Change Order No. 01-011-004 C H A N G E 0 R D E R Project: KJ - NEW DETENTION FACILITY Change Order Number: 01-011-004 Change Order Date: 02/10/94 To Contractor: RODEL GROUP, INC. 1785 WEST 40TH ST HIALEAH, FL Architect's Project #: 33012 Contract For: FIRE PROTECTION SYSTEM Contract Date: 02/19/92 You are directed to make the folLowing changes in this contract; aLl other provisions of the contract shaLL, except as specificaLly changed herein, remain in fuLL force and effect. Issue: 186 - ASI #39/40R - FIRE WATER PUMP In accordance with the Architect's Supplemental Instruction No. 39, suppLy and instaLL the above ground piping and connections for the pre-engineered package fire pump to compLete the installation of this equipment purchased by the Owner. -~ " ~~::5 Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all CI:ltlated.lmpacts due to this contract change for the LUMP SUM AMOUNT of $ 2,936.00 and 0 days. The Original Contract Amount was .................................................................... $ Net Change by PreviousLy Authorized Change Orders .................................................... $ The Contract Amount prior to this Change was ......................................................... $ The Va lue of th i s Change Order is.................................................................... $ The New Contract Amount including this Change Order will be .......................................... $ The Contract Time wiL L change by ..................................................................... The Date of SubstantiaL Completion as of the Date of this Change Order is ............................ 456,295.00 8,906.00 465,201.00 2,936.00 468,137.00 o days 11/01/93 Recommended by Construction Manager: Approved by Architect: Morrison-Knudsen/Gerrits 5090 toll... R~,ad ~no , y y?~'Y HANSEN LIND MEYER ~~;~~ By , ~ i~~4- ate Approved As To Authorized by Owner: lciency: Date Date County Attorney's Office L ~ r:f'\-' y 1/ Attest: Danny L. Kolhage, Clerk BY~~) Depu CLerk DateM~G~ J ~ I ,0,0,1 By Not valid unLess signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.