Change Order No. KJ-010-003
C H A N G E 0 R D E R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-010-003
To Contractor: LAKE PLUMBING, INC.
P.O. BOX 1294
EUSTIS, FL
Change Order Date: 09/02/92
Architects Project #:
32727
Contract For:
PRIME PLUMBING
Contract Date:
02/19/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 063 - DELETE MEZZANINE FLOOR DRAINS
Per the Owner request, and in accordance with Lake Plumbing'S written quotation dated May 5, 1992
(letter No. KJ-010-041), delete FD-3 floor drains and associated piping at the mezzanines in zones D
and t::J < i.
e::::
<::)
(,)
LL:
r.c:.
Cl~
C.::-
u..
':'t
.,.l._
.....
a:
)--~
z
o
W
-J
l.L.
-..r
N
a..
LU
C/.l
"-",l.._1......
:~,::5~
<: ::z:
Cl
~
.L_
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ -4,364.00 and 0 days.
Monroe County Board of County Commissioners
500 Whitehead Street
Key West, FIJI 33040.. ~_
~.~.I\VV'.~....,-.~ ~~
By Mayor/Chairman Date ~
The Origninal Contract Amount was ..... .......... ................... ................... ...............
Net Change by Previously Authorized Change Orders ....................................................
The Contract Amount prior to this Change was .........................................................
The Va l ue of th i s Change Order is....................................................................
The New Contract Amount including this Change Order will be ..........................................
The Contract Time wi II change by............................ ....... ..................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
Recommended by Construction Manager:
Morrison-Knudsen/Gerrits
5090 College Road
Aesl Fla 33045
., A 11L
By
c, · ",. , "-
Date
By
Agreed to by Contractor:
Authorized by Owner:
LAKE PLUMBING, INC.
P.O. BOX 1294
EUstIS, Fl 32727 ~
:t~ m'5.:.
By f Iv'\.
9 - 3 - 9 'L
Date
Attest:
By
By
Date
$ 1,394,753.00
$ -384,782.00
$ 1,009,971.00
$ -4,364.00
$ 1,005,607.00
o days
07/01/93
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.