JAN92 31JM/92
204 1 0 5 5 0 Area B . Emerg Cen - Sele<:t Yef"dor 3fE892 7FE892
20420 1 , 0 "'rea B . Emerg Cen . Issue PO 10FES92 10fEB92
20430 120 120 0 Mea B Emerg Ceo . Fab & Del her 1iFEB92 29JUL92
20450 15 15 0 Area B . UPS Systelll . Cenerate P.O. 13JAI/92 31JAN92
20460 5 5 0 Area B . UPS Syst~ . Se l e<: t Vendor 3FEB92 7FEB92
204 70 1 1 0 Area B UPS System . I ssue PO 10FEB92 10FEB92
2C4a0 145 145 0 Area B UPS Systefll . Fab & Del iver l1FEB92 25EP92
~echanical Equipment
20200 15 15 0 Area B . C\/T . Generate P.O. 13JAlI92 31JAN92
20210 5 5 0 "'rea B . M . Select Verdor 3FEB92 7FEB92
20220 1 1 0 Area B - M' Issue PO 10HS92 iOFEB92
20230 70 70 0 Area B . M . Fab & Deliver 1 jF[B92 i s,...J.. Y92
20250 15 15 0 "'rea B . Ch i II us - Generate P.O. i3JAN92 31JAI/92
20260 5 5 0 Area B . Chilters . Select Vendor 3FEB92 7fE892
20270 1 1 0 Area B Chilters . Issue PO 10fEB92 10FEB92
20280 110 110 0 Area B . Chilters - Feb & Del iver 1 iFE B92 1SJUL92
20300 15 15 0 Area B . AHU . Generate P.O. 13.1,1..1/92 3iJAI/92
20310 5 5 0 Area B . AHU . Select Verdor 3FEB92 7FEB92
20320 1 1 0 "'rea B . AHU . Issue PO 10FEB92 10FEB92
20330 80 80 0 Area B AHU - Fab & Deliver 1HEB92 2JUI<92
~O(\r~ COJ\ty, flor Ida
.. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. . .. .. .. .. .. .. .. ... ... - .. .. .. .. .. .. .. .. .. .. .. .. .. .- .. .. .. .. .. ... .. .. .. .. .. .. .. .. ... .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. ... . .. ... .. .. .. .. .. .. .. .. .. ... .. .. .. .. ... .. ..- .. .. .. .. .. .. .. .. .. .. .. .. .. .. ... .. .. .. .. .. .. .. .. .. .. .. ..
lliooroe CC>J1ty r.et~tion F&Cillty
PR 1 KI;':<J. PROJECT PLAl.'IIER
~onroe t~Jr,ty Cet~t'on Facility
RE~T D~lE '9DEC9' RUW NO. SO
16:28
SCHED RE~T . line s~ip by activity code
.. .... .... ...........
~ClIVITY
10
OOIG REM
DUll. DUR
....... ...........
K~hanical Equiprr~t
22m '0 '0
32300 '0 '0
32310 10 '0
>2320 '0 10
>2330 10 '0
32...'t.40 5 5
40500 '5 '5
405'0 5 5
40520 1 1
40530 40 40
5 os 00 15 '5
505'0 5 5
50520 1 1
50530 40 40
L a-.rd ry E q.Ji pnent
20500 '5 15
205'0 5 5
20520 5 5
20530 85 85
Kitchen Equi~t
30'00 25 25
30"0 5 5
3-0115 5 5
3-0'20 50 50
30130 '5 '5
30'40 35 35
30'50 150 '50
32'50 5 5
324S0 5 5
.. ..... --................ --....-........................................................---..............................
~ClIVITY DESCRIPlION
x
START DATE '~UG91 FIN D~lE 1J
DATA DATE '&10\'9' PAGl
SCHEDULED
STAAT fiNISH
...............-- .......................---.............-----................--....-----......-- --..----- ..................
o
o
o
o
o
o
o
o
o
o
o
o
o
o
Area 8 2rc ft - Erect CWT
Area C - 2~ Fl . Cooler Floors - Install
Area C . 2~ Ft - Cure Floors
Area C - 2rc Fl - Cooler Fr&ming
Area C - 2nd Fl . Cooler P8~ls - Install
Area C 2rc fl . Cooler Trim 'out
Area 0 . AK./S - Generate P.O.
Area 0 . ~~J's . Select Vendor
Area 0 . ~KJ'S - Issue PO
Area 0 . PU's - F&b & Deliver
Area E - AK;'s - Generate P.O.
Area E - A~J'S Select Vendor
Area E A;{J's' I ssue PO
Area E A~/S - Fab & Deliver
Set Equipment
22210 10 '0 0
22220 10 '0 0
22230 '0 '0 0
22240 '0 '0 0
22250 10 '0 0
22260 '0 '0 0
22270 10 '0 0
324-60 15'5 0
42050 5 5 0
52050 5 5 0
~e<hanical System Che<k-out & Balancing
71005 20 20 0
noos 20 20 0
o
o
o
o
Area 8 . l~Jndry Equip - Generate P.O.
Area 8 - L~Jndry Equip' Select Vendor
Area 8 - l:Jndry Equip' Issue PO
Area 8 . L~Jndry Equip - Fab & Deliver
o
o
o
o
o
o
o
o
o
Area C - ,C~che-n Equip' Generate P.O.
Area C . (;tch~ Equip - Staff Revi~
Area C - ('tchen Equip Award P.O.
Area C . ('tche-n Equip' Shop Drawings
Area C . ('tche-n Equip - AlE Revi~ & Approval
Area C . ('tch~ Equip - Fnl Coord wi others
Area C ('tche-n Equip - Fab & Deliver
Area C - 2~ Fl Install (;tche-n Hoods
Area C - 2~ Fl (itche-n Equiprr~t Trim-out
Area B
2-d F 1
fl
Fl
Fl
Fl
fl
Fl
fl
Fl
fl
Set CWT Equipment
Set Chiller Equipment
Set AHU Equipment
Set Switchgear
. Set Emergency Generator
Set UPS Syst~
. Set Laundry Equipment
- Set Kitchen Eq~i~nt
. Set AHU'S D1 and D2
- Set ~HU's . E1 and E2
Area 8 . 2~
Area 8 . 2-d
Area 8 . 2-d
Area 8 2~
Area 8 . ,--d
Area 8 - 2-d
Area C - 2-d
Area 0 . 2~
Area E
2.-d
/.rea A
Area 8
.~h System Tie-in & Initial HVAC T&8
.~h System Tie-in & Initial HV~C T&8
2O<:T92
'6OCT92
3O<X:192
BH0\l92
1DEC92
'5DEC92
13JA~92
3FEB92
'OFEB92
, HE892
nJA~92
3FEB92
10FE892
"FE892
13JAl<92
3FEB92
'OFEB92
HF EB92
13JAI<92
17FEB92
24FEB92
2.w.AR92
"l'.A Y92
2JU~92
2JL:N92
23OCT92
25l'.AR93
13Auc92
13AUC92
13AUc92
13AUG92
13AUG92
3SEP92
13AUG92
41<\AR93
20AUG92
2OC192
14JAH93
1HEB93
15OCT92
290CT92
12N0\l92
30N0\l92
'40EC92
21DEC92
31JAII92
7FEB92
'OFEB92
6APR92
31JM<92
7FES92
'OHB92
6APR92
31JA~92
7FEB92
'4FEB92
'5JUN92
14FEB92
21FES92
28FEB92
&J.A Y92
, JUN92
21 JUL92
5JA~93
29O<:T92
31 ".AR93
26Auc92
26AUG92
26,AuG92
26AUG92
26AUc92
17SEP92
26AUG92
24",AR93
26AUG92
BOCT92
'OFEB93
1 o 1<\AR 93
......................... ................. -.......... ........... ....... .......... ....... .-...... ................... ................-.... ....... ...-.......... ........ ............ --.... ......... -....... ................... ....... ..............
~onroe County, Florida
PRIK~VERA PROJECT PLA~~ER
~onroe County Detention F&cility
JRT DATE 190Ec91 RUN ~o. 50
16:28
~~"ED REPORT - line skip by activity code
~onroe County Detention Facility
START DATE 1 AUG91 FIN DATE 1JU,
DATA DATE 1&10V91 PAGE ~o. 9
........ -...... ... - . .. . .. - . -....-.--...... ...... .--..-...... ..... ..-..---................-....-.-.......-.. --.....- ... - - .. ... .. .. .... ............. ...-.......... ...-..-....- --,
ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDULED
10 DUR DUR X START FI~ISH
. ... . .... .. - . .. .. ....-........... ..... ........ ...- ....-.... ...--. .......-.....-..... .....-.......... - ....-..-... --..... . - ... .. - ... .. ... - .. ... - . .... .. ............ .. .. - .. - .. - . -...
Cei lings
12220 15 15 0 Area A . 2rd Fl - Drywall/Tape/Plaster Ceilings 300cT92 191<0',192
21200 15 15 0 Area 8 . 1st Fl Ceiling Board/Tape/Plaster 16OCT92 5H0V92
22"30 10 10 0 Area 8 . 2rd F I - Drywall/Tape/Plaster Ceilings 10Ee92 14DEe92
31 200 15 15 0 Area C . 1st Fl . Ceiling Board Tape & Plaster 10Ec92 21DEC92
32410 15 15 0 Area C . 2rd Fl . Ceilings 14JA~93 3FEB93
"3330 15 15 0 Area 0 . Dr~all/Tope/Plaster Ceilings - both fl 22DEC92 13JA~93
53380 15 15 0 Area E . Dr~all/Tape/Plaster Clgs - both floors 28JI>.N93 17FEB93
\li re Pulls
11300 10 10 0 Area A . 1st Fl . Wire Pulls 13~OV92 30110',192
122"0 10 10 0 Area A - Zrd Fl . Wire Pulls 20~0V92 7t>EC92
21220 15 15 0 Area 8 . 1st Fl \lire Pull 61<0V92 30N0V92
22"50 20 20 0 Area 8 - Zrd F I . IJ ire Pu II 150Ee92 13JA~93
31220 15 15 0 Area C . 1st Fl . \lire Pull 22DEc92 13JA~93
32400 15 15 0 Area C - 2rd Fl - IJire Pull 22DEe92 BJA~93
"3420 10 10 0 Area D - \lire Pull, start - both floors 300Ee92 13'JA~93
"3430 5 5. 0 Area D . \lire Pull - complete' both floors 14JAI<93 20JA~93
53420 10 '0 0 Area E - \lire Pull - start. both floors 4FEB93 17FEB93
53430 5 5 0 Area E . IJire Pull - complete' both floors 18FEB93 2"FEB93
Trim-out Utilities
',330 15 15 0 Area A - 1st Fl H/E/P/S Trim-out 15DEe92 6JA~93
1228-0 15 15 0 Area A - 2rd fl . H/E/P/S Trim-out 22DEc92 13JA~93
21260 15 15 0 Area 8 . 1st FI - H/E/P/S Trim-out 150EC92 6JAI/93
224-80 10 10 0 Area 8 . 2nd F I . H/E/P/S Trim-out 28JAI/93 10fEIl93
31260 10 10 0 Area C . 1st Fl H/E/P/S Trim-out 28JAI/93 10fEB93
32t.70 10 10 0 .&-rea C - 2rd Fl K/E/P/S Trim-out "KAR93 17HAR93
43470 15 15 0 Area 0 - ~/E/P/S trim-out - both floors 4FEB93 2"FEB93
534 70 15 15 0 Area E - H/E/P/S tri~-out . both floors 11KAR93 31KAR93
Painting
11310 10 10 0 Area A . 1st Fl . Pre? for Bulk Painting 13110V92 30~OV92
11320 10 '0 0 Area A . 1st Fl . Bulk Paint ing 10Ec92 140ECn
12250 10 10 0 Area A . 2rd Fl, Prep for Butk Painting 20~OV92 7DEC92
12260 '0 10 0 Area A . 2rd f I . Bulk Painting 8DEe92 21CEC92
21230 10 10 0 Area 8 - 1st Fl - painting Prep 6'-10V92 19NOV92
21240 10 10 0 Area B - 1stFl Bulk Painting 1DEe92 14DEC92
22L.60 10 10 0 Area 8 - 2rd Fl - Painting Prep 15DEC92 290EC92
22470 10 10 0 Area B - 2nd F I - Bull:. Painting 14JAI<93 27JAW93
31230 10 10 0 Area C - 1st fl . Painting Prep 22CEC92 6JA"'93
312"0 '0 10 0 Area C . 1stfl Bulk Painting 14JAN93 27JAII93
32430 '0 10 0 Area C . 2rd Fl - Paint Prep 14JAIo/93 27JAN93
32"40 10 10 0 Area C - 2nd f I - Bulk Painting 4FEB93 '7fEB93
"3450 10 10 0 Area 0 - Paint prep' both floors 220Ee92 6JA~93
4 3 L.6O 10 10 0 Area 0 . Bulk Paint. both floors 21JAII93 3FEB93
53450 10 10 0 Area E - Paint prep' both floors 28JAIo/93 10fEB93
. .. ... .. - ... . . .. ... .. ... . .. .. .. .- ... . - . .. - .. .. .. .. .. ... .. ... .. .. .. .. .. ... ... .. .. . . . .. .. .. .. .. .. ... .. .. .. .. .. .. .. . .. .. . . .. .. . .. . .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. .. - .. ... ... .. .. ... -.. .. .. .. .. . .. .. - .. .. .. .. .. . ... ... .. .. .. - .. .. .. .. .. .. ... .. ... ..
Konroe Covnty, Florida
REPORT DATE 19DEC91 RUN NO. SO
16:28
SCKED REPORT - line skip by &Ctivity code
ACTIVITY
10
Painting
53460
77020
77030
7701. 0
ri ni shes
11290
11340
11350
1 1 :>60
11370
12230
12270
12290
12300
12310
12320
21190
21210
21250
21270
21280
21290
221.20
22440
221.90
22500
22510
22520
31120
31\90
31210
31250
31270
31280
31290
321.20
32450
321.90
001.0
43045
1.3-400
1.34 1 0
1.31.40
OR1G ROC
DUR DUR
PRlKAVERA PROJECT PLAWWER
~onroe County Detention Facility
~onroe CO'JIty Detent Ion r~ci Ii t
START DAlE 1AUG91
fiN DATE
DATA DATE 1&~0V91
PAC ),
.. ...... ..............-.... .......................................................................................--.. ................ ..-...........-.
10
30
10
60
10
30
10
60
10
15
15
15
10
10
10
15
15
15
15
10
15
15
10
10
15
10
10
5
5
5
5
10
10
10
5
10
10
10
10
10
10
15
10
20
10
5
10
15
15
15
10
10
10
15
15
15
15
10
15
15
10
10
15
10
10
5
5
S
5
10
10
10
S
10
10
10
10
10
10
15
10
20
10
S
x
ACTIVITY DESCRIPTION
SCHEDULED
START FINISH
........................ ....-...................................................................................-......-... ................ ................
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
o
Area E . Bulk Paint - both floors
Painting' Interior Touch-up (start)
Painting. Interior Touch-up (compl)
Painting - Exterior Building
Area A . 1st Fl . Install Doors & Grills
Area A - 1st Fl - Casework
Area A - 1st Fl - Glazing
Area A - 1st Fl - Door Hardware
Area A . 1st Fl - Floor & ~all Coverl~s
Area A . 2nd Fl - Instl Doors & Grills
Area A - 2nd Fl . Cas~rk
Area A . 2nd Fl . Acoustical Tile
Area A - 2nd Fl - Door Hardware
Area A . 2nd Fl . Glazing
Area A - 2nd Fl - Floor & Uall Coverings
Area B 1st Fl Floor Prep
Area 8 . 1st Fl - Doors & Grilles
Area 8 - 1st Fl . Acoustical Tile
Area 8 . 1st Fl . Door Hardware
Area 8 1st FI - Glazing
Area B - 1st FI - Floor & ~allcoveri~s
Area B 2nd Fl - Floor Prep
Area 8 - 2nd FI . Doors & Grilles. Install
Area B - 2nd Fl - Door Hardware
Area 8 . 2nd fl . Glazing
Area B . 2nd Fl . Acoustical Tile
Area 8 - 2nd Fl - Floor & Uallcoverings
Area C - 1st FI . Cer~ic Tile
Area C 1st Fl - Floor Prep
Area C - 1st FI - Doors & Grilles
Area C 1st Fl - Acoustical Tile
Area C 1 st fl . Door Hardware
Area C . 1st Fl - Glazing
Area C 1st fl - Floor Covering
Area C 2nd fl - Install Doors & Grilles
Area C 2nd Fl - Se&mless Floors
Area C 2nd Fl - Other Flooring
Area 0 - 1st Fl . Cell Furniture
Area 0 - 2nd Fl Cell Furniture
Area 0 . Cel I Doors & ,Door Frames
Area 0 - Grout Cell Door Frames' both floors
Area 0 Doors & Grilles - both floors
25FEB93
1&'.AR93
13KAY93
SFE893
i31/0V92
1SDEC92
1SDEC92
iSDEe92
7JAI/93
20N0V92
22DEC92
22DEC92
22DEC92
22DEC92
14JAH93
16OCT92
6N0V92
15DEC92
15DEC92
1SDEC92
7JAI/93
10EC92
15DEC92
28JAH93
28;.1.1/93
28JAH93
11FE893
25sEP92
10EC92
22DEC92
28JAI/93
28JAI/93
28JAW93
i ifEB93
V.J"I<93
i8FEB93
l.,w.A.:93
20AUG92
"SEP92
160<:192
13N0Y92
14JAN93
1OHAR93
2aAPR93
26XAY93
29APR93
30N0V92
6JAI/93
6JAN93
6JAI/93
20JAN93
7DEC92
6JAI/93
13J"N93
13JAN93
13JAN93
3FEB93
290CT92
30N0V92
6JAI/93
2'9D E e92
29DEC92
27JAW93
11.OEC92
mE cn
3FEB93
3fEB93
3FEB93
17FEB93
8OCT92
iI.DEC92
6JAI/93
3FEB93
10FEB93
10FE893
24FEB93
27JAN93
3~'.6,R93
1 n-.AR93
10SEP92
24SEP92
12Nov92
30Nov92
20JAli93
i'<onr c-e C()U')t y. Fl or i da
........... -... ....-.......... - ..................... ......... -.... -..-............ "'..-.............. ........... -- ................".. ............... ............. -................................ --................... ...............-..- .........
Honroe County Detention f6citity
RT CA TE '9:lEC91 RUN NO. 50
'6:28
~_..cO REPORT - tiN! skip by activity code
PRl~~VERA PROJECT PLA~WER
Honroe County Detention facility
START DATE 'AUG91 fIN DATE 'JU_
DATA DATE '8N0V91 PAGE I/O. 13
..-................. ........-.....................-..............-........-...............................-...... ........---.. .................. ....-.......-- ..--.......... .....
ACTIVITY
10
Ol<JG REM
DUR DUR
x
....--...........- ....................---.........--.........................-..................--........ -....--..-- ........---.. .........--.... ............. ..."
.......... .......-- ........ ..---
ACTIVITY DESCRIPTION
Mechanical System Check-out & Balancing
73005 20 20 0 Area 0 - Mech Syste<:l lie-in & Initial HVAC aB
74005 20 20 0 Area C - I<<ech System Tie-in & Initial HVAC T&.8
75005 20 20 0 Area E - Hech System Tie-in & Initial KVAC T&8
75500 10 10 0 HVAC System - final Test & Balance
75600 '0 10 0 Sui lding 0 & H System - Verification I Checkout
no,o 10 10 0 Chlorinate & Flush Drinking \later Lines
Electrical I Security Oevice Verification
71020 '5 15 0 Area A - Point to Point Device Verification
720'0 '5 15 0 Area B - Point to Point Device Veri ficat ion
73010 15 '5 0 Area 0 - Point to Point Oevice Verification
74010 15 15 0 Area C - Point to Point Device Verification
750'0 '5 '5 0 Area E - Point to Foint Device Verification
Fire Protection System Fir~l Test
75 700 20 20 0
Se<urity System Operational Tests
7'010 5 5 0
7'015 5 5 0
7'025 15 15 0
720'5 '5 15 0
73015 15 '5 0
740'5 '5 15 0
75015 '5 15 0
Secur i ty Sys t e1TI
76000
76010
Fi I"\l! I PlXlCh
77050
Integrated Tests
10 '0 0
20 20 0
15 '5 0
Ownerl AE Demonstrations\
80000
5
5
o
Fire Protection System - Fi~al Testi~
Instl Security _System CompUter Equip; Ctl Room
load Security System Programs
Area A Security System Operational Tests
Area B Security System Operationat Tests
Area 0 Security System Operational Tests
Area C Security System Operational Tests
Area E - Security System Operational Tests
Security System
Se;::ur i ty Sys t e1TI
Integrated Test (start)
Integrated Test (c~l)
AlE Building C~t Punchout
Owner/AE D~nstrations & final ~alkthru
SCHEDULED
START fINISH
25FEB93
18.KAR93
1APR93
29APR93
BKAY93
29APR93
14JMI93
" F E B93
25FEB93
1&\AR93
1APR93
241'.AR93
14APR93
28APR93
12KAY93
26KAY93
1 2HA Y93
3fEB93
3KAR93
1i'XAR93
7APR93
21APR93
29APR93 26KAY93
1 HEB93
18FEB93
25FEB93
4KAR93
1&\AR93
8APR93
22APR93
17fEB93
24FEB93
1i'XAR93
24KAR93
7APR93
28APR93
12HAY93
BAA Y93 26/o(A Y93
27l'.AY93 24 JUt-I93
27l'.A Y93 17 JUN93
25 JUt-I93
lJUL93
'0
SECTION 00134
PROPOSAL FORM
Bid Package No. 34
Gypsum Board, Lath , Plaster
BID FROM:
BID TO : MONROE COUNTY PURCHASING DEPARTMENT
PUBLIC SERVICE BUILDING, CROSS WING,
ROOM 002, 510,0 COLLEGE ROAD, STOCK
ISLAND, KEY WEST, FLORIDA 33040
WENTWORTH PLASTERING CO. OF BOCA RATON, INC.
4044 N.E. 7 Avenue
Ft. Lauderdale, FL 33334-3098
The undersigned, having carefully examined the Work and Drawings,
Specifications, Proposal, and Addenda thereto and -other Contract
Documents for the construction of:
Bid package No. 34, Gypsum Board, Lath , Plaster
v
and having carefully examined the site where the Work is to be
performed, having become familiar with all local conditions
including labor ~ffecting the cost thereof, and having
familiarized himself with material availability, Federal, state,
an~ Local laws, ordinances, rules and regulations affecting
performance of the Work, does hereby propose to furnish all
labor, mechanics, superintendents, tools, material, equipment,
transportation services, engineering support, and all incidentals
necessary to perform and complete said Work and work incidental
hereto, in a workman-like manner, in conformance with said
Drawings, Specifications, and other Contract Documents including
Addenda issued thereto.
The undersigned further certifies that he has personally
inspected the actual location of where the Work is to be
,performed, together with the local sources of supply and that he
understands the conditions under which the Work is to be
performed. The successful bidder shall assume the risk of any
and all costs and do lays arising from tho oxiatollce of allY
subsurface or other latent physical condition which could be
reasonably anticipated by reference to documentary information
provided and made available', and from inspection and examination
of the site.
v
03/11/92
GYPSUM BOARDPROPOSA~ FORM (ADD. 8)
00134 - 1
PROPOSAL FORM
Lump Sum Base Bid
Note:
Items are 'furnish and install' where applicable,
as specified in the Scope of Work.
03/11/92
GYPSUM BOARD PROPOSAL FORM (ADD. 8)
1.
Mobilization
$15,000.00
$ 8,500.00
$ 8,500.00
$ 3,000.00
$40,000.00
$526,000.00
$ 80,000.00
$
n
\) ~:!~2~~~~':~o "
TOTAL BASE BID, (words) SIX HUNDRED EIGHTY ONE THOUSAND
-~ - - - - - - - - ---- - -- - - --- - - ---- - - -- - - -- --- - - - Of5: - -- -- - DOLLARS
.
2.
Bond
3.
Sales Tax
4.
Submittals
5.
Non-Load Bearing Wall Framing Systems
Lath and Plaster
6.
7.
Gypsum Board
8.
Miscellaneous Items (use if work items
cannot be categorized in items 1-7 above)
TOTAL BASE BID, Items 1-8, (figures)
00134 - 2
~
,
:'.
\...J
9. Owner o tion 34-01: Zone F G sum Board
~/ DEDUCT (Circle One)
Owner Option 34-01, (figures)
Lath & Plaster
O~~ 9,000.00
----------
----------
Owner Option 34-01, (words) NTNF. THonsAND DOLLARS-----__ _ _
----------------------------------------------------- DOLLARS
10. Owner Option 34-02: Non-Security Fire Walls
c=~~/ DEDUCT (Circle One)
Owner option 34-02, (figures) C)~'35;900.00
Owner Option 34-02, (words) THIRTY FIVE THOUSAND NINE HUNDRED
--------------------------------------------------- DOLLARS
v
L.J
03/11/92
GYPSUM BOARD PROPOSAL FORM (ADD. 8)
00134 - 3
"1
I acknowledge receipt of Addenda No. (s) UIA thru U11
I have included pages 1-4 of ;the Proposal Form /, and attached
the re~~ Bid secur..ity~; Lobbying and Conflict of~nterest
Clause , s~orn st~ent of Public Entity crirnes~, and Non-
Collus1Qn Aff1davit .
(Check mark items above, as a reminder that they are included.)
Mailing Address:
4044 NE 7 Avenue
Fort Lauderdale, FL 33334
Phone Number:
305-564-8008 or Dade Line is 305-944-0090
Date:
June 4, 1992.
Signed:
rf) jhk t8tJJ/JAh>
ORTELIO BARROSO
(Name)
"---'
Vice President
(TTtle)
.
Witness: . ~ c&~
t:OT1\I\Y l'trtlLIC $TAtt OF ~.auM. ( Sea 1 )
H'i c::"'ns~IOM EY.P. AUG. 2,1995
OONOED TAAU G:N:eAAL INS. UJI).
03/11/9.2
GYPSUM BOARD PROPOSAL FORM (ADO. 8)
00134 - 4
'-...
THE AMERICAN INSTITUTE OF ARCHITECTS
I
AlA Document A310
Bid Bond
K~e~:r~~lpl~Et~r~: :~E~~~~~~:~
as Principal, hereinafter called the Principal, and
Employers Insurance of Wausau
a corporation duly organ!zcd under the laws of the State of Wisconsin
as Surety, hereinafter called the Surety, are held and firmly bound unto
(Here in,erl full "a me and addre.. or legal lille of Ownerl
Board of County Commissioners of Monroe County, Florida
that we
(Here insf"r' full n~me and address or lega' litle of Contractorl
IH..r.. in,erl lull name and addr.... or '..gal lill.. of Surely)
as Obligee, hereinafter called the Obligee, in the sum of
-----------Five Percent of Amount Bid------------------ Dollars ($ 5% ),
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by
these presents.
WHE/UAS, the Principal has submitted a ~ .,Do.
t::), :'J,-j (Here in,erl full name, addre.. and de'criplion of projec!)
Bid Package No. 34 - Gypsum Board, Lath and Plaster
Ne~ Detention Facility on Stock Island, Key West, Florida
NOW, THE R EF 0 R E, if the Obligee shall accept ,he bid of the Principal and the Principal shall enter into a Contract
with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding
or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt
payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter
such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty
hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith contract
with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain
in full force and effect.
Signed and sealed this
25th
day of
April
19 92
~~~(
, (Wit s)
Went~or,~h Plasteripg Co.
I. -. -..-)---1.c:- / /:. (P~!ticlp~,
. ... -JZ~-e~'di:..A/
,/
- (Title)
of Boca Raton/~'
(Seal)
-----
.t___
'1,') ..'.'
///;}i j I I. t//'/I-'<".d
, / (Witness)
I Em. ployers Insurance of Wausau
(Su,ety)
(.j7~~. ~y ,
(Title)
Jack E. Fowler, Attorney-in-Fact
(Seal)
AlA DOCUMENT A310 . BID BOND. AlA 8. FEBRUARY 1970 ED . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 N,Y, AVE., N,W" WA5HINGTON, 0, C. 20006
1
~
z
o
w
a:
Z
a:
US
a.
a.
<{
I-
o
Z
(/)
w
o
o
I-
Z
w
~
w
G~
Z0
~~
l I:
,... r-
...~
~~
a:
o
~
LL
o
a:
w
~
~
o
::i
:3
<{
t-
O
Z
~
~
I
t-
EMPlOYERS INSURANCE OF WAl&\lJ A Mutual Company
POWER OF ATTORNEY
(FOR BID BONDS ONLY)
KNOW ALL MEN BY THESE PRESENTS:
That the EMPLOYERS INSURANCE OF WAI'SAU A Mutual Compan~', a corporation dul~' organized and l'xisting under
the laws of the State of Wisconsin, and having its principal office in thp City of Wausau, COUllt~. of Marathon, State of
Wisconsin. has made. constituted and appointed, and dol'S bv tlll'sl' prpsl'nts make, constitutp and appoint __~__~
CHARLES J. NIELSON! JACK E. FOWIF~~~ ACFVFS, JOHN S. HARRIS
its true and lawful attorney-in.fact, with full power and authorit~, hl'reby confprrpd in its namp, place and stead, to execute,
seal, acknowledge and deliver ANY AND ALL BID BONDS OR WHITTEN DOCUMENTS INVOLVIN(; BID Gl1ARAN,
TEES OR IN THE NATURE THEREAFTER _ ~ _ _ _ _ _ _ _ _ _ _ __
and to bind the corporation thereby as fully and to thp samp extent as if such bOllds were sigllpd by thp President. sealed with
the corporate seal of the corporation and dul~' attpstpn by its sP('l'l'tary hl'rl'b~' ratifying ann confirming all that the said
attorney-in-fact may do in the premises,
This powerof attorney is granted pursuant to thl' following rl'solution adopted by the Board of Direc!ors of said Company at a
meeting duly called and held on the IRth day of May. 197:1. which resolution is still in l'ffect:
"RESOLVED, that the Prl'sident and any Vice Prl'sident - eleclivl' or appointivp - of EMPLOYERS INSURANCE OF
W AUSAU A Mutual Company be. and that each of them hereb~' is. authorized to execute powers of llttorney qualifying
the attorney named in the given power of attornl'Y to execute on behalf of EMPLOYEHS INSURANCE OF W AUSAU A
Mutual Compllny bonds. undertakings ann all contracts of surl'lyship: ann that any secn'tar~' or assistant secretary he,
and that each or any of them hereby is, authorizen to attest the eXl'cution of any such power of attorney, ann to attach
thereto the seal of EMPLOYERS INSUHANCE OF WAUSAU A Mutual Company"
"FURTHER RESOLVED. that the signatures of such offin>rs and tlw seal of EMPLOYEHS INSURANCE OF W AUSAU
A Mutual Company may be affixl'n to any such power of attorney or !o an~' certificate relating thprpto by facsimile. and
any such power of attorm'y or certificate bl'aring such facsimilp signatures and facsimile seal shall he valin ann binding
upon the EMPLOYERS INSUHANCE OF W AUSAU A Mutual Company when so affixl'd ann in the future with respect
to any bond, undertaking or contrllct of suretyship to which it is attached,"
IN WrTNESS WHEREOF. EMPLOYERS INSUHANCE OF WAUSAU A Mutual Complln,v hlls cllusl'd thes!' presents to be
signed hy the senior vice president and attested hy its assislant secrelary. and its corporate seal 10 he herelo affixed this IS T day
of MARCH , 19__9)
/;;;'-;;;;i;;\ EMPLOYERS INSURANCE OF WAUSAU A Mutual Company
I; e,OIlPO""'1 t':. ~ ':_
\~}..SE'Al}/ R ~ ~. ~ k ~
'\:"r ~/' y ~
AU,,,', ,A: l~ om D. wy,,:
R, ], Besteman '" Assistant Secretary
Executive Vice President
STATE OF WISCONSIN )
) ss,
COUNT,Y OF MARATHON)
On this 1 S T day of MARrH . 19 iL , hefore me personally came
Bill D, Wymore . to me known, who heing hy me duly sworn, did depose
and say thar he is an executive vice president of Ihe EMPLOYERS INSURANCE OF WAUSAU A MUlual Company, Ihe corporal ion described in
and which execuled the ahove inslrument: that he knows the seal of said corporal ion: Ihal Ihe seal affixed to said inslrument is such corporale
seal and Ihal it was so affixed hy order of Ihe Roard of Directors of said corporation and Ihal he signed his name therelo hy like order.
IN WITNESS WHEREOF. I have hereunto sel my hand and affixed my official seal the day and year herein first ahove written,
~.~.~
Patricia A, Kleman
NOTARY PUBLIC
STATE OF WISCONSIN
MY COMMISSION EXPIRES MAY 29. 1994
CERTIFICATE
Notary Public
(~~~
STATE OF WISCONSIN
CITYOFWAUSAU )ss,
COUNTY OF MARATHON )
I, the undersi~ned. assistant secretllry of EMPLOYERS INSURANCE OF W AUSAU A Mutual Company. a Wisconsin
corporation. do hereby certify that the foregoing and attached power of attorney, WHICH MUSTCONTAIN A V ALl DAT-
ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK, remains in full force and has not been
revoker!; and furthermore that the resolution of the BOllrr! of Directors set forth in the power of attorney is still in force.
Signed and sealed in the City of Wausau. Marathon County. State of Wisconsin. this 25th
of April __ ,19B., A. J ~ L
.:r;.-.,".:z '7 ~
(CO.POItAt~~ R. J. Besteman /' '-
~ SE'Al !l
0, ",.
:'It. 1""
day
Assistant Secretary
NOTE: IF YOU HAVE ANY QUESTIONS REGAHDING THE VALIDITY OR WORDING OF THIS POWER OF
ATTORNEY. CALL TOLL FREE (ROO) R2fi-16fillIN WISCONSIN. CALL(ROO) 472-0(41)
81 )~4222- J 990
i
'-----
SWORN STATEMENT PURSUANT TO SECTION 287.133(3)'(a),
FLORIDA STATUTES, ON PUBLIC ENTITY CRIMES
THIS FORM MUST BE SIGNED AND SWORN TO IN THE PRESENCE OF A NOTARY
PUBLIC OR OTHER OFFICIAL AUTHORIZED TO ADMINISTER OATHS.
1. This sworn statement is submitted to:
MONROE COUNTY
[print name of the public entity]
ORTELIO BARROSO, VICE PRESIDENT
[print individual's name and title]
by
WENTWORTH PLASTERING CO. OF BOCA RATON, INC.
[print name of entity submitting sworn statement]
whose business address is 4044 NE 7 Avenue, Fort Lauderdale,
FL 33334-3098
and (if applicable) its Federal Employer Identification Number
(FEIN) is 59-1284463 (If the entity has no
FEIN, include the Social Security Number of the individual
signing this sworn statement: ) .
for
" ,
'--/
2.
I 'understand that a "public entity crime" as defined in
Paragraph 287.133(1) (g), Florida statutes, means a violation
of any state or federal law by a person with respe~t to and
directly related to the transaction of business with any
public entity or with an agency or political Eubdivision of
any other state or of the united States, including, but not
limited to, any bid or contract for goods or services to be
provided to any public entity or an agency or political
subdivision of any other state or of the United states and
involving antitrust, fraud, theft, bribery, collusion,
racketeering, conspiracy, or material misrepresentation.
3. I understand that "convicted" or "conviction" as defined in
Paragraph 287.133(1) (b), Florida Statutes, means a finding of
guilt or a conviction of a public entity crime, with or
without an adjudication of guilt, in any federal or state
trial court of record relating to charges brought by
indictment or information after July 1, 1989, as a result of
a jury verdict, nonjury trial, or entry of a plea of guilty or
nolo contendere.
4. I understand that an "3.ffiliate" as defined in Paragraph
287.133(1) (a), Florida Statutes, means:
\.J
03/02/92
PUBLIC ENTITY CRIMES (ADD. 6)
00420 - 1
1. A predecessor or successor of a person convicted of a
public entity crime: or
2. An entity under the control of any natural person who is
active in the management of the entity and who has been
convicted of a public entity crime. The term "affiliate"
includes those off icers, directors, executives, partners,
shareholders, employees, members, and agents who are
active in the management of an affiliate. The ownership
by one person of shares constituting a controlling
interest in another person, or a pooling of equipment or
income among persons when not for fair market value under
an arm's length agreement, shall be a prima facie case
that one person controls another person. A person who
knowingly enters into a joint venture with a person who
has been convicted of a public entity crime in Florida
during the preceding 36 months shall be considered an
affiliate.
5. I understand that a "person" as defined in Paragraph
287.133(1) (e), Florida statutes, means any natural person or
entity organized under the laws of any state or of the united
states with the legal power to enter into a binding contract
and which bids or applies to bid on contracts for the
provision of goods, or services let by a public entity, or
which otherwise tran~acts or applies to transact business with
a public entity. The term "Person" includes those officers,
directors, executives, partners, shareholders, employees,
members, and agents who are active in management of an entity.
6. 'Based on information and belief, the statement which I have
marked below is true in relation to the entity submitting this
sworn statement. [indicate which statement applies.]
X Neither the entity submitting this sworn statement, nor
any officers, directors, executives, partners, shareholders,
employees, members, or agents who are active in the management
of the entity, nor any affiliate of the entity has been
charged with and convicted of a public entity crime subsequent
to July 1, 1989.
The entity submitting this sworn statement, or one or
more of, its officers, directors, executives, partners,
shareholders, employees, members, or agents who are active in
the management of the entity, or an affiliate of the entity
has been charged with and convicted of a public entity crime
subsequent to July 1, 1989.
The entity submitting this sworn statement, or one or
03/02/92
PUBLIC ENTITY CRIMES (ADD. 6)
00420 - 2
'-....--'
more of its officers, directors, executives, partners,
shareholders, employees, members, or agents who are active in
the management of the entity, or an affiliate of the entity
has been charged with and convicted of a public entity crime
subsequent to July 1, 1989. However there has been a
subsequent proceeding before a Hearing Officer of the state of
Florida, Division of Administrative Hearings and the Final
Order entered by the Hearing Officer determined that it was
not in the public interest to place the entity submitting this
sworn statement on the convicted vendor list. [attach a copy
of the final order]
I UNDERSTAND THAT THE SUBMISSION OF THIS FORM TO THE CONTRACTING
OFFICER FOR THE PUBLIC ENTITY IDENTIFIED IN PARAGRAPH 1 (ONE) ABOVE
IS FOR THAT PUBLIC ENTITY ONLY AND, THAT THIS FORM IS VALID THROUGH
DECEMBER 31 OF THE CALENDAR YEAR IN WHICH IT IS FILED. I ALSO
UNDERSTAND THAT I AM REQUIRED TO INFORM THE PUBLIC ENTITY PRIOR TO
ENTERING INTO A CONTRACT IN EXCESS OF THE THRESHOLD AMOUNT PROVIDED
IN SECTION 287.017, FLORIDA STATUTES FOR CATEGORY TWO OF ANY CHANGE
IN THE INFORMATION CONTAINED IN ~. ;?;~
~ture]
Date: April 30, 1992
............'
STATE OF
FLORIDA
.
COUNTY OF
BROWARD
PERSONALLY APPEARED BEFORE ME, the undersigned authority,
ORTELIO BARROSO
[name of individual signing]
who, after first being sworn by me,
affixed his/her signature in the space provided above on this
30th
day of
April
19 92
!hA~:;;L#~z" )
My commission expires:
_~~'rT:'I.~,~ Pl;tlL'r{~ ~Tj("""r. ~T P7[~lr;~~1
!>ff C:M';IS.'Hnl1 En> _ ,':'1(;. :;,1')>:5
WII{[)U,' tun" 1~:Mi'.r.!lJ. ntt!. f1ID.
A
F~rm PUR 7068 (Rev. 04/10/91)
"-.../
03/02/92
PUBLIC ENTITY CRIMES (ADD. 6)
00420 - 3
LOBBYING AND CONFLICT OF INTEREST CLAUSE
SWORN STATEMENT UNDER ORDINANCE NO. 010-1990
MONROE COUNTY, FLORIDA
'-.---'
" WENTWORTH PLASTERING CO. OF BOCA RATON,INC."
(Company)
~,~
" warrants that it has not employed, retained or otherwise had
act on its behalf any former County officer or employee subject
to the prohibition of Section 2 of Ordinance No. 010-1990 or any
County officer or employee in violation of Section 3 of Ordinance
No. 010-1990. For breach or violation of this provision the'
County may, in its discretion, terminate this contract without
liability and may also, in its discretion, deduct from the
contract or purchase price, or otherwise recover, the full amount
of any fee, commission, percentage, gift, or consideration paid
to the former County officer or e7J~ /32 tU.u>u
~ (Signature)
Date: April 30, 1992
STATE OF
FLORIDA
BROWARD
COUNTY' OF
PERSONALLY APPEARED BEFORE ME, the undersigned authority,
Orte1io Barroso who, after first being sworn by me, affixed
his/her signature (name of individual signing) in the space
provided above on this 30th. day of April , 1992.
ih.,~ ,uc8~
NOTARY PUBLIC -
My commission expires:
NOTl'uT~ 1'1'IlLIC s'rATE OF FtJ.:fUP~
MY: 'CU4Ml SSIOl'I E)(P. l\.UG. 2, l!I95
DONDED Tlmu CEtll?ML DlS. UNO.
u
07/25/91 LOBBYING AND CONFLICT OF INTEREST CLAUSE
00425 - 1
Non-Collusion Affidavit
, I, Ortelio Barroso of the city of Fort Lauderdale
'according to law on my oath, and under penalty of perjury, depose
and say that;
,-_./ 1.) I am Vice President of the firm of Wentworth
Plaitering Co.of Boca Raton.I~cthe bidder making the Proposal for the
project described in the notice for calling for bids for New Monroe
County Detention Fac. , and that I executed the said proposal with
full authority to do so;
2.) the prices in this bid have been arrived at
independently without collusion, consultation, communication or
agreement for the purpose of restricting competition, as to any
matter relating to such proces with any other bidder or with any
competitor;
3.) unless otherwise required by law, the prices which have
been quoted in this bid have not been knowingly disclosed by the
bidder and will not knowingly be disclosed by the bidder and will
not be knowingly disclosed by the bidder prior to bid opening,
directly or indirectly, to any other bidder or to any competitor;
and
4.) no attempt has been made or will be made by the bidder
to induce any other person, partnership,or corporation to submit,
or not to submit, a bid for the purpose of restricting
competition;
'--,
5. )
correct,
upon the
awarding'
the, statements contained in this affidavit are true and
and made with full knowledge that Monroe County relies
truth of the statements contained in this affidavit ln
contracts for said project"-(O ~ (3~
(Signature of Bidder)
STATE OF FLORIDA
COUNTY OF BROWARD
April 30, 1992
DATE
PERSONALLY APPEARED BEFORE ME, the undersigned authority, _
Ortelio Barroso who, after first being sworn by me,
(name of-individual signing)
affixed his/her signature in the space
30th day of April
provided above on this
92
, 19_.~
;~~~
/ NOTARY PUBLIC
NOTARY rum.Ie STATP. OF FLORIDA
My commission expires: m crnm..SION EXF. ll1JG. 2,1995
BONDED tHRU GENERAL IllS. UJI).
"'-'
11/20/91
NON-COLLUSION AFFIDAVIT
00430 - 1
THE AMERICAN INSTITUTE OF ARCHITECTS
.
AlA Document A201/CM
CONSTRUCTION MANAGEMENT EDITION
General Conditions of the Contract
for Construction
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENcES; CONSULTATION
WITH AN ATTORNEY IS ENCOURAGED.
1980 EDITION
TABLE OF ARTICLES
1. CONTRACT DOCUMENTS 8. TIME
2. ADMINISTRATION OF THE 9. PAYMENTS AND COMPLETION
CONTRACT
10. PROTECTION OF PERSONS At'\D
3. OWNER PROPERTY
4. CONTRACTOR 11. INSURANCE
5. SUBCONTRACTORS 12, CHANGES IN THE WORK
6. V\lORK BY O\VNER OR BY 13. UNCOVERING AND CORRECTION
SEPARA TE CONTRACTORS OF WORK
7. MISCELLANEOUS PROVISIONS 14. TERMINATION OF THE CONTRACT
~ CAUTION: You should use an original AlA document which has this caution printed in red,
~ An original assures that changes will not be obscured as may occur when documents are reproduced.
Copyright 1975, @ 1930. by The American Institute of Architects, 1735 New York A\cnue, N,\\'" Washington, D,C. 2 ()<))6,
Reproduction of the material herein or substantial quotation of its provisions without" riUen permission of the AlA viobles
the copyright laws 01 the U"ited SIale5 and will be subject to legal prosecution,
AtA DOCUM[NT A201iCM . G[SoR~l CosDITIONS Of TH[ CONTRACT fOR CO"STRUCTJON
CONSTRUCTION "'.ANAGEMH-iT EDiTION . JUNE 1980 EDITION . AtA~ . If 1980 . THE
A,',.\[RICAN INSTITUTE OF ARCHITECTS. 1735 NEW YORK AVE.. 1'01,\\". WASHINGTO". D,C 21Xx:l6
A201/CM -1980 1
,~cceptance of Defective of Non-Conforming Work .,6,2,2. 13,3
Acceptance of VVork ",."""".,'" ,9,5,5,9,8,1,9,9,1,9,9,3
Acce,s to VVork """".' ",.'".'" , ", ,,"," ,2,3,6, 6,2,1
Accident Prevention, . , , , , , , , , , , , , , , , , , , ' , ' . , , , . , , .2,3.5, 10
Acts and Omi"ions ",',',""" ,4,18,3,7.4,7,6,2,8,),1,10,5
Addenda, Definition of,.""",.""""",."""., .1,1,1
Additional Costs, Claims for, , . , , , , . . , . , , . , , , , , , . , . " , .12,)
ADMINISTRATION OF THE CONTRAa .,..,....".. .2,4,).3
Agreement, Exll:nt of ....,.,.,.......,....,..,......1,1,1,2
All Risk Imurance "..."",..",...".",.,.,..".. .11,3,1
Allowances ,.,.,."."".."".".,.,...,",..".,.,. ,4,8
Applications for Payment, Contractor's.."., ,2,3.8,9,2,1,9,3,1,
9,3,3,,9.5,3,9.7.1,9,8,2,9,9,1,9,9,3,9.9,5, 11,3,1, 14,2,2
Applications for Payment,
Project,.,.."."""., ,2,3,8,2,3,9,9,3,1,9.4,9,6,1,9.7,1
Approvals. , . , . , , . ,.. , , . , .' , , , . ,2,3,18, 3.4, 4,3,3, 4,5, 4,12,4.
4,12,5,4,12,6,4,12,8,4,13,2,7.7,9.3.2
Arbitration"",,' ,2,3,15,2,3,2],6,2,5,7,9,8.3,1,11.3.7,11,3.3
Architect, Definition of , , . . . , .. , , . , , , , , , , ' ,. . , ,. . , . . . . . ,2,'
Architect, Extent of Authority""." .2,3,3.4,4.12,8, 5,2, 7.7,2,
8,1,3,8.1.4,8,3,1,9.2,9,3,1,9.4,9,5,3,9,6,9,8, 9,9,1, 99,3.
12,1,1,12,1.4,12,3,1,12.4.1,1),1.13,2,'.13,2.5,14,2
Architect, Limitations of Authority and Responsibility..,. ,2.3,2
through 2.3,5, 2.3,13 through 2,3,18, 2,3,22. 4,12,&,
5.2,1, <),4,2, 9,5.4, 9,5,5, 12.4
Architect's Additional Services,. ,3.4,7.7.2,13,2,1,13,2,5,14,2,2
Architect's Approvals."" ,2.3,18,3.4,4,5,4.12,6,4,12,8,4.18,3
Architect's Authority to Reject Work", ,2,3,16, 4,5, 13,1,2, 13,2
Architect', Copyright, , ' , , , , , , , , , , , , , , , , , , , , , , , , , . . , . , . ,1,3
Architect's Decisions, , . , , . , , ,.' , . ,2.3,10 through 2,3,16, 7.7,2,
7,9,1,9.2,9.4,96,2.9,8,1,12,1,4,12,3,1
Architect's In,pections ,',"," ,2,3,16,2,3,21,9.4,2,9,8,1.9.9,1
Architect's Instructions, , , . , , , , , ,2,3,16, 2,3,19, 7.7.2. 12.4, 1),~
Architect's Interpretations, , , ' , , , . .2,3,10 through 2,),13,12,),2
Architect's On-Site Observations, . , , , . ,2,3,4, 2.),6, 2,3,9, 7.7.1.
7.7.4,9.4.2,9,6,1,9,91
Architect's Relationship with Contractor.",. ,1,1.2, 2.3,5, 2,3,6,
2313,23,16,4,3,),4,5,4,7,3,4,12.6,4,18,11,3,6
Architect's Relationship with
5ubcontractors ."".",," , ,," ,1,1,2,2,3,16,9,5,3,9,5,4
Architect's Representations"".." , ,. , , , ' , ,9.4,2, 9,6.1, 9,9,1
Arti,tic Effect"""""""",.". ,.1.2.3,2.3,14,2.3.15,7,9.1
Attorneys' Fees"",."""",.,.".,',., .4.18,1,6,2.5,9,9.2
Award of (ep2fate Contracts, " , . , , ", , , , , , , , , , . . , . ... ,6,1.1
Award of Subcontracts and Other Contracts for
PortiOns of the Work, ' , , , , , , " , " , . ' , ' ' , . , , ' ' , , ' " ,5,2
Boiler and !\,achinery Insurance"..".""""",',.. .11,3,2
Bonds, Lien ,",",', _ . , . , . . , , . . . , , , , , , , , , , , . . , ,9.3,3, 9.92
Eoroes, Performana, labor and Matenal Payment, , , ' .7,5, 9,9,3
Building Permit, , ' , , _ , ' , , " , ,. , , , " , , " . , , ' , ' ' , , , , , , , , ,4.7
Certificate of Substantial Completion", ,9,8,1, 98.2, 9,83, 98.4
Certificates of Inspection, Testing or Approval, , ' , ' , , , , " ,7.7.3
Cert:ficates of Insurance"""""".".,,"'" ,9,3,2,11,1.4
Certificates for Payment, Project, , , , " , ,2,3,9, 2,3.21, 9.4, 9.5,1,
9,55,96,1,9.7.1,9,8.2,9,9,1,9,9,3,12,1.4,14,1.1,14,2,2
Change Orders""""".,.. ,1.1,1.2.3,19,3.4,4,8,2,3,4,11,1,
52,3,7.7,2,8.3,1,9.7,9,9,3,11,3,1,11,3,5,11,3.7,
12,1,12,2,1,12,3,1,13,1,2,13.2,5,13,3,1
Change Orders, Definition of , , " , , , , " , , ' , ' , , , , ' . , , . ,12,1,1
CHANGES IN THE WORK.".,...""..", ,2.3,19,4,11,1,12
INDEX
Claims for Additional Cost or Time"" ,8,3,2, 8.3.3, 12,2,1, 12.3
Claims for Damages"".""".., ,6,1,1, 6.2,5,7.4,8,3,96,1.2
Claims and Disputes Between Contractor
and Owner"""""", ,2.3,12,2,3.15.2.3.23,4,182,7,9
Cleaning Up , , " ' ., , , . , . , , , , , , . , , , , ' , , , , 415 63
Commencement of the Work, Conditions Rei;ti~g 't~' ',32,1: 4,2,
4,7,1,4,10,5,2,1,62,2,7.5,9,2,11,1,11,3.4
Communications. ,. , . ,. ,., . , . . . " , , . ' ,2.3,2, 3,2,6,4,9,1,4,16
Completion,
Conditions Relating 10 ., ,2,3,21, 4,11,4,15,9.4_2.9,9,13,2.2
COMPLETION, PAYMENTS AND..""...,."..."..,.... ,9
Completion of the Project, Substantial ".",,8.1.4, 9,8,3, 9,8.4,
9,9.4,9,9,5,9,9.6,13,2,1,13,2,2
Completion of the Work, Substantial"",,' ,2.3,21, 8,1,1, 8,1.3,
8,2.2,98,9.4.2,9,9,3,11,3,9
Compliance with laws...".."" ,1,),2,1,1,4.6,4.7,4,13,7,1,
7.6,1, 7.7,1,10.22,14,2_1
Concealed Conditions. ' ., , , , , , . , . . . , , , . . , . , , . , .. . , , , . ,12.2
Consent, Written .,..."....,",.,., ,2,3,22,4,14,2,7.2,7,6.2,
9.8,1,9.9,2,9,9,3,11.39
Construction Manager, Definition of ,,',",,' _ , , , . , . , , , , ,22
Construction Manager's Approval" """,., '" ,4,10,1,4,13,2
Construction Manager's
Additional Services,..,.." ,3,4, 7.7.2, 13.2,1, 1325, 14,2.2
Construction Manager's Authority and Responsibility, , , . ,2,3.3,
2,3.5,2,3,16,2.3,10,23,22,4.8,1,4,17,1.4,183,
7.7.4,9,2,10,2,5,11.3,6,12,1.4,14,1,1
Construction Manager's Confirmation, , , . , , ' , ' , , , , , . . . , ,9,9.3
Construction Manager's Consultation with the Architect. 2,3.-
2,3,16,2,3,19,2,3,21,3.4,1,9.6,1,9,8,1,12,1.4.12,3,1,14
Construction Manager's Coordination and Scheduling. , , ,2,3.7,
2.3,17,4.3,1,4,10,1,4,12.4
Construction Manager's Decisions. , , , , , , , , " , , , , , . ,6,3, 8.3,1
Construction Manager's Determinations, ,2,3.3, 6.3,1, 7.7,2, 8.3,1
Construction Manager's Interests","""""" ,11,3,1,11,3,2
Construction Manager's Recommendations", _2,3,8, 2,3,9, 9,3,1,
9.4,1,9,7,1,9.9,1,1211
Construction Manager's Relationship
with Architect"""""."",., .1,1.2,2.3,1, 2,3,3, 2,3.~1
Construction Manager's Relationship with Contractor,.,. ,1,1,2,
23,15,2.3,16,3.2.6,42,1,43.3,4,5,4.7,3,4,11,1, 4,12.4, 4,126,
4,16,1,4.17,1,4,18,5,2,6.2.1,6,2,2,7,6.2,7.7, 7,9,1, 7.9.2,
8.3,1,8,3.2,9.4,1,9,5.4,9,8,1,9,9,1,10,2.6,11,1.4,1136
Construction Manager's Relationship
with Subcontractors".""""""", ,1,1,2, 23,16,53.1
Construction ,,",'anager's Review, "",.",., ,23,8,2.3,17,5,21
Construction Schedule, Contractor's , , ' , , , , , , , , , ' , , , , , . , ,4'-,;)
Contract, Definition of ,." , , _ , , , , , , , , , , , ' , , ' , , ' , . , , , , ,1,1 2
Contract Administration, , , , , . . . , , , , , , , . , , , ' , , . , ' , ,2,3, 4,33
Contract Award and Execution,
Conditions Relating to."., .4.7.1, 4,10, 52, 75,11,1,11.34
CONTRACl DOCUMENTS "....,..,;.".""..".."... "
Contract Documents,
Copies Furnished and Use of ""~"""'" ,1.3,3,2,5,5.)
Contract Documents, Definition of ""','" _"""".. ,1,1,1
Contract Modifications""." """,.'"""""., .1,1,1, 12
Contract Sum, Definition of ",',,',"',',"",","" ,9,9,1
Contract Termination"",,'" " " """".",.',,' .14
Contract Time, Definition of """"",."""""",. ,8,1,1
CONTRAClOR ".""".."""."""",..",..,."...4
Contractor, Definition of "," , ' , , , , , , . , , ' , . ' , , , ' , ,4,1, 6,;.2
Contractor's Construction Schedule, . , ' , " , . , , . . ,. , , , . , ,4,10
2 A201/CM-1980
AlA DOCUME1'o:T \~Ol,'CM . GENERAL CONDITIONS OF THE CO:--:1RACl FOR CONSTRUCTI::;"
CONS:RUCTIO' ,\"'ACEMEST EDITION . )t.:SE 1%0 EDITION . .~IA! . :r. 1980 . ~~E
AMERICAN INST,'L'H OF ARCHITECTS, 1;.35 ,'-'E\\' YORK AVE., N,\\'. \NASHI"'CTOr-;. D.C. 2:':':';
.... II...;' ~,..,~_p_" ....\-- . ,_, -'-,' ........ d ~.:;.E'(" 1.,; S ,. _:",.'r',~ ~. ;~- .~ ",:r~ i~ ~;.:t: k. I.
Contractor's Employees, . , ' , .4.3.2, 4.42, 4.8,1, 4,9, 4,18, 102,1
through 102,4, 10,2,6, 10,3, 11.1.1
Contractor's Liability Insurance""""."""....,..,. ,11.1
Contractor's Relationship with Architect, , , , . ,1,1,2, 2,3,5, 2,3,6,
2,3,13,2,3,16,4.3.3,4,5,4.7.3,4,12,6,4,18.11,3,6
Contractor's Relationship with Construction Manager".. .1,1,2.
2,3,15,2,3,16,3,2,6,4,2,1,4.3,3.4.5,4.7,2.4,11,1.4,12.4.
4,12,6,4,16,1,4.17,1.418,5.2,6,2.1,6,2.2,7,6,2. 7.7, 7,9,1,
7,9,2.8.3,1.8,3.2.9.4,1,9,5.4,9.8,1.9,9.1, 10,2,6.11.1.4. 11,3,6
Contractor's Relationship with Sei=,arate Contractors
and Owner's Forces",..""".,.".".....,.. ,3,2.7. 6
Contractor's Relationshit' with
Subcontractors,.",.", ,1,2.4,5,2,5,3,9.5,2.11,3,3,11.3.6
Contractor's Representations"","'" .1,2.2, 4,5. 4.12,5, 9,3,3
Contractor's ResponsIbility lor Tno>e
Pedorming the \\'ork .""""".".,..,' .4,3,2, 4,18. 10
(:ontractor's Review 01 Contract Documents. . , ,1,2,2. 4,2, 4.7.3
Contractor's Right to Stop the \\ork ",.,.'.,...., ' . , . . . ,9.7
Contractor's Right to Terminate t:-,e Conlract ".'.,.. .,., ,14,'
Contractor's Submittals""""."", ,2,3,18.4,10,4,12,5,2,1.
52.3.9,2,9,3,1,9,8,1.9,9,2,9,9.3
Contractor's Superintendent, , ,.. ,. , ' , ' , ., , , , , , , , . .4,9, 10,2.6
Contractor's Supervision and
Construction Procedures, , ., , ' , , ' ,1.2.4. 2,3,5, 4.3. 4.4. 10
Contractual Liability Insurance"""""""".,., ". ,11,1,3
Coordination and Correlation"""" ,1,2,2. 1,2.4.4,3,1.4.10,1.
4,12,5.6,1,3.6,2.1
Copies Furnished of Drawings and Specifications. ,1,3, 3,2,5, 5,3
Correction of Work"""""""""., ,3,3.3.4,10,2,5.13 2
Cost, Definition 01 "",...",.,."""".",.,',... ,12,1,4
Costs""" ,3.4, 482, .1.15,2, 523. 6.1,1, 6.2,3, 6.2,5, 6.3, 7.7,1,
7.7.2.9.7.11.3,1.11.3,5.12,13,12,1,4,12,3.13,1,2, 13.2, 14,2,2
Cutting and Patching of Work, , , , , , , , , , , ' , , , . . , , , , , , , . ,4,14
Damage to the Work""."",. ,';,14.2,10.2,1,2,10.2.7.11,3,1
Damage to Work""".."" ,4.14,2, 4,18,1. 6,2,4, 62.5, 9,6,15.
1C'.2,1,3, 10,2.2, 10.2.5, 10.3, 13,2,6
Damages, Claims for"""".."..", ,6,1,1, 6,2,5,7.4,9,6,1,2
Damages lor Delay , ' , ' , . , , , . , . , , , , , , . , , ,6,1,1, 8,3.4. 9.7
Day, Definition of "",., , ' , , ' , , , , , , , , . , , . , , , , . . , . . , . ,8,1,5
Decisions 01 the Architect"",." ,2,3,10 through 2,3,16, 7,7,2,
7,9,1, ".2, 9.4, 9,6,1, 9,8,1, 12,1.4,12,3,1
Decisions of the Cor:;truction .\',a-,ager "" ". ,.,.', ,6,3,83,1
Defective or '-.on-C,-,C\iormir,g \'. = rk, Acceptance,
RejectiOn arid Correction c: .",. ,2,3.4.2,3,16,3.3.3.4,'; :;,
62,2,6,2.3,96.1,1.9,9.4,2,13
Defmitions ",."""..'. ,1,1, 2.1,2,2,3,1.4,1,4,12,1 through
412,3.5,1,6.1.2,8.1,9,1,1,12,1.1,12,1.4
Delays and Exterls;:Jns of Time. , , ' , ' , , , , , . , , , , , , , . , , , , . ,8,3
Disputes...",."",.". ,2312,2,3,15,2,3,23,6,2,5,6.3, /,9,1
Documents and Saenp:es at thE 5:1' """",'.", , , . . , , .4,11
Drawings and Speciflca:ions,
L'se and O\',nershp of .', .""""" ,1,3,32.5,4.11.5,3
Easements, , ' . , , , , ,. , " , , , ,. ,.,.",.,.""".,.,.".32,3
Emergencies .".."""""",.,.",.""",."".., ,10,3
Employees. Contractor's."",.", ,4,3.2,4.4,4,4,8,1,4,9,4,18,
10.2.1 :~'0Jgh 10,2.4, 10.2,6, 10.3,11,1,1
Equipment, labor, \\alerials a~:: ,'.', ,1,1.1,4.4,4,5,4,12,4,13,
4,151,6,2,1,9.3,2,9,3,3,9,6,1,3,9,9,2,
10,2.12,11.3,1,12,1.4,13,2,2.13,2,5.14
Execution and Progress of the Work"".", ,1,1,3,1,2.3,2,3,4.
2,3,5.2.3,11,4,2.4,4,1.4,5.4.7,1.6,2,2.7,9,3,
8,2,2,8.3,1,8,3,2,9.6.1.10,2.3.10,2,4,14,2
Execution, Correlation and Intent of
the Contract Documents ",."",."""",.,,1,2.4.7,1
Extensions of Time""""",.,..".",., ,8,3.12,1,1.12,1,2
Failure of Payment by Owner".,..,.",..,.,."", ,9,7. 14,1
Failure of Payment of Subcontractors, , , , . .9,6,1.3, 9,9,2. 14,2,1
Failure to Carry out the Work, , , . , , , . , , , , , , . , , . , , , . . , . ,2.3.5
Final Completion and Final Payment, . .2,3,15,2.321.9,9.13,3,1
Financial Arrangements, Owner's , , , . . .' . . , , , ,. ., . . ,. . ,.3,2,1
Fire and Extended Coverage Insurance."".""".", .11,3,1
Governing Law, . . , . , , , , , , . , , . , , , , , , , , . . . . , , , , ' . . , . . , , .7.1
Indemnification..."..""",..,.."" .4,17. 4,18, 6.2,5. 9,9,2
Identification 01 Contract Documents, . . . , . , . ' ". , .. ..,,1,2.1
Identification of Subcontractors and Suppliers.......,... ,5,2,1
Information and Services Req~ired of
the Owner. . . , . . , . , , , ' , , . . , , , , , ., 3 2 61 9 11 2 11 3
Inspections".."".".. ,~3,16, 2,321. 4'3,3: 7,'7: 12,l,i:9,9:1
Instructions to Bidders"""",.", ",'.'""..,..'., ,1,1,1
Instructions to the Contractor".."". .2,3,2,3,2,6,4,8,1,7.7,2.
12,1.2.12,1.4
INSURANCE ".....,.."",.....",.....,..,......9.8,1.11
Insurance, Contractor's Liability,."",..,.""",.,... .11.1
Insurance, Loss 01 Use",."",."",..,.".""..,.,. .11.4
Insurance, Owner's Liability" , , , , , , , , , , , , , . ' , ." , '" " ,11,2
Insurance, Property".",.,.,.".".""""",.,..., ,11,3
Insurance, Boiler and Machinery"" ,."", ,'.'""" ,11.3,2
Insurance. Special Hazards......,..,.",."",....,. ,11,3,5
Insurance, Stored Materials,. , , , , . , , . , , , , , . , , ",.9,3,2.11,3,1
Insurance Companies. Come~t to Partial Occupancy,." ,11,3,9
Insurance Companies, Settler:-ent With.""""""", ,11,3,8
Intent of the Contract
Documents..,...""", ,1,2.3,2,3,10,2.3.13,2,3.14.12.4
Interest ",.".....'"",,'.,'..' , 7 8
Interpretations, Written.""" ,1,1,1: 2'3,'1'1: '23'1'2'.';;,3:13: 12:4
Labor, .\Iaterials and Equipmcrlt """ ,1,1,3,4.4,4,5,4.12,4,13.
4.15,1,6,2.1.9,3,2,9,3,3,9,6,1.3,9,2,2,10.2,1,2.
11,3,1.12,1,4,13.2,2,13.2.5.14
labor and -'Iaterial Payment Bond """""""",.,..,.7,5
labor Di'putes , , , , , , ' , , , , , , , , , , , , , , , , , , , . , , , , , ",8.3,1
laws and Regulations",."",.., ,1,3,2,1,1,4.6,4./,4,13,7,1.
. 7.6,1, /.7,1. 102.2. 14
Liens ",.', , , , , , , , . . , , , , , , , , . , , , , , , , , , . . 9 3 3 9 9 2 9 9 4 1
Limitations of Authurity ,."",."""", ,2,32: 1;3,8. ;2:4:1
Limitations ot Liability"""..., ,2,3,13, 2,3,16, 2,3,18.3.3.4,2.
4,/,3, ,U2.6, 4,17, 4,18, 6.2,2,7,62,9.4,2,
. . . ?5,4, 9,9.4, 9.9.5, 102.5, 11,1.2, 11,3,6
Limitations of Time, Gener,,' ,,"'" ,2.3,11,2.3.18,3,2,1,3.2.4,
4,2.4.7,1,4,;-,3,4,12,4,4,15,1,5,2,1,5,2,3.6,2,2,7.4.
7.7.7,9,2, E2, 9,5.2, 9,6,1, 9,8, 9,9,11.3,1.11,3.4,
, . 11.3,9,12,1.4.12.4.13.2,1,13,2,2,13,2,5
LimitatIOns of Time, Speciilc '.""" ,3.4,4,10, /.9,2, 8.2, 83,2.
8.3.3,92,931.9.4,1,9,5,1,9.7,11,1.4,11,3,8.
, , , 122,12,3,1,132,2,13.2.7.14,1.14,2,1
limitations. Statutes of """,."."",'. .7,9,2.13,2,2.13,2.7
Loss ot Use Insurance.""""""""",.""...".. ,11.4
AlA DOCUME"\T Al01 CM . C["\[;.'~ CO'\DI110"\5 OF TH[ COS1RACT fOR CO"-:STRl CTION
CO'\5TRUCTI0"\ \\A"\AGE\\["-:T [,>-;0"\ . JL;,,",[ 1980 [DiTION . ,',IA~ . 8198D . THE
^'\lRICAS 1'\51 iTL T E OF AROil1 lC5, 1735 '\[\\' YORK AVE, "'.\\'., \\,-\5HI"'G10"" D.C :'0006
A201iCM-1980 3
."-.laterIJI<. lebor ;,c;d Equipment.",,' ,1.1,3, 44, 4.5, 4,12, 4,13,
4,15,1.6,2.1,93,2,93,3.961,3.9,9,2,
10.21,2.11,3,1,12,1.4,1322,132.5,14
......aterial Suppliers".".""""""",,' ,4,12,1, 5.21,9,33
,'-.leans, ,...If.'thods, Techniques, Sequences and
and Procedures of ComtrlJction """",2,35, 4.3,1, 9.4.2
Minor Changes in the Work",.",."."" ,1,1.1,2,3,19,12.4
MISCHLAt-;EOUS PROVISiONS,.",.,.",."....,., '" ,. ,7
Modifications, Definition of "".,..,.."",,",",.,' ,1,1,1
Modifications to the Contract, , , , , , , .1,1,1, 1,1,2, 2,3,2, 23,22,
4,11,1,4.7.3,12
/-.Iutual Responsibility ,....,..",.".",.,..",."."",6,2
t--.:on,Conforming Work, Acceptance of DefHlive or ",'" ,13,3
t"otice, \Nritten "".""" .23,11,2.3.15,4,2,4.7.3,4,7.4,4,9,
4,12.6,4,12.7,5,2,1,7,3,7.4,7,9,2,8,1,2,8,3,2,8,3,3,
9.4,1,9.6,1,9,7,99,1,9,9,5,10,2.6,11,1.4,11,3,1,
11,3,5,11,3.7,11,3,8,12,2,12,3,13,2,2,132.5,14
I"otices, Permits. Fees and"".""." ,2,3,2, 4.7, 4,13.1, 10.2.2
t"otice of Testing and Inspections,.""".",."",',.,' .7.7
I"otlce to Proceed, , , . , , . , , , , ' , , , , , , , , , .' , , . , , , . , , . , , ,8,1,2
Obser\'ations, Contra(\or's ,."".."""","'" ,1.2,2, 4.7.3
Occupancy"",."".."".,',..,' ,8,1,3,8,1.4,9,5,5,11,3,9
On.Site Impections
by the Architect"",."" ,2,3,16, 2,3,21, 9.4.2, 9,8,1,9,9,1
On-Site Observations by the Architect.,."" ,2.3.4, 2,36,2,3,9,
7.7.1,7,7,4,9.42.9,6.1,9,9,1
Order<. Written"""""""", ,3.3,4,9,12,1.4,12.4,1,13 1
O\....t-;ER """."""""."."".".""..,....,.".,.3
O\\ner. Definiti(,n """",.""".""",""",.,'" ,3,1
Owner, Information and Sc-r\.ices
Required of Ihe ,',"'," ,3.2, 4,7,1, 6,1,3, 6,2, 9, 11,2, 11,3
Owner's Authority",,' _""".,'" ,2,3,21,7.7,2,9,3,1,9,3,2,
9,8,1,11.3,8,12.12,12,1.4
01\ neTS Financial Capability",,""" , , , . , , , . , , , ' , ' , ,3,2,1
Ol\ner's llabillt) Insulance .,...""""""""""",11,2
Ol\ne(s Relationship wilh Subcontractors"""", ,1.1,2, 9,5.4
0\\ nus RighI to Carry Oul the Work, , ' , , ' ' , , , , , , ,3.4, 13,2.4
0\\ ner's Right to Clean Up """""., ,'," "". ,4,15.2, 6.3
Ol\ner's Right to Perform \\ck and to
.-\\\ard Separate Contracts, . " , , ' , , ' , , ' , , , . , , , , ' " ,&,1
a\'. nus Right to Telmlnate the Contract, ,"',',"',' ., ,14,2
(',', ~c' . R.~ht In (\ ;J the \\c' ' ,3,3
O,\nc:,hlp and L,e ot Docume;-r\', ".'"""", ,1,3,32.5.5,)
Pa'chClS of Work. Cutting and"""""" ,. ,-1.14
Patect', I\l',\alilCS and""""""",." .,' ,-:,17,1
Pe\ll1cni 5~nd. labor wd .\\a\(':al """",., ""." .7.5
Pc~ nie:it, CO;1!raclor's :\pp1iCe:liu:\$ tor... . ..2.3.8,9.:2,9.3,9.4,
, 953, '1"1, 9.71, 982,991.995,1.-12.2
P2\n'~ct Prorect Certificates for"."" ,2.39,2.3,21,9.-1,9.5,1,
, . 95'5.961,9.7,1, '18:,99,1.9.93.12.1.4,14,11, 'j,U,2
Pe\ll1f'1t, failure of ,"',",","" ,95.2.9,61,3,9,7,9,92.14
Pa\rr.ent, final"""",.",.""" 2315,23.21,9.9.13,3,1
P2:~n'E~ts, PlogeE's ""."" .-8.7,9.3,955.98,2,9.9.3,12,1.4
P-\YME~TS A~D CO',WlETIOS ."""".,.""",.".",9
Pa'. !C..~~ts to Sl.bccntraclors """",,9.5,2,9,5.3,9.5.4. Q.6,1.3,
, 113,3,l,U,1
Pa:f'lc'1ts Withheld"""".""""".,..,.""."." ,9,6
Performance Bond and labor and .\\atcrial Payment Bond" ,7,5
Permits, fees and ~otices "',',""',' ,3,2.3,4,7,4,13,10.2,2
PERSOt-;S AND PROPERTY, PROnC110N OF , , . . . , , , , , . . , ,10
Product Data, Definition of """""".',".""'" .14,2,2
Product Data, Shop Drawings, Samples and.. ,2.3,18, 4,2.1, 4,12
Progress and Completion".".".""""" ,2,3.4, 7.9.3, 8.2
Progress Payments.",.."" 7.8,7,9,3,9,5,5,9,8.2,9,9,3,12,1.4
Project, Definition of ....".""".."..",...,"'" ,1,1.4
Project Construction Schedule, . , , . . . , , ' , . . , , . , , . " " , ,.4,10
Property Insurance""",."..,."""".",.,.",... ,11,3
PROTECTION OF PERSONS AND PROPERTy............. .10
Record Documents".."...."""".,.""".,."., ,4,11
Regulations and laws".,...." ,... .1,3,2,1,1,4,6,4.7,4,13,1,
7,1,10,2,2,14
Rejection of Work",.,.""."""."", ,2,3,16,4.5,1,13.2
Releases of \Vaivers and liens. , , , , , ' , , , , , , , . , , , , ,9,9,2, 9,9.4
Repre,entations """,..', ,1,2,2,4.5,4,12,5,9.4.2,9,6,1,9,9,1
Representatives,., ,2,1,2,2,2.3.2,2,3,22,3,1,4,1,4,9,5,1,9,3,3
R("ponsibility lor Those Performing the Work,." ,2,3.5,4.3.2,
6,1,3,6,2,9,8,1
Retainage "",',""" , , , , . , , , ,9.3,1, 9.5,2, 9,8.2, 9,9,2, 9,9,3
Review 01 Conlract Documents by the Contractor. , , . , , ,1.2.2,
4.2, 47.3
Re\'iews of Contractor's Submittals by Owner and
Architect"".,.""". .2,3,18,4,10,4,12,5,2,1,5.2,),9.2
Rights and Remedies"...,.."" ,1,1,2,2.3,15,2,3,16,3.3,3,4,
5,),6,1,6.3,7,6,7.9,8.3,1,9,6,1,9,7,
103,12,12,12,2,13,2.2,14
Royalti('s and Palents ........,..,.................... ,4,17
Salety of Per,ons and Property, , , ' , , , , , ' , , , , , , , , . , , , ' , ,10.2
Saki)' PrecautiOns and Programs"""",.""." ,2.3,5,10,1
Sanlples, Definition of ,."""""""".,,"""'" ,4.12.3
Sample5, Shop Drawings, Product Data and",., ,23,17, 23,18.
4.2,4.12
Samples at the Site, Documents and"" ",' ,"',',"" ,4.11
Schedule, Contractor's Construction"""""""".,., ,4,10
Schedule, Project Construction, ",",',""",","',' ,4,10
Schedule 01 \'a!ues .""",.""""",.."""".".,,9,2
Separate Contracts and Contractors"" ,4,14.2,6,11,3,6,13,1,2
Shop Drawings, Definition """".,.,,',' , , , , ' , , , ,4.12,1
Shop Dra\\ings, Product Data and San'ples "'," ,2317,
2318, -1 2. .l.12
Slie, L,e of """",."""".,," ,." ,4.13,62,1
Site In,pections """"." ,1,22,2.3.4,23.21,7,7,98,1,9,9,1
Site \ Isils, ..'\rchitc-ct's ""."",'," ,2.3,4,2.3.6,239,7.71.
7.7,4,9,42,9.6.1,99,1
Special In,peCllon a~d Te'lIng ,'" ,."" ,2.3.16,77
Special Hazards Insurance, , ' , , ' , ' , , , " ' , , , ,113.5
Specifications""".""""", ,,1,1,1,12.4,13
Statutes 01 Llr:li~"tions """., "",., ,7,9,2.13.2.2,1327
Stopping the Work".""""", '" ,3.3, 9,71, 103. :-:,1
Stored .\1ater:als ","",'" ,6.2.1,9.,,2, 102.1.:? 11.3,1, 132,5
SUBCO~TRACTORS """""".""".",..,""",., ,5
Subcontractor<. Deimition of ", "',",',,",", ,5.1,1
Subcontractor<. Work by ,,""" ' ,124, 23,5, 4,3,1, .l 3,2
Subcortractual Relations ' ,5,3
Submittals,.","""""" ,1,3,2.318,410,4,12,52,1.52,3,
92,931,9,81,9.9,1,9.9,3
4 A201/CM--1980
AlA DOCUME....T A201CM. Gc....[,AL (0....DITI0....5 OF THE CC'IR.\CT FOR CO....'IRlC1IO....
CO'~-;::L'C110" ,\\:\"<-\C[.\,[,,\T [DI1\O--': . JL"[ 1900 EO:lIO'\,' . A\A'~ . tI.--19S0 . --:rE
.\\',,;:IC.'\'-; 1~5,lll'lE OF .-\RCHIHCT', 1~3) ....cl\' YORK ,AVE. '1\'.. \\.,~,HI'GTO'-;. D.C :".,'6
Subrogation, \Vaiver of ""..",.'.'",'.'",., '" ",11,3,6
Substantial Completion oj the Project, , , , . , . ,8,1.4, 9.8.3, 9,8.4,
9,9.4,9.9,5,9,9,6,13.2.1,13,2,2
Substantial Completion of the P'0)ect, Definition of .'". .8,1.4
Substantial Completion of the V.ork .,..,., ,2,3,21,8,1,1,8,1,3,
8,2,2,9.4,2,9.8,9,9.3,11,3,9
Substantial Completion of the \\'ork, Definition of . , . . , . . ,8,1.3
Substitution of Subcontractors, , ' , , , , . , . . , , , , , , , , ,5,2,3, 5,2.4
Substitution of the Architect""""".....,."",." ,2,323
Substitution of the Construction .\.Ianager ",.',,'.... . .2,3,23
Substitutions of ,\Iaterials ""..".'""""",., .4,5, 12.1.4
Sub-subcontractors, Definition 01 ",.....,'....,.."..' .5,1,2
Subsurface Conditions.""""....,........,....", .12,1,1
Successors and Assigns."""""",.,.,."",.".,.,. ,7,2
Supervision and Construction Procedures. . . , . , ' , , .1.2.4, 2.3,:;,
4,3,4.4,10
Superintendent, Contractor's"..""..".".".,. ,4,9,10,2.6
Surety, Consent of ""'.,.,."."",,,.'.....'. ,9,9,2,9,9.3
Surveys, , , ' . ' , , , , , , , , , , , , , , , ., ' , , , , , , . . . , , ,. , ,3,2,2, 4,18,)
Taxes .""",.""."""..""",..""",."......,4,6
Termination by the Contractor,., , , , , , , , . , , , , , , , , , . , , . ,14,1
Termination by the O\\ner .""""",.,."""..'"" .14,2
Termination of the ,Architect""",.",.",."""" ,2,3,2)
Termination of the Construction \\anager ,."""", , . ,2,),23
TERMINATION OF THE CONTRACT, , , . , , , . . . , " . . . . , , , . .14
Tests, , , , , , , , , , , , , , , , ., , , , . ,. " . , , . , ,2,3,16, 4.3,3, 7.7, 9.4,2
TIME"",."""" "'" '" ""....".,.....,.'"".,. ,8
Time, Definition of ,.",.,.,."",'..,."""",...", ,8,1
Time, Delays and Extensions oj "",,'.' ,8,3,12,1,12,3,13,2,/
Time limits, Specific..",.,....,.. ,3.4,4,10,7,9,2,8.2,8,3,2,
8,3,3,9,2,93.1,9.4,1,9,5,1,9.7,11,1.4,
11,3,8,12,2,12.3,1,13,2,2,13.2.7,14,1,14,2.1
Title to Work""."""...."".",.""."." 9,3,2, 9,3.3
UNCOVERING AND CORRECTION OF WORK,.. . , . , . , . . . ,13
Uncovering of Work, , . , , , , , . , . , , . , , , , ,. , " , . .. ., , , " ,13,1
Unforseen Conditions. . , . , , . . . . . . , , , , , , , , , ., , . . , ,8,),1, 12,2
Unit Prices, , . , . , , . , . ' , , . , , . , . . , , . , . , , " , . . .12,1.3,2, 12,1,5
Use of Documents, , . , , , . ' . . , , . , . . , , , , " . " , . .1,3, 3,2,5, 5,3
Use of Site. . . . . , , , . , , . , , . , , , . , . . , .. , , . , ,. , . . , , ,4,13, 6,2.1
Values, Schedule of ".' . , , , . , . , . . . , , . . . , , . , , , , . . . , . . . . ,9,2
Waiver of Claims by the Contractor", ,;,6.2, 83.2, 9.9,5, 11,3,6
Waiver of Claims by the Owner,.,.. ,7.6,2,9,9.4,11.3,6,11.4.1
Waiver of liens, , , , . . . , , , . . , , . , , , . , , , , , , , , . , , , , . , . , . .9,9,2
Warranty and \Varranties ",,'., , , , , , , ,2.3,21, 4,5, 9.3.3, 9.8,4,
9,9.4, 13.2.2, 13.2.7
"'/eather Delays. . , , , , , . , . , . , , , , , . . , , , , , , , . , , . . , , , , , . .8,3,1
\Vords, Recognized ,\Ieaning of".,.""".,."""", .1,2,3
Work, Definition of """""...."."",......"", .1,1,)
WORK BY OWNER OR BY SEPARATE CONTRACTORS,.,... ,6
\.....ritten Consent".."", ,2,322,4,14,2,7.2,7,6.2,98.1,9,9,)
\".'ritten Interpretations"".""",.",.. .1.1,1,2.3.11,12,3,2
Written :--':otice ,."" ,2.3,11,2,3,15,4,2,4.7.3,4,7,4,4,9,4,12,6,
4,12.7,52,1,7,3,7.4,7,7,2,7,9,2,8,1.2,8,3,2,8,3.3,9.4,1,
9,6,1,9.7,9,9,1,10,26,11,1.4,11,3,1,11,3.5,11,3.7,
11.3,8,12,2,12.3,1322,13.2,5,14
\".'ritten Orders"."",.".",." ,3,3,4,9,12,1.4,12.4,1,13.1
AlA DOCUM[NT A201.CM . G['E,~, CO'DIIIO~S Of lHE CO~lRACl fOR CO~SlRLCIIOi';
CO~Sl RUClIOi'; ,\\,",'-.\G[\',c-":T [ClI':J'- . JU~[ 1980 [DITION . ,'"'fA'" . IS 1980 . THE
A,\\ERICA,>'; I'-SllllJH Of ,,",,CHIHe,; 1~33 ~[w YORK AVE.. S.W. WASHINGlON. D.C ~0006
A201/CM-1980 5
;----_._~_._~._--------------,._._-------
1___~~N~~~AL CO\DITIONS OF THE
ARTICLE 1
CONTRACT DOCUMENTS
1.1 DHlNITIONS
1.1.1 THE CONTRACT DOCUME'TS
The Contract Documents consist of the Owner-Contractor
Agreement, the Conditions of the Contract (General, Sup-
plementary and other Conditions), the Drawings, the
Specifications, and all Addenda issued prior to and all
Modifications issued "iter execution of the Contract. A
,"dodification is (1) a \\ ritten amendment to the Contract
signed by both parties, (2) a Change Order, (3) a written
interpretation issued by the Architect pursuant to Sub-
paragraph 2,3,11, or (4) a written order for a minor
change in the Work issued by the Architect pursuant to
Paragraph 12.4, The Contract Documents do not include
Bidding Documents such as the Advertisement or Invita-
tion to Bid, the Instructions to Bidders, sample forms, the
Contractor's Bid or portions of Addenda relating to any
of the"e, or any other documents unless specifically enu-
merated in the O\'. ne-Contractor Agreement.
1.1.2 THE CONTR,'!'CT
The Contract Documents form the Contract for Construc-
tion. This Contract represents the entire and integrated
agreement between the parties hereto and supersedes all
prior negotiations, representations or agreements. either
written or oral. The Contract may be amended or modi-
fied only by a .\10dification as defined in Subparagraph
1,1,1, The Contract Documents shall not be cons trued to
create any contractual relationship of any kind between
the Architect and the Contractor. between the Construc-
tion Manager and the Contractor or between the Archi-
tect and the Construction \\an2zer. but the Architect and
the Construction M2n2,ger sr.a:: be entitled to perform-
ance of the obligations of the Contractor intended for
their benefit and to enforcemf':t thereof. Nothing con-
tained in the Contract Docume'1ts shall create an\' con-
tractual relationship bet\4een tl-.e Owner, the Co~struc-
tion Manager or the ."rchitect i:'ld any Subcontractor or
Sub-subcont ractor.
1.1.3 THE WORK
The Work comprises the completed construction required
of the Contractor bv the Con,'act Documents, and in-
cludes all labor nece~sary to p'cduce such construction,
and all materials and equipme:;t incorporated or to be
incorporated in such construction,
1.1.4 THE PROJECT
The Project, as defined in tne Owner-Contractor ,-\gree-
menl. is the total CO:l,truction of which the \\'ork per-
formed under the Contract Docvnents is a part.
1.2 EXECUTION, CORRElATIO\' A"iD INTENT
1.2.1 The Contract Document; shall be signed in not
less than quadruplicate by the O.\ner and the Contractor.
If either the 0\\ ner or the Contractor or both do not sign
the Conditions of the Contract Drawings, Specifications
-_.~--. ~-- ----l
CONTRACT FOR CONSTRUCTION i
---.J
or any of the other Contract Documents, the Architect
shall identify such Documents,
1.2.2 Execution of the Contract by the Contractor is a
representation that the Contractor has visited the site be-
come familiar with the local conditions under \\ hid~ the
\'Vork is to be performed, and has correlated personal
observations with the requirements of the Contr.,ct Docu-
ments.
1.2.3 The intent of the Contract Documents is to include
all items necessary for the proper execution and comple-
tion of the Work. The Contract Documents are comple-
mentary, and what is required by anyone shall be as
binding as if required by all. Work not covered in the
Contract Documents will not be requ;red unless it is con-
sislent therewith and is reasonably inferable therefrom as
being necessary to produce the intended results, Words
and abbreviations which have well-knO\\n technical or
trade meanings are used in the Contract Documents in
accordance with such recognized meanings,
1.2.4 The organization of the Specifications into divi-
sions, sections and articles, and the arrangement of Draw-
ings shall not control the Contractor in diViding the Work
among Subcontractors or in establishing the extent of
Work to be performed by any trade,
1.3 OWT'\ERSHIP AND USE OF DOCUMENTS
1.3.1 All Drawings, Specifications and copies thereof
furnished by the. Architect are and sh]1I remain the prop-
erty of the Architect. They are to be used onh 1\ ith re-
spect to this Project and are not to be used on 'any other
proJect. With the exception of one contract set for each
party to the Contract. such documents are to be returned
or suitably accounted for to the Architect on request at
the completion of the Work. Submi'-5ion or distribution
10 meet official regulatory requirements or for cl:~er pur-
poses In connection with the Project is not to be con-
strued as publication in derogation of the Architect's
common law copyrisht or other resen ed ri?,hts,
ARTiClE 2
ADMINISTRATION OF THE CO\'TRACT
2.1 THE ARCHITECT
2.1.1 The Architect is the per~on lawfulh' licensed to
pr~ctice architecture, or an entity lawfullv practicing Jr-
dlllecture, Identified as such in the 01\ ner-Contractor
J-\greement. The term Architect means the Architect or
the Architect.s authorized representative,
2.2 THE CONSTRUCTION MANAGER
2.2.1, The Construction ,,"'1anager is the person or entity
Identified as such in the Owner-Contractor Ag:eement.
The term Construction Manager means the Construction
Manager or the Construction .\\.mager's a:.;:horized
rep resen 1.1 tive,
2.3 ADMIT'\ISTRA TION OF THE CONTRACT
2,3.1 The Architect and the Construction .\1anager will
ArA DOCL:\IENT AlOI.CM . G['-[RA~ CC..DITIO,NS Of THE CC,-,RACT fOR CONSTRUCTION
CO"STRUCTION MA"AGE \',["T ED:,IO'" . JUNE 1980 EDITIC... . A1A~ . @ 1980 . THE
\\\[RICA" I"STfTUTE Of "RCHITfCTS. 1-0; 'EW YORK AVE., ... W, 1\'ASHi"GTON. DC 2()()()1;
A201/C\1 ~ 1980 6
pro\ Ide ;,aminiqr.1tion of the C-:::ntract a~ he~(:in?fter
descibed.
2,3,2 The /\,chltect and the Co,--"'uction M?nabE-~ will
be the O\\ner's reprcsentatl\es c_'ng construction and
until final payment to all contrac:Jrs is due, The ,",,'chi-
tect and the Comtruction J'~onage~ will Jd\i~e and con-
sult \\ ith the Owner. All i<l,truc::::ns to the Cont~actor
shall be for\'.arded through the Construction ,'v\anager,
The ,Architect and the ConstruC1Jn Manager will ha\e
authoflt\. to .,ct on behalf of the 0,., :ler only to the extent
pro\'ided In the Contract Docun-,,:lts, unless other\\ise
modified bv \\ ritlen instrument in accordance with Sub-
paragraph 2.3,22,
2.3,3 The Comtruction Manager \\ ill determine in fen-
eral that the Work of the Contrac:or is being performed
in accordance with the Contract Cocuments, and will en-
dea\'or to guard the Owner against defects and deficien-
cie~ in the Work of the ContractOr.
2.3.4 The Architect will \'isit the site at inter\'als appro-
priate to the stage of constructiO:l to become generally
familiar with the progress and qUe;ity of the \\'ork and to
determine in general if the \\'ork is proceeding in accord-
"nce with the Contract Documents, However, the Archi-
tect will not be required to mcke exhausti\'e or con-
tinuous on,<ite inspections to check the quality or quan-
tity of the \\'ork, On the basis of on.site obser\'ations as
an architect, the Architect will kHp the Owner informed
of the progress of the \"'ork, and \\ ill endeavor to guard
the Owner against defects and ce:'iciencies in the \\'ork
of the Contr.,ctor,
2.3.5 Neither the ,"rchitect nor .he Construction .\1an-
ager will be responsible for or he'.e control or charge of
construction mean" methods, tec!--lniques, sequences or
procedures, or for safety preca~:,ons and programs in
connection with the Work, and ~.either will be respon-
sible for the Contractor's failure 10 carry out the \\'ork in
accordance with the Contract Documents, ~either the
:\rchitect nor the Construction '''\anager will be respon-
sible for or ha\'e control or chart:c o\er the acts or omis-
,iom of the Contractor. Subcon:-actors, or any of their
agent, or employees, or any othe' "ersons performing an\'
of the Work,
2.3.6 The Architect and the Co.'truction ,\lanager shall
at all times ha\'e access to the \\'ork whereH:r it ic in
preparation and progress, The C~,;.lfac\Or Sh,1!1 p'O\ ide
faciLties for ,uch access "a that the Architect Jnd the
Conctructiofl \\,',n2:;er ma\' perfc:'l their func::on~ under
the Contract Docuf',entc,
2.3.7 The Construction Manager will schedule and coor-
dinate the Work of all contracto', on the Project includ-
Ing their uce of the site, The Cc"truction ,""nager \..ill
keep the Contractor informed 01 :'le Project Construction
Schedule to enable the Contrac:or to plan and perform
the Work properly,
2,3,8 The Construction ,"~anage; will re\'ie\\ all A;,plica-
:ions for Pa\ ment bv the Contractor, including final pay-
ment, and ;\ill J5Sc'mble them '.., ith similar applications
from other contractors on the r'oiect into a cOf"'1bined
Project App!ication for Pa\ men!. The Constrcction \'",n-
ager will then make recommer:'2tions to tr,e ,";chitect
for ccrtification for payment.
2.3.9 Based on the Architect's cbservations, the 'ecom-
mendations of the Construction ;\\.lnager and an e\'alua-
lion of the Project Application for Payn.cnt, the Architect
will determine the amount owing to the Contl"ctor and
will issue a Project Certiflc"te for Pd\ ment inc()lporatin~
cuch amount, as provided in Paragraph 9.4,
2,3.10 The Architect will be the interpreter of the re-
qUirements of the Contract Docu;nents and the judge of
the performance thereunder by both the Owner and the
Contractor,
2.3.11 The Architect will render interpretations neces-
sary for the proper execution or progress of the \Vork,
wdh reasonable promptness Jnd in accordance with
agreed upon lime limits, Either party to the Contract may
make wrilten request to the Architect for such interpreta-
tions,
2.3.12 Claims, disputes and other matters in question
between the Contractor and the Owner relating to the
execution or progress of the \\lork or the interpretation
of the Contract Documents shall be referred initially to
the Architect for decision, After consultation with the
Construction !\1anager, the Architect will render a deci-
sion in writing within a reasonable time,
2,3.13 All interpretations and decisions of the Architect
shall be consistent with the intent of and reasonably in-
ferable from the Contract Documents and will be in writ-
ing or in graphic form, In this capacity as interpreter and
judge, the Architect will endea\'or to secure faithful per-
formance by both the Owner and the Contractor, will not
show partiality to either, and will not be liable for the
reoult of any interpretation or decision rendered in good
faith in such capacity.
2.3.14 The Architect's decisions in matters relating to
artistic effect will be final if consistent with the intent 0
the Contract Documents.
2.3.15 Any claim, dispute or other matter in question
bet\\een the Contractor and the Owner referred to the
Architect through the Con,truction ,".1anager, except those
relating to artistic effect as provided in SubparagrJph
2,3,14 and those which ha\'e been \\ai\'ed by the making
or acceptance of final payment .10 provided in Subpara-
graphs 9,9.4 through 9,9,0, inclusi\e, <hJII be subject to
arbitration upon the written demand of either party,
Ho\\e\'er. no demand for arbitration of any such claim,
diopute or other matter may be made until the earlier of
(1) the date on \\ hich the Architect has rendered a \\Iit-
ten decision, or i2) the tenth day after the parties ha\e
precented their e'. idence to the ,-\rchitect or ha..e been
gi\(Cn a rea'-onable Oppoltunlt) to clo '0, If the ,-\rchiteet
has not rendered a written deCISion by that dale, When
<uch a written deci,ion of the Architect states (1) that the
decision is final but subject to appeal. and (2) that am
demand for arbitration of a claim, di<pute or other m"tler
COlered bv such decision must be m.lde within thirtv da\ s
aiter the date on which the part\' mcking the demand re-
cei\'es the written decision, failure to demand Jrbitration
within o?id thirty day period will result in the /\rchitect's
deci,ion becoming final and binding upon the Owner
and the Contractor, If the Architect renders a decision
after arbitration proceedings have been initiJted. cuch
decision rT\JV be entered JS evidence but \\ill not super-
sede any arbitration proceedings unless the deci,ion is
acceptable to all parties concerned
7 A201/CM -1980
~IA DOCl'.\\EST A2011C,\\ . GE"'ERAl CO-":DITIO"'S OF THE CO-":TR-\CT FOR CO",STRL'CTIO'
CO"ElCTIO~ MA~AGE\\EI"T EDITIO~ . jL'~E 1980 EDITIO~ . AlA'!' . I[; 1980 . THE
-\\'c;,~c',-": I-":SIITUlE OF ARcHlllels, 1;3) o.;E\\' YORK A\'E, -..:"', \'.ASHI-..;CTO"" D.C COCiO<>
\Vl ,i:.->~lNr, ~Jr''',::-~,; ';-:' p~'1 '~,.).:C::-'.
.~, L ~ r.OL:--Jrigl-,112'.'!~ ;i~,j ~~: ~ I,--,~;;-" tr If-gal ~',F '~';;. C-u~il,n
2.3,16 The Architect will ha\e 2:.,:corit\ to reect Work
\\ hlcn does not conform to the C~~:'.,ct Docur--::'1!S ~,nd
to 'lqulre 'peclal in'pcction or te<L"1i', but.\ ill '2;';e <uch
action only aiter con"ultation with :!--:e Con51rucon ",an-
ager, Subject to re\'iew by the Arc~;,:ect, the Co:--,truction
'\'an.,ger will ha\e the authori1\ to reject \\'c~ \\hich
doe, not conform to the Contract Documents. \', hc-never,
in the Construction Manager's op:"':lon, :t IS CO:1' cered
necessary or advisable for the im;::ementction or :f-,e in-
tent of the Contract Documents. the COnQruc1 0'1 '\an-
al;er \\i11 ha\'e authority to require <pecial inspection or
:;qing of the Work in accordance with Subparagraph
;-,...,2 whether or not such Work be then iabricated, in-
stalled or completed, The foregoing authority oi the Con-
struction Manager will be subject to the pro'. isions of
Subparagraphs 2,3,10 through 2,3,16. inclusive, with re-
spect to interpretations and decisions of the ,-\rchitect.
However, neither the Architect's nor the Construction
'''~anager's authority to act under this Subparagraph 2.3,16,
nor any decision made by them in good faith either to
exercise or not to e~ercise such authori1\' shall gi\'e rise
to an\' duty or responsibility of the Architect or the Con-
struction Manager to the Contractor. am' Subcontractor,
an\' of their agents or erllployees, or an\' other person
performing any of the Work,
2.3.17 The Construction Manager will recei\e irom the
Contractor and review all Shop D:J\\ing<, ProGuct Data
and Samples, coordinate them \\ i:t: ,niormation contained
in related documents, and transmit to the ,-\rch:~ect those
recommended for approval.
2.3.18 The Architect will revie" and appro\e or take
other appropriate action upon the Contractor'S ,ubmittals
such as Shop Drawings, Product Data and San-pies, but
O'1I\' far conformance \\ith the ce,ign concept of the
Work and the information given in the Contr2ct Docu-
ments, Such action shall be taken \" ith reasonJbLe prompt-
ness so as to cause no delay, The Architect's 2:;:;ro\al of
a speciiic item shall not indicate 2;:,proval of an as<embly
of which the item is a component
2,3.19 Following consultation ,'. :th the Cc'c'truction
,"anager, the Architect \\ill take 2ppropriate 2clion on
Change Orders in accordance \\,t!-o ,-\rticle 12, 2nd will
ha\e authority to order minor c~2nges ''1 the Work as
pro\ided in Subparagraph 12.4.1,
2.3.20 The Construction \~an2[er ,\ill mainl2'1 at the
Proiect site one record copv at 2; Con:'acts J'a\\ ings,
SpHiiicJtions, Addenda, Change Orders 2nd o:'-:er ."'odi-
iications pertaining to the Project. in pod c-der and
marked currently to record all cf-,ange, m2ee during
construction, and apprO\'ed Sr: p Ora". ,ng, Product
Data and Samples, These ,hall be a\ailabie to :~e .-\rchi-
teet and the Contractor, Jnd sha:: be de!i\ered to the
Arch:tect for the Owner upon co:-\p'etion of t~2 Project.
2.3,21 The Construction \1anat:er \\ ill 2;,i,t :ne Archi-
tect in conducting inspect "ns to determine the dates of
Sub'-!.lntial Completion and iina: completion, 2nd will
recei\e and fOf\\ard to the Owner 'or the Owner's re\iew
\\ rillen warranties and related docr:-:ents 'eql,;;'ed b\ the
Cortract and assembled bv the C::<traClor The ;rchitect
will issue a final Project Certific2te ior Payrr,ent upon
compliance with the requirement, c: Paragraph 9,9,
2.3.22 The duties, re<pansibilities and limitatio'1; of
authority of the Architect and the Comtructlon '\\"'1.;ger
as the Owner's repre,entati\'es during construction ';0' set
forth in the Contract Documents, \\ill not be modl;'led or
extended withaut written consent oi the 0\\ ner, the Con-
tractor, the ,-\rchitect and the Construction ,\\., 'lager,
which consent shall not be unreasonably withheld, Failure
of the Contractor to respond within ten days to a \\ rillen
request shall constitute consent by the Contractor.
2.3.23 In case of the termination of the emplo~ ment of
the Architect or the Construction M.1flager, the O\\ner
shall appoint an architect or a construction manager
against whom the Contractor makes no reasonable objec-
tion and whose status under the Contract Docu!Tlents
shall be that of the former architect or construction man-
ager, respectively, Any dispute in connection with such
appointments shall be subject to arbitration,
ARTICLE 3
OWNER
3.1 DEFINITION
3.1.1 The Owner is the person or entity identified as
such in the Owner-Contractor Agreement. The term
Owner means the Owner or the Owner's authorized
representative.
3.2 INFORMATION AND SERVICES REQUIRED OF
THE OWNER
3.2.1 The Owner shall, at the request of the Contractor,
at the time of execution of the Owner-Contractor Agree-
ment furnish to the Contractor reasonable evidence that
the Owner has made financial arrangements to fulfill the
Owner's obligations under the Contract. Unles; such
rea,onable evidence is furnished, the Contractor is not
required to execute the Owner-Contractor Agreement or
to commence the \Vork,
3.2.2 The Owner shall furnish all sur\'eys describ:"~ the
physical char,lcteristics, legal limitations and utili1\ loca-
tions for the site of the Project, and a legal descript 'In of
the site,
3,2,3 Except as provided in Subparagraph 4,/". the
Owner shall secure and pay for necessary approvals. ease-
ments, assessments and charges required for the construc-
tion, use or occupancy of permanent structures C~ for
permanent changes in exi,ting facilities,
3.2.4 Information or services under the O\\ner', c~trol
shall be furnished by the Owner with reasonable V'::11pt-
ness to avoid dela\ in the orderly progre<s of the \'.:rk,
3,2,5 Unless otherwise provided in the Contract :Jocu-
ments, the Contractor will be iurnished, i:ee of c~ -,rge,
all copies oi Drawings and Speciiicatiom lusonabi.. nec-
e"MY for the execution of the Work,
3,2.6 The Owner shall forward all instructions :0 the
Contractor through the Construction ,"~anager, with <''11ul-
taneous notification to the Architect.
3.2.7 The foregoing are in addition to other dutie' and
responsibilities or the 0\\ ner enumerated herein a - j es-
pecially those in respect to \\'ork B~' 0\\ ner or B\ Sepa-
rate Contractors, Payments and Completion, and i~sur-
ance in Articles 6, 9 and 11. respecti\'ely,
AI~ DOCUMP,T A201iCM . GESERAl CO'-:-0'-5 ,y T;-!E :J'~~',CT rOR CONSJRUCTIO,"o:
CO:--',TRUCTIOS MASAGEMENT EDITIOS . ;L"o:E 1",.:, ED;~ os . ,1,1,1,'" . @ 1980 . THEs,~'1ERICAS I'STITUTE OF ARCHITECTS, 1;:S '-t\\' YOR, A\'E. '- W. \\ASHI"o:GTON, D.C 20006
A201/CM -1980 8
3.3 O\'l"ER'S RIGHT TO STOP THE WORK
),3.1 If the Contractor fails to correct defective V/ork as
required b\ Paragraph 13,2, or pusistently fails to carry
out the \\'ork in accordance \\ dh the Contract Docu-
ments, the Owner, by a written order signed personally or
by an agent specifically so empowered by the Owner in
writing. Olav order the Contractor to stop the \-Vork, or
any portion thereof, until the cause for such order has
been eliminated; however. this right of the Owner to stop
the Work shell not give rise to any duty on the part of the
Owner to exercise this right for the benefit of the Con-
tractor or any other person or entity, except to the extent
required by Subparagraph 6,1,3,
3.4 O\'l'SER'S RIGHT TO CARRY OUT THE WORK
3.4.1. If the Contractor defaults or neglects to carry out
the Vvork in accordance with the Contract Documents,
and fails \\ i:hin seven days after receipt of written notice
from the Owner to commence and continue correction of
such default or neglect with diligence and promptness,
the O\\ner may, afler seven days following receipt by the
Contractor of an additional written notice and without
prejudice to any other remedy the Owner may have,
make good such deficiencies, In such case an appropriate
Change O'der shall be issued deducting from the pay-
ments then or thereafter due the Contractor the cost of
correcting such deficiencies, including compensation for
the Architect's and the Construction Manager's additional
services !Tade necessary by such default, neglect or fail-
ure, Such action by the Owner and the amount charged
to the Contractor are both subject to the prior approval
of the Architect, after consultation with the Construction
,\1anager, Ii the payments then or thereafter due the Con-
tractor are not sufiicient to cover such amount, the Con-
tractor sha:i pa\' the difference to the Owner.
ARTICLE 4
CONTRACTOR
4.1 DEFI"1TI0N
4.1.1 The Contractor is the person or entity identified as
such in the O\\ner-Contractor Agreement. The term Con-
tractor me-2m the Contractor or the Contractor's author-
ized representative,
4.2 REVIEW OF CONTRACT DOCUMENTS
4,2.1 n,e Con:ractor -hall carefully study and compare
the Con\cc.ct Dccuments and <hal! at once report to the
Arc!'iltE'ct ~r~d :~.( C(.>n~:iuc',ion \~~:nJ.ger an,:" error, incon-
,i<\enc\ c~ o:-;-""iol1 that ma\ be discO\ered, The Con-
tractor'shall not be liable to t'he Owner. the Architect or
the Con-t~uct!on Manager for anv oamage resulting from
any such e'IO", inconsistencies or omis<ions in the Con-
triict Docun'ler,\-, The Contractor shall perform no portion
of the \\('k 2.t any time without Contract Documents or,
\\he-re r.oc;,;i;ed, approved Shop Dra\\ings, Product Data
or S"mple- for -,Ich portion of the \Vork,
4,3 SL:PER\'ISION AND CONSTRUCTION
PROCEDL'RES
4,3.1 T~,e Contractor -hall supervise "nd direct the
Work, u- ng the Contractor's best skill and attention, The
Contracto, ~shal! be solely responsible for all construction
means, methoc-, techniques. sequences and procedures:
and shall coordinate all portions of the Work under the
Contract, subject to the overall coordination of the Con-
<iruction \t;lnager.
4.3,2 The Contractor shall be re"ponsible to the Own_
for the acts and omissions of the Contractor's employees,
Subcontractors and their agents and employees, and any
other persons performing any of the \Vork under a con-
tract with the Contractor,
4.3.3 The Contractor shall not be relieved from the
Contractor's obligations to perform the Work in accord-
ance With the Contract Documents either by the activities
or duties of the Construction .'tanager or the Architect
in their administration of the Contract, or by inspections,
tests or appro\'als required or performed under Paragraph
7,7 by persons other than the Contractor,
4.4 LABOR AND ."~ATERIALS
4.4.1 Unless otherwise provided in the Contract Docu-
ments, the Contractor shall provide and pay for all labor,
materials, equipment, tools, construction equipment and
machinery, water, heat, utilities, transportation, and other
facilities and services necessary for the proper e>:ecution
and con,pletion of the Work, whether temporary or per-
manent and whether or not incorporided or to be incor-
porated in the Work,
4.4,2 The Contractor shall at all tinles enforce strict dis-
cipline and good order among the Contractor's em-
ployees and shall not employ on the Work any unfit per-
"on or anyone not skilled in the task assigned them,
4.5 WARRANTY
4.5.1 The Contractor warrants to the Owner, the Archi-
tect and the Construction \tanager that all rnaterials and
equipn;ent furnished under this Contract will be new I
less otherwise specified, and that ,111 Work will be of gol..
quality, free from faults "nd defects "nd in conformance
with the Contract Documents, All Work not conforming
to these requirements. including ~ub,titutions not prop-
erly approved and authorized, may be considered defec-
tive, Ii required by the Architect or the Construction Man-
ager, the Contr2ctor shall furnish ,,,ti,factory evidence as
to the kind "nd quality of materials ;,nd equipment. This
warranty is not limited b\ the pro\ i<ions of Paragraph
13,2,
4,6 TAXES
4,6.1 The Contractor sha!! pay all 'ales, consumer, use
and other <imilar taxes for the \\'ork or portions thereof
pro\icec b tre Cc'ntr2ctc' 1\ hicl, ,C't' il'!-!,1!lv en,lcted at
Ihe lime bids are rcce:\ed, \\hether c: not \ct efiecti\e,
4.7 PER,'.mS, FEES ASD 1'0TlCES
4.7.1 L:nless othu\\ ise pro\ ided in the Contract Docu-
ments. the O\\ner shall stcure and pa\' for the building
permit and the Contractor sh311 <ec'Jce "nd pay for all
other permits and govcnr.cental fees, liceme' and in-pec-
tions necessary for the proper execu,lon Jnd completion
of the \\'ork \\hich are customarily secured after execu-
tion oi the Contract ar,d \\ hich are kgallv required at the
lime bid, are received,
4,7.2 The Contractor sha!1 give all ".,tices and comply
\\'ilh ail laws, ordinances, rules, re;l!lations and lawful
orders oi anv public "Ulhoritv bearing on the perform-
ance of the Work,
9 A201CM -1980
ALA DOCUM[',T A201!CM . GE"ER\l CO"DI1IC", Of THE CO"',~CT FOR CO',STRUC,,_ '
CO'-SlRlOC-": \\A"AGE.",E'-,T EDiTlO'.: . Jl": rc',: [D!TIO" . .\!,\~ . CS'1980 . THE
,,\\[Rl(-\' i'~-11UTE. OF f\~:CHI1tC1S. 1:--j5 .....E\\ ~Or..... ~\'L, '\;\\ \\ ,-\~H!'C10~'. D.C. :'OCfll'
4,7.3 It is not the responsibility of the Contractor to
make certain that the Contract Documents are in accord-
ance with iJpplicJble laws, statutes, building codes and
regulations, If the Contractor ob<ef\es that any of the
Cuntract Documents arc at variance therewith in any re-
spect, the Contractor shall promptly notify the Architect
and the Construction Manager in writing, and any neces-
sary changes shall be accomplished by appropriate
,'~odification,
4.7.4 If the Contractor performs any Work knowing it
to be contrary to such laws, ordinances, rules and regula-
tions, and without such notice to the Architect and the
Construction I\~anager, the Contractor shall assume full
responsibility therefor and shall bear all costs atlributable
thereto.
4.8 AllOWANCES
4.8.1 The Contractor shall include in the Contract Sum
all allowances stated in the Contract Documents, Items
covered by these allowances shall be supplied for such
amounts and by such persons as the Construction Man-
ager may direct, but the Contractor will not be required
to employ persons against whom the Contractor makes a
reasonable obj2ction.
4.8.2 Unless othef\vise provided in the Contract Docu-
ments:
,1 these allowances shall co\'er the cost to the
Contractor, less any applicable trade discount,
of the materials and equipment required by the
allowance, delivered at the site, and all appli-
cable taxes;
.2 the Contractor's costs for unloading and han-
dling on the site, labor. installation costs, O\er-
head, profit and other expenses contemplated
for the original allowance shall be included in
the Contract Sum and not in the allo\\Gnce;
.3 I\hene\er the cost is more or less than the
allowance, the Contract 5:;m shall be adjusted
accordingly by Change Order, the amount of
1\ hich will recognize ch"f',ges, if anv, in han-
dling costs on the site, 'Gbor. installation costs,
overhead, profit and other expenses,
4.9 SUPERINlESDENT
4.9.1 The Contractor shall empJov a competent ouperin-
tendent and necessary a"istants who shall be ir, attend-
ance at tre Proiect site curing the p'ogre,< 01 t"e \\'ork,
The supe:i'l:er,de'lt shall 'epresent :he Contractc' and all
communications siven to the super;ntendent srall be as
binding as if given to the Contractor, Important commu-
nications shall be confirr.led in \\ ::ting, Other cc'mmuni-
cations shall be ,0 confi:rned on I'. r!\ten request in each
case.
4.10 COSTRACTOR'S CO-";STRUCTIO~ SCHEDULE
4.10.1 The Contr,<ctor, irnmediatelv- after being a\\'arded
the Contract, sh.:!!l prep2re and submit for the Construc-
tion ,\\2n;:.ger's 2pprO\al a Contractor', Co:;-truction
Schedule for the Work 1\ hich sha'! prol ide fo: expedi-
tious and practicable execution 0: :I--,e \",'ork, T~; ;che.d-
ule shall be coordinated by the Construction \\Gnager
1\ ith the Project Construction Schedule, The Co~,:ractor's
Construction Schedule shall be revised as required by the
conditions of the Work and the Project, subject to the
Construction ''''~anager's appro\'a!.
4.11 DOCUMESTS AND SAMPLES AT THE SIlE
4.11.1 The Contractor shall maintain at the Project site,
on a current basis, one record copy of all Dral\ings,
Specifications, .-\ddenda, Change Orders and other Modi-
fications, in good order and marked currently to record
all changes made during construction, and approved Shop
Drawings, Product Data and Samples, These shall be
available to the Architect and the Construction "~anager.
The Contractor shall advise the Construction ,...~anager on
a current basis of all changes in the \'\Iork made during
construction,
4.12 SHOP DRAWINGS, PRODUCT DATA AND
SAMPLES
4.12.1 Shop Drawings are drawings, diagrams, schedules
and other data specially prepared for the Work by the
Contractor or any Subcontractor, manufacturer, supplier
or distributor to illustrate some portion of the Work.
4.12.2 Product Data are illustrations, standard schedules,
performance charts, instructions, brochures, diagrams and
olher information furnished by the Contractor to illustrate
a material, product or system for some portion of the
\'\Iork,
4.12.3 Samples are physical examples which illustrate
materials, equipment or workmanship, and establish
standards by 1\ hich the Work will be judged,
4.12.4 The Contractor shall prepare, revie\\', approve and
submit through the Construction Manager, with reason-
able promptness and in such sequence as to cause no de-
lay in the \\'ork or in the work of the Owner or any sepa-
rate contrJetor. all Shop Drawings, Product Data and
Samples required by the Contract Documents, The Con-
tractor shall cooperate with the Construction "~anager in
the Construction ,"'-1anager's coordination of the Contrac-
tor's Shop Drawings, Product Data and Samples with
those of other ,eparate contractors,
4,12.5 By preparing. apprm ing and submitting Shop
Drawings, Product Data and Samples, the Contractor rep-
resents that the Contractor has determined and verified
all materials, field measurements and field construction
criteria related thereto, or I\ill do so with reasonable
promptness, and has checked and coordinated the infor-
mation contained \\ ithin such submittals with the require-
ments of the Work, the Project and the Contract Docu-
ments,
4.12.6 The CO:1tractor shall not be relie\ed of re<ponsibil-
ity for anv de\ ration from the requirement, 01 the Con-
tract Documents bv the Architect's appro\;;1 of Shop
Drawings, Procuct Data or Samples under 5l;bparagraph
2,3,18, unless t"e Contractor has specificalk informed the
Architect and the Construction ,\\anager in 1\ riting of
such deviation at the time of submis<ion ,lnd the-\rchi-
teet has gi\ en \\ ritten appro\al to the specific de\ izdion,
The Contractor shall not be relieled from re,ponsibililv
for errors or onli<sions in the Shop Dr;;\\ ing" Produc't
Data or Samp:e< bv the ,-\rchitect'< appro\JI of them,
4.12.7 The CO'llr"ctor ,hall direct 'peciiic attention. in
writing or on re<ubmitted Shop Drawings. pcoduct Data
or Samples, to revisions other than those ~eques:ed bv the
Architect on pcevious submittals, '
AlA DOCU\\P,T A2ulCM . Gl'cRAL CO'C -0'5 Uf THE c:" :RACT fOR CO,STRl.:cTIO'
CO,STRL'CiO, ,'I-\'\GEME:,-T EDITIOS . ;,--"E 103.) EDI~ C''-.; . AlA>!: . @1980 . THE
A'I[RIC.~' I'S1I1L'E OF ARCf-iiHCTS, 1'33 ,,\\, YO" .WE '1\ ,\\ASHI'GTO:--:, D.C 2(\()()-.
A201/CM -1980 10
4.12,8 ~o portion 01 tile \Vork requiring <ubmisc;oi', 01 a
Shop Or,11\ ing, rroduct 0.1ta or Sample shall be CDm-
r:wnced until the ~ubnli:t.ll has bc('n "l"i)[Oleo b\ the
-\'lhilect as prOI Ideo in SubpM,1gr.1ph 2,3,18, ,-\11 'uch
f',Hllons of the \Vork shJl1 be in Jccordance I\ith cp-
prol ed 'llbmittals,
4,13 USE OF SITE
4.13,1 The Contractor shJl1 confine operations at the site
10 areas permitted bl' law, oldinances, permits .ond the
Cont rael Documents, and shall not unreasonabl) ene um-
ber the site \\ Ith any materials or equipr:lent.
4,13,2 The Contr"ctor shall coordinate all of the Cor:::ac-
tor's operations with, and secure approval from, the Con-
<1ruction I\\anager before using am portion of the site.
4.14 CUTTING AND PATCHING OF WORK
4.14.1 The Contractor shall be responsible for all cutting,
filling or patching that may be required to complete the
\Vork or to make its sen'ral parts fit together proper\,
4.14,2 The Contractor shall not damage or end2:lge- any
portion of the \Vork or the work of the Owner or any
trpJfate contractors by cutting, patching or othe~wise
altering any work, or by exuvation, The Contr.octor shall
not cut or otherwise alter the work of the Owner 0- any
sepMate contractor except with the written consent c: the
Owner and of such separate contractor, The Conu~ctor
shall not unreaoonabll- withhold from the O\',ner 0- any
cepJrate contractor consent to cutting or other.\lse c:ter-
ing the'\\'ork,
4.15 ClEANIt-iG UP
4.15.1 The Contractor shall at all times keep the pref"'lises
free from accumulation of waste materials Of rU2,bish
caused by the Contr,lctor'S operations, At the CCllp'::.:ion
of the Work, the Cont:?ctor shall remme all the Co~:rac-
tor's waste m.,terials ~nd rubbish from and 2:'OU: the
Project as well as all the Contractor's tools, co~,stru.::lion
equipment, machinefl and surplus materials,
4,15.2 If the Contractor tarls to clean up at the co-.',ple-
tion of the \\'ork, the Owner mal do so as pre.. Ic,;'d in
Paragraph 3,4 and the co..t thereoi shall be cherted ::1 :he
Contractor.
4,16 CO '-.t\\U 0",; 'CAlIONS
4.16.1 The Ct :.tr.ictor ,\1;\11 forl\.irO .0]1 com:"~:,,,ic.<ons
to the Owner and the :\rchitect though the Co:"str~ :tion
\ \., nager,
4.17 ROYAllll5 A~D PAll 0",; 1 5
4.17.1 The Contractor shall pay all rOla:ties ~rd kense
fees, shall detend all cuits or claims for infrin;eme"lt of
any patent rights and <hall sale the O\" ner .one: the Con-
struction \\.,I1,,2er harmless from loss 011 accou;,: tr-:-'eot,
except that th; Oil ner, or the Construction .\',anatu as
the case mal' be, shall be responsible for all suc'- loss
1\ hen a p3fti~ular desi~n, process or the produe: ot ~ par-
ticular mJnufacturer or manufacturers is '-eleclte::: b.. 'uch
person or such person's agent. If the Contract:r, C' the
Construction \\,11".1[(" as the ca'-e may be, ha' reao:n to
bc!ie\'e that the de<isn, process or product selectee is an
infringement of .1 patent that pa:tv ,hall be :"op,: -o,ble
for such loss unless such Information is prompt". S' ,;:-n to
the others and "Iso to the Architect.
4,18 ''''DL\\'''FICA liON
4.18.1 To the fullest extent permitted bv law, the Con-
tractor ,ha!1 Indemnify and hold harmless the 0..\ ner, th
Architect. the Construction "~an,1ger, and their agents an,
employees from and against all claims, dam<1ges, losses
and expenses, including, but not limited to, attorneys'
fees arising out of or resulting from the performance of
the \Vork, provided that any such claim, d,lmage, loss or
expense (1) is attributable to bodily injury, sickness, dis-
ease or death, or to injury to or destruction of tangible
propert\' lother tbm the \Vork itself) inc iuding the loss of
use resulting therefrom, and (2) is caused in whole or in
part b\' any negligent act or omission oi the Contractor,
any Subcontractor, anyone dirrctly or indirectly employed
by any of them or anyone for whose acts an) of them
may be liable, regardless of whether or not it is caused
in part by a party indemnified hereur.der. Such obligation
shall not be con~trued to negate, abridge or otherwise
reduce any other right or obligation of indemnity which
would otherwise exist as to any party or person described
in this Paragraph 4,18,
4,18.2 In any and all claims against the Owner, the Archi-
tect, the Construction t\~anager or any at their agents or
emplo\ees by any employee of the Contractor, Jny Sub-
contractor, an)one directly or indirectly employed by any
of them or anyone for whose <1cts Jny at them may be
liable, the indemnificltion obligation under this Para-
graph ,U8 shall not be limited in any I\ay by an\' limita-
tion on the amount or type of damages, compen'ation or
benetits pay"ble by or for the Contractor or any Sub-
contractor under workers' or I\orkmen's compensation
acts, disability benefit acts or other emplolee benefit <1cts,
4.18,3 The obligations of the Contractor under this Para-
graph 4,18 shall not extend to the liability of the ,-\rchite
or the Construction Manager, their <1gents or employees,
a risi ng out of 1.1 i the prepa ration or apprOVJ I of ma ps,
dr<1l\ings, opinions, reports, surveys, Change Orders, de-
signs or specifications, or (2) the giling of or the iailure to
give direction~ or instructions by the -\rchitect or the
Construction .\1Jnager, their agents or cmplmees, pro-
vided such g:\ing or failure to gile is the prim"rv cause
of the injury or damage,
ARTiClE 5
SUBCONTRACTORS
5.1 DEfI~ITIOS
5.1,1 ,-\ Subcon~ractor is a pero')[) 01 t':ltity 1\ no has a
direct contract with the Contractor to perform any of the
\Vork .it t!.e site, The term Subcontractor means a Sub-
contractor or a Subcontractor's authorized representatil e,
The term Subcontractor does not include am separate
contractor or .om 'epMate contractor's <ubcontractors.
5,1,2 ,-\ Sub,<ubcontractor is a person or entil\ who has
a direct or indirect contract with <1 Subcontractor to per-
form 2n\' of the Work at the site, The term Sub.cubcon-
tr<1ctor means a Sub.subcontractor or an ,1Uthorilcd rep.
[esel1t"ti\e t!,ereo1.
5.2 A\\ ARD5 Of 5LJBCONTRAC15 :\~D OTHER
CO'TRAC1S FOR PORT 10"'5 or THE WORK
5.2,1 Unless otherwise required by the Contract Docu-
11 A201/CM --1980
'I~ [..,)CU~\E'iT A~Ol.'CM' GE...."'~ CO....:)ITIO....S Of THE CO....1R,~CT fO, CO....'l'LCli~
='~'''2--;:,z..CT10~ .\t';:--':AGE\',~"T E:J!7:0'\ . JL''\E j~80 EDITJOS . .'\i.-\'! . ,1;: ~93Q . THE
",',,0 ;:..\'-.. '....STITL IE OF ,~,CH:~,C" .,-" ....EII. 10RK A\'E, ....11', ,\ "'11....C10.... DC. 211:>:>0
'7 ~'f
ments or the Bidding Documents, the Contractor, as soon
as practicable after the award of the Contract, ,hall fur,
nish to the Comtruction Manager in writing lor review
by the Owner, the Architect and the Comtruction ,"Ian-
ager, the names of the persons or entities (including those
who are to furnish materials or equipment fabricated to
a special design) proposed for each of the principal por-
tions of the \\'ork, The Comtruction Manager will
promptly reply to the Contractor in writing stating
whether or not the Owner, the Architect or the Con-
struction Manager, after due investigation, has reasonable
objection to any such proposed person or entity. Failure
of the Construction Manager to reply promptly shall con-
stitute notice of no reasonable objection.
5.2.2 The Contractor shall not contract with any such
proposed person or entity to whom the Owner, the Ar-
chitect or the Construction "Ianager has made reasonable
objection under the provisions of Subparagraph 5,2,1, The
Contractor shall not be required to contract with anyone
10 whom the Contractor has a reasonable objection,
5.2.3 If the Owner, the Architect or the Construction
Manager has reasonable objection to any such proposed
person or entity, the Contractor shall submit a substitute
to whom the Owner, the Architect and the Construction
Manager have no reasonable objection, and the Contract
Sum shall be increased or decreased by the difference in
cost occasioned by such substitution and an appropriate
Change Order shall be issued; however, no increase in
the Contract Slim shall be allowed for any such substitu-
tion unless the Contractor has acted promptly and re-
sponsively in submitting names as required by Subpara-
graph 5,2,1,
5.2.4 The Contractor shall make no substitution for any
Subcontractor, person or entity previously selected if the
Owner, the Architect or the Construction Manager makes
reasonable objection to such substitution,
5.3 SUBCONTRACTlJAl RELATIONS
5.3.1 By an appropriate agreement, written where legally
required for validity, the Contractor shall require each
Subcontractor, to the extent of the Work to be performed
by the Subcontractor, to be bound to the Contractor by
the terms of the Con,rac\ Documents, and to assume to-
ward the Contractor all the obligations and re<ponsibili-
ties \\ hich the Contractor, by these Document~;, assumes
to\\ ard the Owner, t~e .'\rcnitect and the Construction
.\\anager, Said agreer:-ent ~h211 preser....e and protect the
right, of t~,e O\', nero the ,'\rd1itect and the Const:..:ction
.\~anager under the Contract Documents with respect to
the \\'ork to be performed by the Subcontractor so that
the subcontracting tt-:ereof \\ III not prejudice such rights,
and ,hall allow to the Subcontractor, unless specifically
pro\ided otherwise in the Contractor-Subcontractor
,Agreement. the benefit of all rights, remedies and redress
agai;'1'; the Contractor that the Contractor, by these Docu-
ments, has against t~e Owner, \\'here appropriate, the
Contractor ,hall requ:-e each Subcontractor to enler into
similar agreements \.,jth their Sub-subcontractor,. The
Contract;r shall make a\'ailable to each proposed Sub-
contractor, prior to ',he execution of the Subcontract,
copies of the Contract Documents to which the Subcon-
tractor will be bound by this Paragraph 5,3, and identify
to the Subcontractor any terms and conditions of the pro-
posed Subcontract which may be at variance with the
Contract Documents, Each Subcontractor shall similarly
make copies of such Documents available to their Sub-
subcontractors,
ARTIClE 6
WORK BY OWNER OR BY
SEPARATE CONTRACTORS
6.1 OWNER'S RIGHT TO PERFORM WORK Af'.;D TO
AWARD SEPARATE CONTRACTS
6.1.1 The Owner reserves the right to perform work re-
lated to the Project with the Owner's own forces, and to
award separate contracts in connection with other por-
tions of the Project or other work on the site under these
or similar Conditions of the Contract. If the Contractor
claims that delay, damage or additional cost is involved
because of such action by the Owner, the Contractor shall
make such claim as provided elsewhere in the Contract
Documents,
6.1.2 When separate contracts are awarded lor different
portions of the Project or other work on the site, the term
Contractor in the Contract Documents in each case shall
mean the Contractor who executes each separate Owner-
Contractor Agreement.
6.1.3 The Owner will provide for the coordination of the
work of the Owner's own forces and of each separate
contractor with the Work of the Contractor, who shall
cooperate therewith as provided in Paragraph 6,2.
6,2 MUTUAL RESPONSIBILITY
6.2.1 The Contractor shall afford the Owner, the Con-
struction Manager and separate contractors reasonable
opportunity for the introduction and storage of their ma-
terials and equipment and the execution of their work,
and shall connect and coordinate the Work with theirs
as required by the Contract Documents,
6.2.2 If any part of the Contractor's Work depends for
proper execution or results upon the work of the Owner
or any separate contractor, the Contractor shall, prior to
proceeding with the Work, promptly report to the Con-
struction Manager any apparent discrepancies or defects
in such other work that render it unsuitable for such
proper execution and results. Failure of the Contractor so
to report shall constitute an acceptance of the Owner's
or separate contractor's wo,k as lit and proper to receive
the \\'ork, except as to CCi<':ltS .... hich may subsequently
become apparent in such work by others,
6,2.3 Any costs caused by defective or ill-timed \vork
shall be borne by the party respor.'ible thereior,
6.2.4 Should the Contractor wrongfully cause damage to
the work or property of the Owner, or to other work or
property on the ;ite, the Contractor shall promptly rem-
edy such damage as prO\ided in Subparagraph 10,2.5,
6,2.5 Should the Contractor \\ rongfully delay or cause
damage to the work or property of any separate contrac-
lor, the Contractor shall, upon due notice. promptly at-
tempt to settle with such other contractor b\' agreement,
or otherwise to resoke the dispute, If such separate con-
tractor sues or initiates an arbitration proceeding against
the Owner on account of any delay or damage alleged to
have been caused by the Contractor, the Owner shall
AlA DOCUMENT A201CM . GE:--;ERAl CO,",01110:--;S OF THE CO....: ?,-\O FOR CO:--;S1 RUOION
CO~,STRUOIO", ,\IA:--;.AGE','ENT EDITION . JUNE 1980 EDITION . AIA@ . iD 1980 . THE
AMER:C.-\:--; 1....'TITL.1[ OF ',CHITEOS, 1735 :-.IE\\' YORK A\'E., "Iv.... WASHINGTO,:--;, o.c. 20006
A201/CM - 1980 12
notify the Contractor Ilho "h,,11 ce~end "uch voceedings
at the Owner's C\pen"e, and if c~v judgment or award
.:sainst the OIl ncr arises therd'c'11, the Contr2clor shall
payor <;atisfy it and <;hall rClmL:.;;rse the Olln('r for all
attorneys' fees and court or arb:ration cmts which the
OIl ncr ha<, incurred,
6.3 OWNER'S RIGHT TO ClEAN CP
(',3.1 If a dispute arises between the Contractor and
<;eparate contractor" a<; to their re<,ponsibility for cleaning
up as reqLJlred by Paragraph 4,1:;, the Owner may clean
up and charge the cost thereof to the contractors r('spon-
srble therefor as the Construct:o~ ,\1anager shall deter-
mine to be just.
ARTiClE 7
MISCEllANEOUS PROVISIONS
7.1 GOVERNING LAW
7.1.1 The Contract shall be gO\ened by the law of the
place where the Project is located,
7.2 sUCnSSORS AND ASSIGNS
7.2.1 The Owner and the Contractor, respectively, bind
them"elves, their partners, successors, assigns and legal
repre"entalives to the other part\ hereto and to the part-
ner", succes<;ors, a<"igns and legal representatives of such
other party with respect to all ce..enants, agreements and
obligations contained in the Cor,tract Documents, r--.;either
party to the Contract shall a"sign the Contract or sublet it
as a whole without the written coment of the other.
7.3 WRITTEN r-.;OTICE
7.3.1 Written notice shall be deemed to have been duly
served if delivered in person to the individual or mem-
ber of the firm or entity or to an officer of the corpora-
tion for whom it was intended, or if deli\ered at or sent
by registered or certified mail te the last business address
known to the party giving the notice,
7.4 ClAI"IS rOR DAMAGES
7.4.1 Should either party to the Contract suf1er injury or
d"rnage to person or proputy ~ec:;use of any act or omis-
sion of the other party or oi c:l)' of the other party's
employees, Jgents or others fer "1 ho"e acts such part\ is
legally liable. claim shall be [T,ade in I\riting to <uch
other part\ :,,'jthin a rea~onable :.-:1e after the iir<.t observ-
(: nee 01 ::-\.11. n I fl,1 iJ r~ 0~ (1,-i n1l1se.
7.5 PERfORMASCE BO~D A!,;D lABOR At-;D
MATERIAL PAYME~T BOSD
7,5,1 The Osner "hall hale '~e right to require the
Contractor to furni~h bonds CO\Cing the faithful perform-
ance of the Contract Jnd the p\ment of all obligations
ari.ing thereunder if and as res,_,red i:l the Bidding Doc-
un!t:nt< or the Contract Docun,E-'1ts,
7.6 RIGHTS AND REMEDIES
7,6,1 Thc dutie~ and obliptlc -< impo~ed bv the Con-
tract Document" and the rigi'> and remedies al'adable
thereunder shall be in addition :: and not a limitation oi,
an)' dutie<, oblisations, rights c~d remedie" etherwi"e im-
po"ed or Jvailable b\' la\\',
7.6.2 i'o cction or icJlure to act by the OIl ner, the Ar-
chitect, the ConstruC:oll Manager or the Contractor sh,,11
conotrtute 2 I\Ji\er of "ny rigf;t or duty ahorded "ny o(
them under the Contr,jct, nor shall any <uch action 0,
failure to ect constitute an appro\'"l of or Jcquie"cence in
any breach thereuncer, except as may be specifically
agreed in II rlting,
7.7 TESTS
7.7.1 If the Contract Documents, laws, ordlnJ.nces, rules,
regulation<, or orders of any public Juthorit) ha\'ing juris-
diction require any portion of the Work to be in<,pected,
tested or apprO\ed, t:-:e Contractor shall give the !\rchitect
and the Construction .\Ianager timely notice of its readi-
ness so the Architect and the Construction .\1anager may
observe such inspection, testing or appro\'al. The Con-
tractor shall bear all costs of such inspections, tests or
approvals conducted by public authorities, Unless other-
wise provided, the Owner shJII bear all costs of other in-
spections, tests or approvals.
7.7.2 If the Architect or the Construction Manager deter-
mines that any Work requires special inspection, testing
or approlal which SubparagrJph /,7,1 does not include,
the Construction .'v\anager will, upon written authoriza-
tion from the Owner, imtruct the Contractor to order
such special in,pectlon, testing or appro\'al. Jnd the Con-
tractor sheil gi\e notice as pro\ided in Subparagraph
/,/,1, If such special impection or testing rneals a failure
of the Work to comp'l Ilith the requirements of the Con-
tract Documents, the Contractor "hall bear all costs
thereof, including cO'llpensation for the Architect's and
the Construction Mar."ger's additional ser\'ices made nec-
eSSJI)' by <uch failu'e; otherwise the Ollner shall bear
ouch cost" and an cppropriate Change Order shall b,
i<5ued.
7.7.3 Rec;uired cert.;'icates of inspection, testing or ap-
proval "hc', be secu'ed by the Contraclor 2nd the Con-
tractor Sr.2,; p~ompt:\' deliver them to the Construction
,\\an2ger fer tra:l"mi,:al to the ,-\fchitect.
7.7.4 Ii tr,e ,-\rchitec: or the Construction !\\2nager I\ishes
to ob"ene the inspections, tests or approl'3!' reqUired by
the Contract Documents, they 1\ ill do 50 promptlv and,
where pract'ccble, at the source of supply,
7.8 t~TEREST
7,8,1 Pal ments due ;ond unpaid under the Contract Doc-
uments sr.a:1 bear ir:erest from the date palment i5 due
"t .ucr r:,','O ,'C the ;::,'[Iie, mav a\Cree upor n 1\ r:::1g or
In :I~C Jb~c:lce :hcr~:,i, ,,t the legal rate pre\"rllns at the
place of Ire Project.
/.9 ,\RE:llRATIOS
7.9.1 Ail C;2i~~'S, dl,~ute' and other malter, in ouestion
between :-I? Contr;,c:or and the 01\ ner Jking o~t of or
re!atins \e. tne Con:~Jct Documents or the breach thereof.
e>.ccpt Q< prol,oed -, 5ubp.Hagraph 23.l~ \\I\h respect
to the ,-\'cnitect's dec,sions on matters relat:ng 10 ,;rtistic
effect, arc e>.ccpt ic c!"im, I\hich hale Ix'en' Ilailed by
the m"ki1~ or acce::3!lCe of tinal p:,vll1crt ,><, prolided
bl' 5ubp,',;e;~2;Jh" c~ --1 through 11<)ll, Illc!;,:'ile, ,hall be
decided :C\ 2r~:tr3t::'~ in accordance \\'ith :he COl1otruc-
tion Indu-:r\ ,-\rbitrc:ion Rules of the :\merican ,-\rbitra-
lion .-\<~oc21ion ther- obtaining unless the perties mutuallv
13 A201/0v\ -1980
.\IA DOCU,\'\E"T A?01'CM . G~"..::-._.'.~ CO"-Oi-:- ::::}".5 OF lHE CO:\l;::ACl Fe,;:; CO"~:,~'C1 :(),~
CO:,S-'-Rl'CIO,- .\\"'-AGE\\E'-, ,:-::--; . ',--;E 1"2,;) EDl:IO~ . A1A~ . (D 1",: . 1HE
:\\HRiC\' !'ST:il.'lE Of,\KCH-~;=T~ --3J ,~:, lOR" .\\'E "'.;,\\ \\\(,1-1:'_,10' li c. ~Ch)Ch)
agree other\\i~e, ~o arbitration arising out of or reiating
to the Contract Documents sh,all inC!L;de by co~~olida-
tion, joinder or in an, other manner, the Architect, the
Construction \\anaser, their emplo)ees or consultants
except by written consent can:aining a specific reference
to the Owner.Contractor Agreement and signed by the
Architect, the Construction \\anager, the O\\ner, the
Contractor and any other per<on sought to be joined, No
arbitration shall include by consolidation, joinder or in
an\' other manner, parties other than the Owner, the
Contractor and any other persons sub<.tantially imolved
in a common question of fact or law, \" hose pre~ence is
required if complete relief is to be accorded in the arbi-
tration, No person other than the 0\\ ner or the Contrac-
tor shall be included as an ooiginal third party or addi-
tional third party to an arbil'ction \\ ~C"e interest or re-
sponSibility is insub<tantial. "'ny cor,ser: to arb:tration
involving an additional perso'l or persens shall not con-
stitute consent to arbitration of any dispute not described
therein or with any person not named or des-cribed
therein, The foregoing aweement to arbitrate and any
other agreement to arbitrate ,",ith an add,tional pers-on or
persons duly consented to b~ the partie~ to the Owner-
Contractor Agreement shall be speciiically enforceable
under the pre\'ailing arbitration law, The award rendered
by the arbitrators shall be fin2i. and judg'l'1ent ma\ be en-
tered upon it in accordance with applic,ble la\', in ilny
court having jurisdiction thereof.
7.9.2 ;-':otic(' of the cemand ior arbitoaLon shall be iiled
in writing with the other part'.' to the O\\ner-Co~tractor
Agreement and with the American Arbitration '-\-socia-
tion, and a copy shall be filed with the Architect and the
Construction \~ilnager, The c,:,mand for arbitration shall
be made within the time limi:s speciilE-d in Subp2cagraph
2,3.15 \\here applicable. and in all other cases "ithin a
reasonable time after the c12~, dispute or other matter
in que<tion has ari~en; .1nd i.., no e\ent shall it be made
after the date when institutic'l of leg21 or equit2~!e pro-
cec-din~s based on such clairr, dispute or other r;,atler in
que<tll~n would be barred t'. the ar;plici1ble st2:ute of
limitations,
7.9.3 L:nless other\\ Ise agreed in \\'rlting, the Cc,-,tractor
,hall carr\' on the Work and ~aintain its progres' during
~n\ arbit~ation proceedings, 2nd the 0,.. ner shall con-
tinue to make paymenb to Ire Contractor in accordance
\\ !:h the Contract Document-
~RTIClE 8
---~-
11.\ i E
8.1 OUlr--1TI0NS
8,1,1 L'nless othen.."e pro,ded, the Contract Time is
the period oi time 2':c:ted in tne Cont'act Docurr.:'nts for
Subs!,'!'::ra! Comp!e:,on oi t;..e \\'ork J' defined 'n Sub-
p,oragr,'ph 8.1.3, includ ng aU'-\~rized 2C ~;lment' ''-,creta,
8.1.2 The date of commer"ement oi the \\'or~, is the
date e'labllshed in a notice :': proceed. Ii there is no no-
tice to proceed, it sha!1 be '.Jch oir.:'r date as .."ay be
e<t"bll,hed in the 0\\ ner-Cc -'ractor \;reement or else,
\\ here :n the Contract Docur-'ent'.
8,1,3 The D,,:e oi Sub<tan: 2: Com:,'e: on of tre Work
or designated portion theree i~ the Date certifiec by the
f\rchite~t "hen construction is suificientlv complete, in
accordance with the Contract Documents, so that the
0" ner or <eparate contr,lcto:S r"n occupy or utili7e the
\Vork or a design,lted portron thereof 1'\.)[ the use for
which it IS intended,
8.1.4 The Date of Substantial Completion of the Project
or designated portion thereof is the Date certified by the
Architect when construction is sufficiently complete so
the Owner Ciln occupy or utill/e the Project or designated
portion thereof for the use tor which it was intended,
8.1.5 The term day as used in the Contract Documents
shall mean calendar day unle~s specifically designated
otherwise,
8.2 PROGRESS AND COMPLETION
8.2,1 All time limits stated in the Contract Documents
:Ire of the e,<ence of the Cont'act
8,2,2 The Contractor shall begin the Work on the date
of commencement as defined in Subparagraph 8,1,2, The
Contractor shall carry the Work forward expeditiousl\'
with adequate forces and shall achie\e Substantial Com-
pletion oi the ,"Vork within the Contract Time,
8.3 OHA)'S AND EXlEfo,;SIOfo,;S OF TIME
8.3,1 If the Contractor is delayed at any time in the
progress of the Work by any act or neglect of the Owner,
the Architect, the Construction \\anager, any of their em-
ployees, any separate contractor employed by the 0\\ ner,
or by changes ordered in the Work, Idbor disputes, fire,
unusual delay in transportiltion, adverse \\eather condi-
tions not reasonably anticipatilble, un,1\'oidable casualties,
any causes beyond the Contractors control, delay author-
ized by the Owner pending ,1rbitrJtion, or by any other
cause \\hich the Construction \\,mager determines ma\'
justiiy the delay, then the Contract Time shall be ex-
tended by Change Order for such reasonable time as the
Construction J\l,lnager may determine,
8.3,2 Any claim for extension ot time shall be made in
\\ riting to the Construction \~an,'ger not more than
t\\enty days after the commenccment of the delay; other-
\\ise it shall be waived, In the Cl'e of ,1 con:inuing dela\
only one claim is necessary, The Contr,lctor shall prmide
,111 estimate of the probable e;;e(t of <uch dela\' on tn",
progre" ot the Work,
8.3.3 Ii no agreement is m.ide stating the dates upon
which interpretations as prm iced in Subp.lr,,(raph 2,3,11
shall be furnished, then no cl,1im for del,>\ shall be
,11!0\\ed on ,,((aunt 01 failure 'n iu,ni,h <lIcn interpret",
lion, untl; ;llteen da\, ~fter '.\ '::1U1 le'quest i5 m~de ;'0:
them, and not then unle<< ,uch cl.,im i< re,"c,'~"ble,
8,3.4 This PiHagral'h 8,3 doc, not exclude the reco\ef\
of damages for delil) b\ ei:l;cr pMl\ under other prf)\ ,-
sions of the Contract Document<.
ARTICLE 9
PAYMENTS AND COMPLETION
9.1 CO!\:TRACT SU.'\i
9,1,1 The Contract Sum is ,L'::f"d In the 0\\ ner-Contrac-
tor ;\grC'cment and, :nclud,--;~ ,H;:hori7ed adjustmentc
thereto, is the total amount p.'\able bv the O\\ner to the
Contractor for the performance 01 the Work under the
Contract Documents,
A201/CM -1980 14
AlA DOCl,;,\\[~T A:01C\\ . Cl 'lR"" ~C':l:T''::.'_: 'A THE C( -.' RACT fOR CO'\SiRL:CTiO\;
CO'STRLCTIO\; \:A'\,AC'''"T [C,-:l'\ . JL'-E -,",3J EDllIC', . AIA@ . 01980 . THE
,\\'lrIC\\; "STI~~ ~E Of .\,CHITfC' 1-35 'E'''. ,~';, ~vE., '-. \\'ASHi-':CTO'. D.C c(\c,)(.
9,2 SCHEDLU or VAIU[S
9,2,1 Rcic"e the iliq r\pplic"tion for p") ment, the Con-
tractor ,n2: ,ubmit to the Con<,(ructic:n ,\\anaser a
schedule ci \ "lue" .1liocated to the \'arious portions of the
\\'o:k:. pre;:".1:f'd in "uch form "nd 'uppo.ted by such data
to 'ubqan':de its MClJrac\' as the Architect and the Con-
'lruction "\anager may require, This schedule. unless
objected 10 bv the Con<trucllon .\1anager or the .\rchitect.
,h,111 be u'ed only .1< a basis for the Contractor's Applica-
tion, for Pc\ment.
9.3 APPlICA TIOI"S rOR PA YM[~T
9.3.1 At east fiitcen days beiore the date for each
progress PC) ment established in the 0\\ ner-Contr actor
Agrcement. the Contractor shall submit to the Con5lruc-
tion Manager an itemized Application for Payment, notar-
ized if rec;uired, supported by such data substantiating
the Contractor's right to payment as the Owner, the Ar-
chitect or the Construction ,'.1anager may require, and re-
flecting retainage, if any, as provided elsewhere in the
Contract Documents, The Construction Iv\anager will as-
,emble the ,\pplication with similar applications from
othc.r cont:2ctors on the Project into a combined Project
Application ior Payment Jnd forward it with recommen-
d"tions to :he Architect within seven days,
9.3.2 Unle's otherwise prO\'ided in the Contract Docu-
ments, pa\ f:1ents \\i11 be made on account of materials or
equipment not incorporated in the Work but deli\ered
and suilabl\ stored at the site and, if apprO\'ed in ad\ance
by the 0\\ r.er. payments may similarly be made for mate-
rials or ec;uipment suitably stored at some other loca-
tion .,greed upon in writing, Payments for materials or
equipment stored on or oft the site shall be conditioned
upon submission by the Contractor of bills of sale or
such other t)rocedures sati<factory to the Owner to e'-lab-
lish the 0,', ner's title to such materials or equipment or
otherwise reotect the Owner's interest, including applica-
ble insura~ce and transportation to the site for those
m"leri,lls .'-d equipment "to:eo oil' \he site,
9,3.3 The Contractor warrants that title to all \\'ork,
materials c~,d equi\':'lcnt cO\'ered by an Application for
Pal ment " :1 P,'Ss to the O\lner either b\' incorporation
in the cor,truction or upon receipt of payment b\ the
Conlracto: ,..hiche\er occurs first, free and clear of all
lien<, clairi" security interests or eI1cumb:.lnce<, huein-
"iter refer'ed to in this Article 9 as 'liens"; and that no
\\'CF~, nv:e'ia/< or c'luipmcnt CO\ cled b\ an ,\pplication
"\" P2\ ni(- ~ \\ ':l! h,-;\ (: hee:! {::cqc" :ed b\ :~e Con ~ ~cctor.
or b\ .111\ _:ner person performing \\'ork at the site or
iurnishing :',lterials and equipment for the Projecl, sub-
ject to an ,<:eement under which an inlerest therein or
an (-r;cumf:','ce thereon is retained by the <e!!c-r 0: oth-
e:\\'!'e imr~'"d b\' the Contractor or such other per'an,
9.4 CER1:fICATES FOR PAYMENT
9.4.1 The ;rchitect \Iill, within se\'en days after the re-
ceipt of the P;oject AppliGdion for Payment with the rec-
ommendat,c,ns of the Construction ,\lanager, reI ie\\ the
Pro;ect A!,;:liution for Palment and either i<sue a Project
Certificate ivr Pal ment to the Owner with a COP\' to the
Con'l'uctic'": V,.,nager {or distribution to the Contr2ctor
for such "r'ounts as the Architect determines are p:op-
erl\' due, 0: notify the Construction ,\r\anager in writing of
the re"sons for \\ ithholding a Certificatl' a' prolided in
Subparagr"ph 9,6,1, Such notlfiution \\ ill be fOf\\,Hded
to the Contracto: b.. the Construction \1.1n,,:;er,
9.4.2 The issuc:1ce oi a Project Certlfiute for Pa\ ment
\\ ill constitute a reprC'Sent"tlon b)' the ,\.chitect to the
Owner that, based on the /\rchitect.s (lb,e,,- ;~lions at the
site as prO\ided in Subparagraph 2.3,4 and the data com-
!)rIsing the Project Application for 1'.1) ment, the \"'ork has
progres"ed to the point indicated; that, to the best oi the
,\rchitect's kno\\ :edge, information and beliet, the quality
of the Work is in accordance with the Contract Docu-
ments :subject to an e\ aluatlon of the Work: for conform-
ance I\ith the Contract Documents upon Substantial
Completion of the \\'ork, to the re,ults of any subsequent
tests required b~ or performed under the Contract Docu-
ments, to minor de\iations from the Contract Documents
correctable prior to completion, and to allY specific quali,
fications stated in the Certificate); and that the Contrac-
tor is entitled to payment in the amount cenified, How-
eler, by issuing a Project Certificate for Pa\ men!, the Ar-
chitect shall not thereby be deemed to represent that the
,\rchitect has made exhausti\e or lOntinuous on,site in-
,pections to check the quality or quanti1\' of the Work,
has re\'iewed the construction means. methods, tech-
niques, sequences or procedures, or has r1'12de an)' exam-
ination to ascertain how or for what purpo,e the Contrac-
tor ha, used the monies pre\'iou<Iy paid on accoullt of the
Contract Sum,
9.5 PROGRESS PAY,\HNTS
9.5.1 After the ,\rchitect has issued a Project Certificate
for Payment, the Owner shall make payment in the man-
ner and within the time prO\'ided in the Contract Docu-
ments,
9,5.2 The Contractor shall prompth' pa)' each Subcon-
tractor upon receipt of payment from the 0\\ ner, out of
the amount paid to the Contr,lctor on account of such
Subcontractor's Work, the amount to I\hich said Subcon-
tractor is entitled. reflecting the percentage actuall\' .e-
tained. if an)', from payment' to the ConCt:actor o~ ac-
count of ,uch SU8contractor's \\'or~, The Contractor <hall
b\' an appropriate agreement with each'Suhcontr;ctor:
require each Subcontractor to make pa\ ments to their
Sub.subcontracto:s in similar manner.
9,5.3 The Architect may, on reque'! ,lnd at the ,\rchi-
tect's discretion, furnish to an\' Sub(ontr2ctor, if prac-
t'cable, ,nformation regarding the percenta:;e, of C0I11-
;crotlo;,) :"r the a:--. ,;"t, .,ppl:ed for b', the C:',~:r"C:c' ::nd
the "Cion taken :~,c-:eon by the Arcnltect on .lCcount of
\\'ork done by such Subcontractor,
9.5.4 '-'either t!-:e 0\\ ner, the Architect nor tne Con'!ruc-
lion \lanager sha ! h2\e an)' obligation to pc\ or to ,ee to
the p2yment oi 2:iY monies to any Suhcor:te;,ctor except
as ma)' otherwise be required bv law,
9,5.5 '-:0 certii'icclion of a progre<s pal me',!. any prog-
re's pa\ ment, or 211\ partial or entire use or occupanc\'
of the Project b\ the Owner, <hall con<titute an accept'-
a, ce of an)' \\'0'1-. not in accordance with the Contract
Documents,
9,6 PAYM[STS \\ITHHElD
9.6,1 The Architect, follol\ ing comultation with the
Construction M"nager, may decline to certify payment
15 A201/C.\1 - 1980
AI~ DOqJME~T A201 CM . CE:-;fRAl (O'':':,IO:-;S OF 1f-'E CO:-;1R~CT FOR CC):-;<1Rl (T I 0'"
co--;s- ;,'~CTIO:-; ,\jA:-;-\GE,\\r:-;T EOITIO:-; . jL:-;E 1980 E01110t--; . .-\Ir\~ . C ',980 . 1HE
.\\\ER C'':-; 1,:-;S11111H or ARCHITEC1S, 1'" ,E\\' \ORK A\'E, --;.\\'., \USHi'Gl0:-;, 0 c. cOOO&
~ .J;" ," . ~
and may \\Ithhold the Certificate in whole or in part to
the extent necessary to reasonabl\ protect :!-c 0" :-:U, if,
III the Architfct's opinion, the Architect :" ~.r",b!e to ~.,ke
representations to the O\\ner as prO\lcE'd In Sucf'Jara-
graph 9.4.2. If the Architect is unable to mJ~e representa-
tions to the Owner as provided in Subparagraph 9.4.2,
and to certify payment in the amount 01 the Project ,Ap-
plication, the Architect \\ill notify the Construction \\an-
ager as provided in Subparagraph 9.4.1. If the Contractor
and the Architect cannot agree on a re\ ised amount. the
Architect \\ ill promptly issue a Project Certificate for Pay-
ment for the amount for which the Architect is able to
m.lke such representations to the Owner. The Architect
may also decline to certify payment or, because of subse-
quently discovered evidence or subsequent obser\ations,
the Architect may nullify the whole or anv part of any
Project Certificate for Payment previously issued to such
extent as may be necessary, in the Architect's opinion, to
protect the Owner from loss because of:
.1 defective \,\'ork not remedied;
.2 third party claims filed or reasonable evidence in-
dicating probable filing of such cl2ims;
.3 failure of the Contractor to make pal ments prop-
erly to Subcontractors, or for labor, materials or
equipment;
.4 reasonable evidence that the VVork cannot be com-
pleted for the unpaid balance of the Contract Sum;
.5 damage to the Owner or another contractor;
.6 reasonJble evidence that the \\'olk will not be
completed \\ithin the Contract Time; or
.7 persistent failure to carry out the Work in accord-
ance wi,h the Contract Documents.
9.6.2 When the grounds in Subparagraph 9.6.1 above
are remO\'ed, payment shall be made for amounts with-
held because of them.
9.7 FAILURE OF PAYMENT
9.7.1 If the Construction t\~anager should fail to issue
recommendations within seven days of receipt of the
Contractor's Application for Payment, or if, through no
feult of the Contractor, the Architect does not issue a
Project Certificate for Pa~ ment within se\ en da\ s after
the Archilect's receipt of the Project Application for Pay-
ment, or if the Owner does not pay the Contractor within
seven days after the date established in t~e Contract Doc.
,"'nents am' amount certified b\. the .-\rch.~ect or a\\arded
by arbitr2l;on, then the Contractor may, ~pon se\e:J addi-
tional days' written notice to the 0\\ nero the Architect
and the Construction Manager. qOP the Work until pay-
ment of the amount owing 11"s been recei\ed. The Con-
tract Sum shall be increased bv the amount of the Con-
tractor's re2sonable costs of shut-do\\ n. delay and start-
up. \\hich shall be effecled by appropriate Ch2nge Order
in accordance with Paragraph 12.3.
9.8 SUBST ANTIAl CO,\1PI ETION
9.8.1 \\'hen the Contractor considers that the V\'ork. or a
designated portion thereof \\ hich is c.cceptable to the
0\\ ner, is substantially complete as de:ir,ed in 5Jbpara-
graph 8.13. the Contractor shall prepare for the Construc-
tion Manager a list of items to be completed or cor-
rected. The failure to include any items on such list does
not a::-:, the responsibility of the Contractor to complete
all \\,' In accord.lIlce \\Ith the Cl)ntr.ll! Documents.
Whc'! . e Architect. on the baSIS of Inspedion and con-
sultJ:,cTl with the Construction '''anager. determines that
the \\ork or design.lted portion thereof is substantially
conl~'ete, the Architect will tren prepJfe a Certificate of
Subst2:Jtial Completion of the Work \\ hich shall establish
the D2te of Substantial Completion of the Work, shall
stale :~e responsibilities of the 0\\ ner and the Contractor
for security. maintenance, heat, utilities, damage to the
Work jnd insurance. and shall fix the time within which
the Contractor shall complete the Items listed therein.
The Certificate of 5ubstantial Completion of the Work
shal! be submitted to the O\\ner and the Contractor for
their \\ ritten acceptance of the responsibilities assigned to
them :n such Certificate.
9.8.2 Upon Substantial Completion of the Work or desig-
nated portion thereof, and upon application by the Con-
tracto- and certification by the Architect, the Owner shall
make payment, reflecting adjustment in retainage, if any.
for such Work or portion thereof as pro\ ided in the Con-
tract Documents.
9.8.3 When the Architect, on the ba<is of inspections,
deterrTlines that the Project or designated portion thereof
is substantially complete, the Architect \\ ill then prepare
a Ce-tiiicate of Substantial Completion of the Project
whic!. shall e~tablish the Date of Subst.lntial Completion
of the Project and fix the time \\ ithin \\ hich the Contrac-
tor srall complete any uncompleted items on the Certif-
icate of Sub~tantial Completion of the Work.
9.8.4 Warranties required by the Contract Documents
~hall commence on the Date of Substantial Completion of
the P~oject or designated porlion thereof unless other-
wise p~ovided in the Certificate of Substantial Comple-
tion of lhe \\'ork or designated pori ion thereof.
9.9 FINAL CO.\1PlETION AI\'D FISAl PAY,\'ENT
9.9.1 Following the Architect's issuance of the Certificate
01 5u::stantial Completion of the \\ or~ or designated por-
tion ::-,ereof, and the Contractor's completion of the
\\or~ the Contractor shall forwa,d to the Construction
Man,,;er a w~itten notice that the Work is ready for final
inspf~tion and acceptance, 2nd s~211 also forward to the
Cons:'uction .\\anager a final ,Application for Pavment.
Upon receipt, the Construction '\anager \\'ill make the
nece;sary e\'aluations and forward recc1mmendations to
the ~. -,hitect who 1\ III promptl\ make "uch inspection.
\\1-(':-, the :'.rchitect ;'inds t':e \\ ork ::cceptable under
the Contract Documents and t!-:e Contract full)' per-
forlT,ed, the Architect will issue a Project Certificate for
Pa\lT.e1t which \\'ill approle the final pa~mcnt due the
Cont'actor. This appro\'al will constitute a representation
that. '0 the best of the Architect', ~no\\ ledge informa-
tion 21d belief, and on the ba~is of observatio~s and in-
~peC:8ns, the \Vork has been cO!'T1pleted in accordance
with the Terms and Conditions of the Contract Docu-
ments and that the entire balance found to be due the
Con"actor. and noted in said Certificate. is due and pay-
able. The Architect's appro\al of "aid Project Certificate
for Fa\ment will constitute a further representation that
the conditions precedent to the Contractor's being en-
titled to final payment as set forth in Subparagraph 9.9.2
ha\E' been fulfilled.
AlA DOCUMEST A201/CM . CE '-ERAL CO'-DITIO'-5 Of THE CO'- 1 R"CT FOR CO's", ~,iO'
CO,STRUCTIO, MANAGE,\IENT EDITlO, . )U,E ~g&" EDITIOS . AIA~ . @ 1950 . THE
.,,~\ERICA' I'-STITUTE Of ARCHITECTS, 1735 'EW 'OR~ AVE.. '-.\\ . \\'ASHI'-GTON. DC ,0006
A201iCM -1980 16
9.9.2 !\eithC'T the final P2\ ment nor the remaining retain-
age shall become due until thc Contractor submits to the
""chitect, through tl:e Construction \1anager, 11) an ahi-
02\ it that 211 payrol!" bills for mJtcrl.,ls .,nd equipment,
and other indebtedness connected With the Work for
\\ hlch the 0\\ ner or the Owner's property might in any
\\ ay be responSible, have been paid or otheT\\ ise satis-
fied, 12) consent of <urety, if any, to final payment, and
'3 If requircd by the Owner, other data e<tablishing pay-
ment or satisfaction of .,11 such obligations, such as re-
ceipts, releases and wai\ers of liens arising out of the
Contract, to the extent and in such form as may be desig-
niiied by the Owner. If any Subcontractor refuses to fur-
ni-h a release or waher required by the Owner, the Con-
tractor mav furnish a bond satisfactory to the Owner to
indemnify 'the Owner against any such lien. If any such
lien remains unsatisfied after all payments are made, the
Contractor shall refund to the Owner all monies that the
latter may be compelled to pay in discharging such lien,
including all costs and rea..onable attorneys' fees.
9.9.3 If, after Substantial Completion of the \\'ork, final
completion thereof is materially delayed through no f2ult
of the Contractor or by the issuance of Change Orders
at1ecting final completion, and the Construction Manager
so confirms, the Owner shall, upon application by the
Contractor and certification by the Architect and without
terminating the Contract, make payment of the balance
due for th2t portion of the Work fully completed and
accepted. If the remaining balance for Work not fully
completed or corrected i.. less than the retainage ..tipu-
lated in the Contract Documents, and if bonds have been
furnished as provided in Paragraph 7.5, the written con-
..ent of the surety to the payment of the balance due for
that portion of the Work fully completed and accepted
<hall be submitted b\' the Contractor to the Construction
~12nager prior to certification of ..uch payment. Such pay-
ment ..hall be ma.de under the Terms and Conditions go\'-
erning final payments. except that it <hall not con<titule a
\\ai\'er of cl2ims.
9.9.4 The making of final payment shall, after the Date
of Substantial Completion of the Project, constitute a
\\ai\er of 211 claims by the Owner except those arioing
jrom:
.1 unsettled liens:
.2 iaulty or defective Work appearing after Substan-
tial Completion of the \\'ork;
.3 failure of the Work to complv with the require-
mc:nt, ui the CJfltract Documents, or
.4 telms oi any 'pccial warr,mlies required by the
Contract Docu,nents.
9.9.5 The acceptance 01 Imal pa)ment <hall, 2fter the
Dele oi Substantial CC:-:lpietion of the Project, con<lii:.Jte
a 1'.2iver of all claims bv the Contractor except those
pre- ,ously mdde in writing and identiiied b\ the Contrac-
tor 2S un,ettled at the time oi the final ,-\pplication ior
Pal men!.
9.9.6 All provisions of lhis Agreement, including w:th-
out I:mitation those establishing obiigetions and proce-
oures, ,hall remain in 'ull force and e;1ect notwith..tand-
mg the making or acceptance of final pa\ment prior to
the Date of Subst~,ntial Completion of the Project.
ARTICLE 10
---
PROTECTION OF PERSONS AND PROPERTY
10.1 SAfETY PRECAUTlOSS ASD PROGRAMS
10.1.1 The Contractor shall be respomlble for initiating,
maintaining and supervising all ..afety prec,utions and
programs in connection With the Work.
10.2 SArLTY OF PERSO!'\S A~D PROPERTY
10.2.1 The Contractor shall take all rc.l'.onable precau-
tions for the safety of, and shall prO\'ide all reasonable
protection to prevent damage, injury or Ims to:
.1 all employees on the \Vork and all other persons
who may be affected there-by;
.2 all the Work and all materials and equipment to
be incorporated therein, whether in storage on or
off the site, under the care, custody or control of
the Contractor or any of the Contractor's Subcon-
tractors or Sub-subcontractors;
.3 other property at the site or adjacent thereto, in-
cluding trees, shrubs, lawns, walks, pavements,
roadways, structures and utilities not designated
for removal, relocation or replacement in the
course of construction; and
.4 the work of the Owner or other ~epJrate contrac-
tors.
10.2.2 The Contractor shall give all notices and comply
\\dh all applicable laws, ordinances, rules, regulations
and lawiul orders of any public authority bearing on the
safety of persons or property or their protection from
damage, injury or loss.
10.2.3 The Contractor shall erect and m2intain, as re-
quire-d by existing conditions and the progress of the
\Vork, 211 reasonable safeguards for safety and protection,
including posting danger signs and other warnings aga.inst
hazards, promulgating safety regulations and notifying
owners and users of adjacent utilities.
10.2.4 \Vhen the use or storage of explosi\es or other
hazardous materials or equ.jJment is nece....ary for the
execution of the Work, the Contractor shall exercise the
utmost care and shall carryon such activities under the
superVision of properly qualified personnel.
10.2.5 The Contractor ..hall promptly remedy all damage
or lo,s (other than d2mage or loss Insured under Para-
graph 11.3) to any property re;erred to in CI2uses 102.1.2
and 10.2.1.3 caused In whole or in part b\ the Contrac-
tor. 2nv Subcontractor 2ny 5~b-(ubcont'actc" ,jn\(J~e di-
rectl\ or indirectly employed b\ In\ of them, or by any-
one for whose acts any of them may be li2ble, and for
which the Contractor is respor"ble under Clau..es 102.1.2
and 10.2.1.3, except damage or lo..s attributable to the
act.. or omi'sions of the 0\\ ner, the Architect, the Con-
struction Manager or anyone dilCctiy or i[',dlrectly em-
plo\f-d by any of them, or b\ anyone for whose Jcts any
of them may be liable, and not .1!trlbul.lble to the iJult
or negligence of the Contr2clor. The foregoing obliga-
tion, of the Contractor are in addltron to the Contractor's
obli?2tlons under ParJgraph ~ 18.
10.2.6 The Contractor sha'i de'ignate a responsible
member of the Contr2ctor's orgJr1i7atlon at the site
whose duty ~ha" be the pre\ention of accidents. This
person ..hall be the Contractor's superintendent unless
17 A201/Co..1--1980
~JA DOCL~\E"iT~10'/CM . Cl'.lRAl CO'011!0'5 OF 1'" co...n~~CT FOR CG.....TRl'CI10N
CO...SlRL 010... MA,"iAGE\'o.'T lOITlO... . jL'...E 1980 l: TIO... . AIA~ . ~ ";980 . THE
.\"ERIC", "STITL'TE or .~;;:CHIT[C1S. F35 'E\\' YORK AlE 'w. \\ASH"CTO-';. DC ;)(1(11,
v:t ~,~;p.IS: Ui1I;c'::~'sJ?j 0! 'J1r,:.:-orr,.;,-J(, ';:::"'~2,~~~ :.: S rC'':'t! _h' 1;;-,'.'''- r1 i<:- ':~l!! '".:~ to !,:,;;:=' r,-::,:,!":' ,AI"'"
othe~.\ ise designated by the Contractor in \\ riting to the
0\\ rer and the Con~tru(tion \\anaser.
10.2.7 The Contractor shall ,"at loco or permit "ny part
of tr,e Work \0 be loaded ,0 as to endanger its safety.
10.3 H.1ERGENCIES
10.3.1 In any emergency ah'ecting the safety of persons
or property the Contractor -hall act at the Contractor's
discretion, to pre\ent threater,ed d2filage, inju/) or loss.
Any additional compensation or extension of time
claimed by the Contractor on account of emergency
work shall be determined a< prO\lced in I\rticle 12 for
Changes in the Work.
ARTICLE 11
INSURANCE
11.1 CONTRACTOR'S LIABILITY I~SURANCE
11.1.1 The Contractor shall purchase and maintain insur-
ance for protection from the claims set forth below which
may arise out of or result f:om the Contractor's opera-
tions under the Contract, \\ nether such operations be' by
the Contractor or by any Subcontractor, or by anyone di-
rect!\' or indirectly employed by an) of them, or by any-
one tor whose acts any of them ma) be liable;
.1 claims under workers' or \\orkmen's compensa-
tion, disability benefit and other similar employee
benefi t acts;
.2 claims for damages becau<;e of bodily inju/)', occu-
pational s.idness or disease, or death of the Con-
tractor's ef'l''.ployees;
.3 claims for damages because of bodily injury, sick-
ness or dis,case, or death of any person other than
the Contractor's emp:oyees;
.4 claims for damages i'lsured by usual personal in-
jury liability coverage which are sustained (1) by
any person as a resJlt of .on offense directly or
indirectly rel"ted to t~e employment of ~uch per-
son by the Contractor, or (2 by any other person;
.5 claims for damages. other than to the \\ork itself,
because of injury 10 or destruction of tangible
property, including :.~ss of L.'e resulting therefrom;
and
.6 claims for damages because of bodilv injury or
death of any person or property damage arising
out of the o\..ner,h.~ ma:r:enance or u-e of an\
motor vehicle.
11.1.2 The insurance req~ red b\ Subparagraph 11.1.1
shail be written for not Ie" than any limits of liability
spe::fied in the Contract Dxume'll,. or required bv law,
wh,chever is greater.
11.1.3 The insurance req~:red b Subparagraph 11.1.1
shal! include contractual 1:2bility ;r;<urance ap;:,!icable to
the Contractor's obligation- under Puagraph .U8.
11.1.4 Certificates of InSU'2r1Ce .occeptable to the Owner
sha!1 be submitted to the C'~'r~,tru':' on .\t,nager for trans-
mittal to the 0\\ ner prior to con)f'~encement oj the \Vork.
These Certificates shall cortain a p'o,ision tha' coverages
afforded under the policie- will r.ot be cance:ed until at
le2st thirty days' prior wr:::en notice has been gi\en to
the Owner.
11.2 OWNER'S LIABILITY I~SURANCE
11.2.1 The O\\r~er sh.lll be f("pon':ble for purchasing
Jnd m"intaining 0\\ ncr'~ Ilabditv in'vrdnce and, "t the
Owner's option, mJY purchase .,nd mamtain in-urance
for protection against claims \\ hich ma\' ari<e' from
operations under the Contract.
11.3 PROPERTY I~SURANCE
11.3.1 Unless othef\\ ise provided, the 0\\ ner shall pur-
chase and maintain property insurar1ce upon the entire
Work at the site to the full insurable \alue thereof. This
insurance shall include the interest, of the 0\\ ner, the
Construction Manager, the Contractor, Subcontractors
and Sub-subcontractors in the \-\'ork. and shall insure
against the perils of fire and extended CQ\erage and shall
include "all risk" insurance for phy~ical loss or damage
including, without duplication of coverage, theft, van-
dali~m and malicious mischief. If the Owner does not
intend to purcha,e such insurance for the full insurable
value of the entire \Vork, the Owner shall inform the
Contractor in writing prior to commencement of the
Work. The Contractor may then effect insurance which
wdl protect the interests of the Contractor, the Contrac-
tor's Subcontractors and the Sub-subcontractors in the
Work, and by appropriate Change Order the cost thereof
shall be charged to the Owner. If the Contr.lctor is dam-
"ged by failure oi the Owner to purchase or maintain
<uch insurance and to so notify the Contractor, then the
Owner shall bear all reasonable COSls properly attributa-
ble thereto. If not covered under 1he all risk insurance
or otherwise provided in the Contract Documents, the
Contractor shall effect and maintain similar property in-
surance on portions of the Work stored ofi the site or in
transit when such portions of the \\'ork are to be in-
cluded in an Application for Pa\ ment under Subp.Ha-
graph 9.3.2.
11.3.2 The Owner shall purchase and maintain such
boiler and machine/)' insurance as mav be required by
the Contract Documents or by la\\. This insurance shall
include the intere:'lS of the Owner, the Construction \\an-
ager, 1he Contractor. Subcontrac10r< ,dld Sub-subcontrac-
tors in the \\'ork.
11.3.3 Any loss insured under Sub::3ragraph 11.3.1 is to
be adjusted with the 0\\ ner and made payable to the
0\\ ner as trustee for the insureds. a,. their interests may
appear, subject to the requirements of any applicable
m(Jrtgagee clause wd of Subparas'aph '11 38. The Con-
tractor shall pa\ each Subcontractor a Ju,t ,hare oi any
Insurance monies received by the Contractor, and by ap-
propriate agreement, written where legallv required for
validity, shall require each SubcontraclOr to make pay-
ments to their Sub-<ubcontractors in similar manner.
11.3.4 The 0\\ ner shall file a CO,)" of all policies \\ ith
the Contractor before an e\posure to loss m,w occur.
11.3.5 If the Contractor request" ,n \'.riling that insur-
ance for risks other than those c<?>cribed in Subpara-
graphs 11.3.1 and 11.3.2, or other special hazJrds, be
Included in the propert\' in,urance POIICV, the 0\\ ner
shall, if pOSSible, include such in'urance,' and the cost
thereof shall be charged to the Contractor by app~opriate
Change Order.
A1.o. DOCUMlNl A20T/CM . GE't;.~l CO':::'~ iO'S OF 1 i-':. CO" RACT FOR CO'S-rRl'CTIO'
CO'STRUCTIOI" ,\\A'AGEMl,T ,::::'10, . }L:'[ 19S~ [DnIO:-': . AIA<!'; . @1980 . lH[
A""RICAN INSTIlUH OF ARCHliEClS. T735 'E\\' YORK A\ E ,\\' W,~SH"GTOI". D.C. :0006
A201/C>"1-1980 18
11.3.6 Thc 0\\ ner and the Cont.actor waive all rights
.,~2in't 11, c.lch other and the Subcontractors, Sub-~ub-
c~':,::actor', at:,cnt- and employees of e2ch other, and (2)
tre :\rch:tect, the Con,tructlon .\1"n2ger and :-eparate con-
tr2ctors, If any, 2r,d their 'ubcontr2ctors, sub-subcontrac-
tor-, agcnts dnd e:llployees, for dam2ges caused by fire or
(\;'wr perils to the extent co\'ered h imUI.lnce obtained
pc:r'UJnt to tlm Paragraph 11.3 or 2ny other property in-
'u'.ince applicable to the Work, EXcept such rights as
tf,e\ m2Y ha\e 10 the proceeds 01 such insurance held
b\ the 0\\ ner a, trustee. The foregoing waiver afforded
the :\rchltect. the Con:-truction Manager. their agents and
C'r:lployees ,hall not extend to the liability imposed by
Subparagraph .US.3. The Owner or the Contractor, as
approprl,lte, shall require of the Architect. the Con~truc-
tion ,"'1anager, ~eparale contractors. Subcontractors and
Sub-subcontractors by appropriate agreements. written
\\here legally rC'quired for \'alidity, similar waivers each
In fa\or of all other parties enumerated in this Sub-
p2ragraph 11.3.6.
11.3.7 If required in writing by any party in interest, the
Owner as trustee shall, upon the occurrence of an in-
q;red loss, gi\'e bond for the proper performance of the
Owner's duties. The Owner shall deposit in a separate
Jccount any money so recei\'ed. and shall distribute it in
accordance with such ,'greement as the parties in interest
ma\' reach, or in accordance with 2n award by arbitration
In \'\hich case the procedure shall be as provided in Para-
~.aph 7.9. If after such loss no other special agreement
i- made, replacement of damaged Work shall be co\ered
b\ an appropriate Change Order.
11.3.8 The Owner, as trustee, shall ha\'e power to adjust
and settle any loss with the insurers unless one of the
p2rties in intereq shall object, in \\ riting within five days
a;:er the occurrence of loss, to the 0\\ ner's exelcise of
this po\\er, and if such objection be n1ade, arbitrators
shall be chosen JS prO\ided in Paragraph 7.9, The O\\ner
as trustee shall. in that case, make settlement with the
Insurers in accordance with the directions of such arbi-
trators. If distribution of the insurance proceeds by arbi-
tration is required, the arbitrator~ \\ill direct 'uch dis-
tribution.
11.3.9 If the 0\\ ner finds it neces'2ry to occupy or use
a portion or po:tlons of the \\'ork prior to Subst2ntial
Completion thereof, such occupanc\' sh,,1I not commence
prior to a time mutually agreed to by the Owner and the
Contr2ctor and to which the insurance compan\' or com-
!,:,'1iec p~()I'id'~( \11(' prope~t\ in<::cncc \'2\( c,~.,'ented
b\ endorsement to the polic\ or pollcie' 1 hi, IT1surance
,~'dl not be onceled or laD'ed on 2ccount of such partial
occupancy, CO'1sent of th~ Contractor z,nd of the insur-
"flce compan\ or cc'mpanies to cuch occupanc\' or use
'~211 not be unreason,-,b!v withheld
11.4 lOSS OF USE I~SURA"CE
11.4.1 The Ol\ner, at the Ol\ner's uption, may purchase
2nd Illaintz:in insurance for protection against loss of use
01 the Owner's properl\' due to fire or other hazards,
l-:ol\e\ er caused. The Owner wai\ es all rights of action
2~ainst the Contractor for loss 01 u'e of the Owner's
p~oputy, including consequential losses due to fire or
ether hazards howc\er caused, to the extent co\ered by
insurance under this Paragraph 11.4.
ARTiClE 12
CHASGES IN THE WORK
12.1 CHA~GE ORDERS
12.1.1 ..\ Chan~e O:der IS a written urder to the Con-
tractor <igned to ,'10\\ the recommendation of the Con-
struction ,\l.maSE-' the .1pprol'al of the Alchitect and the
authorlz.1tion ot t-e O\\ner, Issued .1fter execution of the
Contract, authori2'ng 2 change in the Work or an adjust-
ment in the Co~tract Sum or the Contract Time. The
Contract Sum .,no the Contract Time may be changed
only by Change Order. A Change Order signed by the
Contractor ind,c:es the Contractor's agreemcnt there-
\\ith, includins t:-:e 2dju,tment in the Contract Sum or
the Contract Time.
12.1.2 The O\\ner. I\ithout invalidating the Contract,
may order change:; in the \Vork within the gcneral scope
of the Contract ce,nsisting of additions, deletions or other
revision<;, the Cor:tract Sum and the Contract Time being
adjusted accordingly. All such changes in the Work shall
be authorized bv Change Order, and shall be performed
under the appliC2ble conditions of the Contract Docu-
ments.
12.1.3 The cost or credit to the Owner re'ulting from a
change in the \\ork shall be determined in one or more
of the following "Iays:
.1 by nlUtu2: acceptance of a lump sum ploperly
itemized 2nd 'uJ1ported by sufficient substanti2ting
data to pe'mit e\'aluatlon;
.2 by unit prces 'tated in the Contract Documents or
subsequently agreed upon;
.3 by cost to be determined in a manner asreed upon
by the p2.tles and a mutually acceptable fixed 0'
percentat=e fee; or
.4 by the method provided in Subp.lragraph 12,1.4.
12.1.4 If none of the methods set forth in CI2uses
12.1.3.1,12.1.3.2 or 12.1.3.3 is agreed upon, the Contrac-
tor, provided a \\ ritlen order signed by the Ol\ner is re-
ceived, shall promptly proceed with the \'I'ork invoh ed.
The cost of suc:- \\'ork shall then be determined b\. the
Architect, after consultation with the Construction :"'\an-
ager, on the b::s:s of the reasonable expenditules and
~a\ ings of those per10rming the Work attributable to the
ch.,nge, includl~~ in the case of an increase in the Con-
tract Sum, a ~e2son.,ble allO\\ance for O\erhead and
profit. In such c'e and Jlso under Clauses 12.1.3.3 and
12.13.4 "bO\e '-e Contr"ctor shall keep "no preser:t in
~uch form a, t,- ~ O".ner, the Architect or the Con~t~uc-
tlon \1"nager r.~:;.. prescribe, an iteml7ed accounting to-
gether with ap;:'op~iate <'upporting d.lta for Inclusion in
a ChJTlge Orde L'nle's otherwi'e pre',- locd in the Con-
tract Document, cost shall be lilllilcd to the folio\'. in,,:
cost of materia!- including ~,"Ies tax and cost of deli..er~';
((1-t of I.Jbor, i,,;clud ng 'oual 'ecurity, old age z,~d
unemplo~ mcn! 1~'ur2nce, and fringe benefits required bv
agrcemcnt or c~'tom; workers' or workmen's compE:nsa-
tion insurance: bond premiums; rcnt.,1 \.,Iue of equip-
ment and mad-, :-:ef\; and the addition.,! coqs of ~uper-
\ision and fielci o;{,ce per-onnel directly attributable to
the change. Per-Gins final determin,...tion of cost to the
Owner, payment, on account shall be mJde on the ,Ar-
chitect's appro\a! of a Project Certificate for Paymcnt.
19 A201/CM -- 1980
AlA DOCUMEST A201iCM . Gl'eERAl CC',JIi;O"S Of .HE CO'iTK,\CT fOR CO'STRLC;JO
CO'STRUCTIO'i \\.-\'iAG[\IE'iT [DITIO'e . )L'iE 1960 [DITIO'i . ,.\IA" . 01980 . THE
A,'.\lKICA'e I"STI1L l[ Of-\RCHI1ICT'. --,' 'eEl\ \ORK',\'E, t--:\\.., \\.'.SH:'-Gl0'i, D.C CCXX)';
_1:/'_p~~lt,jG: Ur::::~""','S(.d phcl!0copyir'>9 vio18te~ !J,S. cc.~vrjgf-)t 12.....'5 and is Eu::~-:-{.1 to If.gal rrc,:,ecution.
The 2~ount of credit to be a:':.\ed by the Contractor to
the O,\ner for any deletion or change which re<ults in a
net dE:crease in the Contr ac t 5 _ m \\ III be the a ,cou nt of
the ac:ual net cost as conf,rr;:d by the Archile-ct alter
con,u:tation with the Construction .'~anager. \\hen both
2dd,tiClns and credits covering related \Vork or substitu-
tions a'e involved in anyone change, the allowance for
o\erhead and profit shall be .. gured on the bzcis of the
net ir.uease, if any, with re,pect to that change.
12.1.5 If unit prices are st2led in the Contract Docu-
ment, or ,ubsequently agreed ~pon, and if the c;u2ntities
origlna!!y contemplated are SJ changed in a propo<ed
Chan~e Order that applicatio'. of the agreed unit Pfl(('S
to th~ quantities of \Vork propJsed will cause sub,;tJntial
inequity to the Owner or the Contractor, the 2pp!icable
unit prices shall be equitably adjusted.
12.2 CONCEALED CONDITlOSS
12.2.1 Should concealed conditions encountered in the
performance of the Work below the surface of the ground
or should concealed or unkno.\n conditions in an existing
structure be at variance with :'1e conditions indicated by
the Contract Documents, or should unknown physical
conditions below the surface of the ground or should
concealed or unknown cond:tions inan existing struc-
ture 0; an unusual nature, dif;'ering materially from those
ordinarily encountered and f.:::nerally recognized as in-
herent in work of the charactEr provided for in this Con-
tract. be encountered, the Cor-:!ract Sum shall be equita-
bly ac.usted by Change Order upon claim by either ~arty
made within twenty days after the first obser\'2nce 01 the
conditions.
12.3 ClAIMS FOR ADDITIO:\Al COST
12.3.1 If the Contractor wis~es to make a claim for an
increa;.e in the Contract Sum the Contractor shzll give
the Architect and the Constn.ction t-.\anager \\ ri:len no-
tice thereof within twenty da.s after the occurrence of
the e\ent giving rise to such claim. This notice shall be
gi\ en by the Contractor before proceeding to execute the
\Vork ~xcept in an emergenC\ endangering life or prop-
erty in which case the Conl,"ctor shall proceed in ac-
cord2"1ce with Paragraph 10.:'. No such clwel shall be
\a!id :Jnless so made. If the Owner 2nd the Contractor
cannot agree on the amount of the adjustment in the
Contract Sum, it shall be deermined by the Architect
after cOll"ultationwith the Construction .\1an2ger. ,t\nv
d-,ani:e in the Contract Sum 'esulting from <uc., claim
'~a"'>: authorized bv Ch2ns~ Oreer.
12.3.2 If the Contractor clairs that addltlon3: cc-t is in-
\ohec because of, but not li;-:-,ted to, il' 2n\ \'."Hen in-
teprelation pursuant to Subr""3sraph 2.311, ~ 2m or-
der b\ the Owner to slOp :~" \\'ork pur-uant to Para-
grapf-, 3.3 where the Contrac:.::r was not at fault or Jny
<uch ceder bv the Constructicrl Mar."ser as the 0\\ ner's
~E:ent 3) an)' written order :.Jr a minor ch2~i=e in tf-1e
\\'ork :ssued pursuant to Par,;.::-aph 12.4, or I~ iadure of
pa~ rr:~"1t by the Owner pur<~3nt to Paragrapn Q-, the
Cc,nt',.::tor shall make such c'Jim as pro\ided ''1 Sub-
r,ar2g""ph 12.3.1.
12.4 ."\INOR CHANGES IN THE WORK
12.4.1 The Architect will ha.e "uthorlt\ to o',:er minor
chanEE:s in the \Vork not ill\c\ ing an ad;ustTT,E'nt in the
Contract Sum or e),tension of the Contract Time and not
Illconsistent \\ ith the Intent of the Contract Documents.
Such changes shall be ei1'ccted by written Older issued
through the Construction ,\~anager, and shall be binding
on the Owner end the Contractor. The Contractor shall
carry out such written orders promptly.
ARTIClE 13
UNCOVERING AND CORRECTION OF WORK
13.1 UNCOVERING OF WORK
13.1.1 If any portion of the \\'ork should be co\ered
contrary to the request of the Architect or the Construc-
tion i\1anager, Or to re-quirements specifically expressed in
the Contract Documents, it must. if required in writing by
either, be unco\'ered for their observation and shall be
replaced at the Contractor's expense.
13.1.2 If any other portion of the Work has been cov-
ered which the Architect or the Construction Manager
has not specifically requested to observe prior to its being
covered, either may request to see such \\lork and it shall
be uncovered by the Contractor. If such Work be found
in accordance with the Contract Documents, the cost of
uncovering and replacement shall, by appropriate Change
Order, be char5ed to the Owner. If such Work be found
not in accordance with the Contract Documents, the
Contractor shall pay such costs unless it be found that
this condition I\as c2used by the O\\ner or a separate
contr,lctor as provided in Article 6, in which event the
Owner shall be responsible for the pa)'ment of such costs.
13.2 CORRECTION OF WORK
13.2.1 The Contractor shall promptly correct all Work
rejected by the Architect or the Construction .\1J.nager as
defective or as iailing to conform to the Contract Docu-
ments whether obsened before or after Substantial Com-
pletion 01 the Project and whether or not fabricated, in-
,tailed or com,,:eled. The Contractor shall bear all costs
of correcting ,.Jch IC'Jected \\'ork, including compensa-
tion for the :\rch:tect's and the Construction .\\anager's
additional sen ices made nece<sar)' thereby.
13.2.2 If, within one leM after the Date of Subst2ntial
Completion of the Project or designated portion thereof.
or within one \ear ;,Iter acceptance by the O\\ner of
designJted equ'pment, or within such longer period of
time as may be prescribed by law or bv the terms 01 any
applicable special warranty required bv the Contract Docu.
ments. any of the \\'ork i< found 10 be dClecl".(' or ~J)' In
accordance wltn lhe Contract Document" the Contractor
-hall correct it promp:h' after receipt of a \\ ritten notice
from the Owner to do so unles- the Owner has previ-
(lush [;llen the Contrector .1 I" 'I\ten acceptance of such
condition. Thi< ob!il.'.':on <hall <l;rvi\'e both final P2\ me:
for the \\'ork c', dc,:s",.oted po,' on thereof end term:f1a-
tion of the Co:;tract. Tr:e O\\ner shall give -uch r:o:ice
prompt!v after d'scO\er\ of the condition.
13.2.3 The CcntraC:or shall remme from ,he site all
portion- of the Work \'. ~ich are celective or nO'lconiorm-
in~ Jnd \".hicr. ~2\e not been cn~rc(ted L~ndcr Sub:J2rJ-
gr~phs 4.5.1, 132.1 ,-I'd 1'.2.2 ~nle" rem0\21 is \'.~i'ed
h the Owner.
13.2.4 If the Ccntr2l:or fails (0 correct defect:\e or non-
conforming Work as r'O\ided in Subpara~raphs -i.5.1,
~I~ DOCL:~\[~T A201/CM' G[',[R..l C.Y<DllI0', OF HE C:"-".Cl fOR CO'-S-,L.:CTIO,
(O..,s-;....CTIO~ ,l...1A~AGE,'dENT [DlT,~o.,; . !L'E :?8'~' EC':'C'-' ...\!A~; .~" 19b-,) . lHE
.",[R .::,,- I'-'STITUH OF ARCHIHC1' --35 '-[II )0;:..."\'[ '1\ \\ ..SHI'-C10'-'. ::J C cC'001
A201/C\i -1980 20
13.2.1 2nd 13.2.2, the O\\ner may correct it in accordance
with Paragraph 3.4.
13.2.5 If the Contractor does not proceed with the cor-
rection of such defective or nonconforming Work within
a rea~onable time fixed by written notice from the Archi-
tect issued through the Construction .""",,naser, the Owner
may remO\'e it and may store the materials or equipment
at the expense of the Contractor. If the Contractor does
not pay the cost of such removal and storage \\ ,thin ten
days thereafter, the Owner may, upon ten additional
days' written notice, sell such Work at auction or at pri-
vate sale and shall account for the net proceeds thereoi,
after deducting all the costs that should have been borne
by the Contractor, including compensation for the Archi-
tect's and the Construction ,''''a nager's additional services
made necessary thereby. If such proceeds of sale do not
cover all costs which the Contractor should have borne,
the diiierence shall be charged to the Contractor and an
appropriate Change Order shall be issued. If the payments
then or thereafter due the Contractor are not suiiicient to
cover such amount, the Contractor shall pay the differ-
ence to the Owner.
13.2.6 The Contractor shall bear the cost oi making
good all work of the Owner or separate contractors de-
~troyed or damaged by such correction or removal.
13.2.7 ~othing contained in this Paragraph 132 ~hall be
con<trued to establish a period of limitation \\ ith respect
to any other obligation which the Contractor might have
under the Contract Docurnent~. including Paragraph 4.5
hereof. The est.,blishment oi ;he time periods noted in
Subparagraph 132.2, or such longer period of time as
may be pre~cribed by law or by the terms of any warranty
required by the Contract Document~, relates only to the
~pecific obligation of the Contractor to correct the \Vork,
and ha~ no relationship to the time \" ithin which the
Contractor's obligation to comply \\Ith the Contracl Doc-
uments may be ~ought to be enforced, nor to the time
within which proceedings mev be commenced to e~tab-
li<h the ContrMtor's liabilit\ \'. ilh respect to the Contrac-
tor's obligations other th,ln <pecificallv 10 correct the
\\'ork.
13.3 ACCEPTAl\'CE OF DEFECTIVE OR
NONCO:-'FOR.'~I~G \\ORK
13.3.1 Ii the Owner prefers 10 accept deieck' e or non-
conforming \\'ork, the 0\1 ner may do ~o iIlsteac oi requir-
ing its removal and correction, in \Ihich ca~e a Change
Order \\ III be i"ued to reilec. " 'edGctio:l ,n :'-e Contr.lct
Sum \\ here appropriate and E:Clultable. Such "diustment
shall be effected whether or not iinal pa\ men! ha~ been
made.
ARTICLE 14
-~-
TERMINATION OF THE CONTRACT
14.1
14.1.1
unGer
HR~\I~.\ 1I0N BY THE COSTRACTOR
If Ihe \'Iork is stopped for a period of thirty days
an order of any COl'rt or o'ner public authoritv
having jurisdiction, or as a result of an act of government
such as a declaration of a national emergency making
materials unavarlable, through no act or fault of the Con-
tractor or J Subcontractor or their agents or employees or
any other persons performing any of the Work under a
contract With the Contractor, or if the \^/ork ~hould be
'lopped for a period of thirty days by the Contractor be-
cause oi the Construction Manager's failure to recom-
mend or the Architect's failure to issue a Project Certifi-
cate for Payment 2S Plovided in Paragraph 9.7 or because
the Owner has not made payment thereon as provided in
Paragraph 9.7, then the Contractor may, upon seven addi-
Ilonal days' \\ ritten notice to the Owner, the Architect
and the Construction Manager, terminate the Contract and
recover from the Owner payment for all Work executed
and for any proven loss sustained upon any materials,
equipment, tools, construction equipment and machinery,
including reasonable profit and damages.
14.2 TERMI~ATlOS BY THE OW'NER
14.2.1 If the Contractor is adjudged a bankrupt, or
makes a general assignment for the benefit of creditors,
or if a receiver is appointed on account of the Contrac-
tor's in<olvency, or if the Contractor persistently or re-
peatedly refuses or fails, except in cases for which exten-
sion of time is pro\ ided, to supply enough properly
skilled workers or proper materials, or fails to make
prompt payment to Subcontractors or for materials or
labor, or persistently disregards laws, ordinances, rules,
regulations or orders of any public authority ha\ing juris-
lion. or otherwise is guilty of a subst.,ntial violation of a
pro\ Ision of the Contract Documents, and fails within
se\'en days after receipt of written notice to commence
and continue correction of such default, neglect or \iola-
tlon \\ilh diligence .,nd promptness, the O\\ner, upon
certilrc.llion b\. the :\rchitect after COf1'.ultation \Iith the
Con<truction .\1anager that sufficient cause exists to justify
,uch action, may, after seven days following receipt by
the Contractor of an additional \\ litten notice and with-
out prejudice to any other remedy the 0\\ ner may have,
telminate the emplO\ ment of the Contractor and tJke
possession oi the site and of all materials, equipment,
lools. con<truction equipment and machinery thereon
owned bv the Contr.lctor Jnd mav finish the \\'ork bv
\\hate\er methods the Owner ma~' deem expedient. In
,uch case the Contractor shall not be entitled to receive
.1nv further pa\ment until the Work is fini,hed.
14.2.2 If II'e unpaid bal"nce oi the Contract Sum ex-
(eeeL th; co-I, oi :::- ,!.IIlS the \\ork, inc!ud:~,S co~.~)('n-
-ation for the-\rch!tect's and the CCln~truction \\anager's
,'GalliOn,,1 '-c"ices n-.ede necess.lf\ thereby, such e\cess
-h,,!' be paid to the Contractor. Ii such costs €),ceed the
unp.wl balance. the Contractor ~hall pav the difierence
:0 the O\\ner. The 2~ount to be p"id to the Contractor
or to the 0\\ ner, as the case may be. ,hall be certified by
the .-\rchitect. upon "pplication, in the manner provided
in P;;rapaph 94. and this obligation for payment shall
-Uf\!\ e the terminat;,..., of the Contract.
21 A201 /CM - 1980
.H~ OOCLJ.~\E~T ~:Ol,CM . G['ERAL CO")l~'O"S OF THE CO'-TRACT FOR CO'S1RlCTIO'
CO"S1Rl'CTIOS \',.\""\(',,,,'.;1 lOiliO" . j,'E 1980 [DITIOS . A1A~ . @1980 . THE
..",RICA' 1"11,'- ,[ OF ,\r.ClmlCTS I~',S ,,,.. YORK AVE, '"V', \1 ASHI'G10"; DC. ~0()()6
SECTION 00805
SUPPLEMENTARY GENERAL CONDITIONS
Information contained in this Supplementary Conditions amends,
supplements or clarifies the "General Conditions of the Contract
for Construction, Construction Management Edition, AlA Document
A201/CM dated June 1980 Edition.
In cases of conflict between the General Conditions and these
Supplementary Conditions, wording of this section shall govern.
ARTICLE 1
1. Subparagraph 1.1.3 - third line-after the word
"construction," delete the remaining words and insert the
following:
"and all supplies, tools, construction equipment and
machinery, water, heat, utilities, transportation, and other
facilities, services, and incidentals necessary for the
proper execution and completion of such construction; except
as expressly noted in the Scope of Work or the General
Requirements of the Contract."
2. Subparagraph 1.2.1 - delete in its entirety.
3. Subparagraph 1.2.3 - after the last word "meanings" in the
paragraph add the following sentence:
"In case of discrepancy or disagreement in the contract
documents, specifications, and/or drawings, the ORDER OF
PRECEDENCE shall be:
Contract Agreement
The addenda as issued
The Supplementary General Conditions
General Conditions
The General Requirements
The Technical Specifications
The Drawings (Large scale detail drawings take
precedence over smaller scale general drawings).
Note: Do not rely on scaled dimensions on drawings,
and any discrepancies found shall be brought to the
attention of the A/E through the CM.
01/06/92 SUPPLEMENTARY GENERAL CONCITTONS (ADD. 2)
00805 - 1
4. Add new subparagraph 1.2.5 as follows:
"\i{here on any of the drawings a portion of the Work is dra",'n
out and the remainder is indicated in outline, the parts
dra~n out shall also apply to all other like portions of the
Hork."
5. Add new subparagraph 1.3.2 as follows:
"Unless otherwise provided in the Contract Documents, the
Trade Contractor will be furnished, free of charge, all
copies of Drawings and specifications reasonably necessary
for the execution of the Work."
ARTICLE 2
1. subparagraph 2.2.1 - after the word "representative", add:
"The Construction Manager is not the General Contractor and,
unless otherwise expressly provided in the Contract
Documents, does not assume any of the traditional duties of
a General Contractor. The term Construction Manager means
the Construction Manager acting through his authorized
representative."
2. subparagraph 2.3.4 - first sentence after the word
"Architect," add "along with the Construction Manager."
3. subparagraph 2.3.7 - after the word "properly," add:
"It is the intent of the Contract Documents to allow the
Construction Manager to schedule the performance of all Hork
and the contractors are expected to follow all such schedule
direction. Should a contractor, either in person or through
his subcontractor, supplier, or vendor, fail to maintain
progress according to the Project Schedule and approved
Contractor1s Schedule, or cause delay to another Contractor:
he shall furnish additional labor and/or services such as
overtime as may be necessary to brinq his operations up to
sc_hed~le. all at.Jlo additio_nal cost to the Owner."
4. subparagraph 2.3.15 - delete in its entirety.
5 .
subparagraph
sixth (6th)
"consistent
as to cause
2.3.18 - delete the word "reasonablell in the
line. After the word Ilpromptnessll, add
with the constraints of the project schedule so
no delay."
01/06/92 SUPPLEKENrL~RY GENERAL CONDITIONS (ADD. 2)
00805 - 2
6. Subparagraph 2.3.23 - delete the phrase "against whom the
Contractor makes no reasonable objection and." Also, delete
the last sentence in the subparagraph in its entirety.
ARTICLE 3
1. Subparagraph 3.3.1 - delete from the last sentence the
phrase, ". .., except to the extent required by Subparagraph
6.1.3"
2. Subparagraph 3.4.1 - substitute three (3) days notice in
each case for the seven (7) day notices stipulated. Add at
end of subparagraph the following: "In the event of clean-
up issues, Owner has right to provide a minimum of 24 hours
notice. In the event of safety issues determined to be of a
serious nature, as determined by the CM, notice will given,
and contractor is required to rectify deficiency
immediately."
3. Subparagraph 3.2.1 - delete in its entirety.
ARTICLE 4
1. Subparagraph 4.1.1 - delete in its entirety and insert the
following:
"The Contractor is the same person or entity identified as
the Trade Contractor. A Trade Contractor is the person or
entity identified as such in the Agreement between the Owner
or Construction Manager and a Trade Contractor. The term
Trade Contractor includes one who furnishes material worked
to a special design but does not include one who furnishes
material not so worked and is referred to throughout the
Contract Documents as if singular in number and masculine in
gender. The term Trade Contractor means the Trade
Contractor or his authorized representative."
2. Add new subparagraph 4.4.3 as follows:
"The Contractor is responsible for the conduct of his
employees at all times. Misconduct, destruction of
property, unsafe practices, or violation of any Federal or
State regulations including abuse of alcohol or drugs, will
be cause for permanent dismissal from the project. If any
Contractor employee is determined to be detrimental to the
Project, as deemed by the Construction Manager, the
Contractor will remove and/or replace the employee at the
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 3
request of the Construction Manager. Employees dismissed
from the project will be transported from the jobsite at the
Contractor's expense."
3. Add new subparagraph 4.4.4 as follows:
lIThe Trade Contractor shall be totally responsible for the
security of his work, materials, equipment, supplies, tools,
machinery, and construction equipment."
4. Add new subparagraph 4.4.5 as follows:
"The Trade Contractor shall be responsible for complete,
timely and accurate field measurements as necessary for
proper coordination, fabrication and installation of his
materials and equipment. The Trade Contractor agrees to
cooperate with the Construction Manager, if required, to
accommodate any discovered variations or deviations from the
Drawings and Specifications so that the progress of the Work
is not adversely affected."
5. Subparagraph 4.9.1 - add the following sentence:
liThe superintendent shall be satisfactory to the
Construction Manager and shall not be changed except with
the consent of the Construction Manager, unless the
superintendent proves to be unsatisfactory to the Trade
Contractor or ceases to be in his employ."
6. Subparagraph 4.10.1 - add the following sentence:
"This schedule, to be submitted within three (3) days after
Contract Award, shall indicate the dates for the starting
and completion of the various stages of construction, shall
be revised as required by the conditions of the Work, and
shall be subject to the Construction Manager's approval."
7. Add new subparagraph 4.10.2:
liThe Construction Manager will conduct a weekly scheduling
meeting which the Contractor shall attend. At this meeting,
the parties can discuss jointly such matters as progress,
scheduling, and problems."
8. Add new subparagraph 4.12.9:
"If materials specified in the Contract Documents are not
available on the present market, the Trade Contractor may
01/06/92 SUPPLEHENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 4
submit data on substitute materials through the Construction
Manager to the Architect/Engineer for approval by the
Owner."
9. Subparagraph 4.14.1 - add at line 3 after "properly":
"He shall also provide protection of existing work as
required."
10. Subparagraph 4.14.2 - at end of paragraph, add:
"When structural members are involved, the written consent
of the Architect/Engineer shall also be required. The Trade
Contractor shall not unreasonably withhold from the
Construction Manager or any separate contractor his consent
to cutting or otherwise altering the Work."
11. Add new subparagraph 4.14.3:
"The Trade Contractor shall arrange for any blockouts,
cutouts, or opening required for the installation of his
materials and equipment and the execution of his work,
whether or not shown or indicated on the Drawings. The
Trade Contractor shall be further responsible for sealing
and/or finishing, in an acceptable fashion and meeting any
applicable code requirements, any such blockout, cutout
opening, or other hole in any fire-rated floor, ceiling,
wall, security wall, or any other finished surface".
12. Subparagraph 4.15.1 - at end of paragraph, add:
"Clean up shall be performed to the satisfaction of the
Owner or Construction Manager."
13. Add new subparagraph 4.16.2:
"The Trade Contractor shall promptly return telephone calls
or respond to any other form of communication initiated by
the Construction Manager. Failure to promptly do so shall
be considered a lack of performance on the part of the Trade
Contractor, and may be considered grounds for replacement of
site personnel."
14. Add new Subparagraph 4.16.3:
"All written correspondence to the Construction Manager
shall be serialized, dated, and signed by an authorized
representative of the Trade Contractor. The correspondence
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 5
15. Subparagraph 4.2.1 - at the end of the paragraph, add the
following:
"The Owner and the Architect have acknowledged that
nothing in the Architect's engagement implies any
undertaking by the Architect for the benefit of or
which may be enforced by the Contractor, its
subcontractors, or the surety of any of them; it being
understood that the Architect's obligations are to the
Owner and that, in performing such obligations, the
Architect may increase the burdens and expenses of the
Contractor, its subcontractors, or the surety of any of
them. Neither the Contractor, any Subcontractor, nor
the surety of any of them shall bring any civil suit or
other legal action against the Architect arising out of
or in connection with the Project. II
03/02/92 SUPPLEMENTARY GENER~L CONDITIONS (ADD. 6)
00805 -Sa
16. Subparagraph 4.18.1 - delete from the lOth line, the phrase,
"... (other than the \.;'ork itself)..."
At the end of the paragraph add the following paragraph:
"The first ten dollars ($10) of remuneration paid to the
CONTRACTOR is for the indemnification provided for above."
04/16/92
SUPPLEMENTARY GENERAL CONDITIONS(ADD. 10) 00805 -58
shall be directed to:
Morrison-Knudsen/Gerrits
P.O. Box 5283
Key West, Florida 33040
Attn: Doug Fuller
or hand delivered to Morrison-Knudsen/Gerrits' office
located at 5090 Junior College Road, stock Island, Florida
33040.
serialization procedures will be provided to the Trade
Contractor in the pre-construction meeting."
Each trade contractor shall be required to check his
designated mailbox regularly. This mailbox will be made
available, and located by the Construction Manager.
ARTICLE 5
1. Subparagraph 5.2.3 - delete in its entirety and insert the
following:
"If the Owner or Construction Manager refuses to accept any
person or entity on a list submitted by the Trade Contractor
in response to the requirements of the Contract Documents,
the Trade Contractor shall submit an acceptable substitute;
however, no increase in the Contract Sum shall be allowed
for any such substitution."
ART]CLE 6
1. Subparagraph 6.1.1 - delete the last sentence.
2. Subparagraph 6.1.3 - delete in its entirety, and insert the
following:
"It shall be the responsibility of each contractor to
coordinate his work with the work of other contractors
on the site. The Owner, A/E and Construction Manager
shall be held harmless of any and all costs associated
with improper coordination."
3. Subparagraph 6.2.5 - sixth line, after the word "initiates,"
delete the words "an arbitration proceeding" and substitute
"a claim;" tenth line, delete the words "at the Owner's
expense, and"; thirteenth line, after the words .'and court
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 6
or," delete the word "arbitration" and substitute "claim."
4. Add new subparagraph 6.2.6:
IIShould the Contractor contend that he is entitled to
an extension of time for completion of any portion or
portions of the work, he shall, within (72) hours of
the occurrence of the cause of the delay, notify the
Construction Manager in writing, of his contention:
Setting forth (A) The cause for the delay, (B) A
description of the portion or portions of work affected
thereby, and (C) all details pertinent thereto. A
subsequent written application for the specific number
of days of extension of time requested shall be made by
the Contractor to the Construction Manager within (72)
hours after the delay has ceased to exist.
It is a condition precedent to the consideration or
prosecution of any claim for an extension of time that
the foregoing provisions be strictly adhered to in each
instance and, if the Contractor fails to comply, he
shall be deemed to have waived the claim.
The Contractor agrees that whether or not any delay,
regardless of cause, shall be the basis for an
extension of time he shall have no claim against the
Owner, AlE or Construction Manager for an increase in
the contract price, nor a claim against the Owner, AlE
or Construction Manager for a payment or allowance of
any kind for damage, loss or expense resulting from
delays: Nor shall the Contractor have any claim for
damage, loss or expense resulting from interruptions
to, or suspension of, his work to enable other
contractors to perform their work. The only remedy
available to the Contractor shall be an extension of
time."
ARTICLE 7
1. subparagraph 7.1.1 - delete in its entirety and insert the
following:
liThe contract shall be governed by the laws of the State of
Florida. Venue for any claims or disputes arising under
this contract shall be in the Circuit Court of the 16th
Judicial Circuit of the State of Florida."
-
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 7
2. Subparagraph 7.2.1 - delete in its entirety and insert the
following:
"The Owner or Construction Manager (as the case may be) and
the Trade Contractor each binds himself, his partners,
successors, assigns, and legal representatives of such other
party in respect to all covenants, agreements, and
obligations contained in the Contract Documents. Neither
party to the Contract shall assign the Contract or sublet it
as a whole without the written consent of the other."
3. Add new Subparagraph 7.2.2:
"The Trade Contractor shall not assign any monies due or to
become due under this Contract without prior written consent
of the Owner or Construction Manager. II
4. Subparagraph 7.8.1 - delete in its entirety.
5. Paragraph 7.9 'Arbitration' and all associated subparagraphs
7.9.1, 7.9.2, & 7.9.3 - delete in their entirety.
ARTICLE 8
1. Subparagraph 8.3.1 - delete in its entirety and insert the
following:
"If the Trade Contractor is delayed, at any time, in the
progress of the Work, by any act or neglect of the Owner,
Construction Manager, or the Architect/Engineer, or by any
employee of either, or by any separate contractor employed
by the Owner, or by changes ordered in the Work, or by fire,
unusual delay in transportation, adverse weather conditions
not reasonably anticipatable, unavoidable casualties or any
causes beyond the Trade Contractor's control, or by delay
authorized by the Owner, Construction Manager, or by any
other cause which the Construction Manager determines may
justify the delay, then the Contract Time shall be extended
by no cost Change Order for such reasonable time as the
Construction Manager may determine, in accordance with
subparagraph 6.2.6."
2. Subparagraph 8.3.2 - replace the remainder of the Paragraph
after the word "waived" in line 4 with the follovling:
"Any claim for extension of time shall state the cause of
the delay and the number of days of extension requested. If
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 8
the cause of the delay is continuing, only one claim is
necessary, but the Trade Contractor shall report the
termination of the cause for the delay within twenty (20)
days after such termination; otherwise, any claim for
extension of time based upon that cause shall be waived."
3. Subparagraph 8.3.4 - delete in its entirety and insert the
following:
lilt shall be recognized by the Trade Contractor that he may
reasonably anticipate that as the job progresses, the
Construction Manager will be making changes in, and updating
Construction Schedules. No claim for an increase in the
Contract Sum for either acceleration or delay will be
allowed for extensions of time pursuant to this Paragraph
8.3 or for other changes in the Construction Schedules which
are of the type ordinarily experienced in projects of
similar size and complexity."
4. Add new subparagraph 8.3.5:
"If the Project is delayed as a result of the Trade
Contractor's refusal or failure to begin the Work on the
date of commencement as defined in paragraph 8.1.2, or his
refusal or failure to carry the Work forward expeditiously
with adequate forces, the Trade Contractor causing the delay
shall be liable, but not limited to, delay claims from other
Trade Contractors which are affected."
ARTICLE 9
1. Subparagraph 9.3.3 - add at line 14 after the word "person":
"All Trade Subcontractors and Trade Subsubcontractors shall
execute an agreement stating that title will so pass, upon
their receipt of payment from the Trade Contractor."
2. Subparagraph 9.5.1 - add:
"From the total of the amount determined to be payable on a
progress payment, 10 percent of such total amount will be
deducted and retained by the Owner until final payment is
made. The balance (90 percent) of the amount payable, less
all previous pal~ents, shall be certified for payment. When
not less than 95 percent of the work has been completed, the
Owner may, at his/her discretion (and with the consent of
the surety), prepare an estimate from which will be retained
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 9
an amount not less than twice the contract value or
estimated cost, (whichever is greater), of the work
remaining to be done. The remainder, less all previous
payments and deductions, will then be certified for payment
to the Contractor.
It is understood and agreed that the Contractor shall not be
entitled to demand or receive progress payment based on
quantities of work in excess of those provided in the
proposal or covered by approved change orders, except when
such excess quantities have been determined by the
Construction Manager to be a part of the final quantity for
the item of work in question.
No progress payment shall bind the Owner to the acceptance
of any materials or work in place, as to quality or
quantity. All progress payments are subject to correction
at the time of final payments.
3. Add new subparagraph 9.5.6:
"All material and work covered by partial payments made
shall thereupon become the sole property of the Owner, and
by this provision shall not be construed as relieving the
Trade Contractor from the sole responsibility for the
materials and work upon which payments have been made or the
restoration for any damaged material, or as a waiver to the
right of the Owner or Construction Manager to require the
fulfillment of all the terms of the Contract."
4. Add new subparagraph 9.5.7:
"Except in case of bona fide disputes, or where the Trade
Contractor has some other justifiable reason for delay, the
Trade Contractor shall pay for all transportation and
utility services not later than the end of the calendar
month following that in which services are rendered and for
all materials, tools, and other expendable equipment which
are delivered at the site of the Project. The Trade
Contractor shall pay, to each of his Trade Subcontractors,
not later than the end of the calendar month in which each
payment is made to the Trade Contractor, the representative
amount allowed the Trade Contractor on account of the work
performed by his Trade Subcontractor interest therein. The
Trade Contractor shall, by an appropriate agreement with
each Trade Subcontractor, also require each Trade
Subcontractor to make payments to his suppliers and Trade
Subsubcontractors in a similar manner."
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 10
5. Subparagraph 9.6.1 - delete in its entirety and insert the
following:
liThe Construction Manager/Architect may decline to approve
an Application for 'payment if, in his opinion, the
application is not adequately supported. If the Trade
Contractor and Construction Manager cannot agree on a
revised amount, the Construction Manager shall process the
Application for the amount he deems appropriate. The
Construction Manager may also decline to approve any
Applications for Payment or, because of subsequently
discovered evidence or subsequent inspections, he may
nullify, in whole or part, any approval previously made to
such extent as may be necessary in his opinion because of:
(1) defective work not remedied; (2) third party claims
filed or reasonable evidence indicating probable filing of
such claims; (3) failure of the Trade contractor to make
payments properly to Trade Subcontractors or for labor,
materials, or equipment; (4) reasonable evidence that the
work cannot be completed for the unpaid balance of the
Contract Sum; (5) damage to the Construction Manager, the
Owner, or another contractor working at the project; (6)
reasonable evidence that the Work will not be completed
within the contract time; (7) persistent failure to carry
out the Work in accordance with the Contract Documents.
9.6.1.1 No payment shall be made to the Trade
Contractor until certificates of insurance or other
evidence of compliance by the Trade Contractor, within
all the requirements of Article 12, have been filed
with the Owner and Construction Manager. Further, no
payments on the basis of work performed by a Trade
Subcontractor shall be paid until copies of all bonds
required by Paragraph 7.5 and any certificates of
insurance required of the Trade Subcontractors under
Article 12 have been filed with the Owner."
6. Subparagraph 9.7 - delete in its entirety.
ARTICLE 11
1. Add new subparagraph 11.1.2.1:
The following coverages are required to be ~aintained by all
Trade Contractors and subcontractors in any tier throughout
the entire length of the contract and any extensions
thereof.
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 11
1. Premises and Operation Liability Insurance:
commercial General Liability Insurance shall be
obtained in amounts of not less than $1,000,000 each
occurrence.
coverage shall specifically include:
a. Bodily injury and property damage liability
coverage for premises and operations.
b. Products and completed operations.
c. Independent contractor's exposures.
d. Property damage resulting from explosion,
collapse, or underground (x,c,u) exposures.
e. Blanket contractual liability covering this
contract.
f. Personal injury liability.
g. Broad form property damage liability.
2. Automobile Liability Insurance:
Comprehensive automobile liability insurance shall
include coverage for bodily injury and property damage
liability for a minimum limit of $1,000,000 each
occurrence and shall cover use of owned, non-owned, and
hired vehicles, and include employers' non-ownership
liability coverage.
3. Workers Compensation and Employers Liability Insurance:
statutory Workers' Compensation coverage including
Employers Liability coverage with limits of not less
than $100,000 per person per accident and $500,000 per
person per occurrence for disease. Coverage shall be
provided to cover operations in the state of Florida
and the Voluntary Compensation endorsement shall be
provided. Coverage for ,eberally enacted benefits
shall be provided where applicable.
All insurance policies except the Workers Compensation and
Employers Liability Insurance policy, are required in the
name of Monroe County Board of County Commissioners and
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 12
Morrison-Knudsen/Gerrits as Additional Insured, and provide
a minimum of sixty (60) days notice in the event of
termination, non-renewal or reduction in coverage. Policy
language shall be modified to provide liability coverage for
Cross Liability Suits between insureds ~ithout increasing
the total policy limits. Monroe County reserves the right
to require additional insurance as may be deemed necessary
for any specific project or work.
Insurers providing coverage(s) must be financially stable
and authorized to do business in the state of Florida. The
Monroe County Board of County Commissioners reserves the
right to reject any insurer that it believes to be
unacceptable.
Failure to maintain required insurance coverage in effect
will provide Monroe County, Florida with the option of
terminating the contract upon written notice to the
Construction Manager.
certificates expiring during the term of the contract shall
be replaced with new certificates prior to the expiration of
the original certificates.
Complete and certified copies of all insurance contracts
shall be furnished to The Monroe County Board of County
commissioners if requested.
The certificate Holder on all insurance policies 1S required
to be as follows:
Monroe County Board of County Commissioners, or Monroe
County,
c/o Morrison-Knudsen/Gerrits
P.O. Box 5283
Key West, FL 33040
2. Subparagraph 11.3.7 - second sentence, celete the phrase,
"..., or in accordance with an award by arbitration in which
case the procedure shall be as provided in Paragraph 7.9"
3. Subparagraph 11.3.8 - first sentence, delete the phrase,
'1.. .arbitrators shall be chosen as provided in Paragraph
7.9"
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (~~D. 2)
00805 - 13
4. Subparagraph 11.3.1 - delete in its entirety, and insert the
following:
II Throughout the term of the CONTRACT, the O\'iNER shall
purchase and maintain property insurance on the
completed value of the permanent facility only. The
completed value is defined as all material, labor,
supplies, and equipment intended to be incorporated in
and to become a permanent part of the completed
facility. Such insurance shall include perils of fire,
lightning, and extended perils. The facility as
defined for 11.3.1 includes structures as defined in
the contract drawings and specifications.
Notwithstanding any provisions contained in this
paragraph, the CONTRACTOR shall be responsible for the
first $10,000 on any loss governed by this section.
The CONTRACTOR understands that the O\'iNER I S property
insurance policy contains certain exclusions which are
available upon request from the CONSTRUCTION t-lANAGER. II
04/16/92
SUPPLEMENTARY GENERAL CO~mITIONS (ADD. 10) 00805 -13A
ARTICLE 12
1. Subparagraph 12.1.3 - under item .1, add the following at
the end of the sentence, II as set forth in subparagraph
12.1.611
2. Subparagraph 12.1.4 - replace the remainder of the
paragraph, after the ....:ord "changell in line 25, with the
following:
"Pending final determination of cost, payments on account
shall be made as determined by the Construction Manager.
The amount of credit to be allowed by the Trade Contractor
for any deletion or change, which results in a net decrease
in the Contract Sum, will be the amount of the actual net
cost as confirmed by the Construction Manager. When both
additions and credits covering related Work or substitutions
are involved in anyone change, the allowance for overhead
and profit shall be figured on the basis of the net
increase, if any, with respect to that change."
3. Add new subparagraph 12.1.6:
"The actual cost of Changes in the Work may include all
items of labor or material, power tools, and equipment
actually used, utilities, pro rata charges for foreman, and
all payroll charges such as Public Liability and Workman's
Compensation Insurance. No percentage for overhead and
profit shall be allowed on items of Social Security and
Sales Tax. If deductions are ordered, the credit shall be
the net cost. Items considered as overhead shall include
insurance other than that mentioned above, bond or bonds,
superintendent, timekeeper, clerks, watch~en, use of small
tools, incidental job costs, and general office expenses.
The actual cost of Changes in the Work (other than those
covered by unit prices set forth in the Contract Documents)
shall be computed as follows:
12.1.6.1 If the Trade Contractor performs the actual
Work, the percentage mark-up for overhead and profit
shall be a rnaxirr~~ addition of fifteen percent (15%).
12.1.6.2 If the Trade Subcontractor performs the
actual Work, the percentage mark-up for overhead and
profit shall be a maximum addition of fifteen percent
(15%). If the Trade Contractor does not enter into the
Work, the maximuD mark up for managing this work will
be ten percent (10%).
01/06/92 SUPPLEMENTARY Ge~ERAL CONDITIONS (ADD. 2)
00805 - 14
12.1.6.3 If the Trade Subcontractor performs part of
the actual work, his percentage mark-up for overhead
and profit shall be a maximum addition of fifteen
percent (15%) on his direct work only. If the Trade
Contractor performs part of the actual work, his
percentage mark-up for overhead and profit shall be a
maximum addition of fifteen percent (15%) on his direct
work only.
4. Add new subparagraph 12.1.7:
liThe Trade Contractor shall furnish to the Owner through the
Construction Manager, an itemized breakdown of the
quantities and prices used in computing the value of any
change that might be ordered."
5. Subparagraph 12.3.1 - delete in its entirety and insert the
following:
"If the Trade Contractor claims that any instructions given
to him by the Construction Manager, by drawings or
otherwise, involve extra work not covered by the Contract,
he shall give the Construction Manager written notice
thereof within three (3) days after the receipt of such
instructions and before proceeding to execute the work,
except in emergencies endangering life or property, in which
case the Trade Contractor shall proceed in accordance with
Paragraph 10.3."
Should it not be clear to the Trade Contractor that a change
will involve extra work, written notice given within three
(3) days that the change may involve extra work will be
sufficient notice. If it is later determined that the work
involved in such instruction shall be recognized as an
extra, the amounts of additional compensation to be paid
therefore should be determined in accordance with Paragraph
13.1.
Except as otherwise specifically provided, no claim for
additional cost shall be allowed unless the notice specified
by this Subparagraph is given by the Trade Contractor. If
the Contractor considers that the changed work involves
extra costs, the costs shall be accounted for, and presented
in accordance with subparagraph 12.1.3. All claims shall be
submitted to the Owner through the Construction Manager. II
6. subparagraph 12.3.2 - change the word 'agent' in the 7th
line, to 'representative'. Also, delete item (4).
01/06/92 SUPPLD1ENTARY GEl"'ERAL CONDITIONS (ADD. 2)
00805 - 15
7. Add new subparagraph 12.3.3:
"Unless otherwise agreed in writing, the Contractor
shall carryon the Work and maintain its progress
during any dispute or claim proceeding, and Owner shall
continue to make payments to the Contractor in
accordance with the Contract Documents. Disputes
unresolved shall be settled in accordance with
subparagraph 7.1.1."
ARTICLE 14
1. Subparagraph 14.1.1 - starting at the 8th line, delete the
phrase, "..., or if the Work should be stopped for a period
of thirty days by the CONTRACTOR because of the CONSTRUCTION
MANAGER's failure to recommend or the ARCHITECT's failure to
issue a Project Certificate for Payment as provided in
Paragraph 9.7 or because the OWNER has not made payment
thereon as provided in Paragraph 9.7"
2. subparagraph 14.2.1 - change the words 'seven days' in the
13th and 18th line, to '72 hours'.
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 16
SECTION 00970
PROJECT SAFETY AND HEALTH PLAN
1.1
REGULATIONS AND POLICIES
1.1.1
1.2
1.2.1
Every Trade Contractor and Trade Subcontractor employed
on the Project shall comply with all applicable local,
State, and Federal safety and health regulations and
with Morrison-Knudsen Company, Inc. safety and health
policies as described herein.
PROJECT SAFETY AND HEALTH REQUIREMENTS
It is recognized that it is good business and evidence
of competent leadership to prevent the occurrence of
incidents that lead to occupational injuries or
illnesses. Safety and health requirements on this
project include, but are not limited to, the following:
.1 In general, this accident prevention policy is
based on a sincere desire to eliminate personal
injuries, occupational illnesses, and equipment
and property damage; and to protect the general
public exposed to or associated with the work.
.2 The importance of the safety of all workers on the
project shall be recognized and accident
prevention shall be an integral part of all
operations.
.3 Each Trade Contractor and Trade Subcontractor
shall conduct work in a safe and practical manner
in conformance with the OSHA Safety and Health
Regulations and the latest edition of the Manual
of Accident Prevention, Associated General
Contractors of America.
.4 Each Trade Contractor and Trade Subcontractor
shall observe all applicable Federal, State, local
and project laws and regulations pertaining to
safety and health, pollution control, water
supply, fire protection, sanitation facilities,
waste disposal and other related items.
.5 The Mandatory Safety and Health Rules shall be
posted in a conspicuous location along with the
OSHA and Emergency Phone Number posters.
-
11/21/91
00970 - 1
PROJECT SAFETY AND HEALTH PLAN
.6 A record of all occupational injuries and
illnesses shall be maintained. Medical and lost
time cases shall be properly recorded on the OSHA
log, and reported to MORRISON-KNUDSEN/GERRITS. A
copy of the insurance report for workmen
compensation cases shall be provided to MORRISON-
KNUDSEN/GERRITS.
.7 Each Trade Contractor and Trade Subcontractor
shall provide or arrange for adequate first aid
facilities, emergency transportation and persons
qualified in first aid.
.8 Each Trade Contractor and Trade Subcontractor
shall cooperate fully with all other contractors
in their respective safety and health programs.
.9 Good housekeeping shall be observed at all times.
Waste, debris, and garbage shall be removed daily
or placed in appropriate waste containers. All
materials, tools, and equipment shall be stored in
a safe and orderly fashion. Each contractor shall
donate 10% of their staff to a crew that will
convene every Friday at 1:00pm for a joint site
clean-up effort not to exceed a duration of three
hours.
In summary, there will be a ]-part clean-up plan.
The first part consists of the contractor cleaning
up on a daily basis, his workstations, and his
trade work. The second part consists of the
general clean-up, the concerted effort by all
trade contractors working on the project. A
minimum of (1) crew is to be utilized by each
contractor, or 10%, whichever is more. The third
part consists of the Owner cleaning up for a
particular trade contractor should adequate notice
not compel him to clean up his work. In this
case, the appropriate contractors will be
backcharged.
.10 This project shall be a Hard Hat job and all
supervisors, employees and visitors shall be
required to wear a suitable hard hat while on the
project site.
.11 other appropriate personal protective equipment
shall be provided and worn as required including
11/21/91
PROJECT SAFETY ~ND HEALTH PLAN
00970 - 2
but not limited to long pants, shirts with sleeves
and appropriate leather work boots.
.12 Temporary construction aids such as ladders,
scaffolds, stairs, railings, etc. shall be
provided to facilitate access or working
conditions in a manner that shall conform to the
safety standards specified by Federal, state,
Local or manufacturer's recommendations or
stipulations.
.13 Each Trade Contractor and Trade Subcontractor
shall be expected to indoctrinate his employees as
to the safety and health requirements of this
project and to enforce adherence to safe work
procedures.
.14 If MORRISON-KNUDSEN/GERRITS notifies any Trade
Contractor of any noncompliance with the
provisions of this program, the Trade Contractor
shall make all reasonable efforts to immediately
correct the unsafe conditions or acts.
Satisfactory corrective action shall be taken
within the specified time. If a Trade Contractor
or Trade Subcontractor refuse to correct unsafe or
unhealthy conditions or acts, MORRISON-
KNUDSEN/GERRITS shall take one or more of the
following steps:
a. Cease the operation or a portion thereof.
b. stop payment for the work being performed.
c. Correct the situation using other forces and
back charge the Trade Contractor expenses
incurred.
d. Increase withholding in proportional
increments for that given pay period.
.15 All Trade Contractor's Superintendents shall be
required to attend and participate in all general
project safety meetings. These meetings will be
included in the weekly coordination meetings as
previously specified or on an as needed basis.
.16 All Trade Contractors shall conduct Weekly Tool
Box Safety Training Meetings, and shall document
11/21/91
00970 - 3
PROJECT SAFETY AND HEALTH PLAN
1.3
1. 3.1
1.4
1. 4.1
the minutes on the forms provided. These forms
are to be transmitted to Morrison-Knudsen/Gerrits
on a weekly basis. All employees working at the
project site shall be required to attend and
participate in the meetings.
.17 Shortly after the award of the contract and prior
to the beginning of work, an Activity Hazard
Analysis (phase plan) shall be prepared by the
contractor and submitted to Morrison-
Knudsen/Gerrits for approval. The analysis will
address the hazards for each activity to be
performed in that phase and will present the
procedures and safeguards necessary to eliminate
the hazards or reduce the risk to an acceptable
level. A phase is defined as an operation
involving a type of work presenting hazards not
experienced in previous operations or where a new
subcontractor or work crew is to perform work.
The analysis will be discussed by the contractor
and Morrison-Knudsen/Gerrits on-site
representatives at the Preparatory Inspection
Meeting. Work will not proceed on that phase
until the Activity Hazard Analysis (phase plan)
has been accepted by Morrison-Knudsen/Gerrits.
.18 No personal radios or stereos will be allowed on
the job-site.
FIRE PROTECTION
Every Trade Contractor and Trade Subcontractor employed
on the Project shall exercise good construction
practices to prevent fire. It shall be the
responsibility of the Trade Contractor to insure that
general fire protection facilities are adequate for his
~ork and to provide additional fire protection
facilities and devices, including fire extinguishers as
required by their scope of work.
iWRK NEAR ENERGIZED ELECTRICAL LINES OR OTHER UTILITIES
It shall be the Trade Contractor's sole and exclusive
responsibility (a) to provide personnel capable of
~orking adjacent to energized electrical lines or other
utilities; (b) to provide adequate, safe and properly
~aintained equipment; (c) to conduct all of his work in
accordance with the safety rules and regulations
11/21/91
PROJECT SAFETY AND HEALTH PLAN
00970 - 4
1.5
1.5.1
1.5.2
1.5.3
prescribed by the National Electric Code, National
Electric Safety Code, H30, and Safety Rules for
Installation and Maintenance of Electrical Supply and
Communication Lines Hand Book 81, Occupational Safety
and Health Act of 1970, as well as other safety codes
in effect at the site of construction and as specified
elsewhere herein, or as are generally applicable to the
type of work being performed; and (d) to continuously
supervise and inspect the work being performed to
assure that the requirements of (a), (b), and (c) above
are complied with and nothing in these Contract
Documents shall be held to mean that any such
responsibility is the obligation of the Owner or the
Architect or the Construction Manager.
BARRICADES, WARNING DEVICES AND LIGHTING
The Trade Contractor shall be solely responsible for
providing temporary ladders, guard rails, warning
signs, barricades, night guard lights, and deck or
floor closures required in connection with his work to
comply with Federal, State and local safety
requirements. The Trade Contractor shall be solely and
exclusively responsible for the design, construction,
inspection and maintenance of such facilities at all
times.
It shall be the responsibility of the Trade Contractor
to provide additional temporary lighting, if needed to
maintain safe conditions.
It shall be the sole and exclusive responsibility of
the Trade Contractor to provide a safe place to work
for all laborers and mechanics and other persons
employed on or in connection with the project, and
nothing in these Contract Documents shall be construed
to give any of such responsibility to the Owner, the
Architect, or the Construction Manager.
11/21/91
PROJECT SAFETY AND HEALTH PLAN
00970 - 5
SECTION 00980
CONTRACTOR QUALITY CONTROL PLAN
1.1
1.1.1
1.2
1.2.1
1.2.2
1.2.3
1. 2.4
MORRISON-KNUDSEN/GERRITS' DUTIES AND RESPONSIBILITIES
The Morrison-Knudsen/Gerrits' superintendent will
monitor all work performed by the Trade Contractor and
assist the Trade Contractor with his conformance of the
work to the Contract Drawings and Specifications.
TRADE CONTRACTOR'S DUTIES AND RESPONSIBILITIES
The Trade Contractor is responsible for the quality of
the work performed by his work force on this project as
well as the quality of the material, equipment and
supplies furnished by him to be incorporated into the
work.
The Trade Contractor will designate a Quality Control
Representative who will be on site at all times while
the respective Trade Contractor's work is in progress
and will have the authority and responsibility to
accept or reject items of work. The Trade Contractor's
Quality Control Representative may delegate his duties
but the primary responsibility and authority will rest
on him.
The Trade Contractor's Quality Control Representative
will coordinate the submittal of all shop drawings,
product data and samples to Morrison-Knudsen/Gerrits.
Any submittal that is a variance to the contract
requirements must be identified as such and transmitted
to the Construction Manager for submittal and approval
by the Architect/Engineer or Owner. No work requiring
submittal of a shop drawing, product data or sample
shall commence until the submittal has been reviewed
and approved by the Architect/Engineer.
The Trade Contractor will bear the responsibility of
notifying the designated material-testing laboratory,
whether Monroe County or Contractor is required to
perform testing of materials as required by the
contract drawings and specifications in a timely
fashion to prevent needless cancellations and delays of
work activities. Any costs caused by untimely
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
00980 - 1
1. 2.5
1. 2.6
1.3
1. 3.1
notification shall be borne by the Contractor.
The Trade Contractor's Quality Control Representative
will review his drawings, procurement documents and
contracts to insure that the technical information
provided and all work performed is in accordance with
the latest revisions of the Contract Drawings and
Specifications.
The Trade Contractor's Quality Control Representative
will perform an inspection upon receipt at the site of
the work of all ~aterials, equipment and supplies
including those furnished to him by the Owner. Notes
from this inspection will be filled out on the
appropriate form and included with the Contractor Daily
Quality Control Report. Items which are damaged or not
in conformance with the respective submittals, quality
standards, contract drawings and specifications shall
be brought to the attention of Morrison-
Knudsen/Gerrits' representative on site and then will
be identified and segregated from accepted items.
Items thus identified will not be incorporated into the
work until corrective action acceptable to Morrison-
Knudsen/Gerrits is completed. Items determined
unsalvageable will be removed from the job site. These
items shall be noted as deficient in the applicable
section of the Contractor Daily Quality Control Report.
INSPECTION AND TESTING
INSPECTION PLAN
Morrison-Knudsen/Gerrits utilizes a multi-point
inspection plan for each separate feature of work to be
performed under this Trade Contract, i.e., work
described by each division of the technical provision
section of the contract specifications. This plan
consists of the following:
.1 Preparatory Inspection - Prior to commencing the
work, the Trade Contractor's Quality Control
Representative will meet with ~orrison-
Knudsen/Gerrits' Superintendent and the
Architect's representative if he so desires to
attend and check the following items at a minimum
for conforrr3nce:
(a) Approval of shop drawings and submittals.
00980 - 2
11/21/91 CONTRACTOR QUALITY CONTROL PLAN +ABJJ...--3+
(b) Approval of inspection and test reports of
materials and equipment to be utilized.
(c) Completion of previous operations of
preliminary work.
(d) Availability of materials and equipment
required.
(e) Potential utility outages.
(f) Any other preparatory steps dependent upon
the particular operation.
(g) Quality standards.
(h) Safety or environmental precautions to be
observed. (Phase Hazard)
Note:
Morrison-Knudsen/Gerrits will record the minutes
to this inspection meeting and distribute
accordingly.
.2
Initial inspection - Upon completion of a
representative sample of a given feature of the
work, the Trade Contractor's Quality Control
Representative will meet with the Morrison-
Knudsen/Gerrits Superintendent and the Architect's
representative if he so desires to attend and
check the following items at a minimum for
conformance:
(a) Workmanship to established quality standards.
(b) Configuration to contract drawings and
specifications.
(c) Construction methods, equipment and tools
utilized.
(d) Materials and articles utilized.
(e) Adequacy of testing methods.
(f) Adequacy of shop drawings.
(g) Adequacy of safety or environmental
precautions.
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
00980 - 3
Note:
. 3
Note:
Note:
Morrison-Knudsen/Gerrits will record the minutes
to this inspection meeting and distribute
accordingly.
Follow-up Inspections - The Trade Contractor's
Quality Control Representative will inspect the
work daily to assure the continuing conformance of
the work to the workmanship standards established
during the preparatory and initial inspections.
Additionally, as a part of the follow-up
inspection, sign-off sheets will be utilized as
often as possible. The intent of these sheets is
to achieve concurrence from other trade
contractors and responsible parties that ensuing
work can indeed commence over underlying work.
This will prevent oversights and omissions which
could elevate costs. sign-off sheets shall be
used for, but not be limited to, concrete,
drywall, ceilings, painting, roofing substrates
and flooring. These reports are to be generated
by the applicable Trade Contractor and submitted
to Morrison-Knudsen/Gerrits' superintendent for
approval prior to the start-up of work.
Failure to generate a sign-off sheet or to attain
proper signatures prior to covering up underlying
work may affect payment for that piece of work if
ensuing problems are detected or not. This
disciplinary action shall be carried out via the
Nonconformance Report. (See section 1.4.2 of this
plan.)
The Trade Contractor shall be responsible to
record these inspections and all other project
related activities encountered throughout the day
on the Contractor Daily Quality Control Report.
. 4
Completion Inspections - Upon completion of a
given feature of the work, the Trade Contractor's
Quality Control Representative will meet with
11orrison-Knudsen/Gerrits' superintendent, if he so
desires to attend, to perform an inspection of the
completed work. Non-conforming items will be
identified and corrected prior to commencement of
the next operation.
The Trade Contractor shall conduct and report
00980 - 4
11/21/91 CONTRACTOR QUALITY CONTROL PLAN +~
1.3.1.5
1.3.1.6
1. 3.2
1. 3.3
corrections of this inspection which shall be a
required submittal.
Follow-On Inspections - Upon execution of the
contractor's completion inspection in elements of the
work which result in concealment; such as, ceiling and
drywall installations, MK/G shall schedule and conduct
multi-trade or singular inspections prior to covering
installation.
Note:
MK/G will record the minutes to this
inspection meeting.
Pre-Final Inspection - Upon substantial completion of
the project work MK/G shall coordinate and conduct a
universal inspection of all areas and elements of the
work. The Architect/Engineer may be represented if he
so desires. This inspection shall be completed at
least (15) days prior to the final substantial
completion inspection which shall be conducted by the
A/E. All deficiencies and incomplete work should be
completed prior to the final substantial completion
inspection.
OPERATION AND CHECK OUT TESTING
The Trade Contractor will provide personnel and
equipment to perform the operational tests and checkout
of the equipment, facilities or equipment constructed,
fabricated or installed under this Trade Contract.
Morrison-Knudsen/Gerrits' Superintendent will
coordinate and witness all such tests. Notification
should be given at least ten (10) days in advance of
the scheduled tests.
FINAL INSPECTION and issuance of the A/E CERTIFICATE OF
SUBSTANTIAL COMPLETION
Morrison-Knudsen/Gerrits' Superintendent will
coordinate and attend all final inspections of the work
by the Architect/Engineer. Prior to requesting a final
inspection, all tests for the equipment and systems
must be completed.
Upon completion of the AlE's inspection, the AlE will
publish outstanding items and issue a Project
certificate of Substantial Completion, which will
define the date of 'Turn-Over' to the Owner the care,
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
00980 - 5
control and custody. Reference section 00800,
Substantial Completion.
1.4
REPORTING
Maintaining accurate and retrievable records is
extremely important in the Quality Assurance Program.
These records will act as a main source of information
in the present and in the future for the entire project
management team. The main report that will be utilized
to provide this information is the Daily Quality
Control Report. Nonconformance Reports may also be
issued.
1. 4.1
DAILY QUALITY CONTROL REPORT
The Daily Quality Control Report shall be used to
document the surr~ary of daily inspection activities
performed by the Trade Contractor's designated Quality
Control Representative. It shall include any of the
steps of inspection that are performed that day, all
test monitoring and any rework of nonconforming items.
The daily Quality Control Report section of the Daily
Superintendent's Report will be routinely used for
daily reporting requirements. When the magnitude or
complexity necessitates such, a more separate and
comprehensive form will be used. Reference
Contractor's Daily Report, and as needed Contractor
Daily Quality Control Report, section 01385.
1. 4.2
NONCONFORMANCE REPORT
Nonconformance Reports will be issued for work that is
found to be in nonconformance with the contract
documents or the referenced quality standards. The
report will be issued by Morrison-Knudsen/Gerrits.
It is not the intent to routinely and repeatedly issue
nonconformance reports, but to issue them only after
normal enforcement standards have been exhausted, or if
the work performed is a detriment to the project.
A copy of the Nonconformance Report will be forwarded
to the Project Manager for his information and/or
action. It should also be included in the Trade
Contractor's Daily Quality Report package for general
review.
-
11/21/91 CONTRACTOR QUALITY CONTROL PLAN ffu~D. 3)
00980 - 6
Nonconformance Reports will be signed off once the
deficient item or items have adequately been corrected.
This will be done by the issuing Superintendent and
Project Manager. These sign-offs will be included with
a corresponding corrective action taken. Significant
nonconformances need to be addressed to prevent
recurrence. The signed-off report will also be
submitted for review.
Work activities affected by a Nonconformance Report
will proportionally counteraffect payments. Whether
that be partial or full retainage will be left up to
the discretion of Morrison-Knudsen/Gerrits' management
team.
1.5
NOT USED
1.6
AUDITS
1. 6.1
Morrison-Knudsen/Gerrits may choose at its option to
perform Trade Contractor audits of their Contractor
Quality Control Plan at any time. Reports of these
audit results will be forwarded to the Project Manager
for his action. Any action items noted during an audit
for the Trade Contractor will be followed up and
documented to insure compliance ar.d avoid recurrence.
1.7
SUMMARY
The intention of this plan is to create a system of
checks and balances that will minimize delays caused by
rework and a lack of planning and maximize production
and insure that the finished product is one that the
entire construction team can pride themselves in.
These goals can be achieved by giving the Owner exactly
what he has bought. The owner wi~l expect no more and
through Quality Assurance, the cor.struction team will
provide no less.
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (:.JO. 3)
00980 - 7
SECTION 00800
SUBSTANTIAL COMPLETION AND OWNER ACCEPTANCE
Bid Group 2, and Bid Group 3 Contractors shall turn over care,
custody and control of their work to the Owner as defined in the
issuance of the A/E's Certificate of Substantial Completion of the
Project. All contracts in these bid groups shall exchange as a
group and in unison, possession, maintenance and security
responsibilities with the Monroe County Officials. Any portion of
the work which is in non-conformance with the contract documents or
elements which prevent the Owner's use of the facilities for its
intended use shall be excluded from acceptance. The contractor
shall be responsible for all work performed, equipment, and
materials furnished to, or by the contractor under this contract
until the contractors work is completed and has been accepted by
the Owner as stated in the certificate of Substantial Completion.
In the event of loss, damage or destruction of such work,
equipment, or materials, the contractor at his sole expense shall
promptly repair, restore, or replace such, to the conditions
required by the contract documents.
All warranties and guarantees shall commence as stated on the A/E's
certificate of Substantial Completion.
Substantial Completion certificates for portions of the project or
portions of the work may be used to reduce retention. This partial
certification shall only be used for the purpose of reducing
retention. The implementation and amounts of reduction shall be at
the Owner's sole discretion.
In the event of discrepancy or disagreement in the contract
documents, specifications, and/or drawings, this section will take
precedence over the Supplementary Genera 1 Conditions, General
Condit ions, Genera I Requirements, technical specif ications and
drawings.
11/20/91
OWNER ACCEPTANCE
00800 - 1
SECTION 01027
APPLICATION FOR PAYMENT
PART 1 - GENERAL
1..1 SUMMARY
A.
section includes:
1. Procedures for preparation and submittal
Applications for Payment.
of
B. Related sections
1. section 00750 - General Conditions
2. section 00900 - AlA G702/G703
2. Section 01370 - Schedule of Values
1..2 FORMAT
A. AlA G702 Application and Certificate for Payment
including continuation sheets when required.
1..3 PREPARATION OF APPLICATIONS
A. Present required information in typewritten form.
B.
Execute certification
authorized officer.
by
notarized
signature
of
C. List each authorized Change Order on the form, including
change order number, date and dollar amount.
D. Prepare Application for Final Payment as specified ln
section 01700.
1..4 SUBMITTAL PROCEDURES
A. The initial Application for Payment will not be processed
until the construction schedule, the schedule of values,
and the initial submittal schedule have been received by
the Construction Manager, reviewed and approved by the
Architect.
B. Submi t an updated construction and submi tta 1 schedule
with each Application for Payment.
C. Payment Period: Submit once per month, during the last
OS/20/91
APPLICATION FOR PAYMENT
01027 - 1
week of the month. Payment will be made by the Owner
within (30) days thereafter.
D. Work Item Update Listing - this work sheet, prepared by
the Construction Manager, shows the work items which are
being considered for progress payments. It is to be
billed from the Contractor's approved schedule of values
and approved changes only. The Contractor must fill in
percentages of work completed on each line item or total
dollar amount of Original Suppliers Invoices. Suppliers
Invoices are then attached for payments on materials
stored.
E. Status Meeting - The Contractor's representative and the
Construction Manager review the Contractor's Work Item
Update Listing. Upon agreement between the two parties,
both the Contractor and Construction Manager will sign
off on the form.
F. Estimate Voucher - The Construction Manager will input
the progress into the computer from the Work Item Update
Listing, and will issue the Estimate Voucher to the
Contractor.
G. Submit waivers as required.
H. Submit three (3) copies of each Application for Payment.
1..5 SUBSTANTIATING DATA
A. When the Construction Manager and/or Architect requires
substantiating information, submit data justifying dollar
amounts in question.
B. Provide one copy of data with cover letter for each copy
of submittal. Indicate Application nunber and date, and
line item by number and description.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01027
APPLICATION FOR PAYMENT
01027 - 2
OS/20/91
SECTION 01028
CHANGE ORDER PROCEDURES
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Promptly implement change order procedures.
a. Provide full written data required to evaluate
changes. .
b. Maintain detailed records of the work done on
a time and material/force account basis.
c. Provide full documentation to the Construction
Manager with each request.
2. Designate in writing the member of the Contractor's
organization authorized to accept changes in the
Work.
3. The Owner will designate in writing the person who
is authorized to execute change Orders.
B. Related requirements:
1. Agreement: The amounts of established unit prices.
2. Agreement: The amounts of established allowances.
3. Conditions of the Contract, Article 12 of the
General Conditions:
a. Methods of determining cost or credit to the
Owner resulting from changes in the Work made
on a time and material basis.
b. The Contractor's claims for additional costs.
1..2 DEFINITIONS
A. Change Order, AlA Document G701/CM: Refer to the General
Conditions.
B. Construction Change Directive: A written order to the
Contractor, signed by the Owner, MK/Gerrits and the
Architect, which amends the Contract Documents as
described, and authorizes the Contractor to proceed with
a change which affects the Contract Sum or the Contract
time, for inclusion in a subsequent Change Order.
1..3 PRELIMINARY PROCEDURES
A. A change may be initiated by submitting a Proposal
Request to the Contractor. Request will include:
1. Detailed description of the change, products and
04/30/91
CHANGE ORDER PROCEDURES
01028 - 1
location of the change in the Project.
2. supplementary or revised Drawings and
Specifications.
3. The projected time span for making the change, and
a specific statement as to whether overtime work
is, or is not, authorized.
4. A specific period of time during which the
requested price will be considered valid.
5. Such request is for information only, and is not an
instruction to execute the changes, nor to stop the
Work in progress.
B. The Contractor may initiate changes by submitting a
written notice to the Construction Manager containing:
1. Description of the proposed changes.
2. statement of the reason for making the changes.
3. Statement of the effect on the Contract Sum and the
Contract Time.
4. Statement of the effect on the Work of separate
contractors.
5. Documentation supporting change in the Contract Sum
or the Contract Time, as appropriate.
1..4 CONSTRUCTION CHANGE DIRECTIVE
A. In lieu of Proposal Request, a Construction Change
Directive may be issued for Contractor to proceed with a
change for subsequent inclusion in a Change Order.
B. The Construction Change Directive will describe changes
in the Work, both additions and deletions, with
attachments of revised Contract Documents to def ine
details of the change, and will designate the method of
determining a change in the Contract Sum and change in
the Contract Time.
C. The Owner, Construction Manager, and the Architect will
sign and date the Construction Change Directive as
authorization for the Contractor to proceed with changes.
D. At completion of the change, submit itemized accounting
and supporting data as provided in the Article
"Documentation of Proposals and Claims" of this section.
E. The allowable costs of such work will be determined as
provided in the General Conditions and Supplementary
Conditions.
F. The Owner, Construction Manager and Architect will sign
and date the Change Order to establish the change in the
Contract Sum and in the Contract Time.
CHANGE ORDER PROCEDURES
01028 - 2
04/30/91
G. The Owner and the Contractor will sign and date the
Change Order to indicate their agreement.
1..5 DOCUMENTATION OF PROPOSALS AND CLAIMS
A. support each quotation for a lump-sum proposal, and for
each unit price which has not previously been
established, with sufficient substantiating data to allow
evaluation of the quotation.
B. On request provide additional data to support time and
cost computations:
1. Labor required.
2. Equipment required.
3. Products required.
a. Recommended source of purchase and unit cost.
b. Quantities required.
4. Taxes, insurance and bonds.
5. Credi t for the work deleted from the Contract,
similarly documented.
6. Overhead and profit.
If the Trade Contractor performs the actual
Work, the percentage mark-up for overhead and
profit shall be a maximum addition of fifteen
percent (15%).
If the Trade Subcontractor performs the actual
Work, the percentage mark-up for overhead and
profit shall be a maximum addition of fifteen
percent (15%). If the Trade Contractor does
not enter into the Work, the maximum mark-up
for managing this work will be ten percent
(10%) .
If the Trade Subcontractor performs part of
the actual Work, his percentage mark-up for
overhead and profit shall be a maximum
addition of fifteen percent (15%) on his
direct work only. If the Trade Contractor
performs part of the actual work, his
percentage mark-up for overhead and prof it
shall be a maximum addition of fifteen percent
(15%) on his direct work only.
7. Justification for change in the Contract Time.
C. Support each claim for additional costs, and for the work
done on a time-and-material/force account basis, with
documentation as required for a lump-sum proposal, plus
additional information:
04/30/91
CHANGE ORDER PROCEDURES
01028 - 3
1. Name of the Owner's authorized agent ",,'ho ordered
the work, and date of the order.
2 . Dates and times the work was performed, and by
whom.
3. Time record, summary of hours worked, and hourly
rates paid.
4. Receipts and invoices for:
a. Equipment used, listing dates and times of
use.
b. Products used, listing of quantities.
c. subcontracts.
5. signature of Construction Manager's Superintendent,
concurring with quantities.
1..6 PREPARATION OF CHANGE ORDERS
A. The Construction Manager will prepare each Change Order.
B. Change Order form: AlA Document G701/CM.
C. Change Order will describe changes in the Hork, both
additions and deletions, with attachments of revised
Contract Documents to define details of the change.
D. Change Order will provide an accounting of the adjustment
in the Contract Sum and in the Contract Time.
1..7 LUMP-SUM/FIXED PRICE CHANGE ORDERS
A. Content of Change Orders will be based on either:
1. The Proposal Request and the Contractor's
responsive Proposal as mutually agreed between the
Owner and the Contractor.
2. The Contractor's Proposal for a change, as
recommended by the Architect or Construction
Manager.
B. The Owner, Construction Manager and the Architect will
sign and date the Change Order as authorization for the
Contractor to proceed with the changes.
C. The Contractor may sign and date the Change Order to
indicate agreement with the terms therein.
1..8 UNIT PRICE CHANGE ORDER
A.
The
1.
content of the Change Orders will be based on either:
The definition of the scope of the required
changes.
The Contractor's Proposal for a change, as
recommended by the Architect, or Construction
2 .
04/30/91
CHANGE ORDER PROCEDURES
01028 - 4
Manager.
3. Survey of completed work.
B.
The
1-
2.
amounts of the unit prices to be:
Those stated in the Agreement.
Those mutually agreed upon between
Architect and the Contractor.
the
Owner,
C. When quantities of each of the items affected by the
Change Order be determined prior to start of the Work:
1. The Owner, Construction Manager and the Architect
will sign and date the Change Order as
authorization for the Contractor to proceed with
the changes.
2. The Contractor may sign and date the Change Order
to indicate agreement with the terms therein.
D. When quantities of the items cannot be determined prior
to start of the Work:
1. A Construction Change Directive will be issued
directing the Contractor to proceed with the change
on the basis of unit prices, and will cite the
applicable unit prices.
2. At completion of the change, the cost of such work
will be determined based on the unit prices and
quantities used.
3. The Owner, Construction Manager and the Architect
will sign and date the Change Order to establish
the change in the Contract Sum and in the Contract
Time.
4. The Contractor will sign and date the Change Order
to indicate their agreement with the terms therein.
1..9 CORRELATION WITH THE CONTRACTOR'S SUBMITTALS
A. Revise Schedule of Values and Request for Payment forms
monthly to record each change as a separate item of the
Work, and to record the adjusted Contract Sum prior to
submission of Application for Payment.
B. Revise the Construction Schedule to reflect each change
in the Contract Time pr ior to monthly submissions.
Revise subschedules to show changes for other items of
work affected by the changes.
C. Upon completion of the Work under a change Order, enter
pertinent changes in Record Documents.
04/30/91
CHANGE ORDER PROCEDURES
01028 - 5
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
****************
END OF SECTION 01028
04/30/91
CHANGE ORDER PROCEDURES
01028 - 6
SECURITY PROJECT PROCEDURES
PART 1 - GENERAL
1.1 SUMMARY
A. section Includes
1. Electronic automated computerized security
management system.
2. Provide a complete enclosed raceway system for all
wiring for security devices and controls in
compliance with NEC, NFPA-70 1990 and in accordance
with 16050 and 16111.
3. Drawings for this work are diagrammatic, intended
to convey the extent, general arrangement and
locations of the work. Because of the scale of the
drawings, certain basic items such as conduit
fittings, access panels, cabinet sizes, sleeves,
pull and junction boxes may not be shown. Include
such items where required by code, other sections,
and for proper installation of the work.
4. Equipment specifications may not deal individually
with every part, control, or device which may be
required to produce the equipment warranties.
5. Coordinate with other trades in submittal of shop
drawings. Shop drawings shall detail space
conditions to the satisfaction of concerned trades
and is subject to final review by the Architect.
If installation of equipment, raceways, cable trays
or conduit is performed prior to coordination with
other trades and interferes with work of other
trades, make necessary changes to correct the
condition at no additional cost to the Owner.
6. Provide required integration of components to
create an operational computerized security
management system providing control and monitoring
from a touchscreen CRT.
1.2 TESTS
A. Notify Architect and Owner's representative in writing,
1~ days in advance of testing to prevent delays in
construction schedules.
B. Test systems and place in proper and specified working
order prior to demonstration of the systems.
C. Test system grounds to demonstrate that the ground
resistance does not exceed the requirements of the
transient voltage surge suppression (TVSS) or the
National Electric Codes (NEC).
D. Perform tests required by authorities having jurisdiction
11/18/91
SECURITY PROJECT PROCEDURES
01130-1
over the site.
E. Testing shall be in the presence of the Owner's
designated representatives, Contractor and Architect.
1.3 DEMONSTRATION
A. Pr ior to acceptance of the work, the Secur i ty System
Installer shall demonstrate to the Owner, designated
representatives, Contractor and Architect, the features
and functions of the system, and all subsystems and shall
instruct the Owner in the proper operation and event
sequences of the system.
B. Demonstrate each system and subsystem. The demonstration
is to consist of not less than the following:
1. Designate actual location of each component of a
system or subsystem and demonstrate its function
and its relationship to other components within the
system.
2. Demonstrate the systems and subsystems operations
by actual "START-STOP/ON-OFF" cycling showing how
to work controls, reset devices, replace fuses and
conduct emergency operating/operations procedures.
3. Demonstrate communication, signaling and security
equipment/devices by actual operation of such
devices.
C. Demonstration of systems are to include, but not be
limited to the following:
1. UPS Power and Distribution System
2. Touchscreen CRT operations .
3. Alarm Detection and Signalling Equipment
4. Door Control/Monitoring System
5. Access Control System
6. situation Alarms (Hardwire)
7. Man-Down Alarms (Wireless)
8. CCTV System
9. Intercom Systems
10. Telephone systems (Inmate/Attorney/Visitor)
11. Lighting Control
12. Fire Alarm Interface
13. Cable Supervision system (Random Points to be
Selected by Architect)
D. Security System Installer/Integrator shall furnish the
necessary trained personnel to perform the demonstration
and instructions and shall arrange to have the
sanufacturer's representatives present to assist wi th the
demonstrations. The Security System Installer shall
allow a minimum of one week for performing the prescribed
demonstrations.
E. Security systems Installer/Integrator shall arrange with
the Owner the date and times for performing the
demonstration. The Owner will select date and time for
SECURITY PROJECT PROCEDURES
01130-2
11/18/91
demonstration.
F. Comply with requirements of Section 01670 SYSTEMS
DEMONSTRATIONS.
1. Security System Installer/Integrator shall video
tape in high speed, high quality, VHS format the
demonstration of systems listed.
1.4 QUALIFICATIONS
A. Manufacturer Qualif ications: Company specializing in
electronic automated computerized security management
systems of the same type, scope, operation and magnitude
for a minimum of five years. Documented experience shall
include the following:
1. List at least 10 facilities of equal size and
technical requirements utilizing the equipment
submitted.
2. For each facility, list:
a. Name and location of facility
b. Date of occupancy by Owner
c. Owner's representative to contact and
telephone number
d. Construction Manager and/or General Contractor
e. Architect
B. Use the products of a single manufacturer for similar
type equipment, i.e., motion detectors, magnetic
contacts.
C. Use products made by companies regularly engaged in the
manufacture of the type equipment specified.
1.5 IDENTIFICATION
A. Identify control and sub-control, motor and equipment
controls, remote relay cabinets, address panels, system
interface cabinets, and similar equipment with 1/2" red
lettering or as specified for individual piece of
equipment.
B. Identify pull and junction boxes in service areas,
tunnels, above accessible ceilings, and in accessible
chases with 1/2" red lettering indicating the circuit and
system. Example: Securi ty Alarms "SY", Fire Alarms
"FA", Circuit Number "SY-126".
C. Engraved laminated plastic tags may be used for
identification in lieu of painted lettering.
D. Provide typewritten circuit directories installed in 3
ring binders with transparent page protectors in each
control and sub-control cabinet.
1.6 RECORD DOCUMENTS
A. Provide complete schematic drawings depicting location of
interface, number of conductors, types of connectors,
circuit requirements, and type of enclosure.
11/18/91
SECURITY PROJECT PROCEDURES
01130-3
1.7 PROTECTION OF EQUIPMENT
A. Protect materials stored on the job site. Protect
materials during construction and after installation.
B. Provide and apply protective material immediately upon
receiving the products and maintain throughout the
construction process.
C. Keep products clean and dry or by elevating equipment
above ground and floor.
D. Take precautions to protect apparatus and materials from
damage. Failure to protect materials constitutes
sufficient cause for rejection of the apparatus or
material.
E. Protect equipment and factory finish from damage during
construction operations and until final acceptance.
Restore finishes that become stained, scratched, or
damaged.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
********************
END OF SECTION 01130
SECURITY PROJECT PROCEDURES
01130-4
11/18/91
SECTION 01200
PROJECT MEETINGS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Project meetings
1..2 The CONSTRUCTION MANAGER'S RESPONSIBILITY
A. Construction Manager shall schedule and administer pre-
construction meeting, periodic progress meetings, and
specially called meetings throughout progress of the
Work.
1. Prepare agenda for meetings.
2. Provide notice of each meeting four days in advance
of meeting date, or provide as much advance notice
as possible.
3. Make physical arrangements for meetings.
4. Preside at meetings.
5. Record the minutes; include significant proceedings
and decisions.
6. Reproduce and distribute copies of minutes.
a. To participants in the meeting.
b. To parties affected by decisions made at the
meeting.
c. Furnish three copies of minutes to the
Architect.
B.
Representatives of the Contractors,
suppliers attending meetings shall
authorized to act on behalf of
represents.
subcontractors and
be qualified and
the entity each
C. The Architect and the Owner's Representative may attend
meetings to ascertain that the Work is expedited
consistent with the Contract Documents and construction
schedules.
1..3 PRE-CONSTRUCTION MEETING
A. Location: A central site designated by the Construction
Manager.
B. Attendance:
1. The Owner's Representative.
11/21/91
PROJECT MEETINGS
01200 - 1
2. The Architect and his professional consultants (as
required) .
3. Construction Manager.
4. The Contractor's Superintendent.
5. Major subcontractors.
6. Major suppliers.
7. Others as appropriate.
C. Suggested Agenda:
1. Distribution and discussion of:
a. List of major subcontractors and suppliers.
b. projected Construction Schedules.
2. critical Work sequencing.
3. Major equipment deliveries and priorities.
4. Project Coordination.
a. Designation of responsible personnel.
5. Procedures and processing of:
a. Field decisions.
b. Proposal requests.
c. Submittals.
d. Change Orders.
e. Applications for Payment.
6. Adequacy of distribution of the Contract Documents.
7. Procedures for maintaining Record Documents.
8. Use of premises:
a. Office, work and storage areas.
b. The Owner's requirements.
9. Construction facilities, controls and construction
aids.
10. Temporary utilities.
11. Safety and first-aid procedures.
12. Security procedures.
13. Housekeeping procedures.
14. Distribute meeting minutes within (3) days.
1..4 WEEKLY PROGRESS MEETINGS
A. The Contractor's Project Manager and/or Superintendent
shall be required to attend a weekly scheduling meeting.
B.
Location of the meetings:
Manager.
Office of the Construction
C. Attendance:
1. The Architect and his professional consultants as
needed.
2. Contractors as appropriate to the agenda.
3. suppliers as appropriate to the agenda.
4. others.
D. Suggested Agenda:
11/21/91
PROJECT MEETINGS
01200 - 2
1. Review of Work progress since previous meeting.
2. Field observations, problems, conflicts.
3. Problems which impede Construction Schedule.
4. Review of off-site fabrication, delivery schedules.
5. Corrective measures and procedures to regain
projected schedule.
6. Revisions to Construction Schedule.
7. Progress, schedule, during succeeding Work period.
8. Coordination of schedules.
9. Review submittal schedules.
10. Maintenance of quality standards.
11. Pending changes and substitutions.
12. Review proposed changes for:
a. Effect on Construction Schedule and on
completion date.
b. Effect on other contracts of the Project.
13. Other business.
14. Distribute meeting minutes.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01200
11/21/91
PROJECT MEETINGS
01200 - 3
SECTION 01301
SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. section includes:
1. Submit to the Construction Manager, shop drawings,
product data, certifications and samples required
by the technical sections.
2. Prepare and submit a separate schedule listing
dates for submission and dates for review.
B. Related Sections:
1. section 00750 - GENERAL CONDITIONS
2. Individual submittals required: refer to each
specific section, for certifications, shop
drawings, product data and sample requirements.
1.2 SUBMITTAL TRANSMITTAL FORM
A. Attached, and made a part of this section 01301, is a
copy of the submittal Transmittal Form, which shall be
filled out by the contractor and submitted with each and
every submittal. Follow the instruction sheet, also
attached, for directions on this procedure. It is
essential that the submittal Transmittal Forms are filled
out in their entirety for the system to function
properly.
B. Transmittal Form, originals for contractors use, will be
supplied by the Construction Manager, and is a 6-part
form.
1.3 SUBMITTAL SCHEDULE
A. The Contractor shall submit within seven (7) days of
award of the Contract a preliminary "Submittal Schedule"
to the Construction Manager for review, modification and
response. No payment applications will be processed
prior to finalizing the submittal schedule. The
"Submittal Schedule" shall contain the following
information:
1. specification section number and name.
2. specification section paragraph identification
which describes submittal requirement.
3. Submittal information required, (i.e., sample, test
data, shop drawing, etc.).
08/20/91
SUBMITTALS ~~DD.1)
01301 - 1
B. The Contractor shall also supply the following dates in
order to meet the project schedule.
1.
Date submittal is scheduled to be submitted and
received by the Construction Manager.
Date contractor has scheduled to order material or
equipment or the submittal item.
Date contractor has scheduled delivery to job-site
equipment or the submittal item.
Add any remarks or unique items that the CM or AlE
should be aware of.
2 .
3.
of material or
4.
C. The Contractor shall allow a minimum of (2) weeks for
review of submittal by AlE (in calendar days).
D. The submittal master record will then be used to track
submittals within the process.
1.4 SHOP DRAWINGS
A. Submit legible shop drawings in the form of positive
printing reproducible transparencies, commonly called
sepia prints, suitable for reproduction use on dry print
diazo type machines. Sepia prints which cannot be
reproduced will be returned to the Contractor for
resubmittal.
B. Provide shop drawings as complete submittals (no partial
sets) on original drawings or information prepared solely
by the fabricator or supplier. Deviation from complete
submittals will only be allowed by pre-arranged method.
C. Do not reproduce the Contract Drawings for shop drawing
submittals.
D. Sheet sizes shall not exceed the size of the Contract
Drawings.
E. Each sepia print shall have blank spaces large enough to
accept 4" x 4" review stamps of the Architect and the
Contractor.
F.
Each
1-
2.
3.
sepia print shall carry the following
Project name and contract number.
Date.
Names of:
a. The Architect
b. The Construction Manager
c. The Contractor
d. Supplier
e. Manufacturer
information:
08/20/91
SUBMITTALS -{ADD. 1)
01301 - 2
4. Identification of product or material.
5. Relation to adjacent structure or materials.
6. Field dimensions, clearly stated as such.
7. Specification section number.
8. Applicable standards such as ASTM or Federal
Specification.
9. Identification of deviations from Contract
Documents.
10. Reference to construction drawings by drawing
number and/or detain number.
G. Submit sepia prints without folds either as flat sheets
if size permits, or rolled in tubes.
H. The contractor shall submit (2) reproducibles and (4)
blueline or blackline sets to the CM. The CM will return
(1) reproducible to the contractor after review/return
from the A/E.
1.5 PRODUCT DATA
A. Product data such as catalog cuts, brochures or
manufacturer's sheets may be submitted in lieu of sepia
prints if adequately identified. Submit seven copies of
product data to the Construction Manager.
B. Modify product data sheets to delete information which is
not applicable to the Project. Provide additional
information if necessary to supplement standard
information.
C. Product data sheets that are submitted with extraneous
information not deleted and/or modified will be returned
without review to the Contractor for resubmittal.
D. The contractor shall submit at a minimum, (1) original
and (6) copies to the CM. The CM will return (2) copies
to the contractor after review/return by the A/E.
1.6 SAMPLES
A. Provide samples to illustrate materials, equipment or
workmanship, and to establish standards by which
completed work may be judged.
B. Construct mock-ups as required by the technical sections,
at the Project site in a location designated by the
Construction Manager. Construct mock-ups, including
adjacent work required, to demonstrate the final
appearance of the Work.
08/20/91
SUBMITTALS (ADD.l)
01301 - 3
C. The contractor shall submit (3) samples to the CM, and
(1) will be returned to the contractor after
review/return from the A/E.
1.7 CERTIFICATIONS
A. Provide certifications as required by various technical
sections on the Contractor's letterhead stationary.
certifications shall be identified to this Project, dated
and bear Contractor's signature in the same format used
for the Owner/Contractor agreement.
B. Clearly identify the materials referenced and state that
the material and the intended installation methods, where
applicable, are in compliance with the Contract
Documents. Attach manufacturer's affidavits where
applicable.
C. The contractor shall submit (1) original and (6) copies
to the CM. The CM will return (2) sets to the contractor
after review/return from the A/E.
1.8 THE CONTRACTOR'S RESPONSIBILITIES
A. Before making submittals to the Construction Manager,
review each submittal, make changes or notations as
necessary to conform to the Contract Documents, identify
such review with review stamp and forward reviewed
submittal with comments to the Construction Manager for
review. Return submittals not meeting Contract
requirements to subcontractors and do not forward such
submittals to the Construction Manager.
B. Submit catalog sheets, product data, shop drawings and
where specified, submit calculations, material samples,
color chips or charts, test data, warranties and
guarantees all at the same time for each submittal item.
C. Verify field measurements and product catalog numbers or
similar data.
D.
Clearly identify on the
Construction Manager
submittals from the
Documents.
submittal and transmittal to the
in writing of deviations in
requirements of the Contract
E. After the Construction Manager I s and the Architect I s
review, distribute copies with one copy to be maintained
at the Project site for reference use and other copies
distributed to suppliers and fabricators.
SUBMITTALS (ADD.l+
01301 - 4
08/20/91
.......,.-.. -------- ....- .~-
F. Do not begin the Work which requires submittals until
return of submittals with the Construction Manager's and
the Architect's stamp and initials indicating review.
G. The Contractor's responsibility for errors and omissions
in submittals is not relieved by the Construction
Manager's or the Architect's review of submittals.
H. The Contractor's responsibility for deviations in
submittals from requirements of the Contract Documents is
not relieved by the Construction Manager's or the
Architect's review of submittals unless the Architect
gives written acceptance of specific deviations.
1.9 THE CONSTRUCTION MANAGER'S RESPONSIBILITIES
A. The Construction Manager will return to the Contractor,
without review, all submittals not bearing the
Contractor's review stamp or not showing it has been
reviewed by the Contractor.
B. After the Architect's review, the Construction Manager
will forward submittals to the Contractor and retain one
copy for the Owner. The Contractor sha 11 distribute
copies including other copies distributed to suppliers
and fabricators. The Contractor shall supply copies of
reviewed submittals to the Construction Manager in
sufficient quantity to allow proper coordination of the
Contract.
1.10 THE ARCHITECT'S RESPONSIBILITIES
A. The Architect will review submittals with reasonable
promptness, checking only for conformance with the design
compliance of the Project and compliance with information
given in the Contract Documents.
B. The Architect will make changes or notations directly on
the submittal, identify such review with his review
stamp I obtain and record the Architect file copy and
return the submittal to the Construction Manager.
****************
END OF SECTION 01301
08/20/91
SUBMITTALS (ADD.1)
01301 - 5
-
--
r=
~. g
~ '-'
'"
!- '"
Z ',)
7-
UJ <
::E :t
<
:; >
'- u
0 >
~ "'
'9 Cl '"
~ L:.l ~ UJ
.J
c.. U
i- ::E C; Z
a:
< 0 - UJ 6
0... U ~ z
;: 0
" G: ~
'"
0 ~ UJ
I I z c ~ ~
tJ L:.l
--- <: ?: " ;;
<: ~ <: L:.l
~ .J ~ ~ a:
< c" ::E V)
t '" ~ r-
::E z z Z z
~ ::E ~ < 0 UJ
:J co ~ .., U 6 0
Vl r- <- z Z
~ :J '" ;- ~
l!.l t1 ::E :J '8 :: ~
z a: Vl 0 ~
g ;; ;;:
I I L:.l ~ UJ
a: l>-
e.. :J
V)
Vl ~
,. !:!
00... ;:.:
0
't U
~ l!.l
~ B 0...
.., r
< i <- c-
o I "
~ u
~ "
Vl 0
f-. C
Z
u.l z
;;:2 I g 0
i'.l
u.l <( E
> ! 3
0 ! ~ ::E u
~ ;;:2 I ~ :J U
p.. I - '" ...
;;:2 ~ I ~ ~ 'il
0 ~ '8
>-< ~ ;... ~ t::
...J ~ (..I.. '- " E
< ...J g ~ 0 oS
t < :::E ~ z .~
g :: 0 &
~ Q ~ ~ .." ~ t
~ .;>.
0 C
U ~ ;:;
~ [j
>- p.. Vl a '"
Z '" L:.l
f-< .." Q
< S c ~
Z ::>
~ cC '-' ;.....: '" '9 OJ
f-. r.o , Z i: c:
0 ;: ..,
- :J. c Vi
U t u ~
u.l ~~ ~ .~ ~
0 ~3 z ~
c Q
~ i2? >.: " v
Z L:5i ;2 ~ ;- .. E
;; !2 ~
0 '-'
... L: '" ~
~ 8 ::!: f:.l ~ ~
'-' t:
C
f- :;.
" 3( [~ --1 ~ () () C/) n :.r: j
V > oCJ..a
c-l
--o3(h--1~()()Y.l()~()
aCJr+r;.pj2.~5~sO
g (; (t r+ ~ 2 ~. ~ ~ --:J tj
cO-; t-1 t)~ --::-~-C) ~
C P:;' ~ ~ ::) S ~ !]; Cr:< iJ './J
..., ..- ('t :;:- n ;::";: . c.. ::
~ C ~ - ~ ~ c ~ ~
o ~ ~;r. ~ 5'
C 0;:;
~ ~
:::.;
o'
~
o'
::)
'"
~~~~;~
oc:;::->c:;~
~e:.~:g:::.~
~~E~;~
;::I .--,.., :.: :.: .r:::
Q ~ ~ ;:; ~ ;;.
~ .... .-, ,.. 3 r..
-:2 ~. ?; 1'.. ;: :-
~1~,~~a
"'"'\ '"'::l t"')
~ ~ "
~ ~.
" Co.
<r-
'"
S
g
-<
>-r1QQnw>>
"'0
::00::0 Z>-> "':
n ~ r. 0"0-0::0
<:::1'<'-'-o':JO
n' 0 0;.- ~ "'1 ..., -<
~"'1(t-o~~>
n ~"Or..r.t'"
.P- Oc..c..('J
=:3 ?;'~~:;:O
o ",O-::)v:tj
~ 0" oCM
::g 3 (iJ(JJ
"'1 _. c.. 3
0.... ....
~ [
.....
o
.n
c
::j'
n
c..
r>
~
~
i~~~~
~. ~ ~ ~; l
c.. :.:' c-
~ ~ 0
3
To
~
~
I:~.
?
~
;
l'f)
, .::::/
'-ff~~~~1
;2J~ ~f~
r: I ~;
I i
i I
~ I
~
.Q)
.~
'\Q;
I :'?,\
2~
,,'
!2 .
~x
5 ~
~
,.,
~
~
~
'"
8
,~"-~C~ ~ -~~- -' ~~- =--1 'TTTrrT.~~'--=-1
I iJ ! i i : i '-;- :-1 i
-..- I I~II nr- \
I I 1 1 -
\ Iii \ ~
\ \ I r$1 n
I
1
I
I 1
-1__.:-__
I 1
^ I
/~
' .
, ,
~
,
~.
~
~
~
z
J
"
'<
@) ~
^ IJ t-J t'..) N ...... __ ..... --..... --- X -.J ?'
g'!- ~"':-- ~ .-::. .:r: :-l ,=--;.." ~..
!(![ilil'!:i~l!.!"..l:,i:~__:,i_~l~::__j~!_.'~_
iBnrH!i '" c, ,0 ·
..,cg,-'"'::l"" :::rcQ-
t..3~~9 ~~~5
~~~~~ ~s'---;'3
'<~35 ~.....0:J
~~:- ~~~~
; .~. l -' -0 C
~ ~ ~. 0 ~
~~~ 3~
9: n 0" <;
;::.~ ~ 5" ~.
" ~ ~
~~ 0
a d~ _ i ~-.~ t
~ ~ - -- ~
~ r";
~5 3C-
~
~
;;;c':'
8
"
z
~
C
r.
;:;
"
5
8
=-
>
"
"
;::
7.
:::
-
;;;
> Z
z
f~~
~~2:
i >" ~ ~
;~~
i
;:::
-
x
,;
Z
6
~
s
~
~
:;
C8~
"
~
~ (~)
! ~!
€
~
ii ~
~
!
::j
~0
I~
I
i
;
i
:': :J
~
~ .,
x
~
~
(0
,..
'..,. ~ :..J t..) :-
'"
~~~i[[r
~ g ~ :; Q Q c.
~ ~ ~ ~ n n 5
;; ? c.. g ~ !1_ ~
-:: '6 ~ ;,fI- :;. ~ ~
~ E. ~ t ~ .., ~
~::;-v.7C:"ZC-
~~iif~
~og:.r.-7
HHH
.~ ~ ~ ~ 1l
.... ::l c: ~ C
;R~ a~
;.~~ ~~
~ 3 Q: :;;-
~ ~. f. [
~. ~ ~ ;"
':1 ); ;..
:r-; ~ ~
~
:; 2..
"
"
-'(5
~ x
'"
::. x
~
:;::x
i
g
~
SECTION 01310
PROGRESS SCHEDULES
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Progress schedules
2. Revisions to schedules
B. Related sections:
1. SCOPE OF WORK
C. Description:
1. Progress Schedules:
Promptly after award of the Contract, prepare and
submit to the Construction Manager, construction
progress schedules for the work, with subschedules
of related activities which are essential to its
progress. Also incorporate manpower loading
related to each activity on the construction
schedule.
2. Revisions to Schedule:
Submit revised/updated progress schedules with each
payment application.
1 . . 2 FORMAT
A. Prepare Progress Schedules as a horizontal bar chart with
separate bar for each major portion of Work or operation,
identifying the first work day of each week.
B. Include numeric manpower loading associated with each
horizontal bar, clearly defined.
C.
Scale and spacing:
revisions.
to provide space for notations and
D. Sheet size: minimum 8 1/2" x 11".
1. . 3 CONTENT
A. Indicate complete sequence of construction by activity,
with dates for beginning and completion of each element
of construction.
OS/20/91
PROGRESS SCHEDULES
01310 - 1
B. Show the manpower loading for each activity.
C. Identify each item by Specification section number.
D. Identify work of separate stages and other logically
grouped activities.
E. Identify work of separate floors and other logically
grouped activities.
F. Provide sub-schedules to define critical portions of the
entire schedule.
G. Indicate accumulated percentage of completion of each
item and total percentage of Work completed, as of the
first day of each month.
H. Submit separate schedule of submittal dates for shop
drawings, product data, and samples, including the Owner
furnished products and products identified under
allowances and dates reviewed submittals will be required
from the Architect. Reference Section 01301
Submittals.
I. Indicate del i very dates for the Owner furnished products.
J. Coordinate content with Schedule of Values specified in
section 01370.
1..4 REVISIONS TO SCHEDULES
A. Indicate progress of each activity to date of submittal,
and projected completion date of each activity.
B. Identify activities modified since previous submittal,
major changes in scope, and other identifiable changes.
1. Major changes in scope.
2. Activities modified since previous submission.
3. Revised projections of progress and completion.
4. other identifiable changes.
C. Provide a narrative report as needed to define:
1. Problem areas, anticipated delays and the iffipact on
the schedule.
2. Corrective action recommended and its effect.
3. The effect of changes on schedules of other prime
contractors.
01310 - 2
OS/20/91
PROGRESS SCHEDULES
1..5 SUBMITTALS
A. Submit initial schedules within (3) days after award of
Contract.
1. The Construction Manager will review schedules and
return review copy within ten (10) days after
receipt.
2. If required, re-submit within seven (7) days after
return of review copy.
3. Submit revised Progress Schedules with each
Application for Payment.
1..6 DISTRIBUTION
A. Distribute copies of the reviewed schedules to:
1. Job site file.
2. Subcontractors.
3. Other concerned parties.
B. Instruct recipients to report promptly to the Contractor,
in writing, any problems anticipated by the projections
shown in the schedules.
Note: It is not incumbent upon the Construction Manager
to notify the Trade Contractor when to begin, to
cease, or to resume work nor to give early notice
of faulty or defective work, nor in any way to
superintend so as to relieve the Trade Contractor
of responsibility or of any consequence of neglect
or carelessness.
**************
END OF SECTION 01310
OS/20/91
PROGRESS SCHEDULES
01310 - 3
SECTION 01370
SCHEDULE OF VALUES
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Schedule of Values allocated to the various
portions of the Work, submitted within three (3)
days after award of the Contract.
2. Upon request of the Construction Manager, support
the values with data which will substantiate their
correctness.
3. The Schedule of Values, unless objected to by the
Construction Manager, forms the basis for the
Contractor's Applications for Payment.
1..2 FORM AND CONTENT OF SCHEDULE OF VALUES
A. Type schedule on AlA G703 Form; the Contractor's standard
forms and automated printout will be considered by the
Construction Manager upon the Contractor's request.
Identify schedule with:
1. Title of Project and location.
2. The Architect and Construction Manager.
3. Name and Address of the Contractor.
4. Contract designation.
5. Date of submission.
B. List the installed value of the component parts of the
Work (broken down into labor and material and physical
location) in sufficient detail to serve as a basis for
computing values for progress payments during
construction.
C. Follow the Specifications as the format for listing
component items.
1. Identify each line item with the number and title
of the respective major section of the
Specifications.
D. Itemize separate line item cost for each of the following
general cost items:
1. Mobilization.
2. Bonds, Insurance and Permits.
3. General Conditions spread over project duration on
monthly basis.
04/30/91
SCHEDULE OF VALUES
01370 - 1
4. Clean-up.
5. Submittals.
6. Safety.
E. For each major line item list sub-values of major
products or operations under the item.
2 .
the various portions of the Work:
Include a directly proportional amount
Contractor's overhead and profit for each
For items on which progress payments
requested for stored materials, break
value into:
a. The cost of the materials, delivered
unloaded, with taxes paid.
b. The total installed value.
Submit a subschedule for each separate stage
work specified in section 00300.
of the
item.
will be
down the
F.
For
1.
and
3 .
of
G. The sum of values listed in the schedule shall equal the
total Contract Sum.
1..3 SUBSCHEDULE OF UNIT MATERIAL VALUES
A. Submit a subschedule of unit costs and quantities for:
1. Products on which progress payments will be
requested for stored products.
B. The form of submittal shall parallel that of the Schedule
of Values, with each item identified the same as the line
item in the Schedule of Values.
c. The unit quantity for bulk materials shall include an
allowance for normal waste.
D. Provide unit values for the materials as follows:
1. Cost of the material, delivered and unloaded at the
site, with taxes paid.
2. Installation costs, including the Contractor's
overhead and profit.
E. The installed unit value multiplied by the quantity
listed shall equal the cost of that item in the Schedule
of Values.
1..4 REVIEW AND SUBMITTAL
A. After review by Construction Manager, revise and resubmit
schedule (and Schedule of Material Values) as required.
01370 - 2
04/30/91
SCEEDULE OF VALUES
B. Resubmit revised schedule in same manner.
*************
END OF SECTION 1370
04/30/91
SCHEDULE OF VALUES
01370 - 3
SECTION 01385
DAILY CONSTRUCTION REPORTS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Requirement for Daily Construction Reports by each
Trade Contractor.
2. Scheduled submission times for Daily Construction
Reports.
1..2 FORM AND CONTENT OF DAILY CONSTRUCTION REPORTS
A. Daily Construction Reports shall be submitted by each and
every Contractor performing work on the project. Forms
to be used will be furnished by the Construction Manager.
Items to be addressed on the Report are:
1. Title of Project
2. Name of Trade Contractor
3. Date and day of Report information. For example,
you performed work on Thursday, April 18, 1991, so
you would therefore use "Thursday, 4 / 18/91. II This
holds true even if you did not complete filling out
the Report until Friday, 4/19/91.
4. Contract designation.
S. Note any major Shipments received on that
particular day.
6. Note major equipment used that day.
7. Note manpower used, and designate what trades. For
example, if you were the mechanical contractor, you
would also list how many insulators, pipefitters,
etc. that you were also managing, even if they were
subcontractors. In addition, list the names of the
subcontractors that were on-site that day.
8. Note any deficiencies in your work, and corrective
actions taken to resolve the deficiencies.
9. Note any safety violations discovered, whether or
not caused by your forces.
10. Provide a full description of work performed that
day, and any problems or unusual conditions
discovered.
11. Report is to be signed by the authorized
representati ve of the contractor, and should the
signature not be legible, print the name of the
signer next to the signature.
11/21/91
DAILY CONSTRUCTION REPORTS
01385 - 1
1..3 SCHEDULE OF SUBMITTING DAILY REPORTS
A. Daily Reports are to be submitted at the designated
location described in the pre-construction meeting.
Contractors are to submit the original of their report,
and should keep a copy for their records. The
Construction Manager's photocopying facilities are not to
be used in the reproduction for submission of the
reports.
B. Submit Daily Reports no later than 9:00am the day
following the day of the work described in that
particular report. No exceptions to this rule will be
accepted. Should contractor fail to comply with these
instructions, the contractor's payment application for
the following month will be held in abeyance until such
time the contractor properly submits the delinquent
reports.
*************
END OF SECTION 1385
11/21/91
DAILY CONSTRUCTION REPORTS
01385 - 2
I\IONROE COUNTY CAPITAL II\1PROVEJ\IENT PROJECTS
CONTRACTOR'S DAILY REPORT
PROJECT:
DATE:
SJ-IEET
OF
~.Jdri~~1-:~~~~~~"A1-~~I::l.:AIl"""'~"-----'.
CONTRACTOR:
CONTRACNO.:
~~~~,o5,~~~T~~ ...~.~~
~~ ..-;-.....C.,l..
'If ~-~.g.
\L\JOR SHIPMENTS RECEIVED TODAY
MAJOR EQUIPMENT USED
--
~~IBA'\~w 4IUPd~r ~ r:..l:-~-:'~"" 12:1""7 - _._~.
NUMBER OF PERSONl'\EL O~SITE
---
LlST SUBCOl'\TRACfORS Ol'\SITE
OPC C
C
c
C
c
C
SC SC
T
o
T
A
L
- ..
..~::e~"~-~~~~...;.t..
DEF1CJE~CIES NOTED/CORRECTED; IJ\S?ECTIOJ\S \IADE; TESTS CONDUCTED:
QC REPRESENTATIVE:
SAFETY VJOLATIO~S N01T.D/CORRECTED:
--
FULL DESCRIPTION OF WORK PERFOR"~ED BY AREA; I!\CLUDE ANY PROBLE\IS:
i
I
i
I
f-
i
----
,--------~.--
i
l
I____~~n
i
r--------
r-~----
SITE REPRESE~TATIVE:
), I J ACI1 2j\D--SliEI: rTF'1\ I::l:UI::U
I
~~.~~~~
CO~TRACTOR'S DAILY REPORT
2~'D SHITf
--==-~~~~----l
SHEET ____ OF ___
-~~~
PROJECf:
WORK DAY:
--
CO~TR/\CT :-;0.: D,-\ TE:
~~ii!I.~~I-=-iJiiJijJlV~.AV....7i..'SI&.' ~~~~ W!t~""~''''%:Il'#-W~-PI!~~\.''''
DESCRJPTJON OF WORK PERFORMED. Liq actidtics ~tancd, a(li\'ilic~ comrk:cd, dc13~'!', rc.1Sons for dcl:j~,!" ;,nd
IC~t~Ons for possihle fut UTe del3ys.
~J~ -"~!!J;~.~:r .i.&!i!IV.~~~"';:KI'l u;e~~~'- ll~~~'
--
--
--
--
--
------------
.-----
--
--
--
--
-.-
--
--
----
~
t___________---=--=--==~--------------~--~-
~ n_ _ '. . __=--__=_
l~ ~~~__ ~.~-._. ~ ~~~_..o~...~_ _~.._~_~_ ._._--~ -~-- -~~ -.--.-.----~_.
---
.-- --------...-
J
SECTION 01395
DOCUMENT CLARIFIC~TION REQUESTS (DCR)
PART 1 - GENERAL
1.1 SUMMARY
A. section includes:
1. Notification of Construction Manager in the event
errors, field conflicts, and omissions are found in
the Contract Documents, or clarifications are
necessary.
2. Utilization of DCR form.
B. Related Sections:
1. General Conditions Article 2.3
2. General Conditions Article 8.3.2
3. General Conditions Article 12.3
1.2 FORM AND CONTENT OF DOCUMENT CLARIFICATION REPORTS
A. All errors, field conflicts, and omissions in the
Contract Documents shall be brought to the attention of
the Construction Manager immediately. If clarifications
are necessary, the request is to be conveyed to the CM.
The DCR is a tool established to provide expedient
clarifications of contract drawings, specifications or
field conflicts. It is not meant to be a substitute for
good communication.
B. The DCR is not meant for formal notification of extra
work. Reference General Conditions paragraph 8.3.2 and
12.3, when formal correspondence is required for formal
notif ication of time extensions, and for cost change
notifications.
C. The contractor should propose a solution, and enter on
the form in sufficient detail necessary for the AlE or CM
to confirm the contractor's proposed solution.
D. The contractor is also required to mention all other
trade work which is affected by the problem, and all
trade work which will be affected by the proposed
solution.
11/21/91
DOCUMENT CLARIFICATION REQUESTS
01395 - 1
1.3 UTILIZATION OF OCR FORM
A. The CM will make available the OCR forms for the
contractors use. Attached is a copy of the OCR form, and
the instruction sheet.
*************
ENO OF SECTION 1395
11/21/91
DOCUMENT C~RIFICATION REQUESTS
01395 - 2
DOCUMENT ClARIFICATION REQUEST No.
From: To: M orrison- Knudse n/Ge nits Contract No.
P. O. Box 5283
Key West, FL 33045 Receipt
(305) 292-7845 Logged:
Problem By: Dwg'Spec No./Rcvision/DclaillSecl No.
NE Project No.
Civil SI ruct ural Architectural Security PLB HVAC Elcctrical Specs .
Subject: '
Problem & suggested solution:
-
-~
I MKfG RC\iew:
Solulion:
Solution b\': l Dale: ~1KiG: I Date:
)LKUl -
- DOClJIo{El''T a..o.mCATIOS UQl'EST No. (&)
From: -r- Mor.-a.on-Knu(bcr..'Gcrriu Contan to.:o_ @ I
- --lE'-- P.O.1kw. 528..'
Kt)' WOl, n. J)04~ RU'f:lpl <D
()OS) 292.7JW~ Lou'"
Prol>km By, (1-' p..~'Spec P..o~~:xali/S..ecl 1000
A"EI"n~t.;u '.1Ll' "'1'
.5 CMl Sn.....'.B' Ard>llO;;'llllal Xcvnl\ '1" W.A(" [jenncal .....
'"""" iCO I
l"1('1Nc. 4< su,re'~ ~UOIl
(7 !
--
u
.-
o-
j t.I.:,<:.R.mr- ~
""~-
~ --
~ (is 1_ (-u,' IMI& 1/1- 1- (I~
Dcl,"'
A. By Contractor:
1. From: The OCR ..'ill al\Jays be fro::. the prizr,e contractor.
Subcontractcrs to the Frir,e contractor shall subrr,it DCR's
through their prime contractor.
2. Problem By: This can be the subcontractor, or the prime
cont ractor, or the est,abli shed pr ime contractor
r~presentative, or the established subcontractor
representative.
3. Contract No.: This is the approved contract, contract
nu:rr.ber.
.4. Drlll,,'ing No.: Here insert as much intont/ation as possible
to describe the location in the contract documents of the
particular problem you are ~sk.ing clarificllition. Include
revision level of drawings, and date. Include detail
numbers, include section numbers, include specification
s~ction nUffibers, paragraph locations, all as applicable.
5. civil, Structural, etc.: Here note the particular
division of ~ork the OCR applies to.
6. Subject: Here insert brier, clear,. concise caption
subject, ~hich is representative of problem area.
7. Problem' Suggested Solution: Describe in as much detail
as necessary, the problEa to W'hich clarification is
needed. If additional space is needed, add extra sheets
to back,. and reference attachments in this area no. 7.
Draw sKetches if necessary. Malee photocopy of pa rticular
dra~ing detail and attach if necessary.
B. By Morrison-Knuds~n/Gerrits:
8. DCR No.: Nur.~ers ~ill be assigned as follo~s:
xx-
Project
xxx-
Contractor No.
XXX
Sequential No.
For instance, the first OCR from the contractor of
Contract No. 001 on the New Detention Facility, ~ould be:
l<J-001-001
As another example: The s~venth consecutive OCR logged
on the Ne\t. Detention Facility, \o'as received frota the
contractor of Contract No. 005, ~ould be:
Y.J-005-007
9. Receipt: Logged: This will be t.he date reCEived by the
CPo fror:: the cont.ractor, and ..ill SE:rve as ttle reference
date.
10. AlE Project No.: Tr,e AlE's project r.Ul:1ber loIill be
inserted here, _here and .~En applicable.
11. MK/G Revie",': This .i11 bE the signature or initials of
the Ccnstruction Y.anager, upon revie... of t.he probJem,
.ith the date of sign-oft.
12. MK/G Review: T~is will be the signature cr initials of
the Construction Manager, ~p0n review of tt.e solution.
13. Date: This ..dll be the ca.te of Jol:K/G review and sign-
off.
C. By ~rchitpct;Engineer:
14. Solutic~: The AlE ~ill h~~e insert the solution to the
probler., or ,L-,s,,-,e:-r lr. SO...-,€, other fashion the
clarification being reques~ed. The ~/E n-.ay herein
con!i~ the contractor's F;cposed solution.
15. Solution By: The Entity F~oviding the solution is to
sign here. This ~~y be t~e Construction ~a~ager ~hen
pGrticular clarifications are bE-in~ req'.Jested that can
be ans".:E-red ly the CY.. C:'~EonoJise. it ....'ill be the AlE
represen':.otive.
16. [:'.ate: 77115 ...:ill be "tt-,e c::.':e of si~r;-cff, or ar.s..ering
the DC~ by the A/E.
D. Part-By-Part Distributicr, of €'-;:'O!;rt OCR FOnT.:
a. "''':len tr.e contractor 51..:!::;:.it.s ~.:R. [lE '..:ill re'tain ~9J_9(>nu~.Q
copy.
b. ,,"hen received by t!".e CCr::'::'ector, eM ".:ill retain .rink
copy.
c. The OCR therl is subr..itted tc the AlE. OnCE ans...;ered, the
AlE returns to eM, but retains ~anar~ copy.
d. eM revieW's arls""'er, and sends ~ copy back to
contractor. CY. \.-ill r€t2.:n original 'h'"hite copy for
office files, and Qlue cCFY will go to the jOb-site.
SECTION 01410
TESTING LABORATORY SERVICES
PART 1 - GENERAL
1. .1 SUYiHARY
A. section includes:
1. Selection and payment
2. The Contractor submittals
3. Testing laboratory responsibilities
4. Testing laboratory reports
5. Limits on testing laboratory authority
6. The Contractor responsibilities
7. Schedule of inspections and tests
B.
l.
2.
3 .
section 00750 - GENERAL CONDITIONS
section 01700 - CONTRACT CLOSEOUT
Individual Specification sections: inspections and
tests required, and standards for testing.
1. .2 REFERENCES
A.
ASTM 0-3740 -
Practice for Evaluation of Agencies
in Testing and/or Inspection of Soil
and Rock as Used in Engineering
Design and Construction.
B.
ASTM E-329 -
Recommended Practice for Inspection
and Testing Agencies for Concrete,
Steel, and Bituminous Materials as
used in Construction.
1..3 SELECTION AND PAYMENT
A. The Owner will employ and pay for services of an
independent testing laboratory to perform specified
inspection and testing where so indicated to be performed
by the Owner in technical Specification Sections.
B. Employment of testing laboratory shall in no way relieve
the Contractor of obligation to perform the Work in
accordance with requirements of the Contract Documents.
11/21/91
TESTING LABORATORY SERVICES
01410 - 1
1..4 QUALITY ASSURANCE
A. Comply with requirements of ASTM E-329 and ASTM 0-3740.
B. Testing laboratory: authorized to operate in the State
of Florida.
C. Testing laboratory staff: maintain a full time
registered Engineer on staff to review services.
D. Testing Equipment: calibrated at reasonable intervals
with devices of an accuracy traceable to either National
Bureau of Standards (NBS) Standards or accepted values of
natural physical constants.
E. Meet "Recommended Requirements for Independent Laboratory
Qualification", published by American Council of
Independent Laboratories.
1..5 TESTING LABORATORY RESPONSIBILITIES
A. Test samples of mixes.
B. Provide qualified personnel at the site. Cooperate with
the Architect, Construction Manager and the Contractor in
performance of services.
C. Perform specified inspection, sampling, and testing of
Products in accordance with specified standards.
D. Ascertain compliance of materials and mixes with
requirements of the Contract Documents.
E. Promptly notify the Construction Manager and the
Contractor of observed irregularities or non-conformance
of the Work or products.
F. Perform additional inspections and tests required by the
A/E and Construction Manager.
1..7 TESTING LABORATORY REPORTS
A. After each inspection and test, promptly submit three
copies of testing laboratory report to the Construction
Manager.
B. Include:
1. Date issued
2. Project title and number
3. Name of inspector
4. Date and time of sampling or inspection
TESTING LABORATORY SERVICES
01410 - 2
11/21/91
5. Identification of product and Specifications
section
6. Location in the Project
7. Type of inspection or test
8. Date of test
9. Results of test
10. Conformance with the Contract Documents
C. When requested by the Construction Manager or A/E,
provide interpretation of test results.
1..8 LIMITS ON TESTING LABORATORY AUTHORITY
A. The testing laboratory may not release, revoke, alter, or
enlarge on requirements of the Contract Documents.
B. The testing laboratory may not approve or accept any
portion of the Work.
C. The testing laboratory may not assume any duties of the
Contractor.
D. The testing laboratory has no author i ty to stop the Work.
1..9 THE CONTRACTOR RESPONSIBILITIES
A.
B.
C.
D.
E.
1. .10
A.
Deliver to the testing laboratory at designated location,
adequate samples of materials proposed to be used which
require testing, along with proposed mix designs.
cooperate with testing laboratory personnel, and provide
access to the Work and to the manufacturer's facilities.
Provide incidental labor and facilities to provide access
to the Work to be tested, to obtain and handle samples at
the site or at source of products to be tested, to
facilitate tests and inspections, storage and curing of
test samples.
Notify the Construction Manager and the testing
laboratory 48 hours prior to expected time for operations
requiring inspection and testing services.
Employ services of a separate qualified testing
laboratory and pay for additional samples and tests which
are beyond the specified requirements.
RETEST RESPONSIBILITY
Where the results of required inspections, tests, or
similar services prove unsatisfactory and do not indicate
11/21/91
01410 - 3
TESTING LABORATORY SERVICES
compliance with the requirements of the Contract
Documents, the retests shall be the responsibi Ii ty of the
Contractor regardless of whether the original test was
the Contractor's responsibility.
B. Retesting of the work revised or replaced by the
Contractor is the Contractor's responsibility where
req~ired tests were performed on original work. Costs
and fees for retesting shall be paid by the Contractor.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECu~ION
Not Used
**************
END OF SECTION 01410
TESTING LABORATORY SERVICES
01410 - 4
11/21/91
SECTION 01510
TEMPORARY UTILITIES
PART 1 - GENERAL
1.1
SUMMARY
A.
section includes:
1. Temporary utilities required for construction.
PART 2 - PRODUCTS
2.1
MATERIALS - GENERAL
A.
2.2
A.
Materials shall be new, adequate in capacity for the
required usage, not create unsafe conditions, not violate
requirements of applicable codes and standards, and
comply with NEC Art. 305 - Temporary Wiring.
TEMPORARY ELECTRICITY
The Temporary Power Contractor shall furnish, install and
maintain, temporary electric. power service for
construction needs throughout the construction period and
shall remove such service on completion of the work.
1. Primary temporary electrical underground feeder
will be provided and installed by temporary power
contractor under Bid Group 1, per drawing 1510- TP.
2. At Front Gate transformer location, the temporary
power contractor under Bid Group 1 has installed a
meter, mast, and main breaker panel Nema 3R, per
Detail "A" attached. The final location of each
panel shall be approved by the Construction
Manager.
3. Distribution panels have been provided by the Bid
Group 1 temporary power contractor per drawing 1510
- TP, and Details A, B, C and D, and as follows:
a. Front gate area serving the construction
manager trailer, guard shack and area lights.
(20 ckt. min.)
4.
Power centers for miscellaneous tools and
used in the Work will be provided by the
1 Temporary Power Contractor as follows:
a. distribution boxes with minimum
of four
equipment
Bid Group
11/21/91
01510 - 1
TEMPORARY UTILITIES
double-duplex 15 Amp, 12 O-Vol t grounded
outlets, with GFCI Protection for personnel.
See Detail "B".
b. located so that power is available at any
point of use with not more than 100 ft. power
cords.
c. minimum: one power center on each floor.
d. circuit-breaker protection for each outlet.
e. One panel each for Bui lding Areas
A,B,C,D,E,F,K,L,M,N,O,P and Q.
5. The capacity of each power center in 4. above shall
be 120/240 volts single phase, minimum 50 Amps.
6. The Trade Contractors shall notify the Temporary
Power Contractor when unusually heavy loads, such
as for welding and other equipment with special
power requirements, will be connected so that the
Bid Group 3 Temporary Power Contractor can notify
the power company.
7. Any Trade Contractor requiring service of capacity
or characteristics other than that specified shall
arrange and pay for the additional service.
8. The Temporary Power Contractor shall furnish,
install, and maintain all equipment and wiring
required to distribute the power, up to and
including the power services.
9. The Temporary Power Contractor shall pay all costs
of installation, maintenance, and removal of
temporary services.
10. The Construction Manager will pay the costs of
power needed, including deposits and fees
associated with City Electric except as outlined in
item 13 below
11. Materials shall be new, and must be adequate in
capacity for required usage, and must not violate
the requirements of applicable codes and standards.
Materials used for temporary service shall not be
reused in the permanent system.
12. The Temporary Power Contractor shall comply with
all applicable requirements specified in National
Electric Code Art. 305 when installing the
temporary electric pO'v.'er service, shall maintain
the system to provide continuous service and shall
modify and extend the service as the progress of
11/21/91
TE11PORARY UTILITIES
01510 - 2
the Work requires.
13. Wiring for Trade Contractor field offices and sheds
shall be installed by the Temporary Power
Contractor and paid for by the Trade Contractor
requiring the service.
14. The Temporary Power Contractor shall completely
remove all temporary materials and equipment at
Project Completion. Underground lines may be
disconnected and abandoned in place with approval
of the Construction Manager. The temporary shed as
shown in Detail "C" shall remain the property of
Benson Electric.
15. Feeders to distribution panels from distribution
shed shall be 400 feet maximum length, with two hot
legs and one neutral of the same size as per NEC
Table 310-16 and Article 210-19a FPN.
16. Circuits to Power Centers from Distribution Panels
shall be installed per NEC Art. 305.
17. Feeders and Branch circuits in 15. and 16. above
shall be protected from physical damage.
18. See Detail "c" for temporary power shed
requirements. This sha 11 remain the property of
Benson Electric.
2.3
TEMPORARY SITE LIGHTING
The Temporary Power Contractor shall install and maintain area
lights on the meter poles as shown in Detail "A", 2 lights total.
Temporary Lighting power will be fed from the panels and power
centers covered under section 2.2 TEMPORARY ELECTRICITY.
2.4
TEMPORARY TELEPHONE SERVICE
A.
Each Trade Contractor shall be responsible for arranging
with the local telephone service company to provide
telephone service at the construction site for the use of
his personnel and employees. The Trade Contractor shall
pay all costs for installation, maintenance, removal and
service charges for such service. The Construction
Manager will not act as an answering service for Trade
Contractor's personnel and employees, and Trade
Contractor's personnel and employees will not be
permitted to utilize the Construction Manager's phones
except in cases of an emergency.
11/21/91
TEMPORARY UTILITIES
01510 - 3
2.5
CONTINUING TEl1PORARY ELECTRICITY MAINTENANCE
At the option of the Owner, the Temporary Power
Contractor shall provide a minimum of 1 person full time
for the duration of the construction, estimated to be 18
months. This person will maintain, relocate and repair
the temporary utilities covered under Articles 2.2, 2.3
and 2.4. The bid for this work shall be based on an
hourly rate for licensed electrician.
2.6 TD1PORARY LIGHTING
A. The Electrical Trade Contractor will be responsible for
the installation of the permanent electrical system and
shall also furnish, install and maintain temporary
lighting for construction needs throughout the
construction period and shall remove such temporary
lighting on completion of the Work.
1. Temporary artificial lighting shall be provided in
enclosed Work areas and all other work areas when
natural lighting does not meet minimum
requirements. Temporary artificial lighting in
Work areas shall produce uniform illumination of
20-foot candles.
2. Any Trade Contractor requiring temporary lighting
in addition to that specified, including lighting
for security, temporary offices, storage, shops and
other construction buildings, shall arrange and pay
for such additional temporary lighting.
3. Power requirements and source will be coordinated
with Article 2.2 above.
4. The Electrical Contractor shall comply with the
applicable requirements specified in sections of
Division 16 - Electrical. Materials shall be new,
and must be adequate for required usage, and must
not violate requirements of applicable codes and
standards.
5. Receptacles, fixtures and controls shall be
standard products, meeting UL standards.
6. The Electrical Contractor shall comply with all
applicable requirements specified in sections of
Division 16 Electrical, when installing the
temporary lighting, shall locate fixtures to
provide full illumination of required areas, shall
maintain the system to provide continuous service,
and shall modify and extend the service as the
progress of the Work requires.
7. The Electrical Contractor shall completely remove
teGporary materials and equipment at Project
Completion, except for high voltage underground.
TEMPORARY UTILITIES
01510 - 4
11/21/91
2.7
2.8
TEMPORARY WATER
A.
site Plumbing Contractor will arrange
service company, to provide water for
purposes.
with utility
construction
B.
site Plumbing Contractor will provide temporary water at
locations of two (2) fire hydrants on fire water loop as
directed by Construction Manager; fire water loop will
be charged to provide construction water.
C.
The Construction Manager will pay for water used for
temporary construction purposes.
D.
Building Plumbing Contractor will maintain temporary
water systems, and will remove temporary water
appurtenances at completion of project.
E.
Each Trade Contractor shall be responsible for providing
any additional water (if needed) for construction
purposes. In addition, each Trade Contractor is
responsible for providing potable drinking water for his
personnel and employees, as well as suitable containers,
ice and salt tablets in sufficient quantity to meet the
needs of his labor force.
TEMPORARY HEATING, COOLING AND VENTILATING
Each Trade Contractor shall be responsible for providing, and
operating and maintaining temporary heating, cooling and
ventilating, as required, to maintain adequate environmental
conditions to facilitate the progress of his Work; to meet
minimum condition for the installation of materials; and to
protect materials and finishes from damage due to temperature
or humidity. Each Trade Contractor, subject to the approval
and direction of the Construction Manager, shall:
1. Provide adequate forced ventilation of enclosed
areas for curing of installed materials, to
disperse humidity, and to prevent hazardous
accumulations of dust, fumes, vapors, or gases.
2. If portable heaters are required, utilize only UL
approved units complete with controls.
3. Insure that all safety devices specified for
operation of equipment are functioning properly.
4. Pay all costs of providing, operating, maintaining,
and removing such temporary heating, cooling, and
ventilating equipment as may be required.
11/21/91
TEMPORARY UTILITIES
01510 - 5
The foregoing obligations of the Trade Contractor are in
addition to his obligations under Article 10 of the General
Conditions.
2.9
A.
B.
2.10
TEMPORARY SANITARY FACILITIES
The Owner will provide sanitary facilities in compliance
with laws and regulations.
The Owner will service, clean and maintain facilities and
enclosures.
TEMPORARY FIRE PROTECTION
The Trade Contractor responsible for the installation of the
permanent fire protection system shall furnish, install and
maintain temporary fire protection equipment, materials,
supplies and service within the buildings throughout the
construction period in accordance with the requirements of all
applicable codes and standards. Each floor shall have a
temporary fire protection system. Each Trade Contractor will
be responsible for fire protection required for his own work.
2.11
A.
REMOVAL
Completely rewove temporary materials and equipment when
their use is no longer required.
B.
Clean and repair damage caused by temporary installations
or use of temporary facilities.
C.
Restore permanent facilities used for temporary services
to specified condition.
1. Prior to final painting, the
responsible for the permanent
system, shall remove temporary
Trade Contractor
building lighting
lamps and install
new lamps.
2 .
Pr ior to final inspection, the Trade Contractor
responsible for the building mechanical system
shall replace filters and worn or consumed parts of
mechanical equipment.
***************
EHD OF SECTION 01510
11/21/91
TEMPORARY UTILITIES
01510 - 6
SECTION 01520
CONSTRUCTION AIDS
PART 1 - GENERAL
1 . 1 S U11Y.iAR Y
A. section includes:
1. Construction aids
2. Temporary enclosures
1.2 REQUIREMENTS OF REGULATORY AGENCIES
B.
Comply with Federal,
regulations.
state and
local codes
and
PART 2 - PRODUCTS
2..1 MATERIALS - GENERAL
A. Materials may be new or used, suitable for the intended
use and shall not violate requirements of applicable
codes and standards.
2..2 CONSTRUCTION AIDS
A. Each Trade Contractor shall be responsible for
furnishing, installing, maintaining, and removing on
completion of the Work all scaffolds, staging, ladders,
stairs, ramps, runways, platforms, railings, chutes, and
other such facilities and equipment required by his
personnel to insure their safety and facil i tate the
execution of the Work.
1. Each Trade Contractor shall comply with all
Federal, State and local codes, laws and
regulations governing such construction aids.
2. Each Trade Contractor shall relocate such
construction aids as required by the progress of
construction, by storage or work requirements, and
to accommodate the legitimate requirements of the
Owner or Construction Manager or other separate
contractors employed at the site.
3. Each Trade Contractor shall completely remove
temporary scaffolds, access, platforms, and other
such materials, facilities, and equipment, at the
completion of the Work or when construction needs
can be met by the use of the permanent
construction, provided the Construction Manager has
04/09/91
CONSTRUCTION AIDS
01520 - 1
approved and authorized such use. Each Trade
Contractor shall clean up and shall repair any
damage caused by the installation or by the use of
such temporary construction aids. Each Trade
Contractor shall restore any permanent facilities
used for temporary purposes to their specified
condition.
The foregoing obligations of the Trade Contractor are in
addition to his obligations under Article 10 of the General
Conditions.
2..3 TEMPORARY ENCLOSURES
A. The Trade Contractor responsible for installing the
permanent closure in an opening in an exterior wall shall
be responsible for installing, maintaining, and removing,
as the Work progresses, a temporary weather-tight
enclosure for that opening as necessary to provide
acceptable working conditions, to provide weather
protection for interior materials, to allow for effective
temporary heating, and to prevent entry of unauthorized
persons.
1. Each Trade Contractor shall install such temporary
enclosures as soon as is practical after the
opening is constructed or as directed by the
Construction Manager.
2. Temporary enclosures sha 11 be removable as
necessary for the Work and for handling of
materials.
3. Temporary enclosures shall be completely removed
when construction needs can be met by the use of
the permanent closures.
4. The Trade Contractor responsible for providing,
maintaining, and removing the temporary enclosure
shall clean and shall repair any damage caused by
the installation of such enclosure.
5. Each Trade Contractor shall remain responsible for
insuring that his work, material, equipment,
supplies, tools, machinery, and construction
equipment is adequately protected from damage or
theft and shall provide, maintain and remove such
addi tional temporary enclosures as may be deemed
necessary.
The foregoing obligations of the Trade Contractor are in addition
to his obligations under Article 10 of the General Co"ditions.
****************
END OF SECTION 01520
04/09/91
CONSTRUCTION AIDS
01520 - 2
SECTION 01550
ACCESS ROADS AND PARKING AREAS
A. Each Trade Contractor shall be responsible for installing
and maintaining, until the completion of his Work any
temporary access roads or parking facilities required by
his Work, other than that which has been provided by the
Owner.
B. Any Trade Contractor excavating across an access road or
parking area shall backfill and compact his excavation
and resurface the road or parking area to match the
existing surface. The Trade Contractor shall comply with
all applicable Specifications when so doing.
*********************
END OF SECTION 01550
04/09/91
ACCESS ROADS AND PARKING AREAS
01550 - 1
SECTION 01560
TEMPORARY CONTROLS
PART 1 - GENERAL
1..1 SUMMARY
A. section Includes:
1. Water control
2. Dust control
3. Erosion and sediment control
4. Pollution control
B. Related sections:
1. SCOPES OF WORK
1..2 WATER CONTROL
A. site Grading Contractor shall grade site to drain.
B.
Protect site from puddling or running water.
water barriers to protect site from soil
Maintain excavations free of water. Provide,
and maintain pumping equipment.
Provide
erosion.
operate,
1..3 DUST CONTROL
A. Execute the Work by methods to minimize raising dust from
construction operations.
B. Provide posi ti ve means to prevent a irborne dust from
dispersing into atmosphere.
1..4 EROSION AND SEDIMENT CONTROL
A. Plan and execute construction by methods to control
surface drainage from cuts and fills, from borrow and
waste disposal areas. Prevent erosion and sedimentation.
B. Minimize amount of bare soil exposed at one time.
C. Provide temporary r:easures such as berms, dikes, and
drains, to prevent ~ater flow.
D. Construct fill and waste areas by selective placement to
avoid erosive surface silts or clays.
E. Inspect earthwork to detect evidence of erosion and
OS/20/91
TEMPORARY CONTROLS
01560 - 1
sedimentation; promptly apply corrective measures.
1..5 POLLUTION CONTROL
A. Provide methods, means, and facilities to prevent
contamination of soil, water, and atmosphere from
discharge of noxious, toxic substances, and pollutants
produced by construction operations.
Two (2) 30 c.y. trash containers will be provided by the Owner.
The Masonry Contractor shall be responsible to provide his own
trash dumpsters for masonry waste disposal. Trash containers shall
be located in trash accumulation areas designated by the
Construction Manager. Each Contractor each day shall collect and
deposit in the containers, all rubbish, waste materials, debris,
and other trash from his operations, (excluding masonry), including
any trash generated by his employees during lunch periods or coffee
breaks. Shipping dunnage is to be removed by the receiving
contractor. Paper, boxes and bulk packaging shall be folded or cut
into reasonable sizes and shapes and confined to prevent lost of
trash container volume or wind relocation.
***************
END OF SECTION 01560
OS/20/91
TEMPOR1~RY CONTROLS
01560 - 2
SECTION 01580
PROJECT IDENTIFICATION AND SIGNS
Trade Contractors informational signs on the site shall be limited
to those designating their temporary field offices and sheds. All
such informational signs sha 11 be subject to approval by the
Construction Manager.
*************************
END OF SECTION 01580
11/21/91
PROJECT IDENTIFICATION AND SIGNS
01580 - 1
SECTION 01590
FIELD OFFICES AND SHEDS
A. The Trade Contractor, if he deems it necessary, may
furnish, install, and maintain a temporary field office
for his use and the use of his employees during the
construction period.
B. The Trade Contractor shall furnish, install, and maintain
temporary storage and work sheds to adequately protect
his work, mater ials, equipment, supplies, tools,
machinery, and construction equipment from damage and
theft.
C. The Trade Contractor shall arrange his field office and
sheds so as not to interfere with the construction. The
locations of field offices and sheds shall be coordinated
wi th the Construction Manager. The type, size and
location of field offices and sheds is subject to
approval by the Construction Manager.
D. The Trade Contractor shall arrange and pay for temporary
electricity and telephone service for his field office
and sheds, if he should require such services.
E. The Trade Contractor shall relocate his field office and
sheds as directed by the Construction Manager, at no
additional cost to the Owner or Construction Manager.
F. The Trade Contractor shall completely remove his field
office and sheds on completion of the Work or when
directed by the Construction Manager. The Trade
Contractor shall remove all debris and rubbish and shall
place the area in a clean and orderly condition.
G. The Construction Manager as soon as reasonably possible
will establish a field office on the site and will
maintain such an office during the entire construction
per iod. The Construction Manager I s field off ice wi 11 not
be used as field office by the Trade Contractor or his
employees.
**************
END OF SECTION 01590
04/09/91
FIELD OFFICES AND SHEDS
01590 - 1
SECTION 01595
CONSTRUCTION CLEANING
P~~T 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Cleaning during progress of work.
1..2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with
codes, ordinances, regulations, and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on
Project site.
2. Do not dispose of volatile wastes such as mineral
spirits, oil or paint thinner in storm or sanitary
drains.
PART 2 - PRODUCTS
2..1 MATERIALS
A. Use only those cleaning materials which will not create
hazards to health or property and which will not damage
surfaces.
B. Use only those cleaning materials and methods recommended
by manufacturer of the surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by
cleaning material manufacturer.
D. Sweeping compounds used in cleaning operations shall
leave no residue on concrete floor surfaces that may
affect installation of finish flooring materials.
PP~T 3 - EXECUTION
3..1 DURING CONSTRUCTION
A. Execute cleaning to keep the Work, the site and adjacent
properties free from accumulations of waste materials,
rubbish and windblown debr is , resulting from construction
operations.
B. Provide on-site containers for the collection of waste
04/09/91
CONSTRUCTION CLEANING
01595 - 1
materials, debris, and rubbish.
C. Dispose of waste materials, debris and rubbish off the
site.
3..2 DUST CONTROL
A. Clean interior spaces prior to the start of the finish
painting and continue cleaning on an as-needed basis
until painting is finished.
B. Schedule operations so that dust and other contaminants
resulting from cleaning process will not fall on wet or
newly-coated surfaces.
C. Handle materials in a controlled manner with as little
handling as possible; do not drop or throw materials
form heights.
************
END OF SECTION 01595
04/09/91
CONSTRUCTION CLEANING
01595 - 2
SECTION 01600
MATERIAL AND EQUIPMENT
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Products
2. Transportation and handling
3. storage and protection
4. Security
1. . 2 PRODUCTS
A. Products: means new material, machinery, components,
equipment, fixtures, and systems forming the Work. Does
not include machinery and equipment used for preparation,
fabrication, conveying and erection of the Work.
Products may also include existing materials or
components required for reuse.
B. Do not use materials and equipment removed from existing
premises, except as specifically permitted by the
Contract Documents.
C.
Provide interchangeable components
manufacturer, for similar components.
of
the
same
1..3 TRANSPORTATION AND HANDLING
A. The Trade Contractor shall be responsible for the
transportation of all materials and equipment furnished
under this contract. The Trade Contractor shall also be
responsible for loading, receiving and off-loading at the
site all material and equipment installed un der this
Contract, whether furnished by the Trade Contractor or
the Owner. Unless otherwise provided, the Construction
Manager will not accept delivery on behalf of the Trade
Contractor for his materials and equipment. The Trade
Contractor shall be responsible for coordinating the
installation within the buildings of equipment that is
too large to pass through finished openings.
B. Transport and handle products in accordance with
manufacturer's instructions.
C. Promptly inspect shipments to assure that products comply
04/09/91
MATERIAL AND EQUIPMENT
01600 - 1
with requirements, quantities are correct, and products
are undamaged.
D. Provide equipment and personnel to handle products by
methods to prevent soiling, disfigurement, or damage.
1..4 STORAGE AND PROTECTION
The Trade Contractor shall be responsible for the proper
storage of all materials, supplies, and equipment to be
installed under this Contract. Materials stored on site but
not adequately protected will not be included in estimates for
payment. Except for materials stored within designated and
approved storage sheds, vans, or trailers, the Trade
Contractor shall not bring onto nor store in any manner at the
site any materials and equipment which will not be
incorporated into the permanent Work within seven (7) days
from the delivery date. The Trade Contractor shall be
responsible for arranging and paying for the use of property
off the site for storage of materials and equipment as may be
required.
1. .5 SECURITY
A. Each Trade Contractor shall be totally responsible for
the security of his work, materials, equipment, supplies,
tools, machinery, and construction equipment.
PART~ - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
*************
END OF SECTION 01600
04/09/91
MATERIAL AND EQUIPMENT
01600 - 2
SECTION 01630
POST-BID SUBSTITUTIONS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Post-bid substitutions
1.2 SUBSTITUTIONS
A. Base Bid shall be in accordance with the Contract
Documents.
B.
After the end of the bidding
requests will be considered only
1. Product unavailability
2. Other conditions beyond
Contractor.
period, substitution
in the case of:
the control of the
c. Submit a separate request for each substitution. support
each request with the following information:
1. Complete data substantiating compliance of proposed
substitution with requirements stated in Contract
Documents:
a. Product identification, including
manufacturer's name and address.
b. Manufacturer's literature, identifying:
1) Product description.
2) Reference standards.
3) Performance and test data.
c. Samples, as applicable.
d. Name and address of similar projects on which
product has been used and date of each
installation.
2. Itemized compar ison of the proposed substitution
with product specified, listing significant
variations.
3. Data relating to changes in construction schedule.
4. Effects of substitution on separate contracts.
5. List of changes required in other work or products.
6. Accurate cost data comparing proposed substitution
with product specified.
a. Amount of net change to Contract Sum.
7. Designation of required license fees or royalties.
8. Designation of availability of maintenance
services, sources of replacement materials.
POST-BID SUBSTITUTIONS
01630 - 1
04/09/91
D. Substitutions will not be considered for acceptance when:
1. A substitution is indicated or implied on shop
drawings or product data submittals without a
formal request from Bidder.
2. Acceptance will require substantial revision of
Contract Documents.
3. In judgement of Architect or Construction Manager,
the substitution request does not include adequate
information necessary for a complete evaluation.
4. Requested directly by a subcontractor or supplier.
E. Do not order or install substitute products without
written acceptance of Construction Manager.
F. Architect will determine acceptability of proposed
substitutions.
G. No verbal or written approvals other than by Change Order
will be valid.
1..3 CONTRACTOR'S REPRESENTATION
A. In making formal request for substitution the Contractor
represents that:
1. The proposed product has been investigated and it
has been determined that it is equivalent to or
superior in all respects to the product specified.
2. The same warranties or bonds will be provided for
the substitute product as for the product
specified.
3. Coordination and installation of the accepted
substitution into the Work will be accomplished and
changes as may be required for the Work to be
complete will be accomplished.
4. Claims for additional costs caused by substitution
which may subsequently become apparent will be
waived by the Contractor.
5. Complete cost data is attached and includes related
costs under the Contract, but not:
a. Costs under separate contracts.
b. Architect's costs for redesign or revision of
Contract Documents.
1..4 POST-BID SUBSTITUTION FORM
A. The form is attached to this section.
B. Substitutions will be considered only when the attached
form is completed and included with the submittal with
back-up data.
-
04/09/91
POST-BID SUBSTITUTIONS
01630 - 2
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
04/09/91
POST-BID SUBSTITUTIONS
01630 - 3
TO: Project Architect
HANSEN LIND MEYER INC.
c/o Morrison-Knudsen/Gerrits
P.G.Box 5283 5090 Jr. College Road, Key West, Fl. 33040
(305)292-7845 FAX (305)292-9697
We hereby submit for your consideration the following product inst~.d c
the specified item for the above project:
DRAWING NO.
DRAWING NAME
SPEC. SEC.
SPEC. NAME
PARAGRAPH
SPECIFIED ITEM
Proposed Substitution:
Att~ch complete information on changes to Drawings and/or specification
which proposed substitution will require for its proper installation.
Submit with request necessary samples and substantiating data to proy
equal quality and performance to that which is specified. Clearly mar
manufacturer's literature to indicate equality in performance.
The undersigned certifies that the function, appearance and quality ar
of equal performance and assumes liability for equal performance, equa
design and compatibility with adjacent materials.
Submitted By:
Title
signature
Firm
Address
Telephone
Date
signat~re shall be by person having authority to legally bind his firm t
the above terms. Failure to provide legally binding signature will resul
in retraction of approval.
For use by the Architect:
____Recommended ____Recommended as noted
____Not Recommended ____Received too late
Insufficient data received
By
Date
Fill in Blanks Below:
A. Does the substitution affect dimensions shown on Drawings?
Yes
No
If yes, clearly indicate changes.
B. will the undersigned pay for changes to the building design
including engineering and detailing costs caused by the requeste
substitution?
Yes
No
If no, fully explain:
C. What effect does substitution have on other Contracts or othe:
trades?
D. What effect does substitution have on construction schedule?
E. Manufacturer's warranties of the proposed and specified items are:
Same
Different. Explain:
F. Reason for Request:
G.
Itemized comparison of specified item(s)
substitution; list significant variations:
with the proposec
H. This substitution will amount to a credit or extra cost to the Owne~
of: dollars ($ ).
I. Designation of maintenance services and sources:
(Attach additional sheets if required.)
****************
END OF DOCUMENT 01630
SECTION 01650
STARTING OF SYSTEMS
PART 1 - GENERAL
1..1 SUMMARY
A. Section includes:
1. Starting systems
2. Demonstration and instructions
3. Testing, adjusting, and balancing
B. Related sections:
1. SECTION 01700 - CONTRACT CLOSEOUT
1..2 STARTING SYSTEMS
A. Coordinate schedule for start-up of var ious equipment and
systems.
B. Notify the Construction Manager seven days prior to
start-up of each item.
c. verify that each piece of equipment or system has been
checked for proper lubrication, drive rotation, belt
tension, control sequence, or other conditions which may
cause damage.
D. Verify that tests, meter readings, and specified
electrical characteristics agree with those required by
the equipment or system manufacturer.
E. Verify wiring and support components for equipment are
complete and tested.
F.
Execute start-up under supervision
manufacturer's representative in
manufacturer's instructions.
of responsible
accordance with
G. Execute start-up under supervision of the responsible
Contractors' personnel in accordance with manufacturer's
instructions. All in-line and interface trades shall
cooperatively support and coordinate individual
components and systems to faci Ii tate start-up acti v i ties.
H. When specified in individual Specification Sections,
require manufacturer to provide authorized representative
to be present at the site to inspect, check and approve
11/21/91
STARTING OF SYSTEMS
01650 - 1
equipment or system installation prior to start-up, and
to supervise placing equipment or system in operation.
I. Submit a certified written report that equipment or
system has been properly installed and is functioning
correctly.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01650
11/21/91
STARTING OF SYSTEMS
01650 - 2
SECTION 01670
SYSTEMS DEMONSTRATIONS
PART 1 - GENERAL
1..1 SUMMARY
A. Section includes:
1. Procedures for demonstration of equipment operation
and instruction of the Owner's personnel.
1..2 QUALITY ASSURANCE
A. When specified in individual Sections, provide
manufacturer's authorized representative to demonstrate
operation of equipment and systems, instruct the Owner's
personnel and provide written report that demonstrations
and instructions have been completed.
B. The Owner will provide list of personnel to receive
instructions, and will coordinate their attendance at
agreed-upon times.
1. .3 SUBMITTALS
A. Submit preliminary schedule for the Owner's approval,
listing times and date for demonstration of each item of
equipment and each system, two weeks prior to proposed
dates.
B. Provide operating and maintenance manuals to owner (4)
weeks prior to demonstrations.
c. Submi t reports wi thin one week after completion of
demonstrations, that demonstrations and instructions have
been satisfactorily completed. Give time and date of
each demonstration, and hours devoted to demonstration,
with a list of persons present.
PART 2 - PRODUCTS
NOT USED
PART 3 _- EXECUTION
3..1 PREPARATION
A. Verify equipment has been inspected and put into
SYSTEMS DEMONSTRATIONS
01670 - 1
04/30/91
operation;
performed;
operational.
testing, adjusting, and ba lancing has been
and equ ipment and systems are fully
B.
Have copies
manuals at
instructions.
of completed operation and maintenance
hand for use in demonstrations and
3..2 DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of equipment and
systems to the Owner's personnel two weeks prior to date
of final inspection. For equipment requiring seasonal
operation, perform instructions for other seasons within
six months.
B. Use operation and maintenance manuals as basis of
instruction. Review contents of manual with personnel in
detail to explain aspects of operation and maintenance.
C.
Demonstrate start-up, operation, control,
maintenance, servicing, trouble-shooting and
each item of equipment at agreed-upon
designated location.
adjustment,
shutdown of
times, at
D. Prepare and insert additional data in operations and
maintenance manuals when need for additional data becomes
apparent during instructions.
3..3 TIME ALLOCATED FOR INSTRUCTIONS
A. The amount of time required for instruction on each item
of equipment and system is specified in individual
Sections.
**************
END OF SECTION 01670
04/30/91
SYSTEMS DEMONSTRATIONS
o 1 6 7 0 -- 2
SECTION 01700
CONTRACT CLOSEOUT
PART 1 - GENERAL
1..1 SUMMARY
A. Section includes:
1. Closeout procedures
2. Adjusting
B. Related sections:
1. SECTION 01027 - APPLICATION FOR PAYMENT
2. SECTION 01650 - STARTING OF SYSTEMS
3. SECTION 01730 - OPERATION AND MAINTENANCE DATA
4. SECTION 01740 - WARRANTIES AND BONDS
5. SECTION 08710 - FINISH HARDWARE
6. SECTION 11196 - SECURITY HARDWARE
1..2 PROJECT TERMINATION
A. the Contract requirements are met when construction
acti vi ties have successfully produced, in this order,
these three terminal activities:
1. Substantial Completion
2. Final Completion
3. Final Payment
1..3 SUBSTANTIAL COMPLETION
A. Submi t to the Construction Manager when the Work is
substantially complete:
1. A written notice that the Work, or designated
portion thereof, is substantially complete.
2. A list of items to be completed or corrected (Punch
List) .
3. Request Substantial Completion Observation at a
mutually agreeable date.
4. Certifications of systems and testing/balancing
final reports.
5. Submit evidence of compliance with requirements of
governing authorities:
a. Certificate of Occupancy
b. Certificates of Inspection:
1) Elevators
2) Mechanical systems
3) Electrical systems
4) Kitchen equipment
04/09/91
CONTRACT CLOSEOUT
01700 - 1
5) Fire protection system
6) security system
B. within a reasonable time after receipt of such notice,
the Architect, the Construction Manager, the
Contractor,and the Owner, will make an observation to
determine the status of completion.
C. Should the work be determined to not be substantially
complete the following will occur:
1. The Construction Manager will promptly notify the
Contractor in writing, giving the reasons.
2. The Contractor shall remedy the deficiencies in the
Work, and send a second written notice of
substantial completion.
3. The Work will be reobserved.
D. When the Work is considered substantially complete, the
following will occur:
1. The Construction Manager will prepare a Certificate
of substantial Completion on AlA Form G704,
accompanied by the Contractor's Punch List of items
to be completed or corrected, as verified and
amended. Contract responsibilities are not altered
by inclusion or omission of required Work from the
punch list.
2. The certificate will be executed by all parties and
distribution made.
E. Complete or correct items identified on the punch list
and required by the Contract requirements within time
limit established by the certificate.
1..4 FINAL COMPLETION
A. To attain final completion, the Contractor shall complete
activities pertaining to substantial completion, complete
Work on punch list items and submit written request to
the Construction Manager for final inspection.
B. When the Work is complete, the Contractor shall submit
written certification that:
1. The Contract Documents have been reviewed.
2. Work has been inspected for compliance with the
Contract Documents.
3. Work has been completed in accordance with the
Contract Documents.
4. Equipment and systems have been tested in the
presence of the Owner's represEntative and are
operational.
5. Work is completed and ready for final observation.
04/09/91
CONTRACT CLOSEOUT
01700 - 2
C. The Architect, the Construction Manager, the Contractor
and the Owner will make an inspection to verify the
status of completion with reasonable promptness after
receipt of such certification.
D. Should the Work be considered incomplete or defective:
1. The Construction Manager will promptly notify the
Contractor in writing, listing the incomplete or
defective work.
2. The Contractor shall take immediate steps to remedy
the stated deficiencies and send a second written
certification to the Construction Manager that the
Work is Complete.
3. The Work will be reinspected.
E. When the Work is acceptable under the Contract Documents
the Contractor shall make closeout submittals.
1..5 THE CONTRACTOR'S CLOSEOUT SUBMITTALS TO THE ARCHITECT
A.
Project Record Documents:
01720.
to requirements of SECTION
B. Operating and maintenance data, instructions to the
Owner's personnel: to requirements of SECTION 01730.
C.
Keys and keying schedule:
08710 & 11196.
to requirements of SECTION
D. Spare parts and maintenance materials: to requirements
of individual sections.
E. Evidence of payment and release of liens: to
requirements of General and Supplementary Conditions.
1..6 FINAL ADJUSTMENT OF ACCOUNTS
A. Submit a final statement of accounting to the Architect.
B. Statement shall reflect adjustments to the Contract Sum:
1. The original Contract Sum
2. Additions and deductions resulting from:
a. Previous Change Orders
b. Allowances
c. Unit Prices
d. Deductions for uncorrected Work
e. Penalties and bonuses
f. Deductions for liquidated damages
g. Deductions for reinspection payments
h. Other adjustments
3. Total Contract Sum, as adjusted
04/09/91
CONTRACT CLOSEOUT
01700 - 3
4. Previous pa~~ents
5. Sum remaining due
C. The Construction Manager will prepare a final Change
Order, reflecting adjustments to the Contract Sum which
were not previously made by Change Orders.
1..7 FINAL APPLICATION FOR PAYMENT
A. The Contractor shall submit the final Application for
Payment in accordance with procedures and requirements
stated in the Conditions of the Contract.
PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
Not used
*****************
END OF SECTION 01700
04/09/91
CONTRl>..CT CLOSEOUT
01700 - 4
SECTION 01710
FINAL CLEANING
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Cleaning at completion of Work
1..2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with
codes, ordinances, regulations, and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on
the Project site.
2. Do not dispose of volatile wastes such as mineral
spirits, oil or paint thinner in storm or sanitary
drains.
PART 2 - PRODUCTS
2..1 MATERIALS
A. Use only those cleaning materials which will not create
hazards to health or property and which will not damage
surfaces.
B. Use only those cleaning materials and methods recommended
by manufacturer on the surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by
cleaning material manufacturer.
PART 3 - EXECUTION
3..1 DUST CONTROL
A. Handle materials in a controlled manner with as little
handling as possible.
3..2 FINAL CLEANING
A. Employ skilled workmen for final cleaning.
B. Remove grease, mastic, adhesives, dust, dirt, stains,
fingerprints, labels, and other foreign materials form
sight-exposed interior and exterior surfaces.
04/09/91
FINAL CLEANING
01710 - 1
C. Wash and shine glazing and mirrors.
D. Polish glossy surfaces to a clear shine.
E. Dust cabinetwork and remove markings.
F. Vacuum as needed.
G.
Broom clean exterior paved surfaces;
surfaces of the grounds.
rake clean other
H. Pr ior to f ina 1 completion, or the Owner occupancy,
conduct an inspection of sight-exposed interior surfaces,
exterior surfaces and work areas, to verify that the
entire Work is clean.
I. Clean tunnels and closed off spaces of packing boxes,
wood frame members and other waste materials used in the
Construction.
J. Internally clean the entire system of piping and
equipment. Open dirt pockets and strainers, completely
blowing down as required and clean strainer screens of
accumulated debris.
K. Drain tanks, fixtures and pumps to be free of sludge and
accumulated matter.
L. Remove temporary labels and stickers from fixtures and
equipment. Do not remove permanent name plates,
equipment model numbers and ratings.
M. Thoroughly clean heating and air conditioning equipment,
tanks, pumps and traps. Install or thoroughly clean
filters or filter media, including:
1. The cleaning of permanent f i I ters and the
replacement of disposable filters if units were
operated during construction.
2. The cleaning of ducts, blowers, and coils if the
units were operated during construction.
N. Remove from the site all facilities of items installed or
used for temporary purposes during construction.
O. Restore all adjoining areas to their original or
specified condition.
****************
END OF SECTION 01710
04/09/91
FINAL CLEANING
01710 - 2
SECTION 01720
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Maintain at the job site one copy of:
a. Record Contract Drawings
b. Record Project Manual
c. Coordination drawings
d. Addenda
e. Reviewed shop drawings
f. Change Orders
g. Other modifications to the Contract
h. Field test records
1. .2 GENERAL
A. Store documents in cabinets in temporary field office,
apart from documents used for construction.
B. Maintain documents in clean, dry, legible condition.
C. Do not use Project Record Documents for construction
purposes.
D. Make documents available for inspection by the
Construction Manager, the Architect and the Owner.
E. Failure to maintain documents up-to-date ~ill be cause
for withholding payments.
F. Obtain from the Construction Manager (at no charge) two
sets of the Contract Documents for Project Record
Documents including:
l.
2.
Specifications with
Two complete sets
Drawings.
One complete set of
all addenda.
of black line pr ints of all
3 .
mylar prints of all Drawings.
1. .3 RECORDING
A. Label each docuffient "Project Record".
B. Keep record docuffients current.
PROJECT RECORD DOCUMENTS (ADD. 2)
01720 - 1
01/06/92
C. Do not permanently conceal any work until required
information has been recorded.
D. Contract Drawings:
1. Required information may, as an option, be entered
on a "working set" and then at completion of
Project transfer the information to final submitted
"Project Record" set.
2. Legibly mark to record actual construction:
a. Depths of various elements of foundation in
relation to survey data.
b. Horizontal and vertical location of
underground utilities and appurtenances
referenced to permanent surface improvements.
c. Location of internal utilities and
appurtenances concealed in construction
referenced to visible and accessible features
of structure.
d. Field changes of dimension and detail.
e. Changes made by Change Order or Construction
Change Directive.
f. Details not on original Contract Drawings.
E. specifications and Addenda:
1. Legibly mark up each section to record:
a. Manufacturer, trade name, catalog number and
supplier of each product and item of equipment
actually installed.
b. Changes made by Change Order or Construction
Change Directive.
c. Other items not originally specified.
F. Conversion of schematic layouts:
1. Arrangement of conduits , circuits, piping, ducts
and similar items are in most cases shown
schematically on the Drawings.
2. Legibly mark to record actual construction:
a. Dimensions accurate to within 1" on the
centerline of items shown schematically.
b. Identify each item, for example, "cast lron
drainll "galvanized water".
c. Identify location of each item, for example,
lIunder slab", "in ceiling plenum", "exposed".
3. The Construction Manager may waive requirements of
schematic layout conversion, when in his opinion,
it serves no beneficial purpose. Do not, however,
rely on waivers being issued except specifically
issued by the Construction Manger in writing.
PROJECT RECORD DOCUMENTS (ADD. 2)
01720 - 2
01/06/92
1..4 SUBMITTAL
A. At completion of Project, deliver Project Record
Documents as delineated in paragraph 1.2 F. above, to the
Construction Manager prior to request for final paYment.
B. Accompany submittal with transmittal letter, in
duplicate, containing:
1. Date
2. Project title and HLM Project number
3. The Contractor's name and address
4. Title and number of each record document
5. Certification that each document as submitted is
complete and accurate.
6. Signature of the Contractor, or his authorized
representative.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
***************
END OF SECTION 01720
01/06/92
PROJECT RECORD DOCUMENTS (ADD. 2)
01720 - 3
SECTION 01730
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1. .1 SUl1MARY
A. section includes:
1. Format and content of manuals
2. Instruction of the Owner's personnel
3. Schedule of submittals
B. Related sections:
1. SECTION 01301 - SUBMITTALS
2. SECTION 01700 - CONTRACT CLOSEOUT
3. Individual Specifications sections: specific
requirements for operation and maintenance data.
1..2 QUALITY ASSURANCE
A. Prepare instructions and data by per$onnel experienced in
maintenance and operation of described products.
1..3 FORMAT
A. Prepare data in the form of an instructional manual.
B. Binders: commercial quality, 8-1/2" x 11" three-ring
binders with hardback, cleanable, plastic covers; 1-1/2"
maximum ring size. When multiple binders are used,
correlate data into related consistent groupings.
c. Cover: identify each binder with typed or printed title
OPERATION AND MAINTENANCE INSTRUCTIONS; list title of the
Project and separate building; identify subject matter of
contents.
D. Arrange content by systems under Section numbers and
sequence of Table of Contents of these Specifications.
E. Provide tabbed fly leaf for each separate product and
system, with typed description of product and major
component parts of equipment.
F. Text: manufacturer's printed data, or typewritten data
on 20 pound paper.
G. Drawings: provide with reinforced punched binder tab.
Bind in with text; fold larger drawings to size of text
OS/20/91
OPERATION AND MAINTENANCE DATA
01730 - 1
pages.
1..4 CONTENTS, EACH VOLUME
A. Table of Contents: provide title of the Project; names,
addresses, and telephone numbers of the Construction
Manager, the Architect, consultants, and the Contractor
with name of responsible parties; schedule of products
and systems, indexed to content of the volume.
B. For each product or system: list names, addresses and
telephone numbers of subcontractors and suppliers,
including local source of supplies and replacement parts.
C. Product data: mark each sheet to clearly identify
specif ic products and component parts, and data
applicable to installation. Delete inapplicable
information.
D. Drawings: supplement product data to illustrate
relations of component parts of equipment and systems, to
indicate control and flow diagrams. Do not use the
Project Record Documents as maintenance drawings.
E. Type text: as required to supplement product data.
Provide logical sequence of instructions for each
procedure, incorporating manufacturer's instructions.
F.
Warranties and bonds:
bind in copy of each.
1. .5 l'1ANUAL FOR MATERIALS AND FINISHES
A. Building products, applied materials, and finishes:
include product data, with catalog number, size,
composi tion, and color and texture des ignations. Provide
information for re-ordering custom manufactured products.
B. Instructions for care and maintenance; include
manufacturer's recommendations for cleaning agents and
methods, precautions against detrimental agents and
methods, and recommended schedule for cleaning and
maintenance.
C. Moisture protection and weather exposed products:
include product data listing applicable reference
standards, chemical composition, and details of
installation. Provide recommendations for inspections,
maintenance, and repair.
D. Additional requirements; as specified ln individual
product specification Sections.
OS/20/91
OPERATION AND HAINTENANCE DATA
01730 - 2
1..6 MANUAL FOR EQUIPMENT AND SYSTEMS
A' Each item of equipment and each system: include
descr iption of unit or system, and component parts.
Identify function, normal operating characteristics, and
limiting conditions. Include performance curves, with
engineering data and tests, and complete nomenclature and
commercial number of replaceable parts.
B. panelboard circuit directories: provide electrical
service characteristics, controls and communications.
.C. Include color coded wiring diagrams as installed.
D. Operating procedures: include start-up, break-in, and
routine normal operating instructions and sequences.
Include regulation, control, stopping, shut-down, and
emergency instructions. Include summer, winter, and
special operating instructions.
E. Maintenance requirements: include routine procedures and
guide for trouble-shooting; disassembly, repair, and
reassembly instructions; and alignment, adjusting,
balancing, and checking instructions.
F. Provide servicing and lubrication schedule, and list of
lubricants required.
G. Include manufacturer's printed operation and maintenance
instructions.
H. Include sequence of operation by controls manufacturer.
I. Provide original manufacturer's parts list,
illustrations, assembly drawings, and diagrams required
for maintenance.
J. Provide control diagrams by controls manufacturer as
installed.
K. Provide the Contractor's coordination drawings, with
color coded piping diagrams as installed.
L. Provide charts of valve tag numbers, with location and
function of each valve, keyed to flow and control
diagrams.
M.
Provide list of original manufacturer's spare
current prices, and recommended quantities
maintained in storage.
parts,
to be
OPERATION AND MAINTENANCE DATA
01730 - 3
OS/20/91
N. Include test and balancing reports.
o . Additional requirements: as specif ied in individual
product specification sections.
P. Provide a listing in Table of Contents for design data,
with tabbed fly sheet and space for insertion of data.
1..7 INSTRUCTION OF THE Ow~ER PERSONNEL
A. Before final inspection, instruct the Owner's designated
personnel in operation, adjustment, and maintenance of
products, equipment, and systems, at agreed upon times.
B. For equipment requiring seasonal operation, perform
instructions for other seasons within six months.
C. Use operation and maintenance manuals as basis for
instruction. Review contents of manual with personnel in
detail to explain all aspects of operation and
maintenance.
D.
Prepare and insert additional
Maintenance Manual when need
apparent during instruction.
data in
for such
Operation and
data becomes
1..8 SUBMITTALS
A. Submit two copies of preliminary draft or proposed
formats and outlines of contents before start of the
Work. The Construction Manager and Architect will review
draft and return one copy with comments.
B. For equipment, or component parts of equipment put into
service during construction and operated by the Owner,
submit documents within ten days after acceptance.
C. Submit one copy of completed volumes in final form 15
days prior to final inspection. Copy will be returned
after f ina 1 inspection , with Construction Manager and
Archi tect comments. Revise content of documents pr ior to
final submittal.
D. Submi t t"w copies of revised volumes of data in final
form within ten days after final inspection.
OS/20/91
OPERATION AND Y~INTENANCE DATA
01730 - 4
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01730
OS/20/91
01730 - 5
OPERATION k~D MAINTENANCE DATA