Loading...
07/15/1992 Agreement New Detention Facility Contract KJ-027, Carpentry and General Works; Access Flooring, Resilient Flooring and Carpet; Acoustical Ceilings RJC & Associates, Inc. I. II. c. A. B. C. D. E. F. G. H. I. Form of Agreement Public Construction Bond Certificate of Insurance Table of Contents Schedule of Drawings Scope of Work - Bid Package #35 Scope of Work - Bid Package #37 Scope of Work - Bid Package #39 Milestone Schedule A. Proposal Form, pages 00135-1 through 00135-4 signed by bidder and dated June 8, 1992. 5% Bid Bond from Employers Insurance of Wausau in Wisconsin. Lobbying and Conflict of Interest Clause. Non-Collusion Affidavit. Sworn Statement on Public Entity Crimes. Proposal Form, pages 00137-1 through 00137-3 signed by bidder and dated April 23, 1992. 5% Bid Bond from Employers Insurance of Wausau in Wisconsin. Lobbying and Conflict of Interest Clause. Non-Collusion Affidavit. Sworn Statement on Public Entity Crimes. Proposal Form, pages 00139-1 through 00139-3 signed by bidder and dated April 28, 1992. 5% Bid Bond from Employers Insurance of Wausau in Wisconsin. Lobbying and Conflict of Interest Clause. Non-Collusion Affidavit. Sworn Statement on Public Entity Crimes. B. III. Conditions of the Contract A. General Conditions B. Supplementary Conditions C. Project Safety and Health Plan D. Contractor's Quality Control Plan E. Substantial Completion & Owner's Acceptance F. General Requirements Application for Payment Change Order Procedures Security Project Procedures Project Meetings Submittals Progress Schedules Schedule of Values Daily Construction Report Document Clarification Requests Testing Laboratory Services Temporary Utilities --Continued On Next Pal!e-- New Detention Facility Contract KJ-027, Carpentry and General Works; Access Flooring, Resilient Flooring and Carpet; Acoustical Ceilings RJC & Associates, Inc. --Continuation-- Construction Aids Access Roads and Parking Areas Temporary Controls Project Identification and Signs Field Offices and Sheds Construction Cleaning Material and Equipment Post-Bid Substitutions Starting of Systems Systems Demonstrations Contract Closeout Final Cleaning Project Record Documents Operation and Maintenance Data THE AMERICAN INSTITUTE OF ARCHITECTS F~Lfr ;'1[. >)[':nDf '92 ,~UG 11 1410 :51 :--'1: , \..'L 1"19NROf 1.,):jN; r ; I.". AlA Document A101/CM CONSTRUCTION MANAGEMENT EDITION Standard Form of Agreement Between Owner and Contractor where the basis of payment is a STIPULATED SUM 1980 EDITION THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH AN ATTORNEY IS ENCOURAGED. This document is intended to be used in conjunction with AlA Documents A201/CM, 1980; B141/CM, 1980; and B801, 1980. AGREEMENT No. KJ-027. Carpentry and General Acoustical Ceilings. made as of the AI I~+. 'r day of Hundred and IV iW\c"~. WI Works; Access Flooring. Resilient Flooring and Carpet; ...lit I ~ in the year of Nineteen BETWEEN the Owner: Monroe County Board of County Commissioners 500 Whitehead Street Key West. FL 33040 and the Contractor: RJC & Associates. Inc. 5611 Dewey Street Hollywood. FL 33023 305/987-8301 the Project: New Monroe County Detention Facility 5501 College Road. Stock Island Key West. FL 33040 the Construction Manager: Morrison-Knudsen/Gerrits the Architect: Hansen Lind Meyer/Gonzalez The Owner and the Contractor agree as set forth below. Copyright 1975, @ 1980 by The American Institute of Architects, 1735 New York Avenue, N.W., Washington, D.C. 20006. Re- production of the material herein or substantial quotation of its provisions without written permission of the AlA violates the copyright laws of the United States and will be subject to legal prosecution. AlA DOCUMENT Al0l/CM . OWNER-CONTRACTOR AGREEMENT. CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 173S NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM-1980 1 WARNING: Unlicensed photocopying violates U.S. copyright laws and Is subject to legal prosecution. ARTICLE 1 THE CONTRACT DOCUMENTS The Contract Documents consist of this Agreement, the Conditions of the Contract (General, Supplementary and other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after execution of this Agreement. These form the Contract, and all are as fully a part of the Contract as if attached to this Agreement or repeated herein. An enumeration of the Contract Documents appears in Article 7. ARTICLE 2 THE WORK The Contractor shall perform all the Work required by the Contract Documents for (Here insert the caption descriptive of the Work as used on other Contract Documents.) Bid Group 3, Bid Package No. 35, Carpentry and General Works Bid Group 3, Bid Package No. 37, Access Flooring, Resilient Flooring and Carpet Bid Group 3, Bid Package No. 39, Acoustical Ceilings ARTICLE 3 TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION The Work to be performed under this Contract shall be commenced on the date as established in the Notice to Proceed, and, subject to authorized adjustments, Substantial Completion of the Work shall be achieved not later than the time (Here insert any special provisions for liquidated damages relating to failure to complete on time.) indicated in Section 00353 Milestone Schedule. AlA DOCUMfNT A101/CM . OWNER-CONTRACTOR AGREEMENT' CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM -1980 2 WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution. ARTICLE 4 CONTRACT SUM The Owner shall pay the Contractor in current funds for the performance of the Work, subject to additions and deductions by Change Order as provided in the Contract Documents, the Contract Sum of Five Hundred Fourteen Thousand Eight Hundred............................................ The Contract Sum is determined as follows: (State here the base bid or other lump sum amount, accepted alternates and unit prices, as applicable.) $514,800 Base Base Base 35, Carpentry and General Works............................... 37, Access Flooring, Resilient Flooring and Carpet............ 39, Acoustical Ceilings....................................... Subtotal Bid Package No. 35, 37, and 39 combination credit....................................... Total Bid, Bid, Bid, Bid Package No. Bid Package No. Bid Package No. $329,800 $135,000 $ 75,000 $539,800 $<25,000> $514,800 ARTICLE 5 PROGRESS PAYMENTS Based upon Applications for Payment submitted to the Construction Manager by the Contractor and Project Certificates for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the Contractor as provided in the Contract Documents for the period ending the Twenty Fi fty (25) . ~~ of each month as follows: approxlma y Not later than Thirty (30) days following the end of the period covered by the Application for Payment, Ninety percent ( 90 %) of the portion of the Contract Sum properly allocable to labor, materials and equipment incorporated in the Work and Ni nety percent (90 %) of the portion of the Contract Sum properly allocable to materials and equipment suitably stored at the site or at some other location agreed upon in writing, for the period covered by the Application for Payment, less the aggregate of previous payments made by the Owner; and upon Substantial Completion of the Work, a sum sufficient to increase the total payments to One Hundred percent (100 %) of the Contract Sum, less such amounts as the Architect shall determine for all incomplete Work and unsettled claims as provided in the Contract Documents. (1/ not covered elsewhere in the Contract Documents, here insert any provision lor limiting or reducing the amount retained after the Work reaches a certain stage 01 completion.) Reference Section 00800 Substantial Completion and Owner Acceptance. _ Pay~-d-tle -and- 'tlt1'p'll'i l'l-l1fll'le1" -tfie~6+MfOC-t-G@€tiTAeR~ SA~1.l ~- 4l-t.efe!p~ k,()fll-~ .Qatil..pa.~-~-dl.lil..o.t- ~ ..rete _ efl~W6W; -G-F- ~ -tfie-a9geAC-e-4Aet'eG~ -a-t-~ +e~aA- FiK€-l3l'@o~~ ft ~-t fie-l3hK-e- -e+ -~ +'of6tec-{, _~~w..,.~..~~le-Gll..i.."'_~~..,J. (Usury laws and requirements under the Federal Truth in Lending Act, similar state and local consumer credit laws and other regulations at the Owner's and Contractor's principal places of business, the location of the Project and elsewhere may affect the validity 01 this provision. Specific legal advice should be obtained with respect to deletion, modification or other requirements such as wrHren disclosures or waivers.) AlA DOCUMENT Al0l/CM . OWNER-CONTRACTOR AGREEMENT . CONSTRUCTION MANAGEMENT EDITION' JUNE 1980 EDITION' AIA@ . @1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM -1980 3 WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution. ARTICLE 6 FINAL PAYMENT Final payment, constituting the entire unpaid balance of the Contract Sum, shall be paid by the Owner to the Contractor when the Work has been completed, the Contract fully performed, and the Architect has issued a Project Certificate for Payment which approves the final payment due the Contractor. ARTICLE 7 MISCELLANEOUS PROVISIONS 7.1 Terms used in this Agreement which are defined in the Conditions of the Contract shall have the meanings designated in those Conditions. 7.2 The Contract Documents, which constitute the entire agreement between the Owner and the Contractor, are listed in Article 1 and, except for Modifications issued after execution of this Agreement, are enumerated as follows: (List below the Agreement, the Conditions of the Contract [General, Supplementary and other Conditions], the Drawings, the Specifications, and any Addenda and accepted alternates, showing page or sheet numbers in all cases and dates where applicable.) I. Bidding Documents A. Bid Group 3 Bid Documents for New Monroe County Detention Facility, which include Bidding Documents, Contract Documents, Conditions, Drawings, General Requirements and Technical Specifications, and which are enumerated in the attached Table of Contents, contained in Bid Group 3, pages 00001-1 thru 00001-9, dated 03/24/92, and in the attached Schedule of Drawings contained in Bid Group 3, pages 00993-1 thru 00993-19, dated 05/02/92, all as amended by the addenda listed below. Addendum No. 10 dated April 16, 1992 Addendum No. 11A dated April 21, 1992 Addendum No. lIB dated April 24, 1992 Addendum No. 11C dated May 1, 1992 Addendum No. 11 dated May 5, 1992 Addendum No. 12A dated May 8, 1992 Addendum No. 12B dated May 13, 1992 Addendum No. 12C dated May 15, 1992 Addendum No. 12 dated May 21, 1992 Addendum No. 13 dated June 1, 1992 B. Addendum No. 1A dated November 26, 1991 Addendum No. 1B dated December 11, 1991 Addendum No. 1 dated December 20, 1991 Addendum No. 2A dated January 3, 1992 Addendum No.2 dated January 6, 1992 Addendum No. 3 dated January 9, 1992 Addendum No.4 dated January 13, 1992 Addendum No. 5 dated February 18, 1992 Addendum No. 6 dated March 4, 1992 Addendum No.7 dated March 10, 1992 Addendum No.8 dated March 25, 1992 Addendum No.9 dated April 3, 1992 II. Proposal Documents submitted by FJC & Associates, Inc., on June 9, 1992: BP #35 A. Proposal Form, pages 00135-1 thru 00135-4, signed by bidder, and dated June 8, 1992. B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin. C. Sworn Statement on Public Entity Crimes. D. Lobbying and Conflict of Interest Clause. E. Non Collusion Affidavit. BP #37 A. Proposal Form, pages 00137-1 thru 00137-3, signed by bidder, and dated April 23, 1992. B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin. C. Sworn Statement on Public Entity Crimes. D. Lobbying and Conflict of Interest Clause. E. Non Collusion Affidavit. BP #39 A. Proposal Form, pages 00139-1 thru 00139-3, signed by bidder, and dated April 28, 1992. B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin. C. Sworn Statement on Public Entity Crimes. D. Lobbying and Conflict of Interest Clause. E. Non Collusion Affidavit. Voluntary Alternate Bid Deductive Proposal Form pages 5 and 6. AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT . CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW., WASHINGTON, D.C. 20006 A101/CM -1980 4 WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution. 7.3 Temporary facilities and services: . (Here insert temporary facilities and services which are different from or in addition to those included elsewhere In the Contract Documents.) Reference the documents issued for bidding. 7.4 Working Conditions: (Here list any special conditions affecting the Contract.) Reference the documents issued for bidding. (Sea 1) Attest: Danny L. Kolhage, Clerk of the Court "Approved as to Fonn and Legal Sufficiency" By: .L2L~#~/f (Deputy Cl ) Date: ~-15'" '1':/ / BY:~~ ) Date: I- -- 'Z-- - 9 z....., This Agreement entered into as of the day and year first written above. m1 CAUTION: You should sign an original AlA document which has this caution printed in red. An original assures that changes will not be obscured as may occur when documents are reproduced. OWNER Monroe By: Its: AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT' CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM -1980 5 WARNING: Unlicensed photocopying violates U.S. copyright laws and Is SUbject to legal prosecution. PUBLIC CONSTRUCTION BOND Bond No. 1450-77-086302 BY THIS BOND, We R.J.C. & Associates, Inc. , as Principal and Employers Insurance of Wausau , a corporation, as Surety, are bound to Monroe County Board, of County Corrunissionerlserein called Owner, in the sum of $ 514,800.00 for payment of which we bind ourselves, our heirs, personal representatives, successors, and assigns, jointly and severally. THE CONDITION OF THIS BOND is that if Principal: 1. Performs the contract dated July 15 , 1921-, between Principal and Owner for construction of Monroe County Detention Facility the contract being made a part of this bond by reference, at the times and in the manner prescribed in the contract; and 2. Promptly makes payments to all claimants, as defined in section 255.05(1), Florida Statutes, supplying Principal with labor, materials, or supplies, used directly or indirectly by Principal in the prosecution of the work provided for in the contract; and 3. Pays Owner all losses, damages, expenses, costs, and attorney's fees, including appellate proceedings, that Owner sustains because of a default by Principal under the contract; and 4. Performs the guarantee of all work and materials furnished under the contract for the time specified in the contract, then this bond is void; otherwise it remains in full force. Any changes in or under the contract documents and compliance with any formalities connected with the contract or the changes does not affect Surety's obligation under this bond. DATE ON Ju1v 20. , 19..2.L. BY Employers Insurance of Wausau (NAME OF SURETY) 11/20/91 PUBLIC CONSTRUCTION BOND 00610 - 1 :::L Z o w a: Z a: <t: w 0... 0... <t: f- a z (f) w a o f- Z W ~ W ,,~ Z(f) - (f) 7-=r: t...~ ~~ a: a ~ LL a a: w S a 0... o -...J :g; <t: f- a z (f) ~ I f- No. 214-147- 00298 EMPIOVERS INSURANCE OF WAUSAlJ A Mutual Company POWER OF ATTORNEY KNOW ALL MEN BY THESE PRESENTS: That the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company, a corporation duly organized and existing under the laws of the State of Wisconsin, and having its principal office in the City of Wausau, County of Marathon, State of Wisconsin, has made, constituted and appointed, and does by these presents make, constitute and appoint CHARLES J. NIELSON, JACK E. FOWLER, MARY C. ACEVES, JOHN S. HARRIS its true and lawful attorney-in-fact, with full power and authority hereby conferred in its name, place and stead, to execute, seal, acknowledge and deliver ANY OR ALL BONDS, UNDERTAKINGS, RECOGNIZANCES OR OTHER WRITTEN OBLIGATIONS IN THE NATURE THEREOF INCLUDING CONSENTS OF SURETY AND WAIVERS TO THE CONDITIONS OF CONTRACTS. NOT TO EXCEED THE PENAL SUM OF TEN MILLION DOLLARS ($10,000,000). ~ and to bind the corporation thereby as fully and to the same extent as if such bonds were signed by the President, sealed with the corporate seal of the corporation and duly attested by its secretary hereby ratifying and confirming all that the said attorney-in-fact may do in the premises. This powpr of attorney is granted pursuant to the following resolution adopted by the Board ofl)irectors of said Company at a meeting duly called and held on the 1 Rth day of May, 1 ~l7:l, which resolution is still in effect: "RESOLVED, that the President and any Vice President - plective or appointive - of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company be, and that each of them hereby is, authorized to pxpcute powers of attorney qualifying the attornpy nampd in the givpn power of attorney to pxpcutp on behalf of EMPLOYERS INSURANCE OF W AUSAU A Mutual Company bonds, undertakings and all contracts of surptyship; and that any secrptary or assistant secretary be, and that each or an.v of thpm hprpby is, authorized to attpst thp expcution of any such power of attorney, and to attach thpreto the spal of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company." "FURTH ER RESOLVED, that the signaturps of such officprs and thl' spal of EMPLOYERS INSURANCE OF W AUSAU A Mutual Company may he affixpd to any such power of a ttorn,'y or to any certificatl' relating thereto by facsimile, and any such powpr of attornpy or certificatl' bparing such facsimilp signaturps and facsimill' seal shall be valid and binding upon thp EMPLOYERS INSURANCE OF W AUSAU A Mutual Company when so affixed and in the future with respect to an.v hond, undprtaking or contract of surPlyship to which it is attachpd." IN WITNESS WH EREOF, EMPLOYERS INSURANCE OF W AUSAU A Mutual Company has caused these prpsents to be signed by the senior vice president and attested by its assistant secretary, and its corporate seal to be hereto affixed this Is t day of ,TANTTARY ,19--.9...1. EMPLOYERS INSURANCE OF WAUSAU A Mutual Company ~r:J.~~ Bill D. Wymore l;:::;::;;;) ~.. SEAL// ~~~,;,/j By Executive Vice President Attest: A I! 4L R. J. Blsteman/" Assistant Secretary STATE OF WISCONSIN ) ) ss. COUNTY OF MARATHON) On this Is t JANUARY 91 day of , 19 _ , before me personally came Bill D. Wymore , to me known, who being by me duly sworn, did depose and say that he is an executive vice president of the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company, the corporation described in and which executed the above instrument: that he knows the seal of said corporation: that the seal affixed to said instrument is such corporate seal and that it was so affixed by order of the Board of Directors of said corporation and that he signed his name thereto by like order. I" W ITN FSS W H F R I()I-. I h;l\e hereunto set mv hand and affixed mv official seal the day and year herein first above written. ~.t1.,l~ Patricia A. Kleman NOTARY PUBLIC STATE OF WISCONSIN I STATE OF WISCONSIN CITY OF WAUSAll ) ss. MY COMMISSION EXPIRES MAY 29,1994 COUNTY OF MARATHON I CERTIFICATE I. thp undersigned. assistant spcretary of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company, a Wisconsin corporation. do hprphy cprtify that thp forpgoing and attachpd power of attornl'y, WHICH MUST CONTAIN A VALIDATING STATI<:MENT PRINTED IN THE MARGIN THEREOF IN RED INK, H'mains in full force and has not hl'pn n'\'ok"d; and furthprrnon' that the rpsol ution oft hI' Board of I li rpdors spt forth in thp power of attornpy is still in force. Signl'd and spalpd in thl' City ofWausau, Marathon County. Statp of Wisconsin, this 20th day of ______ -luly_ _____, 1~L_22 Notary Public ti:~;::;~:.~:-?~\ ~ i -'- j = \~:<;;~,::;~~~~i (.-:-::;-;':;0- I:~ LOItl'Olf04fl' .~ ~~ -0- 1 \ \'},SEAL Ii ~~...~,.....;l1 Ad~ / ./ Assistant Secretary R. J. Besteman NOTE IF YOll HA Vr: ANY qUESTIONS RE(~ARI>INC THE V ALIf)ITY OR WORIlING OF THIS POWER OF ATTORN r: y, CALL TOLL FRE E (HOO) H:.!(;- Hili I. II N WISCONSIN. CALL (HOO) .172-0041 ). At~ttlll.~ CERTIFICATE OF INSURANCE ISSUE DATE (MM/DD/YY) PRODUCER Collinsworth, Alter, Nielson, 1wler & Dowling, Inc. . ost Office Box 9315 Miami Lakes, FL 33014-9315 7/301~~ THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE POLICIES BELOW. C~T~~~NY A Maryland Casualty Co. COMPANIES AFFORDING COVERAGE O~~y o'/T~lr .( (1'>-' <{;' (. Insurance Co INSURED C~T~~~NY B NOT' t h ern R. J. C. & Associates, 5611 Dewey Street Hollywood FL Inc. C~T~~~NY C Northern Insurance Co 33023 C~T~~~NY D Liberty Mutual Ins Co C~~~~NY E COVERAGES THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS. EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS. CO LTR TYPE OF INSURANCE POLICY NUMBER POLICY EFFECTIVE POLICY EXPIRATION DATE (MMIDD/YY) DATE (MM/DD/YY) LIMITS A GENERAL LIABILITY EP A 1 522641 9 X COMMERCIAL GENERAL LIABILITY CLAIMS MADE X OCCUR. OWNER'S & CONTRACTOR'S PROTo 11/01/9111/01/92 GENERAL AGGREGATE $ PRODUCTS-COM PlOP AGG. $ PERSONAL & ADV. INJURY $ EACH OCCURRENCE $ FIRE DAMAGE (Anyone fire) $ MED. EXPENSE (Anyone person) $ 1000000 1000000 1000000 1000000 50000 _ ___ 5000 1000000 B AUTOMOBILE LIABILITY ( ANY AUTO ALL OWNED AUTOS SCHEDULED AUTOS X HIRED AUTOS X NON-OWNED AUTOS GARAGE LIABILITY ECA15250468 : C EXCESS LIABILITY X UMBRELLA FORM OTHER THAN UMBRELLA FORM UBA6978610 11/01/91 11/01/92 COMBINED SINGLE LIMIT BODIL Y INJURY (Per person) BODIL Y INJURY (Per accident) PROPERTY DAMAGE .<<~~'.__'H__'_""_'_ 11/01/91 11/01/92 EACH OCCURRENCE AGGREGATE $ $ $ $ 2000000 $ 2000000 D WORKER'S COMPENSATION WC1351429916 2/14/92 2/14/93 X STATUTORY LIMITS EACH ACCIDENT $ 500000 DISEASE-POLICY LIMIT $ 500000 DISEASE-EACH EMPLOYEE $ .~..QQQQ!L . ,,', ""'H,~' ,___.,_.,,,_. AND EMPLOYERS' LIABILITY OTHER Re: New Monroe County Detention Facility 5501 College Road Stock Island, Key West, Fl 33040 DESCRIPTION OF OPERATIONS/LOCATlONSIVEHICLES/SPECIAL ITEMS Monroe Co Board of County Commissioners and !Morrison-Knudsen/Gerrits are added as Additional Insureds as :respect to Liability and work_being---2...~x..foT'med ELthe ~nsLl.!:_~~ I CERTIFICATE HOLDER CANCELLATION 1nroe Co Board of County _Jmmissioners or Monroe County f. Morrison-Knudsen/Gerrits POBox 5283 Key West, Fl 33040 SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO MAIL 60 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES. ,","O1"~'~ "R"'I!~':/ii~~~. rF~--- ACORD 25-5 (7/90) @ACORD CORPORATION 1990 2- 5 TABLB OJ' CONTENTS BID GROUP 3 1. Bidding Documents (Volume X) 03/24/92 section 00030 section 00050 section 00100 section 00113 section 00114 section 00115 section 00116 section 00117 section 00118 section 00119 section 00120 section 00121 section 00127 section 00128 section 00129 section 00130 section 00131 section 00132 section 00133 section 00134 section 00135 Section 00136 section 00137 section 00138 section 00139 section 00140 section 00141 section 00142 section 00148 section 00149 section 00143 section 00144 section 00145 section 00146 Notice of Calling for Bids Project Summary Instructions to Bidders Proposal Forms: Security Systems Prime Electrical Contract Zones A,B,C,D,E Mechanical Process and HVAC Prime Plumbing Contract Zones A,B,C,O,E Fire Protection system Food Service Equipment Laundry Equipment Loading Dock Equipment Pneumatic Tube System Metals-Doors-Glazing Masonry Concrete Roofing stairs & Miscellaneous Metals Sprayed Insulation Sealants Gypsum Board, Lath & Plaster Carpentry Special Flooring Access Flooring, Resilient Flooring & Carpet Ceramic Tile Acoustical Ceilings Painting & Wallcovering Fence & Gates Asphaltic Concrete Paving Wastewater Treatment Plant & utilities Landscaping Schedule of unit Prices: Security systems Prime Electrical Contract Zones A,B,C,O,E Mechanical Process and HVAC Prime Plumbing Contract Zones A,B,C,D,E TABLE OF CONTENTS (ADD. 8) 00001 - 1 03/24/92 section 00147 section 00157 section 00163 section 00220 section 00230 section 00303 Section 00305 Section 00307 section 00309 section 00310 section 00311 Section 00312 section 00313 section 00314 section 00315 section 00316 section 00317 Section 00318 section 00319 section 00320 section 00321 section 00327 Section 00328 section 00329 section 00330 section 00331 section 00332 section 00333 Section 00334 section 00335 section 00336 section 00337 section 00338 section 00339 section 00340 Section 00341 section 00342 section 00343 Section 00344 section 00353 Fire Protection System Metals-Doors-Glazing Pre-Bid Substitutions Geotechnical Data site Survey Scopes of Work for Reference (BG-1 and BG-2) : site Electrical & Temporary Power site Grading & Caissons Concrete Foundations site Plumbing Precast Concrete Hydraulic Elevators Precast Embeds Scopes of Work: Security Systems Prime Electrical Contract Zones A,B,C,D,E Mechanical Process and HVAC Prime Plumbing Contract Zones A,B,C,D,E Fire Protection System Food Service Equipment Laundry Equipment Loading Dock Equipment Pneumatic Tube System Metals-Doors-Glazing Masonry Concrete Roofing stairs & Miscellaneous Metals sprayed Insulation Sealants Gypsum Board, Lath & Plaster Carpentry Special Flooring Access Flooring, Resilient Flooring & Carpet Ceramic Tile Acoustical Ceilings Painting & Wallcovering Fence & Gates Asphaltic Concrete Paving Wastewater Treatment Plant & utilities Landscaping Milestone Schedule TABLE OF CONTENTS (ADO. 8) 00001 - 2 section 00410 Bid Bond - AlA Document A310, February 1970 edition section 00420 Sworn statement on Public Entity Crimes section 00425 Lobbying and Conflict of Interest Clause section 00430 Non-Collusion Affidavit section 00440 Proposed Subcontractor Listing section 00450 Contractor's Qualification statement - AlA Document A305 2. Contract Documents (Volume I) section 00500 standard Form of Agreement Between Owner and Contractor - AlA Document A101/CM, June 1980 edition section 00610 Public Construction Bond 3. Conditions (Volume I) section 00750 General Conditions, AlA Document A201/CM, June 1980 edition section 00800 substantial Completion and Owner Acceptance section 00805 Supplementary General Conditions section 00900 Application & Certificate for Payment - AlA Document G702/G703 section 00905 Contractor's Affidavit of Payment of Debts and Claims section 00908 Contractor's Affidavit of Release of Liens section 00910 Consent of surety to Final Payment - AlA Document G707, April 1970 edition section 00915 Affidavit and Partial Release of Lien section 00970 Project Safety and Health Plan section 00980 Contractor Quality Control Plan 03/24/92 TABLE OF CONTENTS (ADD. 8) 00001 - 3 4. Drawings section 00993 Schedule of Drawings, Bid Group 3 5. General Requirements (Volume I) Section 01027 section 01028 section 01130 section 01200 section 01301 section 01310 Section 01370 section 01385 section 01395 section 01410 Section 01510 section 01520 Section 01550 section 01560 section 01580 Section 01590 section 01595 section 01600 Section 01630 section 01650 section 01670 section 01700 section 01710 section 01720 section 01730 Application for Payment Change Order Procedures Security Project Procedures Project Meetings Submittals Progress Schedules Schedule of Values Daily Construction Reports Document Clarification Requests Testing Laboratory Services Temporary utilities Construction Aids Access Roads and Parking Areas Temporary Controls Project Identification and Signs Field Offices and Sheds Construction Cleaning Material and Equipment Post-Bid Substitutions starting of Systems Systems Demonstrations Contract Closeout Final Cleaning Project Record Documents operation and Maintenance Data 03/24/92 00001 - 4 TABLE OF CONTENTS (ADO. 8) 5. Technical specifications, Bid Group Three, (Volume II, dated November 11, 1991) ADDENDA Addendum No. 1, section 00901, pages 00901-1 thru 00901-7. Addendum No. 2, section 00902, pages 00901-1 thru 00902-7. Addendum No. 3, Section 0090,3, pages 00903-1 thru 00903-7. Addendum No. 5, section 00905, page 00905-1, with Revisions to Contract Documents No. 1, pages 1 and 2. Addendum No. 6, section 00906, page 00906-1, with Revisions to Contract Documents No. 2, page 1. Addendum No. 7, section 00907, page 00907-1. DIVISION 2 - SITEWORK section 02211 section 02215 section 02222 section 02226 section 02510 section 02518 section 02520 section 02580 section 02644 section 02721 section 02730 section 02732 section 02733 section 02800 section 02810 Section 02830 section 02835 section 02930 section 02950 Rough Grading Finish Grading Excavating, Backfilling And compacting For structures Excavating, Backfilling and compacting For utilities Asphaltic Concrete paving Concrete unit Pavers Portland Cement Concrete Paving Pavement Marking Water Mains Sewer Structures sanitary sewerage sewage Force Mains Sewage Pump station site Improvements Irrigation system Fence And Gates Barbed Tape Lawns Trees, Shrubs And Ground Cover DIVISION 3 - CONCRETB section 03100 section 03200 section 03300 section 03520 Section 03600 Concrete Formwork Concrete Reinforcement cast-in-Place Concrete Insulating Concrete Decks Grout 03/24./92 00001 - 5 TABLE OF CONTENTS (ADD. 8) DIVISION 4 - MASONRY section 04200 unit Masonry DIVISION 5 - METALS section 05180 section 05500 section 05510 section 05810 Miscellaneous structural Steel Metal Fabrications Metal stairs . Expansion Joint Covers Assemblies DIVISION 6 - WOOD AND PLASTIC section 06100 section 06200 Rough Carpentry Finish Carpentry DIVISION 7 - THERMAL AND MOISTURE PROTECTION section 07115 section 07210 section 07215 section 07272 section 07530 Section 07730 section 07900 Sheet Waterproofing Building Insulation sprayed Insulation Firestop And Penetration Sealing System single Ply Roofing Roof Accessories Joint Sealers DIVISION 8 - DOORS AND WINDOWS section 08100 section 08211 section 08300 Section 08305 section 08320 section 08410 section 08660 section 08710 section 08800 section 08842 section 08902 Metal Doors And Frames Flush Wood Doors Special Doors Access Panels And Doors Security Metal Doors And Frames Aluminum Entrances security Windows Door Hardware Glazing Security Glazing Aluminum Window Walls DIVISION 9 - FINISHES section 09110 section 09200 section 09250 Section 09300 section 09510 section 09650 section 09680 section 09700 section 09800 Non-Load Bearing Wall Framing systems Lath and Plaster Gypsum Board Tile Acoustical ceilings Resilient Flooring Carpet Special Flooring special coatings 03/24/92 00001 - \. TABLE OF CONTENTS (ADD. 8) DIVISION 9 - FINISHES, cont'4 section 09830 Section 09900 section 09950 Elastomeric coating painting Wallcovering DIVISION 10 - SPECIALTIES section 10100 .Section 10160 Section 10200 section 10270 section 10350 section 10500 section 10520 section 10550 section 10606 section 10800 section 10900 Chalkboards And Tackboards Solid Plastic Toilet Partitions Louvers and Vents Access Flooring Flagpole Steel Lockers Fire Extinguisher Cabinets postal Specialties Security Fencing Assembly Toilet Accessories Miscellaneous specialties DIVISION 11 - EQUIPMENT Section 11110 section 11160 section 11197 section 11200 section 11202 section 11203 section 11204 Section 11205 Section 11206 Section 11208 Section 11211 Section 11212 Section 11217 section 11218 Section 11222 section 11224 section 11400 section 11480 section 11704 Laundry Equipment Loading Dock Equipment security/Detention Equipment Basic Electronic Security Requirements System Central Processing Unit Fire Alarm Interface Programmable Logic Controller Address Panels Relay Cabinets Card Access Control situation Man-Down Equipment Closed Circuit Video Equipment Vehicle Loop Detection operational Intercom system Inmate/Attorney Telephones Metal Detection Equipment Food Service Equipment Athletic Equipment Ice Machines DIVISION 13 - RADIATION PROTECTION section 13090 Radiation Protection DIVISION 14 - CONVEYING SYSTEMS section 14700 section 14240 Pneumatic Tube system Hydraulic Elevators 03/24/92 00001 - 7 TABLE OF CONTENTS (ADD. 8) DIVISION 15 - MECHANICAL section 15000 section 15050 section 15060 section 15085 section 15100 section 15110 section 15130 section 15140 section 15160 Section 15175 section 15242 section 15252 section 15290 section 15330 section 15403 section 15404 section 15408 section 15410 section 15430 section 15440 section 15460 section 15470 section 15490 section 15517 section 15540 section 15684 section 15714 section 15770 section 15785 section 15855 section 15858 Section 15880 section 15884 section 15885 section 15890 section 15894 section 15936 section 15950 section 15965 section 15992 section 15995 General provisions Water Treatment pipe and pipe Fittings piping Identification Valves Heat Trace System Thermometers and Gages pipe Hangers And Supports Pumps Variable Speed Motor Control for Fans and Pumps Vibration Isolation Pipe And Equipment Insulation Ductwork Insulation Wet-Sprinkler system Water Booster Pumps Domestic Water Softener Soil, Waste and Vent System storm Drainage System Plumbing specialties Plumbing Fixtures and Accessories Sump Pumps Hot Water storage Heater Fuel storage And Dispensing Systems Hydronic Specialties Emergency Generator Auxiliaries Centrifugal Chillers Blow Thru Cooling Tower Make-Up Air Units Fan Coil Units Air Handling Units Fans Fire DamperS Combination Smoke And Fire Dampers Air Filters Ductwork Air Terminal Units Grilles, Registers, Diffusers Automatic Temperature Control Systems Building Automation system Tests - piping systems system Balancing and Testing 03/24/92 00001 - 8 TABLE OF CONTENTS (ADD. 8) DIVISION 16 - ELECTRICAL section 16010 section 16111 section 16111 section 16120 section 16155 section 16161 section 16170 section 16199 Section 16300 section 16351 section 16400 section 16425 Section 16450 section 16461 section 16470 section 16471 section 16472 section 16500 Section 16601 section 16605 section 16660 section 16721 section 16781 section 16930 Electrical General provisions Conduit Systems - Bid Group 3 Conduit Systems - Bid Group 2 Wire and Cable Combination Motor Starters Motor Control Centers Disconnect Switches Wiring Devices and Plates Standby Power Generation Uninterruptible Power Supply Service and Power Distribution Systems Main Service switchboard Electrical Systems Grounding Dry Type Distribution Transformers Distribution Panelboards - Circuit Breaker Type Feeder and Branch Circuits and Emergency Wiring Branch Circuit Panelboards - Circuit Breaker Type Lighting Lightning Protection System Transient Voltage/Surge Protection Wiring for Equipment Furnished by Others Fire Alarm System Telephone Conduit Systems Lighting Control Equipment 03/24/92 00001 - 9 TABLE OF CONTENTS (ADD. 8) SECTION 00993 SCHEDULE OF DRAWINGS NUMBER 0.00 0.01 0.02A 0.03 0.04 0.05 1. OOA 1.00B 1. OOC 1.01A 1. 02A 1. 03A 1.04A 1.05A 1. 06 1.06A 1. 07 A 1. 08A 1.09A DRAWING TITLE DRAWING LATEST REVISION DATE Rev 11/11/91 1 Rev 11/11/91 2 Rev 01/09/92 2 Rev 01/09/92 2 Rev 01/09/92 1 Rev 11/11/91 1 Rev 11/11/91 1 Rev 11/11/91 Cover Index of Drawings Symbols and Abbreviations (Architectural) Life Safety Plan Ground Floor Life Safety Plan First Floor Life Safety Plan 2nd Floor Existing Conditions North Existing Conditions Central Existing Conditions South Not Used Not Used Final site Layout Central 2 Rev .9?I9?/92 4 ..~eV .P~19~1~2 Final site Layout and Grading South Be 3 10/15/91 1 RevpAjc)3 /92 1 Rev 11/11/91 4 Rev 02/18/92 Final Grading North Rough Grading and Drainage Final Grading and Drainage Central 1 Rev 02/07/92 2 Re.v04/03j92 Not Used Final site Utilities Central 2 Rev 92/07/92 3 Rev04/03j92 Not Used 1.10 Entrance Enlarge~ent 1 Rev 02/07/92 BG3 10/15/91 1.11 Landscape Plan North 1.12 Landscape Plan Central 1 Rev 02/07/92 05/02/92 BG-3 SCHEDULE OF DRAHINGS (ADD. 11) " 00993 - 1 1.13 Landscape Plan South 1.14 Irrigation Plan North 1.15 Irrigation Plan Central 1.16 Irrigation Plan South 1.17 Pump station Grinder Details 1.18 Not Used 1.19 Not Used 1. 20 site Details Fencing and Paving 1. 21 Landscape Irrigation Details 1. 22 civil Details 3.01 Not Used 3.02 Foundation Plan, Ground Floor Zone B 3.03 Not Used 3.04 Not Used 3.05 Not Used 3.06 Not Used 3.07 Framing Plan First Floor Zone A 3.08 Framing Plan First Floor Zone B 3.09 Framing Plan First Floor Zone C 3.10 Framing Plan First Floor Zone 0 3.11 Framing Plan First Floor Zone E 3.12 Framing Plan First Floor Zone F Alternate 3.13 Framing Plan Second Floor Zone A 3.14 Framing plan Second Floor Zone B 3.15 Framing Plan Second Floor Zone C BG3 10/15/91 BG3 10/15/91 1 Rev 02/07/92 BG3 10/15/91 1 Rev 11/11/91 2 ncv 02/07~ 3 Rev 91i?8/9 2 BG3 10/15/91 BG3 10/15/91 1 Rev 02/18/92 3 Rev 02/07/92 4 Rev 02/07/92 4 Rev 02/07/92 6 Rev 02/07/92 6 Rev 02/07/92 BG3 11/11/91 5 Rev 02/07/92 4 Rev 02/07/92 4 Rev 02/07/92 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 2 3.16 Framing Plan Mezzanine Level Zone D 5 Rev 02/07/92 3.17 Framing Plan Mezzanine Level Zone E 5 Rev 02/07/92 3.18 Framing Plan Mezzanine Floor Zone F BG3 11/11/91 Alternate 3.19 Framing Plan Mechanical Plenum Zone D BG3 11/11/91 3.20 Framing Plan Mechanical Plenum Zone E BG3 11/11/91 3.21 Framing Plan Mechanical Plenum Zone F BG3 11/11/91 Alternate 3.22 Framing Plan Roof Level Zone A 4 Rev 02/07/92 3.23 Framing Plan Roof Level Zone B 3 Rev 02/07/92 3.24 Framing Plan Roof Level Zone C 3 Rev 02/07/92 3.25 Framing Plan Roof Level Zone D 5 Rev 02/07/92 3.26 Framing Plan Roof Level Zone E 5 Rev 02/07/92 3.27 Framing Plan Roof Level Zone F Alternate BG3 11/11/91 3.28 Not Used 3.29 Not Used 3.30 Not Used 3.31 Foundations, sections and Details 4 Rev 02/18/92 3.32 Typical Details 4 Rev 02/07/92 3.33 Sections & Details 4 Rev 02/07/92 3.34 sections & Details 3 Rev 02/07/92 3.35 Precast Wall Schedule & Details 4 Rev 02/07/92 3.36 Precast Column Schedule & Details 4 Rev 02/07/92 3.37 General Notes & Abbreviations & Typical 4 Rev 02/07/92 Details 3.38 sections & Details 3 Rev 02/07/92 3.39 sections & Details 5 Rev 02/07/92 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 3 4.01 Exterior Building Plan Ground Floor Zone A 1 Rev 02/07/92 4.01A Building Plan Ground Floor Zone A 1 Rev 02/07'Q2 4.02 Exterior Building Plan Ground Floor Zone B BG3 11/11/91 4.02A Building Plan Ground Floor Zone B BG3 10/15/91 4.03 Exterior Building Plan Ground Floor Zone C BG3 11/11/91 4.03A Building Plan Ground Floor Zone C BG3 10/15/91 4.04 Exterior Building Plan Ground Floor Zone D BG3 11/11/91 4.04A Building Plan Ground Floor Zone D Housing BG3 10/15/91 4.05 Exterior Building Plan Ground Floor Zone E BG3 11/11/91 Housing 4.05A Building Plan Ground Floor Zone E Housing BG3 10/15/91 4.06 Exterior Building Plan Ground Floor Zone F BG3 11/11/91 Housing Alternate 4.06A Building Plan Ground Floor Zone F Housing BG3 10/15/91 Alternate 4.07 Exterior Building Plan First Floor Zone A 1 Rev 02/07'Q2 4.08 Exterior Building Plan First Floor Zone B BG3 11/11/91 4.09 Exterior Building Plan First Floor Zone C 4 Rev 02/07/92 4.10 Exterior Building Plan First Floor Zone D BG3 11/11/91 Housing 4.11 Exterior Building Plan First Floor Zone E BG3 11/11/91 Housing 4.12 Exterior Building Plan First Floor Zone F BG3 11/11/91 Housing Alternate 4.13 Exterior Building Plan Second Floor Zone A 4 Rev 02/07/92 4.14 Exterior Building Plan Second Floor Zone B BG3 11/11/91 4.15 Exterior Building Plan Second Floor Zone C 3 Rev 02/07/92 4.16 Exterior Building Plan Mezzanine Level 4 Rev 04/03/92 Zone D Housing 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 4 4.17 Exterior Building Plan Mezzanine Level BG3 11/11/91 Zone E Housing 4.18 Exterior Building Plan Mezzanine Level BG3 11/11/91 Zone F Housing Alternate 4.19 Mechanical Plenum Plan Zone 0 BG3 11/11/91 4.20 Mechanical Plenun Plan Zone E BG3 11/11/91 4.21 Mechanical Plenur:\ Plan Zone F Alternate BG3 11/11/91 4.22 Building Plan Roof Level Zone A 4 Rev 02/07/92 4.23 Building Plan Roof Level Zone B 3 Rev 02/07/92 4.24 Building Plan Roof Level Zone C 4 Rev 02/07/92 4.25 Building Plan Roof Level Zone 0 4 Rev 02/07/92 4.26 Building Plan Roof Level Zone E 4 Rev 02/07/92 4.27 Building Plan Roof Level Zone F Alternate BG3 11/11/91 4.28 Exterior Elevations 2 Rev 02/07/92 4.29 Exterior Elevations 1 Rev 02/07/92 4.30 Exterior Elevations 3 Rev 02/07/92 4.31 Exterior Elevations 3 Rev 02/07/92 4.32 Exterior Elevations BG3 11/11/91 4.33 Exterior Elevations BG3 11/11/91 4.33A Exterior Elevations 2 Rev 02/07/92 4.34 Wall sections 4 Rev 02/07/92 4.35 Wall sections 3 Rev 02/07/92 4.36 \\' a 11 sections 2 Rev 02/07/92 4.37 Wall Sections 5 Rev 02/07/92 4.38 Exterior Details 4 Rev 02/07/92 4.39 Exterior Details 4 Rev 02/07/92 4.40 Exterior Details 5 Rev 02/07/92 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 5 ~. 41 4.41A 4.41B 4.42 Exterior Details Exterior Details Exterior Details Metal Door & window Frame Elevations & Details, Door Schedule 4.43 Not Used 4.44 Not Used 4.45 Not Used 4.46 4.47 4.47A 4.48 4.49 4.50 4.51 stair plans & sections stair plans & sections stair plans & sections stair Details Elevator plans & sections Elevator Details Enlarged Cell - Plans & Elevations 4.52 Not used 4.53 4.54 4.55 4.56 4.57 4.58 4.59 4.60 4.61 Interior Building Plan First Floor Zone A Interior Building Plan First Floor Zone B Interior Building Plan First Floor Zone C Interior Bui lding Plan First Floor Zone D Housing Interior Building Plan First Floor Zone E Housing Interior Building Plan First Floor Zone F Housing Alternate Interior Building plan Second Floor Zone A Interior Building Plan Second Floor Zone B Interior Building plan Second Floor Zone C BG3 11/11/91 BG3 11/11/9" 3 Rev 02/07/92 3 Rev 12/20/91 BG3 11/11/91 3 Rev 02/07/92 BG3 11/11/91 BG3 11/11/91 2 Rev 02/07/92 2 Rev 02/07/92 BG3 11/11/0' 3 Rev 02/07/92 2 Rev 01/09/92 1 Rev 11/11/91 2 Rev 01/09/92 2 Rev 01/09/92 1 Rev 01/09/92 2 Rev 02/07/92 1 Rev 11/11/91 1 Rev 11/11/91 00993 - 6 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 4.62 4.63 4.64 4.65 4.66 4.67 4.67A 4.68 4.69 4.70 4.71 4.72 4.73 4.74 4.75 4.76 4.77 4.78 4.79 4.79A 4.80 6.01 6.02 Interior Building Plan Mezzanine Level 0 Housing Interior Building Plan Mezzanine Level Zone E Housing Interior Building Plan Mezzanine Level Zone F Housing Alternate Building sections Building sections Not Used Partition Types Interior Details Interior Details Interior Details Interior Details Interior Details Door Schedule Door Schedule Door Schedule H.M. Elevations Door and Window Details and Buck Types Finish Schedule Finish Schedule Finish Schedule Miscellaneous Details Reflected Ceiling Plan Ground Floor Zone A Not Used 1 Rev 02/07/92 2 Rev 02/07/92 BG3 10/15/91 BG3 10/15/91 2 Rev 01/02/92 2 Rev 02/07/92 2 Rev 02/07/92 1 Rev 02/07/92 2 Rev 02/07/92 1 Rev 02/07/92 2 Rev 02/07/92 3 Rev 01/09/92 4 Rev 01/09/92 2 Rev 01/09/92 1 Rev 01/09/92 BG3 10/15/91 4 ~e~'-{}4/ 03 / 92 5 Rev'04/28/92 4 Rev 0/,/03/92 5 Rev 04/28/92 -2--R€' . 12/20/91 y 5 Rev 04/28/92 BG3 10/15/91 1 Rev 02/07/92 05/02/92 00993 - 7 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 6.03 6.04 6.05 6.06 6.07 6.08 6.09 6.10 6.11 6.12 6.13 6.14 6.15 6.16 6.17 6.18 6.19 6.20 7.00 7.01 7.02 7.03 Reflected Ceiling Plan Ground Floor Zone C BG3 10/15/91 Not Used Not Used Not Used Reflected Ceiling Plan First Floor Zone A 1 Rev 02/07/92 Reflected Ceiling Plan First Floor Zone B BG3 10/15/91 Reflected Ceiling Plan First Floor Zone C BG3 10/15/91 Reflected Ceiling Plan First Floor D Housing BG3 10/15/91 Reflected Ceiling Plan First Floor Zone E Housing Reflected Ceiling plan First Floor Zone F Housing Alternate Reflected Ceiling Plan Second Floor Zone A Reflected Ceiling Plan Second Floor Zone B Reflected Ceiling Plan Second Floor Zone C Reflected Ceiling Plan Mezzanine Level Zone 0 Housing Reflected Ceiling Plan Mezzanine Level Zone E Housing Reflected Ceiling Plan Mezzanine Level Zone F Housing Alternate Ceiling Details Ceiling Details standard Mounting Heights Not used Not used Equipment Plan Ground Floor Zone C 7.04 Not Used BG3 10/15/91 BG3 10/15/91 1 Rev 02/07/92 1 Rev 12/20/91 BG3 10/15/91 1 Rev 02/07, 1 Rev 02/07/92 BG3 10/15/91 2 Rev 02/07/92 2 Rev 04/03/92 1 Rev 11/11/91 BG3 10/15/91 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 8 7.05 Not Used 7.06 Not Used 7.07 Equipment Plan First Floor Zone A 7.08 Equipment Plan First Floor Zone B 7.09 Equipment Plan First Floor Zone C 7.10 Equipment Plan First Floor Zone 0 Housing 7.11 Equipment Plan First Floor Zone E Housing 7.12 Equipment Plan First Floor Zone F Housing Alternate 7.13 Equipment Plan Second Floor Zone A 7.14 Equipment Plan Second Floor Zone B 7.15 Equipment Plan Second Floor Zone C 7.16 Equipment Plan Mezzanine Level Zone 0 Housing 7.17 Equipment Plan Mezzanine Level Zone E Housing 7.18 Equipment Plan Mezzanine Level Zone F Housing Alternate 7.19 Enlarged Toilet/Shower Equipment Plan 7.20 Enlarged Plans 7.21 Millwork Elevations 7.22 Millwork Elevations 7.23 Millwork Elevations 7.24 Millwork Elevations 7.25 Millwork Details 7.26 Millwork Details FS-1 Food Service Equipment Schedule FS-2 Food Service Equipment Plan 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 1 Rev 11/11/91 BG3 10/15/91 BG3 10/15/91 1 Rev 11/11/91 1 Rev 11/11/91 1 Rev 11/11/91 1 Rev 04/03/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 2 Rev 02/07/92 1 Rev 02/07/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 2 Rev 01/02/92 BG3 10/15/91 BG3 10/15/91 00993 - 9 FS-3 Food Service Mechanical plan FS-4 Food Service Electrical Plan FS-5 Food Service Plunbing Plan FS-6 Food Service Equipment Details FS-7 Food Service Equipment Details L-l Laundry Equipment Plan and Schedule L-2 Laundry Mechanical Plan L-3 Laundry Electrical Plan L-4 Laundry Plumbing plan Vol.II 0.00 Cover 0.01 Index of Drawings 8.00 Plumbing Legend 8.00A Plumbing Schedules 8.01 Plumbing Ground Floor Zone A 8.02 Plumbing Ground Floor Zone B 8.03 Plumbing Ground Floor Zone C 8.04 Plumbing Ground Floor Zone 0 Housing 8.05 Plumbing Ground Floor Zone E Housing 8.06 Plumbing Ground Floor Zone F Housing Alternate 8.07 Plumbing First Floor Zone A 8.08 Plumbing First Floor Zone B 8.09 Plumbing First Floor Zone C 8.10 Plumbing First Floor Zone D Housing 8.11 Plumbing First Floor Zone E Housing BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 Rev 11/11/91 BG3 10/15/91 1 Rev 12/20/91 3 Rev 02/07, 2. BG3 10/15/91 3 Rev 01/02/92 2 Rev 01/09/92 BG3 10/15/91 1 Rev 11/11/91 2 Rev 02/07/92 BG3 10/15/91 1 Rev 01/02/92 2 Rev 01/09/92 1 Rev 12/20/91 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 10 8.12 Plumbing First Floor Zone F Housing Alternate 8.13 Plumbing Second Floor Zone A 8.14 Plumbing Second Floor Zone B 8.15 Plumbing Second Floor Zone C 8.16 Plumbing Mezzanine Level Zone D Housing 8.17 Plumbing Mezzanine Level Zone E Housing 8.18 Plumbing Mezzanine Level Zone F Housing Alternate 8.19 Plumbing Plenum Plan Zone D Housing 8.20 Plumbing Plenum Plan Zone E Housing 8.21 Plumbing Plenum Plan Zone F Housing Alternate 8.22 Plumbing Schedules and Details 8.23 Plumbing Riser Diagram 8.24 Plumbing Riser Diagram 8.25 Plumbing Riser Diagram 8.26 Plumbing Riser Diagram 8.27 Plumbing Riser Diagram 8.28 Plumbing Riser Diagram 8.29 Plumbing Riser Diagram 8.30 Plumbing Riser Diagram 8.31 Plumbing Riser Diagram 8.32 Plumbing Riser Diagram 8.33 Plumbing Riser Diagram 8.34 Plumbing Riser Diagram 8.35 Plumbing Kitchen Plan 1 Rev 11/11/91 1 Rev 01/09/92 BG3 10/15/91 2 Rev 12/20/91 1 Rev 12/20/91 BG3 10/15/91 BG3 10/15/91 1 Rev 01/09/92 BG3 10/15/91 BG3 10/15/91 1 Rev 01/02/92 2 Rev 02/07/92 1 Rev 01/09/92 1 Rev 01/09/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 1 Rev 11/11/91 BG3 10/15/91 BG3 10/15/91 1 Rev 01/02/92 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 11 8.36 9.01 9.02 9.03 9.04 9.05 9.06 9.07 9.08 9.09 9.10 9.11 9.12 9.13 9.14 9.15 9.16 9.17 9.18 9.19 9.20 9.21 9.22 10.01 Waste Handling system Details Not Used Not Used Not Used Not Used Not used Not Used piping plan First Floor Zone A piping plan First Floor Zone B piping plan First Floor Zone C piping plan First Floor Zone D Housing piping Plan First Floor Zone E Housing piping Plan First Floor Zone F Housing Alternate piping plan Second Floor Zone A piping plan Second Floor Zone B piping plan Second Floor Zone C piping plan Mezzanine Level Zone D Housing piping Plan Mezzanine Level Zone E Housing piping Plan Mezzanine Level Zone F Housing Alternate Not used Not used Fuel oil Details piping Diagrams Not used 10.02 HVAC plan Ground Floor Zone B 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 1 Rev 01/02/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/9~ BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 00993 - 1; 10.03 HVAC Plan Ground Floor Zone C BG3 10/15/91 10.04 HVAC Plan Ground Floor Zone D Housing BG3 10/15/91 10.05 HVAC Plan Ground Floor Zone E Housing BG3 10/15/91 10.06 HVAC Plan Ground Floor Zone F Housing BG3 10/15/91 Alternate 10.07 HVAC Plan First Floor Zone A 1 Rev 02/07/92 10.08 HVAC Plan First Floor Zone B BG3 10/15/91 10.09 HVAC Plan First Floor Zone C BG3 10/15/91 10.10 HVAC Plan First Floor Zone D Housing 1 Rev 01/09/92 10.11 HVAC Plan First Floor Zone E Housing 1 Rev 01/09/92 10.12 HVAC Plan First Floor Zone F Housing 1 Rev 01/09/92 Alternate 10.13 HVAC Plan Second Floor Zone A 1 Rev 02/07/92 10.14 HVAC Plan Second Floor Zone B 1 Rev 12/20/91 10.15 HVAC Plan Second Floor Zone C 1 Rev 01/09/92 10.16 HVAC Plan Mezzanine Level Zone D Housing BG3 10/15/91 10.17 HVAC Plan Mezzanine Level Zone E Housing BG3 10/15/91 10.18 HVAC Plan Mezzanine Level Zone F Housing BG3 10/15/91 Alternate 10.19 HVAC Plenum Plan Zone D Housing BG3 10/15/91 10.20 HVAC Plenum Plan Zone E Housing BG3 10/15/91 10.21 HVAC Plenum Plan Zone F Housing Alternate BG3 10/15/91 10.22 Not Used 10.23 Not Used 10.24 HVAC Plan Roof Level Zone C 1 Rev 01/09/92 10.25 Not Used 10.26 Not Used 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 13 10.27 Not Used 10.28 Enlarged Mechanical Room Plan 10.29 HVAC Details 10.30 HVAC Details 10.31 HVAC Details 10.32 HVAC Schedules 10.33 HVAC Schedules 10.34 HVAC Schedules 10.35 Central Plant Control Diagrams 10.36 HVAC Temperature Control 10.37 HVAC Smoke control 11.00 Electrical Symbols and Notes 11.00A Electrical site Lighting Plan 11.01 power and Lighting Plan Ground Floor Zone A 11.02 power and Lighting Plan Ground Floor Zone B 11.03 power and Lighting Plan Ground Floor Zone C 11.04 Power and Lighting Plan Ground Floor Zone D Housing 11.05 power and Lighting Plan Ground Floor Zone E Housing 11.06 Power and Lighting Plan Ground Floor Zone F Housing Alternate 11.07 power Plan First Floor Zone A 11.08 Lighting Plan First Floor Zone A 11.09 Power Plan First Floor Zone B 11.10 Lighting Plan First Floor Zone B 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 . 1 Rev 11/11/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 1 Rev 02/07/92 BG3 10/15/91 1 Rev 01/02/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 2 Rev 03/04/92 BG3 10/15/91 2 Rev 03/04/92 BG3 10/15/91 00993 - 14 11.11 11.12 11.13 11.14 11. 15 11. 16 11. 17 11.18 11.19 11.20 11.21 11.22 11.23 11.24 11. 25 11. 26 11.27 11.28 11.29 11.30 power Plan First Floor Zone C Lighting Plan First Floor Zone C Power Plan First Floor Zone D Housing Lighting Plan First Floor Zone D Housing power Plan First Floor Zone E Housing Lighting Plan First Floor Zone E Housing Power Plan First Floor Zone F Housing Alternate Lighting plan First Floor Zone F Housing Alternate Power Plan Second Floor Zone A Lighting Plan Second Floor Zone A power Plan Second Floor Zone B Lighting Plan Second Floor Zone B Power Plan Second Floor Zone C Lighting Plan Second Floor Zone C Power Plan Mezzanine Level Zone D Housing 2 Rev 03/04/92 BG3 10/15/91 3 Rev 03/04/92 BG3 10/15/91 3 Rev 03/04/92 BG3 10/15/91 2 Rev 01/02/92 BG 3 10 / 15/91 1 Rev 03/04/92 BG 3 10/ 15/91 2 Rev 03/04/92 1 Rev 12/20/91 1 Rev 03/04/92 BG3 10/15/91 2 Rev 03/04/92 Power Plan Mezzanine Level Zone E Housing Lighting Plan Mezzanine Level Zone D Housing BG3 10/15/91 2 Rev 03/04/92 Lighting Plan Mezzanine Level Zone E Housing BG3 10/15/91 Power Plan Mezzanine Level Zone F Housing Alternate 1 Rev 12/20/91 Lighting Plan Mezzanine Level Zone F Housing BG3 10/15/91 Alternate 11.31 Power and Lighting Plan Plenum Plan Zone D BG3 10/15/91 Housing 11.32 Power and Lighting Plan Plenum Plan Zone E BG3 10/15/91 Housing 11.33 Power and Lighting Plan Plenum Plan Zone F BG3 10/15/91 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 15 11.34 11.35 11.36 11.37 11. 38 11.39 11.40 11. 41 11.42 11.43 11.44 11. 45 11. 46 11.47 11.48 11. 49 11.50 11.51 11.52 Housing Alternate Power plan Roof Level Zone A Power Plan Roof Level Zone B Power Plan Roof Level Zone C Power Plan Roof Level Zone D Power Plan Roof Level Zone E Power Plan Roof Level Zone F Alternate Electrical Enlarged Kitchen Plan Electrical Enlarged Laundry Plan Lightning Protection Plan Lightning Protection Plan Details Electrical Riser Diagram Part 1 Electrical Riser Diagram Part 2 Electrical Schedules and Details Electrical Schedules and Details Electrical Schedules and Details Electrical Schedules and Details Electrical Schedules and Details Electrical Schedules and Details Not Used 12.01 Communications Plan Ground Floor Zone A 12.02 communications Plan Ground Floor Zone B 12.03 communications Plan Ground Floor Zone C 12.04 communications Plan Ground Floor Zone D Housing 12.05 communications Plan Ground Floor Zone E Housing 05/02/92 BG-3 SCHEDGLE OF DRAWINGS (ADD. 11) BG 3 1 0/ 15 r BG3 10/15/91 1 Rev 01/09/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 2 Rev 01/02/92 1 Rev 11/11/91 BG3 10/15/91 5 Rev 03/0.,92 1 Rev 11/11/91 2 Rev 01/09/92 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 BG3 10/15/91 1 Rev 03/04/92 BG3 10/15/91 BG3 10/15/91 00993 - 1\ 12.06 12.07 12.08 12.09 12.10 12.11 12.12 12.13 12.14 12.15 12.16 12.17 12.18 12.19 12.20 12.21 12.22 12.23 12.24 12.25 12.26 12.27 Communications Plan Ground Floor Zone F Housing Alternate Communications Plan First Floor Zone A communications Plan First Floor Zone B communications Plan First Floor Zone C Communications Plan First Floor Zone D Housing Communications Plan First Floor Zone E Housing Communications Plan First Floor Zone F Housing Alternate Communications Plan Second Floor Zone A Communications Plan Second Floor Zone B Communications Plan Second Floor Zone C communications Plan Mezzanine Level Zone D Housing Communications Plan Mezzanine Level Zone E Housing Communications Plan Mezzanine Level Zone F Housing Alternate Fire Alarm Riser Diagram Telephone Riser Diagram and Elevator Fire Alarm System Not Used Not Used Not Used Security Plan Ground Floor Zone A Security Plan Ground Floor Zone B security Plan Ground Floor Zone C Security plan Ground Floor Zone D Housing BG3 10/15/91 1 Rev 03/04/92 1 Rev 03/04/92 1 Rev 03/04/92 1 Rev 03/04/92 1 Rev 03/04/92 BG3 10/15/91 1 Rev 03/04/92 1 Rev 03/04/92 1 Rev 03/04/92 1 Rev 03/04/92 1 Rev 03/04/92 BG3 10/15/91 BG3 10/15/91 1 Rev 12/20/91 1 Rev 12/20/91 1 Rev 12/20/91 1 Rev 12/20/91 1 Rev 12/20/91 05/02/92 00993 - 17 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 12.28 Security Plan Ground Floor Zone E Housing 1 Rev 12/20/91 12.29 Security Plan Ground Floor Zone F Housing 1 Rev 12/20'~1 Alternate 12.30 Security Plan First Floor Zone A 3 Rev 03/04/92 12.31 Security Plan First Floor Zone B 3 Rev 03/04/92 12.32 Security Plan First Floor Zone C 2 Rev 03/04/92 12.33 security Plan First Floor Zone D Housing 3 Rev 03/04/92 12.34 security plan First Floor Zone E Housing 3 Rev 03/04/92 12.35 Security Plan First Floor Zone F Housing BG3 10/15/91 Alternate 12.36 Security Plan Second Floor Zone A 5 Rev 03/04/92 12.37 Security plan Second Floor Zone B 1 Rev 12/20/91 12.38 security Plan Second Floor Zone C 3 Rev 03/04/92 12.39 Security Plan Mezzanine Level Zone D 3 Rev 03/04/92 Housing 12.40 Security Plan Mezzanine Level Zone E 3 Rev 03/0~ 'Q2 Housing 12.41 Security Plan Mezzanin Level Zone F 1 Rev 12/20/91 Housing Alternate 12.42 Security systems Riser Diagram 2 Rev 02/07/92 12.43 Details 1 Rev 02/07/92 12.44 Details 1 Rev 12/20/91 13.01 Fire Protection Ground Floor Zone A BG3 10/15/91 13.02 Fire Protection Ground Floor Zone B BG3 10/15/91 13.03 Fire Protection Ground Floor Zone C BG3 10/15/91 13.04 Fire Protection Ground Floor Zone D Housing BG3 10/15/91 13.05 Fire Protection Ground Floor Zone E Housing BG3 10/15/91 13.06 Fire Protection Ground Floor Zone F Housing BG3 10/15/91 Alternate 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 18 13.07 Fire Protection First Floor Zone A BG3 10/15/91 13.08 Fire Protection First Floor Zone B BG3 10/15/91 13.09 Fire Protection First Floor Zone C BG3 10/15/91 13.10 Fire Protection First Floor Zone D Housing BG3 10/15/91 13.11 Fire Protection First Floor Zone E Housing BG3 10/15/91 13.12 Fire Protection First Floor Zone F Housing BG3 10/15/91 Alternate 13.13 Fire Protection Second Floor Zone A BG3 10/15/91 13.14 Fire Protection Second Floor Zone B BG3 10/15/91 13.15 Fire Protection Second Floor Zone C BG3 10/15/91 13.16 Fire Protection Mezz. Level Zone D Housing BG3 10/15/91 13.17 Fire Protection Mezz. Level Zone E Housing BG3 10/15/91 13.18 Fire Protection Mezz. Level Zone F Housing BG3 10/15/91 Alternate 13.19 Not Used 13.20 Not Used 13.21 Not Used 13.22 Not Used 13.23 Not Used 13.24 Not Used 13.25 Not Used 13.26 Not Used 13.27 Not Used 13.28 Fire Protection Details BG3 10/15/91 13.29 Fire Protection Details BG3 10/15/91 05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 19 SECTION OO;)~S SCOPE OF woaK Bid Package No. 35 Carpentry , General Works 1.1 General Scope Provide all labor, supervision, engineering, materials, supplies, equipment, tools, transportation, surveying and layout, and protection, to install complete operating systems, and proper execution and completion of all Work specified on the drawings, in the bid package, and the sections of the specifications, which include, but are not limited to the listing that follows. The bidder shall review all drawings, and specification sections that are not specifically listed, for any additional requirements in order to complete the scope of work described herein. specifications sections and Descriptions \ 05810 06100 06200 08300 10100 10160 10350 10500 10520 10550 10800 10900 11480 13090 Expansion Joint Cover Assemblies Rough Carpentry Finish Carpentry Special Doors Chalkboards and Tackboards Solid Plastic Toilet Partitions Flagpole Steel Lockers Fire Extinguisher Cabinets postal Specialties Toilet Accessories Miscellaneous Specialties Athletic Equipment Radiatioft rrotectioft 1.2 special provisions The following special provisions are intended to clarify the scope of work, or highlight features of the work, or modify, change, add to, or delete from the General Scope of this Bid Package. .1 All licenses required in order to perform the scope of work in the specified location, shall be procured and maintained by the contractor and his subcontractors. Contractor shall submit copies to the Construction Manager. Contractor shall be responsible for applying for, and procuring the construction permit as required by 04/30/92 CARPENTRY SCOPE OF WORK (ADD. 11) 00335 - 1 the City of Kay West; however, the Owner shall literally pay the fee for the permit. .2 Contractor shall maintain As-Built drawings~ (Record Drawings per section 01720), of his work progression. A 50% progress of field work submittal, will be required. .3 Provide, replace, and maintain any safety rails and barricades as necessary during the process of work, or during deliveries of materials or equipment. .4 Contractor is to review Division 1 General Requirements for additional responsibilities required in order to perform the work under this Bid Package. Contractor shall pay particular attention to section 01710 Final Cleaning, which shall be performed as scheduled by the CM, which will be at or near the completion of the project. utility Routing and Coordination of the Work ( ( .5 This contractor shall be responsible to coordinate his work with other multiple prime contractors both in the scheduling of field work activities and in the integration of individually furnished items into final composite installations. Coordination drawings procedures shall consist of, but are not limited to, Base Trade Installers Drawings. .6 All unfinished surfaces of materials or equipment furnished or installed by this contractor, shall be inspected for readiness by follow-on contractors and the eM, prior to installation of follow-on work. This would include bringing back to original condition, surfaces disturbed by welding, burning, or other disfigurement, which will need to be made ready for finish painting, or other work. The Masonry Contractor shall pay particular attention to protect and clean flooring surfaces in compliance with floor covering installation. Materials and Equipment Furnished bv Others All materials furnished by the Owner, other contractors for the Owner, or by the CM for the Owner, for installation by this contractor shall upon delivery, be unloaded, transferred, stored and fully protected by the contractor until installed. Any demurrage or similar charge incurred due to failure of the contractor to promptly unload the materials and equipment shall be the responstbility of the contractor. .7 04/30/92 00335 - 2 CARPENTRY SCOPE OF WORK (ADD. 11) The contractor shall carefully examine all materials and equipment furnished by the Owner, or any of his designees, (other contractors or the CM). The contractor shall complete receiving reports describing the quantity and condition of the materials or equipment. The contractor shall be responsible for subsequent damage or loss until installation is completed and accepted by the Owner. Should the contractor fail to report any visible signs of damage in the receiving report as indicated above, then all parties may assume that the damage occurred while the materials and equipment were in the care, custody and control of the receiving contractor. Any material furnished by the Owner, at an off-site location, on other than a charge basis in connection with the contract, shall be deemed as held by the contractor on consignment. All such materials not used in the fabrication of materials or equipment required under the contract shall be returned to the applicable party, as directed, at their expense; and, if not accounted for or so returned, shall be paid for by the contractor. .8 All incoming materials and equipment shall be coordinated with other trades and the CM is to be notified, in order that proper lavdown. staging and stockina areas are developed, prior to release for shipping. within the building, areas shall be restricted and stocking areas will be authorized in writing. .9 If in the event of conflicting, or overlapping requirements in any area of the bidding documents, technical specifications, or drawings, the most stringent condition shall be bid and constructed. Notify the CM in any event, in order to not compromise the Owner's right to make appropriate decisions. .10 This contractor is reminded of inmate contact areas and perimeters, and of the requirement for security devices, fasteners, connectors, and any other work associated with this bid package scope of work, in order that proper care and construction is performed in accordance with the standards and guidelines set forth by the regulatory agencies governing jails. .11 Furnish and install all plywood backing panels for telephones and telephone boards, in accordance with section 06100 Rouqh Carpentry. Furnish and install wood blocking, furring, grounds, 04/30/92 CARPENTRY SCOPE OF WORK (ADD. 11) 00335 - 3 curbs, nailers and ~tber rough wood items, for the work of this bid package, and all other trades. Roof carpentry is by others, as is cast- in-place concrete formwork. Furnish and install all concealed wood blocking at drywall partitions to fully support cabinetwork prior to the installation of drywall. Provide shop drawings detailing wood blocking required for installation of cabinetwork. .12 Furnish and install Flagpole, in accordance with section 10350, including foundation. .13 Furnish and install Fire Extinguisher Cabinets and Fire Extinguisher Wall Brackets, in accordance with section 10520. Fire Hose Cabinets are by others. .14 Furnioh and inotall Lcad Lined Film CasDcttc Cabincto and Desi9natin~ Plaque, in accordance '",rith section 130'0 Radiation Protcction. ( All other radiation protection matcrialo arc furniahed and inotalled by others. Testing is by others. .15 Furnish and install all expansion joints, that are for precast concrete or masonry. For example, but not limited to, see detail 4/4.41a. Follow section 05810. .16 Contractor shall provide an allowance, and as a part of his base bid, the equivalent of (240) manhours, which shall include mobilization, labor, equipment, materials, taxes, incidentals, overhead and profit, for the purpose of performing work similar to that in this bid package. .17 Furnish and install with section 06200. Contractor who will control rooms. all Finish Carpentry in accordance Coordinate with security Systems provide information for layout of .18 Owner option No. 35-01: Zone 'F' CarpentrY At the option of the Owner, furnish and install Zone 'F' Carpentry, similar to Zones 'D' and 'E'. This area is defined as the area bound by column lines G to La, and 17 line to 24 line, as well as column lines 37 to X, and U line to 42 line. ( 04/30/92 CARPENTRY SCOPE OF WORK (ADD. 11) 00335 - 4 .19 Final Cleaning This contractor shall be responsible for final cleaning program, which will be conducted beginning at completion of prefinal inspection, and continuing through final punchlist execution. All surfaces shall be cleaned with appropriate cleansers as directed by the Owner's representative. Vacuum all dust accumulations and clean all accessible areas. Review. other trade contractors scopes of work for specific exclusions. This Contractor shall be responsible for all other general cleaning, in order to make ready for final inspection, and satisfaction of final inspection. ~~()':~~~~P~!1:9:::'S?!\P?~~?:':':'~:~!!"fi:~~.:!ti:::.:.:~.!:~~+"t:~~~~!'#.g Ifiz._.iiAll1IiilII16Iilll 1.3 By Others ( .1 Fire Hose Cabinets in section 10520, are by Fire Protection Contractor. .2 Lc~d lincd wall systcms, X r~y view yindows/lcnd lined fr~lftes, utility shiclding, ~nd pcnetr~tion shiclding, ~rc by othcr tradc contr~ctors, ~3 rcl~teG to Scction 13090 R~di~tion rrotection. Testing is by others. .3 Roofing, and roof rough carpentry. .4 Cast-in-place concrete formwork. 04/30/92 CARPENTRY SCOPE OF WORK (ADD. 11) 00335 - 5 SBCTION 00337 SCOPB OF WORK Bid Paokage No. 37 Aooess Flooring, Resilient Flooring , carpet 1.1 General Scope Provide all labor, supervision, engineering, materials, supplies, equipment, tools, transportation, surveying and layout, and protection, to install complete operating systems, and proper execution and completion of all Work specified on the drawings, in the bid package, and the sections of the specifications, which include, but are not limited to the listing that follows. The bidder shall review all drawings, and specification sections that are not specifically listed, for any additional requirements in order to complete the scope of work described herein. sections and Descriptions of the Work 09650 09680 10270 Resilient Flooring carpet Access Flooring \ 1.2 Special provisions The following Special provisions are intended to clarify the scope of work, or highlight features of the work, or modify, change, add to, or delete from the General Scope of this Bid Package. .1 All licenses required in order to perform the scope of work in the specified location, shall be procured and maintained by the contractor and his subcontractors. Contractor shall submit copies to the Construction Manager. Contractor shall be responsible for applying for, and procuring the construction permit as required by the city of Key West; however, the Owner shall literally pay the fee for the permit. .2 Contractor shall maintain As-Built drawings. (Record Drawings per section 01720), of his work progression. A 50% progress of field work submittal, will be required. .3 Provide, replace, and maintain any safety rails and barricades as necessary during the process of work, or during deliveries of materials or equipment. \ 03/25/92 FLOORING SCOPE OF WORK (ADD. 8) 00337 - 1 .4 Contractor is to review Division 1 General Requirements for additional responsibilities required in order to perform the work under this Bid Package. Contractor shall pay particular attention to section 01710 Final Cleaning, which shall be performed as scheduled by the CM, which will be at or near the completion of the project. .5 Materials and Equipment Furnished by Others All materials furnished by the Owner, other contractors for the Owner, or by the CM for the Owner, for installation by this contractor shall upon delivery, be unloaded, transferred, stored and fully protected by the contractor until installed. Any demurrage or similar charge incurred due to failure of the contractor to promptly unload the materials and equipment shall be the responsibility of the contractor. The contractor shall carefully examine all materials and equipment furnished by the Owner, or any of his designees, (other contractors or the CM). The contractor shall complete receiving reports describing the quantity and condition of the materials or equipment. The contractor shall be responsible for subsequent damage or loss until installation is completed and accepted by the Owner. I Should the contractor fail to report any visible signs of damage in the receiving report as indicated above, then all parties may assume that the damage occurred while the materials and equipment were in the care, custody and control of the receiving contractor. Any material furnished by the Owner, at an off-site location, on other than a charge basis in connection with the contract, shall be deemed as held by the contractor on consignment. All such materials not used in the fabrication of materials or equipment required under the contract shall be returned to the applicable party, as directed, at their expense; and, if not accounted for or so returned, shall be paid for by the contractor. .6 Coordination of the Work This contractor shall be responsible to coordinate his work with other multiple prime contractors both in the scheduling of field work activities and in the integration of individually furnished items into final composite installations. 03/25/92 FLOORING SCOPE OF WORK (ADD. 8) 00337 - 2 .7 Contractor shall perform and/or coordinate all required testing and provide adequate personnel in order to facilitate all testing to the requirements of the contract documents. ( .8 All incoming materials and equipment shall be coordinated with other trades and the eM is to be notified, in order that proper laydown. stag ing and stocking areas are developed, prior to release for shipping. Within the building, areas shall be restricted and stocking areas will be authorized in writing. .9 If in the event of conflicting, or overlapping requirements in any area of the bidding documents, technical specifications, or drawings, the most stringent condition shall be bid and constructed. Notify the CM in any event, in order to not compromise the Owner's right to make appropriate decisions. .10 This contractor is reminded of inmate contact areas and perimeters, and of the requirement for security devices, fasteners, connectors, and any other work associated with this bid package scope of work, in order that proper care and construction is performed in accordance with the standards and guidelines set forth by the regulatory agencies governing jails. .11 Furnish and install Resilient Floorinq, in accordance with Section 09650, including vinyl composition tile, vinyl base, rubber tile, and adhesives and miscellaneous materials required for installation. This shall also include base around access flooring. Xllil:r_l1;tt.I~I:l!;l:::!1i@.~I:E!ll~+~.:'::~p:~:~:'''l:)P:l?1:i Upon installation of resilient flooring, place two (2) coats of wax, and then provide temporary protection. When directed by the CM, remove temporary floor protection, and strip, wax, and buff out. .12 Furnish and install Direct accordance with Section 09680, protection. Glue-Down Carpet, in including clean-up and .13 Furnish and install access flooring in accordance with Section 10270, including grounding connectors, cable cut- out protection, panel lifting devices, and aluminum grilles with dampers. Provide for all transitions to dissimilar flooring system. Provide for temporary floor protection, after installation. ( 04/03/92 FLOORING SCOPE OF WORK (ADD. 9 ) 00337 - 3 This contractor ,:;hall furnish a set of reproducible drawings, which will be routed to the Electrical Contractor, Mechanical Contractor, and security Systems Contractor, in order for utility routing, cut-outs, and pedestal location verification, to be scheduled and coordinated. Note: Grounding connectors shall be taken to (1) point, for termination. Extra stock shall be provided by contractor, consisting of (5) each panels. .14 Perform all floor preparations, to include all sanding, levelling, and defect repair, and be responsible for the cleanliness of existing concrete, which is to receive flooring. sixty (60) calendar days prior to installation, inspect existing floors which are to receive flooring finish, and follow up with a (14) day, prior to mobilization inspection. .15 Provide final cleaning of all types of flooring in this bid package, upon substantial completion, as directed by the CM. .16 Contractor shall provide the CM the results of moisture ( testinq, and other tests as suggested by manufacturer. .17 Provide for ventilation for safety and drying as necessary. .18 Owner Option No. 37-01: Zone IF' Resilient Flooring and Carpet: At the option of the Owner, furnish and install Zone 'F' Resilient Flooring and Carpet, similar to Zones '0' and , E I . This area is defined as the area bound by column lines G to La, and 17 line to 24 line, as well as column lines 37 to X, and U line to 42 line. 03/25/92 FLOORING SCOPE OF WORK (ADD. 8) 00337 - 4 SECTION 00339 SCOPE OF WORK Bid Package No. 39 Acoustical ceilings 1.1 General Scope Provide all labor, supervision, engineering, materials, supplies, equipment, tools, transportation, surveying and layout, and protection, to install complete operating systems, and proper execution and completion of all Work specified on the drawings, in the bid package, and the sections of the Specifications, which include, but are not limited to the listing that follows. The bidder shall review all drawings, and specification sections that are not specifically listed, for any additional requirements in order to complete the scope of work described herein. specifications sections and Descriptions 05810 09510 13090 Expansion Joint Cover Assemblies Acoustical Ceilings Radiation Protection l 1.2 Special provisions The following Special provisions are intended to clarify the scope of work, or highlight features of the work, or modify, change, add to, or delete from the General Scope of this Bid Package. .1 All licenses required in order to perform the scope of work in the specified location, shall be procured and maintained by the contractor and his subcontractors. Contractor shall submit copies to the Construction Manager. Contractor shall be responsible for applying for, and procuring the construction permit as required by the City of Key West; however, the Owner shall literally pay the fee for the permit. . .2 Contractor shall maintain As-Built drawinqs, (Record Drawings per section 01720), of his work progression. A 50% progress of field work submittal, will be required. .3 Provide, replace, and maintain any safety rails and barricades as necessary during the process of work, or , 03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8) 00339 - 1 during deliveries of materials or equipment. .4 Contractor is to review Division 1 General Requirements for additional responsibilities required in order to perform the work under this Bid Package. Contractor shall pay particular attention to section 01710 Final Cleaning, which shall be performed as scheduled by the CM, which will be at or near the completion of the project. .5 Access Panels and Doors - Install all access panels and doors that are required to be installed in acoustical ceilinqs. Coordinate with other trade contractors for locations. Access panels and doors will be furnished by others. The Access Panels and Doors Schedule, attached and labelled Attachment 'B', represents those access panels and doors that are not shown on the plans, but which are required by other trade contractors. The schedule shows several types, and that they are to be installed in various substrates. This schedule is to be used as a guide, in order for this contractor to bid and understand the requirements of this scope of work item. The quantities are not absolute, and contractor shall be required to make installations of all quantities that are I to be installed in acoustical ceilings. .6 Materials and Eauipment Furnished bv others All materials furnished by the Owner, other contractors for the Owner, or by the CM for the Owner, for installation by this contractor shall upon delivery, be unloaded, transferred, stored and fully protected by the contractor until installed. Any demurrage or similar charge incurred due to failure of the contractor to promptly unload the materials and equipment shall be the responsibility of the contractor. The contractor shall carefully examine all materials and equipment furnished by the Owner, or any of his designees, (other contractors or the CM). The contractor shall complete receiving reports describing the quantity and condition of the materials or equipment. The contractor shall be responsible for subsequent damage or loss until installation is completed and accepted by the Owner. Should the contractor fail to report any visible signs of damage in the receiving report as indicated above, then all parties may assume that the damage occurred while the 03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8) 00339 - 2 materials and equipment were in the care, custody and control of the receiving contractor. Any material furnished by the Owner, at an off-site location, on other than a charge basis in connection with the contract, shall be deemed as held by the contractor on consignment. All such materials not used in the fabrication of materials or equipment required under the contract shall be returned to the applicable party, as directed, at their expense; and, if not accounted for or so returned, shall be paid for by the contractor. .7 Coordination of the Work This contractor shall be responsible to coordinate his work with other multiple prime contractors both in the scheduling of field work activities and in the integration of individually furnished items into final composite installations. .8 All incoming materials and equipment shall be coordinated with other trades and the CM is to be notified, in order that proper lavdown. staqing and stockinq areas are developed, prior to release for shipping. within the building, areas shall be restricted and stocking areas will be authorized in writing. \, .9 If in the event of conflicting, or overlapping requirements in any area of the bidding documents, technical specifications, or drawings, the most strinqent condition shall be bid and constructed. Notify the eM in any event, in order to not compromise the Owner's right to make appropriate decisions. .10 This contractor is reminded of inmate contact areas and perimeters, and of the requirement for security devices, fasteners, connectors, and any other work associated with this bid package scope of work, in order that proper care and construction is performed in accordance with the standards and guidelines set forth by the regulatory agencies governing jails. .11 Furnish and install expansion ioint cover assemblies in accordance with section 05810, which are to be installed in the work of this contractor. .12 Furnish and install Acoustical Ceilings, which includes mineral fiber ceiling with revealed edge with suspension system and related items. This shall also include acoustical ceiling tile adhered to substrate. \ 03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8) 00339 - 3 .13 Provide for additional suspension wires as necessary to limit ceiling deflection to 1/360 of span. Provide background drawings as necessary to facilitate coordination of suspension wires. Coordinate with mechanical and electrical contractors, and their fixtures/devices which are to be supported by the ceiling system. .14 Provide other trades the finished ceiling elevation, and assist with other trades in the installation of their fixtures and devices. .15 Pre-measure all rooms and adjust patterns as necessary, and as approved by Owner's representative. .16 Coordinate with other trades, and with the rough-in installation of their work. .17 Coordinate and provide fixture hanqers for lay-in suspended fixtures and devices. .18 Provide all hold-down clips as required by applicable building codes. .19 Owner Option No. 39-01: Zone 'F' Acoustical Ceilings: At the option of the Owner, furnish and install Zone 'F' Acoustical Ceilings, similar to Zones 'DI and IE'. This area is defined as the area bound by column lines G to La, and 17 line to 24 line, as well as column lines 37 to X, and U line to 42 line. 1.3 By Others .1 Sprayed Insulation, paragraph 2.1 D., Sprayed Acoustical Treatment, is by others. 03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8) 00339 - 4 ATTACHMENT 'B' ACCESS PANELS AND DOORS Gypsum w/Standard Lock Size Quantity 1- 12" x 12" 25 2. 18" x 18" 0 3. 18" x 24" 1 4. 24" x 24" 0 5. 24" x 36" 2 Gypsum wI Standard Lock. Fire-Rated Panels Size Quantity 6. 12" x 12" 45 7. 18" x 18" 51 ( 8. 18" x 24" 0 9. 24" x 24" 0 10. 24" x 36" 0 Plaster wI Standard Lock Size Quantity 11. 12" x 12" 4 12. 18" x 18" 0 13. 18" x 24" 0 14. 24" x 24" 0 15. 24" x 36" 0 , 03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8) 00339 - 5 Plaster w/Standard Lock, Fire-Rated Panels size Quantity 16. 12" x 12" 4 17. 18" x 18" 16 18. 18" x 24" 0 19. 24" x 24" 0 20. 24" x 36" 0 Security Plaster w/security Lock Size Quantity 21- 12" x 12" 245 22. 18" x 18" 4 23. 18" x 24" 0 24. 24" x 24" 24 25. 24" x 36" 0 security Plaster w/Security Lock, Fire-Rated Panels size Quantity 26. 12" x 12" 66 27. 18" x 18" 0 28. 18" x 24" 0 29. 24" x 24" 0 30. 24" x 36" 0 security Masonry w/Security Lock size Quantity 31. 24" x 24" 32. 24" x 36" o o 03/11/92 ACOUSTICAL CEILING SCQPE OF WORK (ADD. 8) 00339 - 6 SBCTION 00353 MILESTONE scaEDULE The bar chart and associated activity listing presented in this section depicts the approximate du~ation, sequence, and flow of work of major work groups. Not all activities are shown and groupings are subjective. Logic diagrams generating the presented document are available for bidder review in the office of the Construction Manager. Contractors will be required to submit construction schedules to meet the requirements of the presented milestones and in accordance with the Master Project Schedule. The Contractors are to note the following special milestone dates required for the Project. a. Building Temperature and Humidity Controlled for Finishes , Follow-on Work. . . . . . . . . . . . . . . . . .11/15/92 b. Start Contractor Completion Inspections.01/11/93 c. Start Prefinal Inspections . . Project Completion . . . . . .03/02/93 . .07/01/93 d. 03/16/92 MILESTONE SCHEDULE (ADD. 8) 00353 - 1 ( IT 1iI : I . ioi I ~. I E ~ , I i J g~ j I i ~ ~ I . I i~ f- - - ii: 0 i~ - ... ~ ~ ; I ! i~ )1 j j ~ 1 >- <IJ ~ .... ...... .... UJ Ii] IOU=l "0 10 = l .... u. 0 c... UJ I J 0e::I: ...... O<...J U. .- (/) J <IJ ~=. I j . e: 0 >- QI ..... <IJ <IJ IX) e: QI II ::;,Of") 0 ~ <...J~~ I) Qle: J II o::;,a: c...o~ ~ e:<...J I j 0 0 ::It QI ..... o IX) c... ! e: 0 ::It I! J5 ~ ~~ II ~ H f0- il l ~ ~ I I ..II i ~ il t- 1 I , ila ~ ! . .111 i ~ i I I i I . j~~i j ~ I I Ii . J . I I ! e I iii i 1 l k ... ( .........................~......................................................................................................... ~ CcM\ty, Florldl ,.IMAVERA PROJECT PLAIINEI ( IT DATE 19DEC91 IMI NO. 50 Monroe CcM\ty Detention feelllty 16:28 sce IEPOltT . line skip br ectlvlty code Monroe CcM\ty Detention Fectl Ity STAlT DATI 1MJG91 FlI DATI l.IUL93- DATA DATE 18N0V91 PAGE NO. 1 ..-.. ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ..... ACTIVln ORIG IEJI ACTIVITY DESClIPTlClI SCHEDUlED II DUI DUI I STAlT FlIISH ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ..... Site Utllt~l.. 5 1 0 100 _ 0:' ITP . lite Utll Itf.. 9OCT91A 9OCT91A 1325 5 5 0 , IW . Zone C . ,,-Sl_ s.nltary . Loedl,. Dock 4MAI92 10MA192 1330 5 5 0 IW . Zone C . ItOl"ll Drain (.II 28-0 & Upat...-) 4MAI92 10MA192 1340 5 5 0 IW . Zone C , ItOl"ll Dr.ln Unlet 1.12 & Upatr.. 4MAI92 10M192 2000 30 5 a sw . Utllltl.. . ~.round SUbaltt.l. 13SEP91A 22IIOV91 2005 10 10 0 sw . Utllltl.. . AlE ~l of U'G SUbalttels 25N0V91 9DEC91 2010 15 15 0 IW . Utllftl.. . Install Outfall Itructures 1ODEC91 31DEC91 2015 5 5 0 sw . UtH Itl.. . Instl U/G TelIpOf'ary Pwr & Tala 1ODEC91 16DEC91 2020 5 5 0 sw . Utfl Itl.. . lenftary TNit LIne . L. Dock 1ODEC91 16DEC91 2OZ5 10 10 0 sw . Utllttt.. . 1_lndar of Senltery Trri Lln 11DEC91 31DEC91 2030 10 10 0 sw . Utllttl.. . Electrical Iul:tbenk end Tela 17DEC91 31DEC91 2035 15 15 0 IW . Utfl Itl.. . Instl Creywat... Une 2JAN9Z 22.1AN92 Z040 15 15 0 sw . Utfl Itf.. . Instl ~tlc Watar Line 2JAN9Z 22.1A119Z 2045 15 15 0 sw . Uti lltl.. . Instl Efflwnt LIne 2JAN9Z 22.1AN92 2050 15 15 0 sw . Utfl Itl.. . Instl Cas LIne 2JAN9Z 22.1A119Z ( 3005 10 10 0 sw . Ent.-.nce toed . Eff lwnt Une 13JAN9Z 24.1AN9Z 3010 10 10 0 IW . Entrance loed . ~tlC/N "'In 13JAN9Z 24.IAN9Z 3015 10 10 0 IW . Ent.-.nce loed . T..t/FlUIh/Dlslnfect DW/AI 27JA1192 7FEB92 3020 5 . 5 0 sw . Ent.-.nce 10IId . Tie- In DW/N LIne to FIM 10fE192 14'E192 3050 15 15 0 IW . Utfl Itl.. . 0YerMad Pwar/Tal.p,ona Line 13JAN9Z 31.1A119Z 3055 5 5 0 IW . Utfl It I.. . TllIpOI'ary "'rlTala St.rtt4>> 3'E192 7FEB92 5000 15 15 0 sw. UtHltl.. . Storti D...ln TNit Linea 17 JUII92 &lUt.92 5005 15 15 0 IW . Utllltl.. - ID L.t...l.ls & Trench Drain 17 JUN92 8JUt. 92 S010 15 15 0 IW - Utllltl.. - Sanitary L.t....l. 17 JUN92 I.IUt. 92 c:.t uana 1025 10 0 100 SW . c:.faon Load Teat 7OCT91A 17OCT91A 1030 10 0 100 SW . AlE levlew of Catuon Loed T..t Data 18OCT91A 6IIOV91A 1035 40 0 100 SW . c:.faon lebar SUbatttals - Itart 13AUG91A 6OCT91A 1040 15 0 100 SW . Cat..on lebar SUbattt.l. . C~lete 7OCT91A 290CT91A 1045 5 0 100 SW - AlE levlew of Catuon leber SUbatttal. 300CT91 A 6ilN91A 1050 10 9 10 SW . 'ebrlcate & DellVel' Calaaon leber 13N0V91A 29IIOV91 1055 25 0 100 IV . "Indloed IIocItffcatton Prich" 6OCT91A 1311OV91A 1060 1 1 0 SW . IOCC Apvl of "tndloed Ch.... 20N0V91- 2OIIOV91 1100 15 15 0 SW . Zone A . Cat ssons 2DEC91 2ODEC91 1150 15 15 0 SW . Zone D . Catuona 23DEC91 14JAN9Z 1 ZOO 10 10 0 SW . Zone . - Catssons 15JAN92 28.1AN92 1250 15 15 0 IV . Zone E . Catssons 29JA1192 18FEI92 1300 10 10 0 SW . Zone C . c:.fssons 19FE192 3MAR92 Colu.w 1105 15 15 0 IV . Zone A . Colu.w & IUse Concrete 23DEC91 14JAII92. ( 1110 5 5 0 IV . Zone A . V...lfy Locations of Colu.w 15JAN92 Z1JA1192 1115 20 20 0 IV . Zone A . Col,--, Concrete CW'e Period 15JA1192 11FEI92 11S5 15 15 0 IV . Zone D . Colu.w IIUec Concrete 15JA1192 4FE892 ................................................................................................................................... MorV'Oe Ccu\ty, Florldl PllMVERA PIOJECT PWIIEI Monroe ~ty Det.,Uon Fec:1lfty W'OIT DATI 19OEt91 IMI 110. SO ":21 SC1IED ItEPOIlT . line Iklp by IlCtlvlty code Monroe Cowlty Det.,tlon FIlCH Ity 'TART DATI 1AUG91 fll DATI .f DATA DATE 1811OV91 PAGE 10. 2 ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ..... ..... .-..- .... .... . ... ..--...... ................................................ ........ ........ ........ ........ ..... ACTIVln . OItIG REM II DUI DUI ACTIVITY DlICIIPTICII SCIIEOUlED START FIIISH I Colu.1l 1160 5 5 0 SW . Zone 0 . verify locatfen of Colu.1l 5FE192 " FEI92 "65 20 20 0 . - SW . ZoneD . Coluw. Concrete CUre Period .. 5FE192 3MAR92 1205 10 10 . SW . Zone . . COll..._ & .n se COncrete 29JM92 " FEB92 1210 5 5 0 IW . Zone . . verify Locatlen of Colu.1l 12FE19Z 1lfE192 1215 20 20 0 SW . Zone . . Coluw. Concrete CUre Period 12FE19Z 10MAl92 1255 15 15 0 SW . Zone E . Cob... & Mise Concrete 19FE192 10MAl92 1260 5 5 0 SW . Zone E . verify locatlone of Colwna 11MAl92 17MAR92 1265 20 20 0 SW . Zone E . Coh... Concrete CUre Period 11MAl92 7AP192 1305 10 10 0 SW . Zone C . CoI~ & Mise COncrete 4MAR92 17MAR92 1310 5 5 0 IU . ZonI C . Verify Locatlen of Colu.1l 18MAR92 24MR92 1315 20 20 0 SW . Zone C . Coluw. Concrete CUre Period 18MAR92 1WR92 1320 20 20 0 SW . Zone C . f/IIPIC Concrete Loedf~ Dock 4MAR92 31MAR9Z Erection Drewlngs 7020 15 15 0 Pr~t . Coluw. Interfeee Detal Is 2111OV91 12DEt91 7'030 15 15 0 Precalt . ArM A . fr_l~ Dr..,lngs 2111OV9'1 12OEC91 7040 10 10 0 Pr~t . A.... A . All Apvl of fr_l~ Drawings 1]OEC91 21DEt91 7100 15 15 0 Prec.lt . A..... . & I . fr_f~ Drawings 13DEC91 6JAN92 7110 10 10 0 Precalt - AreM . & D . All Aptl of fr_l~ .. 7,1A192 2O.1A1192 7200 15 15 0 P.....t . Areea C & I . f.....~ o......ngs 7.1A192 27 .IAII92 n10 10 10 0 Precalt . Areas C & I . All .,. of F.....,. .. 2IJA192 10FE192 UtHltf../precest Coordlrwtlon Effort 7005 10 0 100 Coordfrwtlon Method Declafan 111OV91A 1511O'/91A 7050 20 20 0 P~t . ArM A . UtllPc:lt Coordfrwtfan ''''''' 16DEt91 7120 20 20 0 Precalt . Ar... . I D . UtllPc:lt Coordfrwtfan 11DEC91 15.1A1192 7220 15 15 0 Prec.lt . AreM C & I . UtI/PCSt Coordlrwtfan 16JA192 5FE192 Detan Drawings 7'060 15 15 0 Precalt - ArM A . Detaf I 0....1. 3ODEC91 2OJA1192 7070 10 10 0 Pr~t . A.... A . All Apv. of Detan orawf. 21.1A192 3FE892 7130 15 15 0 Precalt . AreeI' & D . Deten or..,l. 21.1A192 10FEB92 7140 10 10 0 P~t - AreM . & D . AllAlHI of Detaf I .. 11 FEI92 24FE892 7Z3O 15 15 0 Precelt . A..... C & I . Detan Drewl. 11FE192 2MAR92 n40 10 10 0 PrecMt . Ar... C & E . All Aptl of Detal I Dwp 3MAR92 16MAR92 Flbrlcatfan 7OlSO 20 20 0 PrecMt . A.... A - Fabrfcatlan 4FEB92 2MAR92 7090 5 5 0 PrecMt . Ar.. A . legln Shlppl,. to Sft. 3MAR92 9MAR92 7150 20 20 0 Precalt . ArH . - Fabrication 25 FEB92 23MAR92 7160 10 10 0 PrecMt . ArH . . legfn Shlppf,. to Sit. 2WR92 6APR92 7170 40 40 0 Precast . A.... 0 - Fabrfcatfon 25FEB92 2OAPR92 7110 10 10 0 Precelt . Ar.. D . legln Shfpplng to Sit. 21APR92 4MAY92 7250 25 25 0 Precast . A.... C - Fabrication 25MAR92 28APR92 7260 5 5 0 Precast .0 A.... C - legln Shipping to 1ft. 29API92 5MAY92 7270 40 40 0 Precalt . A.... E - 'abrlcatlon 18MAR92 12MAY92 7280 5 5 0 Precalt . Ar.. E - legln Shlppf,. to 1ft. . 13MAY92 19MAY92 . { { ...............................................................................................................-....-.............. Ronroe Cculty. 'lor f cia PlIMAVEItA PROJECT PLAMI Monroe Cowlty DetentIon ,ectt It)' IllT DATI 19DEC91 RUN NO. 50 Monroe Coc.my Detent'on FIlCH It)' STAltT DATI 1AUG9'f fllDATI UUl93* 16:28 SOlED ItEPOItT . lIne ak'p by IICtfvfty code DATA DATI 18NCN91 PAGE *t. S ..... ..... .... .... . ... .......... ...........--....-.............................. ........ ........ ........ ..-.-... ..... ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDUlED ID OUI DUI I STAltT FIIISH ..... ..... .... .... . ... -......... ..........--....-...................-........... ........ ........ .......- ...-.--- -.--. PrecMt lrectfon 10000 40 40 0 Precest . A.... A . lrectlon 10MAR92 4MAY92 20000 30 30 0 Precut . ArM . - lrectfon 5MAY92 16JU1192 30000 30 30 0 preceat ~ A.... C . lrectlon 17 JUII92 29M.92 40000 30 30 0 precest . A.... D . ErllCtfon 5MAY92 16JU1192 50000 30 30 0 Precut - Area I . Erect'on 17JUN92 29JUl92 Roof 10050 10 10 0 Are. A . loof . looffng 3JUN92 16JU1192 20050 10 10 0 Area . - Roon~ 9JUl92 22JUl92 30050 10 10 0 Area C - Roofl~ 2OAUG92 2SEP92 40050 10 10 0 Area D - loofl~ 9M.92 22M.92 50050 10 10 0 Ar.. E - Roofl~ 2OAUG92 2SEP92 St.l,.. 10010 5 5 0 Area A - T8IIIpOf'ary Acceu St.f,.. 5MAY92 11RAY92 20120 10 10 0 Ar.. . . Ir<<t Sta'", 16JUl92 29JUl92 30080 10 10 0 Ar.. C . Erect Stal,.. 27AUG92 10SEP92 ( 40120 10 10 0 A.... D - Erect Ital,.. 16JUl92 29JUl92 43050 15 15 0 Ar.. D - 2nd Fl ~ Rezz Handralla 6NJG92 26MJG92 43060 10 10 0 Ar.. D . 1at Pl . Interior St.l,.. 6NJG92 19MJG92 50080 10 10 0 A.... E - Erect Stal,.. 27AUG92 10SEP92 53050 15 15 0 A.... I - 2nd II . Meu "__.1 la 11SEP92 IOCT92 53060 10 10 0 Ar.. I . 1st Pi - Intarlor Ita',.. 1asEP92 10em Elwators 10100 15 15 0 A.... A - Elwators - lough-In , 9JUL 92 29JUl92 10110 5 5 0 A.... A - Elwators . Car & Pl.tf~ 3OJUL92 5MJG92 10120 5 5 0 Ar.. A - Elwators . Doors & Fr_ 6NJG92 12MJG92 10130 20 20 0 A.... A - Ilevators . Conatruct Cabs & Trf..out 13AUG92 10SEP92 Illb EIIbedI 11000 15 15 0 A.... A - 1st Pl - "lEIP/S Sllb EIIbeds 12MY92 2.u92 12000 20 20 0 A.... A - 2nd Pl - MlEIP/I Illb EIIbeds 12M Y92 9Jl1192 21000 10 10 0 Ar.. . . 1st fl - "lEIP/I Sllb E.Itleda 17 MI92 3O.UI92 22000 15 15 0 Ar.. . - 2nd Fl - "lEIP/I Ilab EIIbeds 17 JUI92 8JUL92 31000 10 10 0 A.... C - 1st Fl - MlEIP II Sllb EIIbeds 3OJUl92 12AUG92 32000 15 15 0 ArM C - 2nd fl - MJE/P/S Slab E.Itleda 22JUl92 11AUG92 41000 15 15 0 Area D - 1at FI - RlEIP/I Slab E.Itleda 17 J\II9Z IJUL 92 42000 20 20 0 ArM D . 2nd Fl - MlElP/I Sllb E.Itleda 17 J\II9Z 15JUL92 51000 15 15 0 Area I - 1at Fl - MlE/P/I Illb E.Itleda 3OJUL92 19MJG92 52000 20 20 0 Ar.. I - 2nd fl - t4/E1P/S Illb EIIbeda 3OJUL92 26AUG92 II'" 10030 5 5 0 Ar.. A - loof - TOPP'ng 19MAY92 2MAY92 11010 10 10 0 A.... A - 1at Fl.- FIR/PIC Sllb 3J\119Z 16JU1192 "- 12010 10 10 0 Ar.. A - 2nd FI - F/RIP/C Sllb 17 JUII92 3O.UI92 20020 5 5 0 A.... . . Roof Toppfng 24J\119Z 3O.IUII92 21010 10 10 0 Are. . - 1at Fl - FIRIPIC Sllb 1 JUL 92 15JUL92 ------..................-.....................................................................-.................................... McllYOe Ccu\ty, flori. PttIMAVERA PRO.IECT PI.AIIMEI Monroe CoLf1ty Detention '1CIlIey IEPClIT DATI 1ac:91 lUll 110. 50 Monroe ~ty Detention FIeHlty START DATI 1AUG91 FIN DATI ,l 16:21 SCIIED ItEPOIT . line .klp by ICtlvtty code DATA DATI 1811OW1 PAGE 11). 4 ..... ..... .... .... . .-. .......... ................................................ ........ ........ .....-.. ........ ..... ACTIYln OR I G ItSt ACTIYln DESCRIPTIOI SCHEDUlED ID OUR OUR I START FINISH --... ..... .... .... . ... -........- ...-.--......................................... ..-..... ~.._.... ........ ........ ...-. II'" 22010 10 10 0 A.... . . 2nd Fl - fJI/PIC Illb 16.IUL 92 29JUL92 22200 10 10 0 AI''' . . 2nd Fl - flllPIC .1.... & ~t. 3OJUL92 12AUG92 22JOO 10 10 0 AI''' . . 2nd Fl - lneulatlon brei & Illb . cvr 160CT92 29OCT92 30020 5 5 0 A.... C . Roof TClIlPlne .,-- 6MJG92 12AU892 31010 10 10 0 AI''' C . 1st Fl . FJl/PIC Illb 13AUG92 26MJG92 32010 10 10 0 AI''' C . 2nd Fl - fJI/P/C Sllb 3SEJl92 11SEP92 40020 5 5 0 AI''' - Roof TClIlPlne 24.1U192 3OAJN92 41010 10 10 0 Ar.. . 1at Fl . f~ & Rebar for Sllb 17.1U192 3OAJN92 41020 10 10 0 Ar.. - 1st Fl . Pour/Cur. Sllb 9JUl92 22.1Ul92 42010 10 10 0 A.... . 2nd '1 - F~ & ....1' for Sllb 11.1U192 3O.1U192 42020 10 10 0 Ar.. . 2nd fl - POA/I' /OIft S 1 Ib 23JUl92 5Al1G92 42040 5 5 0 A.... . 2nd Fl . Pour Ecf.II p peds 13AUG92 19AUG92 50020 5 5 0 AI''' - Roof Tapplne 6MJG92 12AUG92 51010 10 10 0 ArM . 1st fl - ,~ & .eber for ~llb 30JUL 92 12AUG92 51020 10 10 0 A.... . 1st Fl - Pour/Olft Illb 2OMJG92 2SEP9Z 52010 10 10 0 A.... . 2nd fl . f~ & ..... for Sllb 3OJUL92 12AUG92 I 52020 10 10 0 A.... . 2nd Fl - Pour/Oln Illb 3SEP92 17SEP92 -. 52040 5 5 0 Are. . 2nd Fl . Pour Equip peds 25SEP92 10CT9Z JIesonry 11020 5 5 0 AI''' A . 1st fl . L.,out 'art/Set 'r_1Vnd U.l 17.A1192 23.1U192 .' 11040 15 15 0 AI''' A . 1st fl . ....llfIo'l . letll~ 16.IUL92 5AUG92 11050 35 35 0 A.... A . 1st fl - lethrooa & ShaMel' TH. 6AUG92 24SEP9Z 11070 20 20 0 AI''' A . 1st fl - ....Cfli'Y . Offices & DonI ArMs 24.U192 22JUL92' 12020 5 5 0 A.... A . 2nd fl . L.,out 'artltled/Set Fr_IV 1 JUL92 1JUL92 12050 15 15 . A.... A - 2nd FI. - FIlII . 'I 9JUL92 29JUL92 12210 15 15 0 AI''' A . 2nd Fl - eer.tc Tt 1. 9OCT92 29OCT92 20100 10 10 0 AI''' . . ....onry . Stal ra 11.A1192 5O.IUI92 20110 10 10 0 Ar.. . - CUre ....llII. 'I' Sulra 1 JUl92 15JUL92 21020 5 5 0 Aru . . 1st fl .. L-rout Part/Set Fr_1Vnd U.l 16.IUL92 22JUL92 21040 10 10 0 AI''' . . 1st Fl . ReaonrY . . 6MJG92 19AUG92 21050 10 10 0 Ar.. . . 1st .1 . c:er.fc Tt le . . 2OAlJG92 ZSEP92 21070 20 20 0 Ar.. . . 1st '1 . ....llfIo~ 23JUL92 19MJG92 22020 5 5 0 Ar.. . . 2nd fl - uv-out Part/Set Door Fr.-s/V 3OJUL92 5MJG92 22040 10 10 0 Area . . 2nd Fl - .... anry . . 2OAUG92 2SEP92 22050 15 15 0 Are. . - 2nd fl. IIMonI"Y Support Syst_ .ough' 6AUG92 26MJG92 22060 15 15 0 Are. . . 2nd fl- IIMonI"Y 6AUG92 26AUG92 - 22280 10 10 0 Ar.. . . 2nd fl - CaIplete Exterior Masonry 1asEP92 10CT9Z 30060 10 10 0 Ar.. C . MasonrY . Stalra 3OJUL92 12AUG92 30070 10 10 0 Ar.. C . Cure "-onI'Y . St. I ra 13AUG92 26AUCi9Z . 31020 5 5 0 AI''' C . 1st Fl - t.ar-out 'art/Set Dr Fr..-JWII 27AUG9Z 2SEP92 31040 15 15 0 Ar.. C . 1st Fl - ..........., 3SEP92 24SEP9Z 32020 5 5 0 Area C . 2nd Fl . l-rout Part/Set Fr_1Vnd U.l 1asEP92 24SEP9Z 32040 15 15 0 Are. C . 2nd fl - IIMonI"Y 25SEP92 1socm ..............................................................................................................~.................... Monroe CoI.nty Detention FeclUty "'":~ Cowlty, Flor'. PRIMAVERA PRO.IECT PlAIIIIEl IT DATE 19DEC91 RUN 110. 50 Monroe CCUIty Detention Fecfllty ":21 SC'!fD IEPOIT - line Iklp by ect'v'ty code STAlT DATI 1AUG91 FUI DATE 1MO- DATA DATI 1811OV91 PAGE 110. 5 ..... ..... .... .... . ... .......... ....................~........................... ----.... ----...- -..-.... ..-..... ..... ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCIIEDtA.ED II DUI DUI I STAlT FlMISH ..... ..... .... .... . ... .......... .........................~...............-.....- ......~. .......~ ........ ........ ..... Ruorvy 40100 10 10 0 Area D - Muonry' Ital... . 17.1U1192 3O.U92 40110 10 10 0 Area D - CUre RasonrY . Sta'rs , 1.IUL 92 15M.92 41030 5 5 0 Ar.. D . 1at Fl - L~ Part/Set F.--J\h:I WlI 2S.IUL92 29.IUL92 41050 15 15 0 A.... D - 1at Fl - ....llhi7 - 1at lewl ..Ua . 3O.IUL 92 19MJG92 41010 10 10 0 A.... D - 1at Fl - MaaoIV'Ya - 2OAUG92 2StP92 42030 5 5 0 ArM D - 2nd Fl - L~ Part/Set Fr_JUnd WIt 6AUG92 12AUG92 43010 10 10 0 Area D - 2nd Fl - Masonry - 2nd lewl 3SEP92 17SEP92 43020 25 25 0 Ar.. D - 1at FI - ..'" lay Masonry Wall. 6AUG92 10SEP92 50060 10 10 0 Ar.. E . MMorwy . Sta'ra 3OJUl92 12MJG92 50010 10 10 0 Area I - CUre w..onry - Stl'ra 13AUG9Z 26MJG92 51030 5 5 0 Ar.. I - 1.t Fl - L~ Part/Set f.--J\h:l Wll 3SEP92 10SEP92 51040 15 15 0 Ar.. I - 1at Fl - ~ ~t Sysu. III 11SEP92 1OCT92 51050 15 15 0 Area E - 11t .1 - IIUonrY - 11t lewl ..Ua n SEP92 10CT92 51010 10 10 0 Ar.. I . 1st Fl - Reaonry a . 25SEP92 IOCT92 52030 5 5 0 Area I - 2nd .l - L~ Part/Set fr_JUnd Wll 1~ 2UEP92 ( 53010 10 10 0 Areal - 2nd FI I MeIdnry - 2nd lewl 9OCT9Z ~tR 53020 25 25 0 Ar.. I . 1.t fl - MI", lay Maaonry Will. 18SEP92 Z20CJ92 Drywall 12030 25 25 0 A.... A . 2nd Fl - DrywaU fr.',. 9JUL92 12MJG92 12200 15 15 0 Area A - 2nd fl - Drywall/Ttpe/Pl_ter Willa 18SEP92 IOCT92 Spray-on INUlatlon 12070 10 10 0 Area A - 2nd fl - Spray-on lnaulltlon . Prap 3OJUL92 12AUG92 120lIO 5 5 0 Ar.. A - 2nd 'l - Spnron lnaulatlon - Spray 13AU&92 19MJG92 22080 10 10 0 A.... . - 2nd Fl - ......,.on lnaulatlon - Prap 6MJli92 19MJG92 22090 5 5 0 ArM' . 2nd Fl - ......,.on lnaulltlon 27NJG92 2SEP92 32060 5 5 0 Area C - 2nd fl - Spray-on InlUlltlon Pnp 9OCT9Z 150CT92 32070 5 5 . Area C - 2nd Fl - Spray'on lnaulltlon - Spray 160CT92 za,cJR 43010 10 10 0 Area D . 2nd Fl - lpI".ay-on lnaulatlon 2OCT9Z 15OCl92 53010 10 10 0 Area I - 2nd fl- Spray-on lI.ulatlon 6NCN92 19MDV92 Utility lough-In ; .. c 10020 5 5 0 Area A - loof - hnetrltlona & loof Accessorl. 12MAY92 18Mm 10040 5 5 0 Area A - loof - CUrbs ~ 21MAY92 UJI92 10060 10 10 0 Area A - Roof -.aoof.Dr.',.ge 19MY92 2.u92 11030 15 15 0 Ar.. A - 1at Fl - I?\Ullbh'lJ III II ..th~ 24Jt1192 15JUL92 11060 20 20 0 A.... A - 11t Fl - ,Muonry 1/1 SUpport (M/EIPIS) 24Jt1192 22JUl92 12040 25 25 0 Area A - 2nd fl,- "-onlY III SUpport (MlElPIS) 9JUl92 12AUG92 12060 15 15 0 " A.... A . 2nd flc-J;eU!.", Anchors & ....,.. 9JUL92 Z9JUl92 20010 5 5 0 ArM . -Roof -. ~t...tlona & loof aee.sorl. 11.AJ19Z 23.UI92 20030 5 5 0 ArM' - Roof ~. r'.'", 1 JUL92 ~92 20040 10 10 0 ~ Aree . - Roof Dtaf~ ~ - 24.U192 I.IUL 92 ( 21030 10 10 0 Area . - 1st Ft - P\.I,.~ I~- ~n II . 23JUL92 5AUG92 21060 20 20 0 A.... . - 1st 'J - ~ 1uFPort, SyIt_ III 23JUL92 19MJG92 22030 10 10 0 . - Area' - 2nd .t - Ph.pl", I~-In II . 6AUG92 19MJG92 . ................................................................................................................................... IEP<lIT DATI 1CJDEC91 lUll NO. 50 . Monroe Cou1ty Detentfon Facfl fty 16:21 SCItED IEPOIT - tfne slcfp by actfyfty code Nontoe C<<Mrty Detentfon Facltfty STAlT DATI 1AUG91 Fill DATI . ( Monrol.' Cou1ty, Flor-lde PRIMAVERA PROJICT PUllllEI DATA DATI 18NOY91 PAGE.. 6 ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ..... ACTlVln OIIG 10 ID OUR OUR ACTIVln DEICIIPTIOI SCHEDUlED STAlT FIIIIII II- .. I ..... ..... .... .... . ... ......~... ................................................ ........ ........ ........ ........ ..... UtfUty lOUIh-fn 30010 5 5 0 ArM C . loof . PenetratIon & loof Accessorf.. 30JUL 92 5MJ892 - 30030 5 5 0 Ar.. C . loof CUrbI 13AUG92 19MJ892 " 30040 10 10 e' ArM C - loof Dr.'...... t' 6MJG92 19MJG92 . '. 31030 15 15 0 ArM C - 1st Ft - IIIsonry ~t - Syst_ III 3IEP92 24SEP92 31070 15 15 0 Area C - 1st Ft - Ph_fl'll lOUIh-fn a II 3SEP92 24SEP92 32030 15 15 0 Ar.. C - 2nd Fl - RMGnry'~t . Syst_ III 25SEP92 150CT92 32050 10 10 0 Area C - 2nd Ft . eell1,.Anchon & Hengers 25SEP92 8OCT92 32100 10 10 0 Area C - 2nd fl .,.tUlbll'll lOUIh-fn a sa 25SEP92 8OCT92 40010 5 5 0 Area . loof . Penetratlona & loof Accessorl.. 17.ll1192 23JU1192 40030 5 5 0 Area - loof CUrbI . ,'" ~~' 1.1Ul92 8JUL92 40040 10 10 0 Area - loof Dnl,... ., - 24.ll1192 8JUL92 41040 15 15 0 ArM - 1at Ft .- ....on;y SUpport Syst_ III 3OJUL92 19AUG92 41060 10 10 0 Area - 1st 'l - PlUlbfl'lllough'ln' Ir 3OJUL92 12AUG92 43000 10 10 0 Ar.. . 2nd Fl - IIuonry SUpport Syst_ III 3IEP92 17SEP92 43030 10 10 0 Area . 2nd Ft . eel t Il'lIIPl... H.,..rs & Sprts 11SEP92 10CT92 . s0010 5 5 0 Ar.. - loof . Penetr.tlona & loof Ace..sorl.. 3OJUL92 5MJ892 / 50030 5 5 0 Ar.. . Roof CUrbI . 13AUG92 19AUG92 50040 10 10 0 ArM - loof Drsl,... 6MJG92 19M11i92 51060 10 10 0 Ar.. . 1at ft- PlUlbfl'lllough'in a "r 11SEP92 24SEP92 53000 10 10 0 Ar.. - 2nd'l - RMonry SUpport Syst_ III 9OCT92 22OCT92 53030 10 10 0 ArM . 2nd ft . cell Il'lIIPt... Ilan8ers & SprU 23OCT92 5IIOV92 lult Inst.ll.tion of Utilitl.. ". 25 25 0 Ar.. A . 1at ft - IMlC Ductwork lult Instl 23.IUl92 26MJG92 '''00 25 25 0 ArM A . 1at ft - IMC Pipll'll lult Instl 23.IUl92 26MJG92 11120 25 25 0 ArM A . 1at ft . PlUlbfl'lll&ltk Instl 23.IUl92 26MJG92 '''40 25 25 0 Ar.. A . 1st ft - Pw/UI Cardlft lult Inst 23.IUl92 26MJG92 1 "60 25 25 0 ArM A . 1at ,l _.~ Ccinll.Ift lult Inst.ll 23.IUl92 26IlUG92 ",ao 25 25 0 Ar.. A . 1at 'l - -ffre "Prohctlon lult Instl 23.1UL92 26IlUG92 12090 20 20 0 Ar.. A - 2nd ft - WAC Ductwork lult Instl 2OAUG92 17SEP92 12100 15 15 0 Ar.. A - 2nd Ft - WAC Plpll'll lult Instl 2OAUG92 10SEP92 12110 15 15 0 ArM A . 2nd fl . PlUlbfl'lllult Instl 2OAUG92 10SEP92 12120 15 15 0 A.... A - 2nd Ft . Pw/UI eonc..lt lult Instl 2OAUG92 10SEP92 12130 15 15 0 ArM A - 2nd ft - SecUrltj~ Conci.Ift lult Ins 2OAUG92' 10SEP92 12140 15 15 0 Area A - 2nd Fi - FIre .PrOtectlon lult Instl 2OAUG92 10SEP92 21<<110 15 15 0 ArM I - 1at fl ."WAC Ductwoi1t . lult Install- . 2OMJG92 10SEP92 21090 5 5 0 Ar.. 1-.' 1at"t -WAC Plpfriii' - lult lnet.ll-- 2OMJG92 26MJG92 21100 10 10 0 Ar.. I - 1st 'F;~Ptuibt,.:~..lult IniitaU 2OAUG92 2SEP92 21110 15 15 0 ArM I ,""t h . Pwlltt Cardlft . Bult Instell 2OMJG92 10SEP92 21120 10 10 O. Ar.. . . 1at Fl . Sec~ CcriIUft . lult Instal 2OAUG92 2SEP92 21130 10 10 0 Ar.. . - 1at Fl - Fire protection' lult Install 2OMJG92 2SEP92 22100 10 10 0 Ar.. I -'2ncI Ft >>"WACCDUR.ort -'ilult Inst.U' 3SEP92 17SEP92 22110 15 15 0 ArM I - 2nd fl....~lIVAC ,tift.. - ....tt Inst.ll 3IEP92 24SEP92 22120 10 10 0 ArM . . 2nd Fl" ;':-'lUlbll'll. lult lnstallatton 3SEP92 1 tsEP92 ....................................-._......_~.................................................................................... NclnrOe Ccurty, Florlde PlIMVEIA PltOJECT Pt.ANIIEI Monroe County Detention 'ecH fty d DATE 190EC91 lUll 10. 50 Monroe Coc.Irty Detention FecH Ity 16:21 SCIIED REPORT . line sltfp by ectfvtty code START DATI 1NJG91 fll DATE 1JUl93* DATA DATI 18NOV9t PAGE 10. 7 ..... ..... .... .... . ... .......... .........................~~..................... ........ ........ ........ ........ ..... ACTIYln ORIG REM ACfIVln DESCRIPTIOI SCHEDULED or ID M M I STAlT FlIIII ..... ..... ......... . ... .......... ............-.......~..~........................ ........ ........ ..~..... ........ ..... "'lit lnatallatlon of Utll Itl. 22130 " " 0 Ar.. . .. ,Zrld Fl . PwlU, CorQIft . "'lit InataU 3SEP92 24SEP92 22140 10 10 0 Ar.. . . Zrld Fl . seycc. CorQIft . lullt lnatal 3SEP92 17SEP92 22150 10 10 0 Area' . Zrld Fl t fI... protectfon . lult lnatall 3SEP92 17SEP92 m10 15 15 0 ArM . . Zrld 'I . Ancfllfery Pipe 16OCT92 5NCJII92 31OS0 15 15 0 Ar.a C . 1st 'I . IIYAC Ductworlt lullt lnatall 25SEP92 15OCT92 31060 5 5 0 Ar.. C . 1st Fl . IVAC Plplne . lullt lnatall 25SEP92 10em 310e0 15 15 0 Ar.a C . 1st '1 . Plu.bfne . Butlt lnatall 25SEP92 1socm 31090 20 20 0 Ar.. C . 1st Fl . Pwr/Ltl CordJlt . Built lnat.ll 25SEP92 . 22OCI92 31100 20 20 0 Ar.. C . 1st Fl . See/eo. CordJft . lult lnatal 25SEP92 22OCT92 31110 15 15 0 Ar.a C . tst Fl . '1... protec:Uon . lullt lnatall 25SEP92 1socm :szoeo 15 15 0 Ar.. C . Zrld Fl . IVAI: Ductwork . lullt lnatall 230CT92 1211CW92 32090 10 10 0 Ar.. C . Zrld Fl . IVAC Plpfne . "'It lnatall 230CT92 511M2 32110 10 10 0 Ar.. C . Zrld Fl . Plu.bfne . "'It lnatall 230CT92 511M2 32120 15 15 0 ArM C . Zrld Fl . Pw/Lt, CorQIft . lult lnatall 230CT92 1211CW92 32130 10 10 0 ArM C . Zrld Fl . see/eo. CordJlt . "'It lnatal 230CT92 51OV92 ( 32140 10 10 0 . ArM C . Zrld Fl . FI... protectfon . lult lnatall 23OCT92 51OV92 43100 15 15 0 ArM D . 1st '1 . 11.1 1 If de A . vert ch... uti 160CT92 51OV92 43110 15 15 0 . ArM D . 1st Fl . 11.1 1 Ifde . . vert chase uti 6IIOV92 3OIiICW92 43120 15 15 0 Ar.. D . Zrld Fl . 11.1 1 Ifde A . hortz chaM uti 6IIOV92 3OIiICW92 43130 15 15 0 ArM D . Zrld Fl . 11.1 1 If de . . hortz chaM uti 10EC92 Z1DEC92 r 43200 15 15 0 ArM D . 1st Fl . .. 2 Ifde C . vert chaM uti 16OCT92 51OV92 43210 15 15 0 A.... D . 1st Fl . 11.1 2 If de D . vert chaM uti 6IIOV92 3OIiICW92 43220 15 15 0 ArM D . Zrld Fl . .. Z ..de C . hortz chaM uti 6IIOV92 3OIiICW92 43230 15 15 0 Ar. D . Zrld Fl . .. ~ If de D . hortz ell... uti 10EC92 Z1DEC92 43300 30 30 0 A.... D . Zrld,l . IIedlanfcal Iocla Utf lltf.. 160CT92 3OIiICW92 4mO 20 20 0 Ar. D . ~OffICl Utflltf. 160CT92 1211OV92 53100 15 15 0 A.... E . 1st Fl . .. 3 Ifde E . vert chaM uti 2OIOV92 14DEC92 53110 15 15 0 Ar.. E . 1st Fl . 11.1 3 If de , . vert chaM uti 15OEC92 6.IM93 "'20 15 15 0 Ar.. E . Zrld Fl . III 3 Ifde E . horll chaM uti 15DEC92 6.IM93 53130 15 15 0 ArM E . 2nd Fl . III 3 If de , . hortz ell... uti 7JA1193 27 .IM93 53200 15 15 0 Ar.. E . 1st Fl . III 4 Sfde G . vert chaM uti 2OIOV92 14DEC92 53210 15 15 0 Ar.. E . 1st Fl . III 4 Sfde I . vert chase uti 15DEC92 6.IAII93 53220 15 15 0 Area E . 2nd Fl . III 4 Sfde G . horfl ell... uti 1SDEC92 6.IAII93 53230 15 15 0 Area E . 2nd Fl . III 4 Sfde I . horfl chase uti 7JA1193 27.1M93 53300 30 30 0 ArM E . 2nd fl . Mec:henfcal R~ UtU W.. 2ONOV92 6.IM93 5l33O 20 20 0 Ar.. E . ~ffca Utf I 2OIOV92 Z1DEC92 Ceu lne Fr_I", 11200 5 5 0 Ar.. A . 1st Fl . Cel lIne Fr.lne In A1000 27AUG92 2SEP92 11210 5 5 0 Area A . 1st Fl . Cel t lne Fr.lne In A1029 3SEP92 10SEP92 11 220 5 5 0 Area A . 1st Fl ~ eel I fne Fr.fne In A1039 11 SEP92 11SEP92 ( 11230 5 5 0 ArM A . 1stF' . Cetllne F~tne In A1049 18SEP92 24SEP92 12150 15 15 0 Area A . 2nd Fl . Ceu lne Fr.tne 18SEP92 8OCT92 ~ 21140 10 10 0 ArM . . 1st Fl . Cell lne Fr.fne 11 SEP92 24SEP92 ................................................................................................................................... Monroe Ccurty, , lorl de PRIMAVERA PROJECT PI.AMEI Nonroe ~ty Detention 'acllfty REPORT DATE 19OEC91 RUN NO. 50 Monroe Cowlty Detention FecH Ity 16:21 SCHED REPORT. line skIp by activIty code STAlT DATI 1MJCi91 fll DATE DATA DATE UI..0\I91 PAGE 10. a ACTIVln ORIS Rat ID DUI M C' ACTlvsn -DlSCltIPTlOI SCHEDULED ITAll fllllI I . . --- ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ....- Cel II.. Fr.lng c~ "'.' 22070 10 10 0 Are.' . 2nd Fl . Cell f.. AnChors & hngers 6MIG92 19AiJG92 ," 22160 5 5 0' Ar.. . . 2nd Fl '.. Celllri.1r..... 25SEP92 10Cm [; 31130 5 5 . ' Area C . 1st ,. .:cifllrii ,,..Ing . Stert 2lOCT92 29OCT92 31140 5 5 . Aree C . 1st Fl . "Celllne '~Ine . Calplete 300CT92 5IOV92 32160 10 10 0 Area C . 2nd Fl . Cell fne '....Ing 1311OV92 3OIIOV92 43340 10 10 0 Area D . Cel I Ing Fri..... 1311OV92 3OIIOV92 53340 10 10 0 Ar.. E . Celli.. Fr.... ; 22DEC92 6.IA1193 Syat_ Dropa I T..tlne / P\n:h.out 11240 10 10 0 Area A . 1st Fl . Syatlllil Dropa . Stert 3SEP92 11SEP92 11250 5 5 0 Area A . 1st Fl - Syat_ Dropa . Calplete Z5SEP92 1OCT92 11260 5 5 0 Ar.. A . 1st '1 . T..t 'UtU fty PIpIng Syst_ 2OCT92 aocm 11270 5 5 0 Area A . 1st PI .. lVIdl.out Above Cell Ing UorIt 9OCT92 1SOCm 1Z160 15 15 0 Ar.. A . 2nd PI . Utflfty Syat_ Dropa . Start 18SEP92 aocm 12170 5 5 0 Area A . 2nd Fl .. "Utfltty Iyst_ Dropa . Cpt 9OCT92 15DCT92 12180 5 5 0 A.... A . 2nd Fl . T..t Uti I Ity PipIng Syat_ 160CT92 22OCT92 12190 5 5 0 Area A . 2nd Fl : pya-out Above Cel I Ing Yortt 2lOCT92 29OCT92 21150 10 10 0 Ar.. . . 1st tl . Sya~ Dropa . Start 11SEP92 24seP92 \ 21160 5 5 0 Ar.. . . 1st Fl . Syat_ Dropa . Calplete 25SEP92 10Cm 21170 5 5 0 A.... . . 1st '1 . Syat_ T..t 2OCT92 aocm 21180 5 5 0 A.... . . 1st F\ . P\n:It-out 9OCT92 150CT92 22170 5 5 0 ArM . . 2nd Fa . Sya~ ~ 2OCT92 aocm 22400 10 10 -0 A.... . . 2nd Ft . Syau. T_t 6IDI92 1911OV92 22410 5 5 0 A.... . . 2nd Fl . Ilva-out 2OIOV92 3OIOV92 31150 5 5 0 A.... C . 1st Fl . Sya~ Dropa . Start 3OOCT92 5IIOV92 31160 5 5 0 A.... C . 1st Fl . Ivs~''''' . Calplete 6IDI92 1211OV92 31170 5 5 0 A.... C . 1st '1 . Ivst- Teet 1311OV92 1911OV92 31110 5 5 0 A.... C . 1st 'I . Sya~ "",,.out 2OIOV92 3OIOV92 32170 5 5 0 A.... C . 2nd '1 . Sya~ Oropa . Start 1311OV92 1911OV92 32110 5 5 0 A.... C . 2nd Fl . Syat_ 'DrOp. . Calplete 10EC92 7DEC92 32190 5 5 0 ArM C . 2nd Fl . Syat_ t..t &>>EC92 14DEC92 32200 5 5 0 Area C . 2nd fl . ","".out 15DEC92 21DEC92 43310 5 5 0 ArM D . 2nd Fl . T..t Syst_ 22DEC92 29DEC92 43320 5 5 0 Ar.. D . 2nd Fl . PWd.out 3CIlEC92 6.IA193 43350 5 5 0 ArM D . Syst_ D~". both floors 10EC92 7DEC92 43360 5 5 0 ArM D . Syat_ T..t . ~Off . both floors 1DEC92 14DEC92 43370 5 5 0 ArM D . P\n:II-out . ~f . both floors 15DEC92 21DEC92 53110 5 5 0 Ar.. E . 2nd Fl . T..t Syat_ 28.WI93 3FEa93 53320 5 5 0 Ar.. E '. 2rid Fl . ~.out 4fE893 10FE1193 53350 5 5 0 ArM E . Syat_ -'rcipa . both floors 7.1M93 13JA193 53360 5 5 0 Ar.. E . Syat_ Teet . ~f . both floors 14.1A1193 2O.IA193 53370 5 5 0 ArM E . P\R:h-out . DaYrWOff - both floors 21.1M93 27 JA1193 Cell I "IS '.' 11280 20 20 0 Area A . 1st Fl . Cell Ing loard!TaptlPl..ter 160CT92 1211OV92 ................................................................................................................................... tIonroe CowIty, Florlde PtIMAVERA PROJECT PLAlllER Monroe CowIty DetentIon FecH Ity ( lilT DATI 190EC91 llIt NO. 50 Jbv'oe Cou'tty Detention Facility STAlT DATI ,MIG9t "I DATI 1.IUL93* 16.21 tCIIED REPORT . line skip by actfvlty code DATA DATI ,.."." PAGE 10. 9 ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ..... ACTIVln ORIG REM ACTIVln DESCRIPTIOI SCHEDUlED It. .':'" .D M M I START ,..1. ~ ..... ...-. .... .... . ... .-........ ................................................ ........ .....~.. ........ ........ ..... Celli... 12220 15 15 0 ArM A . 2nd Fl . Drywll/Tape/Pl..ter Cell I... 300CT92 1911DV92 21_ 15 15 .0 ArM . . 1at ,t Cel I Ing 1oardIT.,./Pl..ter 16OCT92 51OV92 22UO 10 10 0 ArM . . 2nd Fl . Df'YMIlllTape/Pl..ter Cen I... 'DEC92 14DEC92 31_ 15 15 0 Ar.. C . 1st Fl . Cel t 11'11 Ioarel Tape & Pleeter 1DEC92 21DEC92 32410 15 15 0 Ar.. C . 2nd Fl . Cell I "IS 14JA1193 3FE193 43380 15 15 0 Ar.. D . DrywelllTape/Pl..ter Celli... . both fl 22DEC92 13.1M93 53380 15 15 0 Ar.. E . DrywlllTape/pt..ter Clp . both floors 28JA1193 17FE193 "Ire Pulls 11300 10 10 0 Ar.. A . 1st Fl . Wire Pulls 13N0V92 3OIIOV92 12240 10 10 0 Ar_ A . 2nd Fl . \ltre Pull. 2ONOV92 7DEC92 21220 15 15 0 ArM . . 1st '1 WIre Pull 6IIOV92 3OIIDV92 22450 20 20 0 Ar.. . . 2nd Fl . Wf... Pull 15DEC92 13.1A1193 31220 15 15 0 Area C . 1st Fl . Wire Pull 22DEC92 13.1A1193 32400 15 15 - ,0 Ar.. C . 2nd Fl . WI r. Pull 22DEC92 13.1A1193 , 43420 10 10 0 Ar.. D . Wire Pull . start. both floors 3ODEC92 11.1M9J ( 43430 5 5. 0 Ar_ D . Wf... Pull . CCllIIPlete - both floors 14JA1193 20JAIIri 53420 10 10 0 Ar.. E . VI re Pull . etart . both floors 4FEm 17FE193 53430 5 5 0 ArM E . Wi... Pull . CCllIIPlete . both floors 1aFEm 24FE193 Trllrout Utflltl.. 11no 15 15 0 ArM A . 1st Fl . J4/EIP/I TrIa-out 15DEC92 6.IAII9S 12210 15 15 0 ArM A . 2nd Fl . t4IElP/I TrIa-out 22DEC92 13.1A1195 21_ 15 15 0 Ar.. . . 1st Fl . M/ElP/I Tria-out 15DEC92 6.IAII93 22480 10 10 0 Area . . 2nd Fl . tVEIP/I Tr la-out 28JA1193 10fU93 31_ 10 10 0 Area C . 1st Fl . tVEIP/I Tria-out 28JA1193 10fU93 32470 10 10 0 ArM C . 2nd Fl . t4IEIP/l Trllrout 4MAl93 11MM93 43470 15 15 0 Area D . M/EIP/S trllrout . both floors 4FEm 24FE193 53470 15 15 0 Area E . M/EIP/I tria-out --,both floors 11MAR93 311N93 Paintfl'll 11310 10 10 0 Aree A . 1et Fl . Prep for lullt Painting 13N0V92 3OIIDV92 11320 10 10 0 Area A . 1st Fl . tulk Palnti", 1DEC92 14DEC92 12250 10 10 0 Area A . 2nd Fl . Prep for "'lit Painting . 2ONOV92 711EC92 12260 10 10 0 Area A . 2nd Fl . lullt Painting 8OEC92 21DEC92 21230 10 10 . Area . . 1st Fl . PaInting Prep 6IlOV92 1911DV92 21240 10 10 0 Area . . 1st Fl . lult Paintfng 1DEC92 14DEC92 22460 10 10 0 Area . . 2nd Fl . Pafntlng Prep 1SOEC92 29DEC92 22470 10 10 0 Area . . 2nd Fl . lul\( Painting 14JA1193 27.1M93 31230 10 10 0 ArM C . 1st Fl.. ,.Intlne Prep 22DEC92 6.IAII9S 31240 10 10 . 0 Area C . 1st Fl . lulk PaInting 14JA1193 27 .IAII93 32430 10 10 0 ArM C . 2nd Fl . P.lnt Prep 14JAN93 27~ 32440 10 10 0 ArM C . 2nd Fl . "'Lit Palntfng 4FEm 1~ ( 43450 10 10 0 Area D . PaInt prep . both floors 22DEC92 6.IM9J (: ~. 43460 10 10 0 Area D . lullt Paint. both floors 21 JAN93 3FEI93 , 53450 10 10 0 Area E . Paint prep . both floors 2IJAN93 10FB95 ...............................................................................................-................................-.- Monroe Ccurty, Florlde PttlMAVERA PItO.IIC1' .u.a Monroe Ccu\ty Detent I on 'ac It I ty REPORT DATI 19DEC91 RUI NO. 50 tIonroe Cowlty Detention 'ecfllty STAlT DATI 1AUQ91 nlDATI 16:21 SCHED REPOIT . Une skip by activity code DATA DATI 1eNOV9t PAGE ID. 10 ..... ..... .... .... . ... .......... ................................................ ........ ................. ........ ..... ACTIVln 011 G REM ACTIVln DEICRIPTIOI SCIIEDULED ID DUI DUI I STAlT FlIIII A.' ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ -.-.. Palnttng 53460 10 10 , A.... E . Butt Paint. botlt floors 25FEI93 1ClMA19J 77'020 30 30 . Painting - Inter'..... Touch... (sUM:) 18MAR93 2IAPI93 0(1 77U3O 10 10 , PaInt tng . Intertor Touch... lCClllpl) 13M Y9S 26MY9S 77040 60 60 . p.tntlng - Exterior aut ldtlll 5FE193 29API9J 0<. FInIsh.. 11290 10 10 . A.... A - 1st ,l . lnatall Doors & Grills 13NO\192 3ONCN92 ,. 11340 15 15 0 ArM A - 1at Fl . CaNwort 15DEC92 6.IAN93 11350 15 15 0 Ar.. A - 1st '1 - Gl.ztng 15OEC92 6JAI9J 11360 15 15 0 ArM A - 1at Fl . Door 1Iardwe... 15DEC92 6.IAN93 1, 11m 10 10 0 A.... A - 1st Fl - Floor & vall CoYerI. 7JA1193 2OJA1193 12230 10 10 . Ar.. A - 2nd Fl - lnatl Doors & Grit Is 2ONOV92 7DEC92 12270 10 10 . ArM A - 2nd Fl - C.....-t 22DEC92 6JAII93 12290 15 15 '" ArM A - 2nd Fl - ~ttcal TIle 22DEC92 13JA119.S 1ZSOO 15 15 . ArM A - 2nd Fl - Door ~ 22DEC92 13JA119.S C 12310 15 15 . ArM A - 2nd Fl - Glul", 22DEC92 13M1193 r 12320 15 15 . A.... A . 2nd Ft - Floor & Ulll Coverf. 14.1A1193 ,]FE193 { 21190 10 10 . A.... . - 1st '1 - ,loor Pr8p 160CT92 29OCT92 21210 15 15 0 ArM . - 1st 'I - Doors & Irlt lee 6IICN92 3C*DV92 21250 15 15 0 Ar.. . - 1at Fl - ~tlcal Ttle 15DEC92 6JAII93 21m 10 10 0 A.... . - 1st Fl . Door ......... 15OEC92 29DEC92 21_ 10 10 . A.... . - 1st Fl - Glul"'.. 15DEC92 29DEC92 21290 15 15 0 A.... . - 1at Fl . Floor & Vallcovwf. 7.1A1193 27 MI9J 22420 10 10 0 Ar.. . - 2nd Fl . floor Prep 10EC92 14DEC92 22440 10 10 0 ArM . - 2nd Fl . Doors & .,.fU.. . lnat.ll 15OEC92 29DEC92 " 22490 5 , 0 A.... . - 2nd Fl . Door .......... 2IJA119S 3f093 ~' Z2500 5 5 0 Ar.. . - 2nd Fl - Gl.ll", 2IJAII93 3FEI93 22510 5 5 . ArM . - 2nd Fl . Acouatlcal Tile 2IJA1193 3f093 22520 5 ~ 0 A.... . - 2nd Fl - Floor & UlllCCNWtngs 11 F09J 17F093 31120 10 10 . ArM C - 1st Fl . cw.fc TIle 25SEP92 8OCT92 31190 10 10 0 Ar.. C - 1at Fl - Floor Prep 1DEC92 14DEC92 31210 10 10 . A.... C - 1st Fl - Doors & .,.111.. 22DEC92 6.IM93 31250 5 5 0 ArM C - 1at Fl - ~t'cal Tile 2IJAII93 3F093 r ' 31270 10 10 . ArM C - 1st Fl - Door ........ 2IJA1193 1GfEI9J r,- 31_ 10 10 0 Ar.. C - 1st Fl - Glul", 2IJA193 10f093 31290 10 10 0 A.... C - 1st Fl -"Floor Covering 11 FEI93 24fE893 ';: 32420 10 10 0 ArM C - 2nd Fl . lnataU Doors & Grill.. 14JAII9J 2'1.1A1193 ' 32450 10 10 . ,- ArM C - 2nd Fl - ....l... floors 1aFE193 3MAI93 32490 10 10 . Area C - 2nd Fl -' Othef-' ,loorlng 4MAl93 11MA1t93 43040 15 15 . ArM D - 1st Fl - Celt furniture 2OAUG92 101EP92 43045 10 10 > 0 A.... D - 2nd Fl . Cell fUmt ture ;. 11SEP92 241EP92 " 43400 20 . ' 0 Area D - Cell Doors &.ooot Fr_ - , 160CT92 121OV92 : ' 2D 43410 10 10 ,,' 0 . , Area D . Grout Cen Door ,~ .. both floors 131OV92 ~,,' ( ~ " 43440 5 5 -' 0 Area 0 - Doors & ern l..'~ both floors 14JAII9J ZCWlII93 ................................................................................................................................... IIonrOe C<<.I\ty, norl. PlIMAVERA PltOJECT PLAllNU Monroe ~ty Detentfon 'actl Ity I UUCl91' 'II DATI ..T DATI 190EC91 lUll 10. SO Monroe Cow\ty Detention Fecit fty START DATI ,.W 16:21 t. SC1IED ItEPORT . line skip by ectfvlty code DATA DATI 18N01191 PAGE 10. U ..... ..... .... .... . ... .....-.... ................................................ .......- ........ ......... ........ ..... ACTIYln ORIG REM ACTIVITY DESCRIPTIOl SCHEDULED ~"'. ' ID M M I STAlT ,.11111 ..-.. -.... .... .... . --. .........- ........................--...................... .......- ........ ........ ........ ..... "nl..... : ,--. .... - 43410 15 15 0 ArM D . CaMwort . botll floors 4FE193 24FE19S f'~ 43490 15 1S . Ar.. D . Gluf", . both floors 4FEI93 24FE19S C'~ ~' (, 43500 1S 1S 0 ArM D . Door Hardwe... . both floors 4FE193 24FE19S 43510 15 15 . ArM D . Accgtlcal Cetll", . both floors 4FE193 Z4FE893 43520 10 10 0 Ar.. D . Floor prep . both floors 4FEB93 17fU9J 43530 10 10 . Ar.. D . Floor coverl", . both floors 25FEI93 10MAR93 53040 15 15 0 Area E . 1st Fl . Cell furniture 2OCT92 22OCT92 53045 10 10 0 Ar.. E . 2nd Fl . Cell Furniture 230CT92 5IIH92 53400 20 20 0 Ar.. E . Cell Doors & Door Fr_ . both Floors 2OIOV92 21DEC92 53410 10 10 0 ArM E . Grout Cell Door fr_ . both floors 22DEC92 6.Wt9S 53440 5 , 1>> Ar.. E . DoorS & Grin.. - both floors 1IFE193 24FE193 S3480 15 15 0 Area E . Casework . both floors 111Wt93 311N93 53490 15 15 0 Ar.. E . stulng . both floors 111Wt93 311N93 53500 15 15 0 Ar.. E . Door llardwer. ,- both floors 11MAR93 311N93 53510 15 15 0 Ar.. E . Accgtfcal Cefl f", . both floors 111Wt93 31MAR93 ( 53520 10 10 0 Ar.. E . floor prep . both floors 11MAR93 24MA193 53530 10 10 0 ArM E . Floor cowrfne . botll floors 1AP1l93 14AP193 Electrical Equt~t 20350 15 15 0 Area' . svttchgeer . ~.ta P.O. 13JA1192 31 JAII92 20360 5 5 0 ArM' . SWftcheur . Select Vendor 3FE192 7FEI92 20370 1 1 0 ArM . . SWltchteer . I.- PO 10FE192 10fE192 20380 70 70 0 Area' . SWftc:heMr . 'lib & DeiWI' 11FEI92 ,..m 20400 15 15 0 ArM . . ...... &en . ......t. '.0. 13.lA1192 3UA1192 20410 5 5 0 Ar.. . . ...... .. . Select Vendor 3fE192 7FEI92 20420 1 1 0 ArM . . ...... &en . lnue PO 10FE192 10FE192 20430 120 120 0 Ar.. . . ...... &en . 'lib & Del fWl' 11FE192 29JUL92 20450 15 15 0 Aree . . tI'I Syst_ . Generat. p.o. 13JA1192 31.1AII92 20460 5 5 0 Ar.. . . tI'I Syst_ . Select Vendor 3FE192 7FEI92 20470 1 1 0 Aree' . tI'I Syst_ ..Issue PO 10FE192 10fE192 20410 145 145 0 ArM . . tI'I Syst. . FIIb & Del iver 11 FEm 2SEP92 Mec:Mnfcal Equfpltnt 20200 15 15 0 Area . . cur - Generate ,.0. 13JAN92 31.lA1192 20210 5 5 0 Area . . cur ....lect Vendor 3FEB92 7FEI92 20220 1 1 . Area' . cur . Issue PO 10FEB92 10FE892 20230 70 70 0 Ar.. . . cur . .flb & Del Iv., 11 FEB92 ,..m 20250 15 15 0 Area' . Chillers. o.nerat. P.o. 13JA1192 31.M1192 20260 5 , . ArM . . Chi n.... . Select Vendor 3FEB92 7fEI92 20270 1 1 0 ArM . . Chin.... . lnue PO 10fEB92 1Oft192 20280 110 110.. 0 ArM . . Chfll.... - FIIb' Oellver 11FEB92 15.IUL92 20300 15 15 0 Area' . AW . Generate P.O. 13.1A1192 31JAN92 20310 5 5 0 ArM . . AHU . Select Vendor 3FQ92 .7FE192 "- 20320 1 1 . 0 Aree . . AIlI . I ssue fIG.. " ". ~ ? 10FE192 10fE192 .. 20330 eo eo! 0 ArM . . AHU . Fib , Del I WI" 11FEI92 2.UI92 - ..~....................................._.......................................................................................... ~ Cculty, 'lorl. "JMAVERA PIO.IIC'f PI.AMI Monroe eou,ty Detention lecUltr IEJUT DATE 19OEC91 lUll 10. 50 16:21 SCHED IlEPClIT . line Hip by activity code Monroe Cou'Ity Detention Fec III ty START DATI 1AUGt1 FIN DATI ( DATA DATE 18N0\/91 PAGE 10. 12 ..... ..... .... .... . ... .......... ...................................-............ ........ ..-..... .--..... .....-.. ..... ACTIVln ORIG REM ,< ACTIVln DEICIIPTlOI SC1IEDUlED ID DUI M I IT AlT Fill.. I', " > ..... ..... .... .... . ... .......... ...........................-.......-........-.-. ........ ..--...- .....-.. ..---... ..... MedlInlcal Equl...,t , 22290 10 10 . Area . . 2nd Fl . II'IICt all 2OCT92 150CT92 - ~t >>, 32300 10 10 0 1 A.... C . 2nd Fl . COOl.. 'loon ....Inat.ll 160CT92 29OCT92 ?' .0,-', ' 32310 10 10 0 A.... C . 2nd '1 .cure,loon ' 3OOCT92 121Ol192 32320 10 10 0 ArM C . 2nd n . COOL.. '....1'" 1311GY92 ~ ,J,;, 32330 10 10 0 Area C . 2nd Fl . COOL.. "'ls ..Inatlll 1oeC92 14OEC92 32340 5 , 0 Area C . 2nd Fl .' Cooler Yrl. .out 15DfC92 Z1DEC92 40500 15 " . ArM D . AIlJ'. . Generate P.O. 13JAN92 31.1A1192 40510 5 5 0 ArM D . AIlJ's . Select Yendor 3FE892 7FEI92 40520 1 1 0 Area D . AIIU'. . Jsaue PO lOFE892 10FE192 40530 40 40 0 Area D . AIIU'. . ,., DeliWI' " FEI92 WIl92 50500 " 15 0 Area E . AIIU'. . lIner.te '.0. 13JA1192 31.1A1192 50510 , , 0 ArM E . AIlJ's . Select v.ndor 3FE192 7FEI92 50520 1 1 . Area E . AIIU's . I... PO 10FE192 10FE892 50530 40 40 0 Area E . AIIU'. . ,. & DeliWI' 11FE192 WR92 Lantry Equl...,t 20500 15 " 0 ArM . . L..ay E",lp . Gener.te '.0. 13JAN92 3UAl192 t' . ~,' 20510 5 , 0 Area . . L..ay EcJ.rlp . Select Vendor 3FE892 7FEI92 " , 20520 5 5 0 Area . . L..ay Equip. lsaue PO 10FE892 14FE192 20530 15 15 0 Area . . L..ay Equip . F. & DelIver 17FE192 15.u192 KItchen Equl~ 30100 25 25 0 Area C . Kitchen Equfp . Generate P.O. 13JAN92 14FE192 30110 5 5 0 Area C . Kitchen Equip. Staff IwI_ 17FE192 21 FEI92 3011' 5 , 0 ArM C . KItchen Equfp . Allard '.0. ZitFE192 2IFEI92 30120 50 50 0 Area C . Kitchen Equip . .. Ir..l.. 2MAI92 Mlm 30130 15 15 0 ArM C . Kitchen .... . AlE 1..,1_ & AFProval 11MAm 1&W92 30140 35 35 . ArM C . Kitchen Equip. fnl Coord WI oth.... 2.UI92 21....92 30150 150 150 . Area C . KItchen Equip. ,. & Delfver 2.UI92 5.IM93 32150 5 , 0 ArM C . 2nd Fl . InataU ICltdlen IoocIa 23OCT92 29OCT92 32410 5 5 0 ArM C . 2nd Fl . ICltdlln Equl~ Trl.-out 25MAI93 311tAR93 Set Equt s-ent . m10 10 10 0 Ar.. . . 2nd Fl . Set an' E",Is-ent 13AUG92 26MJG92 22220 10 10 0 Ar.. . . 2nd Fl . Set C2lfller Equl~ ; 13AUG92 26MJG92 22230 10 10 . ArM . . 2nd Fl . Set AlII EqulpMnt 13AUG92 26MJ892 22240 10 10 0 ArM . . 2nd Fl . Set ....tc:htMr . . 13AUG92 2MUG92 22250 10 10 0 Area . . 2nd Fl. Set' .....eencv Genentor 13AUG92 26MJG92 ~- 22260 10 10 0 Area . . 2nd Fl . Set lJIIlyst_ ' 3SEP92 17SEP92 22210 10 ;0 0 Area . . 2nd Fl . Set LanIry Equi...,t 13AUG92 26MJG92 32460 15 .15 0 Area C . 2nd Fl . Set Kitchen Equl~ Wl93 2Wl9J 42050 5 5 0 Area D . 2nd Fl . let AlII'. - D1 and D2 2OMJG92 26MJliI92 _,; 52050 , 5 0 Area E . 2nd Fl . let .... · E1 and E2 2OCT92 IOCT92 ~' Mech..lcal Syst_ Cbeclt.out & "lancing .,,'. '!':li:'\ 71005 20 20 0 A.... A . Mec:h Syat. TI,,'ft & Inltl.l IVAC TU ' 14JA1193 10fU93 ' ~;>. 72005 20 20 0 Area 8 . Mec:h Syat_ 'TI..ln & Inltfal WAC TU " FEI93 1l1Wt9J : . ". ................................................................................................................................... Monroe Cculty Detention 'acll Ity ~ Cowlty, Florlde PRIMAVERA PROJECT PLANMEl lCT DATE 19OEC91 IMI NO. 50 Monroe Ccgrty Detention FacUlty 16:21 ICIIED REPORT. line Iltlp by ectlvlty code START DATI 1AUQ91 '111 DATI 1.IUL93. DATA DATE 1811OV91 PAGe 10. 13 ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ..... ACTIVITY ORIG IEJI ACTIVITY OESCRIPTlOI SCHEDUlED ID M DUI I START FlIIS" ..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ..-..... ..... I Rechenlcal Syat_ Chec:k.out & lalMCI", 73005 2D 20 0 Area D . RedlSyst_ Tle.ln & Inltl.l IVAC TU 25FE193 24MR93 74005 2D 20 0 Area C . RedlSyst_ Tla.ln & Initial WAC TU 18MAR93 1W193 7'5005 2D 2D 0 Area E . Redl Syst_ Tle.ln & Initial WAC TII 1APR93 28API93 75500 10 10 0 IVAC Syst_ . Ftnal Tnt & lal....:e 29APm 12Mm 75600 10 10 0 Building 0 & .. Syst_ . VerificatIon / Checltout 13MA Y93 26MY93 77010 10 10 0 ChlorInate & FlUlh Drinking Water linN 29APR93 12Mm Electrical/Security Device Verification 71020 15 15 0 Ar.. A - Point to Point DevIce VerifIcatIon 14JAN93 3FE193 72010 15 15 0 Area' . Point to.polnt Device VerifIcatIon 11FEI93 3MAR93 73010 15 15 0 Ar.. D . PoInt to Point Device Verification 25FEB93 17MAR93 74010 15 15 0 A.... C . Point to Point Devlca Verification 18MAR93 7APR93 75010 " 15 0 Area E . Point to Point Device VerifIcation 1APR93 21APR93 FI... Protection Syst_ Flnel Test 757'00 2D 20 0 Fire Protection Syst. . Flnel T..Un. 29APR93 26Mm r ",Ity Syst_ Operational Tests ( 71010 5 5 0 Instl Security .Syst_ CClIIIpJter Equip a Ctl R~ 11FE193 17FE193 71015 , 5 0 load Security Syst_ PrOllr_ 1SFE193 24FE193 71025 15 15 0 Ar.. A . Saarlty Syst_ Oper.tlonal T..ts 25FE193 11MA193 no15 15 15 0 A.... . . Sacurlty Syst. Operational T..ts 4MAR93 24IWt93 7301' 15 15 0 Ar.. D . Sacurlty Syst_ OperatIonal T..ts 18MAR93 1APR93 74015 15 15 0 Area C . Security Syat_ Oper.tlonal Tests WR93 2IAPR93 7501 , 15 15 0 Ar.. E . Security Syat_ Operational Tests 22APR93 12MAm Security Syst_ Intllr.tad Tnts 76000 10 10 0 security Syst_ . Integrated T..t (st.rt) 13MAm 26MY93 76010 20 20 0 security Syst. . Integr.ted Teat (c~l) 27MAY93 24JUN93 Flnel P\n:h 77050 15 " 0 AlE lulldlng CclIIpOnInt PwdIout 27MAY93 17 JUN93 Otntr/ M o.onstrltlona\ aoooo , 5 0 rNnerlAE. D....tr.tlona & Final Wllkthru 25JUN93 1.lUl93 ( ~ I SECTION 00135 PROPOSAL FORM Bid Package No. 35 Carpentry & General Works BID TO MONROE COUNTY PURCHASING DEPARTMENT PUBLIC SERVICE BUILDING, CROSS WING, ROOM 002, 5100 COLLEGE ROAD, STOCK ISLAND, KEY WEST, FLORIDA 33040 BID FROM: R.J.C. & Associates, Inc. 5611 Dewey Street Hollywood, Florida 33023 The undersigned, having carefully examined the Work and Drawings, Specifications, Proposal, and Addenda thereto and other Contract Documents for the construction of: Bid Package No. 35 Carpentry and having carefully examined the site where the Work is to be performed, having become familiar with all local conditions including labor affecting the cost thereof, and having familiarized himself with material availability, Federal, state, and Local laws, ordinances, rules and regulations affecting performance of the Work, does hereby propose to furnish all labor; mechanics, superintendents, tools, material, equipment, transportation services, engineering support, and all incidentals necessary to perform and complete said Work and work incidental hereto, in a workman-like manner, in conformance with said Drawings, Specifications, and other Contract Documents including Addenda issued thereto. The undersigned further certifies that he has personally inspected the actual location of where the Work is to be performed, together with the local sources of supply and that he understands the conditions under which the Work is to be performed. The successful bidder shall assume the risk of any and all costs and delays arising from the existence of any subsurface or other latent physical condition which could be reasonably anticipated by reference to documentary information provided and made available, and from inspection and examination of the site. 05/19/92 CARPENTRY PROPOSAL FORM (ADD. 12) 00135- 1 :2IiTh.L LLb.. - ...---- ,~~= .,-- , J.\. ". ~ A. _.....1....- __........~tj RIC & ASSOCIATES, IHe 5611 DEWEY STREET HOl t YWOO[l, FLORIDA 33023 PROPO~A:r,. FORM Lt.1JTIlL Sum Base Bid Note: Items are 'furnish and install' where as specified in the Scope of Work. 1. Mobilization 2 . Bond 3. Sales Tax 4 . Submittals 5. Section 05810 Expansion Joint Cover Assemblies 6. Section 06100 Rough carpentry 7. Section 06200 Finish carpentry -(., " ~ , ,. \: ';, '>, applicable, $ 5,000.00 $ 2,980.00 $ 11,840.00 $ 2,500.00 $ 25,956.00 $ 5,040.00_ $ 144,810.00 7A. s~ctiori OBj06t~&~i~1 8. Section 10100 Chalkboards and Tackboards 9. Section 10160 Solid Plastic Toilet Partitions $ 8,820.00 $ 14,629.00 $ $ 2,924.00 $ 24,570.00 $ 2,218.00 $ 2,662.00 $ 30,154.00 $ 1,512.00 $ 6,615.00 $ 10. Section 1027~eess Flooring 11. ,section 10350 Flagpole 12. Section 10500 Steel Lockers 13. Section 10520 Fire Extinguisher Cabinets 14. Section 10550 Postal Specialties 15. section 10800 Toilet Accessories 16. Section 10900 Miscellaneous Specialties 17. Section 11480 Athletic Equipment tB--.--&eet ion 1.3 09-e-RtJ d i tJ t i oR-P-l:'~t-eeHen 05/19/92 CARPENTRY PROPOSAL FORM (ADD. 12) 00135 - 2 . --..- ,.,.-.....=~~~ f 19. Miscellaneous Items (use if work items cannot be categorized in items 1-18 above) $_N.C.. 20. Allowance - (240) manhours 6,480.00 21. Final Cleaning $ $ 4,000.00 TOTAL BASE BID, Items 1-21, (figures) $ 329,800.00 ---------- ---------- TOTAL BASE BID, (words) Tht:"ee Hundt:"ed Twenty-Nine Thousand Eight Hundced -------------------------------------00/100 DOLLARS 22. Owner option 35-01: Zone F Carpentry ~/ DEDUCT (Circle One) -------------------------------------------00/100 DOLLARS Owner Option 35-01, (figures) $ 39,000.00 ---------- ---------- Owner option 35-01, (words) Thit:"ty Nine Thousand --------------- 05/19/92 CARPENTRY PROPOSAL FORM (ADD. 12) 00135 - 3 I acknowledge receipt of Addenda No. (s) 1 thcough 12 C I have included pages 1-4 of the Proposal Form X , and attached the required Bid Security X , Lobbying and Conflict of Interest Clause X , Sworn Statement of Public Entity crimes_~, and Non- Collusion Affidavit ~heck mark items above, as ~~eminde~ that th~are included~ Mailing Address: R.J.C. & Associates, Inc. 5611 Dewey Stceet Hollywood, Flocida 33023 / Phone Number: Date: 8 June 1992 Signed: pcesident witness: l6f~ ~ (Seal) 00135 - 4 05/19/92 CARPENTRY PROPOSAL FORM (ADD. 12) THE AMERICAN INSTITUTE OF ARCHITECTS I RECEIVED AlA Document A310 "PR ? 7 1(lqi rl,f.C It ASSOflATFS, 'NI Bid Bond KNOW All MEN BY THESE PRESENTS, that we 'H~,. insert full n.m~ .nd .dd,~" 0' l~g.1 titl~ of Conl,octo') R.J.C. & Associates, Inc. as Principal, hereinafter called the Principal, and IH~,~ ins~'t full n.m~ and .dd,~" or l~g.1 I;II~ of Su'~tyl Employers Insurance of Wausau a corporation duly orgcll1!zcd under the laws of the State of Wisconsin as Surety, hereinafter called the Surety, are held and firmly bound unto (Here in~ert full name .and .1dd,e5~ or legoll .,tle of Owner) Board of County Commissioners of Monroe County, Florida as Obligee, hereinafter called the Obligee, in the sum of -----------Five Percent of Amount Bid------------------ Dollars ($ 5% ), for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. WHEREAS, the Principal has submitted a bid for (H~r(' insert full name, .lddrelil) and description of projectl Bid Package No. 35 - Carpentry N~w Detention Facility on Stock Island, Key West, Florida NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith contract with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain in full force and effect. Signed and sealed this 25th day of April 19 92 _fUHI"I' ;\l\ (~\H(,i/( (Wit ess) I Associates Inc. (Principal) ~ mt/e) . (Seal) IJffll1/ t/ iWd'r.d , (Witness) ura e of Wausau (Surety) ~'~G.1~ mt/e) Jack E. Fowler, Attorney-in-Fact (Seal) AlA DOCUMENT A310 . 810 BOND. ^'^ e . FEBRU^RY 1970 ED . THE ^MERIC^N INSTITUTE OF ^RCHITECTS, 1735 N,Y. ^VE" NW., WMHINGTON, D. C. 20006 1 ~ z o w a: Z a: lii Cl. Cl. <( r- o z (f) w o o r- z w 2 w ,,~ Z(f) - (f) 7:;: D.~ ~~ a: o ~ LL o a: w ~ o Cl. o :J ~ <( r- o z ~ ~ I r- EMPlOYERS INSURANCE OF WAUSAlJ A Mutual Company POWER OF ATTORNEY (FOR BID BONDS ONLY) KNOW ALL MEN BY THESE PHESENTS: That the EMPLOYERS INSURANCE OF WAUSAI J A Mutual ('ompan.v. a corporation dul~' organizpd and l'xisting undf'r the laws of the State of Wisconsin, and having its principal officI' in thp Cit.\' of \Vausau, ('ount~' of l\brathon, State of Wisconsin, has made, constituted and appointed. and does h~' thpsp pn'sents makp, constitutl' and appoint ____.,.__ CHARLES J. NIELSON~ JACK E~-EOWLER~ MARY c. ACEVFS~ JOHN S. HARRIS its true and lawful a ttorn Py in-fact, with full powpr and authorit~, Iwrehy conferred in its name, plan' and stead, to pxecute. seal. acknowledge and deliver ANY AND ALL Bill BONDS OR WRITTEN DOCUMENTS INVOLVIN(; Bill GITARAN TEES OR IN THE NATURE THEREAFTER __ _ _ _ _ _ _ __ and to hind the corporation thprehy as full~' and to thl' saml' extl'nt as if such honds Werl' sigl1f'd hy thl' President, sealed with the corporate seal of the corporation and dul.\' attpsted hy its spnetarv hpn.h~' ratif~'ing and confirming all that the said attorney-in-fact may do in the premises. This power of attorney is granted pursuant to thp following rpsolution adopted hy thp Board of Dirpctors of said Compan.v at a meeting duly called and hpld on thp IRth day of May, 197:l, which rpsolution is still in effpct: "RESOLVED, that the Presidpnt and any Vice Presir/pnt - eJpctivl' or appointivp - of EMPLOYEHS INSURANCE OF W AUSAU A Mutual Company hI', and that ench of them herphv is, authorized to execute powers of nttorney qualifying the attorney nnmpd in the given powpr ofattornl'~' to expcutl' on Iwhalf of EMPLOYERS INSURANCE OF W AUSAI) A Mutual Company bonds, undertakings and all contrncts of sllrl'lyship; and that any sperptary' or assistant seCTptary he, and that each or any of thpm hereby is, authorized to attest the eXl'clltion of an.v such powpr of nttorney'. and to nhach thereto the spal of EMPLOYERS INSURANCE OF WAITSAU A Mlltllal Company" "FURTHER RESOLVED, thnt tll(' signatuH's ofsllch officers and Ill(' sl'al of EMPLOYERS INSUHANCE OF W Al rSAtI A Mutual Company may be nffixed to any such powpr of attorrll'Y or to an~' cf'rtificate relating IIll'reto hy facsimile, and any such power of attorney or certificntp bparing such facsimile signatun's and facsimill' spal shallllP valid and binding upon the EMPLOYERS INSURANCE OF W AUSAU A Mutual Compr.n~' whl'n so affixpd and in tIll' futtHP with resppct to any bond. undertaking or contract of suretyship to which it is attachpd" IN WITNESS WHEREOF, EMPLOYERS INSUHANCE OF W AIISAI J A Mutual Company has caused these presents to bp signed hy the senior vice president and attestcd hy its assistant secretary. and its corporate seal to he hereto affixed this IS T day of ~<::~____.. 19__9.1 ,~-;-:.:~~- d':'o"o",;~ FMPLOYFRS INSURANCE OF WAUSAU A Mutual Company \\SE'Al)/ R ~ ~,~~~ x:'. ;;,,~, ~ Au.., A l~ Rill n. wym: R, J, Besteman ", Assistant Secretary STATE OF WISCONSIN ) ) ss. COUN1Y OF MARATHON) Executive Vice President On this 1 S T day of MARrH , 19 .elL , hefore l11e personally came - Bill D. Wymore . to me known. who heing hy me duly sworn, did depose and say that he is an executive vice president of the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company. the corporation descrihed in and which executed the above instrument; that he knows the seal of said corporation: that the seal affixed to said instrument is such corporate seal and that it was so affixed by order of the Hoard of Directors of said corporation and that he signed his name thereto hy like order. IN WITNESS WHEREOF. I have hereunto set my hand and affixed my official seal the day and year herein first ahove written. ~.a.~ Patricia A. Kleman NOTARY PUBLIC STATE OF WISCONSIN MY COMMISSION EXPIRES MAY 29, 1994 CERTIFICATE Notary Public /::~~.~';'.'.;".'.f{~;;\ {~/ 1I~'.~~ y) '~~:~::,;,:;~~li STATE OF WISCONSIN CITYOFWAUSAU )ss COUNTY OF MARATHON) I. the undersigned, assistant secretary of EMPLOYEHS INSURANCE OF WAUSAU A Mutual Companv. a Wisconsin corporation, do hereby certify that the foregoing and attached power of attorney. WHICH Ml1STCONT AIN'A V ALlDAT- ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK. remains in full force and has not heen rpvoked; and furthermore that the resolution of the Hoard of Dirpctors spt forth in the powpr of attorney is still in force. Signed and sealed in the City of Wausau, Marathon County, State of Wisconsin, this 25 th of April ___ . 19_9~. A. d 4-L t-;--:::-""'~ ~ {<<::.~~:.;;~ R. J, Besteman / l' ' \,~SEAl ~I ~~I day Assistant Secretary NOTE: IF YOU Ht\VE ANY QUESTIONS REGARIHNG THE VALIDITY OR WORlHNG OF THIS POWER OF ATTOHNE\. CALL TOLL FREE (ROO) R2fl-lflf11 <IN WISCONSIN. CALL (ROO) 472-004\} RJ5-4n2-1 990 .~ l'jl , ". ~ " 11 LOBBYING AND CONFLICT Of~R'L~!<ES'L CLAUS~ S~9~N ST~TEMENT U~DER ORDINANCE NO. 010-1990 MON-FJ2~~OUNT~~_LXLORI DA " RJC & ASSOCIATES, I INC. (Company) ff If warrants that it has not employed, retained or otherwise had act on its behalf any former County officer or employee subject to the prohibition of section 2 of Ordinance No. 010-1990 or any County officer or employee in violation of section J of Ordinance No. 010-1990. For breach or violation of this provision the County may, in its discretion, terminate this contract without liability and may also, in its discretion, deduct from the contract or purchase price, or otherwise recover, the full anount of any fee, commission, percentage, gift, or consid ration paid to the former County officer or em 'lee". Date: STATE OF FLORIDA COUNTY OF , BROWARD PERSONALLY APPEARED BEFORE J. TAYLOR who, his/her signature (name of provided above on this 23 HE, the undersigned authority, RICHARD after first being sworn by me, affixed individual signing) in the space ' day of ~_, 1992-. ~~~~ NOTARY PUBLIC Hy commlSSlon explres: PAMELA FRAZIER McRAE My Comm. Exp. 5-13-94 Bonded Thru SeMc:e Ins. Co. 07/25/91 LOBBYING AND CONFLICT OF INTEREST CLAUSE 00425 - 1 ,-' :.,~ .... .._......'---~----,..,..,..- --> ~!-~_.'.' ~~..::. :..'}~.~~.~'.'_~~'-t~J~:~~~~~~.:~~~;fr{c.~~~'~~~'..~~T~~~'''~!?!.~~~~~f_ -- . . ,tigJ2 .::~r;gJcj~\,l'~l..SJJ~\Jj i cJ~~I_ iJ:~ " I , RICHARD J. TAYLOR according to law on my o~th, and say that; __ of the city of HOLLYWOOD and under penalty of perjury, depose 1. ) I am RTCHARf)~. 'PAYLOR of the firm of & ASSOCIATES, INC. , the bidder r:laking the Proposed project described in the notice for calling for bids for COUNTY DETENTION CENTE~ and that I executed the said proposal full authority to do so; RJC for the MONROE Hi'.::h 2.) the pr~ces in this bid have been arrived at independently without collusion, consultation, communication or agreement for the purpose of restricting competition, as to any matter relating to such proces with any other bidder or with any competitor; J.) unless otherwise required by law, the prlces which have been quoted in this bid have not been knowingly disclosed by the bidder and will not knowingly be disclosed by the bidder and will not be knowingly disclosed by the bidder prior to bid opening, directly or indirectly, to any other bidder or to any competitor; and 4.) no attempt has been made or will be made by the bidder to induce any other person, partnership or corporation to submit, or not to submit, a bid for the purpose of restricting competition; 5. ) correct, upon the a'.varding the statements contained in this affidavit are true and and made with full knowledge that Monroe County relies truth of the statements contai ed in this affidavit in contracts for said project. STATE OF COUNTY OF FLORIDA BROWARD PERSONALLY APPEARED BEFORE ME, the undersigned authority, _ RICHARD J. TAYLOR Vlho, after first being SI-lOrn by me, (name of individual signing) affixed his/her signature in the space provided above on this 23 ________ day of APRIL I932~ ..,......~ ~~R-;~~tc'7l~ (~,.@.. PAMElA FRAZIEIl MeftAE Hy commission explres: :.: f'\JBUC e My Camm. Exp. 6-13-94 \~ ott: Bonded Thru ServIce Ins. Co. ......?!: f'" 11/20/91 NON-COLLUSION AFFIDAVIT 00430 - 1 ... ' _.::~i\Qc"!f""~'.''''!;~'' ~.?~~~~"",~:il7~~~L"~":.'~'~"l'y"""""lI~,,,,:-=-t'!,.~~i""V!':~~:"'1t1I~ ~:'!:';f"\r~'!"~,""""~'?"i":JI..'?ft~~..,.~~:.:."",,,."'{~~, ~~c'":":"'~ -t " .. , SWORN STATEMENT PURSUANT TO SECTION 287.133(3) (a), FLORIDA ~T~TYTEQ, ON PUBLIC ENTITY CRIMES THIS FORM MUST BE SIGNED AND SWORN TO IN THE PRESENCE O? A NOTARY PUBLIC OR OTHER OFFICIAL AUTHORIZED TO ADMINISTER OATHS. 1. This sworn statement is submitted to: MONROE COUNTY PURCHASING DEPARTMENT [print name of the public entity] -, by RICHARD J. TAYLOR, PRESIDENT [print individual's name and title] for RJC & ASSOCIATES, INC. [print name of entity submitting sworn statement) vlhose business address is 5611 DEWEY STREET, HOLLYWOOD, FL 33023 Employer Identification Number (If the entity has no Number of the individual ) . and (if applicable) its Federal (FEIN) is_ 59-1867103 FEIN, include the Social Securit:i signing this sworn statement: 2. I understand that a "publ ic ent i ty cr ime" a s de: ined in paragraph 287.133 (1) (g), Florida Statutes, means a ';iolation of any state or federal law by a person with respect to and directly related to the transaction of bus iness ',.;i th any public entity or with an agency or political subdi~ision of any other state or of the united States, including, but not limited to, any bid or contract for goods or services to be provided to any public entity or an agency or political subdivision of any other st.ate or of the united States and involving antitrust, fraud, theft, bribery, collusion, racketeering, conspiracy, or material misrepresentation. 3. I understand that "convicted" or "conviction" as defined In Paragraph 287.133(1) (b), Florida Sta~utes, means a finding of guilt or a conviction of a public entity crime, viith or without an adjudication of guilt, in any federal or state trial court of record relating to charges brought by indictment or information after July 1, 1989, as a result of a jury verdict, nonjury trial, or entry of a plea of guilty or nolo contendere. 4. I understand that an "affiliate" as defined In Paragraph 287.133 (1) (a), Florida Statutes, means: 03/02/92 PUBLIC ENTITY CRIMES (ADD. 6) 00420 - 1 '~~'~'\lrlr;jf~,~~,~;..... *'Tl"'~~ -1ft..' "'";"~?\;4;_"'.ITl,~""'l.~~r:.....I.;.t~,tI,.~\l~~" 5. 1. A predecessor or successor of a person convicted of a public entity crime: or An entity under the control of any natural person who is active in the management of the entity and who has been convicted of a public entity crime. The term "affiliate" includes those off icers, directors , executives, partners, shareholders, employees, members, and agents '.,;ho are active in the management of an affiliate. The ownership by one person of shares constituting a controlling interest in another person, or a pooling of equip~ent or income among persons when not for fair market value under an arm's length agreement, shall be a prima facie case that one person controls another person. A person ',.;ho knowingly enters into a joint venture with a person who has been convicted of a public entity crime in Florida during the preceding 36 months shall be considered an affiliate. 2. I understand that a "person" as defined in Paragraph 287.133(1) (e), Florida statutes, means any natural person or entity organized under the laws of any state or of the united states with the legal power to enter into a binding contract and which bids or applies to bid on contracts for the provision of goods or services let by a public entity, or which otherwise transacts or applies to transact business with a public entity. The term "Person'! includes those officers, directors, executives, partners, shareholders, employees, members, and agents who are active in management of an entity. 6. Based on information and belief, the statement whibh I have marked below is true in relation to the entity submitting this sworn statement. [indicate which statement applies.] X Neittler the entity submitting this sworn statement, nor any officers, directors, executives, partners, shareholders, employees, members, or agents who are active in the manage~ent of the entity, nor any affiliate of the entity has been charged with and convicted of a public entity crime subsequent to July I, 1989. __ The entity submitting this S\'iorn statement, or one or more of its officers, directors, executives, partners, shareholders, employees, members, or agents who are active in the management of the entity, or an affiliate of the entity has b~en charged with and convicted of a public entity crime subsequent to July I, 1989. The entity submitting this sworn statement, or one or . (I 03/02/92 . PUBLIC ENTITY CRIMES (ADD. 6) 00420 - 2 ~ 'of' " . /'" _,'. lJJ.....J~..~:'t).~I,:.~,~..'I.<~,.M..l' I,..~.~~.l... \""..~'~ ~. . /';' ,) (. 1 ~' gf ~:::. r~ .. ~~ ..." r . . more of its officers, directors, executives, partne~s, shareholders, employees, members, or agents who are active in the management of the entity, or an affiliate of the entity has been charged v!ith and convicted of a public entity criffie subsequent to July I, 1989. Hm.,rever there has been a subsequent proceeding before a Hearing Officer of the State of F lor ida, Di'v is ion of Admini stra t i ve Hear ings and the F ina 1 Order entered by the Hearing Officer determined that it was not in the public interest to place the entity submitting this sworn statement on the convicted vendor list. [attach a COp! of the final order] I UNDERSTAND THAT 'THE SUBHISSION OF THIS FORH TO THE COiiTR..;CTIHG OFFICER FOR THE PUBLIC ENTITY IDENTIFIED IN PARAGRAPH 1 (ONE) ABOVE IS FOR THAT PUBLIC ENTITY ONLY AND, THAT THIS FORM IS VALID THROuGH DECEMBER 31 OF THE CALENDAR YEAR IN WHICH IT IS FILED. I ALSO UNDERSTAND THAT I AN REQUIEED TO INFORl1 THE PUBLIC ENTITY PRIOR TO ENTERING INTO A CONTR1\CT IN EXCESS OF THE THRESHOLD AHOUNT PROVIDED IN SECTION 287.017, FLOR_IDA STATUTES FO~CATEGORY TWO F !I.NY CHANGE IN THE INFORMATION CONTAINED IN THIS rfoRM. .... J [Signatu\e1 Da te : k I \ STATE OF FLORIDA COUNTY OF BROWARD PERSONALLY APPEARED BEFORE ME, the undersigned authority, RICHARD J. TAYLOR [name of individual signing] who, after first being sworn by me, affixed his/her signature in the space provided above on this 23 day of APRIL , 19 92 ___~~~~ Yl/a&r. NOTARY PUBL'I:C Form PUR 7068 (Rev. ~-- 04/10/9 My commission expires: PUBLIC ENTITY CRIMES (ADD. 6) 00420 - 3 03/02/92 :,. c J'~-"=_"" c'._."'!:L,',. '.", _.,. ..... . c. . .".c-:..." ... _ ' ~;t . . '"._ ,,':.~. '. ~. ._\ ....-~..:, .. '~~"J!~_~~~~~~~~~~~~f~~~~~~~:~~~_~~~~ SECTION 00137 PROPOSAL FORM Bid package No. 37 Access Floo'ring, Resilient Flooring & Carpet j BID TO MONROE COUNTY PURCHASING DEPARTMENT PUBLIC SERVICE BUILDING, CROSS WING, ROOM 002, 5100 COLLEGE ROAD, STOCK ISLAND, KEY WEST, FLORIDA 33040 BID FROM: RJC & ASSOCIATES, INC. ~l DEWEY STREET HOLLYWOOD, FL 33023 (305) 987~8301 FAX (305) 985-8796 The undersigned, having carefully examined the Work and Drawings, Specifications, Proposal, and Addenda thereto and other Contract Documents for the construction of: Bid Package No. 37 Access Flooring, Resilient Flooring & Carpet and having carefully examined the site where the Work is to be performed, having become familiar with all local conditions including labor affecting the cost thereof, and having familiarized himself with material availability, Federal, State, and Local laws, ordinances, rules and regulations affecting performance of the Work, does her~by propose to furnish all labor, mechanics, superintendents, tools, material, equipment, transportation services, engineering support, and all incidentals necessary to perform and complete said Work and work incidental hereto, in a workman-like manner, in conformance with said Drawings, Specifications, and other Contract Documents including Addenda issued thereto. The undersigned further certifies that he has personally inspected the actual loc~tion of where the Work is to be performed, together with the local sources of supply and that he understands the conditions under which the Work is to be performed. The successful bidder shall assume the risk of any and all costs and delays arising from the existence of any subsurface or other latent physical condition which could be reasonably ant~cipated by reference to documentary information provided and made available, and from inspection and examination of the site. 03/11/92 RESILIENT FLOORING PROPOSAL FORM (ADD. 8) 00137 - 1 ~.i.==-::..__. flIG 8. AS.SOCIATES. INC. 5511 DlWFY STREET . jOllY/Non!, FLORIDA 33023 LumIL.l)um ease_Bid PROPOSAL_Y_9RM t Note: Items are 'furnish and install' where as specified in the Scope of Work. applicable, I $ 3, OCJtJ . _ I $ I, )D O. --- . $ 31 tJoo . .-:- i I I $ I,OOCJ.-- , $ , 1., 5"'08. - , $ q 2., ta1 . -- . $ Z2.j oot!>. - $ -r9- l 1. Hobilization 2. Bond 3. Sales Tax 4. Submittals 5. Access Flooring 6. Resilient' Flooring 7. Carpet 8. Miscellaneous Items (use if work items cannot be categorized in items 1-7 above) ..., TOTAL BASE BID, Items 1-8, (figures) $ 135 O~.- ====~===== TOTAL BASE BID, (~ords) _Ql-.l~ H~"'i)R.--'=~ AN~ ""HIQ.~ 1="lvF; -IHa.s~/~o DOLL~RS 9. OWllS!X--9'p~;ion 37-01:. Zone F Resilient Flooring & Carpet ~ DEDUCT (Circle One) Owner Option 37-01/ (figures) $201oOD. - ====-======== O'lmer Option 37-01/ (words) Ilu~Nry THouc:;.A,.JO DOLLARS 03/11/92 RESILIENT FLOORING PROPOSAL FOru1 (ADD. 8) 00137 - 2 ,~ ' .. \ . , " il . , "'\ ~ \ \ ( I J ~ I. I I . l . i \ \ A,: > . 't:~;~... ~ ~, 'j, I acknow ledge rece ipt of Addenda No. (s) 0"-' ~ 1T-n..'-1.. \ S I have included pages 1-3 of the Proposal Form____, and attached the required Bid Security , Lobbying and Conflict of Interest Clause , swor,n Statement of Public Entity Crimes and Non- Collusion Affida'vit (Chgck m.ar~ i t~rn~_above_-,-_~!:!_~min_der tha t theY-2re included.) Mailing Address: Phone Number: Date: 4/23/92 Signed: i \ RJC & ASSOCIATES, INC. 5611 DEWEY STREET HOLLYWOOD, FL 33023 (305) 987-8301 FAX (305) 985-8796 J. TAYLOR (Name) witness: 03/11/92 RESILIENT FLOORING PROPOSAL FORM (ADD. 8) 00137 - 3 THE AMERICAN INSTITUTE OF ARCHITECTS I RECEIVEr) AlA Document A310 ^PR ~ 7 19CJ/ PJ.c. & ASSOCIATES. iNf Bid Bond KNOW All MEN BY THESE PRESENTS, that we IHe-re inSf"rt full n,me and ~ddress or IIPg,' title of (ontuctor) R.J.C. & Associates, Inc. as Principal, hereinafter called the Principal, and IHt"re in\~rt full n,me and ..dd'E"H or leg,1 title of SUff"tyJ Employers Insurance of Wausau a corporation duly organ!~cd iJjider the laws of the State of Wisconsin as Surety, hereinafter called the Surety, are held and firmly bound unto (Here InSf'" full iiolme and address or le-g.J1 tille of Ownrr) Board of County Commissioners of Monroe County, Florida as Obligee, hereinafter called the Obligee, in the sum of -----------Five Percent of Amount Bid------------------ Dollars ($ 5% ), for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. WHErUAS, the Principal has submitted a bid for (Here insert lull name, address and description of project) Bid Package No. 37 - Access Flooring, Resilient Flooring and Carpet Ne~ Detention Facility on Stock Island, Key West, Florida NOW, THE R EF 0 R E, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such larger lImount for which the Obligee may in good faith contract with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain in full force and effecl. Signed and sealed this 25th day of April 19 92 Inc. - r Iii 11 R I , \ I ) dill I I f ,It (Withess) (Seal) ,), ')' fr/dj /" I //'1t f.(jf (Witness) I 10, s Insurance of Wausau (Surety) . ~~ f. '1-~ (Title) I Jack E. Fowler, Attorney-in-Fact (Seal) AlA DOCUM(NT A31' . BID BOND. ^'^ ~. FEBRU^RY 1970 ED . THE ^MERIC^N INSTITUTE OF ^RCHITECT5, 1735 N.Y, ^VE" NW" WMHlNGTON, O. C. 20006 1 ~ z o w cr Z cr ~ a... a... <( I- a z en w a o I- Z w 2 w C)~ Zt0 - en .......~. - III '[ Q..LL ~~ cr a ~ LL a a: w ~ a a... o :::::i ~ <( I- a z ~ ~ I I- EMPlOYERS INSURANCE OF WAUSAlJ A Mutual Company POWER OF ATTOHNEY (FOR BID BONDS ONLY) KNOW ALL MEN BY THESE PRESENTS: That thf' EMPLOYERS INSURANCE OF WA! 'SAil A l\1utual ('ompan~', a corporation dul.\' organizNI and existing unner thp laws of thp Statp of Wisconsin, and having its principal officf' in till' Citv of Wausau. Count\' of Marathon, Statf' of Wisconsin, has madp, constitutf'd and appointf'd, and dol'S 1J\' thf'se prf'sl'nts makl'. constitute and appoint .,..__...~. ---.C.HARLES J. NIELSON.. JACK.. E. FOWL ER.. ~R.LL........AC.E\l.Es.........JQHN S. HARR I S its trul' and lawful attornl'y.in.fact, with full pOWl'r and authorit~, hl'rl'hy confl'rrf'd in its twml', placf' and stf'ad, to I'Xl'cutl', seal, acknowledge and delivl'r ANY AND ALL BIll BONIlS (>R WRITTEN DOCllMENTS INVOIXIN(; Bill (;UARAN. TEES OR IN THE NATtTRE TI/EREAF1'ER _ _ . _ _ _ __ and to bind the corporation thereby as full~' and to tI", sam!' I'xtl'nt as if such honds WI'rf' signpd hy till' l'rpsidpnt, seall'd with the corporate spa] of thl' corporation and dulv attf'stpo h~' its sl'crP(ar~' Ill'n'h~' ratif~'ing and confirming all that thl' said attorney.in.fact may do in the premises. This power of attorney is granted pursuant to tlw following resolution adoptl'd h~' the Roard of Directors of said Compan~' at a meeting duly caliI'd and hl'ld on thl' lRth day of May, 197:\, which rpsolution is still in pffect: "RESOLVED, that the Prl'sident and any Vice Presidpnt - l'll'ctivl' or appointivl' - of EMPLOYERS INSURANCE OF W AlJSAU A Mutual Company be, and that each of them hl'rl'hy is. authorizl'd to I'xecute powers of attorney qualifying the aUorney named in thl' givl'n power of aUornl'Y to l',(l'cutl' on I'l'half of EMPLOYERS INSURANCE OF WAlJSAU A Mutual Company honds, undertakings and all contracts of surl'tyship: and that any sl'crptar~' or assistant secretary bl', and that pach or any of thl'm herl'by is, authorizl'd to aUl'st thl' l'xpcution of any such powpr of attornp~', and to altach therl'to thl' sl'al of EMPLOYERS INSURANCE OF WAllSAU A Mutual Compnny:' "FURTI/ER RESOLVED, that tlll'signaturps of such officl'rs and till' spal of EMPLOYERS INSUHANCE OF W AllSAll A Mutual Company may bl' affixl'd to an,\' such powpr of aUOrlll'V or to any' cprtificatl' rplating thl'rpto Irv facsimile, and any such power of attorney or cl'rtificatl' hl'aring such f,lcsimill' signaturl's and facsimill' spa! shall hl' valid [lnd hinding upon the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company whpn so affixl'rl anrl in thl' futurp with rpspl'ct to any bond. undertaking or contract of surf'lyship to which it is attach"d." IN WITNESS WHEHEOF. EMPLOYEHS INSUHANCE OF W AUSAU A Mutual Compnn~' has causpd tlll'sl' prl'sl'nts to bl' signed h\' the senior vice president nnn nttested hv its nssistant secretary, and its corporate seal to he hereto affixed this __~ day of ____~t18RCIj~______, 19----.91 l::'~~;'-"~::"~ ~i roll'Olf." t~ \' SE"AL // ~ '- '\':'.. ~" Ry ~ AU"t ,A: l~ 1';11 D. W,": R. J, Besleman ,/ Assistant Secretary FMPLOYFRS INSURANCE OF WAUSAU A Mutual Compnny ~'~~ Executive Vice President STATE OF WISCONSIN ) ) sS. COUNTY OF MARATHON) On this 1 S T day llf MARrH , 19 .9..L . hefore me personnlly carne Bill D. Wymore , 10 me known, who heing hy me duly sworn. did depose and sny lhal he is an execulive vice president of the El\lPLOYERS INSURANCE OF WAUSAU A Mutual Company. the corporation descrihed in and which executed thc ahove instrument: that he knows the seal of said corporation; thaI the seal affixed 10 said instrument is such corporate seal and that il was so al"fixed hy order of the Rllard of Direclors of said corporation and thaI he signed his nmne Ihereto hy like order. IN WITNESS WHEREOF, I have hereunto set my hand and nffixed my official seal the dav and year herein first ahove written. ~.t1.,~ Patricia A. Kleman NOTARY PUBLIC STATE OF WISCONSIN MY COMMISSION EXPIRES MAY 29, 1994 CERTIFICATE Notary Public _.<<;~~~~'.':t'~{~~;\ l~~?;;~~:~~!; j STATE OF WISCONSIN CITY OF WAlJSAlI ) ss COUNTY OF MARATHON) I. thl.' undl.'rsigned, assistant sl.'cretary of EMPLOYERS INSURANCE OF WAUSAlI A Mutual Company. a Wisconsin corporation, do hl.'rebycertify that the foregoing and attachl'd powerofattornl'Y, WHICH MUST CO NT AIN'A V ALlDAT- ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK, rl'mains in full force and has not bl.'en revoked; and furthl.'rmorl' that the rl'solution of thp Roard of Dirl'ctors set forth in the powpr of attornl'Y is still in forpp. Siltned and sealed in the City of Wausau. Marathon County. Statl' of Wisconsin, this __~~. of April . Hl~. A. d ~ ~ / 'j<< ~ R, J. Besteman day Assistant Secretary NOTE: IF 'lOll HAVE ANY QUESTIONS HE(;AHIHN(~ THE VALIDITY OH WORIHNG OF TillS POWER OF ATTORNEY, CALL TOLL FREE (ROO) ~2hI6f)lliN WISCONSiN, CALL (R0014720041) , , RI.'i.4222.1 990 ~ ;J ~ r -- . ;.-' }:oO'JB.Y HIGj\ND CONfLICT_OF Hi:t~"Rr:.:ST_~J:JMLE:"E Bji91UL~1'A T~tl.~li'!'._.lLNJ.l"EB__Q R PLHI\BQP,-.J.LQ_"--. --.9.1 0 - 122. Q tiQliRQ~_c::'9In{,L'( ,.JJ~9.BJJ2~ " RJC & ASSOCIATES, INC. " (Company) 11 ~;2rrants that it has not employed, retair1ed or otllerwise 112d act on i t.s behC1l f any [ ormer Coun t '{ of f icer or emp levee subj ect. to the prohibition of ::;c,ct.ion :~ or Ordinance 1'10.010--1990 or C\ny Count~y officer or emplo'./e0 in vlolClU.on of section J of Ordin,.'~ncl:: Po. 010-1990. For brcclch or violitLic'n of this provision the County may, in l.ts discr.ctioll, terminate t.his c:ont.r,:.ct. ,-,'ithout 1 .i 2 b i 1 i t Y an cl m i1 y a 1:~ () , i nil: :; d i 0:: C r p t ion, ,:1 e cl u c t f rem the con tract or pureh:1 ,:;? pr ice, cr ot hcr'-';.i s c rl?covcr, th e full ClnClU r,t of any [0"", commi.~;sion, percC'nLJcjc, qift., or consicler.i1tion p,~id tn the former county of r j ,'0' or e,," o\'''e'<~ure)__'''___~''_ STATE OF __FLoRIQ!L_.______ COUNTY OF BROWARD PERSOn,\LLY APPE1,PED BEFORE l-lS, thc~ undersi{Jnecl i:\uthority, RlCHARn_. _~'!',~~{LOR.._.___.._m._..___ ',.;ho, after first bei.nq SHorn by me, affixed hisjht"r siqnature (name of inclivic1uill signing) in the ~3pace prov ided obove on t~h i s~~_.._. day 0 f_.l\.J::'..RIJ~___._m_n ' J 9.92.. :f~~Cffl~...._,__.. NOTAPY PUBLIC PH comml.SSlon explres: PAMELA FRAZIER McRAE My Comm. up, 6-13-94 Bonded ThnJ Serva Ins. eo, 07/25/91 LOBBYIJ1G AND CONFLICT OF IN'I'EPE's1' CLAUSE 00<',25 - 1 f.:'~~~."'Pfl~" ...." ..... .~.~._r.~~f~:~-..,__:~~. ..~.;'....:.y;'}'7"T.,. .";7.~.i'Tn;r"r~.-:".'....--i~tl.~.:'.,;,y~'.~H:,'";~f'~~,~' I :--lI~~'~~-::""rl'''-'-f'' . ;--,!., ,"-1 ,.;.. .,,_;' ", .~.,;......~.:.":"....,."r-~.:!..I.-:.T:'!'ll''P,~:r~ '~""i...~:m~;.nr.,..', ~ -- . H9_I"l_~_~ gJ l1J~i9_n__l\f U._cl c.yj t: I, RICHARD J. TAYLOH_______ of U1e city of ___HO~YW~~______ according to la;..; on my oatJ" and under penalty of perjury, depose and Si",y tha t; 1 . ) I a m __~J~[~R!?__~"__'!'f\J'LQ~__~________ 0 f the f j nn 0 [ _RJ~______ _~_A~OCIATES, INC._______, the bic1cler making the Proposal for the pro j e c t de s c r i be din the not ice for call in g for bid s for N-';;~J1QNJ~QE__ ~~UNT~ DETENr!'};O~__F~~~_J;.;rT'p,nd th,-:'\t I executed the said proposal \,;i ~_h full authority to do so; 2. ) the pr ices in this bid have bE'en arr i ved at independently without collusion, consultation, commtlnjcation or agreement for t.he p~lrpose of restr ictinq competi tion, as to un}' matter relating to such proces with any other bidder or with al1Y competitor; 3.) unless otherdise required by law, the prices 'dhich have been quoted in th is bid ba ve not_ been knov! ing 11' eli sc losed by the> bidder and 'd ill not kno1,./ i ng 1 y be disc losed by the bidder and I,; i lJ not be knO'.,lingly disclosed by t.he bidder prior to bid openinq, directly or indirectly, to any other bidder or to any competitor; and 4.) no attempt has been made or 'dill be made by the bidder to induce any other person, partnership or corporation to submit, or not. to submit, a bid [or ~-_he P'Xl:-pO~,C of restrictin,! competition; 5. ) correct, upon the a'darding the statements contained in this and made with full knowledge 1t truth of the statements conta'n d contracts for said project. affidavit are true and /Vlonroe County relics in_hZid~nt "'~ ratu e of Bidder) STATE OF COUNTY OF FLORIDA -------- --_.__._~-_._-_.'--'---'------ BROWARD RIL 3, 1992 ._--_._-------_._-------~--- DATE PERSONALLY APPEARED BEFORE ME, the undersigned authority, RI<~ttARQ__~ TA1.LOR______________.___. 'd h 0 , aft e r fir s t be in q s \--to r n by 1" e , (name of individual signing) affixed hiS/her signature in the space provided above on this _~~________ day of ___ APIli~___________, 19__9-_2-. _~ ~4Ln~~/rz~ NOTP~~IC My commJ.SSlon PAMELA fRAZIER McRAE My Comm. Exp. 6-13-94 Bonded Tllru ServIce Ins. 00. 11/20/91 NON-COLLUSION AFFIDAVIT 004]0 - 1 . :j,l!"."'i!'~~~~.~~~~lf~~~~,'r,~':U......'""Yl"ii,l'..~.,.:-,..".,., '. "l;f' 17':-:~'i~l~,"':"_~....~:-:'tfr-":'.~,.: ';'"'~f"'.~VN,".r::-\": ~...:ow:-~"'G=-'''i'1 ~"".i,~~':;""~.qr~:,:, ":~_' ,~.". ~':?r. 7r'-':..~~~...,~~:r~~~i~I!...:tt~ ~ t . ~ SWORN STATEMENT PURSUANT TO SECTION 287.133 (3) (a) / FLORIDA STA-'ITJTES / ON PUBLIC ENTI'l'Y CRIl1ES ,. ~ THIS FORM MUST BE SIGNED AND SWORN TO IN THE PRESENCE O? A NOTARY PUBLIC OR OTHER OFFICIAL AUTHORIZED TO AmUNISTER OATES. 1. This sworn statement is submitted to: NEW MONROE COUNTY DETENTION FACILITY [print name of the public entity) i;< by RICHARD J. TAYLOR, PRESIDENT [print individual's name and title] for RJC & ASSOCIATES, INC. ______ [print name of entity submitting sworn statement} whose business address 1S HOLLYWOOD, FL 33023 ~~---- and (if applicable) its (FEIN) is 59-1867103 FEIN, include the 50,-::ia1 Sccl:rit}' signing this sworn statement: 5611 DEWEY STREET, Federa 1 Emp lcyer I den t i fica t iOi: ?iu::;t::er (If the entity has no Number of the individual ) . . 2 . I un d erst and t hat a " pub lie en tit Y c 2.- i me" a s de fin e din Pare,graph 287.133 (1) (g), Il.Qrid~J!,j'l.tjdtes, means a '/io::'e..tion of any state or federe..l law by a person with respe=t to and cl i rect 11' re 1 a ted to the transact ion 0 f bus i :.e ss ',.; i '-:, c. ny public entity or with an agency or political subdivisi6n of any other state or of th~ United states, including, but not li~ited to, any bid or contract for goods or services to be provided to any public entity or an agency or political subcli v is ion of any other state or of the Un i ted States and involving antitrust, fraud, theft, bribery, collusion, racketeering, conspiracy, or material misrepresentation. 3. I understand that "convicted" or "conviction" as defined i.. Paragraph 287.133 (1) (b), f~orida--"C;tat1d.tes, mea..s a. finding of g u i 1 tor a con vi c t ion 0 f a pub 1 ice n tit l' c rim e , ;'i i the r Hit.hout an adjudication of guilt, In any federa] or state trial court of record relating to charges brought by indictment or infor~ation after July 1, 1989, as a result of a jury verdict, nonjury trial, o~ entry of a ple~ of guilty or nolo contendere. 4 . I unc1e'rstand 287.133(1) (a), that an "affiliate" as defined Florida statute~, means: in Pa!"2ql.-2.ph . 03/02/92 PUBLIC ENTITY CRIMES (ADD. G) G0420 - 1 ,;.J~w...j5] -; An;.':.~:~~:~.~~-' ':;~~.~'. "?::r:::.::":~~;-rt.'~ ~~;;[ ~':~.;.~ I~~':~7.~ ~: ~;:.~::-~..-::::_:: ~:'-., _'.~ --;;;:.7~~:':~-':7~~~= '.7:~:~:::/:-,~?_~7:r:.:',:;::i :::;?::~~;7:;;S::", ': 1f;;T-~~'"1;~r:~:.~~7;;::;,~.~~~~~j , J I 1 5. RJC & !iSSOCtAlES, INC. 56! 1 DElVfY STREET HOLLYWOOD, n.OIlHlA 33023 1. A predecessor or successor of a person convicted of a public entity crime: or An entity under the control of any natural person ~ho is active in the management of the entity and who has been convicted of a public: entity crime. The t~erm "affili2te" includes those officers, directors, executives, partners, shareho Jders, employees, mer:bers, and agen t S "';:10 are active in the management of an affiliate. The c~~ershi2 by one person of shares constituting a cantroiling interest in another person, or a pooling of equi~nent or income a~ons persons when not for fair market va~ue under all a~mls le~gttl agreement, sh~ll be a prima fa=ie case t h 2.. ton e per son con t r.- 0 1 S 2. not h e:- pel'" S 0 rl . .~ De :- S 0 T1 \-: II e, knowingly e~ters into a joint venture with a pers~n ~hc has been convicted of a public entity crime in Florida dUl'ing the ;:receding 36 months shall be cons_~dereci a:t affiliate. tit 2. I understand that a "person" as defined in ?aragc.Gph 2 8 7 . 1 J J ( 1) (e), :" 1.9);" i d a_3 tat u_t e s, r,', e a n san y n a t u r i1 1 P e :::- son 0:- en tit y 0 r 9 ani zed II n de r the 1 a','; s 0 f a li ~r S tat e 0 r 0 f the (j nit e ;~: states with the legal power to enter into a binding contract and which bids or applies to bid on contracts ~u~ the provision of CjGc:1s cr services let by a public e;--!tic.y, c:- ~;hich ot_her;'Jise tr2nsacts or applies to transact busi~sss ~~.~t~~ a pub lie en tit), . The t e::: n:1 11 P e 2__ S 0 i1 !l i Y': C 1 u des tho s e c f f '. c'= "l,':3 , directcrs, executives, partne~s, shareholders, e~plcyee5, members, and age n t s \,:ho are act i ve in Pc. nagement. c fan en t i t~. . ~ t;::~ ,~~ 6. Based on information and belief, the statement which I have marked below is true in relation to the entity submitting this sworn statement. [indicate which statement applies.] 03/02/92 '. :... ~"'~~'I\'..~l;:,~'_~'='~;J.'Y""" ;'.' ,. ..".....~ --, .1'-.= -~.:-"'..",..,....I'Iii"l<'f".... ~ ~...~ ~: ,.,.,._'~fT);i ~;.' , ...1'~, Ie;! ,:r\(I;:J:j~'~'iJ",_ -':';'~?;f'!.; ,,/ Jl'~~~~.. :~i~~~r'!~; #if'{:;.~~'~~,~.::.Jii~;..I;~_..7:.~~;t"$~.~~'t-.~:-f~~ti-:P~\.- ;~';'~'I'Zf1~J~i~~~~~~*r~.;~,;1~ .-X__ He i tiler t:--,e ent i ty submi tt ing th i s s'.!orn sta tellent, nor any officers, di:-ectors, executives, partners, shareholders, employees, members, or agents ~ho are active in the n2~agerre~t of the entity, nor any affiliate of the entity has !-:ee:i charged with and convicted of a public entity crimes~tsequent to July 1, 1989. The entity subrr;itting this S','io-::n statement, or ene or more of its officers, directors, executives, partners, shareholders, eDployees, members, or agents who are ective i~ the management of the entity, or en affiliate of the entity has been cha:-ged with and convicted of a public eGtity cr12e subsequent to July 1, 1989. The entity submitting this sworn statement, er cne::: 0:- I Pl.:SLIC ENTITY C~nt-1ES (?,DD. 6) 0')420 - 2 ~ } :-,:i :. , :'-i ~< 1.< ;:~ ~ RJC 3. ASSOCIATES. INC 5611 OrWEY SlRf.El HOlLYWOOD rtORIlJi'. 13023 ~ more of its officers, directors, executives, pa~t~e~s shareholders, employees, me~be~s, O~ agents wt18 are 2cti~.:e i~ the management of the entity, or an affiliate of t~e e~city has bee n c h Cl. ::: 9 e d vI i t h and con v i c t e ci 0 f a pub 1 ice n t i. ::. y' c::: i::-. ,2 5 II b s e (1 u e n t t 0 J u 1 y 1 , 1 9 8 9 . E 0 \',1 eve r the 1:.- e r. 2. :; t E: e ~1 .J. subse:::lue:!t proceeding befo:::e a Heari:!; Officer of tr:e State of F 1 or ida, D i'v- is ion of i'.dmin is t:::a t ive Hear ings and ::;,e F i.na J Order entered by the Hearing Officer determined t~a::' i::. was not ill the pllblic interes~ to place t!1G entity SUbDi~~i~g ~his s~orn state~ent en the CC~~!~cted ve~dor lj_st. [a~t2=~ a CCC\: of the final order] .. ., f t'f I UllDEPST.'\UO TI!.\T 'I;n:: SUBlUSSIOU OF THIS FORr1 TO THE CC:;-=-?.\CT:!:~;G OFFICt:R FOR THE PL;rL~C FtiTIT"{ ID:::tHIF'ISD III P.~..p.AGH!\r:I 1 (':::::::: .".:=C;i:=: IS fOR TfIt\T pueu:c ;:~,:'ITTi Ot:LY ;,tlD,-~'::-".T TE:l.S FOPJ.l IS '::..::"=-~'~';:~.:::"::::::-: DECS;,:t3ER 31 Oi" THE C!\L>:~;ml\R YEi'.? Pi i'!:lICE IT IS FILS]. .:',::":;0 U,mERST;'..~m TEi'-.T I .'\?; RLQUIF.FD TO HiI"OR;'! THE PUBLIC EIIT:;:~":- ??:::O? TO ENTERIJlG INTO P. Cm';T?.~,CT IN EXCESS OF TEE TnRESHOLD l..HOl'::'.:' r?O-':I~ED IN SECTIOU 287.017, n=0RJDL_.$T.?l.TU'I' __ FO? c.".T:::GORY IN THE INFOPJ'IJ1.TIOtl conTAINED IN ,-!I' f'Ol fib 1992-_~__ STATE OF FLORIDA t. COUNTY OF BROWARD PERSONALLY APP2.11.::<.ED BEFORE: 112, the \..:ndersigned aut:1C:!:ity, RICHARD J. TAYLOR [name of individual signing] v,ho, a:ter first being s';,'c~n ty Tle, affixed his/her signature in the space provided above on t~is ~3____day of _~RIL 19 92 ~~~i3LJ7~ My commission explres: PAMELA FRAZIEPt McRAE My Comm. Exp. 6.13.94 Bonded Thru Service Ins. Co. ; Form PUR 7068 (Rev. 04/10/91) . 03/02/92 Pu3LIC ENTITY CRH:~S (ADD. 6) 00420 - 3 ~ ~..:, 'f;:'" "~:~"";7,~~of",~:,,,'..-r-:~.'\~;--'11;';:;I """1 "f-~~~i1~r~;":~7,- ~:.~ ',~,.l."," 1~~;~~,i7!Y7'';''~-:~;y7~.''''''!'r!7':'''7,~'t~7'~~7T,,' . '~-:-':TT!~~"P:.~'3.'.<~~~l''T.''G'; o SECTION 00139 PROPOSAL FORM Bid Package No. 39 Acoustical ceilings : i BID TO MONROE COUNTY PURCHASING DEPARTMENT PUBLIC SERVICE BUILDING, CROSS WING, ROOM 002, 5100 COLLEGE ROAD, STOCK ISLAND, KEY WEST, FLORIDA 33040 BID FROM: RJC & ASSOCIATES, INC. 5611 DEWEY STREET HOLLYWOOD, FL 33023 (305) 987-8301 FAX (305) 985-8796 The undersigned, having carefully examined the Work and Drawings, specifications, Proposal, and Addenda thereto and other Contract Documents for the construction of: Bid Package No. 39, Acoustical Ceilings ; \ '." and having carefully examined the site where the Work is to be performed, having become familiar with all local conditions including labor affecting the cost thereof, and having familiarized himself with material availability, Federal, State, and Local laws, ordinances, rules and regulations affecting performance of the Work, does hereby propose to furnish all labor, mechanics, superintendents, tools, material, equipment, t~ansportation services, engineering support, and all incidentals necessary to perform and complete said Work and work incidental hereto, in a workman-like manner, in conformance with said Drawings, Specifications, and other Contract Documents including Addenda issued thereto. The undersigned further certifies that he .has personally inspected the actual location of where the Work is to be performed, together with the local sources of supply and that he understands the conditions under which the Work is to be performed. The successful bidder shall assume the risk of any and all costs and delays arising from the existence of any subsurface or other latent physical condition which could be reasonably anticipated by reference to documentary information provided and made available, and from inspection and examination of the site. ( 03/11/92 ACOUSTICAL PROPOSAL FORM (ADD. 8) 00139 - 1 RJC & ASSOCIATES. INC 5611 DEWEY STREET llOLLYWOOD. FLORIDA 330?3 i I ~ ,; , ~ " PROPOSAL FORM Lump Sum Base Bid ,1 j 1 Note: Items are 'furnish and install' where applicable, as specified in the Scope of Work. 6. Miscellaneous Items (use if work items cannot be categorized in items 1-5 above) $ 3,000.- $ \. OOD. - . $ I. 5o~.- . $ Soo.- $ "'I, 4d". - $ ~ .i 1. Mobilization: J 2. Bond " 3. Sales Tax 4. Submittals 5. Acoustical Ceilings :! .1 TOTAL BASE BID, Items 1-5, (figures) :=~~~~~~::,;- ; .1 TOTAL BASE BID, (words) ::::>e\lG,...,+) 'Fl VE '.i 7 . Owner option 39-01: Zone F Acoustical Ceilinqs @)/ DEDUCT (circle One) Owner Option 39-01, (figures) :J:-l:~~~~~ Owner option 39-01, (words) ~\~\E:E:,...a. ~~4:11'\'~~ DOLLARS 03/11/92 ACOUSTICAL PROPOSAL FOm1 (ADD. 8) 00139 - 2 , ' " f7\ \~-~::) ~-- '1 A '..0.. 'j :i 1 I .; " -j , I ;.; -1 , , .1 " {-- , \' , -, .'i .1 .' j , "j 1 :t 1 .~ ! : I " J .: I . I ! /" I acknowledge receipt of Addenda No. (s) D t-.\" ---r14~~ ,~ I have included pages 1-3 of the Proposal Form ,and attached the required Bid Security____, Lobbying and Conflict of Interest clause ,Sworn Statement of Public Entity Crimes ,and Non- Collusion Affidavit____ I (Check mark items above, as a reminder that they are included.) Mailing Address: RJC & ASSOCIATES, INC. 5611 DEWEY STREET HOLLY~OOD, FL 33023 Phone Number: (305) 987-8301 FAX (305) 985-8796 Date: 4/28/92 Signed: PRESIDENT witness: (T~ le'A;;. / (Seal) 03/11/92 ACOUSTICAL PROPOSAL FORM (ADD. 8) 00139 - 3 THE AMERICAN INSTITUTE OF ARCHITECTS I AlA Document A310 Bid Bond KNOW ALL MEN BY THESE PRESENTS, R.J.C. & ASSOCIATES, INC. that we fH~re insert full n.ame and ,dd'e-S5 or legal ti,te of Contrictor) as Principal, hereinafter called the Principal, and Employers Insurance of Wausau (Here inserl full name and address or lega' litle of Su,ety) Wisconsin a corporation duly orgim!~cd under the laws of the State of as Surety, hereinafter called the Surety, are held and firmly bound unto (Here IOserl full name and address 0' legal tille of Owne,) Board of County Commissioners of Monroe County, Florida as Obligee, hereinafter called the Obligee, in the sum of ---------Fi ve Percent of Amount Bid---------- Dollars ($ ---5%--- l, for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents. WHEREAS, the Principal has submitted a bid for (He,e insert full name, add,ess and description of projecll NEW DETENTION FACILITY ON STOCK ISLAND, KEY WEST, FLORIDA, BID PACKAGE 39 - ACOUSTICAL CEILINGS NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty hereof between the amount specified in said bid and such larger ilmount for which the Obligee may in good faith contrilct with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain in full force and effect Signed and sealed this 1st day of May 19 92 (Witness) (Seal) /~)) I~ ~{el I: (tel (;t.fA / (Witness) Wausau (Seal) AlA DOCUMENT All. . BID BONO. AlA ~ . FEBRUARY 1970 ED . THE AMERICAN INSTITUTE OF ARCHITECTS, 173S N,Y. AVE" N.W" WASHINGTON, O. C 20006 1 :i z 0 w a: Z a: Lfj 0.. 0.. <{ ~ 0 z (/) w 0 0 ~ z w 2 w C) ~ ~ Z (/) - en OZ. I C. .L. ~ >- W z a: 0 ~ LL 0 a: w ~ 0 0.. 0 :i ~ <{ ~ 0 Z ~ ~ I ~ EMPIOVERS INSURANCE OF WAUSAlJ A Mutual Company POWER OF ATTORNEY (FOR BID BONDS ONLY) KNOW ALL MEN BY THESE PRESENTS: That the EMPLOYERS INSURANCE OF WAt~SAU A Mutual Compan~', a corporation dul~. organized <lnd existing under the laws of the St<lte of Wisconsin, and having its principal office in thp Cit~. of Wausau. Count~' of Marathon, State of Wisconsin, has made, constituted and appointed, and does hv thpsp prpsents make, ronstitute and <lppoint ____. CHARLES J. NIELSON, JACK E. FOWlER, MARY c. ACEVES, JOHN S. HARRIS its true and lawful attorney-in-fact, with full power and authority hereby conferred in its name, place and stead, to execute. seal, acknowledge and deliver ANY AND ALL HID HONDS OR WRITTEN DOCtJMENTS INVOLVING BID GUARAN- TEES OR IN THE NATURE THEREAFTER _ _ _ _ _ _ _ _ _ _ _ _ __ and to bind the corporation thereby as fully and to the same extent as if such bonds were signed by the President, seah'd with the corporate seal of the corporation and duly attested by its serretary hereb~' ratifying and confirming all that the said attorney-in-fact may do in the premises. This power of attorney is granted pursuant to the following resolution adopted b~' the Hoard of Directors of said Company at a meeting duly called and held on the 18th day of May. J 97:3. which resolution is still in effect: "RESOLVED. that the President and any Vice President - eledive or appointive - of EMPLOYF:RS INSURANCE OF W AUSAU A Mutual Company be, and that each of them hereby is. authorized to execute powers of attorney qualifying the attorney named in the given power of attorney to execute on behalf of EMPLOYERS INStJRANCF: OF W AUSAU A Mutual Company bonds, undertakings and all contrarts of suretyship: "nd that any secretar~' or assistant secretary be. and that each or any of them hereby is, authorized to attest the execution of any such power of attorney. and to attach thereto the seal of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company." "FURTHER RESOLVED, that the signatures of such officers and the seal of EMPLOYERS INSURANCE OFWAUSAU A Mutual Company may be affixed to any such power of attorney or to any certificate relating thereto by facsimile. and any such power of attorney or cE'rti fica te bearing such facsimile signatures and facsimile seal shall be valid and binding upon the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company when so affixed and in thE' future with respect to any bond, undertaking or contract of suretyship to which it is attached:' IN WITNESS WHEREOF, EMPLOYERS INSURANCE OF W AtJSAU A Mutual Company has caused these presents to he signed hy the senior vice president and attested hy its assistant secretary. and its corporate seal to he hereto affixed this 1ST day of MARCH . 19--.9.1 r:~~~';'-";;::-"'.. I.. ~\ I: (Olll'0Ito41, t.\ ~ l. -'- '. . \\ SEAli/ H ' ~... :;1 y AU,,,, ~ 1 ~ BOIl D. wym: R. J. Besteman -" Assistant Secretary EMPLOYERS INSURANCE OF WAUSAU A Mutual Company ~'~~ Executive Vice President STATE OF WISCONSIN ) ) ss. COUNTY OF MARATHON) On this 1 S T day of MARrH . 19 .9..L . hefore me personally came Bill D, Wymore , to me known. who heing by me duly sworn. did depose and say that he is an executive vice president of the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company. the corporation described in and which executed the ahove instrumeot; that he knows the seal of said corporation: thai the seal affixed to said instrument is such corporate seal and that it was so affixed hy order of the Hoard of Directors of said corporation and that he signed his name thereto by like order. IN WITNESS WHEREOF. I have hereunto set my hand and affixed my official seal the day and year herein first above written. ~a..~ Patricia A. Kleman NOTARY PUBLIC STATE OF WISCONSIN MY COMMISSION EXPIRES MAY 29.1994 CERTIFICATE Notary Public /~~~~:;':~:':.!~-~;;\ (~:~~:.:~~i~~~~) STATE OF WISCONSIN CITY OF W AUSAU ) ss. COUNTY OF MARATHDN ) I, the undersigned. assistant secretary of EMPLOYERS INSURANCF: OF WAUSAU A Mutual Company, a Wisconsin corporation, do hereby certify that the foregoing and attached powerof attorney, WHICH MUST CONTAIN A V ALIDA T- ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK, remains in full force and has not been revoked; and furthermore that the resolution of the Board of Directors set forth in the power of attorney is still in force, Signed and sealed in the City of Wausau, Marathon County, State of Wisconsin. this Is t of May __ .19~? . A d ~L .p~'i:: 'j ~ f'C'.:'~"'~ R. J. Besteman ;- , \ SEAL ,I ~, ,~I day Assistant Secretary NOTE: IF YOU HAVE ANY QUESTIONS REGARDING THE VALIDITY OR WORDING OF THIS POWER OF ATTORNEY, CALL TOLL FREE (800) R2h-lhhL (IN WISCONSIN. CALL (800) 472-0(41) RI5-4222-1 990 l :',}' M ~. , )., :,1 ~ ."'.. R' . ;>t. I) 1. I) ;:-!_C}])J i J. ~_; G l~~~i__~_~_~I_~~-~_=~_-_~ ~_l~~_k~_l- ~; T Ll~~J::.) J_C j.J ~_\.:d~.,-- ~ S "li.!2JW S TAT E):(,1:l:L't.-_ll.t:_Q~E_QR DIN AN C E NO. 0 1 0 - 1 9 9 0 HONRQ~__COUNTY, FLORIDA " RJC & ASSOCIArES, INC. (Company) " " ~arrants that it has not e~ployed, retained or othe~~ise had act on its behalf any for~e~ Co~~ty officer or employee s~bject to the prohibition of Section 2 of Ordinance ~o. 010-~990 o~ a~v County ;fficer or e~?loyee i~ violation of section J of C~dina~~e No. 010-1990. For b~each or violation of this provisio~ t~e County may, in~its discretion, terminate this contract ~it~out liability and may also, in its discretion, deduct fro~ the contract or purchase price, cr other~:ise recover, ttle fc~l 2~c~~t of any fee, commissio~, percentage, gift, or considera~ion aaid to the former County 0= fieee c" "plcyee" / Signature) STATS Ot FLORIDA COUl'ITY O? _t1R<;MAlliL----------- PERSONALLY APPEARED SE?OaE M~, the undersigned :authority, RICHARD J. TA.YLQR ,,:ho, after first being SHorn by ,,'2, af:ixed his/her signature (naDe of individual signing) in the s~a=e provided above on this 28TH day of APRIL 19 92. ----- WnLI.. .../~~ ~(!&-. NOTARY PUBLI My co~rn~SSlon exp~res: 07/25/91 LOBBYHJG ;'_~;D COlifLICl' OF IN'!"'EEEST CLl-.USE c' () :, 2 S - 1 ~:.~__~:t!_ ~:_~~~ _~!d~:~~~.~~~~4~T~~ ~~fI~t~~'?"..~~;~~ ~/~}:'I~ ~~.~' ~';.'f~t::~ ~.. '?:'..~~}~:.,;...-~~:?!.:~'~~:.>.~":;?~~;.~.~F~~..r~~~.::~~!2~~~~: ~Jo:;~~ :~ :."::.5_~;'~?-'~~/ ~'l ':".,. "1 , ~ :'i 1~ ~ ~ ~ t ( ! " . j i; 11 SWORN STATE~ENT UNDER ORD~NANCE NO. 010-1990 HO~~OE COUNTY, FLORIDA RJC & ASSOCIA~ES, INC. (COmpany) I " warrants that it has not e~ployed, retained or other~ise had act on its behalf any forDer County officer or employee s~bject to the prohibition of section 2 of Ordinance ~o. 010-1990 or a~y County officer or e~?loyee i~ violation of Section J of Crdinance No. 010-1990: ~or ~~each ~r viclat~on of t~is provisicn,tte County may, In?lts Clscretlc~, cerrnlnate thIS contract ~lt~ou~ liability and may alse, in its discretion, deduct frc~ t~e contract or purchase price, cr other~ise recover, the f~:l a~c~~t of anv fee, commission, perce~t2ge, gift, or considera~io~ aaid t t.;;, r- r m p y- CO" ,.., ~ -J 0 ~ f' i ,- -'" ,- 0 ~ ' D 1 C \' ""' e 11 o n_ 0 '._ ~..c" _u~-_ - ......' / Signature) 11 11 IL 28, 1992 STi\TS Of' FLORIDA COUNTY OF __BROWARD PERSO!.JALLY APPEARSJ S::::rO:?E HS, the unders gned ~2.uthor it::', --- RICHARD J. TAY1QR ,,:ho, efter first be ng S'dorn b'l "e, af:i>:ec. his/her signature (na~e of individual signing) in th~ s~ace provided above on this 28TH da'! of APRIL '9 92. -- c/l,~ J~:" '-h;~ tWTARY PUBLI My co~rnlsslon explres: 07/25/91 LOBBYI:iG P;O CON?LI':::i' OF Hi'!:EEEST CLf..USE C. G ~ 2 5 - 1 ~~~_ ~~~~~ .~1t.:~_t4~_~~'4["~~T:T'=;~:~-j.~~:~~-::~~ ~~?~;-::'~~l~~ ?:'..::?~:.::!~~?I.:~'~~:~'-~=~~~'~~~:'~~~~:}?:,:~~ 5~?-~:~.::: ~:5:':, :~::~:_:;,.~~~ . ., (I) I I RICHARD J. TAYLOR according to law on my oath, and say that; of the city of HOLLYWOOD and under penalty of perJury, depose 1. ) I am RICHARD J. TAYLOR of the f irn e: RJC & ASSOCIATES, INC. , the bidder making the Propos=.l for the .fyro~ ect descr ibed in the not ice for ca 11 ing for b ids fer NEW MONROE COUN D TENTION FACILITY Cl"d that I executed the sa id proposel ',.: i th full authority to do so; 2.) the pr~ces in this bid have been arrived at independently \vithout collusion, consultation, co~nunic2~ie:t or agreement for the p~rpose of restricting co~petition, as to any matter relating to such proces with any other bidder or w~t~ any competitor; 3.) unless otherwise required by law, the prices wnlcn have been quoted in this bid 11ave not been knowingly disclcse~ ~'.' t~1e bidder and will not knowingly be disclosed by the bidder end will not be knowingly disclcsed by the bidder prior to bid c;en:~g, directly or indirectly, to any other bidder or to any cc~petitor; and 4.) no attempt has been made or will be made by t~e bidder to induce any other person, partnership or corporation ~~ S~b2it, or not to subrni t, a b:c for tl:'2 p'Jrpose of res tr lct i ng competition; 5. ) correct, upon the a'.vard ing the staterne~ts contained in and 'made ~ith full kno~lejge truth of the statements cont contracts for said project. this affidavit are tr~e and tha t Honroe Cour,~ ': r s: =- i es in this affi-:e:.';i~ 2-~: STATE OF COUNTY OF FLORIDA BROWARD of Bic'c'2r) PERSONALLY A?P~ARED BEFORE MS, the undersigned a~~~ority, _ RICHARD J. TAYLOR "lho, after first being s'..:crr: ty ?e, (name of individucl signing) provided above O~ t~is 19 92 . ~~~~ PAMELA fRAIlER McRAE NOT AR Y ;,; g L.L C My Comm. Exp. 6-13-94 Bonded Thru SeIvIce Ins. (h, affixed his/her signature in the soace 28TH day of APRIL My commlss~on expl~es: 11/20/91 NON-COLLUSION AFFIDAVIT C'J<;]O - 1 r.:~ .: _~_ ":"~~~~r:!_"3!_~r.~~~~>~-:V!.:~!~~'J?:~~~:~~'~~~r:~~'~.'""~:'--_T-??:-~~'~~~~ -~'_' :\~ ',r: .~~~~~_'t:~~~:~~/:_~2~~~,~~~t~'~::'?:.'!'!~:~~~!~~.!?:::E::~?~~~'~-Y-~:-2~~~ - . . SWORN STATE1-1ENT PURSUANT TO SECTION 287. 133 (3) (a) , FL9RIDELJ?_Tj\..J'~-LTES, ON PUBLIC ENTITY CRDiES THIS FOR...'{ MUST BE SIGNED AND SWORN TO IN THE PRESENCE Or' A }10TARY PUBLIC OR OTHER OFFICli\L AUTHORIZED TO ADHINISTER Ol\'rES. 1. This sworn state~ent is submitted to: _M~ COUNTY PURCHASING DEPARTMENT [print name of the public entity] by 8lQ[ARD ~. TAYLOR, PRESIDENT [print individual's na~e and title] for RJC & ASSOCIATES, INC. (print name of entity submitting sworn state~e~tJ whose business address is HOLLYWOOD, FLORIDA 33023 - 5611 DEWEY STREET, ancl (if applicable) it.s Federal Elnployer Idelltificatic:-:. ~i~~ce:- ( FE IN) is _-59=18fi11Q3_______________ . ( 1ft he en t i :. y :-, a 0;, no F2IN, include ~he Soci.al SecLl'i.tj' Number of the ir:ci.:':i:::L':21 signing this s~orn state~ent: ) . 2. I understand that a "publ ic ent i ty C1- ime" as ce f i :--,s::: .:..n Paragraph 227. 2-JJ (1) (g), I')-,-ol'id~9.tCl!utg..?" means a ';ic:'?tio!", of any state or federal law by a person with res~e=t ~o a~j c1 i rect ly re 12 ted to the t r 2.!tsact ion 0 f bus i !',e s s ,,~~.. z: ny public entity or with an age~cy or political subdivision of ~I1Y other state or of the u~ited states, includi~g ~~t not li~ited to, ~r~ bid or contract for goods O~ services tc be pr-ovic1ed to any public er.tit:l ::Jr an agency or pe,l:':::i.cal subdivision of"' any other state or of the United S~2tes and involving antitrust, fraud, th€~ft, bribery, cO}_~']5:Ci1, racketeering, conspiracy, or ~aterial misrepresentatio~. 3. I understand that "convicted" or "con\(iction" as def::--,ed In Paragraph 287.133(1) (b), Florida statutes, means a fir.ding of gu i 1 t or a COil.v ict ion of a ptlbl ic entity cr irne, !...~ i:.h C~ Hit_hout an adjudication of guilt, in ar;y federal- o~ state trial court of record relating to charges br::Jug~t bv indictment or- infor-~ation after July 1, 1989, as a r-es~lt a~ a jury verdict, nonjury trial, or entry of a plea of g~iltj or nolo contenc1e~e. 4 . I c. n d e,r s tan d t 11 a tan " a f f i 1 i ate" as de fin e d l n ? a ~ 2, ~ r 2. ~ h 287 . 13 J ( 1) (a), flor..lda__St_a tutes, :.,eans: 03/02/92 PUBLIC ENTITY CRIMES (ADD. G) C,Ct,2J - ~ , :':1~~_'?~ -; J?7_:.:.:.~~,'""r;'1":: ;~~::'_ :r;:r::;.:'.';:_r:::-~:;~'~ :'"..i;r ~:~~~ .-:~ ...~,~; - . .__;-r:::~-:..-:yo."'(:_:: :~h. - ..7:'-:~;.~-..~~,=.:.-~~;_~.=:~.-~;;~;..-~.~72;7;:-:...:<i._:...~:Z;:::-~.~:T.=::~~. ~;;T~~; ~ ~ ~~i~ .f~~7~;:::~~~'.~-~;:~~ 1 1 ~ 5. R.lC &. ASSOCIAit\ IliC 5611 DEWEY SIfI[ET HOlLYWOOD, FlORIDA 33023 1. A predecessor or successor of a person convic~ej of a public entity crime: or An entity under the control of any natural person ~ho is active in the rnanag~ment of the entity and who ~as been convicted of a public entity crime. The terii1 "a.::ili~te" includes those officers, directors, e>::ecutives, ~;:::rtn€rs, sharehqlders, employees, neDbers, and c.gent.s "';,10 ere active in the manage~ent o~ an affiliate. The c~nership by one person of shal-es constituting a co:',t:::-::llling interest in ano~her person, or a pooling of eq~i;sent or income aDong persons when not for fair market va~~e under an arm's length agreement, shall be a prima facie case tJ,a ton e per son con t r- 0 1 S 2. Ii 0 the r per s O;l , .'^.. ':: e :- so:: i'; h 0 k n 0\-1 i n -j 1 Y '=, n t e r sin t 0 2. j 0 i n t v e n t u r e \y i t h a r:- e :- S 0;l T..; h 0 has been convicted of a p~blic entity crlme in Flc:-id2. during th~ t")!~ec:~c1Lng 36 months shall be consiie:-ecl a,l affiliate. . 2. I understand that a "p.??:'son" as defined in =='a:-ag:.i:\ph 2 8 7 . 1 3 3 ( 1) (e), 1"LQ_r i d a 0 t d_l!..J::_e s, n e a n san y n a t 1..1 r a 1 != e r- son 0 r entity organized under the la~s of any state or of ~he united states with the legal power to enter into a binding contr-act and which bids or applies ~a bid on contracts -~- the provision of goods or sc::r'Jic'2s let by a public e;-,=--=-ty, or which other~is'2 transacts or a~~lies to transact b~sin~5s ~ith a publil~ ent.it':l. The t<:::nl "Person" ipcludes those =:=~cers, directors, executives, pa:-tne~s, shareholders, e~~lcyees, members, and agents who are active in man~gement c: an entity. ~ _Oll' 6. Based on information and belief, the statement whic~ I have marked below is true in relation to the entity submit~ing this S',-lOrn state:t,ent. [inc:icClte ,,-,hich st.atement applies. J 03/02/92 , ...... "", ~ _.r.l.. -\,. . .... ., ....~.~f . ~_ Neither the entit_y submitting this s'...'orn state:c:e!lt, nor a!lY officers, di:-ectors, exec~ti~es, partners, sh2re~olders, employees, members, or agents who are active in the ~anage~ent of the entity, nor any cif;::iliate of the entity n2S tee:l charged with and convicted of a public entity crimes~t5equent to July 1, 1989. __ The entity subrr;itting this S','lOrn statement, 0:- one or more of its officers, directors, executives, par-tners, shar-eholders, employees, members, or agents who are aC~lve in the management of the entity, or an affiliate of the entity has been char-ged with and convicted of a public enti~y crime subsequent to July 1, 1989. The entity submitting this sworn statement, ~- one or <<I PUGLIC ENT2:T'{ c!UI-ms U~DD . 6) O':;~20 - 2 ":\~'n~('.>j:,,,,:'-"irjr.:?':;r.::l"";'iiir.;(':.,:._""~ ."'F""'==~.~':~' , .l\~~~ ('..,et,.~in:..1:....'f;.'.<,I.~;I,~'~'~'fl'....:i;~!',"(,~!,'f..tt-.xfJ0!.i:.~~~,,1...:,~.tl,,;~f~ ,.:f.,1'j,-.~..\o., "i1,....} ,\ ......, ~ ~'. ..,..,.tr!!'S'mY.l.. .,~. ~..., "~f,'t'~ . .,_, ..' _ ." '-r , . " '1 Ir- y ."(' ..,' ... .~,,"Y' H'.~t. ,-.:-;~P'J'ii~~.l>'f.:;'~~-).,<,,;'ir~.,it: - , ~ ~. ('. I_:~ RJC & ASSOCIATES. INC, 5611 DEWEY STREET HQLLYWOOO. FLORIDA 33023 " more of its officers, directors, executives, ;a=tners, shareholders, emplojees, ~e~bers, or agents who a=e 2cti~.:e in the management of the entity, or an affiliate of ~~e encity has bee n c 11 a r 9 ed"" i t h and con vie t e d 0 f a pub 1 ice n ::: i ": Y c r i;.. e sub s e que n t to J u 1 y 1 , l ') S 9 , H 01" eve r the 1" e r.2. :=: :c E e n a subsequent proceeding befo=e a Hearing Officer of the State of F lor ida I D i~v' is ion of ,z'.d",ir, is tra t i ve Hear ings and ~,:e F ':.na 1 Order entered by the Hearing Officer determined t~a::: it was not in the public intercs~ to place t110 entity sct~i~~i~g this s:{or~ statemeT1t Cf1 the cC~~.I~cted vendor li.st. [2~~~=~ a cop~~ cf the final crde~J . I UNDEP.STA~ro THXr THE SUDl-!ISSIOi'l OF THIS FOPJ1 TO TH:': CC:;;:-?'.:'..CTI;rG OFFICi::? FOR THE FC;B::.oIC EUTIT'L ~=:;::::irTIFIED HI F!..FJ\G!D\PH 1 (=::;:::) r.3C'~:::: IS FO? TH1.T PIJBLIC E:::TIT'i O:!L'i i,i:Q ,T!Li\T THIS FOPJ.j IS ...._~.,~:::= '-Ti-:~~00G;: DECE1'12ER 31 Of' THE C.'\LSim!'-.R Y:E>? It1 \'lH:!:CH IT IS FI LE~, _ .;:C.LSO UNDERST.;',.:'JD THAT I ~'1 REQUIPED TO IHF0R11 THE PUBLIC ENTl:T'~' ?RIOR TO ENTERn~G INTO 1\ C01:--:'?~'\CT IN E;~CESS OF THE THRESHOLD P.._l~Ol'!;'.:' P?D\~IDED IN SECTION 2 S 7 " 017, F!ol2RIJ)I._,'2-'I2J----'-!.'l~~ FOR CAT:Lr.:.GORY 'n:-::-' CF .:'.::',: C~L'..~lGE IN THE INFORHATIOIl CO!:';.'iU:iED r:~ 1'1-< _ FOR!'. ----------- 2 STAYE: OF FLORIDA COUNTY OF BROWARD PLRSONALLY APPE.;:'SED BEFOR:~ ;.;S, the undersigned au'.::.hc:city, RICHARD J. TAYLOR [name of individual signing] ,,:ho I aftF~r first be ing s',:srn by De, affixed his/her signature In the space provided above on '.::.his 28TH day of APRIL Yne& My commlSSlon expIres: PAMELA FRAZIER McRAE My Comm. Exp. 6-13-94 Bonded Thru ServIce ,... Cll. t\; , Form PUR 7068 (Rev. 04/10/91) . 03/02/92 PU3LIC ENTIT"::' CRIHES (fI.DD, 6) (-::;';20 - 3 ~ :~. .~w..;_.~..~. ...r:.~~...::?]f.~l:e<;:r;.-r.~~fTV~, :......1. J!;'~~.t ~-'TJ".;~t~~~..:r~~~::-.~;:~mY7t.~"!""" ...-:.1-~'3, }~.:.rl.r,,~.;;"'1~'~tr8~1-IJ:'::':'~.~;'?f.ii'7:~:.'-:O~.~!':!~~,lj~~:~ t'f.l'.~l': ..~~.~ .~ - ::~;:~ :;~~-?;~P:_~7;:~~tr~i'~ ~ ,;;r.....Jt..".,~~l\';V,...~~W---', ,r~"'\I..,,",....,r'i.,~.. ~.~,::Ji4,)~",-.., _ ,,';ti_,,:.... ,.J t.....~~...J~~=>>tt;tii~~t~... RJC & ASSOCIATES. IHC, 5611 OEWEY STREET 11(11' YWOOO, FLORIDA 33023 VOLUNTAR\ ALTERNATE BID REVISED (ADD. 12) [lEDUCTIVE PROPOSAL FORM 10: Monroe Coulty Purchasing Department Attn: Mr. D~ck Ccfnr, Director of Purchasing Bidder hereby states tllat separate, distinct and stand-alone bids have been submitted rr the following bid packages: 1 . B id Packa9-e_N~ --1iUWl~~ 1t 3i__ ___ __~~fL~ :?25"' _________ -!)~~~-~l- ------ k11V\~t:~ '* .3 ~ Qe~cription 4-W<'v.v'\ ~lC\~ I ~ Ar0:/1 ~~ CA~6N~t f\Nfj ~SpJl'A.,I\L. WoR.ks ~S~ Jl.llQf1;'1' 1(E~: Levrr- A...;! CA~ AC..o\1 f,.~ utl\L.. 0;; I ~~j l1;::eI1} 2 . 3 . 4 . 5. 6. 7. 8 . 9. A t the option of the O,mer, and if the bidder is awarded more than (1) bid package, bidder hereby offers the following DEDUCT proposal peree-R-t=-a~prices, for the Owner's benefit. -t f.--4:--h e O'.JfieF tWares--e.i:-d s-eft----:i:-to em s dedB€-'I=eEi-4rom the base--lr.i:-as--eF- enoh .:l bev-e, "6- m.:lY be bid p.:lcJc.:lge. -a-eave, % Ill.:l y---be bid p~e-:- .:lbove, ~ m.:lY be bid p.:lcJc.:lge.- ~e, "6- m.:lY be bid p.:lcJc.:lge. .:lbove, "6- m.:lY be bid p.:lcJc.:lge-:- I- f--4:.}:}.c QT,;n C F .:l V.:lres--e 1:-4 s-en--i--t:-ems lie4uet:e-4---E-rom the base--hids of eaoh -f+-t,he---ewn e r .:l \/.:l res- -b Hi ~T--t) IT-it:em s d-(~a-ucted frem the ba-se-l:r.i:B:s 0 f eaoh ~t-~ the Owner .:lW.:lros--b.i:-ds-ef'l~ffiS deduet:€l---4rom the ba-s-e-hMs-e-:f-e-aoh :[€--t:-he-Gw-ne r .:l wa-ra-s--bi.d-=-.---eft---i-:E-ems d"'~due-t:e-€l-----f-re~l:s~-b-ias- 0 f ea eh __ * -lkJ'~~lO"';~ ~,(),. I~"I~ 15.f.)~ ~l OS/21/92 I - ADDENDUM NO. 12 p.../J :;~ fJ! PAGE - 5 I f the Owner awards bids on items _2.AAi"-.:L____ (from 1 isting above), ;;~9~ 1)0LLl~R~ may be deducted from the sum total of -the base bids of the listed items. If the Owner ay;ards bids on items Z+-~A"d '1--(from listing above), gS:mO. ~ . DOI"L~BB. may be deduct_ed from the sum total of 1::.he base bids of the listed items. If the Owner awards bids on items ~ 2.+1,tw~(from listing above), ;;~AOO 'DOL~M-l? may be deducted from the sum total of the base bids. of the Tisted items. If the ownerawarc1Sbids on ifems. (fromlistThgab6ve), .s.___-'-__--------'DOt.k~9. maybe deducted from the si.llT\total>ofthe base bids of the'listedjtems. If the Oymer aYlards bids on items (from 1 istingabove) , .s. DQL.LA~maybe deducted from the sumdtotalofthe ,base bids of the listed items. If the o...,11er awards bids on items (fr()mli~.tiI1gabove) , $ --J2QJ;..LARSmaybe deducted fron) the sum. tota lof dtlie base bidsof<the>listeditefus. Bidder/Company RJC & ASSOCIATES. INC. 51111 OEWE Y :mm. r HOLtYWOOn, FLORIDA 33023 Mailing Address: ------.-.---.------- ----------- Phone Number: 305 - "ttp')-~'3tJl Date'_~/~L-. signed: Viitness: ?J2. rsl 'H~,-r-r -1-~ (Seal) OS/21/92 ADDENDUM NO. 12 PAGE - 6 THE AMERICAN INSTITUTE OF ARCHITECTS . AlA Document A201/CM CONSTRUCTION MANAGEMENT EDITION General Conditions of the Contract for Construction THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH AN ATTORNEY IS ENCOURAGED. 1980 EDITION TABLE OF ARTICLES 1. CONTRACT DOCUMENTS 8. TIME 3. OWNER 9. PAYMENTS AND COMPLETION 10. PROTECTION OF PERSONS AND PROPERTY 2. ADMINISTRATION OF THE CONTRACT 4. CONTRACTOR 5. SUBCONTRACTORS 11. INSURANCE 6. WORK BY OWNER OR BY SEPARATE CONTRACTORS 12. CHANGES IN THE WORK 13. UNCOVERING AND CORRECTION OF WORK 7. MISCELLANEOUS PROVISIONS 14. TERMINATION OF THE CONTRACT ~ CAUTION: You should use an original AlA document which has this caution printed In red. w.IiI An original assures that changes will not be obscured as may occur when documents are reproduced. Copyright 1975, Cl 1980, by The American Institute of Architects, 1735 New York Avenue, N.W.. Washington, D.C. 20006. Reproduction of the material herein or substantial quotation of its provisions without wrillen permission of the AlA violates the copyright laws of the U:lited States and wiu be subject to legal prosecution. AlA DOCUMENT A2t1/CM . GH':ERAl CO~DITIONS OF THE CONTRACT FOR CONSTRUCTION CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION · AlA- . @ 1980 · THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE.. N.W., WASHINGTON, D.C. 20006 A201/CM - 1980 1 '..l ._._ __J:._,_.L..',..~I._'_-,.....~l~_~e""'..:r'" Acceptance of Defective of Non-Conforming Work. .6.2.2, 13.3 Acceptance of Work. . ., . . . . . ., . . . . . . .9.5.5, 9,8.1, 9.9.1, 9.9.3 Acce~~ to Work. . . . . . . . , . . . . . . . ... . . . . . . . . . . . . . .2.3.6, 6.2.1 Accident Prevention. ....... ., . ..... .. . . . . . . . . . .,. .2.3.5, 10 Act~ and Omi~~ions ............. .4.18.3, 7.4, 7,6.2, 8.3.1, 10.5 Addenda, Definition of .............................. .1.1.1 Additional Co~ts, C1aim~ for .......................... .12.3 ADMINISTRATION OF THE CONTRACT............. .2,4.3.3 Agreement, Extent of .............................. .1.1, 1.2 All Risk Insurance .................................. .11.3.1 Allowances .......................................... .4.8 Applications for Payment, Contractor's.. . . . . .2.3.8, 9.2.1, 9.3.1, 9,3,3.,9.5.3,9.7.1,9.8.2,9.9.1,9.9.3,9.9.5, 11.3.1, 14.2.2 Applications for Payment, H' Project................ .2,3.8,2.3.9,9.3.1,9.4,9.6.1,9.7.1 Approvals.... . .. .......... .... .2,3.18, 3.4, 4,3,3,4.5, 4,12.4, 4.12.5,4.12.6,4,12.8,4.13.2,7.7,9.3.2 Arbitration. . .. . ., .2.3.15,2.3.23,6.2.5,7,9, 8.3.1, 11.3.7, 11.3.8 Architect, Definition of ................ ... ............. .2.1 Architect, Extent of Authority....... .2.3.3.4,4.12.8,5,2,7.7.2, 8.1.3,8.1.4,8.3.1,9.2,9,3.1,9.4,9.5.3,9.6,9.8, 9.9.1, 9.9.3, 12.1.1,12.1.4,12.3.1,12.4.1,13.1,13.2.1,13.2.5,14.2 Architect, limitations of Authority and Responsibility. . . . .2.3.2 through 2.3.5, 2.3.13 through 2.3.18, 2.3.22,4.12.6, 5.2.1,9.4.2,9.5.4,9.5.5,12.4 Architect's Additional Services.. .3.4,7.7.2,13.2,1,13.2.5,14.2.2 Architect's Approvals. .., . .2.3.18, 3.4,4.5, 4.12.6, 4.12.8, 4.18.3 Architect's Authority to Reject Work... .2.3,16,4.5,13.1.2,13.2 Architect's Copyright. .. . . . . .. . .... .. . . . .. . . .. . .. .:. . ...1.3 Architect's Decisions. . . . . . . .. ... ..2.3.10 through 2.3.16, 7.7.2, 7.9.1,9.2,9.4,9,6.2,9.8.1,12.1.4,12.3.1 Architect's Inspections. .... . . . .2.3.16, 2.3.21, 9.4.2, 9,8,1,9.9.1 Architect's Instructions. . . . . . .. . .2.3.16, 2.3.19, 7.7.2,12.4,13.. Architect's Interpretations. .... . .. .2.3.10 through 2.3.13, 12.3.2 Architect's On-Site Ob~ervations ...... .2.3.4, 2.3.6, 2.3.9, 7.7.1, 7.7.4,9.4.2, 9.6.1,9.9,1 Architect's Relationship with Contrador ..... .1.1.2, 2.3.5, 2.3.6, 2.3.13,2.3.16,4.3.3,4.5,4.7.3,4.12.6,4.18,11.3.6 Architect's Relationship with Subcontractors. ...... . . .... .. . . .1.1.2, 2.3,16, 9.5,3, 9.5.4 Architect's Representations .................9.4.2, 9,6.1, 9.9.1 Artistic Effect... .... ............... .1.2,3,2.3.14,2.3.15,7.9.1 Attorneys' fees.......... .............. .. .4.18.1,6.2.5,9.9.2 Award of Separate Contracts. .. .. . .... . . . . . . . . . . . ., . .. .6.1.1 Award of Subcontracts and Other Contracts for Portions of the Work. . .. . .. . ., . .. . . . ... . . . . .. . . . .. .5.2 Boiler and Machinery Insurance.. ... . . . . . . . . . . . . . . . .. .11.3.2 Bonds, lien ....................................9.3.3, 9.9.2 Bonds, Performance, labor and Material Payment. . .. .7.5,9.9.3 Building Permit. . ..... .. .., . ............ . . . . .. . .. . . .. . .4.7 Certificate of Substantial Completion... .9.8.1,9.8.2,9.8,3,9.8.4 Certificates of Inspection, Te~ting or Approval. .. ........ .7.7.3 Certificates of In~urance ...,................... .9.3.2,11.1.4 Certificates for Payment, Projed ....... .2.3.9,2.3.21,9.4,9.5.1, 9.5.5,9.6.1,9.7.1,9.8.2,9.9.1,9.9.3,12.1.4,14.1.1,14.2.2 Change Orders .............. .1.1.1, 2.3.19, 3.4, 4.8.2.3,4.11.1, 5.2.3,7.7.2,8.3.1,9.7,9.9.3,11.3.1,11.3.5,11.3.7, . 12.1,12.2.1,12.3.1,13.1.2,13.2.5,13.3.1 Change Orders, Definition of ............. . . .. . . . .. ., .12.1.1 CHANGES IN THE WORK................. .2.3.19,4.11.1, 12 INDEX Claims for Additional Cost or Time. . . . .8.3.2,8.3.3, 12.2.1, 12.3 Claims for Damages.............. .6,1,1, 6.2,5, 7.4, 8.3, 9,6.1.2 Claims and Disputes Between Contractor and Owner............. .2.3,12,23,15,2.3.23,4,18,2, 7,9 Cleaning Up . . ... .... . . .. . . . . . . . . . . . . . . . .. . . .. . .. .4.15, 6.3 Commencement of the Work, Conditions Relating to .3.2.1,4.2, 4.7.1,4.10,5.2.1,6.2,2,7.5,9.2,11.1,11.3.4 Communications..... ........ ....... . .2.3.2, 3.2.6,4.9,1,4.16 Completion, Conditions Relating to.. .2.3.21, 4.11, -4.15,9.4.2,9.9,13.2.2 COMPLETION, PAYMENTS AND ..........................9 Completion of the Project, Substantial.. .... .8,1.4,9.8.3,9.8.4, 9.9.4,9.9.5,9.9.6,13.2.1,13.2.2 Completion of the Work, Substantial... .... .23.21, 8.1.1, 8.1.3, 8.2.2,9,8,9.4.2,9.9.3,11.3.9 Compliance with Laws ....... ... . .1.3,2.1.1,4.6.4.7,4.13,7.1, 7.6.1, 7.7.1,10.2.2,14.2.1 Concealed Conditions ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . .12.2 Consent, Written ....................2.3.22,4.14.2,7,2,7.6.2, 9.8.1,9.9.2,9,9,3,11.3.9 Construction Manager, Definition of .................... .2.2 Construction Manager's Approval .............. .4.10.1, 4.13.2 Construdion Manager's Additional Services........ .3.4,7.7.2,13.2.1,13.2.5,14.2.2 Construction Manager's Authority and Responsibility... . .2.3.3, 23.5,2.3.16,2.3.10, 2.3.22,4.8.1,4.17.1,4.18.3, 7.7.4,9.2,10.2.5,11.3.6,12.1.4,14.1.1 Construction Manager's Confirmation ...................9.9,3 Construdion Manager's Consultation with the Architect .2.3- 2.3.16,2.3.19,2.3.21,3.4.1,9,6.1.9.8.1,12.1.4,12.3.1,14. Construction Manager's Coordination and Scheduling.. . .2.3.7, 2.3.17,4.3.1,4.10.1, 4.12.4 Construction Manager's Decisions. . . . . . . . . .. ..... . .6.3, 8,3.1 Construction Manager's Determinations. .2.3.3. 6.3.1, 7.7.2,8.3.1 Construdion Manager's Interests................ 11.3.1,11.3.2 Construction Manager's Recommendations... .2.3.8, 2.3.9, 9.3.1, 9.4,1,9.7.1,9,9.1, 12.1.1 Construdion Manager's Relationship with Architect.......... .... ... . .1.1.2, 2,3.1, 2.3.3, 2.3.21 Construction Manager's Relationship with Contrador .....1.1.2, 2.3.15,23.16,3.2,6,4.2.1,43.3,4.5,4.7.3,4.11.1, 4.12.4, 4.12.6, 4.16.1,4.17.1,4.18,5.2,6,2.1,6.2.2,7.6.2,7.7, 7.9.1,7.9.2, 8.3.1,8.3.2,9.4.1,9.5.4,9.8.1,9.9.1,10.2.6,11.1.4,11.3.6 Construdion Manager's Relationship with Subcontractors.......... .... .. .. .1.1.2,2.3.16,5.3.1 Construdion Manager's Review..........,. .2.3.8, 2.3.17,5.2.1 Construction Schedule, Contrictor's .. . . . .. ... ... ... . .. . .4.10 Contrad, Definition of ............. . . . . . . . . . . . . . . . . . . .1.1,2 Contract Administration........ ..... . ............ .2.3,4.3.3 Contrad Award ilnd Execution, Conditions Relating to..... .4.7.1, 4.10, 5.2, 7.5,11.1,11,3.4 CONTRACT DOCUMENTS ..........;....................1 Contrad Documents, Copies Furnished and Use of ... . ~. . . . .. . ., .1.3, 3.2.5, 5.3 Contract Documents, Definition of .....................1.1.1 Contract Modifications............. ... ............. 1.1.1,12 Contrad Sum, Definition of ...........................9.9.1 Contract Termination ...................................14 Contrad Time, Definition of .. .. .... . " .. ... ......... . .8.1.1 CONTRACTOR ..................................,......4 Contractor, Definition of ........ ... .. ............ .4.1, 6.1.2 Contractor's Construction Schedule .................... .4.1r) 2 A201/CM-1980 AlA DOCUMENT A2ft/CM . GENERAl CONDITIONS Of THE CONTRACT fOR CONSTRUCTION CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlA. . ~ 1980 . THE AMERICAN INSTITUTE Of ARCHITECTS. 1735 NEW YORK AVE., N.W., WASHI!'/GTON, D.C. 20006 WAR~I!NG: Unlicensed photocopying \~ol.tes U.S. copyright leNS ~ Is euIljee! to!~1 rmeecutlon. Contractor's Employees. . . . . .4.3.2, 4.4.2, 4.8.1, 4.9, 4.18, 10,2.1 through 10.2.4, 10.2.6, 10.3, 11,1.1 Contractor's liability Insurance.. .. . ., . . . . . . . . . . . . . . . . . .11.1 Contractor's Relationship with Architect ..... .1.1.2, 2.3,5, 2.3.6, 2.3.13,2.3.16,4.3.3,4,5,4.7,3,4.12.6,4.18,11.3.6 Contractor's Relationship with Construction Manager. .. . .1.1.2, 2.3.15,2,3.16,3.2.6,4.2,1,4,3.3,4.5,4.7.2, 4.11.1, 4.12.4, 4.12.6,4.16.1,4.17.1,4.18,5.2,6.2.1,6,2.2,7.6.2, 7.7, 7.9.1, 7.9.2,8.3.1,8.3.2,9.4.1,9.5.4,9.8.1,9.9.1,10.2.6, 11.1.4, 11.3.6 Contractor's Relationship with Separate Contractors and Owner's Forces.... .., ......... . . . ... . . .,. .3,2.7, 6 Contractor's Relationship with Subcontractors..... .,. . .1.2.4, 5.2, 5.3, 9.5.2, 113.3, 11.3.6 Contractor's Representations .......... .1.2.2, 4,5, 4.12.5, 9.3.3 Contractor's Responsibility for Those Performing the Work.. .. .,. .. ...... . . . ., .4.3,2, 4.18, 10 ~ontractor's Review of Contract Documents ....1,2.2, 4.2, 4.73 Contractor's Right to Stop the Work .....................9.7 Contractor's Right to Terminate the Contract. . . . . . . . . . .. .14.1 Contractor's Submittals. .... ...... ... .2.3.18, 4.10, 4.12, 5.2.1, 5.2.3,9.2,9.3.1,9,8.1,9.9.2,9.9.3 Contractor's Superintendent. . .. . ., . . . . . . . . . . . . . . . .4.9, 10.2.6 Contractor's Supervision and Construction Procedures. . . . . . . . . .1.2.4, 2,3.5, 4.3, 4.4, 10 Contractual liability Insurance.... ...... . .. . .. . .. . ... .11.1.3 Coordination and Correlation...... ...1.2,2,1.2.4,4.3.1,4,10.1, 4.12.5,6.1.3,6.2.1 Copies Furnished of Drawings and Specifications. .1.3, 3,2.5, 5.3 Correction of Work.................... .3.3,3.4,10,2,5,132 Cost, Definition of ................................. .12.1.4 Costs...... .3.4,4,8.2,4.15.2,5,2,3,6.1.1,6.2.3,6,2.5,6,3,7.7.1, 7.7.2,9.7,11.3.1,11.3.5,12.1,3,12.1.4,12.3,13.1.2,13,2,14.2.2 Cutting and Patching of Work. ., . ., . . . . . . . . . . . . . ... .. . .4.14 Damage to the Work........... .4.14.2,10.2.1.2,10.2.7,11.3.1 Damage to Work. . . ..... ... . .4.14,2,4.18.1,6.2.4,6.2.5,9.6.15, 10.2.1.3,10.2,2,10.2.5,10.3,13.2.6 Damages, Claims for.. ..... .......... .6.1.1,6.2.5, 7.4,9.6.1.2 Damages for Delay. . '" ., ...... ;....... . ... .6.1.1,8.3.4,9.7 Day, Definition of ................................... .8.1.5 Decisions of the Architect........ .2.3.10 through 2.3.16, 7.7.2. 7.9.1,9,2,9.4,9.6.1,9.8,1,12,1.4,12.3.1 Decisions of the Construction Manager. . . . . .. . . . .. . .6,3, 8,3.1 Defective or Son.Conforming Work, Acceptance, Rejection and Correction of . . .. . .2.3.4, 2.3.16, 3.3, 3.4, 4.5, 6.2.2,6.2.3,9.6.1.1,9,9,4.2,13 Definitions. . . . . . . . ... .. . .1.1, 2.1, 2.2, 3.1, 4.1, 4.12.1 through 4.12.3,5.1,6.1.2,8,1,9,1.1,12.1.1,12.1.4 Delays and Extensions of Time. ... . . . . . . . . . . . . . . . . ..... .8.3 Disputes. . . . . . . . . . . . ... . .2.3.12, 2.3.15, 23.23, 6.2.5, 6.3, 7.9.1 Documents and Samples at the Site.. .. . . . . . . . . . . . . . .. . .4.11 Drawings and Specifications, Use and Ownership of ............. . . .1.3, 3.2.5, 4.11, 5.3 Easements. . .. ... ... .... ., ............ . . . .,. ........ .3.2.3 Emergencies ........................................ .10.3 Employees, Contractor's .......... .4.3.2, 4.4.4, 4.8.1, 4.9, 4.18, 10.2.1 through 10.2.4, 10,2.6,10.3,11.1.1 Equipment, labor, Materials and...... 1.1.1,4.4,4.5,4.12,4.13, 4.15.1,6.2.1,9.3.2,93.3,9,6.1.3,9.9,2, 10.2.1.2,11.3.1,12.1.4,13.2.2,13.2.5,14 Execution and Progress of the Work. . .. . . . . .1.1.3, 1.2.3, 2.3.4, 2.3.5,23.11,4.2,4.4,1,4.5,4.7.1,6.2.2,7,9.3, 8.2.2,8.3,1,8.3.2,9.6.1,10.2.3,10.2.4,14.2 Execution, Correlation and Intent of the Contract Documents ......................1.2,4.7.1 Extensions of Time... .......... ...... .... .8,3,12.1.1,12.1.2 Failure of Payment by Owner. . . . . . . . . . . . . . . . . . . . . . .9.7, 14.1 Failure of Payment of Subcontractors ......9,6.1.3, 9.9.2, 14.2.1 Failure to earry out the Wort.. .. . . . .. . .. . . ...... . .. . . .2.3.5 Final Completion and Final Payment. . .2.3.15,2.3.21,9.9,13.3.1 Financial Arrangements, O.....-ner's .... ...... ........... . .3.2.1 Fire and Extended Coverage Insurance. . . . . ... ... .. . ., .11.3.1 Governing law.. .............. ... . ................... .7.1 Indemnification.. . .. . . . ....... . . . . .. .. .4.17, 4.18, 6,2.5, 9.9.2 Identification of Contract Documents .................. .1.2.1 Identification of Subcontractors and Suppliers........ ... .5.2.1 Information and Services Required of the Owner. . . . . .. . . . .... . . . . . . . . . . .3.2, 6.1, 9, 11.2,11.3 Inspections... . .. ...... . .2.3.16,2.3.21,4,3.3,7.7,12.1.2,9.9.1 Instructions to Bidders. . . .... . . . . . . . . . . . . ....... ... . . .1.1.1 Instructions to the Contractor.... . . . .. .2.3.2, 3.2.6, 4.8.1,7.7.2, 12.1.2,12.1.4 INSURANCE. .. ................. . ....... ......... .9.8.1,11 Insurance, Contractor's liability ....................... .11.1 Insurance, loss of Use . . ... ,. ... . . . . .. . . . . ., . .. . . ... .. .11.4 Insurance, Owner's liability..... . .. . .... ........ ...... .11.2 Insurance, Property ...................................11.3 Insurance, Boiler and Machinery. . .. .. . .......... .... .11.3.2 Insurance, Special Hazards.......... .... . ...... ... ...11.3.5 Insurance, Stored Materials.... . .. . . . . .. . . .......9.3.2,11.3.1 Insurance Companies, Conse:!t to Partial Occupancy.... .11.3.9 Insurance Companies, Settle::1ent With. . ., . ..... . . . . .. .11.3.8 Intent of the Contract Documents...... ........1.2.3, 2.3.10, 2.3.13, 2.3.14,12.4 Interest ............................................. .7.8 Interpretations, Written. ..... . .1.1.1, 2.3.11, 2.3.12, 2.3.13, 12.4 labor, Materials and Equipment.. . . . . .1.1.3, 4.4, 4.5, 4.12, 4.13, 4.15.1,62.1,9.3.2,9.3.3,9.6.1.3,9.2.2,10,2.1.2, 11.3.1,12.1.4,13.2.2,13.2.5,14 labor and Material Payment Bond...................... .7.5 labor Disputes. . . . . . . . . . ... .. . . . . . . . . . . . .... .. . . ., . . .8.3.1 laws and Regulations. . . ..... . . . . .1.3, 2.1.1, 4.6, 4.7, 4.13, 7.1, , 7.6.1,7.7.1,10.2.2,14 lIens...... ......... ........... ........ .9.3.3, 9.9.2, 9.9.4.1 limitations of Authority.... ... . . . . .. . .. . .2.3.2, 11.3.8, 12.4.1 limitations of liability. . .... . . . . .2.3,13, 23.16, 2.3.18, 3.3,4.2, 4.7.3,4.12.6,4.17,4.18,6.2.2,7.6.2,9.4.2, 9.5.4,9.9.4,9.9.5,10.2.5,11.1.2,11.3.6 limitations of Time, Genera~ ...... . .2.3.11,2.3.18, 3.2.1, 3.2.4, 4.2,4.7.1,4.7.3,4.12.4,4.15.1,5.2.1,5.2.3,6.2.2,7.4, 7.7,7.9.2,8.2,9.5.2,9.6,1,9.8,9.9,11.3.1,11.3.4, . .. . 1.:1.3.9,12.1.4, 12.4,13.2.1,13.2.2,13.2.5 llmltallons of TIme, Specific....... . .3.4, 4.10, 7.9.2, 8.2, 8.3.2, 8.3.3, 9.~. 9.3.1, 9.4.1, 9.5.1, 9.7, 11.1.4, 11.3.8, , . . 12.2,12.3.1,13.2.2,13.2.7,14.1,14.2.1 lImItatIons, Statutes of .................. .7.9.2, 13.2.2, 13.2J loss of Use Insurance. . .. ... . .. . . . . . . . . . ... ... . .. . ... .11.4 AlA DOCUMENT A201/CM . GENERAL CONDIlIONS OF THE CONTRACT FOR CONSTRUCTION CONSTRUCTION M^N^GE,I.\ENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE ^MERICAN INSTITUTE OF ^RCHITECTS, 1735 NEW YORK ^VE.. N,W., WMHINGTON, D.C. 2OOll6 A201/CM-1980 3 '_l.-_,_~._ _ "__ ._t...._~ 'IC=: f""""'" .~:...I-..~..c::::."..,ir.;~ubi~r:-tt('ll~:"~.""'"':JsecuHon. Materials, labor and Equipment...... .1.1.3, 4,4, 4,5, 4.12, 4,13, 4.15,1,6,2,1,9.3.2,9.3.3,9.6,1.3,9.9,2, 10.2.1.2,11,3,1,12.1,4,13.2.2,13.2.5,14 Material Suppliers....................... .4.12.1, 5.2.1, 9.3.3 Means, Methods, Techniques, Sequences and and Procedures of Construction........ .2.3,5,4.3,1,9,4.2 Minor Changes in the Work............... .1.1,1,2.3.19,12.4 MISCELLANEOUS PROVISIONS ...........................7 Modifications, Definition of ...........................1.1.1 Modifications to the Contract.. . . . ., .1.1.1, 1.1.2, 2.3.2, 2.3,22, 4.11.1,4.7.3,12 Mutual Responsibility................................. .6.2 Non-Conforming Work, Acceptance of Defective or .... . . .13.3 Notice, Written. . . ........ .2.3.11,2.3,15,4.2, 4.7.3, 4.7.4, 4.9. 4.12,6,4.12.7,5.2.1,7.3,7,4,7.9.2,8.1.2,8.3.2,8.3.3, 9,4,1,9,6.1,9.7,9.9,1,9,9.5,10.2.6,11,1,4,11.3.1, 11.3.5,11.3.7,11.3,8,12.2,12.3,13.2.2,13,2.5,14 Notices, Permits, Fees and. . ........ .. .2.3.2, 4.7, 4.13,1, 10.2.2 Notice of Testing and Inspections... ....... . . . .......... .7.7 Notice to Proceed................................... .8.1.2 Observations, Contractor's....... . . ........ . . .,. .1,2.2, 4.7.3 Occupancy. . .. ... ... ..... ......... .8.1.3, 8,1,4,9.5.5, 11.3.9 On-Site Inspections by the Architect........., .2.3.16,2,3.21,9.4.2,9.8.1,9.9,1 On-Site Observations by the Architect. . . . . . ..2.3,4,2.3.6,2.3.9, 7.7.1,7.7,4,9.4,2,9.6.1,9.9.1 Orders. Written................. .3.3,4.9,12.1,4,12.4,1,13 1 OWNER ...............................................3 Owner, Definition. ................................... .3.1 Owner, Information and Services Required of the.. ....... .3,2,4.7.1,6,1.3,6.2,9,11.2,11.3 Oy.ner's Authority. ...... . .,. ...... .2.3.21, 7.7.2,9.3.1, 9.3.2, 9.8.1,11.3.8,12.1.2,12.1.4 Owner's Financial Capability......................... .3.2.1 Owner's liability Insurance ..,........................ .11.2 Owner's Relationship with Subcontractors... .. .. . . .1.1.2,9.5,4 Owner's Right to Carry Out the Work..... ... . .... .3.4,13.2.4 Owner's Right to Clean Up ...................... .4,15.2, 6.3 Owner's Right to Perform Work and to Award Separate Contracts.......... .. ., . ...... . . . .. .6.1 Owner's Right to Terminate the Contract, .... .. .....' . . . .14.2 Owner's Right to Stop the Work........................ .3.3 Ownership and Use of Documents.. .. .. ..... .. .1.3,3.2.5,5.3 Patching of Work, Cutting and......... . . .., ... ... .. . . .4,14 Patents, Royalties and. ... . ...,. .. . ... .,. .. .......... .4,17.1 Payment Bond, labor and Material. . .. . . . . . . . . . . ., . . . . . . .7.5 Payment, Contractor's Applications for .... , .2.3.8, 9,2, 9.3, 9.4, 9.5.3,9.6,1,9.7.1,9.8.2,9.9,1,9.9.5,14.2.2 Payment, Project Certificates for..... ,. .2.3,9,2.3.21,9,4,9.5.1, 9.5.5,9.6.1,9.7.1,9.8.2,9.9.1,9.9.3,12.1,4,14,1.1,14.2.2 Payment, Failure of ..........,.....9.5.2, 9.6.1.3, 9.7, 9.9.2, 14 Payment, Final. .. . . ............... 2.3.15, 2.3.21, 9.9, 13.3,1 Payments, Progress. . . ..... . ,i.8, 7.9.3, 9.5.5, 9.8.2,9,9.3,12.1.4 PAYMENTS AND COMPlETION..........................9 Payments to Subcontractors ..........9,5.2,9.5.3,9.5,4,9,6.1.3, 11.3.3,14.2.1 Payments Withheld ....................................9.6 Performance Bond and labor and Material Payment Bond. . .7.5 Permits, Fees and Notices. . . .. . . . . . . . . .3.2,3, 4.7, 4,13. 10.2,2 PERSONS AND PROPERTY, PROTECTION OF . . . . . . . . . . . . . .10 Product Data, Definition of ..................,...... .14.2,2 Product Data, Shop Drawings, Samples and. . .2.3.18,4.2.1,4.12 Progress and Completion ....................2.3.4, 7.9.3, 8,2 Progress Payments....... ...7,8, 7,9.3,9.5.5,9.8,2.9.9.3, 12.1.4 Project, Definition of ............................... .1.1.4 Project Construction Schedule..... .... . .. ., . .,. .. . ., .. .4.10 Property Insurance. .. . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . .. .11.3 PROTECTION OF PERSONS AND PROPERTY ............. .10 Record Documents .................................. .4.11 Regulations and laws... ...... . . ... .1.3,2.1.1,4.6,4.7,4.13.1, 7.1, 10,2,2, 14 Rejection of Work......,................ .2.3,16,4,5.1,13,2 Releases of Waivers and liens .......... . . . . , . . . . ,9,9.2, 9,9,4 Representations.. ....... .. .1,2,2, 4,5, 4.12,5, 9.4,2, 9,6.1, 9.9.1 Representatives. . . .2.1, 2.2, 2.3,2, 2.3.22, 3.1,4.1,4.9,5.1,9.3.3 Responsibility for Those Performing the Work. . .. .2.3.5, 4.3.2, 6.1.3, 6.2, 9.8.1 Retainage ......................9.3.1, 9.5.2, 9,8.2, 9.9.2, 9.9.3 Review of Contract Documents by the Contractor... ... .1.2.2, 4.2,4.7.3 Reviews of Contractor's Submittals by Owner and Architect... ...... . . . , . .2,3.18, 4.10, 4,12, 5,2.1, 5,2.3, 9.2 Rights and Remedies. . . . . . . . . . . . .1.1.2, 2,3.15, 2.3,16, 3,3, 3.4, 5.3,6.1,6.3,7.6,7,9,8.3.1,9,6.1,9.7, 10,3,12.1.2,12.2.13.2,2,14 Royalties and Patents ................................ .4.17 Safety of Persons and Property ........,............... .10,2 Safety Precautions and Programs.. . .. . . . . , . . . .... .2,3.5, 10,1 Samples. Definition of .. . . . , . . . . , . . . . . . . . . . . . . . . . . . . .4,12.3 Samples, Shop Drawings, Product Data and. . . . . .2.3.17,2.3.18, 4,2, 4.12 Samples at the Site, Documents and. . . . . . . . . ..... . ., .. .4.11 Schedule, Contractor's Construction. . . . . . . . . . . . . . . . . . ., .4.10 Schedule, Project Construction. ... . . . . . ... .. . ., ....... .4.10 Schedule of Values ....................,...............9.2 Separate Contracts and Contractors.... .4.14,2,6,11.3.6,13.1.2 Shop Drawings, Definition..... . . . . .. , , , . . . , .. , .' . .. .4.12.1 Shop Drawings, Product Data and Samples. . , . . ..,. . .. .2.3.17, 2.3,18,4,2,4.12 Site, Use of . . . . . . .... . . . . . . . . . . . . . . . . . . . , . . . ... .4.13, 6,2.1 Site Inspections........... .1.2,2,2.3,4,2.3.21,7.7,9.8.1,9,9.1 Site Visits. Architect's..........,..... ,2.3.4, 2.3,6, 2,3.9, 7.7.1, 7.7.4,9,4,2,9.6.1,9,9.1 Special Inspection and Testing...........,',..... .2,3,16,7.7 SpeCial Hazards Insurance........................... .11,3.5 Specifications.............................. .1.1.1, 1.2.4, 1.3 Statutes oi limitations. . . . . . . , . . . . . . . . . , . .7.9.2, 13.2.2, 13.2.7 Stopping the Work. . . . . . . . . . . . . . . . . . . . . .3.3, 9.7.1, 10.3, 14.1 Stored Materials........... .6.2.1,9.3.2,10.2,1.2,11.3.1,13.2,5 SUBCONTRACTORS ....................................5 Subcontractors, Definition of ...............,......... .5.1.1 Subcontractors, Work by .......... . . . .1.2.4, 2.3.5, 4.3.1, 4.3.2 Subcontractual Relations .................,............ .5.3 Submittals.. ........... .... .1.3,2.3.18,4,10,4.12,5.2.1,5.2.3, 9,2,9.3.1, 9.8.1, 9.9.1,9,9.3 4 A201/CM-1980 AlA DOCUMENT A201/CM . GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION CO'STRUCTION MANAGEMENT EDITION . JUNE 19l1O EDITION . AlA@> . @ 1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D,C. ~0006 WARNI'IC, Unlicensed o~ ~C'c",~v:~c v;cl"'es U S copvriQhl law', A"'-! ., t 10 I..~_.-..r -'''l"")!I;er-:~I'n 'v. Subrogation, Waiver of ............................. .11.3,6 Substantial Completion of the Project... .... .8.1.4, 9.8.3, 9.8.4, 9,9.4,9.9.5,9.9.6,13,2.1,13,2.2 Substantial Completion of the Project, Definition of ..... .8.1.4 Substantial Completion of the Work....... .2.3.21,8.1.1,8.1.3, 8.2.2,9.4.2,9.8,9.9.3,11.3.9 Substantial Completion of the Work, Definition of ....... .8.1.3 Substitution of Subcontractors ............. . . . . . . .5,2.3, 5.2.4 Substitution of the Architect. ... . . . . . . . . . . . . . . . . . . . .. .2.3.23 Substitution of the Construction Manager. . . .. . ... ... . .2.3.23 Substitutions of Materials ....................... ,4,5, 12.1.4 Sub-subcontractors, Definition oj .... ... .. .. ........... .5.1.2 Subsurface Conditions.. . . . ...... . . .. . . . . . . . . . .. . . . . .12.1.1 Successors and Assigns. . ................... . . ... .. .... .7.2 Supervision and Construction Procedures. . . . . .. .. .1.2.4, 2.3.5, 4.3, 4.4, 10 Superintendent, Contractor's...... .. ... . ., . . . . ... .4.9,10.2.6 Suret}', Consent of ...........,..................9.9.2, 9.9.3 Surveys. . . . . , . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . .3.2.2, 4,18,3 Taxes ............................................... .4.6 Termination by the Contractor.... '" . . . .. .. . . ., . ..... .14.1 Termination by the Owner....... .. . . . .. . . . . . ... .. . . .. .14.2 Termination of the Architect ...,.....................2.3.23 Termination of the Construction \tanager ... .. . . .. .... .2.3.23 TERMINATION OF THE CONTRACT..... ... ... .......... .14 Tests............................... .2.3.16,4.3.3,7.7,9.4.2 TIME................................................. .8 Time, Definition of ................................... .8.1 Time, Dela}'s and Extensions of .,....... .8,3, 12,1, 12.3, 13.2.7 Time Limits, Specific ...............3,4, 4.10, 7.9,2, 8.2, 8.3.2, 8.3,3,9.2,9,3,1,9,4,1,9.5.1,9.7,11.1.4, 11.3.8,12,2,12.3,1,13,2.2,13.2.7,14.1,14.2.1 Title to Work ..................................9.3.2, 9.3.3 UNCOVERING AND CORRECTION OF WORK. . . . . . . . . . . . .13 Uncovering of Work ................................. .13.1 Unforseen Conditions.... . . . . . . . . ............. .. .8.3.1,12.2 Unit Prices..... ........ ... .. ............. ..12.1.3.2, 12.1.5 Use of Documents. . . .. . . . . . . . . . . . . . ... .. . . .. .1.3, 3.2.5, 5.3 Use of Site. . . . . . . . . .. . . . . . . .. . . . . . . .. . .. . .. . . . .4.13, 6.2.1 Values, Schedule of ....................................9.2 Waiver of Claims by the Contractor. . . .7.6.2,8.3.2,9.9.5,11.3.6 Waiver of Claims by the Owner..... .7.6.2, 9.9.4, 11.3.6, 11.4.1 Waiver of Liens ................,.....................9.9.2 Warranty and Warranties. . . . . . . . . . . . . .2.3.21, 4.5, 9.3,3, 9.8.4, 9.9.4, 13.2.2, 13.2.7 Weather Delays. . . . . . . . . . . . . . . . . . . . ... . . . . . . . .. . . .. . .8.3.1 Words, Recognized Meaning of ........................1.2.3 Work, Definition of ..................................1.1.3 WORK BY OWNER OR BY SEPARATE CONTRACTORS.......6 Wrillen Consent......... .2.3.22,4.14.1,7.1,7,6,2,9.8.1,9.9.3 Written Interpretations... . .. . . .. .........1,1.1,1.3.11, 11.3.1 Written Notice...... .2.3.11,2.3,15,4.2,4.7.3,4.7.4,4.9,4.12.6, 4,11.7,5,2.1,7.3,7.4,7.7.2,7.9.2,8.1,1,8.3.2,8,3.3,9.4.1, 9.6.1,9.7,9,9.1,10,2.6,11.1.4,11.3.1,11.3.5,11.3.7, 11.3,8, 122, 12.3, 13.2,2, 13.2.5, 14 Wrillen Orders. .. . . .. .. . . . . .. .. . ,3.3,4.9, 12.1.4, 12.4.1, 13.1 AlA DOCUMENT A201/CM . GENERAL Cmml1l0NS OF THE CONTRAG fOR CONSTRUGION CONSTRUCTION MANAGEMENT EDIT'O-': . JUNE 1980 EDITION . AlA- . @ 1980 . THE AMERICAN INSTITUTE OF ARCHITEGS 1~35 NEW YORK AVE.. N,W., WASHINGTON, D.C. 20006 A201/C~--1980 5 WAqt.llt.l~' Unlic~nsed ohotocopying vlolat~s U.S. cOpyright laws and Is subject to l~gal proseeutle>r. GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION ARTICLE 1 CONTRACT DOCUMENTS 1.1 DEFINITIONS 1.1.1 THE CONTRACT DOCUMENTS The Contract Documents consist of the Owner-Contractor Agreement, the Conditions of the Contract (General, Sup- plementary and other Conditions), the Drawings, the Specifications, and all Addenda issued prior to and all Modifications issued after execution of the Contract. A Modification is (1) a written amendment to the Contract signed by both parties, (2) a Change Order, (3) a written interpretation issued by the Architect pursuant to Sub- paragraph 2.3.11, or (4) a written order for a minor change in the Work issued by the Architect pursuant to Paragraph 12.4. The Contract Documents do not include Bidding Documents such as the Advertisement or Invita- tion to Bid, the Instructions to Bidders, sample forms, the Contractor's Bid or portions of Addenda relating to any of these. or any other documents unless specifically enu- merated in the Owner-Contractor Agreement. 1.1.2 THE CONTRACT The Contract Documents form the Contract for Construc- tion. This Contract represents the entire and integrated agreement between the parties hereto and supersedes all prior negotiations, representations or agreements, either written or oral. The Contract may be amended or modi- fied only by a Modification as defined in Subparagraph 1.1.1. The Contract Documents shall not be construed to create any contractual relationship of any kind between the Architect and the Contractor, between the Construc- tion Manager and the Contractor or between the Archi- tect and the Construction Manager, but the Architect and the Construction Manager shall be entitled to perform- ance of the obligations of the Contractor intended for their benefit and to enforcement thereof. Nothing con- tained in the Contract Documents shall create any con- tractual relationship between the Owner, the Construc- tion Manager or the Architect and any Subcontractor or Sub-subcontractor. 1.1.3 THE WORK The Work comprises the completed construction required of the Contractor by the Contract Documents, and in- cludes all labor necessary to produce such construction, and all materials and equipment incorporated or to be incorporated in such construction. 1.1.4 THE PROJECT The Project, as defined in the Owner-Contractor Agree- ment, is the total construction of which the Work per- formed under the Contract Documents is a part. 1.2 EXECUTION, CORRELATION AND INTENT 1.2.1 The Contract Documents shall be signed in not less than quadruplicate by the Owner and the Contractor. If either the Owner or the Contractor or both do not sign the Conditions o{ the Contract, Drawings, Specifications or any of the other Contract Documents, the Architect shall identify such Documents. 1.2.2 Execution of the Contract by the Contractor is a representation that the Contractor has visited the site, be- come familiar with the local conditions under which the Work is to be performed, and has correlated personal observations with the requirements of the Contract Docu- ments. 1.2.3 The intent of the Contract Documents is to include all items necessary for the proper execution and comple- tion of the Work. The Contract Documents are comple- mentary, and what is required by anyone shall be as binding as if required by all. Work not covered in the Contract Documents will not be requ;red unless it is con- sistent therewith and is reasonably inferable therefrom as being necessary to produce the intended results. Words and abbreviations which have well-known technical or trade meanings are used in the Contract Documents in accordance with such recognized meanings. 1.2.4 The organization of the Specifications into divi- sions, sections and articles, and the arrangement of Draw- ings shall not control the Contractor in dividing the Work among Subcontractors or in establishing the extent of Work to be performed by any trade. 1.3 OWNERSHIP AND USE OF DOCUMENTS 1.3.1 All Drawings, Specifications and copies thereof furnished by the Architect are and shJII remain the prop- erty of the Architect. They are to be used only with re- spe~t to th~s Project and are not to be used on any other prOJect. With the exception of one contract set for each party to the Contract, such documents are to be returned or suitably accounted for to the Architect on request at the completion of the Work, Submission or distribution to meet official regulatory requirements or for other pur- poses in connection with the Project is not to be con- strued as publication in derogation of the Architect's common law copyright or other reserved rights. ARTICLE 2 ADMINISTRATION OF THE CONTRACT 2.1 THE ARCHITECT 2.1.1 The Architect is the person lawfully licensed to practice architecture. or an entity lawfully practicing ar- chitecture, identified as such in the Owner-Contractor Agreement. The term Architect means the Architect or the Architect's authorized representative. 2.2 THE CONSTRUCTION MANAGER ~.2.1 , ,The Construction Manager is the person or entity Identified as such in the Owner-Contractor Agreement. The term Construction Manager means the Construction Manager or the Construction Manager's authorized representative. 2.3 ADMINISTRATION OF THE CONTRACT 2.3.1 The Architect and the Construction Manager will AlA DOCUMENT A20lICM . GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlAe . @ 1980 . niE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 :. ._._ - 'I ~ __ A201/CM -1980 6 . l_., '.... ........04 :r r..h,;c ~, 0_ I...,... ",:. _ provide administration of the Contract as hereinafter described. 2.3.2 The Architect and the Construction Manager will be the Owner's representatives during construction and until final payment to all contractors is due, The Archi- tect and the Construction Manager will advise and con- sult with the Owner. All instructions to the Contractor shall be forwarded through the Construction Manager. The Arshitect and the Construction Manager will have authority to act on behalf of the Owner only to the extent provided in the Contract Documents, unless otherwise modified by written instrument in accordance with Sub- paragraph 2.3.22. 2.3.3 The Construction Manager will determine in gen- eral that the Work of the Contractor is being performed in accordance with the Contract Documents, and will en- deavor to guard the Owner against defects and deficien- cies in the Work of the Contractor. 2.3.4 The Architect will visit the site at intervals appro- priate to the stage of construction to become generally familiar with the progress and quality of the \Vork and to determine in general if the \\lork is proceeding in accord- ance with the Contract Documents. However, the Archi- tect will not be required to make exhaustive or con- tinuous on-site inspections to check the quality or quan- tity of the Work. On the basis of on-site observations as an architect. the Architect will keep the Owner informed of the progress of the Work, and will endeavor to guard the Owner against defects and deficiencies in the Work of the Contractor. 2.3.5 Neither the Architect nor the Construction Man- ager will be responsible for or have control or charge of construction means, methods, techniques, sequences or procedures, or for safety precautions and programs in connection with the Work, and neither will be respon- sible for the Contractor's failure to carry out the Work in accordance with the Contract Documents. Neither the Architect nor the Construction Manager will be respon- sible for or have control or charge over the acts or omis- sions of the Contractor, Subcontractors, or any of their agents or employees, or any other persons performing any of the Work. 2.3.6 The Architect and the Construction Manager shall at all times have access to the \'\'ork wherever it is in preparation and progress. The Contractor shall prO\ ide facilities for such access so that the Architect and the Construction Manager may perform their functions under the Contract Documents. 2.3.7 The Construction Manager will schedule and coor- dinate the \,\'ork of all contractors on the Project includ- ing their use of the site. The Construction Manager will keep the Contractor informed of the Project Construction Schedule to enable the Contractor to plan and perform the Work properly. 2.3.8 The Construction Manager will review all Applica- tions for Payment by the Contractor, including final pay- ment, and will assemble them with similar applications from other contractors on the Project into a combined Project Application for Payment. The Construction Man- ager will then make recommendations to the Architect for certification for payment. 2.3.9 Based on the Architect's observations, the recom- mendations of the Construction Manager and an evalua- tion of the Project Application for Payment, the Architect \,vill determine the amount owing to the Contractor and will issue a Project Certificate for Payment incorporating such amount, as provided in Paragraph 9.4. 2.3.10 The Architect will be the interpreter of the re- quirements of the Contract Documents and the judge of the performance thereunder by both the Owner and the Contractor. 2.3.11 The Architect will render interpretations neces- sary for the proper execution or progress of the Work, with reasonable promptness and in accordance with agreed upon time limits. Either party to the Contract may make written request to the Architect for such interpreta- tions. 2.3.12 Claims, disputes and other matters in question between the Contractor and the Owner relating to the execution or progress of the Work or the interpretation of the Contract Documents shall be referred initially to the Architect for decision. After consultation with the Construction Manager, the Architect will render a deci- sion in writing within a reasonable time. 2.3.13 All interpretations and decisions of the Architect shall be consistent with the intent of and reasonably in- ferable from the Contract Documents and will be in writ- ing or in graphic form. In this capacity as interpreter and judge, the Architect will endeavor to secure faithful per- formance by both the Owner and the Contractor, will not show partiality to either, and will not be liable for the result of any interpretation or decision rendered in good faith in such capacity. 2.3.14 The Architect's decisions in matters relating to artistic effect will be final if consistent with the intent of the Contract Documents. 2.3.15 Any claim, dispute or other matter in question between the Contractor and the Owner referred to the Architect through the Construction Manager, except those relating to artistic effect as provided in Subparagraph 2.3.14 and those which have been waived by the making or acceptance of final payment as provided in Subpara- graphs 9.9.4 through 9.9.6, inclusive, shall be subject to arbitration upon the written demand of either party, However, no demand for arbitration of any such claim, dispute or other matter may be made until the earlier of (1) the date on which the Architect has rendered a writ- ten decision, or (2) the tenth day after the parties have presented their evidence to the Architect or have been given a reasonable opportunity to do so, if the Architect has not rendered a written decision by that date. When such a written decision of the Architect states (1) that the decision is final but subject to appeal, and (2) that any demand for arbitration of a claim, dispute or other matter covered by such decision must be made within thirty days after the date on which the party making the demand re- ceives the written decision, failure to demand arbitration within said thirty day period will result in the Architect's decision becoming final and binding upon the Owner and the Contractor. If the Architect renders a decision after arbitration proceedings have been initiated, such decision may be entered as evidence but will not super- sede any arbitration proceedings unless the decision is acceptable to al,l parties concerned. 7 A201/CM - 1980 AlA DOCUMENT A20l/CM . GENERAL CONDITIONS OF THE CONTRACT fOR CONSTRUCTION CONSTRLCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlAe . @ 1980 . THE AMERICA'l INSTITUTE Of ARCHITECTS, 1735 NEW YORK AVE., N,W" WASHINGTON, D.C. 20006 WARNING: Unlicensed pholocopying violates U.S. copyright IlIWS ..nd Is sublecl~o legal prosecutl'!n. V~ 2.3.16 The Architect will have authority to reject Work which does not conform to the Contract'Documents, and to require special inspection or testing, but will take such action only after consultation with the Construction .'v1an- ager. Subject to review by the Architect, the Construction Manager will have the authority to reject Work which does not conform to the Contract Documents. Whenever, in the Construction Manager's opinion. it is considered necessary or advisable for the implementation of the in- tent of the Contract Documents, the Construction .\1an- ager will have authority to require special inspection or testing of the Work in accordance with Subparagraph 7.7.2 whether or not such Work be then fabricated, in- stalled or completed. The foregoing authority of the Con- struction Manager will be subject to the provisions of Subparagraphs 2.3.10 through 2.3.16, inclusive, with re- spect to interpretations and decisions of the Architect. However, neither the Architect's nor the Construction Manager's authority to act under this Subparagraph 2.3.16. nor any decision made by them in good faith either to exercise or not to exercise such authority shall give rise to anv duty or responsibility of the Architect or the Con- struction Manager to the Contractor, any Subcontractor, any of their agents or employees, or anv other person performing any of the Work. 2.3.17 The Construction Manager will receive from the Contractor and review all Shop Drawings. Product Data and Samples, coordinate them with information contained in related documents, and transmit to the Architect those recommended for approval. 2.3.18 The Architect will review and approve or take other appropriate action upon the Contractor's submittals such as Shop Drawings, Product Data and Samples, but only for conformance with the design concept of the Work and the information given in the Contract Docu- ments. Such action shall be taken with reasonable prompt- ness so as to cause no delay. The Architect's approval of a specific item shall not indicate approval of an assembly of which the item is a component. 2.3.19 Following consultation with the Construction Manager, the Architect will take appropriate action on Change Orders in accordance with Article 12, and will have authority to order minor changes in the Work as provided in Subparagraph 12.4.1. 2.3.20 The Construction Manager will maintain at the Project site one record copy of all Contracts, Drawings, Specifications, Addenda, Change Orders and other Modi- fications pertaining to the Project, in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples. These shall be available to the Archi- tect and the Contractor, and shall be delivered to the Architect for the Owner upon completion of the Project. 2.3.21 The Construction Manager will assist the Archi- tect in conducting inspections to determine the dates of Substantial Completion and final completion, and will receive and forward to the Owner for the Owner's review written warranties and related documents required by the Contract and assembled by the Contractor. The Architect will issue a final Project Certificate for Payment upon compliance with the requirements of Paragraph 9.9. 2.3.22 The duties, responsibilities and limitations of authority of the Architect and the Construction Manager as the Owner's representatives during construction as set forth in the Contract Documents, will not be modiiied or extended without written consent of the Owner, the Con- tractor, the Architect and the Construction Manager, which consent shall not be unreasonably withheld. Failure of the Contractor to respond within ten days to a wrillen request shall constitute consent by the Contractor. 2.3.23 In case of the termination of the employment of the Architect or the Construction Manager, the Owner shall appoint an architect or a construction manager against whom the Contractor makes no reasonable objec- tion and whose status under the Contract Documents shall be that of the former architect or construction man- ager, respectively. Any dispute in connection with such appointments shall be subject to arbitration. ARTICLE 3 OWNER 3.1 DEFINITION 3.1.1 The Owner is the person or entity identiiied as such in the Owner-Contractor Agreement. The term Owner means the Owner or the Owner's authorized representative. 3.2 INfORMATION AND SERVICES REQUIRED OF THE OWNER 3.2.1 The Owner shall, at the request of the Contractor, at the time of execution of the Owner-Contractor Agree- ment furnish to the Contractor reasonable evidence that the Owner has made financial arrangements to fultill the Owner's obligations under the Contract. Unless such reasonable evidence is furnished, the Contractor is not required to execute the Owner-Contractor Agreement or to commence the Work. 3.2.2 The Owner shall furnish all surveys describing the physical characteristics, legal limitations and utilih loca- tions for the site of the Project, and a legal descrip!;on of the site. 3.2.3 Except as provided in Subparagraph 4.7.1. the Owner shall secure and pay for necessary approvals. ease- ments, assessments and charges required for the construc- tion, use or occupancy of permanent structures or for permanent changes in existing facilities. 3.2.4 Information or services under the Owner's control shall be furnished by the Owner with reasonable prompt- ness to avoid delay in the orderly progress of the Work. 3.2.5 Unless otherwise provided in the Contract Docu- ments, the Contractor will be furnished. free of d:arge, all copies of Drawings and Specifications reasonabh nec- essary for the execution of the Work. 3.2.6 The Owner shall forward all instructions to the Contractor through the Construction Manager, with simul- taneous notification to the Architect. 3.2.7 The foregoing are in addition to other duties and responsibilities of the Owner enumerated herein and es- pecially those in respect to Work By Owner or By Sepa- rate Contractors, Payments and Completion, and Insur- ance in Articles 6, 9 and 11, respectively. AlA DOCUMENT A201/CM . GENERAL CONDITIONS OF THE CO!'llTRACT FOR CONSTRUCTION CO:>;STRUCTION MANAGEMENT EDITION . JUNE 19&:l EDITION . AlA. . ~ 1980 . THE A'IERlCAN INSTITUTE OF ARCHITECTS, 1735 'EW VORl.: AVE., N.W., WASHIr-.:GTON, D.C. 20006 A201/CM -1980 8 3.3 OWNER'S RIGHT TO STOP THE WORK 3.3.1 If the Contractor fails to correct defective Work as required by Paragraph 13.2, or persistently fails to carry out the Work in accordance with the Contract Docu- ments, the Owner, by a written order signed personally or by an agent specifically so empowered by the Owner in writing, may order the Contractor to stop the Work, or any portion thereof, until the cause for such order has been eliminated; however, this right of the Owner to stop the Work shall not give rise to any duty on the part of the Owner to exercise this right for the benefit of the Con- tractor or any other person or entity, except to the extent required by Subparagraph 6.1.3. 3.4 OWNER'S RIGHT TO CARRY OUT THE WORK 3.4.1. If the Contractor defaults or neglects to carry out the Work in accordance with the Contract Documents, and fails within seven days after receipt of written notice from the Owner to commence and continue correction of such default or neglect with diligence and promptness, the Owner may, after seven days following receipt by the Contractor of an additional written notice and without prejudice to any other remedy the Owner may have, make good such deficiencies. In such case an appropriate Change Order shall be issued deducting from the pay- ments then or thereafter due the Contractor the cost of correcting such deficiencies, including compensation for the Architect's and the Construction Manager's additional services made necessary by such default, neglect or fail- ure. Such action by the Owner and the amount charged to the Contractor are both subject to the prior approval of the Architect, after consultation with the Construction Manager. Ii the payments then or thereafter due the Con- tractor are not sufficient to cover such amount, the Con- tractor shall pay the difference to the Owner. ARTICLE 4 CONTRACTOR 4.1 DEfINITION 4.1.1 The Contractor is the person or entity identified as such in the Owner-Contractor Agreement. The term Con- tractor means the Contractor or the Contractor'S author- ized representative. 4.2 REVIEW OF CONTRACT DOCUMENTS 4.2.1 The Contractor shall carefully study and compare the Conlract Documents and shall at once report to the Architect and the Construction Manager any error, incon- sistency or omission that may be discovered. The Con- tractor shall not be liable to the Owner, the Architect or the Construction Manager for any damage resulting from any such errors. inconsistencies or omissions in the Con- tract Documents, The Contractor shall perform no portion of the \A;ork at any time ,\'ithout Contract Documents or, where required, approved Shop Drawings, Product Data or Samples for sllch portion of the Work. 4.3 SUPERVISION AND CONSTRUCTION PROCEDURES 4.3.1 The Contractor shall supervise and direct the Work, using the Contractor's best skill and attention. The Contractor shall be solely responsible for all construction means, methods, techniques, sequences and procedures; and shall coordinate all portions of the Work under the Contract, subject to the overall coordination of the COII- struction Manager. 4.3.2 The Contractor shall be responsible to the Owne, for the acts and omissions of the Contractor's employees, Subcontractors and their agents and employees, and any other persons performing any of the Work under a con- tract with the Contractor. 4.3.3 The Contractor shall not be relieved from the Contractor's obligations to perform the Work in accord- ance with the Contract Documents either by the activities or duties of the Construction Manager or the Architect in their administration of the Contract, or by inspections, tests or approvals required or performed under Paragraph 7.7 by persons other than the Contractor. 4.4 LABOR AND MATERIALS 4.4.1 Unless otherwise provided in the Contract Docu- ments, the Contractor shall provide and pay for all labor, materials, equipment, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities and services necessary for the proper execution and completion of the Work, whether temporary or per- manent and whether or not incorporated or to be incor- porated in the Work. 4.4.2 The Contractor shall at all times enforce strict dis- cipline and good order among the Contractor's em- ployees and shall not employ on the Work any unfit per- son or anyone not skilled in the task assigned them. 4.5 WARRANTY 4.5.1 The Contractor warrants to the Owner, the Archi- tect and the Construction Manager that all materials and equipment furnished under this Contract will be new U! less otherwise specified, and that all Work will be of gOOl. quality, free from faults and defects and in conformance with the Contract Documents. All Work not conforming to these requirements, including substitutions not prop- erly approved and authorized, may be considered defec- tive. If required by the Architect or the Construction Man- ager, the Contractor shall furnish satisfactory evidence as to the kind and quality of materials and equipment. This warranty is not limited bv the provisions of Paragraph 13.2. 4.6 TAXES 4.6.1 The Contractor shall pay all sales. consumer, use and other similar taxes for the Work or portions thereof provided by the Contractor which are legally enacted at the time bids are received, whether or not yet effective. 4.7 PERMITS, FEES AND NOTICES 4.7.1 Unless otherwise provided in the Contract Docu- ments, the Owner shall secure and pay for the building permit and the Contractor shall secure and pay for all other permits and governmental fees. licenses and inspec- tions necessary for the proper execution and completion of the Work which are customarily secured after execu- tion of the Contract and which are legally required at the time bids are received. 4.7.2 The Contractor shall give all notices and comply with all laws, ordinances. rules, regulations and lawful orders of any public authority bearing on the perform- ance of the Work. 9 A201iCM -1980 AlA DOCUMEST A201/CM . GENERAL COPOo/OlTIONS OF THE CONTRACT FOR CONSTRUCTlO:-' CONSTRUCTIO, MANAGEMENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE AMERICAS I'STITUTE OF ARCHITECTS. 1735 NEW YORK AVE.. N.W.. WASHINGTON, D.C. 2{)(}()o L . ,_ _ _..... .~..... .:.....,...... _ I' e ...,......,.;;,.,kf 1~..~ ~nrt :t;. ~l.I'<P('t 10 'et!{~! ')~S{'{.' .' 4.7.3 It is not the responsibility of the Contractor to make certain that the Contract Documents are in accord- ance with applicable laws, statutes, building codes and regulations. If the Contractor observes that any of the Contract Documents are at variance therewith in any re- spect, the Contractor shall promptly notify the Architect and the Construction Manager in writing, and any neces- sary changes shall be accomplished by appropriate Modification. 4.7.4 If the Contractor performs any Work knowing it to be contrary to such laws, ordinances, rules and regula- tions, and without such notice to the Architect and the Construction Manager, the Contractor shall assume full responsibility therefor and shall bear all costs attributable thereto. 4.8 ALLOWANCES 4.8.1 The Contractor shall include in the Contract Sum all allowances stated in the Contract Documents. Items covered by these allowances shall be supplied for such amounts and by such persons as the Construction Man- ager may direct, but the Contractor will not be required to employ persons against whom the Contractor makes a reasonable obj-:?ction. 4.8.2 Unless otherwise provided in the Contract Docu- ments: .1 these allowances shall cover the cost to the Contractor, Jess any applicable trade discount, of the materials and equipment required by the allowance, delivered at the site, and all appli- cable taxes; .2 the Contractor's costs for unloading and han- dling on the site, labor, installation costs, over- head, profit and other expenses contemplated {or the original allowance shall be included in the Contract Sum and not in the allowance; .3 whenever the cost is more or less than the allowance, the Contract Sum shall be adjusted accordingly by Change Order. the amount of which will recognize changes, if any. in han- dling costs on the site, labor, installation costs, overhead, profit and other expenses. 4.9 SUPERINTENDENT 4.9.1 The Contractor shall employ a competent superin- tendent and necessary assistants who shall be in attend- ance at the Project site during the progress of the Work. The superintendent shall represent the Contractor and all communications given to the superintendent shall be as binding as if given to the Contractor. Important commu- nications shall be confirmed in writing. Other communi- cations shall be so confirmed on written request in each case. 4.10 CONTRACTOR'S CONSTRUCTION SCHEDULE 4.10.1 The Contractor, immediately after being awarded the Contract, shall prepare and submit for the Construc- tion Manager's approval a Contractor's Construction Schedule for the Work which shall provide {or expedi- tious and practicable execution of the Work. This sched- ule shall be coordinated by the Construction .\1anager with the Project Construction Schedule. The Contractor's Construction Schedule shall be revised as required by the conditions of the Work and the Project, subject to the Construction Manager's approval. 4.11 DOCUMENTS AND SAMPLES AT THE SITE 4.11.1 The Contractor shall maintain at the Project sile, on a current basis, one record copy of all Drawings, Specifications, Addenda, Change Orders and other Modi- fications, in good order and marked currently to record all changes made during construction, and approved Shop Drawings, Product Data and Samples. These shall be available to the Architect and the Construction Manager. The Contractor shall advise the Construction Manager on a current basis of all changes in the Work made during construction. 4.12 SHOP DRAWINGS, PRODUCT DATA AND SAMPLES 4.12.1 Shop Drawings are drawings, diagrams, schedules and other data specially prepared {or the Work by the Contractor or any Subcontractor, manufacturer, supplier or distributor to illustrate some portion of the Work. 4.12.2 Product Data are illustrations, standard schedules, performance charts, instructions, brochures, diagrams and other information furnished by the Contractor to illustrate a material, product or system for some portion of the Work. 4.12.3 Samples are physical examples which illustrate materials, equipment or workmanship, and establish standards by which the Work will be judged. 4.12.4 The Contractor shall prepare, review, approve and submit through the Construction Manager, with reason- able promptness and in such sequence as to cause no de- lay in the Work or in the work of the Owner or any sepa- rate contractor, all Shop Drawings, Product Data and Samples required by the Contract Documents. The Con- tractor shall cooperate with the Construction Manager in the Construction Manager's coordination of the Contrac- tor's Shop Drawings, Product Data and Samples with those of other separate contractors. 4.12.5 By preparing, approving and submitting Shop Drawings, Product Data and Samples, the Contractor rep- resents that the Contractor has determined and verified all materials, field measurements and field construction criteria related thereto, or will do 50 with reasonable promptness, and has checked and coordinated the infor- mation contained within such submittals with the require- ments of the Work, the Project and the Contract Docu- ments. 4.12.6 The Contractor shall not be relieved of responsibil- ity for any deviation from the requirements of the Con- tract Documents by the Architect's approval of Shop Drawings, Product Data or Samples under Subparagraph 2.3.18, unless the Contractor has specifically informed the Architect and the Construction Manager in writing of such deviation at the time of submission and the Archi- tect has given written approval to the specific devialion. The Contractor shall not be relieved {rom responsibility for errors or omissions in the Shop Drawings, Product Data or Samples by the Architect's approval of them. 4.12.7 The Contractor shall direct specific attention, in writing or on resubmitted Shop Drawings, Product Data or Samples, to revisions other than those requested by the Architect on previous submittals. "I" DOCUMENT A.101/CM . GENERAL CONDITIONS OF THE co~'nRACT FOR CO~STRUCT'ON CONSTRUCTION MAN."GEMENT EDITION . JUNE 1980 EDmON . AlA" . ~ 1980 . THE A'URICAN "STITUTE OF ARCHITECTS, 1735 NEW YORK AVE.. 'W.. WASHINGTON, D.C. ;!OO(lo. A201/CM -1980 10 ".;,'~~; t'.;c-t!_ 'I'>~::::-'........-;:,;.. .",~'i....,., 4.12.8 No portion of the \^.'ork requiring submission of a Shop Drawing, Product Data or Sample shall be com- menced until the submittal has been approved by the Architect as provided in Subparagraph 2.3.18. All such portions of the Work shall be in accordance with ap- proved submittals. 4.13 USE OF SITE 4.13.1 The Contractor shall confine operations at the site to areas permitted by law, ordinances, permits and the Contract Documents, and shall not unreasonably encum- ber the site with any materials or equipment. 4.13.2 The Contractor shall coordinate all of the Contrac- tor's operations with, and secure approval from, the Con- struction Manager before using any portion of the site. 4.14 CUTTING AND PATCHING OF WORK 4.14.1 The Contractor shall be responsible for all cutting, fitting or patching that may be required to complete the \Vork or to make its several parts fit together properly. 4.14.2 The Contractor shall not damage or endanger any portion of the Work or the work of the Ov.mer or any separate contractors by cutting, patching or otherwise altering any work, or by excavation. The Contractor shall not cut or otherwise alter the work of the Owner or any separate contractor except with the written consent of the Owner and of such separate con\ractor. The Contractor shall not unreasonabl\' withhold from the Owner or any separate contractor consent to cutting or otherwise alter- ing the'Work. 4.15 CLEANING UP 4.15.1 The Contractor shall at all times keep the premises free from accumulation of waste materials or rubbish caused by the Contractor's operations. At the completion of the Work, the Contractor shall remove all the Contrac- tor's waste materials and rubbish from and about the Project as well as all the Contractor's tools, construction equipment. machinery and surplus materials. 4.15.2 If the Contractor fails to clean up at the comple- tion of the Work, the Owner may do so as provided in Paragraph 3.4 and the cost thereof shall be charged to the Contractor. 4.16 COMMUNICATIONS 4.16.1 The Contractor shall forward all communications to the Owner and the Architect through the Construction Manager. 4.17 ROYALTIES AND PATENTS 4.17.1 The Contractor shall pay all royalties and license fees, shall defend all suits or claims for infringement of any patent rights and shall save the Owner and the Con- struction Manager harmless from loss on account thereof, except that the Owner, or the Construction Manager as the case may be, shall be responsible for all such loss when a particular design, process or the product of a par- ticular manufacturer or manufacturers is selected by such person or such person's agent. If the Contractor, or the Construction Manager as the case may be, has reason to believe that the design, process or product selected is an infringement of a patent, that party shall be responsible for such loss unless such information is promptly given to the others and also to the Architect. 4.18 INDEMNIFICATION 4.18.1 To the fuilest extent permitted by law, the Con- tractor shall indemnify and hold harmless the Owner, thl Architect. the Construction Manager, and their agents ana employees from and against all claims, damages, losses and expenses, including, but not limited to, attorneys' fees arising out of or resulting from the performance of the Work, provided that any such claim, damage, loss or expense (1) is attributable to bodily injury, sickness, dis- ease or death, or to injury to or destruction oi tangible property (other than the Work itself) including the loss of use resulting therefrom, and (2) is caused in whole or in part by any negligent act or omission oi the Contractor, any Subcontractor. anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, regardless of whether or not it is caused in part by a party indemnified hereur.der. Such obligation shall not be construed to negate, abridge or otherwise reduce any other right or obligation of indemnity which would othen,vise exist as to any party or person described in this Paragraph 4.18. 4.18.2 In any and all claims against the Owner, the Archi- tect, the Construction Manager or any of their agents or employees by any employee of the Contractor, any Sub- contractor, anyone directly or indirectly employed by any of them or anyone for whose acts any of them may be liable, the indemnification obligation under this Para- graph 4.18 shall not be limited in any way by any limita- tion on the amount or type of damages, compensation or beneiits payable by or for the Contractor or any Sub- contractor under workers' or workmen's compensation acts, disability benefit acts or other employee benefit acts. 4.18.3 The obligations of the Contractor under this Para graph 4.18 shall not extend to the liability of the Architec, or the Construction Manager, their agents or employees, arising out of (1 j the preparation or approval of maps, drawings, opinions, reports, surveys, Change Orders, de- signs or specifications, or (2) the giving of or the failure to give directions or instructions by the Architect or the Construction Manager, their agents or employees, pro- vided such giving or failure to give is the primary cause of the injury or damage. ARTICLE 5 SUBCONTRACTORS 5.1 DEFINITION 5.1.1 A Subcontractor is a person or entity who has a direct contract with the Contractor to perform any of the Work at the site. The term Subcontractor means a Sub- contractor or a Subcontractor's authorized representative. The term Subcontractor does not include any sepa rate contractor or any separate contractor's subcontractors, 5.1.2 A Sub-subcontractor is a person or entity who has a direct or indirect contract with a Subcontractor to per- form any of the Work at the site, The term Sub-subcon- tractor means a Sub-subcontractor or an authorized rep- resen ta tive thereof. 5.2 AWARDS OF SUBCONTRACTS AND OTHER CONTRAaS FOR PORTIONS OF THE WORK 5.2.1 Unless otherwise required by the Contract Docu 11 A201/CM - 1980 ,\IA OOCUMENT A201/CM . GESERAL CosDITIONS OF THE COSTR,\CT FOR COSSTRUCTlO~ CONSTRUCTION M."NAGEME~T EDITION . JUNE 1980 EDITION . AlAe . @ 1980 . THE AMERICA~ INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" N,W., WASHINGTOS, o,c. 2000& \)0" cu ""1~. I t,..,li....,.,....c..:..4 ... 1~""'.n('l"\l"l"in,., \,h'~'~c:. tIC:; ~rv'vr;~ht 12W$ 2,,(1 i5 SUb:K1 to::- lpo~l orosecution ments Or the Bidding Documents, the Contractor, as soon as practicable after the award of the Contract, shall fur- nish to the Construction Manager in writing for review by the Owner, the Architect and the Construction Man- ager, the names of the persons or entities (including those who are to furnish materials or equipment fabricated to a special design) proposed for each of the principal por- tions of the Work. The Construction Manager will promptly reply to the Contractor in writing stating whether or not the Owner, the Architect or the Con- struction Manager, after due investigation, has reasonable objection to any such proposed person or entity. Failure of the Construction Manager to reply promptly shall con- stitute notice of no reasonable objection. 5.2.2 The Contractor shall not contract with any such proposed person or entity to whom the Owner, the Ar- chitect or the Construction Manager has made reasonable objection under the provisions of Subparagraph 5.2.1. The Contractor shall not be required to contract with anyone to whom the Contractor has a reasonable objection. 5.2.3 If the Owner, the Architect or the Construction Manager has reasonable objection to any such proposed person or entity, the Contractor shall submit a substitute to whom the Owner, the Architect and the Construction Manager have no reasonable objection, and the Contract Sum shall be increased or decreased by the difference in cost occasioned by such substitution and an appropriate Change Order shall be issued; however, no increase in the Contract Sum shall be allowed for any such substitu- tion unless the Contractor has acted promptly and re- sponsively in submitting names as required by Subpara- graph 5.2.1. 5.2.4 The Contractor shall make no substitution for any Subcontractor, person or entity previously selected if the Owner, the Architect or the Construction Manager makes reasonable objection to such substitution. 5.3 SUBCONTRACTUAl RELATIONS 5.3.1 By an appropriate agreement, written where legally required for validity, the Contractor shall require each Subcontractor, to the extent of the Work to be performed by the Subcontractor, to be bound to the Contractor by the terms of the Contract Documents, and to assume to- ward the Contractor all the obligations and responsibili- ties which the Contractor. by these Documents, assumes toward the Owner, the Architect and the Construction Manager. Said agreement shall preserve and protect the rights of the Owner, the Architect and the Construction Manager under the Contract Documents with respect to the Work to be performed by the Subcontractor so that the subcontracting thereof will not prejudice such rights, and shall allow to the Subcontractor, unless specifically provided otherwise in the Contractor-Subcontractor Agreement. the benefit of all rights, remedies and redress against the Contractor that the Contractor, by these Docu- ments, has against the Owner. Where appropriate, the Contractor shall require each Subcontractor to enter into similar agreements with their Sub-subcontractors. The Contractor shall make available to each proposed Sub- contractor, prior to the execution of the Subcontract, copies of the Contract Documents to which the Subcon- tractor will be bound by this Paragraph 5.3, and identify to the Subcontractor any terms and conditions of the pro- posed Subcontract which may be at variance ",,;;11 the Contract Documents. Each Subcontractor shall similarly make copies of such Documents available to their Sub- subcontractors. ARTICLE 6 WORK BY OWNER OR BY SEPARATE CONTRACTORS 6.1 OWNER'S RIGHT TO PERfORM WORK AND TO AWARD SEPARATE CONTRACTS 6.1.1 The Owner reserves the right to perform work re- lated to the Project with the Owner's own forces, and to award separate contracts in connection with other por- tions of the Project or other work on the site under these or similar Conditions of the Contract. If the Contractor claims that delay, damage or additional cost is involved because of such action by the Owner, the Contractor shall make such claim as provided elsewhere in the Contract Documents. 6.1.2 When separate contracts are awarded for different portions of the Project or other work on the site, the term Contractor in the Contract Documents in each case shall mean the Contractor who executes each separate Owner- Contractor Agreement. 6.1.3 The Owner will provide for the coordination of the work of the Owner's own forces and of each separate contractor with the Work of the Contractor, who shall cooperate therewith as provided in Paragraph 6.2. 6.2 MUTUAL RESPONSIBILITY 6.2.1 The Contractor shall afford the Owner, the Con- struction Manager and separate contractors reasonable opportunity for the introduction and storage of their ma- terials and equipment and the execution of their work, and shall connect and coordinate the Work with theirs as required by the Contract Documents. 6.2.2 If any part of the Contractor's Work depends for proper execution or results upon the work of the Owner or any separate contractor, the Contractor shall, prior to proceeding with the Work, promptly report to the Con- struction Manager any apparent discrepancies or defects in such other work that render it unsuitable for such proper execution and results. Failure of the Contractor so to report shall constitute an acceptance of the Owner's or separate contractor's work as fit and proper to receive the Work, except as to defects which may subsequently become apparent in such work by others. 6.2.3 Any costs caused by defective or ill-timed work shall be borne by the party responsible therefor. 6.2.4 Should the Contractor wrongfully cause damage to the work or property of the Owner, or to other work or property on the site, the Contractor shall promptly rem- edy such damage as provided in Subparagraph 10.2.5. 6.2.5 Should the Contractor wrongfully delay or cause damage to the work or property of any separate contrac- tor, the Contractor shall, upon due notice. promptly at- tempt to settle with such other contractor by agreement, or otherwise to resolve the dispute. If such separate con- tractor sues or initiates an arbitration proceeding against the Owner on account of any delay or damage alleged to have been caused by the Contractor, the Owner shall AlA DOCUMENT A201/CM . GENERAL CONDITIONS Of THE CO!>;TRACT fOR CONSTRUCTION COr-;STRUCTIO:-.: /l.1ANAGEMENT EDITION . JUNE 1980 EDITIO!l: . AlAe . @ 1980 . THE AMERICAN I'STITUTE Of ARCHITECTS, 173S NEW YORK AVE" N.W., WASHINGTON, D.C. 20006 A201/CM - 1980 12 notify the Contractor who sh,,11 defend such proceedings at the Owner's expense, and if any judgment or award against the Owner arises therefrom, the Contractor shall payor satisfy it and shall reimburse the Owner for all attorneys' fees and court or arbitration costs which the Owner has incurred, 6.3 OWNER'S RIGHT TO CLEAN UP 6.3.1 If a dispute arises between the Contractor and separate contractors as to their responsibility for cleaning up as required by Paragraph 4.15, the Owner may clean up and charge the cost thereof to the contractors respon- sible therefor as the Construction Manager shall deter- mine to be just. ARTICLE 7 MISCELLANEOUS PROVISIONS 7.1 GOVERNING lAW 7.1.1 The Contract shall be governed by the law of the place where the Project is located. 7.2 SUCCESSORS AND ASSIGNS 7.2.1 The Owner and the Contractor, respectively, bind themselves, their partners, successors, assigns and legal representatives to the other party hereto and to the part- ners, successors, assigns and legal representatives of such other party with respect to all covenants, agreements and obligations contained in the Contract Documents. Neither party to the Contract shall assign the Contract or sublet it as a whole without the written consent of the other. 7.3 WRITTEN NOTICE 7.3.1 Written notice shall be deemed to have been duly served if delivered in person to the individual or mem- ber of the firm or entity or to an officer of the corpora- tion for whom it was intended, or if delivered at or sent by registered or certified mail to the last business address known to the party giving the notice. 7.4 CLAIMS FOR DAMAGES 7.4.1 Should either party to the Contract suffer injury or damage to person or property because of any act or omis- sion of the other party or of any of the other party's employees, agents or others for whose acts such party is legally liable, claim shall be made in writing to such other party within a reasonable time after the first observ- ance of such injul) or damage. 7.5 PERFORMANCE BOND AND LABOR AND MATERIAL PAYMENT BOND 7.5.1 The Owner shall have the right to requi re the Contractor to furnish bonds covering the faithful perform- ance of the Contract and the payment of all obligations arising thereunder if and as required in the Bidding Doc- uments or the Contract Documents. 7.6 RIGHTS AND REMEDtES 7.6.1 The duties and obligations imposed by the Con- tract Documents and the rights and remedies available thereunder shall be in addition to, and not a limitation of, any duties, obligations, rights and remedies otherwise im- posed or available by law, 7.6.2 No action or failure to act by the Owner, the Ar- chitect, the Comtruction Manager or the Contractor shall constitute a waiver of any right or duty afforded any of them under the Contract, nor shall any such action or failure to act constitute an approval of or acquiescence in any breach thereunder, except as may be specifically agreed in writing. 7.7 TESTS 7.7.1 If the Contract Documents, laws, ordinances, rules, regulations or orders of any public authority having juris- diction require any portion of the Work to be inspected, tested or approved, the Contractor shall give the Architect and the Construction Manager timely notice of its readi- ness so the Architect and the Construction Manager may observe such inspection, testmg or approval. The Con- tractor shall bear all costs of such inspections, tests or approvals conducted by public authorities. Unless other- wise provided, the Owner shall bear all costs of other in- spections, tests or approvals. 7.7.2 If the Architect or the Construction Manager deter- mines that any Work requires special inspection, testing or approval which Subparagraph 7.7.1 does not include, the Construction Manager will, upon written authoriza- tion from the Owner, instruct the Contractor to order such special impection, testing or approval, and the Con- tractor shall give notice as provided in Subparagraph 7.7.1. If such special inspection or testing reveals a failure of the Work to compiy with the requirements of the Con- tract Documents, the Contractor shall bear all costs thereof, including compensation for the Architect's and the Construction Manager's additional services made nec- essary by such failure; otherwise the O\\ner shall bear such costs, and an c: ppropriate Change Order shall be issued. 7.7.3 Required certiiicates of inspection, testing or ap- proval shall be secu'ed by the Contractor and the Con- tractor shall promptly deliver them to the Construction Manager iar transmi::al to the Architect. 7.7.4 If the Architect or the Construction Manager wishes to observe the inspections, tests or approvals required by the Contract Documents. they will do so promptly and, where practicable, at the source of supply. 7.8 INTEREST 7.8.1 Payments due and unpaid under the Contract Doc- uments shall bear interest from the date pavment is due at such ra:e as the parties may agree upor in writing or, in the absence thereof, at the legal rate prevailing at the place of the Project. 7.9 ARBITRA TION 7.9.1 All claims, di;putes and other matters in question between the Contractor and the Owner ari;ing out of or relating to the Contrc:ct Documents or the breach thereof. except as prO\ided ;:"1 Subparagraph 2.3.14 with respect to the Architect's decisions on matters relating to artistic effect, and except for claims which have been waived by the making or accep~ance of iinal payment as provided by Subparagraphs 9.?A through 9,9.6. inclusive, shall be decided bv arbitration in accordance with the Construc- tion Industry Arbitration Rules of the American Arbitra- tion Association then obtaining unless the parties mutually 13 A201/CM - 1980 AlA DOCUMENT A201/CM . GE,,~>'L CO-':DIT"O-':S OF THE CONTRACT FOt CO:-':SHL'CTlON CONSTRUCTlOS MANAGEMEST ,:J1TI0" . l"_"E 1980 EDITION . AlAe . ~ 1980 . THE AMERICAN INSTITUTE OF ARCH1;ECTS. ,;35 :-'E",\' YORK AVE., N.W" WASH1'GTON, D.C. 2()()()b "" ~,,".l""'. 11...1._...__. "" _...,....,.........~_..;...._ :^I~fDc:':! c:: ....",..\.'.,,-...,4 I;3VJ~ ~...,:-' ic: ~ _:hiect.: 'co~f (H'O'.:iecufion. agree otherwise. No arbitration arising out of or relating to the Contract Documents shall include, by consolida- tion, jOinder or in any other manner, the Architect, the Construction Manager, their employees or consultants except by written consent containing a specific reference to the Owner-Contractor Agreement and signed by the Architect, the Construction Manager, the Owner, the Contractor and any other person sought to be joined. No arbitration shall include by consolidation, joinder or in any other manner, parties other than the Owner, the Contractor and any other persons substantially involved in a common question of fact or law, whose presence is required if complete relief is to be accorded in the arbi- tration. No person other than the Owner or the Contrac- tor shall be included as an original third party or addi- tional third party to an arbitration whose interest or re- sponsibility is insubstantial. Any consent to arbitration involving an additional person or persons shall not con- stitute consent to arbitration of any dispute not described therein or with any person not named or described therein. The foregoing a&"eement to arbitrate and any other agreement to arbitrate with an additional person or persons duly consented to by the parties to the Owner- Contractor Agreement shall be specifically enforceable under the prevailing arbitration law. The award rendered by the arbitrators shall be final. and judgment ma~ be en- tered upon it in accordance with applicable la\\ in any court having jurisdiction thereof. 7.9.2 Notice of the demand for arbitration shall be filed in writing with the other party to the Owner-Contractor Agreement and with the American Arbitration Associa- tion, and a copy shall be filed with the Architect and the Construction Manager. The demand for arbitration shall be made within the time limits specified in Subparagraph 2.3.15 where applicable. and in all other cases within a reasonable time after the claim. dispute or other matter in question has arisen; and in no event shall it be made after the date when institution of legal or equitable pro- ceedings based on such claim. dispute or other matter in question \,vould be barred by the applicable statute of limitations. 7.9.3 Unless otherwise agreed in writing. the Contractor shall carry on the Work and maintain its progres~ during any arbitration proceedings. and the Owner shall con- tinue to make payments to the Contractor in accordance with the Contract Documents. ARTICLE 8 TIME 8.1 DEFINITIONS 8.1.1 Unless otherwise provided, the Contract Time is the period of time allotted in the Contract Docurr.ents for Substantial Completion of the Work as defined in Sub- paragraph 8.1.3, including authorized adjustments :hereto. 8.1.2 The date of commencement of the War:' is the date e~tablished in a notice to proceed. If there is no no- tice to proceed. it shall be such other date a~ may be established in the Owner-Contractor Agreement or else- where in the Contract Document~. 8.1.3 The Date of Substantial Completion of the Work or designated portion thereof is the Date certified by the Architect when construction is sufficiently complete, in accordance with the Contract Documents, so that the Owner or separate contracto~s c~n occupy or utilize the Work or a designated portion thereof lbr the use (or which it is intended. 8.1.4 The Date of Substantial Completion of the Project or designated portion thereof is the Date certified by the Architect when construction is sufficiently complete so the Owner can occupy or utilize the Project or designated portion thereof for the use for which it was intended. 8.1.5 The term day as used in the Contract Documents shall mean calendar day unless specifically designated otherwise. 8.2 PROGRESS AND COMPLETION 8.2.1 All time limits stated in the Contract Documents are of the essence of the Contract. 8.2.2 The Contractor shall begin the Work on the date of commencement as defined in Subparagraph 8.1.2. The Contractor shall carry the Work forward expeditiously with adequate forces and shall achieve Substantial Com- pletion of the Work within the Contract Time. 8.3 DELAYS AND EXTENSIONS OF TIME 8.3.1 If the Contractor is delayed at any time in the progress of the Work by any act or neglect of the Owner, the Architect, the Construction Manager, any of their em- ployees. any separate contractor employed by the Owner, or by changes ordered in the Work, labor disputes, fire. unusual delay in transportation. adverse weather condi- tions not reasonably anticipatable, unavoidable casualties, any causes beyond the Contractor's control, delay author- ized by the Owner pending arbitration. or by any other cause which the Construction Manager determines may justify the delay, then the Contract Time shall be ex- tended by Change Order for such reasonable time as the Construction Manager may determine. 8.3.2 Any claim for extension of time shall be made in writing to the Construction Manager not more than twenty days after the commencement of the delay; other- wise it shall be waived. In the case of J continuing dela\ only one claim is necessary. The Contractor shall provide an estimate of the probable efiect of such delay on the progress of the Work. 8.3.3 If no agreement is made stating the dates upon which interpretations as provided in Subparagraph 2.3,11 shall be furnished. then no c1,lim for delay shall be allowed on account of failure to furnish such interpreta- tions until iifteen da~ s after \\ ritten request is made for them. and not then unless such claim is reasonable, 8.3.4 This Paragraph 8.3 does not exclude the recoverv of damages for delay by either party under other provi- sions of the Contract Document<, ARTICLE 9 PAYMENTS AND COMPLETION 9.1 CONTRACT SUM 9.1.1 The Contract Sum is qaled in the Owner-Contrac- tor Agreement and, including authorized adjustment~ thereto. is the total amount payable by the Owner to the Contractor for the performance of the Work under the Contract Documents. A'A DOCUMENT A201iCM . GE~ERAl CO:-;DITIO'-'S OF THE CC'TRACT FOR C01'STRUCTIO:-; COSSTRLCTIO~ .\IA:-':AGEME1'T EDITION . ILSE 1980 EDIlIO"" . AI^~ . @ 1980 . THE AMERICA" INSTITUE OF ARCHITECTS, 1i3; 'E\\' YORK AVE.. "W., WASHINGTON, D.C. ~ A201/CM -1980 14 ~-~:,... .- ~~. '.....~....~- --, 9.2 SCHEDULE OF VALUES 9.2.1 Before the firq Application for Payment. the Con- tractor shall submit to the Construction Manager a schedule of values allocated to the various portions of the Work, prepared in such form and supported by such data to substantiate its accuracy as the Architect and the Con- struction Manager may require, This schedule, unless objected to by the Construction Manager or the Architect, shall be used only as a basis for the Contractor's Applica- tions for Payment. 9.3 APPLICATIONS FOR PAYMENT 9.3.1 At least fifteen days before the date for each progress payment established in the Owner-Contractor Agreement, the Contractor shall submit to the Construc- tion Manager an itemized Application for Payment, notar- ized if required, supported by such data substantiating the Contractor's right to payment as the Owner, the Ar- chitect or the Construction Manager may require, and re- flecting retainage, if any, as provided elsewhere in the Contract Documents, The Construction Manager will as- ~emble the Application with similar applications from other contractors on the Project into a combined Project Application for Payment and forward it with recommen- dations to the Architect within seven days. 9.3.2 Unless otherwise provided in the Contract Docu- ments, payments will be made on account of materials or equipment not incorporated in the Work but delivered and suitably stored at the site and, if approved in advance by the Owner, payments may similarly be made for mate- rials or equipment suitably stored at some other loca- tion agreed upon in writing. Payments for materials or equipment stored on or off the site shall be conditioned upon submission by the Contractor of bills of sale or such other procedures satisfactory to the Owner to estab- lish the Owner's title to such materials or equipment or otherwise protect the Owner's interest, including applica- ble insurance and transportation to the site for those materials and equipment stored on the site. 9.3.3 The Contractor warrants that title to all Work, materials and equipment covered by an Application for Payment will pass to the Owner either by incorporation in the construction or upon receipt of payment by the Contractor, whichever occurs first. free and clear of all liens, claims, security interests or encumbrances, herein- aiter referred to in this Article 9 as "liens"; and that no \\lork, materials or equipment covered by an Application for Payment will have been acquired by the Contractor, or by any other person performing Work at the site or furnishing materials and equipment for the Project, sub- ject to an agreement under which an interest therein or an encumbrance thereon is retained by the seller or oth- erwise imposed by the Contractor or such other person, 9.4 CERTIFICATES FOR PAYMENT 9.4.1 The Architect will, within seven days after the re- ceipt of the Project Application for Payment with the rec- ommendations of the Construction Manager, review the Project Application for Payment and either issue a Project Certificate for Payment to the Owner with a copy to the Construction Manager for distribution to the Contractor for such amounts as the Architect determines are prop- erly due, or notify the Construction Manager in writing of the reasons for withholding a Certificate as provided in Subparagraph 9.6.1, Such notification will be forwarded to the Contractor by the Construction Manager. 9.4.2 The issuance of a Project Certificate for Pa)'ment will constitute a representation by the Architect to the Owner that, based on the Architect's observations at the site as provided in Subparagraph 2.3.4 and the data com- prising the Project Application for Payment, the Work has progressed to the point indicated; that, to the best of the Architect's knowledge, information and belief, the quality of the Work is in accordance with the Contract Docu- ments (subject to an evaluation of the Work for conform- ance with the Contract Documents upon Substantial Completion of the Work, to the results of any subsequent tests required by or performed under the Contract Docu- ments, to minor deviations from the Contract Documents correctable prior to completion, and to any specific quali- fications stated in the Certificate); and that the Contrac- tor is entitled to payment in the amount certified. How- ever, by issuing a Project Certificate for Pa\ment. the Ar- chitect shall not thereby be deemed to rep'resent that the Architect has made exhaustive or continuous on-site in- spections to check the quality or quantity of the Work, has reviewed the construction means, methods, tech- niques, sequences or procedures, or has made any exam- ination to ascertain how or for what purpose the Contrac- tor has used the monies previously paid on account of the Contract Sum. 9.5 PROGRESS PAYMENTS 9.5.1 After the Architect has issued a Project Certificate for Payment, the Owner shall make payment in the man- ner and within the time provided in the Contract Docu- ments. 9.5.2 The Contractor shall promptly pay each Subcon- tractor upon receipt of payment from the Owner, out of the amount paid to the Contractor on account of such Subcontractor's Work, the amount to which said Subcon- tractor is entitled, reflecting the percentage actually re- tained, if any, from payments to the Contractor on ac- count of such Subcontractor's Work. The Contractor shall, by an appropriate agreement with each Subcontractor, require each Subcontractor to make payments to their Sub-subcontractors in similar manner. 9.5.3 The Architect may, on request and at the Archi- tect's discretion, furnish to any Subcontractor, if prac- ticable, information regarding the percentages of com- pletion or the amount, applied for by the Contractor and the action taken thereon by the Architect on account of Work done by such Subcontractor. 9.5.4 Neither the Owner, the Architect nor the Construc- tion I\1anager shall have any obligation to payor to see to the payment of any monies to any Subcontractor except as may otherwise be required by law. 9.5.5 No certification of a progress payment, any prog- ress payment, or any partial or entire use or occupancy oi the Project by the Owner, shall constitute an accept- ance of any Work not in accordance with the Contract Documents. 9.6 PAYMENTS WITHHELD 9.6.1 The Architect, following consultation with the Construction Manager, may decline to certify payment 15 A201/CM -1960 AlA DOCUMENT A201/CM . GENERAL CO~DITIO"S OF THE CONTRACT FOIt CONSTRl'CTION COSSTRUCTION MAt\AGEMENT EDITION . jU"'E 1980 EDITION . AlA- . @ 1980 . THE AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE.. N.W., WASHI"'GTON, D.C. 20006 '.'~D'."Ur:. 11....f;,-"'...t:-c..t'..... .....tr -'''''''''''t!"'n ,.;.....l'::l.t',~ 11 ~ ,.."n\f~;...t-.t '~.ws and i~ subll?c. tt"\ I~";!il o"O~p~utlo". and may withhold the Certificate in whole or in part to the extent necessary to reasonably protect the 0" ner, if, in the Architect's opinion, the Architect is unable to make representations to the Owner as provided in Subpara- graph 9.4.2. If the Architect is unable to make representa- tions to the Owner as provided in Subparagraph 9.4.2, and to certify payment in the amount of the Project Ap- plication, the Architect will notify the Construction Man- ager as provided in Subparagraph 9.4.1, If the Contractor and the Architect cannot agree on a revised amount, the Architect will promptly issue a Project Certificate for Pay- ment for the amount for which the Architect is able to make such representations to the Owner. The Architect may also decline to certify payment or, because of subse- quently discovered evidence or subsequent observations, the Architect may nullify the whole or any part of any Project Certificate for Payment previously issued to such extent as may be necessary, in the Architect's opinion, to protect the Owner from loss because of: .1 defective Work not remedied; .2 third party claims filed or reasonable evidence in- dicating probable filing of such claims; .3 failure of the Contractor to make payments prop- erly to Subcontractors, or for labor, materials or equipment; .4 reasonable evidence that the Work cannot be com- pleted for the unpaid balance of the Contract Sum; .5 damage to the Owner or another contractor; .6 reasonable evidence that the Work will not be completed within the Contract Time; or .7 persistent failure to carry out the Work in accord- ance with the Contract Documents. 9.6.2 When the grounds in Subparagraph 9.6.1 above are removed, payment shall be made for amounts with- held because of them. 9.7 FAILURE OF PAYMENT 9.7.1 If the Construction Manager should fail to issue recommendations within seven days of receipt of the Contractor's Application for Payment, or if, through no fault of the Contractor, the Architect does not issue a Project Certificate for Payment within seven days after the Architect's receipt of the Project Application for Pay- ment, or if the Owner does not pay the Contractor within seven days after the date established in the Contract Doc- uments any amount certified by the Architect or awarded by arbitration, then the Contractor may, upon seven addi- tional days' written notice to the Owner, the Architect and the Construction Manager, stop the Work until pay- ment of the amount owing has been received. The Con- tract Sum shall be increased by the amount of the Con- tractor's reasonable costs of shut-down, delay and start- up, which shall be effected by appropriate Change Order in accordance with Paragraph 12.3. 9.8 SUBSTANTIAL COMPLETION 9.8.1 When the Contractor considers that the Work, or a designated portion thereof which is acceptable to the Owner, is substantially complete as defined in Subpara- graph 8.1.3, the Contractor shall prepare for the Construc- tion Manager a list of items to be completed or cor- rected. The failure to include any items on such list does not alter the responsibility of the Contractor to complete all Work in accordance with the Contract Documents. When the Architect, on the basis of inspection and con- sultation with the Construction Manager, determines that the Work or designated portion thereof is substantially complete, the Architect will then prepare a Certificate of Substantial Completion of the Work which shall establish the Date of Substantial Completion of the Work, shall state the responsibilities of the Owner and the Contractor for security, maintenance, heat, utilities. damage to the Work and insurance, and shall fix the time within which the Contractor shall complete the items listed therein. The Certificate of Substantial Completion of the Work shall be submitted to the Owner and the Contractor for their written acceptance of the responsibilities assigned to them in such Certificate. 9.8.2 Upon Substantial Completion of the Work or desig- nated portion thereof, and upon application by the Con- tractor and certification by the Architect. the Owner shall make payment, reilecting adjustment in retainage, if any, for such Work or portion thereof as provided in the Con- tract Documents. 9.8.3 When the Architect, on the basis of inspections, delermines that the Project or designated portion thereof is substantially complete, the Architect will then prepare a Certificate of Substantial Completion of the Project which shall establish the Date of Substantial Completion ot the Project and fix the time within which the Contrac- tor shall complete any uncompleted items on the Certif- icate of Substantial Completion of the Work. 9.8.4 Warranties required by the Contract Documents shall commence on the Date ot Substantial Completion of the Project or designated portion thereof unless other- wise provided in the Certificate of Substantial Comple- tion of the \Vork or designated portion thereof. 9.9 FINAL COMPLETION AND FINAL PAYMENT 9.9.1 Following the Architect's issuance of the Certiiicate of Substantial Completion of the Work or designated por- tion thereof, and the Contractor's completion of the Work, the Contractor shall forward to the Construction Manager a written notice that the Work is ready for final inspection and acceptance, and shall also forward to the Construction Manager a final Application for Payment. Upon receipt, the Construction .\\anager will make the necessary evaluations and forward recommendations to the Architect who will promptly make such inspection. When the Architect finds the Work acceptable under the Contract Documents and the Contract fully per- formed, the Architect will issue a Project Certificate for Payment which will approve the iinal payment due the Contractor. This approval will constitute a representation that, to the best of the Architect's knowledge, informa- tion and belief, and on the basis of observations and in- spections, the Work has been completed in accordance with the Terms and Conditions of the Contract Docu- ments and that the entire balance found to be due the Contractor, and noted in said Certificate, is due and pay- able. The Architect's approval of said Project Certificate for Payment will constitute a further representation that the conditions precedent to the Contractor's being en- titled to final payment as set forth in Subparagraph 9.9.2 have been fulfilled. All. DOCUMENT A201/CM . GENERAL CONDITlO....S OF THE CO!'.iTRACT FOR CONSTRUCTION CO,,"'STRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE AMERICAN INSTITUTE OF ARCHITECTS. 173S NEW YORK AVE.. KW.. WASHI!'GTON, D.C 20006 A201/CM -1980 16 V/" PN,...,r:. ! 'f"'ltr....pnct:l.~ I""lh,...,fl""\('("trr'/i,,-::; vi~l("~('~ I." S CC'::J\'''~O'''1 fEW.>"; ;incf ic; ~; 'biecf '(' ie-gaf oro~ecution. 9.9.2 Neither the final payment nor the remaining retain- age shall become due until the Contractor submits to the Architect, through the Construction Manager, (1) an affi- davit that all payrolls, bills for materials and equipment, and other indebtedness connected with the Work for which the 6wner or the Owner's property might in any way be responsible, have been paid or otherwise satis- fied, (2) consent of surety, if any, to final payment, and (3) if required by the Owner, other data establishing pay- ment or satisfaction of all such obligations, such as re- ceipts, releases and waivers of liens arising out of the Contract. to the extent and in such form as may be desig- nated by the Owner. If any Subcontractor refuses to fur- nish a release or waiver required by the Owner, the Con- tractor may furnish a bond satisfactory to the Owner to indemnify the Owner against any such lien. If any such lien remains unsatisfied after all payments are made, the Contractor shall refund to the Owner all monies that the latter may be compelled to pay in discharging such lien, including all costs and reasonable attorneys' fees. 9.9.3 If, after Substantial Completion of the Work, final completion thereof is materially delayed through no fault of the Contractor or by the issuance of Change Orders affecting final completion, and the Construction Manager so confirms, the Owner shall, upon application by the Contractor and certification by the Architect and without terminating the Contract, make payment of the balance due for that portion of the Work fully completed and accepted. If the remaining balance for Work not fully completed or corrected is less than the retainage stipu- lated in the Contract Documents, and if bonds have been furnished as provided in Paragraph 7.5, the written con- sent of the surety to the payment of the balance due for that portion of the Work fully completed and accepted shall be submitted by the Contractor to the Construction Manager prior to certification of such payment. Such pay- ment shall be made under the Terms and Conditions gov- erning final payments, except that it shall not constitute a waiver of claims. 9.9.4 The making of final payment shall, after the Date of Substantial Completion of the Project, constitute a waiver of all claims by the Owner except those arising from: .1 unsettled liens; .2 faulty or defective Work appearing after Substan- tial Completion of the Work; .3 failure of the Work to comply with the require- ments of the Contract Documents; or .4 terms of any special warranties required by the Contract Documents. '9.9.5 The acceptance of final payment shall, after the Date of Substantial Completion of the Project, constitute a waiver of all claims by the Contractor except those pre\ iously made in writing and identified by the Contrac- tor as unsettled at the time of the final Application for Payment. 9.9.6 All provisions of this Agreement. including with- out limitation those establishing obligations and proce- dures, shall remain in full force and effect notwithstand- ing the making or acceptance of final payment prior to the Date of Substantial Completion of the Project. ARTICLE 10 PROTECTION OF PERSONS AND PROPERTY 10.1 SAFETY PRECAUTIONS AND PROGRAMS 10.1.1 The Contractor shall be responsible for initiating, mainlaining and supervising all safety precautions and programs in connection with the Work. 10.2 SAFETY OF PERSONS AND PROPERTY 10.2.1 The Contractor shall take all reasonable precau- tions for the safety of, and shall provide all reasonable protection to prevent damage, injury or loss to: .1 all employees on the Work and all other persons who may be affected thereby; .2 all the Work and all materials and equipment to be incorporated therein, whether in storage on or off the site, under the care, custody or control of the Contractor or any of the Contractor's Subcon- tractors or Sub-subcontractors; .3 other property at the site or adjacent thereto, in- cluding trees, shrubs, lawns, walks, pavements, roadways, structures and utilities not designated for removal, relocation or replacement in the course of construction; and .4 the work of the Owner or other separate contrac- tors. 10.2.2 The Contractor shalf give all notices and comply with all applicable laws, ordinances, rules, regulations and lawful orders of any public authority bearing on the safety of persons or property or their protection from damage, injury or loss. 10.2.3 The Contractor shall erect and maintain, as re- quired by existing conditions and the progress of the Work, all reasonable safeguards for safety and protection, including posting danger signs and other warnings against hazards, promulgating safety regulations and notifying owners and users of adjacent utilities. 10.2.4 When the use or storage of explosives or other hazardous materials or equipment is necessary for the execution of the Work, the Contractor shall exercise the utmost care and shall carry on such activities under the supervision of properly qualified personnel. 10.2.5 The Contractor shall promptly remedy all damage or loss (other than damage or loss insured under Para- graph 11.3) to any property referred to in Clauses 10.2.1.2 and 10.2.1.3 caused in whole or in part by the Contrac- tor. anv Subcontractor, any Sub-subcontractor, anyone di- rectly or indirectly employed by any of them, or by any- one for whose acts any of them may be liable, and for which the Contractor is responsible under Clauses 10.2.1.2 and 10.2.1.3, except damage or loss attributable to the acts or omissions of the Owner, the Architect, the Con- struction Manager or anyone directly or indirectly em- ployed by any of them, or by anyone for whose acts any of them may be liable, and not attributable to the fault or negligence of the Contractor. The foregoing obliga- tions of the Contractor are in addition to the Contractor's obligations under Paragraph 4.18. 10.2.6 The Contractor shalf designate a responsible member of the Contractor's organization at the site whose duty 'shall be the prevention of accidents. This person shalf be the Contractor's superintendent unless 17 A201/CM -1980 AlA DOCUMENT A201/CM . GENERAL CONDITIONS Of THE CONTRACT fOR CONSTRUCTION CONSTRUCTION MANACEMENT EDITION . JUNE 1980 EDITION . AlA_ . @ 1980 . THE AMERICA" INSTITUTE OF ARCHITECTS, 173S NEW YORK AVE., N.W.. WASHINGTON. D.C 2OOOf, WARNING: Unlicensed ph:>tocopylng v101atM U.S. copyright IllW!l and Is subject to legal prosecution. otherwise designated by the Contractor in writing to the Owner and the Construction Manager. 10.2.7 The Contractor shall not load or permit any part of the Work to be loaded so as to endanger its safety. 10.3 EMERGENCIES 10.3.1 In any emergency affecting the safety of persons or properly Ihe Contractor shall act, at the Contractor's discretion, to prevent threatened damage, injury or loss. Any additional compensation or extension of time claimed by the Contractor on account of emergency work shall be determined as provided in Article 12 for Changes in the Work. ARTICLE 11 INSURANCE 11.1 CONTRACTOR'S L1ABtLlTY INSURANCE 11.1.1 The Contractor shall purchase and maintain insur- ance for protection from the claims set forth below which may arise out of or result from the Contractor's opera- tions under the Contract, whether such operations be-by the Contractor or by any Subcontractor, or by anyone di- rectly or indirectly employed by any of them, or by any- one for whose acts any of them may be liable: .1 claims under workers' or workmen's compensa- tion, disability benefit and other similar employee benefit acts; .2 claims for damages because of bodily injury, occu- pational sickness or disease, or death of the Con- tractor's employees; .3 claims for damages because of bodily injury, sick- ness or disease, or death of any person other than the Contractor's employees; .4 claims for damages insured by usual personal in- jury liability coverage which are sustained (1) by any person as a result of an offense directly or indirectly related to the employment of such per- son by the Contractor, or (2) by any other person; .s claims for damages, other than to the Work itself, because of injury to or destruction of tangible property, including loss of use resulting therefrom; and .6 claims for damages because of bodily injury or death of any person or property damage arising out of the ownership. maintenance or use of any motor vehicle. 11.1.2 The insurance required by Subparagraph 11.1.1 shall be written for not less than any limits of liability specified in the Contract Documents or required by law, whichever is greater. 11.1.3 The insurance required by Subparagraph 11.1.1 shall include contractual liability insurance applicable to the Contractor's obligations under Paragraph 4,18. 11.1.4 Certificates of Insurance acceptable to the Owner shall be submitted to the Construction Manager for trans- mittal to the Owner prior to commencement of the Work. These Certificates shall contain a provision that coverages afforded under the policies will not be canceled until at least thirty days' prior written notice has been given to the Owner. 11.2 OWNER'S LIABILITY INSURANCE 11.2.1 The Owner shall be responsible for purchasing and maintaining Owner's liability in5urance and, at the Owner's option, may purchase and maintain imurance for protection against claims which may arise' from operations under the Contract. 11.3 PROPERTY INSURANCE 11.3.1 Unless otherwise provided, the Owner shall pur- chase and maintain property insurance upon the entire Work at the site to the full insurable value thereof. This insurance shall include the interests of the Owner, the Construction Manager, the Contractor, Subcontractors and Sub-subcontractors in the Work, and shall insure against the perils of fire and extended coverage and shall include "all risk" insurance for physical loss or damage including, without duplication of coverage, theft, van- dalism and malicious mischief. If the Owner does not intend to purchase such insurance for the full insurable value of the entire Work, the Owner shall inform the Contractor in writing prior to commencement of the Work. The Contractor may then effect insurance which will protect the interests of the Contractor, the Contrac- tor's Subcontractors and the Sub-subcontractors In the Work, and by appropriate Change Order the cost thereof shall be charged to the Owner. If the Contractor is dam- aged by failure of the Owner to purchase or maintain such insurance and to so notify the Contractor, then the Owner shall bear all reasonable costs properly attributa- ble thereto, If not covered under the all risk insurance or otherwise provided in the Contract Documents. the Contractor shall effect and maintain similar property in- surance on portions of the Work stored off the site or in transit when such portions of the V'/ork are to be in- cluded in an Application for Payment under Subpara- graph 9.3.2. 11.3.2 The Owner shall purchase and maintain such boiler and machinery insurance as may be required by the Contract Documents or by law. This insurance shall include the interests of the Owner, the Construction Man- ager, the Contractor. Subcontractors and Sub-subcontrac- tors in the Work. 11.3.3 Any loss insured under Subparagraph 11.3.1 is to be adjusted with the Owner and made payable to the Owner as trustee for the insureds, as their interests may appear, subject to the requirements of any applicable mortgagee clause and of Subparagraph 11.3.8. The Con- tractor shall pay each Subcontractor a just share of any insurance monies received by the Contractor, and by ap- propriate agreement, written where legally required for validity, shall require each Subcontractor to make pay- ments to their Sub-5ubcontractors in similar manner. 11.3.4 The Owner shall file a copy of all policies with the Contractor before an exposure to loss may occur. 11.3.5 If the Contractor requests in writing that insur- ance for risks other than those described in Subpara- graphs 11.3.1 and 11.3.2, or other special hazards, be included in the property insurance policy, the Owner shall. if possible, include such insurance. and the cost thereof shall be charged to the Contractor by appropriate Change Order. AlA OOCUMENT A201/CM . GENERAL CONOITIONS OF THE CONTRACT FOR CONSTRUCTION CO"'STRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE AMERICAN INSTITUTE OF ARCHITECTS. 173S NEW YORK AVE.. NW., WASHINGTON, D.c. :!0006 A201/CM - 1980 18 WI\R'<"-lG' lJ"';"""ed ""c,t"c~,,\"- 0 vlolat"s l' ~, copyrlc"t laws ar>tl is subject 't) lege; prosecution, 11.3.6 The Owner and the Contractor waive all rights against (1) each other and the Subcontractors, Sub-sub. contractors, agents and employees of each other, and (2) the Architect, the Construction Manager and separate con- tractors, if any, and their subcontractors, sub-subcontrac- tors, agents and employees, for damages caused by fire or other perils to the extent covered by insurance obtained pursuant to this Paragraph 11.3 or any other property in- ~urance applicable to the Work, except such rights as they may have to the proceeds of ~uch insurance held by the Owner as trustee. The foregoing waiver afforded the Architect. the Construction Manager, their agents and employees shall not extend to the liability imposed by Subparagraph 4.18.3. The Owner or the Contractor, as appropriate, shall require of the Architect, the Construc- tion Manager, separate contractors, Subcontractors and Sub-subcontractors by appropriate agreements, written where legally required for validity, similar waivers each in favor of all other parties enumerated in this Sub- paragraph 11.3.6. 11.3.7 If required in writing by any party in interest, the Owner as trustee shall, upon the occurrence of an in- ~ured loss, give bond for the proper performance of the Owner's duties. The Owner shall deposit in a separate account any money so received, and shall distribute it in accordance with such agreement as the parties in interest may reach, or in accordance with an award by arbitration in which case the procedure shall be as provided in Para- graph 7.9, If after such loss no other special agreement is made, replacement of damaged Work shall be covered bv an appropriate Change Order. 11.3.8 The Owner, as trustee, shall have power to adjust and settle any loss with the insurers unless one of the parties in interest shall object, in writing within five days after the occurrence of loss, to the Owner's exercise of this power, and if such objection be made, arbitrators shall be chosen as provided in Paragraph 7.9. The Owner as trustee shall, in that case, make settlement with the insurers in accordance with the directions of such arbi- trators. If distribution of the insurance proceeds by arbi- tration is required, the arbitrators will direct such dis- tribution. 11.3.9 If the Owner finds it necessary to occupy or use a portion or portions of the Work prior to Substantial Completion thereof, such occupancy shall not commence prior to a time mutually agreed to by the Owner and the Contractor and to which the insurance company or com- panies providing the property insurance have consented by endorsement to the policy or policies. This insurance shall not be canceled or lapsed on account of such partial occupancy. Consent of the Contractor and of the insur- ance company or companies to such occupancy or use shall not be unreasonably withheld. 11.4 LOSS OF USE INSURANCE 11.4.1 The Owner, at the Owner's option, may purchase and maintain insurance for protection against loss of use of the Owner's property due to fire or other hazards, however caused. The Owner waives all rights of action against the Contractor for loss of use of the Owner's property, including consequential losses due to fire or other hazards however caused, to the extent covered by insurance under this Paragraph 11.4. ARTICLE 12 CHANGES IN THE WORK 12.1 CHANGE ORDERS 12.1.1 A Change Order is a written order to the Con- tractor signed to show the recommendation of the Con- struction Managf~, the approval of the Architect and the authorization oj t~e Owner, issued after execution of the Contract, authorizing a change in the Work or an adjust- ment in the Contract Sum or the Contract Time. The Contract Sum and the Contract Time may be changed only by Change Order. A Change Order signed by the Contractor indicates the Contractor's agreement there- with, including the adjustment in the Contract Sum or the Contract Time, 12.1.2 The Ow ner, without invalidating the Contract, may order changes in the Work within the general scope of the Contract consisting of additions, deletions or other revisiom, the Contract Sum and the Contract Time being adjusted accordingly, All such changes in the Work shall be authorized bv Change Order, and shall be performed under the applicable conditions of the Contract Docu- ments. 12.1.3 The cost or credit to the Owner resulting from a change in the Work shall be determined in one or more of the following ways: .1 by mutual acceptance of a lump sum properly itemized and supported by sufficient substantiating data to pe~mit evaluation; .2 by unit prices stated in the Contract Documents or subsequently agreed upon; .3 by cost to be determined in a manner agreed upon by the pa~ties and a mutually acceptable fixed or percentage fee; or .4 by the method provided in Subparagraph 12.1.4. 12.1.4 If none of the methods set forth in Clauses 12.1.3.1,12.1.3.2 or 12.1.3.3 is agreed upon, the Contrac- tor, provided a written order signed by the Owner is re- ceived, shall promptly proceed with the Work involved. The cost of such Work shall then be determined bv the Architect, after consultation with the Construction ~1an- ager, on the basis of the reasonable expenditures and savings of those performing the Work attributable to the change, including, in the case of an1ncrease in the Con- tract Sum, a reasonable allowance for overhead and profit. In such case, and also under Clauses 12.1.3.3 and 12,13.4 above, :~e Contractor shall keep and present. in such form as the Owner, the Architect or the Construc- tion Manager may prescribe. an itemized accounting to- gether with apvopriate supporting data for inclusion in a Change Order, Unless otherwise provided in the Con- tract Documents cost shall be limited to the follow ing: cost of materials, including sales tax and cost of delhery; cost of labor. including social security, old age and unemployment insurance, and fringe benefits required by agreement or custom; workers' or workmen's compensa- tion insurance; bond premiums; rental value of equip- ment and machinery; and the additional costs of super- vision and field office personnel directly attributable to the change. Pending final determination of cost to the Owner, payments on account shall be made on the Ar- chitect's apprO\'al of a Project Certificate for Payment. 19 A201/CM -1980 AlA DOCUMENT A201/CM . GENERAL CO'DITIONS OF THE CONTRACT FOR CONSTRUCTION CONSTRUCTION MANAGEMENT EDIlIO'- . JUNE 1980 EDITION · AlAe . ~ 1980 . THE A~ERICAN INSTITUTE OF ARCHIlECTS, -'-j; Io;EW YORK AVE.. N.W" WASHINGTON. D.C 20006 WARNING: Unlicensed photocopying violates U.S. copyright laws and Is subject to legal prosecution. The amount of credit to be allowed by the Contractor to the Owner for any deletion or change which results in a net decrease in the Contract Sum will be the amount of the actual net cost as confirmed by the Architect after consultation with the Construction Manager. When both additions and credits covering related Work or substitu- tions are involved in anyone change, the allowance for overhead and profit shall be figured on the basis of the net increase, if any, with respect to that change. 12.1.5 If unit prices are stated in the Contract Docu- ments or subsequently agreed upon, and if the quantities originally contemplated are so changed in a p~op~sed Change Order that application of the agreed unit pnc.es to the quantities of Work proposed will cause subs~antlal inequity to the Owner or the Contractor, the applicable unit prices shall be equitably adjusted. 12.2 CONCEALED CONDITIONS 12.2.1 Should concealed conditions encountered in the performance of the Work below the surface of the ground or should concealed or unknown conditions in an existing structure be at variance with the conditions indicated by the Contract Documents, or should unknown physical conditions below the surface of the ground or should concealed or unknown conditions in' an existing struc- ture of an unusual nature, differing materially from those ordinarily encountered and generally recognized as in- herent in work of the character provided for in this Con- tract, be encountered, the Contract Sum shall be equita- bly adjusted by Change Order upon claim by either party made within twenty days after the first observance of the conditions. 12.3 CLAIMS FOR ADDITIONAL COST 12.3.1 If the Contractor wishes to make a claim for an increase in the Contract Sum, the Contractor shall give the Architect and the Construction Manager written no- tice thereof within twenty days after the occurrence of the event giving rise to such claim. This notice shall be given by the Contractor before proceedin.g to .execute the \\lork. except in an emergency endangermg hfe or prop- erty in which case the Contractor shall proceed in ac- cordance with Paragraph 10.3. No such claim shall be valid unless so made. Ii the Owner and the Contractor cannot agree on the amount of the adjustment in, the Contract Sum, it shall be determined by the Architect after consultation with the Construction Manager. Any change in the Contract Sum resulting from such claim shall be authorized by Change Order. 12.3.2 If the Contractor claims that additional cost is in- volved because of, but not limited to. (1) any written in- terpretation pursuant to Subparagraph 2.3.11, (2) any or- der by the Owner to stop the Work pursuant to Para- graph 3.3 where the Contractor was not at fault, or any such order by the Construction Manager as the Owner's agent. (3) any written order for a minor change in the Work issued pursuant to Paragraph 12.4, or (4) failure of payment by the Owner pursuant to Paragraph 9.7. the Contractor shall make such claim as provided in Sub- paragraph 12.3.1. 12.4 MINOR CHANGES IN THE WORK 12.4.1 The Architect will have authority to order minor changes in the Work not involving an adjustment in the Contract Sum or extension of the Contract Time and not inconsistent with the intent of the Contract Documents. Such changes shall be effected by written order issued through the Construction Manager, and shall be binding on the Owner and the Contractor. The Contractor shall carry out such written orders promptly. ARTICLE 13 UNCOVERING AND CORRECTION OF WORK 13.1 UNCOVERING OF WORK 13.1.1 If any portion of the Work should be covered contrary to the request of the Architect Or the Construc- tion Manager, or to requirements specifically expressed in the Contract Documents, it must, if required in writing by either, be uncovered for their observation and shall be replaced at the Contractor's expense. 13.1.2 If any other portion of the Work has been cov- ered which the Architect or the Construction Manager has not specifically requested to observe prior to its being covered, either may request to see such Work and it shall be uncovered by the Contractor. If such Work be found in accordance with the Contract Documents, the cost of uncovering and replacement shall, by appropriate Change Order, be charged to the Owner. If such Work be found not in accordance with the Contract Documents, the Contractor shall pay such costs unless it be found that this condition was caused by the Owner or a separate contractor as provided in Article 6, in which event the Owner shall be responsible for the payment of such costs. 13.2 CORREalON OF WORK 13.2.1 The Contractor shall promptly correct all Work rejected by the Architect or the Construction Manager as defective or as failing to conform to the Contract Docu- ments whether observed before or after Substantial Com- pletion of the Project and whether or not fabricated, in- stalled or completed. The Contractor shall bear all costs of correcting such rejected Work, including compensa- tion for the Architect's and the Construction Manager's additional services made necessary thereby. 13.2.2 Ii, within one year after the Date of Substantial Completion of the Project or designated portion thereof, or within one year after acceptance by the Owner of designated equipment, or within such longer period of time as may be prescribed by law or by the terms of any applicable special warranty required by the Contract Docu- ments, any of the Work is found to be defective or not in accordance with the Contract Documents, the Contractor shall correct it promptly after receipt of a written notice from the Owner to do so unless the Owner has previ- ously given the Contractor a wrillen acceptance of such condition. This obligation shall survive both final pavment for the Work or designated portion thereof and termina- tion of the Contract. The Owner shall give such notice promptly after discovery of the condition. 13.2.3 The Contractor shall remove from the site all portions of the Work which are defective or nonconform- ing and which have not been corrected under Subpara- graphs 4.5.1, 13.2.1 and 13.2,2, unless removal is waived by the Owner. 13.2.4 If the Contractor fails to correct defective or non- conforming Work as provided in Subparagraphs 4.5.1, AlA DOCUMENT A201/CM . GENERAL CONDITIO~S OF THE CONTRACT FOR CONSTRUCTION CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlAe . @1980 . THE ,.....\ERIC..'1 INSTITUTE OF ARCHITECTS. 173S NEW YORK AVE" N,\\'.. WASHINGTON. D.C 20006 A201/CM - 1980 20 We.t:F::NC' \""l("l?n~pd nh~,tocC"nv;"''''' vir"t~.,c.t:' us ("o"vrict)t law~ ?...,~ i~ ~~'I:-;F-t::t tf"l !:>...~, proseC'(I.r,...~ 13.2.1 and 13.2.2, the Owner may correct it in accordance with Paragraph 3.4. 13.2.5 If the Contractor does not proceed with the cor- rection of such defective or nonconforming Work within a reasonable time fixed by written notice from the Archi- tect issued through the Construction Manager, the Owner may remove it and may store the materials or equipment at the expense of the Contractor. If the Contractor does not pay the cost of such removal and storage within ten days thereafter, the Owner may, upon ten additional days' written notice, sell such Work at auction or at pri- vate sale and shall account for the net proceeds thereof, after deducting all the costs that should have been borne by the Contractor, including compensation for the Archi- tect's and the Construction Manager's additional services made necessary thereby. If such proceeds of sale do not cover all costs which the Contractor should have borne, the difference shall be charged to the Contractor and an appropriate Change Order shall be issued. If the payments then or thereafter due the Contractor are not sufficient to cover such amount, the Contractor shall pay the differ- ence to the Owner. 13.2.6 The Contractor shall bear the cost of making good all work of the Owner or separate contractors de- stroyed or damaged by such correction or removal. 13.2.7 Nothing contained in this Paragraph 13,2 shall be construed to establish a period of limitation with respect to any other obligation which the Contractor might have under the Contract Documents, including Paragraph 4.5 hereof. The establishment of the time periods noted in Subparagraph 13.2,2, or such longer period of time as may be prescribed by law or by the terms of any warranty required by the Contract Documents, relates only to the specific obligation of the Contractor to correct the Work, and has no relationship to the time within which the Contractor's obligation to comply with the Contract Doc- uments may be sought to be enforced, nor to the time within which proceedings may be commenced to estab- lish the Contractor's liability with respect to the Contrac- tor's obligations other than specifically to correct the Work. 13.3 ACCEPTANCE OF DEFEOIVE OR NONCONFORMING WORK 13.3.1 If the Owner prefers to accept defective or non- conforming Work, the Owner may do so instead of requir- ing its removal and correction. in which case a Change Order will be issued to reflect a reduction in the Contract Sum ",'here appropriate and equitable. Such adjustment shall be effected whether or not final payment has been made. ARTICLE 14 TERMINATION OF THE CONTRACT 14.1 TERMINATION BY THE CONTRACTOR 14.1.1 If the Work is stopped for a period of thirty days under an order of any court or other public authority having jurisdiction, or as a result of an act of government such as a declaration of a national emergency making materials unavailable, through no act or fault of the Con- tractor or a Subcontractor or their agents or employees or any other persons performing any of the Work under a contract with the Contractor, or if the Work should be stopped for a period of thirty days by the Contractor be- cause of the Construction Manager's failure to recom- mend or the Architect's failure to issue a Project Certifi- cate for Payment as provided in Paragraph 9.7 or because the Owner has not made payment thereon as provided in Paragraph 9.7, then the Contractor may, upon seven addi- tional days' written notice to the Owner, the Architect and the Construction Manager, terminate the Contract and recover from the Owner payment for all Work executed and for any proven loss sustained upon any materials, equipment, tools, construction equipment and machinery, including reasonable profit and damages. 14.2 TERMINATION BY THE OWNER 14.2.1 If the Contractor is adjudged a bankrupt, or makes a general assignment for the benefit of creditors, or jf a receiver is appointed on account of the Contrac- tor's insolvency, or if the Contractor persistently or re- peatedly refuses or fails, except in cases for which exten- sion of time is provided, to supply enough properly skilled workers or proper materials, or fails to make prompt payment to Subcontractors or for materials or labor, or persistently disregards laws, ordinances, rules, regulations or orders of any public authority having juris- tion, or otherwise is guilty of a substantial violation of a provision of the Contract Documents, and fails within seven days after receipt of written notice to commence and continue correction of such default, neglect or viola- tion with diligence and promptness. the Owner, upon certification by the Architect after consultation with the Construction Manager that sufficient cause exists to justify such action, may, after seven days following receipt by the Contractor of an additional written notice and with- out prejudice to any other remedy the Owner may have, terminate the employment of the Contractor and take possession of the site and of all materials, equipment, lools, construction equipment and machinery thereon owned by the Contractor and may finish the Work by whatever methods the Owner may deem expedient. In ~uch case the Contractor shall not be entitled to receive any further payment until the Work is finished. 14.2.2 If the unpaid balance of the Contract Sum ex- ceeds the costs of finishing the Work, including compen- sation for the Architect's and the Construction Manager's additional services made necessary thereby, such excess shall be paid to the Contractor. If such costs exceed the unpaid balance, the Contractor shall pay the difference to the Owner. The amount to be paid to the Contractor or to the Owner. as the case may be. shall be certified by the Architect, upon application, in the manner provided in Paragraph 9.4, and this obligation for payment shall survive lhe termination of the Contract. 21 A201/CM -1980 AlA DOCUMENT A2t1/CM . GENERAL CONDIlIO~S Of THE CONTRACT fOR CONSTRUCTION CONSTRUCTION ,\V."IAGEMENT EDITION . JU~E 1980 EDITION . AlAe · Cll980 · THE ,,,\[RICA" INSTilL TE Of ARCHIlECTS.I;35 NEW YORK AVE.. NW., WASHlsGTON, D,C. 20006 ". ,~..",..... "_~"~_'~_ .....t..r. ~....r ~"'v;"""'-.I">~tl~ _'""'~''';Qh~I'''').'sP!''diS~,\lbjecttoleQalpro'5ecution. SECTION 00805 SUPPLEMENTARY GENERAL CONDITIONS Information contained in this Supplementary Conditions amends, supplements or clarifies the "General Conditions of the Contract for Construction, Construction Management Edition, AlA Document A201/CM dated June 1980 Edition. In cases of conflict between the General Conditions and these Supplementary Conditions, wording of this section shall govern. ARTICLE 1 1. Subparagraph 1.1.3 - third line-after the word "construction," delete the remaining words and insert the following: "and all supplies, tools, construction equipment and machinery, water, heat, utilities, transportation, and other facilities, services, and incidentals necessary for the proper execution and completion of such construction; except as expressly noted in the Scope of Work or the General Requirements of the Contract." 2. Subparagraph 1.2.1 - delete in its entirety. 3. Subparagraph 1. 2.3 - after the last word "meanings" in the paragraph add the following sentence: "In case of discrepancy or disagreement in the contract documents, specifications, and/or drawings, the ORDER OF PRECEDENCE shall be: Contract Agreement The addenda as issued The Supplementary General Conditions General Conditions The General Requirements The Technical Specifications The Drawings (Large scale detail drawings take precedence over smaller scale general drawings). Note: Do not rely on scaled dimensions on drawings, and any discrepancies found shall be brought to the attention of the AlE through the CM. 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 1 4. Add new subparagraph 1.2.5 as follows: "'i\'here on any of the drawings a portion of the h'ork is drawn out and the remainder is indicated in outline, the parts drawn out shall also apply to all other like portions of the Work." 5. Add new subparagraph 1.3.2 as follows: "Unless otherwise provided in the Contract Documents, the Trade Contractor will be furnished, free of charge, all copies of Drawings and Specifications reasonably necessary for the execution of the Work." ARTICLE 2 1. Subparagraph 2.2.1 - after the word "representative", add: liThe Construction Manager is not the General Contractor and, unless otherwise expressly provided in the Contract Documents, does not assume any of the traditional duties of a General Contractor. The term Construction Manager means the Construction Manager acting through his authorized representative." 2. Subparagraph 2.3.4 - first sentence after the word "Architect," add "along with the Construction Manager." 3. subparagraph 2.3.7 - after the word "properly," add: "It is the intent of the Contract Documents to allow the Construction Manager to schedule the performance of all Work and the contractors are expected to follow all such schedule direction. Should a contractor, either in person or through his subcontractor, supplier, or vendor, fail to maintain progress according to the Project Schedule and approved Contractor's Schedule, or cause delay to another Contractor: De shall furnish additional labor and/or services such as overtime as may be necessary to brinq his operations up to schedule, all at no additional cost to the Owner." 4. Subparagraph 2.3.15 - delete in its entirety. 5. subparagraph 2.3.18 - delete the word "reasonable" in the sixth (6th) line. After the word "promptness", add "consistent with the constraints of the project schedule so as to cause no delay." 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 2 6. Subparagraph 2.3.23 - delete the phrase "against whom the Contractor makes no reasonable objection and." Also, delete the last sentence in the subparagraph in its entirety. ARTICLE 3 1. Subparagraph 3.3.1 - delete from the last sentence the phrase, ". .., except to the extent required by Subparagraph 6.1.3" 2. Subparagraph 3.4.1 - substitute three (3) days notice in each case for the seven (7) day notices stipulated. Add at end of subparagraph the following: "In the event of clean- up issues, Owner has right to provide a minimum of 24 hours notice. In the event of safety issues determined to be of a serious nature, as determined by the CM, notice will given, and contractor is required to rectify deficiency immediately." 3. Subparagraph 3.2.1 - delete in its entirety. ARTICLE 4 1. Subparagraph 4.1.1 - delete in its entirety and insert the following: liThe Contractor is the same person or entity identified as the Trade Contractor. A Trade Contractor is the person or entity identified as such in the Agreement between the Owner or Construction Manager and a Trade Contractor. The term Trade Contractor includes one who furnishes material worked to a special design but does not include one who furnishes material not so worked and is referred to throughout the Contract Documents as if singular in number and masculine in gender. The term Trade Contractor means the Trade Contractor or his authorized representative." 2. Add new subparagraph 4.4.3 as follows: "The Contractor is responsible for the conduct of his employees at all times. Misconduct, destruction of property, unsafe practices, or violation of any Federal or state regulations including abuse of alcohol or drugs, will be cause for permanent dismissal from the project. If any Contractor employee is determined to be detrimental to the Project, as deemed by the Construction Manager, the Contractor will remove and/or replace the employee at the 01/06/92 SUPPLEMENTARY GEN~RAL CONDITIONS (ADD. 2) 00805 - 3 request of the Construction Manager. Employees dismissed from the project will be transported from the jobsite at the Contractor's expense.1I 3. Add new subparagraph 4.4.4 as follows: "The Trade Contractor shall be totally responsible for the security of his work, materials, equipment, supplies, tools, machinery, and construction equipment.1I 4. Add new subparagraph 4.4.5 as follows: liThe Trade Contractor shall be responsible for complete, timely and accurate field measurements as necessary for proper coordination, fabrication and installation of his materials and equipment. The Trade Contractor agrees to cooperate with the Construction Manager, if required, to accommodate any discovered variations or deviations from the Drawings and Specifications so that the progress of the Work is not adversely affected. II 5. Subparagraph 4.9.1 - add the following sentence: liThe superintendent shall be satisfactory to the Construction Manager and shall not be changed except with the consent of the Construction Manager, unless the superintendent proves to be unsatisfactory to the Trade Contractor or ceases to be in his employ.1I 6. Subparagraph 4.10.1 - add the following sentence: "This schedule, to be submitted within three (3) days after Contract Award, shall indicate the dates for the starting and completion of the various stages of construction, shall be-revised as required by the conditions of the Work, and shall be subject to the Construction Manager's approval." 7. Add new subparagraph 4.10.2: liThe Construction Manager will conduct a weekly scheduling meeting which the Contractor shall attend. At this meeting, the parties can discuss jointly such matters as progress, scheduling, and problems. II 8. Add new subparagraph 4.12.9: "If materials specified in the Contract Documents are not available on the present market, the Trade Contractor may 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 4 submit data on substitute materials through the Construction Manager to the Architect/Engineer for approval by the Owner." 9. Subparagraph 4.14.1 - add at line 3 after "properly": "He shall also provide protection of existing work as required." 10. Subparagraph 4.14.2 - at end of paragraph, add: "When structural members are involved, the written consent of the Architect/Engineer shall also be required. The Trade Contractor shall not unreasonably withhold from the Construction Manager or any separate contractor his consent to cutting or otherwise altering the Work." 11. Add new subparagraph 4.14.3: "The Trade Contractor shall arrange for any blockouts, cutouts, or opening required for the installation of his materials and equipment and the execution of his work, whether or not shown or indicated on the Drawings. The Trade Contractor shall be further responsible for sealing and/or finishing, in an acceptable fashion and meeting any applicable code requirements, any such blockout, cutout opening, or other hole in any fire-rated floor, ceiling, wall, security wall, or any other finished surface". 12. Subparagraph 4.15.1 - at end of paragraph, add: "Clean up shall be performed to the satisfaction of the Owner or Construction Manager." 13. Add new subparagraph 4.16.2: "The Trade Contractor shall promptly return telephone calls or respond to any other form of communication initiated by the Construction Manager. Failure to promptly do so shall be considered a lack of performance on the part of the Trade Contractor, and may be considered grounds for replacement of site personnel." 14. Add new Subparagraph 4.16.3: "All written correspondence to the Construction Manager shall be serialized, dated, and signed by an authorized representative of the Trade Contractor. The correspondence 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 5 15. Subparagraph 4.2.1 - at the end of the paragraph, add the following: liThe Owner and the Architect have acknowledged that nothing in the Architect's engagement implies any undertaking by the Architect for the benefit of or which may be enforced by the Contractor, its subcontractors, or the surety of any of them; it being understood that the Architect's obligations are to the Owner and that, in performing such obligations, the Architect may increase the burdens and expenses of the Contractor, its subcontractors, or the surety of any of them. Neither the Contractor, any Subcontractor, nor the surety of any of them shall bring any civil suit or other legal action against the Architect arising out of or in connection with the Project." 03/02/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 6) 00805 -5a 16. Subparagraph 4.18.1 - delete from the loth line, the phrase, II... (other than the Work itself)...1I At the end of the paragraph add the following paragraph: liThe first ten dollars ($10) of remuneration paid to the CONTRACTOR is for the indemnification provided for above.1I 04/16/92 SUPPLEMENTARY GENERAL CONDITIONS(ADD. 10) 00805 -SB shall be directed to: Morrison-Knudsen/Gerrits P.O. Box 5283 Key West, Florida 33040 Attn: Doug Fuller or hand delivered to Morrison-Knudsen/Gerrits. office located at 5090 Junior College Road, stock Island, Florida 33040. Serialization procedures will be provided to the Trade Contractor in the pre-construction meeting." Each trade contractor shall be required to check his designated mailbox regularly. This mailbox will be made available, and located by the Construction Manager. ARTICLE 5 1. Subparagraph 5.2.3 - delete in its entirety and insert the following: IIIf the Owner or Construction Manager refuses to accept any person or entity on a list submitted by the Trade Contractor in response to the requirements of the Contract Documents, the Trade Contractor shall submit an acceptable substitute; however, no increase in the Contract Sum shall be allowed for any such substitution.1I ARTICLE 6 1. Subparagraph 6.1.1 - delete the last sentence. 2. Subparagraph 6.1.3 - delete in its entirety, and insert the following: lilt shall be the responsibility of each contractor to coordinate his work with the work of other contractors on the site. The Owner, A/E and Construction Manager shall be held harmless of any and all costs associated with improper coordination.1I 3. Subparagraph 6.2.5 - sixth line, after the word "initiates,1I delete the words "an arbitration proceedingll and substitute "a claim;1I tenth line, delete the words "at the Owner.s expense, and"; thirteenth line, after the words "and court 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 6 or," delete the word "arbitration" and substitute "claim." 4. Add new subparagraph 6.2.6: "Should the Contractor contend that he is entitled to an extension of time for completion of any portion or portions of the work, he shall, within (72) hours of the occurrence of the cause of the delay, notify the Construction Manager in writing, of his contention: setting forth (A) The cause for the delay, (B) A description of the portion or portions of work affected thereby, and (C) all details pertinent thereto. A subsequent written application for the specific number of days of extension of time requested shall be made by the Contractor to the Construction Manager within (72) hours after the delay has ceased to exist. It is a condition precedent to the consideration or prosecution of any claim for an extension of time that the foregoing provisions be strictly adhered to in each instance and, if the Contractor fails to comply, he shall be deemed to have waived the claim. The Contractor agrees that whether or not any delay, regardless of cause, shall be the basis for an extension of time he shall have no claim against the Owner, A/E or Construction Manager for an increase in the contract price, nor a claim against the Owner, A/E or Construction Manager for a payment or allowance of any kind for damage, loss or expense resulting from delays: Nor shall the Contractor have any claim for damage, loss or expense resulting from interruptions to, or suspension of, his work to enable other contractors to perform their work. The only remedy available to the Contractor shall be an extension of time. II ARTICLE 7 1. subparagraph 7.1.1 - delete in its entirety and insert the following: "The contract shall be governed by the laws of the State of Florida. Venue for any claims or disputes arising under this contract shall be in the Circuit Court of the 16th Judicial Circuit of the State of Florida." 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 7 2. Subparagraph 7.2.1 - delete in its entirety and insert the following: "The Owner or Construction Manager (as the case may be) and the Trade Contractor each binds himself, his partners, successors, assigns, and legal representatives of such other party in respect to all covenants, agreements, and obligations contained in the Contract Documents. Neither party to the Contract shall assign the Contract or sublet it as a whole without the written consent of the other." 3. Add new Subparagraph 7.2.2: "The Trade Contractor shall not assign any monies due or to become due under this Contract without prior written consent of the Owner or Construction Manager." 4. subparagraph 7.8.1 - delete in its entirety. 5. Paragraph 7.9 'Arbitration' and all associated subparagraphs 7.9.1, 7.9.2, & 7.9.3 - delete in their entirety. ARTICLE 8 1. Subparagraph 8.3.1 - delete in its entirety and insert the following: "If the Trade Contractor is delayed, at any time, in the progress of the Work, by any act or neglect of the Owner, Construction Manager, or the Architect/Engineer, or by any employee of either, or by any separate contractor employed by the Owner, or by changes ordered in the Work, or by fire, unusual delay in transportation, adverse weather conditions not reasonably anticipatable, unavoidable casualties or any causes beyond the Trade Contractor's control, or by delay authorized by the Owner, Construction Manager, or by any other cause which the Construction Manager determines may justify the delay, then the Contract Time shall be extended by no cost Change Order for such reasonable time as the Construction Manager may determine, in accordance with subparagraph 6.2.6.11 2. Subparagraph 8.3.2 - replace the remainder of the Paragraph after the word "waived" in line 4 with the following: "Any claim for extension of time shall state the cause of the delay and the number of days of extension requested. If 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 8 the cause of the delay is continuing, only one claim is necessary, but the Trade Contractor shall report the termination of the cause for the delay within twenty (20) days after such termination; otherwise, any claim for extension of time based upon that cause shall be waived. II 3. Subparagraph 8.3.4 - delete in its entirety and insert the following: "It shall be recognized by the Trade Contractor that he may reasonably anticipate that as the job progresses, the Construction Manager will be making changes in, and updating Construction Schedules. No claim for an increase in the Contract Sum for either acceleration or delay will be allowed for extensions of time pursuant to this Paragraph 8.3 or for other changes in the Construction Schedules which are of the type ordinarily experienced in projects of similar size and complexity." 4. Add new subparagraph 8.3.5: "If the Project is delayed as a result of the Trade Contractor's refusal or failure to begin the Work on the date of commencement as defined in paragraph 8.1.2, or his refusal or failure to carry the Work forward expeditiously with adequate forces, the Trade Contractor causing the delay shall be liable, but not limited to, delay claims from other Trade Contractors which are affected." ARTICLE 9 1. Subparagraph 9.3.3 - add at line 14 after the word "person": "All Trade Subcontractors and Trade Subsubcontractors shall execute an agreement stating that title will so pass, upon their receipt of payment from the Trade Contractor." 2. Subparagraph 9.5.1 - add: "From the total of the amount determined to be payable on a progress payment, 10 percent of such total amount will be deducted and retained by the Owner until final payment is made. The balance (90 percent) of the amount payable, less all previous payments, shall be certified for payment. When not less than 95 percent of the work has been completed, the Owner may, at his/her discretion (and with the consent of the surety), prepare an estimate from which will be retained 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 9 an amount not less than twice the contract value or estimated cost, (whichever is greater), of the work remaining to be done. The remainder, less all previous payments and deductions, will then be certified for payment to the Contractor. It is understood and agreed that the Contractor shall not be entitled to demand or receive progress payment based on quantities of work in excess of those provided in the proposal or covered by approved change orders, except when such excess quantities have been determined by the Construction Manager to be a part of the final quantity for the item of work in question. No progress payment shall bind the Owner to the acceptance of any materials or work in place, as to quality or quantity. All progress payments are subject to correction at the time of final payments. 3. Add new subparagraph 9.5.6: "All material and work covered by partial payments made shall thereupon become the sole property of the Owner, and by this provision shall not be construed as relieving the Trade Contractor from the sole responsibility for the materials and work upon which payments have been made or the restoration for any damaged material, or as a waiver to the right of the Owner or Construction Manager to require the fulfillment of all the terms of the Contract." 4. Add new subparagraph 9.5.7: "Except in case of bona fide disputes, or where the Trade Contractor has some other justifiable reason for delay, the Trade Contractor shall pay for all transportation and utility services not later than the end of the calendar month following that in which services are rendered and for all materials, tools, and other expendable equipment which are delivered at the site of the Project. The Trade Contractor shall pay, to each of his Trade Subcontractors, not later than the end of the calendar month in which each payment is made to the Trade Contractor, the representative 2TI10unt allowed the Trade Contractor on account of the work performed by his Trade Subcontractor interest therein. The Trade Contractor shall, by an appropriate agreement with each Trade Subcontractor, also require each Trade Subcontractor to make payments to his suppliers and Trade Subsubcontractors in a similar manner." 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 10 5. Subparagraph 9.6.1 - delete in its entirety and insert the following: "The Construction Manager/Architect may decline to approve an Application for Payment if, in his opinion, the application is not adequately supported. If the Trade Contractor and Construction Manager cannot agree on a revised amount, the Construction Manager shall process the Application for the amount he deems appropriate. The Construction Manager may also decline to approve any Applications for Payment or, because of subsequently discovered evidence or subsequent inspections, he may nullify, in whole or part, any approval previously made to such extent as may be necessary in his opinion because of: (1) defective work not remedied; (2) third party claims filed or reasonable evidence indicating probable filing of such claims; (3) failure of the Trade contractor to make payments properly to Trade Subcontractors or for labor, materials, or equipment; (4) reasonable evidence that the work cannot be completed for the unpaid balance of the Contract Sum; (5) damage to the Construction Manager, the Owner, or another contractor working at the project; (6) reasonable evidence that the Work will not be completed within the contract time; (7) persistent failure to carry out the Work in accordance with the Contract Documents. 9.6.1.1 No payment shall be made to the Trade Contractor until certificates of insurance or other evidence of compliance by the Trade Contractor, within all the requirements of Article 12, have been filed with the Owner and Construction Manager. Further, no payments on the basis of work performed by a Trade Subcontractor shall be paid until copies of all bonds required by Paragraph 7.5 and any certificates of insurance required of the Trade Subcontractors under Article 12 have been filed with the Owner." 6. Subparagraph 9.7 - delete in its entirety. ARTICLE 11 1. Add new subparagraph 11.1.2.1: The following coverages are required to be maintained by all Trade Contractors and subcontractors in any tier throughout the entire length of the contract and any extensions thereof. 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 11 1. Premises and Operation Liability Insurance: commercial General Liability Insurance shall be obtained in amounts of not less than $1,000,000 each occurrence. Coverage shall specifically include: a. Bodily injury and property damage liability coverage for premises and operations. b. Products and completed operations. c. Independent contractor's exposures. d. Property damage resulting from explosion, collapse, or underground (x/c,u) exposures. e. Blanket contractual liability covering this contract. f. Personal injury liability. g. Broad form property damage liability. 2. Automobile Liability Insurance: Comprehensive automobile liability insurance shall include coverage for bodily injury and property damage liability for a minimum limit of $1,000,000 each occurrence and shall cover use of owned, non-owned, and hired vehicles, and include employers' non-ownership liability coverage. 3. Workers Compensation and Employers Liability Insurance: statutory Workers' Compensation coverage including Employers Liability coverage with limits of not less than $100,000 per person per accident and $500,000 per person per occurrence for disease. Coverage shall be provided to cover operations in the state of Florida and the Voluntary Compensation endorsement shall be provided. Coverage for deferally enacted benefits shall be provided where applicable. All insurance policies except the Workers Compensation and Employers Liability Insurance policy, are required in the name of Monroe County Board of County Commissioners and 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 12 Morrison-Knudsen/Gerrits as Additional Insured, and provide a ~inimum of sixty (60) days notice in the event of termination, non-renewal or reduction in coverage. Policy language shall be modified to provide liability coverage for Cross Liability suits between insureds ~ithout increasing the total policy limits. Monroe County reserves the right to require additional insurance as may be deemed necessary for any specific project or work. Insurers providing coverage(s) must be financially stable and authorized to do business in the state of Florida. The Monroe County Board of County Commissioners reserves the right to reject any insurer that it belie~es to be unacceptable. Failure to maintain required insurance coverage in effect will provide Monroe County, Florida with the option of terminating the contract upon written notice to the Construction Manager. certificates expiring during the term of the contract shall be replaced with new certificates prior to the expiration of the original certificates. Complete and certified copies of all insurance contracts shall be furnished to The Monroe County Board of County Commissioners if requEsted. The certificate Holder on all insurance policies is required to be as follows: }~onroe County Board of County Commi ss ioners, or Monroe County, c/o Morrison-Knudsen/Gerrits P.O. Box 5283 Key West, FL 33040 2. Subparagraph 11.3.7 - second sentence, delete the phrase, "..., or in accordance with an award by arbitration in which case the procedure shall be as provided in Paragraph 7.9" 3. Subparagraph 11.3.8 - first sentence, delete the phrase, II.. .arbitrators shall be chosen as provided in Paragraph 7.9" 01/06/92 SUPPLEMENTARY GE1;ERAL CONDI'rrONS U..::m. 2) 00805 - 13 4. Subparagraph 11.3.1 - delete in its entirety, and insert the follO\.Jing: 11 Throughout the term of the CONTRACT, the o\'iNER shall purchase and maintain property insurance on the completed value of the perr::anent facility only. The completed value is defined as all material, labor, supplies, and equipment intended to be incorporated in and to become a permanent part of the completed facility. Such insurance shall include perils of fire, lightning, and extended perils. The facility as defined for 11.3.1 includes structures as defined in the contract drawings and specifications. Notwithstanding any provisions contained in this paragraph, the CONTRACTOR shall be responsible for the first $10,000 on any loss governed by this section. The CONTRACTOR understands that the o\'iNER I S property insurance policy contains certain exclusions which are available upon request from the CONSTRUCTION l'-1ANAGER.1I 04/16/92 SUPPLU1ENTARY GENERAL CO~;DITIONS (ADD. 10) 00805 -13A ARTICLE 12 1. Subparagraph 12.1.3 - under item .1, add the following at the end of the sentence, II, as set forth in subparagraph 12.1.611 2. Subparagraph 12.1.4 - replace the remainder of the paragraph, after the word IIchangell in line 25, with the following: IIpending final determination of cost, payments on account shall be made as determined by the Construction Manager. The amount of credit to be allowed by the Trade Contractor for any deletion or change, which results in a net decrease in the Contract Sum, will be the amount of the actual net cost as confirmed by the Construction Manager. When both additions and credits covering related Work or substitutions are involved in anyone change, the allowance for overhead and profit shall be figured on the basis of the net increase, if any, with respect to that change.1I 3. Add new subparagraph 12.1.6: "The actual cost of Changes in the Work may include all items of labor or material, power tools, and equipment actually used, utilities, pro rata charges for foreman, and all payroll charges such as Public Liability and Workman's Compensation Insurance. No percentage for overhead and profit shall be allowed on items of Social Security and Sales Tax. If deductions are ordered, the credit shall be the net cost. Items considered as overhead shall include insurance other than that mentioned above, bond or bonds, superintendent, timekeeper, clerks, watchmen, use of small tools, incidental job costs, and general office expenses. The actual cost of Changes in the Work (other than those covered by unit prices set forth in the Contract Documents) shall be computed as follows: 12.1.6.1 If the Trade Contractor performs the actual Work, the percentage mark-up for overhead and profit shall be a maximun addition of fifteen percent (15%). 12.1.6.2 If the Trade Subcontractor performs the actual Work, the percentage mark-up for overhead and profit shall be a maximum addition of fifteen percent (15%). If the Trade Contractor does not enter into the Work, the maximum mark up for managing this work will be ten percent (10%). 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 14 12.1.6.3 If the Trade Subcontractor performs part of the actual work, his percentage mark-up for overhead and profit shall be a maximum addition of fifteen percent (15%) on his direct work only. If the Trade Contractor performs part of the actual work, his percentage mark-up for overhead and profit shall be a maximum addition of fifteen percent (15%) on his direct work only. 4. Add new subparagraph 12.1.7: liThe Trade Contractor shall furnish to the Owner through the Construction Manager, an itemized breakdown of the quantities and prices used in computing the value of any change that might be ordered." 5. Subparagraph 12.3.1 - delete in its entirety and insert the following: IIIf the Trade Contractor claims that any instructions given to him by the Construction Manager, by drawings or otherwise, .involve extra work not covered by the Contract, he shall give the Construction Manager written notice thereof within three (3) days after the receipt of such instructions and before proceeding to execute the work, except in emergencies endangering life or property, in which case the Trade Contractor shall proceed in accordance with Paragraph 10.3." Should it not be clear to the Trade Contractor that a change will involve extra work, written notice given within three (3) days that the change may involve extra work will be sufficient notice. If it is later determined that the work involved in such instruction shall be recognized as an extra, the amounts of additional compensation to be paid therefore should be determined in accordance with Paragraph 13.1. Except as otherwise specifically provided, no claim for additional cost shall be allowed unless the notice specified by this Subparagraph is given by the Trade Contractor. If the Contractor considers that the changed work involves extra costs, the costs shall be accounted for, and presented in accordance with subparagraph 12.1.3. All claims shall be submitted to the Owner through the Construction Manager. II 6. Subparagraph 12.3.2 - change the word 'agent' in the 7th line, to 'representative'. Also, delete item (4). 01/06/92 SUPPLEMENTARY GE~ERAL CONDITIONS (ADD. 2) oose5 - 15 7. Add new subparagraph 12.3.3: "Unless otherwise agreed in writing, the Contractor shall carryon the Work and maintain its progress during any dispute or claim proceeding, and Owner shall continue to make payments to the Contractor in accordance with the Contract Documents. Disputes unresolved shall be settled in accordance with subparagraph 7.1.1." ARTICLE 14 1. Subparagraph 14.1.1 - starting at the 8th line, delete the phrase, "..., or if the Work should be stopped for a period of thirty days by the CONTRACTOR because of the CONSTRUCTION MANAGER's failure to recommend or the ARCHITECT's failure to issue a Project certificate for Payment as provided in Paragraph 9.7 or because the OWNER has not made payment thereon as provided in Paragraph 9.7" 2. Subparagraph 14.2.1 - change the words 'seven days' in the 13th and 18th line, to '72 hours'. 01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2) 00805 - 16 SECTION 00970 PROJECT SAFETY AND HEALTH PLAN 1.1 REGULATIONS AND POLICIES 1.1.1 1.2 1.2.1 Every Trade Contractor and Trade Subcontractor employed on the Project shall comply with all applicable local, State, and Federal safety and health regulations and with Morrison-Knudsen Company, Inc. safety and health policies as described herein. PROJECT SAFETY AND HEALTH REQUIREMENTS It is recognized that it is good business and evidence of competent leadership to prevent the occurrence of incidents that lead to occupational injuries or illnesses. Safety and health requirements on this project include, but are not limited to, the following: .1 In general, this accident prevention policy is based on a sincere desire to eliminate personal injuries, occupational illnesses, and equipment and property damage; and to protect the general public exposed to or associated with the work. .2 The importance of the safety of all workers on the project shall be recognized and accident prevention shall be an integral part of all operations. .3 Each Trade Contractor and Trade Subcontractor shall conduct work in a safe and practical manner in conformance with the OSHA Safety and Health Regulations and the latest edition of the Manual of Accident Prevention, Associated General Contractors of America. .4 Each Trade Contractor and Trade Subcontractor shall observe all applicable Federal, State, local and project laws and regulations pertaining to safety and health, pollution control, water supply, fire protection, sanitation facilities, waste disposal and other related items. .5 The Mandatory Safety and Health Rules shall be posted in a conspicuous location along with the OSHA and Emergency Phone Number posters. 11/21/91 00970 - 1 PROJECT SAFETY AND HEALTH PLAN .6 A record of all occupational injuries and illnesses shall be maintained. Medical and lost time cases shall be properly recorded on the OSHA log, and reported to MORRISON-KNUDSEN/GERRITS. A copy of the insurance report for workmen compensation cases shall be provided to MORRISON- KNUDSEN/GERRITS. .7 Each Trade Contractor and Trade Subcontractor shall provide or arrange for adequate first aid facilities, emergency transportation and persons qualified in first aid. .8 Each Trade contractor and Trade Subcontractor shall cooperate fully with all other contractors in their respective safety and health programs. .9 Good housekeeping shall be observed at all times. Waste, debris, and garbage shall be removed daily or placed in appropriate waste containers. All materials, tools, and equipment shall be stored in a safe and orderly fashion. Each contractor shall donate 10% of their staff to a crew that will convene every Friday at 1:00pm for a joint site clean-up effort not to exceed a duration of three hours. In summary, there will be a 3-part clean-up plan. The first part consists of the contractor cleaning up on a daily basis, his workstations, and his trade work. The second part consists of the general clean-up, the concerted effort by all trade contractors working on the project. A minimum of (1) crew is to be utilized by each contractor, or 10%, whichever is more. The third part consists of the Owner cleaning up for a particular trade contractor should adequate notice not compel him to clean up his work. In this case, the appropriate contractors will be backcharged. .10 This project shall be a Hard Hat job and all supervisors, employees and visitors shall be required to wear a suitable hard hat while on the project site. .11 other appropriate personal protective equipment shall be provided and worn as required including 11/21/91 PROJECT SAFETY AND HEALTH PLAN 00970 - 2 but not limited to long pants, shirts with sleeves and appropriate leather work boots. .12 Temporary construction aids such as ladders, scaffolds, stairs, railings, etc. shall be provided to facilitate access or working conditions in a manner that shall conform to the safety standards specified by Federal, state, Local or manufacturer's recommendations or stipulations. .13 Each Trade Contractor and Trade Subcontractor shall be expected to indoctrinate his employees as to the safety and health requirements of this project and to enforce adherence to safe work procedures. .14 If MORRISON-KNUDSEN/GERRITS notifies any Trade Contractor of any noncompliance with the provisions of this program, the Trade Contractor shall make all reasonable efforts to immediately correct the unsafe conditions or acts. Satisfactory corrective action shall be taken within the specified time. If a Trade Contractor or Trade Subcontractor refuse to correct unsafe or unhealthy conditions or acts, MORRISON- KNUDSEN/GERRITS shall take one or more of the following steps: a. Cease the operation or a portion thereof. b. stop payment for the work being performed. c. Correct the situation using other forces and back charge the Trade Contractor expenses incurred. d. Increase withholding in proportional increments for that given pay period. .15 All Trade Contractor's Superintendents shall be required to attend and participate in all general project safety meetings. These meetings will be included in the weekly coordination meetings as previously specified or on an as needed basis. .16 All Trade Contractors shall conduct Weekly Tool Box Safety Training Meetings, and shall document 11/21/91 00970 - 3 PROJECT SAFETY AND HEALTH PLAN the minutes on the forms provided. These forms are to be transmitted to Morrison-Knudsen/Gerrits on a weekly basis. All employees working at the project site shall be required to attend and participate in the meetings. .17 Shortly after the award of the contract and prior to the beginning of work, an Activity Hazard Analysis (phase plan) shall be prepared by the contractor and submitted to Morrison- Knudsen/Gerrits for approval. The analysis will address the hazards for each activity to be performed in that phase and will present the procedures and safeguards necessary to eliminate the hazards or reduce the risk to an acceptable level. A phase is defined as an operation involving a type of work presenting hazards not experienced in previous operations or where a new subcontractor or work crew is to perform work. The analysis will be discussed by the contractor and Morrison-Knudsen/Gerrits on-site representatives at the Preparatory Inspection Meeting. Work will not proceed on that phase until the Activity Hazard Analysis (phase plan) has been accepted by Morrison-Knudsen/Gerrits. .18 No personal radios or stereos will be allowed on the job-site. 1.3 FIRE PROTECTION 1. 3.1 Every Trade Contractor and Trade Subcontractor employed on the Project shall exercise good construction practices to prevent fire. It shall be the responsibility of the Trade Contractor to insure that general fire protection facilities are adequate for his work and to provide additional fire protection facilities and devices, including fire extinguishers as required by their scope of work. 1.4 WORK NEAR ENERGIZED ELECTRICAL LINES OR OTHER UTILITIES 1. 4.1 It shall be the Trade Contractor's sole and exclusive responsibility (a) to provide personnel capable of working adjacent to energized electrical lines or other utilities; (b) to provide adequate, safe and properly maintained equipment; (c) to conduct all of his work in accordance with the safety rules and regulations 11/21/91 PROJECT SAFETY k~D HEALTH PLAN 00970 - 4 1.5 1. 5.1 1. 5.2 1. 5.3 prescribed by the National Electric Code, National Electric Safety Code, H30, and Safety Rules for Installation and Maintenance of Electrical supply and Communication Lines Hand Book 81, Occupational Safety and Health Act of 1970, as well as other safety codes in effect at the site of construction and as specified elsewhere herein, or as are generally applicable to the type of work being performed; and (d) to continuously supervise and inspect the work being performed to assure that the requirements of (a), (b), and (c) above are complied with and nothing in these Contract Documents shall be held to mean that any such responsibility is the obligation of the Owner or the Architect or the Construction Manager. BARRICADES, WARNING DEVICES AND LIGHTING The Trade Contractor shall be solely responsible for providing temporary ladders, guard rails, warning signs, barricades, night guard lights, and deck or floor closures required in connection with his work to comply with Federal, State and local safety requirements. The Trade Contractor shall be solely and exclusively responsible for the design, construction, inspection and maintenance of such facilities at all times. It shall be the responsibility of the Trade Contractor to provide additional temporary lighting, if needed to maintain safe conditions. It shall be the sole and exclusive responsibility of the Trade Contractor to provide a safe place to work for all laborers and mechanics and other persons employed on or in connection with the project, and nothing in these Contract Documents shall be construed to give any of such responsibility to the Owner, the Architect, or the Construction Manager. 11/21/91 PROJECT SAFETY AND HEALTH PLAN 00970 - 5 SECTION 00980 CONTRACTOR QUALITY CONTROL PLAN 1.1 1.1.1 1.2 1.2.1 1.2.2 1. 2.3 1. 2.4 MORRISON-KNUDSEN/GERRITS' DUTIES AND RESPONSIBILITIES The Morrison-Knudsen/Gerrits' superintendent will monitor all work performed by the Trade Contractor and assist the Trade Contractor with his conformance of the work to the Contract Drawings and Specifications. TRADE CONTRACTOR'S DUTIES AND RESPONSIBILITIES The Trade Contractor is responsible for the quality of the work performed by his work force on this project as well as the quality of the material, equipment and supplies furnished by him to be incorporated into the work. The Trade Contractor will designate a Quality Control Representative who will be on site at all times while the respective Trade Contractor's work is in progress and will have the authority and responsibility to accept or reject items of work. The Trade Contractor's Quality Control Representative may delegate his duties but the primary responsibility and authority will rest on him. The Trade Contractor's Quality Control Representative will coordinate the submittal of all shop drawings, product data and samples to Morrison-Knudsen/Gerrits. Any submittal that is a variance to the contract requirements must be identified as such and transmitted to the Construction Manager for submittal and approval by the Architect/Engineer or Owner. No work requiring submittal of a shop drawing, product data or sample shall commence until the submittal has been reviewed and approved by the Architect/Engineer. The Trade Contractor will bear the responsibility of notifying the designated material-testing laboratory, whether Monroe County or Contractor is required to perform testing of materials as required by the contract drawings and specifications in a timely fashion to prevent needless cancellations and delays of work activities. Any costs caused by untimely 11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3) 00980 - 1 1. 2.5 1. 2.6 1.3 1. 3.1 notification shall be borne by the Contractor. The Trade Contractor's Quality Control Representative will review his drawings, procurement documents and contracts to insure that the technical information provided and all work performed is in accordance with the latest revisions of the Contract Drawings and Specifications. The Trade Contractor's Quality Control Representative will perform an inspection upon receipt at the site of the work of all materials, equipment and supplies including those furnished to him by the Owner. Notes from this inspection will be filled out on the appropriate form and included with the Contractor Daily Quality Control Report. Items which are damaged or not in conformance with the respective submittals, quality standards, contract drawings and specifications shall be brought to the attention of Morrison- Knudsen/Gerrits' representative on site and then will be identified and segregated from accepted items. Items thus identified will not be incorporated into the work until corrective action acceptable to Morrison- Knudsen/Gerrits is completed. Items determined unsalvageable will be removed from the job site. These items shall be noted as deficient in the applicable section of the Contractor Daily Quality Control Report. INSPECTION AND TESTING INSPECTION PLAN Morrison-Knudsen/Gerrits utilizes a multi-point inspection plan for each separate feature of work to be performed under this Trade Contract, i.e., work described by each division of the technical provision section of the contract specifications. This plan consists of the following: .1 Preparatory Inspection - Prior to commencing the work, the Trade Contractor's Quality Control Representative will meet with Morrison- Knudsen/Gerrits' Superintendent and the Architect's representative if he so desires to attend and check the following items at a minimum for conformance: (a) Approval of shop drawings and submittals. 00980 - 2 11/21/91 CONTRACTOR QUALITY CONTROL PLAN ~~D. 3) (b) Approval of inspection and test reports of materials and equipment to be utilized. (c) Completion of previous operations of preliminary work. (d) Availability of materials and equipment required. (e) Potential utility outages. (f) Any other preparatory steps dependent upon the particular operation. (g) Quality standards. (h) Safety or environmental precautions to be observed. (Phase Hazard) Note: Morrison-Knudsen/Gerrits will record the minutes to this inspection meeting and distribute accordingly. .2 Initial inspection - Upon completion of a representative sample of a given feature of the work, the Trade Contractor's Quality Control Representative will meet with the Morrison- Knudsen/Gerrits superintendent and the Architect's representative if he so desires to attend and check the following items at a minimum for conformance: (a) Workmanship to established quality standards. (b) Configuration to contract drawings and specifications. (c) Construction methods, equipment and tools utilized. (d) Materials and articles utilized. (e) Adequacy of testing methods. (f) Adequacy of shop drawings. (g) Adequacy of safety or environmental precautions. 11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3) 00980 - 3 Note: .3 Note: Note: Morrison-Knudsen/Gerrits will record the minutes to this inspection meeting and distribute accordingly. Follow-up Inspections - The Trade Contractor's Quality Control Representative will inspect the work daily to assure the continuing conformance of the work to the workmanship standards established during the preparatory and initial inspections. Additionally, as a part of the follow-up inspection, sign-off sheets will be utilized as often as possible. The intent of these sheets is to achieve concurrence from other trade contractors and responsible parties that ensuing work can indeed commence over underlying work. This will prevent oversights and omissions which could elevate costs. Sign-off sheets shall be used for, but not be limited to, concrete, drywall, ceilings, painting, roofing substrates and flooring. These reports are to be generated by the applicable Trade Contractor and submitted to Morrison-Knudsen/Gerrits' superintendent for approval prior to the start-up of work. Failure to generate a sign-off sheet or to attain proper signatures prior to covering up underlying work may affect payment for that piece of work if ensuing problems are detected or not. This disciplinary action shall be carried out via the Nonconformance Report. (See section 1.4.2 of this plan. ) The Trade Contractor shall be responsible to record these inspections and all other project related activities encountered throughout the day on the Contractor Daily Quality Control Report. . 4 Completion Inspections - Upon completion of a given feature of the work, the Trade Contractor's Quality Control Representative will meet with Morrison-Knudsen/Gerrits' Superintendent, if he so desires to attend, to perform an inspection of the completed work. Non-conforming items will be identified and corrected prior to commencement of the next operation. The Trade Contractor shall conduct and report 00980 - 4 11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3) 1.3.1.5 1.3.1.6 1. 3.2 1.3.3 corrections of this inspection which shall be a required submittal. Follow-On Inspections - Upon execution of the contractor's completion inspection in elements of the work which result in concealment; such as, ceiling and drywall installations, MK/G shall schedule and conduct multi-trade or singular inspections prior to covering installation. Note: MK/G will record the minutes to this inspection meeting. Pre-Final Inspection - Upon substantial completion of the project work MK/G shall coordinate and conduct a universal inspection of all areas and elements of the work. The Architect/Engineer may be represented if he so desires. This inspection shall be completed at least (15) days prior to the final substantial completion inspection which shall be conducted by the AlE. All deficiencies and incomplete work should be completed prior to the final substantial completion inspection. OPERATION AND CHECK OUT TESTING The Trade Contractor will provide personnel and equipment to perform the operational tests and checkout of the equipment, facilities or equipment constructed, fabricated or installed under this Trade Contract. Morrison-Knudsen/Gerrits' Superintendent will coordinate and witness all such tests. Notification should be given at least ten (10) days in advance of the scheduled tests. FINAL INSPECTION and issuance of the AlE CERTIFICATE OF SUBSTANTIAL COMPLETION Morrison-Knudsen/Gerrits' Superintendent will coordinate and attend all final inspections of the work by the Architect/Engineer. Prior to requesting a final inspection, all tests for the equipment and systems must be completed. Upon completion of the AlE's inspection, the A/E will publish outstanding items and issue a Project Certificate of Substantial Completion, which will define the date of 'Turn-Over' to the Owner the care, 11/21/91 CONTRACTOR QUALITY CONTROL PLAN {ADD. 3) 00980 - 5 control and custody. Reference section 00800, Substantial Completion. 1.4 REPORTING Maintaining accurate and retrievable records is extremely important in the Quality Assurance Program. These records will act as a main source of information in the present and in the future for the entire project management team. The main report that will be utilized to provide this information is the Daily Quality Control Report. Nonconformance Reports may also be issued. 1. 4.1 DAILY QUALITY CONTROL REPORT The Daily Quality Control Report shall be used to document the summary of daily inspection activities performed by the Trade Contractor's designated Quality Control Representative. It shall include any of the steps of inspection that are performed that day, all test monitoring and any rework of nonconforming items. The daily Quality Control Report section of the Daily superintendent's Report will be routinely used for daily reporting requirements. When the magnitude or complexity necessitates such, a more separate and comprehensive form will be used. Reference Contractor's Daily Report, and as needed Contractor Daily Quality Control Report, section 01385. 1. 4.2 NONCONFORMANCE REPORT Nonconformance Reports will be issued for work that is found to be in nonconformance with the contract documents or the referenced quality standards. The report will be issued by Morrison-Knudsen/Gerrits. It is not the intent to routinely and repeatedly issue nonconformance reports, but to issue them only after normal enforcement standards have been exhausted, or if the work performed is a detriment to the project. A copy of the Nonconformance Report will be forwarded to the Project Manager for his information and/or action. It should also be included in the Trade Contractor's Daily Quality Report package for general review. 11/21/91 CONTRACTOR QUALITY CONTROL PIAN (ADD. 3) 00980 - 6 Nonconformance Reports will be signed off once the deficient item or items have adequately been corrected. This will be done by the issuing Superintendent and Project Manager. These sign-offs will be included with a corresponding corrective action taken. Significant nonconformances need to be addressed to prevent recurrence. The signed-off report will also be submitted for review. Work activities affected by a Nonconformance Report will proportionally counteraffect payments. Whether that be partial or full retainage will be left up to the discretion of Morrison-Knudsen/Gerrits' management team. 1.5 NOT USED 1.6 AUDITS 1. 6.1 Morrison-Knudsen/Gerrits may choose at its option to perform Trade Contractor audits of their Contractor Quality Control Plan at any time. Reports of these audit results will be forwarded to the Project Manager for his action. Any action items noted during an audit for the Trade Contractor will be followed up and documented to insure compliance and avoid recurrence. 1.7 SUMMARY The intention of this plan is to create a system of checks and balances that will minimize delays caused by rework and a lack of planning and maximize production and insure that the finished product is one that the entire construction team can pride themselves in. These goals can be achieved by giving the Owner exactly what he has bought. The owner will expect no more and through Quality Assurance, the construction team will provide no less. 11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3) 00980 - 7 SECTION 00800 SUBSTANTIAL COMPLETION AND OWNER ACCEPTANCE Bid Group 2, and Bid Group 3 Contractors shall turn over care, custody and control of their work to the Owner as defined in the issuance of the A/E's certificate of Substantial Completion of the Project. All contracts in these bid groups shall exchange as a group and in unison, possession, maintenance and security responsibilities with the Monroe County Officials. Any portion of the work which is in non-conformance with the contract documents or elements which prevent the Owner's use of the facilities for its intended use shall be excluded from acceptance. The contractor shall be responsible for all work performed, equipment, and materials furnished to, or by the contractor under this contract until the contractors work is completed and has been accepted by the Owner as stated in the Certificate of Substantial Completion. In the event of loss, damage or destruction of such work, equipment, or materials, the contractor at his sole expense shall promptly repair, restore, or replace such, to the conditions required by the contract documents. All warranties and guarantees shall commence as stated on the A/E's certificate of Substantial Completion. Substantial Completion certificates for portions of the project or portions of the work may be used to reduce retention. This partial certification shall only be used for the purpose of reducing retention. The implementation and amounts of reduction shall be at the Owner's sole discretion. In the event of discrepancy or disagreement in the contract documents, specifications, and/or drawings, this section will take precedence over the Supplementary General Conditions, General Conditions, General Requirements, technical specif ications and drawings. OWNER ACCEPTANCE 00800 - 1 11/20/91 - - _. . -. -. --"' -~~ ---........ -- SECTION 01027 APPLICATION FOR PAYMENT PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Procedures for preparation and submittal Applications for Payment. of B. Related sections 1. section 00750 - General Conditions 2. section 00900 - AlA G702/G703 2. section 01370 - Schedule of Values 1. .2 FORMAT A. AlA G702 Application and Certificate for Payment including continuation sheets when required. 1..3 PREPARATION OF APPLICATIONS A. Present required information in typewritten form. B. Execute certification authorized officer. by notarized signature of C. List each authorized Change Order on the form, including change order number, date and dollar amount. D. Prepare Application for Final Payment as specified in section 01700. 1..4 SUBMITTAL PROCEDURES A. The initial Application for Payment will not be processed until the construction schedule, the schedule of values, and the initial submittal schedule have been received by the Construction Manager, reviewed and approved by the Architect. B. Submi t an updated construction and submittal schedule with each Application for Payment. C. Payment Period: submit once per month, during the last OS/20/91 APPLICATION FOR PAYMENT 01027 - 1 week of the month. Payment will be made by the Owner within (30) days thereafter. D. Work Item Update Listing - this work sheet, prepared by the Construction Manager, shows the work items which are being considered for progress payments. It is to be billed from the Contractor's approved schedule of values and approved changes only. The Contractor must fill in percentages of work completed on each line item or total dollar amount of Original Suppliers Invoices. Suppliers Invoices are then attached for payments on materials stored. E. status Meeting - The Contractor's representative and the Construction Manager review the Contractor's Work Item Update Listing. Upon agreement between the two parties, both the Contractor and Construction Manager will sign off on the form. F. Estimate Voucher - The Construction Manager will input the progress into the computer from the work Item Update Listing, and will issue the Estimate Voucher to the Contractor. G. Submit waivers as required. H. Submit three (3) copies of each Application for Payment. 1..5 SUBSTANTIATING DATA A. When the Construction Manager and/or Architect requires substantiating information, submit data justifying dollar amounts in question. B. Provide one copy of data with cover letter for each copy of submittal. Indicate Application number and date, and line item by number and description. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used ************** END OF SECTION 01027 APPLICATION FOR PAYMENT 01027 - 2 OS/20/91 SECTION 01028 CHANGE ORDER PROCEDURES PART 1 - GENERAL 1. .1 SUMl1ARY A. section includes: 1. Promptly implement change order procedures. a. Provide full written data required to evaluate changes. b. Maintain detailed records of the work done on a time and material/force account basis. c. Provide full documentation to the Construction Manager with each request. 2. Designate in writing the member of the Contractor's organization authorized to accept changes in the Work. 3. The Owner will designate in writing the person who is authorized to execute Change Orders. B. Related requirements: 1. Agreement: The amounts of established unit prices. 2. Agreement: The amounts of established allowances. 3. Conditions of the Contract, Article 12 of the General Conditions: a. Methods of determining cost or credit to the Owner resulting from changes in the Work made on a time and material basis. b. The Contractor's claims for additional costs. 1..2 DEFINITIONS A. Change Order, AlA Document G701/CM: Refer to the General Conditions. B. Construction Change Directive: A written order to the Contractor, signed by the Owner, MK/Gerr i ts and the Architect, which amends the Contract Documents as described, and authorizes the Contractor to proceed with a change which affects the Contract Sum or the Contract time, for inclusion in a subsequent Change Order. 1..3 PRELIMINARY PROCEDURES A. A change may be initiated by submitting a Proposal Request to the Contractor. Request will include: 1. Detailed description of the change, products and 04/30/91 CHANGE ORDER PROCEDu~ES 01028 - 1 location of the change in the Project. 2. Supplementary or revised Drawings and Specifications. 3. The projected time span for making the change, and a specif ic statement as to whether overtime work is, or is not, authorized. 4. A specific period of time during which the requested price will be considered valid. 5. Such request is for information only, and is not an instruction to execute the changes, nor to stop the Work in progress. B. The Contractor may initiate changes by submitting a written notice to the Construction Manager containing: 1. Description of the proposed changes. 2. Statement of the reason for making the changes. 3. Statement of the effect on the Contract Sum and the Contract Time. 4. statement of the effect on the Work of separate contractors. 5. Documentation supporting change in the Contract Sum or the Contract Time, as appropriate. 1..4 CONSTRUCTION CHANGE DIRECTIVE A. In I ieu of Proposal Request, a Construction Change Directive may be issued for Contractor to proceed with a change for subsequent inclusion in a Change Order. B. The Construction Change Directive will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to def ine details of the change, and will designate the method of determining a change in the Contract Sum and change in the Contract Time. C. The Owner, Construction Manager, and the Architect will sign and date the Construction Change Directive as authorization for the Contractor to proceed with changes. D. At completion of the change, submit itemized accounting and supporting data as provided in the Article "Documentation of Proposals and Claims" of this section. E. The allowable costs of such work will be determined as provided in the General Conditions and Supplementary Conditions. F. The Owner, Construction Manager and Architect will sign and date the Change Order to establish the change in the Contract Sum and in the Contract Time. 04/30/91 CHANGE ORDER PROCEDURES 01028 - 2 G. The Owner and the Contractor will sign and date the Change Order to indicate their agreement. 1..5 DOCUMENTATION OF PROPOSALS AND CLAIMS A. Support each quotation for a lump-sum proposal, and for each unit price which has not previously been established, with sufficient substantiating data to allow evaluation of the quotation. B. On request provide additional data to support time and cost computations: 1. Labor required. 2. Equipment required. 3. Products required. a. Recommended source of purchase and unit cost. b. Quantities required. 4. Taxes, insurance and bonds. 5 . Credit for the work deleted from the Contract, similarly documented. 6. Overhead and profit. If the Trade Contractor performs the actual Work, the percentage mark-up for overhead and profit shall be a maximum addition of fifteen percent (15%). If the Trade Subcontractor performs the actual Work, the percentage mark-up for overhead and profit shall be a maximum addition of fifteen percent (15%). If the Trade Contractor does not enter into the Work, the maximum mark-up for managing this work will be ten percent (10%). If the Trade Subcontractor performs part of the actual Work, his percentage mark-up for overhead and profit shall be a maximum addition of fifteen percent (15%) on his direct work only. If the Trade Contractor performs part of the actual work, his percentage mark-up for overhead and prof it shall be a maximum addition of fifteen percent (15%) on his direct work only. 7. Justification for change in the Contract Time. C. Support each claim for additional costs, and for the done on a time-and-material/force account basis, documentation as required for a lump-sum proposal, additional information: work with plus 04/30/91 CHANGE ORDER PROCEDURES 01028 - 3 1. Name of the Owner's authorized agent who ordered the work, and date of the order. 2. Dates and times the work was performed, and by whom. 3. Time record, summary of hours worked, and hourly rates paid. 4. Receipts and invoices for: a. Equipment used, listing dates and times of use. b. Products used, listing of quantities. c. Subcontracts. 5. signature of Construction Manager's superintendent, concurring with quantities. 1..6 PREPARATION OF CHANGE ORDERS A. The Construction Manager will prepare each Change Order. B. Change Order form: AlA Document G701/CM. C. Change Order will describe changes in the Work, both additions and deletions, with attachments of revised Contract Documents to define details of the change. D. Change Order will provide an accounting of the adjustment in the Contract Sum and in the Contract Time. 1..7 LUMP-SUM/FIXED PRICE CHANGE ORDERS A. Content of Change Orders will be based on either: 1. The Proposal Request and the Contractor's responsive proposal as mutually agreed between the Owner and the Contractor. 2. The Contractor's Proposal for a change, as recommended by the Architect or Construction Manager. B. The Owner, Construction Manager and the Architect will sign and date the Change Order as authorization for the Contractor to proceed with the changes. C. The Contractor may sign and date the Change Order to indicate agreement with the terms therein. 1..8 UNIT PRICE CHANGE ORDER A. The 1. content of the Change Orders will be based on either: The definition of the scope of the required changes. The Contractor's Proposal for a change, as recommended by the Architect, or Construction 2. 04/30/91 CHANGE ORDER PROCEDURES 01028 - 4 Manager. 3. Survey of completed work. B. The 1. 2. amounts of the unit prices to be: Those stated in the Agreement. Those mutually agreed upon between Architect and the Contractor. the Owner, C. When quanti ties of each of the items affected by the Change Order be determined prior to start of the Work: 1. The Owner, Construction Manager and the Architect will sign and date the Change Order as authorization for the Contractor to proceed with the changes. 2. The Contractor may sign and date the Change Order to indicate agreement with the terms therein. D. When quantities of the items cannot be determined prior to start of the Work: 1. A Construction Change Directive will be issued directing the Contractor to proceed with the change on the basis of unit prices, and will cite the applicable unit prices. 2. At completion of the change, the cost of such work will be determined based on the unit prices and quantities used. 3. The Owner, Construction Manager and the Architect will sign and date the Change Order to establish the change in the Contract Sum and in the Contract Time. 4. The Contractor will sign and date the Change Order to indicate their agreement with the terms therein. 1..9 CORRELATION WITH THE CONTRACTOR'S SUBMITTALS A. Revise Schedule of Values and Request for Payment forms monthly to record each change as a separate item of the Work, and to record the adjusted Contract Sum prior to submission of Application for Payment. B. Revise the Construction Schedule to reflect each change in the Contract Time prior to monthly submissions. Revise subschedules to show changes for other items of work affected by the changes. C. Upon completion of the Work under a Change Order, enter pertinent changes in Record Documents. 04/30/91 CHANGE ORDER PROCEDURES 01028 - 5 PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED **************** END OF SECTION 01028 - 04/30/91 CHANGE ORDER PROCEDURES 01028 - 6 SECURITY PROJECT PROCEDURES PART 1 - GEl;ERAL 1.1 SUMMARY A. section Includes 1. Electronic automated computerized security management system. 2. Provide a complete enclosed raceway system for all wiring for security devices and controls in compliance with NEC, NFPA-70 1990 and in accordance with 16050 and 16111. 3. Drawings for this work are diagrammatic, intended to convey the extent, general arrangement and locations of the work. Because of the scale of the drawings, certain basic items such as conduit fittings, access panels, cabinet sizes, sleeves, pull and junction boxes may not be shown. Include such items where required by code, other sections, and for proper installation of the work. 4. Equipment specifications may not deal individually with every part, control, or device which may be required to produce the equipment warranties. 5. Coordinate with other trades in submittal of shop drawings. Shop drawings shall detail space conditions to the satisfaction of concerned trades and is subject to final review by the Architect. If installation of equipment, raceways, cable trays or conduit is performed prior to coordination with other trades and interferes with work of other trades, make necessary changes to correct the condition at no additional cost to the Owner. 6. Provide required integration of components to create an operational computerized security management system providing control and monitoring from a touchscreen CRT. 1.2 TESTS A. Notify Architect and Owner's representative in writing, 1~ days in advance of testing to prevent delays in construction schedules. B. Test systems and place in proper and specified working order prior to demonstration of the systems. C. 'Test system grounds to demonstrate that the ground resistance does not exceed the requirements of the transient voltage surge suppression (TVSS) or the National Electric Codes (NEC). D. Perform tests required by authorities having jurisdiction 11/18/91 SECURITY PROJECT PROCEDURES 01130-1 over the site. E. Testing shall be in the presence of the Owner's designated representatives, Contractor and Architect. 1.3 DEMONSTRATION A. Pr ior to acceptance of the work, the Security System Installer shall demonstrate to the Owner, designated representatives, Contractor and Architect, the features and functions of the system, and all subsystems and shall instruct the Owner in the proper operation and event sequences of the system. B. Demonstrate each system and subsystem. The demonstration is to consist of not less than the following: 1. Designate actual location of each component of a system or subsystem and demonstrate its function and its relationship to other components within the system. 2. Demonstrate the systems and subsystems operations by actual "START-STOP/ON-OFF" cycling showing how to work controls, reset devices, replace fuses and conduct emergency operating/operations procedures. 3. Demonstrate communication, signaling and security equipment/devices by actual operation of such devices. c. Demonstration of systems are to include, but not be limited to the following: 1. UPS Power and Distribution system 2. Touchscreen CRT Operations . 3. Alarm Detection and signalling Equipment 4. Door Control/Monitoring System 5. Access Control System 6. situation Alarms (Hardwire) 7. Man-Down Alarms (Wireless) 8. CCTV System 9. Intercom Systems 10. Telephone Systems (Inmate/Attorney/Visitor) 11. Lighting Control 12. Fire Alarm Interface 13. Cable Supervision System (Random Points to be Selected by Architect) D. Security System Installer/Integrator shall furnish the necessary trained personnel to perform the demonstration and instructions and shall arrange to have the manufacturer's representatives present to assist with the demonstrations. The Security System Installer shall allow a minimum of one week for performing the prescribed demonstrations. E. Security systems Installer/Integrator shall arrange with the Owner the date and times for performing the demonstration. The Owner will select date and time for 11/18/91 SECURITY PROJECT PROCEDURES 01130-2 - .- -----_.~-~.....,- demonstration. F. Comply with requirements of Section 01670 SYSTEMS DEMONSTRATIONS. 1. security System Installer/Integrator shall video tape in high speed, high quality, VHS format the demonstration of systems listed. 1.4 QUALIFICATIONS A. Manufacturer Qualifications: Company specializing in electronic automated computerized security management systems of the same type, scope, operation and magnitude for a minimum of five years. Documented experience shall include the following: 1. List at least 10 facilities of equal size and technical requirements utilizing the equipment submitted. 2. For each facility, list: a. Name and location of facility b. Date of occupancy by Owner c. Owner's representative to contact and telephone number d. Construction Manager and/or General Contractor e. Architect B. Use the products of a single manufacturer for similar type equipment, i.e., motion detectors, magnetic contacts. C. Use products made by companies regularly engaged in the manufacture of the type equipment specified. 1.5 IDENTIFICATION A. Identify control and sub-control, motor and equipment controls, remote relay cabinets, address panels, system interface cabinets, and similar equipment with 1/211 red lettering or as specified for individual piece of equipment. B. Identify pull and junction boxes in service areas, tunnels, above accessible ceilings, and in accessible chases with 1/2" red lettering indicating the circuit and system. Example: Secur i ty Alarms "SY", Fire Alarms "FA", Circuit Number "SY-126". C. Engraved laminated plastic tags may be used for identification in lieu of painted lettering. D. Provide typewritten circuit directories installed in 3 ring binders with transparent page protectors in each control and sub-control cabinet. 1.6 RECORD DOCUMENTS A. Provide complete schematic drawings depicting location of interface, number of conductors, types of connectors, circuit requirements, and type of enclosure. 11/18/91 SECURITY PROJECT PROCEDURES 01130-3 1.7 PROTECTION OF EQUIPMENT A. Protect mater ials stored on the job site. Protect materials during construction and after installation. B. Provide and apply protective material immediately upon receiving the products and maintain throughout the construction process. C. Keep products clean and dry or by elevating equipment above ground and floor. D. Take precautions to protect apparatus and materials from damage. Failure to protect materials constitutes sufficient cause for rejection of the apparatus or material. E. Protect equipment and factory finish from damage during construction operations and until final acceptance. Restore finishes that become stained, scratched, or damaged. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION NOT USED ******************** END OF SECTION 01130 SECURITY PROJECT PROCEDURES 01130-4 11/18/91 SECTION 01200 PROJECT MEETINGS PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Project meetings 1..2 The CONSTRUCTION MANAGER'S RESPONSIBILITY A. Construction Manager shall schedule and administer pre- construction meeting, periodic progress meetings, and specially called meetings throughout progress of the Work. 1. Prepare agenda for meetings. 2. Provide notice of each meeting four days in advance of meeting date, or provide as much advance notice as possible. 3. Make physical arrangements for meetings. 4. Preside at meetings. 5. Record the minutes; include significant proceedings and decisions. 6. Reproduce and distribute copies of minutes. a. To participants in the meeting. b. To parties affected by decisions made at the meeting. c. Furnish three copies of minutes to the Architect. B. Representatives of the Contractors, suppliers attending meetings shall authorized to act on behalf of represents. subcontractors and be qualified and the entity each C. The Architect and the Owner's Representative may attend meetings to ascertain that the Work lS expedited consistent with the Contract Documents and construction schedules. 1..3 PRE-CONSTRUCTION MEETING A. Location: A central site designated by the Construction Manager. B. Attendance: 1. The Owner's Representative. 11/21/91 PROJECT MEETINGS 01200 - 1 2. The Architect and his professional consultants (as required) . 3. Construction Manager. 4. The Contractor's Superintendent. 5. Major subcontractors. 6. Major suppliers. 7. others as appropriate. c. suggested Agenda: 1. Distribution and discussion of: a. List of major subcontractors and suppliers. b. Projected Construction Schedules. 2. critical Work sequencing. 3. Major equipment deliveries and priorities. 4. Project Coordination. a. Designation of responsible personnel. 5. Procedures and processing of: a. Field decisions. b. Proposal requests. c. Submittals. d. Change Orders. e. Applications for Payment. 6. Adequacy of distribution of the Contract Documents. 7. Procedures for maintaining Record Documents. 8. Use of premises: a. Office, work and storage areas. b. The Owner's requirements. 9. Construction facilities, controls and construction aids. 10. Temporary utilities. 11. Safety and first-aid procedures. 12. Security procedures. 13. Housekeeping procedures. 14. Distribute meeting minutes within (3) days. 1..4 WEEKLY PROGRESS MEETINGS A. The Contractor's Project Manager and/or Superintendent shall be required to attend a weekly scheduling meeting. B. Location of the meetings: Manager. Office of the Construction C. Attendance: 1. The Architect and his professional consultants as needed. 2. Contractors as appropriate to the agenda. 3. suppliers as appropriate to the agenda. 4. others. D. suggested Agenda: 11/21/91 PROJECT MEETINGS 01200 - 2 1. Review of Work progress since previous meeting. 2. Field observations, problems, conflicts. 3. Problems which impede Construction Schedule. 4. Review of off-site fabrication, delivery schedules. 5. Corrective measures and procedures to regain projected schedule. 6. Revisions to Construction Schedule. 7. Progress, schedule, during succeeding Work period. 8. Coordination of schedules. 9. Review submittal schedules. 10. Maintenance of quality standards. 11. Pending changes and substitutions. 12. Review proposed changes for: a. Effect on Construction Schedule and on completion date. b. Effect on other contracts of the Project. 13. Other business. 14. Distribute meeting minutes. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used ************** END OF SECTION 01200 11/21/91 PROJECT MEETINGS 01200 - 3 SECTION 01301 SUBMITTALS PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Submit to the Construction Manager, shop drawings, product data, certifications and samples required by the technical sections. 2. Prepare and submit a separate schedule listing dates for submission and dates for review. B. Related Sections: 1. Section 00750 - GENERAL CONDITIONS 2 . Individual submittals required: refer to each specific section, for certifications, shop drawings, product data and sample requirements. 1.2 SUBMITTAL TRANSMITTAL FORM A. Attached, and made a part of this section 01301, is a copy of the submittal Transmittal Form, which shall be filled out by the contractor and submitted with each and every submittal. Follow the instruction sheet, also attached, for directions on this procedure. It is essential that the submittal Transmittal Forms are filled out in their entirety for the system to function properly. B. Transmittal Form, originals for contractors use, will be supplied by the Construction Manager, and is a 6-part form. 1.3 SUBMITTAL SCHEDULE A. The Contractor shall submit within seven (7) days of award of the Contract a preliminary "Submittal Schedule" to the Construction Manager for review, modification and response. No payment applications will be processed prior to finalizing the submittal schedule. The "Submittal Schedule" shall contain the following information: 1. Specification Section number and name. 2. Specification Section paragraph identification which describes submittal requirement. 3. Submittal information required, (i.e., sample, test data, shop drawing, etc.). 08/20/91 SUBMITTALS (ADD.l) 01301 - 1 B. The Contractor shall also supply the following dates in order to meet the project schedule. 1. Date submittal is scheduled to be submitted and received by the Construction Manager. Date contractor has scheduled to order material or equipment or the submittal item. Date contractor has scheduled delivery to job-site equipment or the submittal item. Add any remarks or unique items that the CM or A/E should be aware of. 2. 3 . of material or 4 . C. The Contractor shall allow a minimum of (2) weeks for review of submittal by A/E (in calendar days) . D. The submittal master record will then be used to track submittals within the process. 1.4 SHOP DRAWINGS A. Submi t legible shop drawings in the form of posi ti ve pr inting reproducible transparencies, commonly ca lled sepia prints, suitable for reproduction use on dry print diazo type machines. Sepia prints which cannot be reproduced will be returned to the Contractor for resubmittal. B. Provide shop drawings as complete submittals (no partial sets) on original drawings or information prepared solely by the fabricator or supplier. Deviation from complete submittals will only be allowed by pre-arranged method. C. Do not reproduce the Contract Drawings for shop drawing submittals. D. Sheet sizes shall not exceed the size of the Contract Drawings. E. Each sepia print shall have blank spaces large enough to accept 4" x 4" review stamps of the Architect and the Contractor. F. Each 1. 2. 3. sepia print shall carry the following Project name and contract number. Date. Names of: a. The Architect b. The Construction Manager c. The Contractor d. Supplier e. Manufacturer information: 08/20/91 SUBMITTALS (ADD.l) 01301 - 2 4. Identification of product or material. 5. Relation to adjacent structure or materials. 6. Field dimensions, clearly stated as such. 7. Specification section number. 8. Applicable standards such as ASTM or Federal Specification. 9. Identification of deviations from Contract Documents. 10. Reference to construction drawings by drawing number and/or detain number. G. Submit sepia prints without folds either as flat sheets if size permits, or rolled in tubes. H. The contractor shall submit (2) reproducibles and (4) blueline or blackline sets to the CM. The CM will return (1) reproducible to the contractor after review/return from the A/E. 1.5 PRODUCT DATA A. Product data such as catalog cuts, brochures or manufacturer's sheets may be submitted in lieu of sepia prints if adequately identified. Submit seven copies of product data to the Construction Manager. B. Modify product data sheets to delete information which is not applicable to the Project. Provide additional information if necessary to supplement standard information. C. Product data sheets that are submitted with extraneous information not deleted and/or modified will be returned without review to the Contractor for resubmittal. D. The contractor shall submit at a minimum, (1) original and (6) copies to the CM. The CM will return (2) copies to the contractor after review/return by the A/E. 1.6 SAMPLES A. Provide samples to illustrate materials, equipment or workmanship, and to establish standards by which completed work may be judged. B. Construct mock-ups as required by the technical sections, at the Project site in a location designated by the Construction Manager. Construct mock-ups, including adjacent work required, to demonstrate the final appearance of the Work. 08/20/91 SUBMITTALS (ADD.l) 01301 - 3 C. 'The contractor shall submit (3) samples to the CM, and (1) will be returned to the contractor after review/return from the A/E. 1.7 CERTIFICATIONS A. Provide certifications as required by various technical sections on the Contractor's letterhead stationary. certifications shall be identified to this Project, dated and bear Contractor's signature in the same format used for the Owner/Contractor agreement. B. Clearly identify the materials referenced and state that the material and the intended installation methods, where appl icable, are in compl iance with the Contract Documents. Attach manufacturer's affidavits where applicable. C. The contractor shall submit (1) original and (6) copies to the CM. The CM will return (2) sets to the contractor after review/return from the AlE. 1.8 THE CONTRACTOR'S RESPONSIBILITIES A. Before making submittals to the Construction Manager, review each submittal, make changes or notations as necessary to conform to the Contract Documents, identify such review with review stamp and forward reviewed submittal with comments to the Construction Manager for review. Return submittals not meeting Contract requirements to subcontractors and do not forward such submittals to the Construction Manager. B. Submit catalog sheets, product data, shop drawings and where specified, submit calculations, material samples, color chips or charts, test data, warranties and guarantees all at the same time for each submittal item. C. verify field measurements and product catalog numbers or similar data. D. clearly identify on the Construction Manager submittals from the Documents. submittal a~d transmittal to the in writing of deviations in requirements of the Contract E. After the Construction Manager's and the Archi tect' s review, distribute copies with one copy to be maintained at the Project site for reference use and other copies distributed to suppliers and fabricators. SUBMITTALS {ADD.1} 01301 - 4 08/20/91 F. Do not begin the Work which requires submittals until return of submittals with the Construction Manager's and the Architect's stamp and initials indicating review. G. The Contractor's responsibility for errors and omissions in submittals is not relieved by the Construction Manager's or the Architect's review of submittals. H. The Contractor's responsibility for deviations in submi ttals from requirements of the Contract Documents is not relieved by the Construction Manager's or the Architect's review of submittals unless the Architect gives written acceptance of specific deviations. 1.9 THE CONSTRUCTION MANAGER'S RESPONSIBILITIES A. The Construction Manager will return to the Contractor, without review, all submittals not bearing the Contractor's review stamp or not showing it has been reviewed by the Contractor. B. After the Architect's review, the Construction Manager will forward submittals to the Contractor and retain one copy for the Owner. The Contractor shall distribute copies including other copies distributed to suppliers and fabricators. The Contractor shall supply copies of reviewed submittals to the Construction Manager in sufficient quantity to allow proper coordination of the Contract. 1.10 THE ARCHITECT'S RESPONSIBILITIES A. The Architect will review submittals with reasonable promptness, checking only for conformance with the design compliance of the Project and compliance with information given in the Contract Documents. B. The Architect will make changes or notations directly on the submittal, identify such review with his review stamp, obtain and record the Architect file copy and return the submittal to the Construction Manager. **************** END OF SECTION 01301 08/20/91 SUBMITTALS {ADD.1) 01301 - 5 b Z w :2: :::l ... U 0 ~ ~ 0 C:l w ~ ~ U ;- ~ v Z 0:: ~ 0 - UJ u ;: ct; " ~ '" cL. 0 " w I I z c C1: ~ G <: < ~ , ~ 0: ~ ::i ::;: b ~ E '" ~ z z z "" ::;: ~ < 0 ::> {: ":l U Vl '" " ~ ::> Vl ~ In ;; L!J L!J ~ ::> ~ z 0:: Vl 0 - g ;; " I I L!J ;; a: .... ;:J ,.... < C Vl f-- Z u.l ::'E u.l > a g: ~ 6 a ....J""u.. <<....J f--",,< P.:Gf-- <at: uo::~ rp..Vl f-- ~ Z 0:: 6 f-- U u.J o 0:: Z o ~ 7- i o .." G: 00 ~~ 6...; c.; , - t, ~ Q~3 ::2?~ ::;: .7:. ~ o f- ~~_. = h < 'J z < '" < > > '" '" c z <:> ~ Q - o z ~ < .. V') ,. L!J 0 <5 >lo U ~ ~ E' ;;: I -, v ,.... > ~ -- - ~ c5 z g 0 <: 2 u 3 ~ ~ ~ .; I ~ ::> u - Vl ". I ,.... := ~ -.:; ~ .~ ~ t: ~ <-. E ;, ~ " (5 ,; '" ~ -, z ";;' " ~ i ~ - 5 C - '-' 0 '" c:J ... 0 c ,.: ~ Z <:: c: 0. c u V') .~ z g -, " <: ~ .. u ;; \J \J ::;: ~ :,: E ~ ::;. - -- ;=== --- ~ L!J ;; uJ 0:: In f.. z L!J o Z ~ 0: L!J .... :J Vl ~ ::;: ~ o ~ ~ ::> .. c ." Vi ~ j! IS oj E :2 " '" ~ ~ ~ ~ ;:1 ~C~ r "-i ~ (; r; :/: n :/: -l o -> ov-< -;I l-1 nl)V;(jCF() .. r. ::; ^' :T 0 :::"~:J~G~ 2 ::.-.0 ::.-.:J v _:::-o~t':1 ~~!J~U:l1 ~.::.. c..=: :J ~ :.; ~ :;. z -V':.r'. --'" 3~~i~ n .- r-1' ~ ...., n n (t '1 C. :l. .., O;:l c:: PJ ~ ,. ::J ~~(t~G :r-t:~"'n o~ c:: ::. :=--: n ;:: o. ::J :Il ~~~t,;::::~ oo~>o~ ~ =- ~:g ::. ::: E.~~~~~ ~ ...... ..., :,; ... c.: !;l > n - " .,. =,tn9.,Y3i ~ :~ ~ ~ ~. ~ ~l~ ~.~ ~. i 0;; '" s 5 -< .,. ::l cr. :r- 'T1CJonc::J> > -;I ~O;;.;:%);o>-;I n~r.o-.:J-.:J::O <:T<....-.:J-.:JO (1;. (t ",. PJ '1 .., <: ~'1(t-.:J~~> n ~-.:J n r, t"" P- (30.c. ~<PJPJ() (\ n :Il tr. 0 '" 0. ::l tr. C1 if OC::tT1 :3 oerC/) _. 0. :3 " ~. n c. ::l o PJ 'U 'U '1 o < e:. '1 (t ..D c:: ::;. n 0. \> ~ ~ ~~l~i c..:.: ." C"- ~- ~ a ~ 3 ~ ;:, ~ ~ ~. !~- - -~T - u--- ~rr I ~r-Jnll-rl!I--: -~i~ ~~: f:= C~=7~1~ I Jj" ; 1 I 'I ~ ~ ~ !: ~ ;- z : 1- -I t i <-- 1 iFJ, ~ ~ ; ~ ~ \K r'l' ' i ii, \ ii, ~ < ~ ~ ; ~ '.:::/ ' i II II , ' I ' ~ ~ -;; -< , , ~ ~~- ~T ~ ~ ~ , 1/ ~z ~t ~; f _>~>>=1 < ~!t\.1 ~ = - ,-W' s - ~ ~ ~ '~i\ '! : ; U\ i i i V 3: I . ~ I I Zi. i . .: ,;:s.. ',t' ; I I ;?'\ '~; - ~~~-- ~ ~\, ~ ~ I, ; I~ ~ '~ '> C8~ x ~ (0. ~ ~. ~ ! " ~ i ~ ~ > z ~ ! ~ :; ., ~ ~ 0 ~- ~ ~ ~ ~ :J @) ~, ~ z ~ ---'~=:"-~ 2 J x <: @~ ,. :: t..,) N N t"'.-'.................- ~:--F-.":;:X:-J.~~ _ X.... -~. . ~ ~ ~ :~t.J:-~ n ~~ ~ i [ [ ~ ! ~ ? ~ ::: Q Q n . -' =:~nn~^.- ~.-._~-- - , c- g ~ ~_ ; "" ;-~E......:;.~~ ~~~~~;[ j :.. ~ ~, 3 ~ ~::..~~~ '- n ~:r, - 3 ngt~~ .. ~ :; F."..:s '0 f~: !f; ~ C:or. ~!.l r. 3 c' :II C Hi l( ~. ~ ~ ;" ~ :;. ;. (r; ~ n n !2., ~. ~~i~~~~i~j~~~~[]~t~~~~~6 _ _ <; =_ ~' ~ ri. 3 X 1") ~ ]. 3 ~ =:' ?: __ ~ if :;f =- n ~=r.~~.~.?~ao~'~c~~~~~;_~;3~X ~ :.. ::'... ......' r. ~ ~ ::> -. -., -- ... L.: _ ,,~= ~ g ~.' : ;. =- ~ =- ~_' ~_ ~ '1 - - .... ~ ~ "V-:o -co -- ;;;; 5~ !illl! o-~" ~~6?~~~~~ ~~ t ~- S" :;- :::.; 3 g'"::Sc'~~"l ""' _ c. 3 '"'0 ""'I ~~~!~ "'Q )0( ::l _ (') '<~35 f";. ('; ;II 1; ::l ~ = .~. 5- ~ ::l "" ;; :;.~ ~ n C'. .....n .2 _'7~;?:;Ij... ~ -~ ~ ~ "" ~ - ~ ~ ~ - :; g ~ ~ ~ :_r;' .<i i:"[ ~ V) ~ it; 0 ~;;~. s g? ~B K~ ::l ~ ~' ? -, "8.:; 3'" 2~ 'r,' !:':. . ~~ ~ ~ .. z-;;:.; r. ""\ :; ~ :? ., ~ -;; ;'(5 ~ x .. c .. g =- x 8 " ;;:x n S. l z ~ :;. n '-' " ;; ? :; ~ SECTION 01310 PROGRESS SCHEDULES PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Progress schedules 2. Revisions to schedules B. Related sections: 1. SCOPE OF WORK c. Description: 1. Progress Schedules: Promptly after award of the Contract, prepare and submi t to the Construction Manager, construction progress schedules for the work, with subschedules of related activities which are essential to its progress. Also incorporate manpower loading related to each activity on the construction schedule. 2. Revisions to Schedule: Submit revised/updated progress schedules with each payment application.. 1. .2 FORMAT A. Prepare Progress Schedules as a hor i zonta 1 bar chart with separate bar for each major portion of Work or operation, identifying the first work day of each week. B. Include numeric manpower loading associated with each horizontal bar, clearly defined. C. Scale and spacing: revisions. to provide space for notations and D. Sheet size: minimum 8 1/2" x 11". 1..3 CONTENT A. Indicate complete sequence of construction by activity, with dates for beginning and completion of each element of construction. OS/20/91 PROGRESS SCHEDULES 01310 - 1 B. Show the manpower loading for each activity. c. Identify each item by specification section number. D. Identify work of separate stages and other log ically grouped activities. E. Identify work of separate floors and other logically grouped activities. F. Provide sub-schedules to define critical portions of the entire schedule. G. Indicate accumulated percentage of completion of each item and total percentage of Work completed, as of the first day of each month. H. Submit separate schedule of submittal dates for shop drawings, product data, and samples, including the Owner furnished products and products identified under allowances and dates reviewed submittals will be required from the Architect. Reference section 01301 Submittals. I. Indicate delivery dates for the Owner furnished products. J. Coordinate content with Schedule of Values specified in Section 01370. 1..4 REVISIONS TO SCHEDULES A. Indicate progress of each activity to date of submittal, and projected completion date of each activity. B. Identify activities modified since previous submittal, major changes in scope, and other identifiable changes. 1. Major changes in scope. 2. Activities modified since previous submission. 3. Revised projections of progress and completion. 4. other identifiable changes. c. Provide a narrative report as needed to define: 1. Problem areas, anticipated delays and the impact on the schedule. 2. Corrective action recommended and its effect. 3. The effect of changes on schedules of other prime contractors. PROGRESS SCHEDULES 01310 - 2 OS/20/91 1..5 SUBMITTALS A. Submit initial schedules within (3) days after award of Contract. 1. The Construction Manager will review schedules and return review copy within ten (10) days after receipt. 2. If required, re-submit within seven (7) days after return of review copy. 3. Submit revised Progress Schedules with each Application for Payment. 1..6 DISTRIBUTION A. Distribute copies of the reviewed schedules to: 1. Job site file. 2. Subcontractors. 3. other concerned parties. B. Instruct recipients to report promptly to the Contractor, in writing, any problems anticipated by the projections shown in the schedules. Note~ It is not incumbent upon the Construction Manager to notify the Trade Contractor when to begin, to cease, or to resume work nor to give early notice of faulty or defective work, nor in any way to superintend so as to relieve the Trade Contractor of responsibility or of any consequence of neglect or carelessness. ************** END OF SECTION 01310 OS/20/91 PROGRESS SCHEDULES 01310 - 3 SECTION 01370 SCHEDULE OF VALUES PART 1 - GENERAL 1..1 SUMMARY A. Section includes: 1. Schedule of Values allocated to the various portions of the Work, submitted within three (3) days after award of the Contract. 2. Upon request of the Construction Manager, support the values with data which will substantiate their correctness. 3. The Schedule of Values, unless objected to by the Construction Manager, forms the basis for the Contractor's Applications for Payment. 1..2 FORM AND CONTENT OF SCHEDULE OF VALUES A. Type schedule on AlA G703 Form; the Contractor's standard forms and automated printout will be considered by the Construction Manager upon the Contractor's request. Identify schedule with: 1. Title of Project and location. 2. The Architect and Construction Manager. 3. Name and Address of the Contractor. 4. Contract designation. 5. Date of submission. B. List the installed value of the component parts of the Work (broken down into labor and material and physical location) in sufficient detail to serve as a basis for computing values for progress paYments during construction. C. Follow the Specifications as the format for listing component items. 1. Identify each line item with the number and title of the respective major section of the Specifications. D. Itemize separate line item cost for each of the following general cost items: 1. Mobilization. 2. Bonds, Insurance and Permits. 3. General Conditions spread over project duration on monthly basis. 04/30/91 SCHEDULE OF VALUES 01370 - 1 4. Clean-up. 5. Submittals. 6. Safety. E. For each major line item list sub-values of major products or operations under the item. 2. the various portions of the Work: Include a directly proportional amount Contractor's overhead and profit for each For items on which progress payments requested for stored materials, break value into: a. The cost of the materials, delivered and unloaded, with taxes paid. b. The total installed value. Submit a subschedule for each separate stage of work specified in section 00300. of the item. will be down the F. For 1. 3 . G. The sum of values listed in the schedule shall equal the total Contract Sum. 1..3 SUBSCHEDULE OF UNIT MATERIAL VALUES A. Submit a subschedule of unit costs and quantities for: 1. Products on which progress payments will be requested for stored products. B. The form of submittal shall parallel that of the Schedule of Values, with each item identified the same as the line item in the Schedule of Values. C. The unit quantity for bulk materials shall include an allowance for normal waste. D. Provide unit values for the materials as follows: 1. Cost of the material, delivered and unloaded at the Site, with taxes paid. 2. Installation costs, including the Contractor's overhead and profit. E. The installed unit value multiplied by the quantity listed shall equal the cost of that item in the Schedule of Values. 1..4 REVIEW AND SUBMITTAL A. After review by Construction Manager, revise and resubmit schedule (and Schedule of Material Values) as required. 04/30/91 SCHEDULE OF VALUES 01370 - 2 B. Resubmit revised schedule in same manner. ************* END OF SECTION 1370 04/30/91 SCHEDULE OF VALUES 01370 - 3 SECTION 01385 DAILY CONSTRUCTION REPORTS PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Requirement for Daily Construction Reports by each Trade Contractor. 2. Scheduled submission times for Daily Construction Reports. 1..2 FORM AND CONTENT OF DAILY CONSTRUCTION REPORTS A. Daily Construction Reports shall be submitted by each and every Contractor performing work on the project. Forms to be used will be furnished by the Construction Manager. Items to be addressed on the Report are: 1. Title of Project 2. Name of Trade Contractor 3. Date and day of Report information. For example, you performed work on Thursday, April 18, 1991, so you would therefore use "Thursday, 4 / 18 / 91. " This holds true even if you did not complete filling out the Report until Friday, 4/19/91. 4. Contract designation. 5. Note any major Shipments received on that particular day. 6. Note major equipment used that day. 7. Note manpower used, and designate what trades. For example, if you were the mechanical contractor, you would also list how many insulators, pipefitters, etc. that you were also managing, even if they were subcontractors. In addition, list the names of the subcontractors that were on-site that day. 8. Note any deficiencies in your work, and corrective actions taken to resolve the deficiencies. 9. Note any safety violations discovered, whether or not caused by your forces. 10. Provide a full description of work performed that day, and any problems or unusual conditions discovered. 11. Report is to be signed by the al1thorized representati ve of the contractor, and should the signature not be legible, print the name of the signer next to the signature. 11/21/91 DAILY CONSTRUCTION REPORTS 01385 - 1 1..3 SCHEDULE OF SUBMITTING DAILY REPORTS A. Daily Reports are to be submitted at the designated location described in the pre-construction meeting. Contractors are to submit the original of their report, and should keep a copy for their records. The Construction Manager's photocopy ing faci 1 i ties are not to be used in the reproduction for submission of the reports. B. Submit Daily Reports no later than 9:00am the day following the day of the work described in that particular report. No exceptions to this rule will be accepted. Should contractor fail to comply with these instructions, the contractor's payment application for the following month will be held in abeyance until such time the contractor properly- submits the delinquent reports. ************* END OF SECTION 1385 DAILY CONSTRUCTION REPORTS 01385 - 2 11/21/91 - -.,.-- '_'4 ...... _ ..--'-'-iO.__.:.~_._.,..,..".~ -..- "_..~___'_"'- _,..-. _~ __.. _'_. :_._ = i\IONROE COUNTY CAPITAL Il\lPROVE,\lENT PROJECTS CONTRACTOR'S DAILY REPORT PROJ ECT: DATE: SHEET OF ~~')-~~~~..~~r- II! ~~..u ~ ".it .l11:\.>S"-e...~~ 'l'l'f:WWi~~-- CONTRACTOR: ~"..>S..~~~~~.:r=~ M..\JOR SH1PMENTS RECEIVED TODAY CONTRACRO.: ::s:~~.,..~~~~~~ !\t~OR EQUIPMENT USED ~~~~.~~~~~g...:J" .~~,-' --'-'-~,-~~~- NUMBER OF PERSONNEL O~SITE LlST SUBCONTRACTORS Ol\:SITE OFC C C C C C C SC SC T o T A L ~~~-c,~~__"",...~~_..., .".~~~~~J: DEFICIEJ\CIES NOTED/CORRECrED; INSPECTIONS ~iADE; TESTS CONDUCTED: QC REPRESEl\:TATIVE: S:\FETY V]OLATIO~S NOTEDiCORRECTED: -- ~---_. FULL DESCRIPTION OF WORK PERFOR~1ED BY AREA; INCLUDE ANY PROBLB1S: --~---- .----- SITE R.EPRESE';T.h.TIVE: =. .h. I J ACH ;>"-1) ::.:1EET1Fl\t:.J:1Jt:1J 2~D SHEET r==---~---~~=~- CO~;~ACTO;S DA~;~EPORT -----~- SHE;;~_~~:~~;:~-~_:=c~~l \~~~"'<...._...."'-.& R .__~--,..,.~~ ---------.------------ I PROJECT: WORK DAY: ~~-~~------ ------ CO'.;TRACT ~O.: DA TE: ,.~~~.~Ii\'t(~~...~ "-"'ilJii.~~~~:;'~ DESCR1PTJON OF WORK PERFORMED Liq a(livilic~ ~lar1l'd, 8Cli\.ilic~ cumrlclc<J, d('la)'~, rC~l~ons for dcl:j)'s, and r(,.J~ons for po"iblc future dc\3ys. ~1:;iii4:~~..JtI'L...- I ...;;u.......&::l'''''''~--- -1....t..........r.'""-"'-ffr~~.4i"t.~~=__..~~~~.......--.."'. -- -- -- .-- -- -- --------- -- -- -~ -- -- -~ .----------.---- - -------- ----- L -----~ =====_=~==_c= SECTION 01395 DOCUMENT CLARIFICATION REQUESTS (DCR) PART 1 - GENERAL 1.1 SUMMARY A. Section includes: 1. Notification of Construction Manager in the event errors, field conflicts, and omissions are found in the Contract Documents, or clarifications are necessary. 2. utilization of DCR form. B. Related Sections: 1. General Conditions Article 2.3 2. General Conditions Article 8.3.2 3. General Conditions Article 12.3 1.2 FORM AND CONTENT OF DOCUMENT CLARIFICATION REPORTS A. All errors, field conflicts, and omissions in the Contract Documents shall be brought to the attention of the Construction Manager immediately. If clarifications are necessary, the request is to be conveyed to the CM. The DCR is a tool established to provide expedient clarifications of contract drawings, specifications or field conflicts. It is not meant to be a substitute for good communication. B. The DCR is not meant for formal notification of extra work. Reference General Conditions paragraph 8.3.2 and 12.3, when formal correspondence is required for formal notif ication of time extensions, and for cost change notifications. C. The contractor should propose a solution, and enter on the form in sufficient detail necessary for the A/E or CM to confirm the contractor's proposed solution. D. The contractor is also required to mention all other trade work which is affected by the problem, and all trade work which will be affected by the proposed solution. 11/21/91 DOCUMENT CLARIFICATION REQUESTS 01395 - 1 1.3 UTILIZATION OF DCR FORM A. The CM will make available the DCR forms for the contractors use. Attached is a copy of the DCR form, and the instruction sheet. ************* END OF SECTION 1395 11/21/91 DOCUMENT CLARIFICATION REQUESTS 01395 - 2 ..<< -~-. .,--.-......- --...._,--- -... DOCUMENT CL<\RIFICATlON REQUEST No. From: To: Morrison- Knudse n/G errits Contract )\0. P. O. Box 5283 Key West, FL 33045 Receipt (305) 292-7S45 Lqgged: Problem By: DwglSpec No./Revision/Detail/Sect No. AlE Project No. Civil Siructural Architectural Se.curity PLB HVAC Electrical S~. Subject: . ~'W -- - .it. Problem & suggested solution: .., - - -- I \IK'G Rc\icw: Solution: -- Solulion bv: I Dale: I MI</G: I Dale: ')CROl , DOCUMU.' UARJnCA no' llQl'IST 1'0. (5) From: r M~KJ)IXbCn.'Vemtl (.or.ullnf'o. C~' ._@-- ,. o. >> ~1A.\ -- ).;.("'0 ~ot. FL ))04~ ReceIpt CD (~)~:.m~ Lou'. prrt-km By: 12. ' Dwa.'Sfu p.;vJ1l.....R~lail.&>n ,,"u A'l: P'n'f<<1 p...... \10' ,"l' __ .~ eMl s.\rvo.r~ AJo..Ie('\W" So.~"" ,LJj HVAC f.jox'lr.cal '''' ....,.., i'" ) I"wbkrr...lI.I"d-....:!~.~ -_..~ :'1 .- -- --.- - --- .----- - I "H:<. !<.....--- ~' ""~~ -- -~-- ~ ---- .- .- ---- ~ ('\5 1_ i1J,' 119& (11- ltlfl :,.~ = ~. By Contractor: 1. From: The OCR ~ill al~ays be froffi the Fri~e contractor. subcontractors to the prire contrbctor Shlloll submit OCR's through their prime contractor. 2. Problem By: This contractor, or representative, representative.. can be the subcontractor, or the prime the establ ished prime contractor or the established subcontractor 3. Contract No.: This is the approved contract, contract nun-iller. 4. Drli....ing No.: Here insert as Dluch infonr.ation as possible to d€:scribe the locatior. in the contract documents of the particular problem you are asking clarification. Include revision level of drawings, and date. Include detail numbers, include section nun~ers, include specification section nurr~ers, paragraph locations, all as applicable. 5. civil, structural, etC.: Here note the particular division of ~ork the DC~ app~ies to. 6. subject: Here insert brief, clear, concise caption subject, ,,'rdch is representative of problt=.m area. 7. Problem' suggested Solution: Describe in as much detail as necessary, t.he problem to~which clarification 1s needed. If additional space is needed, add extra sheets to back, and reference attachments in this area no. 7. Dra.. sketches if necessary. Make photocopy of particular dra~inq detail and attach if necessary. B. By Morrison-Knudsen/Gerrits: 8. DCR No.: Nurriliers ~ill be assigned bS fol1o~s: xx- Project xxx- Contractor }oIo. XXX Seq..Jential No. For instance, the first OCR from t.he contr~ctor of Contract No. 001 on the NeY Detention Facility, ~ould be: KJ-{'01-00l ~s another exa~ple: The seventh consecutive OCR logged on the New Detention Facility, \"as rece i ved fro. the contractor of Contract No. 005, ~ould be: KJ-005-007 9. ~eceipt Ifl9ged: This will be the date received by the eM from the cont.ractor, and ....ill s~rve as the reference date. 10. AlE Project No.: The AlE's project nu:::ber ,.'ill be insErted here, ~here and ~ht=.n applicable. 11. Y.K/G Revie...': Tt.is ...:ill bE the signature or initials of the Constructien ~~n~qer, upon revie.. of t.he prcbleJt, kith the date of ~ign-off. 12. MK/G ~evie*: ~tis _ill be the signature cr initials of the Construction Manager, upon revie.... of the solution. 13. Date: This ...dll be the date of ~K/G review and sign- oft. c. By Architect/Engineer: 14. Solutic~: The hiE .i11 here inSErt the solution to the probler., or o;)s""er lr. some ot.her fashion the clllriflcation being requested. The AlE roay herein confint the 'contract.or's fToposed solution. 15. Solution By: The entity providing the solution is to sign here. This rr.ay be the Construction Manager ....hen particular c1arifications are being requested that can be ansl,."ered ty the CY.. Othendse, it ....il1 be the 1-./E representative. 16. Date: This )o.'i11 be the date of sign-off, or ans...:ering the DCR by the AlE. D. Part-By-Part oistri~ution of ~-part OCR ror~: a. "'''hen the co.Jtractor sub;:its DCR, he .....ill retain gQ1..denrod copy. b. ~"hen received by the contractor, CM ""ill retain fiD.ls. copy. c. The DCR then is sub~itted to the ^/E. Once ans.ered, the AlE returns to eM, but retains Can~ copy. d. eM revie~s a~s~er, and sends Green copy back to contractor. Cl'. ",'ill retain original !5.hite copy for office files, and !Uue copy will go to the job-site. SECTION 01410 TESTING LABORATORY SERVICES PART 1 - GENERAL 1..1 SUMMARY A. Section includes: 1. Selection and payment 2. The Contractor submittals 3. Testing laboratory responsibilities 4. Testing laboratory reports 5. Limits on testing laboratory authority 6. The Contractor responsibilities 7. Schedule of inspections and tests B. 1. 2 . 3 . section 00750 - GENERAL CONDITIONS section 01700 - CONTRACT CLOSEOUT Individual Specification sections: inspections and tests required, and standards for testing. 1..2 REFERENCES A. ASTM D-3740 - Practice for Evaluation of Agencies in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction. B. ASTM E-329 - Recommended Practice for Inspection and Testing Agencies for Concrete, Steel, and Bituminous Materials as used in Construction. 1..3 SELECTION AND PAYMENT A. The Owner will employ and pay for services of an independent testing laboratory to perform specified inspection and testing where so indicated to be performed by the Owner in technical Specification Sections. B. Employment of testing laboratory shall in no way relieve the Contractor of obI igation to perform the Work in accordance with requirements of the Contract Documents. 11/21/91 TESTING LABORATORY SERVICES 01410 - 1 1..4 QUALITY ASSURANCE A. Comply with requirements of ASTM E-329 and ASTM D-3740. B. Testing laboratory: authorized to operate in the state of Florida. C. Testing laboratory staff: maintain a full time registered Engineer on staff to review services. D. Testing Equipment: calibrated at reasonable intervals with devices of an accuracy traceable to either National Bureau of standards (NBS) ~tandards or accepted values of natural physical constants. E. Meet "Recommended Requirements for Independent Laboratory Qualification", published by American council of Independent Laboratories. 1..5 TESTING LABORATORY RESPONSIBILITIES A. Test samples of mixes. B. Provide qualified personnel at the site. Cooperate with the Architect, Construction Manager and the Contractor in performance of services. C. Perform specified inspection, sampling, and testing of Products in accordance with specified standards. D. Ascertain compliance of materials and mixes with requirements of the Contract Documents. E. Promptly notify the Construction Manager and the contractor of observed irregularities or non-conformance of the Work or products. F. Perform additional inspections and tests required by the A/E and Construction Manager. 1..7 TESTING LABORATORY REPORTS A. After each inspection and test, promptly submit three copies of testing laboratory report to the Construction Manager. B. Include: 1. Date issued 2. Project title and number 3. Name of inspector 4. Date and time of sampling or inspection TESTING LABORATORY SERVICES 01410 - 2 11/21/91 5. Identif ication of product and Specifications section 6. Location in the Project 7. Type of inspection or test 8. Date of test 9. Results of test 10. Conformance with the Contract Documents C. When requested by the Construction Manager or A/E, provide interpretation of test results. 1..8 LIMITS ON TESTING LABORATORY AUTHORITY A. The testing laboratory may not release, revoke, alter, or enlarge on requirements of the Contract Documents. B. The testing laboratory may not approve or accept any portion of the Work. C. The testing laboratory may not assume any duties of the Contractor. D. The testing laboratory has no author i ty to stop the Work. 1..9 THE CONTRACTOR RESPONSIBILITIES A. B. C. D. E. 1. .10 A. Deliver to the testing laboratory at designated location, adequate samples of materials proposed to be used which require testing, along with proposed mix designs. Cooperate with testing laboratory personnel, and provide access to the Work and to the manufacturer's facilities. Provide incidental labor and facilities to provide access to the Work to be tested, to obtain and handle samples at the site or at source of products to be tested, to facilitate tests and inspections, storage and curing of test samples. Notify the Construction Manager and the testing laboratory 48 hours prior to expected time for operations requiring inspection and testing services. Employ services of a separate qualified testing laboratory and pay for additional samples and tests which are beyond the specified requirements. RETEST RESPONSIBILITY Where the results of required inspections, tests, or similar services prove unsatisfactory and do not indicate 11/21/91 01410 - 3 TESTING LABORATORY SERVICES compliance with the requirements of the Contract Documents, the retests shall be the responsibility of the Contractor regardless of whether the original test was the Contractor's responsibility. B. Retesting of the work revised or replaced by the Contractor is the Contractor's responsibility where required tests were performed on original work. Costs and fees for retesting shall be paid by the Contractor. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used ************** END OF SECTION 01410 11/21/91 TESTING LABORATORY SERVICES 01410 - 4 -.. --"'~--.T--'.'--.-'.-----~'-"-"'---.'- -"';:.". -'"--.--.' ,.., -,." SECTION 01510 TEMPORARY UTILITIES PART 1 - GENERAL 1.1 SUMMARY A. section includes: 1. Temporary utilities required for construction. PART 2 - PRODUCTS 2.1 MATERIALS-- GENERAL A. Materials shall be new, adequate in capacity for the required usage, not create unsafe conditions, not violate requirements of applicable codes and standards, and comply with NEe Art. 305 - Temporary Wiring. 2.2 TEMPORARY ELECTRICITY A. The Temporary Power Contractor shall furnish, install and maintain, temporary electric. power service for construction needs throughout the construction period and shall remove such service on completion of the work. 1. Primary temporary electrical underground feeder will be provided and installed by temporary power contractor under Bid Group 1, per drawing 1510- TP. 2. At Front Gate transformer location, the temporary power contractor under Bid Group 1 has installed a meter, mast, and main breaker panel Nema 3R, per Detail "A" attached. The final location of each panel shall be approved by the Construction Manager. 3. Distribution panels have been provided by the Bid Group 1 temporary power contractor per drawing 1510 - TP, and Details A, B, C and D, and as follows: a. Front gate area serving the construction manager trailer, guard shack and area lights. (20 ckt. min.) 4. Power centers for miscellaneous tools and used in the Work will be provided by the 1 Temporary Power Contractor as follows: a. distribution boxes with minimum equipment Bid Group of four 11/21/91 TEMPORARY UTILITIES 01510 - 1 double-duplex 15 Amp, 120-Volt grounded outlets, with GFCI Protection for personnel. See Detail "B". b. located so that power is available at any point of use with not more than 100 ft. power cords. c. minimum: one power center on each floor. d. circuit-breaker protection for each outlet. e. One panel each for Building Areas A,B,C,D,E,F,K,L,M,N,O,P and Q. 5. The capacity of each power center in 4. above~shall be 120/240 volts single phase, minimum 50 Amps. 6. The Trade Contractors shall notify the Temporary Power Contractor when unusually heavy loads, such as for welding and other equipment with special power requirements, will be connected so that the Bid Group 3 Temporary Power Contractor can notify the power company. 7. Any Trade Contractor requiring service of capacity or characteristics other than that specified shall arrange and pay for the additional service. 8. The Temporary install, and required to including the Power Contractor shall furnish, maintain all equipment and wiring distribute the power, up to and power services. 9. The Temporary Power Contractor shall pay all costs of installation, maintenance, and removal of temporary services. 10. The Construction Manager will pay the costs of power needed, including deposits and fees associated with city Electric except as outlined in item 13 below 11. Materials shall be new, and r:mst be adequate in capacity for required usage, and must not violate the requirements of applicable codes and standards. Materials used for temporary service shall not be reused in the permanent system. 12. The Temporary Power Contractor shall comply with all applicable requirements specified in National Electr ic Code Art. 305 when insta II ing the temporary electr ic power service, sha II rna inta in the system to provide continuous service and shall modify and extend the service as the progress of 11/21/91 TEMPORARY UTILITIES 01510 - 2 the Work requires. 13. wiring for Trade Contractor field offices and sheds shall be installed by the Temporary Po.....er Contractor and paid for by the Trade Contractor requiring the service. 14. The Temporary Power Contractor shall completely remove all temporary materials and equipment at Project Completion. Underground lines may be disconnected and abandoned in place with approval of the Construction Manager. The temporary shed as shown in Detail "e" shall remain the property of Benson Electric. 15. Feeders to distribution panels from distribution shed shall be 400 feet maximum length, with two hot legs and one neutral of the same size as per NEC Table 310-16 and Article 210-19a FPN. 16. Circuits to Power Centers from Distribution Panels shall be installed per NEC Art. 305. 17. Feeders and Branch Circuits in 15. and 16. above shall be protected from physical damage. 18. See Detail "C" for temporary power shed requirements. This shall remain the property of Benson Electric. 2.3 TEMPORARY SITE LIGHTING The Temporary Power Contractor shall install and maintain area lights on the meter poles as shown in Detail "A", 2 lights total. Temporary Lighting power will be fed from the panels and power centers covered under Section 2.2 TEMPORARY ELECTRICITY. 2.4 TEMPORARY TELEPHONE SERVICE A. Each Trade Contractor shall be responsible for arranging with the local telephone service company to provide telephone service at the construction site for the use of his personnel and employees. The Trade Contractor shall pay all costs for installation, maintenance, removal and service charges for such service. The Construction Manager will not act as an answering service for Trade Contractor's personnel and employees, and Trade Contractor's personnel and employees will not be permitted to utilize the Construction Manager's phones except in cases of an emergency. 11/21/91 TL~PORARY UTILITIES 01510 - 3 2.5 CONTINUING TEMPORARY ELECTRICITY MAINTENANCE At the option of the Owner, the Temporary Power Contractor shall provide a minimum of 1 person full time for the duration of the construction, estimated to be 18 months. This person will maintain, relocate and repair the temporary utilities covered under Articles 2.2, 2.3 and 2.4. The bid for this work shall be based on an hourly rate for licensed electrician. 2.6 TEMPORARY LIGHTING A. The Electrical Trade Contractor will be responsible for the installation of the permanent electrical system and shall also furnish, install and maintain temporary lighting for construction needs throughout the construction period and shall remove such temporary lighting on completion of the Work. 1. Temporary artificial lighting shall be provided in enclosed Work areas and all other work areas when natural lighting does not meet minimum requirements. Temporary artif icial lighting in Work areas shall produce uniform illumination of 20-foot candles. 2. Any Trade Contractor requiring temporary lighting in addition to that specified, including lighting for security, temporary offices, storage, shops and other construction buildings, shall arrange and pay for such additional temporary lighting. 3. Power requirements and source will be coordinated with Article 2.2 above. 4. The Electrical Contractor shall comply with the applicable requirements specified in sections of Division 16 - Electrical. Materials shall be new, and must be adequate for required usage, and must not violate requirements of applicable codes and standards. 5. Receptacles, fixtures and controls shall be standard products, meeting UL standards. 6. The Electrical Contractor shall comply with all applicable requirements specified in sections of Division 16 Electrical, when installing the temporary lighting, shall locate fixtures to provide full illumination of required areas, shall maintain the system to provide continuous service, and shall modify and extend the service as the progress of the Work requires. 7. The Electrical Contractor shall completely remove temporary materials and equipment at Project Completion, except for high voltage underground. 11/21/91 TEMPORARY UTILITIES 01510 - 4 2.7 A. B. C. D. E. 2.8 TEMPORARY WATER site Plumbing Contractor will arrange service company, to provide water for purposes. with utility construction site Plumbing Contractor will provide temporary water at locations of two (2) fire hydrants on fire. water loop as directed by Construction Manager; fire water loop will be charged to provide construction water. The Construction Manager will pay for water used for temporary construction purposes. Building Plumbing Contractor will maintain temporary water systems, and will remove temporary water appurtenances at completion of project. Each Trade Contractor shall be responsible for providing any additional water (if needed) for construction purposes. In addition, each Trade Contractor is responsible for providing potable drinking water for his personnel and employees, as well as suitable containers, ice and salt tablets in sufficient quantity to meet the needs of his labor force. TEMPORARY HEATING, COOLING AND VENTILATING Each Trade Contractor shall be responsible for providing, and operating and maintaining temporary heating, cooling and ventilating, as required, to maintain adequate environmental conditions to facilitate the progress of his Work; to meet minimum condition for the installation of materials; and to protect materials and finishes from damage due to temperature or humidity. Each Trade Contractor, subject to the approval and direction of the Construction Manager, shall: 1. Provide adequate forced ventilation of enclosed areas for curing of installed materials, to disperse humidity, and to prevent hazardous accumulations of dust, fumes, vapors, or gases. 2. If portable heaters are required, utilize only UL approved units complete with controls. 3. Insure that all safety devices specified for operation of equipment are functioning properly. 4. Pay all costs of providing, operating, maintaining, and removing such temporary heating, cooling, and ventilating equipment as may be required. 11/21/91 01510 - 5 TEMPORARY UTILITIES The foregoing obligations of the Trade Contractor are in addition to his obligations under Article 10 of the General Conditions. 2.9 A. B. 2.10 TEMPORARY SANITARY FACILITIES The Owner will provide sanitary facilities in compliance with laws and regulations. The Owner will service, clean and maintain facilities and enclosures. TEMPORARY FIRE PROTECTION The Trade Contractor responsible for the installation of the permanent fire protection system shall furnish, install and maintain temporary fire protection equipment, materials, supplies and service within the buildings throughout the construction period in accordance with the requirements of all applicable codes and standards. Each floor shall have a temporary fire protection system. Each Trade Contractor will be responsible for fire protection required for his own work. 2.11 A. B. REMOVAL Completely remove temporary materials and equipment when their use is no longer required. Clean and repair damage caused by temporary installations or use of temporary facilities. c. Restore permanent facilities used for temporary services to specified condition. 1. Prior to final painting, the responsible for the permanent system, shall remove temporary Trade Contractor building lighting lamps and install new lamps. 2 . Pr ior to final inspection, the Trade Contractor responsible for the building mechanical system shall replace filters and worn or consumed parts of mechanical equipment. *************** END OF SECTION 01510 11/21/91 TEMPORARY UTILITIES 01510 - 6 SECTION 01520 CONSTRUCTION AIDS PART 1 - GENERAL 1.1 SUl1MARY A. section includes: 1. Construction aids 2. Temporary enclosures 1.2 REQUIREMENTS OF REGULATORY AGENCIES B. Comply with Federal, regulations. state and local codes and PART 2 - PRODUCTS 2..1 MATERIALS - GENERAL A. Materials may be new or used, suitable for the intended use and shall not violate requirements of applicable codes and standards. 2..2 CONSTRUCTION AIDS A. Each Trade Contractor shall be responsible for furnishing, installing, maintaining, and removing on completion of the Work all scaffolds, staging, ladders, stairs, ramps, runways, platforms, railings, chutes, and other such facilities and equipment required by his personnel to insure their safety and faci li tate the execution of the Work. 1. Each Trade Contractor shall comply with all Federal, State and local codes, laws and regulations governing such construction aids. 2. Each Trade Contractor shall relocate such construction aids as required by the progress of construction, by storage or work requirements, and to accommodate the legitimate requirements of the Owner or Construction Manager or other separate contractors employed at the site. 3. Each Trade Contractor shall completely remove temporary scaffolds, access, platforms, and other such materials, facilities, and equipment, at the completion of the Work or when construction needs can be met by the use of the permanent construction, provided the Construction Manager has 04/09/91 CONSTRUCTION AIDS 01520 - 1 approved and authorized such use. Each Trade Contractor shall clean up and shall repair any damage caused by the installation or by the use of such temporary construction aids. Each Trade Contractor shall restore any permanent facilities used for temporary purposes to their specif ied condition. The foregoing obligations of the Trade Contractor are in addition to his obligations under Article 10 of the General Conditions. 2..3 TEMPORARY ENCLOSURES A. The Trade Contractor responsible for installing the permanent closure in an opening in an exterior wall shall be responsible for installing, maintaining, and removing, as the Work progresses, a temporary weather-tight enclosure for that opening as necessary to provide acceptable working conditions, to provide weather protection for interior materials, to allow for effective temporary heating, and to prevent entry of unauthorized persons. 1. Each Trade Contractor shall install such temporary enclosures as soon as is practical after the opening is constructed or as directed by the Construction Manager. 2. Temporary enclosures shall be removable as necessary for the Work and for handling of materials. 3. Temporary enclosures shall be completely removed when construction needs can be met by the use of the permanent closures. 4. The Trade Contractor responsible for providing, maintaining, and removing the temporary enclosure shall clean and shall repair any damage caused by the installation of such enclosure. 5. Each Trade Contractor shall remain responsible for insuring that his work, material, equipment, supplies, tools, machinery, and construction equipment is adequately protected from damage or theft and shall provide, maintain and remove such additional temporary enclosures as may be deemed necessary. The foregoing obligations of the Trade Contractor are in addition to his obligations under Article 10 of the General Conditions. **************** END OF SECTION 01520 04/09/91 CONSTRUCTION AIDS 01520 - 2 SECTION 01550 ACCESS ROADS AND PARKING AREAS A. Each Trade Contractor shall be responsible for installing and maintaining, until the completion of his Work any temporary access roads or parking facilities required by his Work, other than that which has been provided by the Owner. B. Any Trade Contractor excavating across an access road or parking area shall backfill and compact his excavation and resurface the road or parking area to match the existing surface. The Trade Contractor shall comply with all applicable Specifications when so doing. ********************* END OF SECTION 01550 04/09/91 ACCESS ROADS AND PARKING AREAS 01550 - 1 SECTION 01560 TEMPORARY CONTROLS PART 1 - GENERAL 1..1 SUMMARY A. Section Includes: 1. Water control 2. Dust control 3. Erosion and sediment control 4. Pollution control B. Related sections: 1. SCOPES OF WORK 1..2 WATER CONTROL A. site Grading Contractor shall grade site to drain. B. Protect site from puddling or running water. water barriers to protect site from soil Maintain excavations free of water. Provide, and maintain pumping equipment. Provide erosion. operate, 1..3 DUST CONTROL A. Execute the Work by methods to minimize raising dust from construction operations. B. Provide positive means to prevent airborne dust from dispersing into atmosphere. 1..4 EROSION AND SEDIMENT CONTROL A. Plan and execute construction by methods to control surface drainage from cuts and fills, from borrow and waste disposal areas. Prevent erosion and sedimentation. B. Minimize amount of bare soil exposed at one time. C. Provide temporary Deasures such as berms, dikes, and drains, to prevent water flow. D. Construct fill and waste areas by selective placement to avoid erosive surface silts or clays. E. Inspect earthwork to detect evidence of erosion and OS/20/91 TEMPORARY CONTROLS 01560 - 1 sedimentation; promptly apply corrective measures. 1..5 POLLUTION CONTROL A. Provide methods, means, and facilities to prevent contamination of soil, water, and atmosphere from discharge of noxious, toxic substances, and pollutants produced by construction operations. Two (2) 30 c.y. trash containers will be provided by the Owner. The Masonry Contractor shall be responsible to -provide his own trash dumpsters for masonry waste disposal. Tr~shcontainers shall be located in trash accumulation areas designated by the Construction Manager. Each Contractor each day shall collect and deposit in the containers, all rubbish, wast~ materials, debris, and other trash from his operations, (excluding masonry), including any trash generated by his employees during lunch periods or coffee breaks. Shipping dunnage is to be removed by the receiving contractor. Paper, boxes and bulk packaging shall be folded or cut into reasonable sizes and shapes and confined to prevent lost of trash container volume or wind relocation. *************** END OF SECTION 01560 OS/20/91 TEMPORARY CONTROLS 01560 - 2 - .~- -<olr--"~,~' 'f't.,~~--..-..~---.-._,~-",.~-o--.'[..:..~-~.......", ~ ~_'_'."__'_'.. _ ___'__."'. ~ SECTION 01580 PROJECT IDENTIFICATION AND SIGNS Trade Contractors informational signs on the site shall be limited to those designating their tenporary field offices and sheds. All such informational signs shall be subject to approval by the Construction Manager. ************************* END OF SECTION 01580 11/21/91 PROJECT IDENTIFICATION AND SIGNS 01580 - 1 SECTION 01590 FIELD OFFICES AND SHEDS A. The Trade Contractor, if he~_ deems it necessary I may furnish, install, and maintain a temporary field office for his use and the use of his employees during the construction period. B. The Trade Contractor shall furnish, install, and maintain temporary storage and work sheds to adequately protect his work, materials, equipment, supplies, tools, machinery, and construction equipment from damage and theft. C. The Trade Contractor shall arrange his field office and sheds so as not to interfere with the construction. The locations of field offices and sheds shall be coordinated with the Construction Manager. The type, size and location of field offices and sheds is subject to approval by the Construction Manager. D. The Trade Contractor shall arrange and pay for temporary electricity and telephone service for his field office and sheds, if he should require such services. E. The Trade Contractor shall relocate his field office and sheds as directed by the Construction Manager, at no additional cost to the Owner or Construction Manager. F. The Trade Contractor shall completely remove his field off ice and sheds on completion of the Work or when directed by the Construction Manager. The Trade Contractor shall remove all debris and rubbish and shall place the area in a clean and orderly condition. G. The Construction Manager as soon as reasonably possible will establish a field office on the site and will maintain such an office during the entire construction period. The Construction Manager's field office will not be used as field office by the Trade Contractor or his employees. ************** END OF SECTION 01590 04/09/91 FIELD OFFICES AND SHEDS 01590 - 1 SECTION 01595 CONSTRUCTION CLEANING PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Cleaning during progress of work. 1..2 DISPOSAL REQUIREMENTS : ~. A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws. 1. Do not burn or bury rubbish and waste materials on Project site. 2. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains. PART 2 - PRODUCTS 2..1 MATERIALS A. Use only those cleaning materials which will not create hazards to health or property and which will not damage surfaces. B. Use only those cleaning materials and methods recommended by manufacturer of the surface material to be cleaned. C. Use cleaning materials only on surfaces recommended by cleaning material manufacturer. D. Sweeping compounds used in cleaning operations shall leave no residue on concrete floor surfaces that may affect installation of finish flooring materials. PART 3 - EXECUTION 3..1 DL~ING CONSTRUCTION A. Execute cleaning to keep the Work, the site and adjacent properties free from accumulations of waste materials, rubbish and windblown debris, resulting from construction operations. B. Provide on-site containers for the collection of waste 04/09/91 CONSTRUCTION CLEANING 01595 - 1 materials, debris, and rubbish. C. Dispose of waste materials, debris and rubbish off the site. 3..2 DUST CONTROL A. Clean interior spaces prior to the start of the finish painting and continue cleaning on an as-needed basis until painting is finished. B. Schedule operations so that dust and other contaminants resulting from cleaning process will not fall on wet or newly-coated surfaces. C. Handle materials in a controlled manner with as little handling as possible; do not drop or throw materials form heights. ************ END OF SECTION 01595 04/09/91 CONSTRUCTION CLEANING 01595 - 2 SECTION 01600 MATERIAL AND EQUIPMENT PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1 . Products 2. Transportation and handling 3. storage and protection 4. Security 1..2 PRODUCTS A. Products: means new material, machinery, components, equipment, fixtures, and systems forming the Work. Does not include machinery and equipment used for preparation, fabrication, conveying and erection of the Work. Products may also include existing materials or components required for reuse. B. Do not use materials and equipment removed from existing premises, except as specifically permitted by the Contract Documents. C. Provide interchangeable components manufacturer, for similar components. of the same 1..3 TRANSPORTATION AND HANDLING A. The Trade Contractor shall be responsible for the transportation of all materials and equipment furnished under this contract. The Trade Contractor shall also be responsible for loading, receiving and off-loading at the site all material and equipment installed un der this Contract, whether furnished by the Trade Contractor or the Owner. Unless otherwise provided, the Construction Manager will not accept delivery on behalf of the Trade Contractor for his materials and equipment. The Trade Contractor shall be responsible for coordinating the installation within the buildings of equipment that is too large to pass through finished openings. B. Transport and handle products in accordance with manufacturer's instructions. C. Promptly inspect shipments to assure that products comply 04/09/91 MATERIAL AND EQUIPMENT 01600 - 1 with requirements, quantities are correct, and products are undamaged. D. Provide equipment and personnel to handle products by methods to prevent soiling, disfigurement, or damage. 1..4 STORAGE AND PROTECTION The Trade Contractor shall be responsible for the proper storage of all materials, supplies, and equipment to be installed under this Contract. Materials stored on site but not adequately protected will not be included in estimates for payment. Except for materials stored ~lthin designated and approved storage sheds, vans, or .1:railers, the Trade Contractor shall not bring onto nor store in any manner at the site any materials and equipment which will not be incorporated into the permanent Work within seven (7) days from the delivery date. The Trade Contractor shall be responsible for arranging and paying for the use of property off the site for storage of materials and equipment as may be required. 1..5 SECURITY A. Each Trade Contractor shall be totally responsible for the security of his work, materials, equipment, supplies, tools, machinery, and construction equipment. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used ************* END OF SECTION 01600 04/09/91 MATERIAL fu~D EQUIPMENT 01600 - 2 SECTION 01630 POST-BID SUBSTITUTIONS PART 1 - GENERAL 1.1 SUMMARY A. section includes: 1. Post-bid substitutions 1.2 SUBSTITUTIONS A. Base Bid shall be in accordance with the Contract Documents. B. After the end of the bidding requests will be considered only 1. Product unavailability 2. Other conditions beyond Contractor. period, substitution in the case of: the control of the C. Submit a separate request for each substitution. Support each request with the following information: 1. Complete data substantiating compliance of proposed substitution with requirements stated in Contract Documents: a. Product identification, including manufacturer's name and address. b. Manufacturer's literature, identifying: 1) Product description. 2) Reference standards. 3) Performance and test data. c. samples, as applicable. d. Name and address of similar projects on which product has been used and date of each installation. 2. Itemized compar ison of the proposed substitution with product specified, listing significant variations. 3. Data relating to changes in construction schedule. 4. Effects of substitution on separate contracts. 5. List of changes required in other work or products. 6. Accurate cost data comparing proposed substitution with product specified. a. Amount of net change to Contract Sum. 7. Designation of required license fees or royalties. 8. Designation of availability of maintenance services, sources of replacement materials. 04/09/91 POST-BID SUBSTITUTIONS 01630 - 1 D. Substitutions will not be considered for acceptance when: 1. A substitution is indicated or implied on shop drawings or product data submittals without a formal request from Bidder. 2. Acceptance will require substantial revision of Contract Documents. 3. In judgement of Architect or Construction Manager, the substitution request does not include adequate information necessary for a complete evaluation. 4. Requested directly by a subcontractor or supplier. E. Do not order or install substitute products without written acceptance of Construction Manager. F. Architect will determine acceptability of proposed substitutions. G. No verbal or written approvals other than by Change Order will be valid. 1..3 CONTRACTOR'S REPRESENTATION A. In making formal request for substitution the Contractor represents that: 1. The proposed product has been investigated and it has been determined that it is equivalent to or superior in all respects to the product specified. 2. The same warranties or bonds will be provided for the substitute product as for the product specified. 3. Coordination and installation of the accepted substitution into the Work will be accomplished and changes as may be required for the Work to be complete will be accomplished. 4. Claims for additional costs caused by substitution which may subsequently become apparent will be waived by the Contractor. 5. Complete cost data is attached and includes related costs under the Contract, but not: a. Costs under separate contracts. b. Architect's costs for redesign or revision of Contract Documents. 1..4 POST-BID SUBSTITUTION FORM A. The form is attached to this section. B. Substitutions will be considered only when the attached form is completed and included with the submittal with back-up data. 04/09/91 POST-BID SUBSTITUTIONS 01630 - 2 -.-. --- '~.' "". --~-~'>'-"''---~.''''r''V-,"".',,",,"---'.''.'-..-~~-~>.'''':r'~ 'f:<-'--:--,' ~',..~- -"'-- '~ PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used 04/09/91 POST-BID SUBSTITUTIONS 01630 - 3 TO: Project Architect HANSEN LIND MEYER INC. c/o Morrison-Knudsen/Gerrits P.O. Box 5283 5090 Jr. College Road, Key West, Fl. 33040 (305)292-7845 FAX (305)292-9697 We hereby submit for your consideration the following product instL~d c the specified item for the above project: DRAWING NO. DRAWING NAME SPEC. SEC. SPEC. NAME PARAGRAPH SPECIFIED ITEM Proposed Substitution: Attach complete information on changes to Drawings and/or Specificatio~ which proposed substitution will require for its proper installation. Submit with request necessary samples and substantiating data to pro~ equal quality and performance to that which is specified. Clearly mal manufacturer's literature to indicate equality in performance. The undersigned certifies that the function, appearance and quality al of equal performance and assumes liability for equal performance, equc design and compatibility with adjacent materials. Submitted By: Signature Title Firm Address Telephone Date signature shall be by person having authority to legally bind his firm t the above terms. Failure to provide legally binding signature will resu= in retraction of approval. For use by the Architect: ____Recommended ____Recommended as noted ____Not Recommended ____Received too late Insufficient data received By Date Fill in Blanks Below: A. Does the substitution affect dimensions shown on Drawings? Yes No If yes, clearly indicate changes. B. will the undersigned pay for changes to the building design including engineering and detailing costs caused by the requestec substitution? Yes No If no, fully explain: C. What effect does substitution have on other Contracts or othel trades? D. What effect does substitution have on construction schedule? E. Manufacturer's warranties of the proposed and specified items are: Same Different. Explain: F. Reason for Request: G. Itemized comparison of specified item(s) substitution; list significant variations: with the proposec H. This substitution will amount to a credit or extra cost to the Ownel of: dollars ($ ). I. Designation of maintenance services and sources: (Attach additional sheets if required.) **************** END OF DOCUMENT 01630 SECTION 01650 STARTING OF SYSTEMS PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. starting systems 2. Demonstration and instructions 3. Testing, adjusting, and balancing B. Related sections: 1. SECTION 01700 - CONTRACT CLOSEOUT 1..2 STARTING SYSTEMS A. Coordinate schedule for start-up of various equipment and systems. B. Notify the Construction Manager seven days pr ior to start-up of each item. C. verify that each piece of equipment or system has been checked for proper lubrication, drive rotation, belt tension, control sequence, or other conditions which may cause damage. D. Verify that tests, meter readings, and specified electrical characteristics agree with those required by the equipment or system manufacturer. E. Verify wiring and support components for equipment are complete and tested. F. Execute start-up under supervision manufacturer's representative in manufacturer's instructions. of responsible accordance with G. Execute start-up under supervision of the responsible Contractors' personnel in accordance with manufacturer's instructions. All in-line and interface trades shall cooperatively support and coordinate individual components and systems to facilitate start-up activities. H. When specified in individual Specif ication sections, require manufacturer to provide authorized representative to be present at the site to inspect, check and approve 11/21/91 STARTING OF SYSTEMS 01650 - 1 equipment or system installation prior to start-up, and to supervise placing equipment or system in operation. I. Submit a certified written report that equipment or system has been properly installed and is functioning correctly. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used ************** END OF SECTION 01650 11/21/91 STARTING OF SYSTEMS 01650 - 2 SECTION 01670 SYSTEMS DEMONSTRATIONS PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Procedures for demonstration of equipment operation and instruction of the Owner's personnel. 1..2 QUALITY ASSURANCE A. When specified in individual Sections, provide manufacturer's authorized representative to demonstrate operation of equipment and systems, instruct the Owner's personnel and provide written report that demonstrations and instructions have been completed. B. The Owner will provide list of personnel to receive instructions, and will coordinate their attendance at agreed-upon times. 1. .3 SUBMITTALS A. Submit preliminary schedule for the Owner's approval, listing times and date for demonstration of each item of equipment and each system, two weeks prior to proposed dates. B. Provide operating and maintenance manuals to owner (4) weeks prior to demonstrations. C. Submi t reports wi thin one week after completion of demonstrations, that demonstrations and instructions have been satisfactorily completed. Give time and date of each demonstration, and hours devoted to demonstration, with a list of persons present. PART 2 - PRODUCTS NOT USED PART 3 - EXECUTION 3..1 PREPARATION A. Verify equipment has been inspected and put into 04/30/91 SYSTEMS DEMONSTRATIONS 01670 - 1 operation; performed; operational. testing, adjusting, and balancing has been and equipment and systems are fully B. Have copies manuals at instructions. of completed operation and maintenance hand for use in demonstrations and 3..2 DEMONSTRATION AND INSTRUCTIONS A. Demonstrate operation and maintenance of equipment and systems to the Owner's personnel two weeks prior to date of final inspection. For equipment requiring seasonal operation, perform instructions for other seasons within six months. B. Use operation and maintenance manuals as basis of instruction. Review contents of manual with personnel in detail to explain aspects of operation and maintenance. C. Demonstrate start-up, operation, control, maintenance, servicing, trouble-shooting and each item of equipment at agreed-upon designated location. adjustment, shutdown of times, at D. Prepare and insert additional data in operations and maintenance manuals when need for additional data becomes apparent during instructions. 3..3 TIME ALLOCATED FOR INSTRUCTIONS A. The amount of time required for instruction on each item of equipment and system is specified in individual Sections. ************** END OF SECTION 01670 04/30/91 SYSTEMS DEMONSTRATIONS o 1 67 0 .- 2 - , ..~. .._c,_ ~..." ~_' .._, _... ,_, ''',__ __ .~_'''', ~__- . ':"'_ SECTION 01700 CONTRACT CLOSEOUT PART 1 - GENERAL 1. . 1 SUMYiARY A. section includes: 1. Closeout p~ocedures 2. Adjusting B. Related sections: 1. SECTION 01027 - APPLICATION FOR PAYMENT 2. SECTION 01650 - STARTING OF SYSTEMS 3. SECTION 01730 - OPERATION AND MAINTENANCE DATA 4. SECTION 01740 - WARRANTIES AND BONDS 5. SECTION 08710 - FINISH HARDWARE 6. SECTION 11196 - SECURITY HARDWARE 1..2 PROJECT TERMINATION A. the Contract requirements are met when construction acti vi ties have successfully produced, in this order, these three terminal activities: 1. Substantial Completion 2. Final Completion 3. Final Payment 1..3 SUBSTANTIAL COMPLETION A. Submit to the Construction Manager when the Work is substantially complete: 1. A written notice that the Work, or designated portion thereof, is substantially complete. 2. A list of items to be completed or corrected (Punch List) . 3. Request Substantial Completion Observation at a mutually agreeable date. 4. certifications of systems and testing/balancing final reports. 5. Submit evidence of compliance with requirements of governing authorities: a. certificate of Occupancy b. certificates of Inspection: 1) Elevators 2) Mechanical systems 3) Electrical systems 4) Kitchen equipment 04/09/91 CONTRACT CLOSEOUT 01700 - 1 5) Fire protection system 6) Security system B. within a reasonable time after receipt of such notice, the Architect, the Construction Manager, the Contractor,and the Owner, will make an observation to determine the status of completion. C. Should the work be determined to not be substantially complete the following will occur: 1. The Construction Manager will promptly notify the Contractor in writing, giving the reasons. 2. The Contractor shall remedy the deficiencies in the Work, and send a second written notice of substantial completion. 3. The Work will be reobserved. D. When the Work is considered substantially complete, the following will occur: 1. The Construction Manager will prepare a certificate of Substantial Completion on AlA Form G704, accompanied by the Contractor's Punch List of items to be completed or corrected, as verified and amended. Contract responsibilities are not altered by inclusion or omission of required Work from the punch list. 2. The certificate will be executed by all parties and distribution made. E. Complete or correct items identified on the punch list and required by the Contract requirements wi thin time limit established by the certificate. 1..4 FINAL COMPLETION A. To attain final completion, the Contractor shall complete activities pertaining to substantial completion, complete Work on punch list items and submit written request to the Construction Manager for final inspection. B. When the Work is complete, the Contractor shall submit written certification that: 1. The Contract Documents have been reviewed. 2. Work has been inspected for compliance with the Contract Documents. 3. Work has been completed in accordance with the Contract Documents. 4. Equipment and systems have been tested in the presence of the Owner's representative and are operational. 5. Work is completed and ready for final observation. CONTRACT CLOSEOUT 01700 - 2 04/09/91 C. D. The Architect, the Construction Manager, the Contractor and the Owner will make an inspection to verify the status of completion with reasonable promptness after receipt of such certification. Should the Work be considered incomplete or defective: 1. The Construction Manager will promptly notify the Contractor in writing, listing the incomplete or defective work. 2. The Contractor shall take immediate steps to remedy the stated deficiencies and send a second written certification to the Construction Manager that the Work is Complete. 3. The Work will be reinspected. E. When the Work is acceptable under the Contract Documents the Contractor shall make closeout submittals. 1..5 THE CONTRACTOR'S CLOSEOUT SUBMITTALS TO THE ARCHITECT to requirements of SECTION A. Project Record Documents: 01720. B. Operating and maintenance data, instructions to the Owner's personnel: to requirements of SECTION 01730. C. Keys and keying schedule: 08710 & 11196. to requirements of SECTION D. Spare parts and maintenance materials: to requirements of individual sections. E. Evidence of payment and release of liens: to requirements of General and Supplementary Conditions. 1..6 FINAL ADJUSTMENT OF ACCOUNTS A. Submit a final statement of accounting to the Architect. B. Statement shall reflect adjustments to the Contract Sum: 1. The original Contract Sum 2. Additions and deductions resulting from: a. Previous Change Orders b. Allowances c. Unit Prices d. Deductions for uncorrected Work e. Penalties and bonuses f. Deductions for liquidated damages g. Deductions for reinspection payments h. Other adjustments 3. Total Contract Sum, as adjusted 04/09/91 CONTRACT CLOSEOUT 01700 - 3 4. Previous payments 5. Sum re~aining due C. The Construction Manager will prepare a final Change Order, reflecting adjustments to the Contract Sum which were not previously made by Change Orders. 1..7 FINAL APPLICATION FOR PAYMENT A. The Contractor shall submit the final Application for Payment in accordance with procedures and requirements stated in the Conditions of the Contract. PART 2 - PRODUCTS Not used PART 3 - EXECUTION Not used ***************** END OF SECTION 01700 04/09/91 CONTRACT CLOSEOUT 01700 - 4 SECTION 01710 FINAL CLEANING PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Cleaning at completion of Work 1..2 DISPOSAL REQUIREMENTS A. Conduct cleaning and disposal operations to comply with codes, ordinances, regulations, and anti-pollution laws. 1. Do not burn or bury rubbish and waste materials on the Project site. 2. Do not dispose of volatile wastes such as mineral spirits, oil or paint thinner in storm or sanitary drains. PART 2 - PRODUCTS 2..1 MATERIALS A. Use only those cleaning materials which will not create hazards to health or property and which will not damage surfaces. B. Use only those cleaning materials and methods recommended by manufacturer on the surface material to be cleaned. C. Use cleaning materials only on surfaces recommended by cleaning material manufacturer. PART 3 - EXECUTION 3..1 DUST CONTROL A. Handle materials in a controlled manner with as little handling as possible. 3..2 FINAL CLEANING A. Employ skilled workmen for final cleaning. B. Remove grease, mastic, adhesives, dust, dirt, stains, fingerprints, labels, and other foreign materials form sight-exposed interior and exterior surfaces. 04/09/91 FINAL CLEANING 01710 - 1 C. Wash and shine glazing and mirrors. D. Polish glossy surfaces to a clear shine. E. Dust cabinetwork and remove markings. F. Vacuum as needed. G. Broom clean exterior paved surfaces; surfaces of the grounds. rake clean other H. Prior to final completion, or the . Owner occupancy, conduct an inspection of sight-exposed ~nterior surfaces, exterior surfaces and work ~areas, to verify that the entire Work is clean. I. Clean tunnels and closed" off spaces of packing boxes, wood frame members and other waste materials used in the Construction. J. Internally clean the entire system of piping and equipment. Open dirt pockets and strainers, completely blowing down as required and clean strainer screens of accumulated debris. K. Drain tanks, fixtures and pumps to be free of sludge and accumulated matter. L. Remove temporary labels and stickers from fixtures and equipment. Do not remove permanent name plates, equipment model numbers and ratings. M. Thoroughly clean heating and air conditioning equipment, tanks, pumps and traps. Install or thoroughly clean filters or filter media, including: 1. The cleaning of permanent filters and the replacement of disposable f il ters if units were operated during construction. 2. The cleaning of ducts, blowers, and coi ls if the units were operated during construction. N. Remove from the site all facilities of items installed or used for temporary purposes during construction. O. Restore all adjoining areas to their original or specified condition. **************** END OF SECTION 01710 04/09/91 FINAL CLEANING 01710 - 2 SECTION 01720 PROJECT RECORD DOCUMENTS PART 1 - GENERAL 1..1 SUMMARY A. Section includes: 1. Maintain at the job site one copy of: a. Record Contract Drawings b. Record Project Manual c. Coordination drawings d. Addenda e. Reviewed shop drawings f. Change Orders g. Other modifications to the Contract h. Field test records 1. .2 GENERAL A. Store documents in cabinets in temporary field office, apart from documents used for construction. B. Maintain documents in clean, dry, legible condition. C. Do not use Project Record Documents for construction purposes. D. Make documents avai lable for inspection by the Construction Manager, the Architect and the Owner. E. Failure to maintain documents up-to-date will be cause for withholding payments. F. Obtain from the Construction Manager (at no charge) two sets of the Contract Documents for Project Record Documents including: 1- 2. Specifications with Two complete sets Drawings. One complete set of all addenda. of black line prints of all 3 . mylar prints of all Drawings. 1. .3 RECORDING A. Label each document "Project Record". B. Keep record documents current. 01/06/92 PROJECT RECORD DOCUMENTS (ADD. 2) 01720 - 1 C. Do not permanently conceal any work until required information has been recorded. D. Contract Drawings: 1. Required information may, as an option, be entered on a "working set" and then at completion of project transfer the information to final submitted IIproject Record" set. 2. Legibly mark to record actual construction: a. Depths of various elements of foundation in relation to survey data. b. Horizontal and vertical location of underground utilities and appurtenances referenced to permanent surface improvements. c. Location of internal utilities and appurtenances concealed in construction referenced to visible and accessible features of structure. d. Field changes of dimension and detail. e. Changes made by Change Order or Construction Change Directive. f. Details not on original Contract Drawings. E. Specifications and Addenda: 1. Legibly mark up each section to record: a. Manufacturer, trade name, catalog number and supplier of each product and item of equipment actually installed. b. Changes made by Change Order or Construction Change Directive. c. Other items not originally specified. F. Conversion of schematic layouts: 1. Arrangement of conduits , circuits, piping, ducts and similar items are in most cases shown schematically on the Drawings. 2. Legibly mark to record actual construction: a. Dimensions accurate to within 111 on the centerline of items shown schematically. b. Identify each item, for example, "cast iron drain" IIgalvanized water". c. Identify location of each item, for example, "under slab", "in ceiling plenum", lIexposedll. 3. The Construction Manager may waive requirements of schematic layout conversion, when in his opinion, it serves no beneficial purpose. Do not, however, rely on waivers being issued except specifically issued by the Construction Manger in writing. PROJECT RECORD DOCUMENTS (ADD. 2) 01720 - 2 01/06/92 1. .4 SUBMITTAL A. At completion of Project, deliver Project Record Documents as delineated in paragraph 1.2 F. above, to the Construction Manager prior to request for final payment. B. Accompany submi ttal with transmi ttal letter, in duplicate, containing: 1. Date 2. Project title and HLM Project number 3. The Contractor's name and address 4. Title and number of each record document 5. certif ication that each document as submitted is complete and accurate. 6. signature of the Contractor, or his authorized representative. PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used *************** END OF SECTION 01720 01/06/92 PROJECT RECORD DOCUMENTS (ADD. 2) 01720 - 3 SECTION 01730 OPERATION AND MAINTENANCE DATA PART 1 - GENERAL 1..1 SUMMARY A. section includes: 1. Format and content of manuals 2. Instruction of the Owner's personnel 3. Schedule of submittals B. Related sections: 1. SECTION 01301 - SUBMITTALS 2. SECTION 01700 - CONTRACT CLOSEOUT 3. Individual specifications sections: specific requirements for operation and maintenance data. 1..2 QUALITY ASSURANCE A. Prepare instructions and data by personnel exper ienced in maintenance and operation of described products. 1. . 3 FORMAT A. Prepare data in the form of an instructional manual. B. Binders: commercial quality, 8-1/2" x 11" three-ring binders with hardback, cleanable, plastic covers; 1-1/2" maximum ring size. When multiple binders are used, correlate data into related consistent groupings. C. Cover: identify each binder with typed or printed title OPERATION AND MAINTENANCE INSTRUCTIONS; list ti tle of the Project and separate building; identify subject matter of contents. D. Arrange content by systems under section numbers and sequence of Table of Contents of these Specifications. E. Provide tabbed fly leaf for each separate product and system, with typed description of product and major component parts of equipment. F. Text: manufacturer's printed data, or typewritten data on 20 pound paper. G. Drawings: provide with reinforced punched binder tab. Bind in with text; fold larger drawings to size of text OS/20/91 OPERATION AND MAINTENANCE DATA 01730 - 1 pages. 1..4 CONTENTS, EACH VOLUME A. Table of Contents: provide title of the project; names, addresses, and telephone numbers of the Construction Manager, the Architect, consultants, and the Contractor with name of responsible parties; schedule of products and systems, indexed to content of the volume. B. For each product or system: list names, addresses and telephone numbers of subcontractors ~nd suppliers, including local source of supplies and replacement parts. C. Product data: mark each sheet to clearly identify specific products and component parts, and data applicable to installation. Delete inapplicable information. D. Drawings: supplement product data to illustrate relations of component parts of equipment and systems, to indicate control and flow diagrams. Do not use the Project Record Documents as maintenance drawings. E. Type text: as required to supplement product data. Provide logical sequence of instructions for each procedure, incorporating manufacturer's instructions. F. Warranties and bonds: bind in copy of each. 1..5 Y~UAL FOR MATERIALS AND FINISHES A. Building products, applied materials, and finishes: include product data, with catalog number, size, composi tion, and color and texture designations. Provide information for re-ordering custom manufactured products. B. Instructions for care and maintenance; include manufacturer's recommendations for cleaning agents and methods, precautions against detrimental agents and methods, and recommended schedule for cleaning and maintenance. C. Moisture protection and weather exposed products: include product data listing applicable reference standards, chemical composition, and details of installation. Provide recommendations for inspections, maintenance, and repair. D. Additional requirements; as specified in individual product specification sections. OS/20/91 OPERATION AND }~INTENANCE DATA 01730 - 2 1..6 MANUAL FOR EQUIPMENT AND SYSTEMS A. Each item of equipment and each system: include descr iption of unit or system, and component parts. Identify function, normal operating characteristics, and limiting conditions. Include performance curves, with engineer ing data and tests, and complete nomenclature and commercial number of replaceable parts. B. Panelboard circuit directories: provide electrical service characteristics, controls and communications. .c. Include color coded wiring diagrams as installed. D. Operating procedures: include start-up, break-in, and routine normal operating instructions and sequences. Include regulation, control, stopping, shut-down, and emergency instructions. Include summer, winter, and special operating instructions. E. Maintenance requirements: include routine procedures and guide for trouble-shooting; disassembly, repair, and reassembly instructions; and alignment, adjusting, balancing, and checking instructions. F. Provide servicing and lubrication schedule, and list of lubricants required. G. Include manufacturer's printed operation and maintenance instructions. H. Include sequence of operation by controls manufacturer. I. Provide original manufacturer's parts list, illustrations, assembly drawings, and diagrams required for maintenance. J. Provide control diagrams by controls manufacturer as installed. K. Provide the Contractor's coordination draw ings, with color coded piping diagrams as installed. L. Provide charts of valve tag numbers, with location and function of each valve, keyed to flow and control diagrams. M. Provide list of original manufacturer's spare parts, current prices, and recommended quantities to be maintained in storage. OS/20/91 OPERATION AND MAINTENANCE DATA 01730 - 3 N. Include test and balancing reports. o. Additional requirements: as specified in individual product specification ~ections. P. Provide a listing in Table of Contents for design data, with tabbed fly sheet and space for insertion of data. 1..7 INSTRUCTION OF THE OWNER PERSONNEL A. Before final inspection, instruct the Owner's designated personnel in operation, adjustment, and maintenance of products, equipment, and systems, at agreed upon times. B. For equipment requiring seasonal operation, perform instructions for other seasons within six months. C. Use operation and maintenance manuals as basis for instruction. Review contents of manual with personnel in detail to explain all aspects of operation and maintenance. D. Prepare and insert additional Maintenance Manual when need apparent during instruction. data in f or such Operation and da ta becomes 1. .8 SUBMITTALS A. Submit two copies of preliminary draft or proposed formats and outlines of contents before start of the Work. The Construction Manager and Architect will review draft and return one copy with comments. B. For equipment, or component parts of equipment put into service during construction and operated by the Owner, submit documents within ten days after acceptance. C. Submi t one copy of completed volumes in final form 15 days prior to final inspection. Copy will be returned after final inspection, with Construction Manager and Architect comments. Revise content of documents prior to final submittal. D. Submi t two copies of revised volumes of data in final form within ten days after final inspection. OS/20/91 OPERATION AND MAINTENANCE DATA 01730 - 4 PART 2 - PRODUCTS Not Used PART 3 - EXECUTION Not Used ************** END OF SECTION 01730 OS/20/91 01730 - 5 OPERATION AND MAINTENANCE DATA