07/15/1992 Agreement
New Detention Facility
Contract KJ-027, Carpentry and General Works; Access Flooring,
Resilient Flooring and Carpet; Acoustical Ceilings
RJC & Associates, Inc.
I.
II.
c.
A.
B.
C.
D.
E.
F.
G.
H.
I.
Form of Agreement
Public Construction Bond
Certificate of Insurance
Table of Contents
Schedule of Drawings
Scope of Work - Bid Package #35
Scope of Work - Bid Package #37
Scope of Work - Bid Package #39
Milestone Schedule
A.
Proposal Form, pages 00135-1 through 00135-4 signed by bidder and dated June 8, 1992.
5% Bid Bond from Employers Insurance of Wausau in Wisconsin.
Lobbying and Conflict of Interest Clause.
Non-Collusion Affidavit.
Sworn Statement on Public Entity Crimes.
Proposal Form, pages 00137-1 through 00137-3 signed by bidder and dated April 23, 1992.
5% Bid Bond from Employers Insurance of Wausau in Wisconsin.
Lobbying and Conflict of Interest Clause.
Non-Collusion Affidavit.
Sworn Statement on Public Entity Crimes.
Proposal Form, pages 00139-1 through 00139-3 signed by bidder and dated April 28, 1992.
5% Bid Bond from Employers Insurance of Wausau in Wisconsin.
Lobbying and Conflict of Interest Clause.
Non-Collusion Affidavit.
Sworn Statement on Public Entity Crimes.
B.
III. Conditions of the Contract
A. General Conditions
B. Supplementary Conditions
C. Project Safety and Health Plan
D. Contractor's Quality Control Plan
E. Substantial Completion & Owner's Acceptance
F. General Requirements
Application for Payment
Change Order Procedures
Security Project Procedures
Project Meetings
Submittals
Progress Schedules
Schedule of Values
Daily Construction Report
Document Clarification Requests
Testing Laboratory Services
Temporary Utilities
--Continued On Next Pal!e--
New Detention Facility
Contract KJ-027, Carpentry and General Works; Access Flooring,
Resilient Flooring and Carpet; Acoustical Ceilings
RJC & Associates, Inc.
--Continuation--
Construction Aids
Access Roads and Parking Areas
Temporary Controls
Project Identification and Signs
Field Offices and Sheds
Construction Cleaning
Material and Equipment
Post-Bid Substitutions
Starting of Systems
Systems Demonstrations
Contract Closeout
Final Cleaning
Project Record Documents
Operation and Maintenance Data
THE AMERICAN INSTITUTE OF ARCHITECTS
F~Lfr ;'1[. >)[':nDf
'92 ,~UG 11 1410 :51
:--'1:
,
\..'L
1"19NROf 1.,):jN; r ; I.".
AlA Document A101/CM
CONSTRUCTION MANAGEMENT EDITION
Standard Form of Agreement Between
Owner and Contractor
where the basis of payment is a
STIPULATED SUM
1980 EDITION
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION WITH
AN ATTORNEY IS ENCOURAGED.
This document is intended to be used in conjunction with AlA Documents
A201/CM, 1980; B141/CM, 1980; and B801, 1980.
AGREEMENT No. KJ-027. Carpentry and General
Acoustical Ceilings.
made as of the AI I~+. 'r day of
Hundred and IV iW\c"~. WI
Works; Access Flooring. Resilient Flooring and Carpet;
...lit I ~
in the year of Nineteen
BETWEEN the Owner:
Monroe County Board of County Commissioners
500 Whitehead Street
Key West. FL 33040
and the Contractor:
RJC & Associates. Inc.
5611 Dewey Street
Hollywood. FL 33023
305/987-8301
the Project:
New Monroe County Detention Facility
5501 College Road. Stock Island
Key West. FL 33040
the Construction Manager:
Morrison-Knudsen/Gerrits
the Architect:
Hansen Lind Meyer/Gonzalez
The Owner and the Contractor agree as set forth below.
Copyright 1975, @ 1980 by The American Institute of Architects, 1735 New York Avenue, N.W., Washington, D.C. 20006. Re-
production of the material herein or substantial quotation of its provisions without written permission of the AlA violates the
copyright laws of the United States and will be subject to legal prosecution.
AlA DOCUMENT Al0l/CM . OWNER-CONTRACTOR AGREEMENT. CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 173S NEW YORK AVE., N.W., WASHINGTON, D.C. 20006
A101/CM-1980 1
WARNING: Unlicensed photocopying violates U.S. copyright laws and Is subject to legal prosecution.
ARTICLE 1
THE CONTRACT DOCUMENTS
The Contract Documents consist of this Agreement, the Conditions of the Contract (General, Supplementary and
other Conditions), the Drawings, the Specifications, all Addenda issued prior to and all Modifications issued after
execution of this Agreement. These form the Contract, and all are as fully a part of the Contract as if attached to this
Agreement or repeated herein. An enumeration of the Contract Documents appears in Article 7.
ARTICLE 2
THE WORK
The Contractor shall perform all the Work required by the Contract Documents for
(Here insert the caption descriptive of the Work as used on other Contract Documents.)
Bid Group 3, Bid Package No. 35, Carpentry and General Works
Bid Group 3, Bid Package No. 37, Access Flooring, Resilient Flooring and Carpet
Bid Group 3, Bid Package No. 39, Acoustical Ceilings
ARTICLE 3
TIME OF COMMENCEMENT AND SUBSTANTIAL COMPLETION
The Work to be performed under this Contract shall be commenced on the date as established in the Notice to
Proceed,
and, subject to authorized adjustments, Substantial Completion of the Work shall be achieved not later than the time
(Here insert any special provisions for liquidated damages relating to failure to complete on time.)
indicated in Section 00353 Milestone Schedule.
AlA DOCUMfNT A101/CM . OWNER-CONTRACTOR AGREEMENT' CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM -1980 2
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution.
ARTICLE 4
CONTRACT SUM
The Owner shall pay the Contractor in current funds for the performance of the Work, subject to additions and
deductions by Change Order as provided in the Contract Documents, the Contract Sum of
Five Hundred Fourteen Thousand Eight Hundred............................................
The Contract Sum is determined as follows:
(State here the base bid or other lump sum amount, accepted alternates and unit prices, as applicable.)
$514,800
Base
Base
Base
35, Carpentry and General Works...............................
37, Access Flooring, Resilient Flooring and Carpet............
39, Acoustical Ceilings.......................................
Subtotal
Bid Package No. 35, 37, and 39 combination credit.......................................
Total
Bid,
Bid,
Bid,
Bid Package No.
Bid Package No.
Bid Package No.
$329,800
$135,000
$ 75,000
$539,800
$<25,000>
$514,800
ARTICLE 5
PROGRESS PAYMENTS
Based upon Applications for Payment submitted to the Construction Manager by the Contractor and Project Certificates
for Payment issued by the Architect, the Owner shall make progress payments on account of the Contract Sum to the
Contractor as provided in the Contract Documents for the period ending the Twenty Fi fty (25) . ~~ of each
month as follows: approxlma y
Not later than Thirty (30) days following the end of the period covered by the Application for Payment,
Ninety percent ( 90 %) of the portion of the Contract Sum properly allocable to labor, materials and
equipment incorporated in the Work and Ni nety percent (90 %) of the portion of the Contract
Sum properly allocable to materials and equipment suitably stored at the site or at some other location agreed upon
in writing, for the period covered by the Application for Payment, less the aggregate of previous payments made by
the Owner; and upon Substantial Completion of the Work, a sum sufficient to increase the total payments to
One Hundred percent (100 %) of the Contract Sum, less such amounts as the Architect shall determine for
all incomplete Work and unsettled claims as provided in the Contract Documents.
(1/ not covered elsewhere in the Contract Documents, here insert any provision lor limiting or reducing the amount retained after the Work reaches a certain
stage 01 completion.)
Reference Section 00800 Substantial Completion and Owner Acceptance.
_ Pay~-d-tle -and- 'tlt1'p'll'i l'l-l1fll'le1" -tfie~6+MfOC-t-G@€tiTAeR~ SA~1.l ~- 4l-t.efe!p~ k,()fll-~ .Qatil..pa.~-~-dl.lil..o.t- ~ ..rete
_ efl~W6W; -G-F- ~ -tfie-a9geAC-e-4Aet'eG~ -a-t-~ +e~aA- FiK€-l3l'@o~~ ft ~-t fie-l3hK-e- -e+ -~ +'of6tec-{,
_~~w..,.~..~~le-Gll..i.."'_~~..,J.
(Usury laws and requirements under the Federal Truth in Lending Act, similar state and local consumer credit laws and other regulations at the Owner's
and Contractor's principal places of business, the location of the Project and elsewhere may affect the validity 01 this provision. Specific legal advice should
be obtained with respect to deletion, modification or other requirements such as wrHren disclosures or waivers.)
AlA DOCUMENT Al0l/CM . OWNER-CONTRACTOR AGREEMENT . CONSTRUCTION
MANAGEMENT EDITION' JUNE 1980 EDITION' AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM -1980 3
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution.
ARTICLE 6
FINAL PAYMENT
Final payment, constituting the entire unpaid balance of the Contract Sum, shall be paid by the Owner to the
Contractor when the Work has been completed, the Contract fully performed, and the Architect has issued a Project
Certificate for Payment which approves the final payment due the Contractor.
ARTICLE 7
MISCELLANEOUS PROVISIONS
7.1 Terms used in this Agreement which are defined in the Conditions of the Contract shall have the meanings
designated in those Conditions.
7.2 The Contract Documents, which constitute the entire agreement between the Owner and the Contractor, are listed
in Article 1 and, except for Modifications issued after execution of this Agreement, are enumerated as follows:
(List below the Agreement, the Conditions of the Contract [General, Supplementary and other Conditions], the Drawings, the Specifications, and any Addenda
and accepted alternates, showing page or sheet numbers in all cases and dates where applicable.)
I. Bidding Documents
A. Bid Group 3 Bid Documents for New Monroe County Detention Facility, which include Bidding Documents, Contract
Documents, Conditions, Drawings, General Requirements and Technical Specifications, and which are enumerated
in the attached Table of Contents, contained in Bid Group 3, pages 00001-1 thru 00001-9, dated 03/24/92, and
in the attached Schedule of Drawings contained in Bid Group 3, pages 00993-1 thru 00993-19, dated 05/02/92,
all as amended by the addenda listed below.
Addendum No. 10 dated April 16, 1992
Addendum No. 11A dated April 21, 1992
Addendum No. lIB dated April 24, 1992
Addendum No. 11C dated May 1, 1992
Addendum No. 11 dated May 5, 1992
Addendum No. 12A dated May 8, 1992
Addendum No. 12B dated May 13, 1992
Addendum No. 12C dated May 15, 1992
Addendum No. 12 dated May 21, 1992
Addendum No. 13 dated June 1, 1992
B. Addendum No. 1A dated November 26, 1991
Addendum No. 1B dated December 11, 1991
Addendum No. 1 dated December 20, 1991
Addendum No. 2A dated January 3, 1992
Addendum No.2 dated January 6, 1992
Addendum No. 3 dated January 9, 1992
Addendum No.4 dated January 13, 1992
Addendum No. 5 dated February 18, 1992
Addendum No. 6 dated March 4, 1992
Addendum No.7 dated March 10, 1992
Addendum No.8 dated March 25, 1992
Addendum No.9 dated April 3, 1992
II. Proposal Documents submitted by FJC & Associates, Inc., on June 9, 1992:
BP #35 A. Proposal Form, pages 00135-1 thru 00135-4, signed by bidder, and dated June 8, 1992.
B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin.
C. Sworn Statement on Public Entity Crimes.
D. Lobbying and Conflict of Interest Clause.
E. Non Collusion Affidavit.
BP #37 A. Proposal Form, pages 00137-1 thru 00137-3, signed by bidder, and dated April 23, 1992.
B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin.
C. Sworn Statement on Public Entity Crimes.
D. Lobbying and Conflict of Interest Clause.
E. Non Collusion Affidavit.
BP #39 A. Proposal Form, pages 00139-1 thru 00139-3, signed by bidder, and dated April 28, 1992.
B. 5% Bid Bond from Employers Insurance of Wausau, Wisconsin.
C. Sworn Statement on Public Entity Crimes.
D. Lobbying and Conflict of Interest Clause.
E. Non Collusion Affidavit.
Voluntary Alternate Bid Deductive Proposal Form pages 5 and 6.
AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT . CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., NW., WASHINGTON, D.C. 20006 A101/CM -1980 4
WARNING: Unlicensed photocopying violates U.S. copyright laws and is subject to legal prosecution.
7.3 Temporary facilities and services: .
(Here insert temporary facilities and services which are different from or in addition to those included elsewhere In the Contract Documents.)
Reference the documents issued for bidding.
7.4 Working Conditions:
(Here list any special conditions affecting the Contract.)
Reference the documents issued for bidding.
(Sea 1)
Attest: Danny L. Kolhage, Clerk of the Court
"Approved as to Fonn and Legal Sufficiency"
By: .L2L~#~/f
(Deputy Cl )
Date:
~-15'" '1':/
/
BY:~~
)
Date: I- -- 'Z-- - 9 z.....,
This Agreement entered into as of the day and year first written above.
m1
CAUTION: You should sign an original AlA document which has this caution printed in red.
An original assures that changes will not be obscured as may occur when documents are reproduced.
OWNER
Monroe
By:
Its:
AlA DOCUMENT A101/CM . OWNER-CONTRACTOR AGREEMENT' CONSTRUCTION
MANAGEMENT EDITION . JUNE 1980 EDITION . AIA@ . @1980 . THE AMERICAN
INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006 A101/CM -1980 5
WARNING: Unlicensed photocopying violates U.S. copyright laws and Is SUbject to legal prosecution.
PUBLIC CONSTRUCTION BOND
Bond No. 1450-77-086302
BY THIS BOND, We R.J.C. & Associates, Inc. , as Principal and Employers
Insurance of Wausau , a corporation, as Surety, are bound to Monroe County Board, of County
Corrunissionerlserein called Owner, in the sum of $ 514,800.00 for payment of
which we bind ourselves, our heirs, personal representatives,
successors, and assigns, jointly and severally.
THE CONDITION OF THIS BOND is that if Principal:
1. Performs the contract dated July 15 , 1921-, between
Principal and Owner for construction of Monroe County Detention Facility
the contract being made a part of this bond by reference, at the
times and in the manner prescribed in the contract; and
2. Promptly makes payments to all claimants, as defined in
section 255.05(1), Florida Statutes, supplying Principal with
labor, materials, or supplies, used directly or indirectly by
Principal in the prosecution of the work provided for in the
contract; and
3. Pays Owner all losses, damages, expenses, costs, and
attorney's fees, including appellate proceedings, that Owner
sustains because of a default by Principal under the contract;
and
4. Performs the guarantee of all work and materials furnished
under the contract for the time specified in the contract, then
this bond is void; otherwise it remains in full force.
Any changes in or under the contract documents and compliance
with any formalities connected with the contract or the changes
does not affect Surety's obligation under this bond.
DATE ON Ju1v 20. , 19..2.L.
BY
Employers Insurance of Wausau
(NAME OF SURETY)
11/20/91
PUBLIC CONSTRUCTION BOND
00610 - 1
:::L
Z
o
w
a:
Z
a:
<t:
w
0...
0...
<t:
f-
a
z
(f)
w
a
o
f-
Z
W
~
W
,,~
Z(f)
- (f)
7-=r:
t...~
~~
a:
a
~
LL
a
a:
w
S
a
0...
o
-...J
:g;
<t:
f-
a
z
(f)
~
I
f-
No. 214-147- 00298
EMPIOVERS INSURANCE OF WAUSAlJ A Mutual Company
POWER OF ATTORNEY
KNOW ALL MEN BY THESE PRESENTS:
That the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company, a corporation duly organized and existing under
the laws of the State of Wisconsin, and having its principal office in the City of Wausau, County of Marathon, State of
Wisconsin, has made, constituted and appointed, and does by these presents make, constitute and appoint
CHARLES J. NIELSON, JACK E. FOWLER, MARY C. ACEVES, JOHN S. HARRIS
its true and lawful attorney-in-fact, with full power and authority hereby conferred in its name, place and stead, to execute,
seal, acknowledge and deliver ANY OR ALL BONDS, UNDERTAKINGS, RECOGNIZANCES OR OTHER WRITTEN
OBLIGATIONS IN THE NATURE THEREOF INCLUDING CONSENTS OF SURETY AND WAIVERS TO THE
CONDITIONS OF CONTRACTS. NOT TO EXCEED THE PENAL SUM OF TEN MILLION DOLLARS
($10,000,000). ~
and to bind the corporation thereby as fully and to the same extent as if such bonds were signed by the President, sealed with
the corporate seal of the corporation and duly attested by its secretary hereby ratifying and confirming all that the said
attorney-in-fact may do in the premises.
This powpr of attorney is granted pursuant to the following resolution adopted by the Board ofl)irectors of said Company at a
meeting duly called and held on the 1 Rth day of May, 1 ~l7:l, which resolution is still in effect:
"RESOLVED, that the President and any Vice President - plective or appointive - of EMPLOYERS INSURANCE OF
WAUSAU A Mutual Company be, and that each of them hereby is, authorized to pxpcute powers of attorney qualifying
the attornpy nampd in the givpn power of attorney to pxpcutp on behalf of EMPLOYERS INSURANCE OF W AUSAU A
Mutual Company bonds, undertakings and all contracts of surptyship; and that any secrptary or assistant secretary be,
and that each or an.v of thpm hprpby is, authorized to attpst thp expcution of any such power of attorney, and to attach
thpreto the spal of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company."
"FURTH ER RESOLVED, that the signaturps of such officprs and thl' spal of EMPLOYERS INSURANCE OF W AUSAU
A Mutual Company may he affixpd to any such power of a ttorn,'y or to any certificatl' relating thereto by facsimile, and
any such powpr of attornpy or certificatl' bparing such facsimilp signaturps and facsimill' seal shall be valid and binding
upon thp EMPLOYERS INSURANCE OF W AUSAU A Mutual Company when so affixed and in the future with respect
to an.v hond, undprtaking or contract of surPlyship to which it is attachpd."
IN WITNESS WH EREOF, EMPLOYERS INSURANCE OF W AUSAU A Mutual Company has caused these prpsents to be
signed by the senior vice president and attested by its assistant secretary, and its corporate seal to be hereto affixed this Is t day
of ,TANTTARY ,19--.9...1.
EMPLOYERS INSURANCE OF WAUSAU A Mutual Company
~r:J.~~
Bill D. Wymore
l;:::;::;;;)
~.. SEAL//
~~~,;,/j
By
Executive Vice President
Attest: A I! 4L
R. J. Blsteman/"
Assistant Secretary
STATE OF WISCONSIN
)
) ss.
COUNTY OF MARATHON)
On this Is t
JANUARY 91
day of , 19 _ , before me personally came
Bill D. Wymore , to me known, who being by me duly sworn, did depose
and say that he is an executive vice president of the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company, the corporation described in
and which executed the above instrument: that he knows the seal of said corporation: that the seal affixed to said instrument is such corporate
seal and that it was so affixed by order of the Board of Directors of said corporation and that he signed his name thereto by like order.
I" W ITN FSS W H F R I()I-. I h;l\e hereunto set mv hand and affixed mv official seal the day and year herein first above written.
~.t1.,l~
Patricia A. Kleman
NOTARY PUBLIC
STATE OF WISCONSIN I STATE OF WISCONSIN
CITY OF WAUSAll ) ss. MY COMMISSION EXPIRES MAY 29,1994
COUNTY OF MARATHON I CERTIFICATE
I. thp undersigned. assistant spcretary of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company, a Wisconsin
corporation. do hprphy cprtify that thp forpgoing and attachpd power of attornl'y, WHICH MUST CONTAIN A
VALIDATING STATI<:MENT PRINTED IN THE MARGIN THEREOF IN RED INK, H'mains in full force and has
not hl'pn n'\'ok"d; and furthprrnon' that the rpsol ution oft hI' Board of I li rpdors spt forth in thp power of attornpy is still in force.
Signl'd and spalpd in thl' City ofWausau, Marathon County. Statp of Wisconsin, this 20th day
of ______ -luly_ _____, 1~L_22
Notary Public
ti:~;::;~:.~:-?~\
~ i -'- j =
\~:<;;~,::;~~~~i
(.-:-::;-;':;0-
I:~ LOItl'Olf04fl' .~
~~ -0- 1 \
\'},SEAL Ii
~~...~,.....;l1
Ad~
/ ./
Assistant Secretary
R. J. Besteman
NOTE IF YOll HA Vr: ANY qUESTIONS RE(~ARI>INC THE V ALIf)ITY OR WORIlING OF THIS POWER OF
ATTORN r: y, CALL TOLL FRE E (HOO) H:.!(;- Hili I. II N WISCONSIN. CALL (HOO) .172-0041 ).
At~ttlll.~
CERTIFICATE OF INSURANCE
ISSUE DATE (MM/DD/YY)
PRODUCER
Collinsworth, Alter, Nielson,
1wler & Dowling, Inc.
. ost Office Box 9315
Miami Lakes, FL 33014-9315
7/301~~
THIS CERTIFICATE IS ISSUED AS A MATTER OF INFORMATION ONLY AND
CONFERS NO RIGHTS UPON THE CERTIFICATE HOLDER. THIS CERTIFICATE
DOES NOT AMEND, EXTEND OR ALTER THE COVERAGE AFFORDED BY THE
POLICIES BELOW.
C~T~~~NY A
Maryland Casualty Co.
COMPANIES AFFORDING COVERAGE
O~~y
o'/T~lr .( (1'>-'
<{;' (.
Insurance Co
INSURED
C~T~~~NY B
NOT' t h ern
R. J. C. & Associates,
5611 Dewey Street
Hollywood FL
Inc.
C~T~~~NY C
Northern
Insurance Co
33023
C~T~~~NY D
Liberty Mutual
Ins Co
C~~~~NY E
COVERAGES
THIS IS TO CERTIFY THAT THE POLICIES OF INSURANCE LISTED BELOW HAVE BEEN ISSUED TO THE INSURED NAMED ABOVE FOR THE POLICY PERIOD
INDICATED. NOTWITHSTANDING ANY REQUIREMENT, TERM OR CONDITION OF ANY CONTRACT OR OTHER DOCUMENT WITH RESPECT TO WHICH THIS
CERTIFICATE MAY BE ISSUED OR MAY PERTAIN, THE INSURANCE AFFORDED BY THE POLICIES DESCRIBED HEREIN IS SUBJECT TO ALL THE TERMS.
EXCLUSIONS AND CONDITIONS OF SUCH POLICIES. LIMITS SHOWN MAY HAVE BEEN REDUCED BY PAID CLAIMS.
CO
LTR
TYPE OF INSURANCE
POLICY NUMBER
POLICY EFFECTIVE POLICY EXPIRATION
DATE (MMIDD/YY) DATE (MM/DD/YY)
LIMITS
A GENERAL LIABILITY EP A 1 522641 9
X COMMERCIAL GENERAL LIABILITY
CLAIMS MADE X OCCUR.
OWNER'S & CONTRACTOR'S PROTo
11/01/9111/01/92 GENERAL AGGREGATE $
PRODUCTS-COM PlOP AGG. $
PERSONAL & ADV. INJURY $
EACH OCCURRENCE $
FIRE DAMAGE (Anyone fire) $
MED. EXPENSE (Anyone person) $
1000000
1000000
1000000
1000000
50000
_ ___ 5000
1000000
B AUTOMOBILE LIABILITY
( ANY AUTO
ALL OWNED AUTOS
SCHEDULED AUTOS
X HIRED AUTOS
X NON-OWNED AUTOS
GARAGE LIABILITY
ECA15250468
: C EXCESS LIABILITY
X UMBRELLA FORM
OTHER THAN UMBRELLA FORM
UBA6978610
11/01/91 11/01/92 COMBINED SINGLE
LIMIT
BODIL Y INJURY
(Per person)
BODIL Y INJURY
(Per accident)
PROPERTY DAMAGE
.<<~~'.__'H__'_""_'_
11/01/91 11/01/92 EACH OCCURRENCE
AGGREGATE
$
$
$
$ 2000000
$ 2000000
D
WORKER'S COMPENSATION
WC1351429916
2/14/92 2/14/93 X STATUTORY LIMITS
EACH ACCIDENT $ 500000
DISEASE-POLICY LIMIT $ 500000
DISEASE-EACH EMPLOYEE $ .~..QQQQ!L
. ,,', ""'H,~' ,___.,_.,,,_.
AND
EMPLOYERS' LIABILITY
OTHER
Re: New Monroe County Detention Facility 5501 College Road
Stock Island, Key West, Fl 33040
DESCRIPTION OF OPERATIONS/LOCATlONSIVEHICLES/SPECIAL ITEMS
Monroe Co Board of County Commissioners and
!Morrison-Knudsen/Gerrits are added as Additional Insureds as
:respect to Liability and work_being---2...~x..foT'med ELthe ~nsLl.!:_~~
I CERTIFICATE HOLDER CANCELLATION
1nroe Co Board of County
_Jmmissioners or Monroe County
f. Morrison-Knudsen/Gerrits
POBox 5283
Key West, Fl 33040
SHOULD ANY OF THE ABOVE DESCRIBED POLICIES BE CANCELLED BEFORE THE
EXPIRATION DATE THEREOF, THE ISSUING COMPANY WILL ENDEAVOR TO
MAIL 60 DAYS WRITTEN NOTICE TO THE CERTIFICATE HOLDER NAMED TO THE
LEFT, BUT FAILURE TO MAIL SUCH NOTICE SHALL IMPOSE NO OBLIGATION OR
LIABILITY OF ANY KIND UPON THE COMPANY, ITS AGENTS OR REPRESENTATIVES.
,","O1"~'~ "R"'I!~':/ii~~~. rF~---
ACORD 25-5 (7/90)
@ACORD CORPORATION 1990
2- 5
TABLB OJ' CONTENTS
BID GROUP 3
1. Bidding Documents (Volume X)
03/24/92
section 00030
section 00050
section 00100
section 00113
section 00114
section 00115
section 00116
section 00117
section 00118
section 00119
section 00120
section 00121
section 00127
section 00128
section 00129
section 00130
section 00131
section 00132
section 00133
section 00134
section 00135
Section 00136
section 00137
section 00138
section 00139
section 00140
section 00141
section 00142
section 00148
section 00149
section 00143
section 00144
section 00145
section 00146
Notice of Calling for Bids
Project Summary
Instructions to Bidders
Proposal Forms:
Security Systems
Prime Electrical Contract Zones
A,B,C,D,E
Mechanical Process and HVAC
Prime Plumbing Contract Zones A,B,C,O,E
Fire Protection system
Food Service Equipment
Laundry Equipment
Loading Dock Equipment
Pneumatic Tube System
Metals-Doors-Glazing
Masonry
Concrete
Roofing
stairs & Miscellaneous Metals
Sprayed Insulation
Sealants
Gypsum Board, Lath & Plaster
Carpentry
Special Flooring
Access Flooring, Resilient Flooring &
Carpet
Ceramic Tile
Acoustical Ceilings
Painting & Wallcovering
Fence & Gates
Asphaltic Concrete Paving
Wastewater Treatment Plant & utilities
Landscaping
Schedule of unit Prices:
Security systems
Prime Electrical Contract Zones
A,B,C,O,E
Mechanical Process and HVAC
Prime Plumbing Contract Zones A,B,C,D,E
TABLE OF CONTENTS (ADD. 8)
00001 - 1
03/24/92
section 00147
section 00157
section 00163
section 00220
section 00230
section 00303
Section 00305
Section 00307
section 00309
section 00310
section 00311
Section 00312
section 00313
section 00314
section 00315
section 00316
section 00317
Section 00318
section 00319
section 00320
section 00321
section 00327
Section 00328
section 00329
section 00330
section 00331
section 00332
section 00333
Section 00334
section 00335
section 00336
section 00337
section 00338
section 00339
section 00340
Section 00341
section 00342
section 00343
Section 00344
section 00353
Fire Protection System
Metals-Doors-Glazing
Pre-Bid Substitutions
Geotechnical Data
site Survey
Scopes of Work for Reference (BG-1 and
BG-2) :
site Electrical & Temporary Power
site Grading & Caissons
Concrete Foundations
site Plumbing
Precast Concrete
Hydraulic Elevators
Precast Embeds
Scopes of Work:
Security Systems
Prime Electrical Contract Zones
A,B,C,D,E
Mechanical Process and HVAC
Prime Plumbing Contract Zones A,B,C,D,E
Fire Protection System
Food Service Equipment
Laundry Equipment
Loading Dock Equipment
Pneumatic Tube System
Metals-Doors-Glazing
Masonry
Concrete
Roofing
stairs & Miscellaneous Metals
sprayed Insulation
Sealants
Gypsum Board, Lath & Plaster
Carpentry
Special Flooring
Access Flooring, Resilient Flooring &
Carpet
Ceramic Tile
Acoustical Ceilings
Painting & Wallcovering
Fence & Gates
Asphaltic Concrete Paving
Wastewater Treatment Plant & utilities
Landscaping
Milestone Schedule
TABLE OF CONTENTS (ADO. 8)
00001 - 2
section 00410 Bid Bond - AlA Document A310, February
1970 edition
section 00420 Sworn statement on Public Entity Crimes
section 00425 Lobbying and Conflict of Interest Clause
section 00430 Non-Collusion Affidavit
section 00440 Proposed Subcontractor Listing
section 00450 Contractor's Qualification statement -
AlA Document A305
2. Contract Documents (Volume I)
section 00500 standard Form of Agreement Between Owner
and Contractor - AlA Document A101/CM,
June 1980 edition
section 00610 Public Construction Bond
3. Conditions (Volume I)
section 00750 General Conditions, AlA Document
A201/CM, June 1980 edition
section 00800 substantial Completion and Owner
Acceptance
section 00805 Supplementary General Conditions
section 00900 Application & Certificate for Payment -
AlA Document G702/G703
section 00905 Contractor's Affidavit of Payment of
Debts and Claims
section 00908 Contractor's Affidavit of Release of
Liens
section 00910 Consent of surety to Final Payment - AlA
Document G707, April 1970 edition
section 00915 Affidavit and Partial Release of Lien
section 00970 Project Safety and Health Plan
section 00980 Contractor Quality Control Plan
03/24/92
TABLE OF CONTENTS (ADD. 8)
00001 - 3
4. Drawings
section 00993 Schedule of Drawings, Bid Group 3
5. General Requirements (Volume I)
Section 01027
section 01028
section 01130
section 01200
section 01301
section 01310
Section 01370
section 01385
section 01395
section 01410
Section 01510
section 01520
Section 01550
section 01560
section 01580
Section 01590
section 01595
section 01600
Section 01630
section 01650
section 01670
section 01700
section 01710
section 01720
section 01730
Application for Payment
Change Order Procedures
Security Project Procedures
Project Meetings
Submittals
Progress Schedules
Schedule of Values
Daily Construction Reports
Document Clarification Requests
Testing Laboratory Services
Temporary utilities
Construction Aids
Access Roads and Parking Areas
Temporary Controls
Project Identification and Signs
Field Offices and Sheds
Construction Cleaning
Material and Equipment
Post-Bid Substitutions
starting of Systems
Systems Demonstrations
Contract Closeout
Final Cleaning
Project Record Documents
operation and Maintenance Data
03/24/92
00001 - 4
TABLE OF CONTENTS (ADO. 8)
5. Technical specifications, Bid Group Three, (Volume II, dated
November 11, 1991)
ADDENDA
Addendum No. 1, section 00901, pages 00901-1 thru
00901-7.
Addendum No. 2, section 00902, pages 00901-1 thru
00902-7.
Addendum No. 3, Section 0090,3, pages 00903-1 thru
00903-7.
Addendum No. 5, section 00905, page 00905-1, with
Revisions to Contract Documents No. 1, pages 1 and 2.
Addendum No. 6, section 00906, page 00906-1, with
Revisions to Contract Documents No. 2, page 1.
Addendum No. 7, section 00907, page 00907-1.
DIVISION 2 - SITEWORK
section 02211
section 02215
section 02222
section 02226
section 02510
section 02518
section 02520
section 02580
section 02644
section 02721
section 02730
section 02732
section 02733
section 02800
section 02810
Section 02830
section 02835
section 02930
section 02950
Rough Grading
Finish Grading
Excavating, Backfilling And compacting
For structures
Excavating, Backfilling and compacting
For utilities
Asphaltic Concrete paving
Concrete unit Pavers
Portland Cement Concrete Paving
Pavement Marking
Water Mains
Sewer Structures
sanitary sewerage
sewage Force Mains
Sewage Pump station
site Improvements
Irrigation system
Fence And Gates
Barbed Tape
Lawns
Trees, Shrubs And Ground Cover
DIVISION 3 - CONCRETB
section 03100
section 03200
section 03300
section 03520
Section 03600
Concrete Formwork
Concrete Reinforcement
cast-in-Place Concrete
Insulating Concrete Decks
Grout
03/24./92
00001 - 5
TABLE OF CONTENTS (ADD. 8)
DIVISION 4 - MASONRY
section 04200 unit Masonry
DIVISION 5 - METALS
section 05180
section 05500
section 05510
section 05810
Miscellaneous structural Steel
Metal Fabrications
Metal stairs
. Expansion Joint Covers Assemblies
DIVISION 6 - WOOD AND PLASTIC
section 06100
section 06200
Rough Carpentry
Finish Carpentry
DIVISION 7 - THERMAL AND MOISTURE PROTECTION
section 07115
section 07210
section 07215
section 07272
section 07530
Section 07730
section 07900
Sheet Waterproofing
Building Insulation
sprayed Insulation
Firestop And Penetration Sealing System
single Ply Roofing
Roof Accessories
Joint Sealers
DIVISION 8 - DOORS AND WINDOWS
section 08100
section 08211
section 08300
Section 08305
section 08320
section 08410
section 08660
section 08710
section 08800
section 08842
section 08902
Metal Doors And Frames
Flush Wood Doors
Special Doors
Access Panels And Doors
Security Metal Doors And Frames
Aluminum Entrances
security Windows
Door Hardware
Glazing
Security Glazing
Aluminum Window Walls
DIVISION 9 - FINISHES
section 09110
section 09200
section 09250
Section 09300
section 09510
section 09650
section 09680
section 09700
section 09800
Non-Load Bearing Wall Framing systems
Lath and Plaster
Gypsum Board
Tile
Acoustical ceilings
Resilient Flooring
Carpet
Special Flooring
special coatings
03/24/92
00001 - \.
TABLE OF CONTENTS (ADD. 8)
DIVISION 9 - FINISHES, cont'4
section 09830
Section 09900
section 09950
Elastomeric coating
painting
Wallcovering
DIVISION 10 - SPECIALTIES
section 10100
.Section 10160
Section 10200
section 10270
section 10350
section 10500
section 10520
section 10550
section 10606
section 10800
section 10900
Chalkboards And Tackboards
Solid Plastic Toilet Partitions
Louvers and Vents
Access Flooring
Flagpole
Steel Lockers
Fire Extinguisher Cabinets
postal Specialties
Security Fencing Assembly
Toilet Accessories
Miscellaneous specialties
DIVISION 11 - EQUIPMENT
Section 11110
section 11160
section 11197
section 11200
section 11202
section 11203
section 11204
Section 11205
Section 11206
Section 11208
Section 11211
Section 11212
Section 11217
section 11218
Section 11222
section 11224
section 11400
section 11480
section 11704
Laundry Equipment
Loading Dock Equipment
security/Detention Equipment
Basic Electronic Security Requirements
System Central Processing Unit
Fire Alarm Interface
Programmable Logic Controller
Address Panels
Relay Cabinets
Card Access Control
situation Man-Down Equipment
Closed Circuit Video Equipment
Vehicle Loop Detection
operational Intercom system
Inmate/Attorney Telephones
Metal Detection Equipment
Food Service Equipment
Athletic Equipment
Ice Machines
DIVISION 13 - RADIATION PROTECTION
section 13090 Radiation Protection
DIVISION 14 - CONVEYING SYSTEMS
section 14700
section 14240
Pneumatic Tube system
Hydraulic Elevators
03/24/92
00001 - 7
TABLE OF CONTENTS (ADD. 8)
DIVISION 15 - MECHANICAL
section 15000
section 15050
section 15060
section 15085
section 15100
section 15110
section 15130
section 15140
section 15160
Section 15175
section 15242
section 15252
section 15290
section 15330
section 15403
section 15404
section 15408
section 15410
section 15430
section 15440
section 15460
section 15470
section 15490
section 15517
section 15540
section 15684
section 15714
section 15770
section 15785
section 15855
section 15858
Section 15880
section 15884
section 15885
section 15890
section 15894
section 15936
section 15950
section 15965
section 15992
section 15995
General provisions
Water Treatment
pipe and pipe Fittings
piping Identification
Valves
Heat Trace System
Thermometers and Gages
pipe Hangers And Supports
Pumps
Variable Speed Motor Control for Fans
and Pumps
Vibration Isolation
Pipe And Equipment Insulation
Ductwork Insulation
Wet-Sprinkler system
Water Booster Pumps
Domestic Water Softener
Soil, Waste and Vent System
storm Drainage System
Plumbing specialties
Plumbing Fixtures and Accessories
Sump Pumps
Hot Water storage Heater
Fuel storage And Dispensing Systems
Hydronic Specialties
Emergency Generator Auxiliaries
Centrifugal Chillers
Blow Thru Cooling Tower
Make-Up Air Units
Fan Coil Units
Air Handling Units
Fans
Fire DamperS
Combination Smoke And Fire Dampers
Air Filters
Ductwork
Air Terminal Units
Grilles, Registers, Diffusers
Automatic Temperature Control Systems
Building Automation system
Tests - piping systems
system Balancing and Testing
03/24/92
00001 - 8
TABLE OF CONTENTS (ADD. 8)
DIVISION 16 - ELECTRICAL
section 16010
section 16111
section 16111
section 16120
section 16155
section 16161
section 16170
section 16199
Section 16300
section 16351
section 16400
section 16425
Section 16450
section 16461
section 16470
section 16471
section 16472
section 16500
Section 16601
section 16605
section 16660
section 16721
section 16781
section 16930
Electrical General provisions
Conduit Systems - Bid Group 3
Conduit Systems - Bid Group 2
Wire and Cable
Combination Motor Starters
Motor Control Centers
Disconnect Switches
Wiring Devices and Plates
Standby Power Generation
Uninterruptible Power Supply
Service and Power Distribution Systems
Main Service switchboard
Electrical Systems Grounding
Dry Type Distribution Transformers
Distribution Panelboards - Circuit
Breaker Type
Feeder and Branch Circuits and Emergency
Wiring
Branch Circuit Panelboards - Circuit
Breaker Type
Lighting
Lightning Protection System
Transient Voltage/Surge Protection
Wiring for Equipment Furnished by Others
Fire Alarm System
Telephone Conduit Systems
Lighting Control Equipment
03/24/92
00001 - 9
TABLE OF CONTENTS (ADD. 8)
SECTION 00993
SCHEDULE OF DRAWINGS
NUMBER
0.00
0.01
0.02A
0.03
0.04
0.05
1. OOA
1.00B
1. OOC
1.01A
1. 02A
1. 03A
1.04A
1.05A
1. 06
1.06A
1. 07 A
1. 08A
1.09A
DRAWING TITLE
DRAWING
LATEST
REVISION DATE
Rev 11/11/91
1 Rev 11/11/91
2 Rev 01/09/92
2 Rev 01/09/92
2 Rev 01/09/92
1 Rev 11/11/91
1 Rev 11/11/91
1 Rev 11/11/91
Cover
Index of Drawings
Symbols and Abbreviations (Architectural)
Life Safety Plan Ground Floor
Life Safety Plan First Floor
Life Safety Plan 2nd Floor
Existing Conditions North
Existing Conditions Central
Existing Conditions South
Not Used
Not Used
Final site Layout Central
2 Rev .9?I9?/92
4 ..~eV .P~19~1~2
Final site Layout and Grading South
Be 3 10/15/91
1 RevpAjc)3 /92
1 Rev 11/11/91
4 Rev 02/18/92
Final Grading North
Rough Grading and Drainage
Final Grading and Drainage Central
1 Rev 02/07/92
2 Re.v04/03j92
Not Used
Final site Utilities Central
2 Rev 92/07/92
3 Rev04/03j92
Not Used
1.10 Entrance Enlarge~ent
1 Rev 02/07/92
BG3 10/15/91
1.11 Landscape Plan North
1.12 Landscape Plan Central
1 Rev 02/07/92
05/02/92 BG-3 SCHEDULE OF DRAHINGS (ADD. 11)
"
00993 - 1
1.13 Landscape Plan South
1.14 Irrigation Plan North
1.15 Irrigation Plan Central
1.16 Irrigation Plan South
1.17 Pump station Grinder Details
1.18 Not Used
1.19 Not Used
1. 20 site Details Fencing and Paving
1. 21 Landscape Irrigation Details
1. 22 civil Details
3.01 Not Used
3.02 Foundation Plan, Ground Floor Zone B
3.03 Not Used
3.04 Not Used
3.05 Not Used
3.06 Not Used
3.07 Framing Plan First Floor Zone A
3.08 Framing Plan First Floor Zone B
3.09 Framing Plan First Floor Zone C
3.10 Framing Plan First Floor Zone 0
3.11 Framing Plan First Floor Zone E
3.12 Framing Plan First Floor Zone F Alternate
3.13 Framing Plan Second Floor Zone A
3.14 Framing plan Second Floor Zone B
3.15 Framing Plan Second Floor Zone C
BG3 10/15/91
BG3 10/15/91
1 Rev 02/07/92
BG3 10/15/91
1 Rev 11/11/91
2 ncv 02/07~
3 Rev 91i?8/9 2
BG3 10/15/91
BG3 10/15/91
1 Rev 02/18/92
3 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
6 Rev 02/07/92
6 Rev 02/07/92
BG3 11/11/91
5 Rev 02/07/92
4 Rev 02/07/92
4 Rev 02/07/92
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 2
3.16 Framing Plan Mezzanine Level Zone D 5 Rev 02/07/92
3.17 Framing Plan Mezzanine Level Zone E 5 Rev 02/07/92
3.18 Framing Plan Mezzanine Floor Zone F BG3 11/11/91
Alternate
3.19 Framing Plan Mechanical Plenum Zone D BG3 11/11/91
3.20 Framing Plan Mechanical Plenum Zone E BG3 11/11/91
3.21 Framing Plan Mechanical Plenum Zone F BG3 11/11/91
Alternate
3.22 Framing Plan Roof Level Zone A 4 Rev 02/07/92
3.23 Framing Plan Roof Level Zone B 3 Rev 02/07/92
3.24 Framing Plan Roof Level Zone C 3 Rev 02/07/92
3.25 Framing Plan Roof Level Zone D 5 Rev 02/07/92
3.26 Framing Plan Roof Level Zone E 5 Rev 02/07/92
3.27 Framing Plan Roof Level Zone F Alternate BG3 11/11/91
3.28 Not Used
3.29 Not Used
3.30 Not Used
3.31 Foundations, sections and Details 4 Rev 02/18/92
3.32 Typical Details 4 Rev 02/07/92
3.33 Sections & Details 4 Rev 02/07/92
3.34 sections & Details 3 Rev 02/07/92
3.35 Precast Wall Schedule & Details 4 Rev 02/07/92
3.36 Precast Column Schedule & Details 4 Rev 02/07/92
3.37 General Notes & Abbreviations & Typical 4 Rev 02/07/92
Details
3.38 sections & Details 3 Rev 02/07/92
3.39 sections & Details 5 Rev 02/07/92
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 3
4.01 Exterior Building Plan Ground Floor Zone A 1 Rev 02/07/92
4.01A Building Plan Ground Floor Zone A 1 Rev 02/07'Q2
4.02 Exterior Building Plan Ground Floor Zone B BG3 11/11/91
4.02A Building Plan Ground Floor Zone B BG3 10/15/91
4.03 Exterior Building Plan Ground Floor Zone C BG3 11/11/91
4.03A Building Plan Ground Floor Zone C BG3 10/15/91
4.04 Exterior Building Plan Ground Floor Zone D BG3 11/11/91
4.04A Building Plan Ground Floor Zone D Housing BG3 10/15/91
4.05 Exterior Building Plan Ground Floor Zone E BG3 11/11/91
Housing
4.05A Building Plan Ground Floor Zone E Housing BG3 10/15/91
4.06 Exterior Building Plan Ground Floor Zone F BG3 11/11/91
Housing Alternate
4.06A Building Plan Ground Floor Zone F Housing BG3 10/15/91
Alternate
4.07 Exterior Building Plan First Floor Zone A 1 Rev 02/07'Q2
4.08 Exterior Building Plan First Floor Zone B BG3 11/11/91
4.09 Exterior Building Plan First Floor Zone C 4 Rev 02/07/92
4.10 Exterior Building Plan First Floor Zone D BG3 11/11/91
Housing
4.11 Exterior Building Plan First Floor Zone E BG3 11/11/91
Housing
4.12 Exterior Building Plan First Floor Zone F BG3 11/11/91
Housing Alternate
4.13 Exterior Building Plan Second Floor Zone A 4 Rev 02/07/92
4.14 Exterior Building Plan Second Floor Zone B BG3 11/11/91
4.15 Exterior Building Plan Second Floor Zone C 3 Rev 02/07/92
4.16 Exterior Building Plan Mezzanine Level 4 Rev 04/03/92
Zone D Housing
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 4
4.17 Exterior Building Plan Mezzanine Level BG3 11/11/91
Zone E Housing
4.18 Exterior Building Plan Mezzanine Level BG3 11/11/91
Zone F Housing Alternate
4.19 Mechanical Plenum Plan Zone 0 BG3 11/11/91
4.20 Mechanical Plenun Plan Zone E BG3 11/11/91
4.21 Mechanical Plenur:\ Plan Zone F Alternate BG3 11/11/91
4.22 Building Plan Roof Level Zone A 4 Rev 02/07/92
4.23 Building Plan Roof Level Zone B 3 Rev 02/07/92
4.24 Building Plan Roof Level Zone C 4 Rev 02/07/92
4.25 Building Plan Roof Level Zone 0 4 Rev 02/07/92
4.26 Building Plan Roof Level Zone E 4 Rev 02/07/92
4.27 Building Plan Roof Level Zone F Alternate BG3 11/11/91
4.28 Exterior Elevations 2 Rev 02/07/92
4.29 Exterior Elevations 1 Rev 02/07/92
4.30 Exterior Elevations 3 Rev 02/07/92
4.31 Exterior Elevations 3 Rev 02/07/92
4.32 Exterior Elevations BG3 11/11/91
4.33 Exterior Elevations BG3 11/11/91
4.33A Exterior Elevations 2 Rev 02/07/92
4.34 Wall sections 4 Rev 02/07/92
4.35 Wall sections 3 Rev 02/07/92
4.36 \\' a 11 sections 2 Rev 02/07/92
4.37 Wall Sections 5 Rev 02/07/92
4.38 Exterior Details 4 Rev 02/07/92
4.39 Exterior Details 4 Rev 02/07/92
4.40 Exterior Details 5 Rev 02/07/92
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 5
~. 41
4.41A
4.41B
4.42
Exterior Details
Exterior Details
Exterior Details
Metal Door & window Frame Elevations &
Details, Door Schedule
4.43 Not Used
4.44 Not Used
4.45 Not Used
4.46
4.47
4.47A
4.48
4.49
4.50
4.51
stair plans & sections
stair plans & sections
stair plans & sections
stair Details
Elevator plans & sections
Elevator Details
Enlarged Cell - Plans & Elevations
4.52 Not used
4.53
4.54
4.55
4.56
4.57
4.58
4.59
4.60
4.61
Interior Building Plan First Floor Zone A
Interior Building Plan First Floor Zone B
Interior Building Plan First Floor Zone C
Interior Bui lding Plan First Floor Zone D
Housing
Interior Building Plan First Floor Zone E
Housing
Interior Building Plan First Floor Zone F
Housing Alternate
Interior Building plan Second Floor Zone A
Interior Building Plan Second Floor Zone B
Interior Building plan Second Floor Zone C
BG3 11/11/91
BG3 11/11/9"
3 Rev 02/07/92
3 Rev 12/20/91
BG3 11/11/91
3 Rev 02/07/92
BG3 11/11/91
BG3 11/11/91
2 Rev 02/07/92
2 Rev 02/07/92
BG3 11/11/0'
3 Rev 02/07/92
2 Rev 01/09/92
1 Rev 11/11/91
2 Rev 01/09/92
2 Rev 01/09/92
1 Rev 01/09/92
2 Rev 02/07/92
1 Rev 11/11/91
1 Rev 11/11/91
00993 - 6
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
4.62
4.63
4.64
4.65
4.66
4.67
4.67A
4.68
4.69
4.70
4.71
4.72
4.73
4.74
4.75
4.76
4.77
4.78
4.79
4.79A
4.80
6.01
6.02
Interior Building Plan Mezzanine Level 0
Housing
Interior Building Plan Mezzanine Level
Zone E Housing
Interior Building Plan Mezzanine Level
Zone F Housing Alternate
Building sections
Building sections
Not Used
Partition Types
Interior Details
Interior Details
Interior Details
Interior Details
Interior Details
Door Schedule
Door Schedule
Door Schedule
H.M. Elevations
Door and Window Details and Buck Types
Finish Schedule
Finish Schedule
Finish Schedule
Miscellaneous Details
Reflected Ceiling Plan Ground Floor Zone A
Not Used
1 Rev 02/07/92
2 Rev 02/07/92
BG3 10/15/91
BG3 10/15/91
2 Rev 01/02/92
2 Rev 02/07/92
2 Rev 02/07/92
1 Rev 02/07/92
2 Rev 02/07/92
1 Rev 02/07/92
2 Rev 02/07/92
3 Rev 01/09/92
4 Rev 01/09/92
2 Rev 01/09/92
1 Rev 01/09/92
BG3 10/15/91
4 ~e~'-{}4/ 03 / 92
5 Rev'04/28/92
4 Rev 0/,/03/92
5 Rev 04/28/92
-2--R€' . 12/20/91
y
5 Rev 04/28/92
BG3 10/15/91
1 Rev 02/07/92
05/02/92
00993 - 7
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
6.03
6.04
6.05
6.06
6.07
6.08
6.09
6.10
6.11
6.12
6.13
6.14
6.15
6.16
6.17
6.18
6.19
6.20
7.00
7.01
7.02
7.03
Reflected Ceiling Plan Ground Floor Zone C BG3 10/15/91
Not Used
Not Used
Not Used
Reflected Ceiling Plan First Floor Zone A 1 Rev 02/07/92
Reflected Ceiling Plan First Floor Zone B BG3 10/15/91
Reflected Ceiling Plan First Floor Zone C BG3 10/15/91
Reflected Ceiling Plan First Floor D Housing BG3 10/15/91
Reflected Ceiling Plan First Floor Zone E
Housing
Reflected Ceiling plan First Floor Zone F
Housing Alternate
Reflected Ceiling Plan Second Floor Zone A
Reflected Ceiling Plan Second Floor Zone B
Reflected Ceiling Plan Second Floor Zone C
Reflected Ceiling Plan Mezzanine Level
Zone 0 Housing
Reflected Ceiling Plan Mezzanine Level
Zone E Housing
Reflected Ceiling Plan Mezzanine Level
Zone F Housing Alternate
Ceiling Details
Ceiling Details
standard Mounting Heights
Not used
Not used
Equipment Plan Ground Floor Zone C
7.04 Not Used
BG3 10/15/91
BG3 10/15/91
1 Rev 02/07/92
1 Rev 12/20/91
BG3 10/15/91
1 Rev 02/07,
1 Rev 02/07/92
BG3 10/15/91
2 Rev 02/07/92
2 Rev 04/03/92
1 Rev 11/11/91
BG3 10/15/91
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 8
7.05
Not Used
7.06
Not Used
7.07 Equipment Plan First Floor Zone A
7.08 Equipment Plan First Floor Zone B
7.09 Equipment Plan First Floor Zone C
7.10 Equipment Plan First Floor Zone 0 Housing
7.11 Equipment Plan First Floor Zone E Housing
7.12 Equipment Plan First Floor Zone F Housing
Alternate
7.13 Equipment Plan Second Floor Zone A
7.14 Equipment Plan Second Floor Zone B
7.15 Equipment Plan Second Floor Zone C
7.16 Equipment Plan Mezzanine Level Zone 0
Housing
7.17 Equipment Plan Mezzanine Level Zone E
Housing
7.18 Equipment Plan Mezzanine Level Zone F
Housing Alternate
7.19 Enlarged Toilet/Shower Equipment Plan
7.20 Enlarged Plans
7.21 Millwork Elevations
7.22 Millwork Elevations
7.23 Millwork Elevations
7.24 Millwork Elevations
7.25 Millwork Details
7.26 Millwork Details
FS-1 Food Service Equipment Schedule
FS-2 Food Service Equipment Plan
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
1 Rev 11/11/91
BG3 10/15/91
BG3 10/15/91
1 Rev 11/11/91
1 Rev 11/11/91
1 Rev 11/11/91
1 Rev 04/03/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 02/07/92
1 Rev 02/07/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 01/02/92
BG3 10/15/91
BG3 10/15/91
00993 - 9
FS-3
Food Service Mechanical plan
FS-4
Food Service Electrical Plan
FS-5
Food Service Plunbing Plan
FS-6
Food Service Equipment Details
FS-7
Food Service Equipment Details
L-l
Laundry Equipment Plan and Schedule
L-2
Laundry Mechanical Plan
L-3
Laundry Electrical Plan
L-4
Laundry Plumbing plan
Vol.II
0.00
Cover
0.01 Index of Drawings
8.00 Plumbing Legend
8.00A Plumbing Schedules
8.01 Plumbing Ground Floor Zone A
8.02 Plumbing Ground Floor Zone B
8.03 Plumbing Ground Floor Zone C
8.04 Plumbing Ground Floor Zone 0 Housing
8.05 Plumbing Ground Floor Zone E Housing
8.06 Plumbing Ground Floor Zone F Housing
Alternate
8.07 Plumbing First Floor Zone A
8.08 Plumbing First Floor Zone B
8.09 Plumbing First Floor Zone C
8.10 Plumbing First Floor Zone D Housing
8.11 Plumbing First Floor Zone E Housing
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
Rev 11/11/91
BG3 10/15/91
1 Rev 12/20/91
3 Rev 02/07, 2.
BG3 10/15/91
3 Rev 01/02/92
2 Rev 01/09/92
BG3 10/15/91
1 Rev 11/11/91
2 Rev 02/07/92
BG3 10/15/91
1 Rev 01/02/92
2 Rev 01/09/92
1 Rev 12/20/91
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 10
8.12 Plumbing First Floor Zone F Housing
Alternate
8.13 Plumbing Second Floor Zone A
8.14 Plumbing Second Floor Zone B
8.15 Plumbing Second Floor Zone C
8.16 Plumbing Mezzanine Level Zone D Housing
8.17 Plumbing Mezzanine Level Zone E Housing
8.18 Plumbing Mezzanine Level Zone F Housing
Alternate
8.19 Plumbing Plenum Plan Zone D Housing
8.20 Plumbing Plenum Plan Zone E Housing
8.21 Plumbing Plenum Plan Zone F Housing
Alternate
8.22 Plumbing Schedules and Details
8.23 Plumbing Riser Diagram
8.24 Plumbing Riser Diagram
8.25 Plumbing Riser Diagram
8.26 Plumbing Riser Diagram
8.27 Plumbing Riser Diagram
8.28 Plumbing Riser Diagram
8.29 Plumbing Riser Diagram
8.30 Plumbing Riser Diagram
8.31 Plumbing Riser Diagram
8.32 Plumbing Riser Diagram
8.33 Plumbing Riser Diagram
8.34 Plumbing Riser Diagram
8.35 Plumbing Kitchen Plan
1 Rev 11/11/91
1 Rev 01/09/92
BG3 10/15/91
2 Rev 12/20/91
1 Rev 12/20/91
BG3 10/15/91
BG3 10/15/91
1 Rev 01/09/92
BG3 10/15/91
BG3 10/15/91
1 Rev 01/02/92
2 Rev 02/07/92
1 Rev 01/09/92
1 Rev 01/09/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
1 Rev 11/11/91
BG3 10/15/91
BG3 10/15/91
1 Rev 01/02/92
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 11
8.36
9.01
9.02
9.03
9.04
9.05
9.06
9.07
9.08
9.09
9.10
9.11
9.12
9.13
9.14
9.15
9.16
9.17
9.18
9.19
9.20
9.21
9.22
10.01
Waste Handling system Details
Not Used
Not Used
Not Used
Not Used
Not used
Not Used
piping plan First Floor Zone A
piping plan First Floor Zone B
piping plan First Floor Zone C
piping plan First Floor Zone D Housing
piping Plan First Floor Zone E Housing
piping Plan First Floor Zone F Housing
Alternate
piping plan Second Floor Zone A
piping plan Second Floor Zone B
piping plan Second Floor Zone C
piping plan Mezzanine Level Zone D Housing
piping Plan Mezzanine Level Zone E Housing
piping Plan Mezzanine Level Zone F Housing
Alternate
Not used
Not used
Fuel oil Details
piping Diagrams
Not used
10.02 HVAC plan Ground Floor Zone B
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
1 Rev 01/02/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/9~
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
00993 - 1;
10.03 HVAC Plan Ground Floor Zone C BG3 10/15/91
10.04 HVAC Plan Ground Floor Zone D Housing BG3 10/15/91
10.05 HVAC Plan Ground Floor Zone E Housing BG3 10/15/91
10.06 HVAC Plan Ground Floor Zone F Housing BG3 10/15/91
Alternate
10.07 HVAC Plan First Floor Zone A 1 Rev 02/07/92
10.08 HVAC Plan First Floor Zone B BG3 10/15/91
10.09 HVAC Plan First Floor Zone C BG3 10/15/91
10.10 HVAC Plan First Floor Zone D Housing 1 Rev 01/09/92
10.11 HVAC Plan First Floor Zone E Housing 1 Rev 01/09/92
10.12 HVAC Plan First Floor Zone F Housing 1 Rev 01/09/92
Alternate
10.13 HVAC Plan Second Floor Zone A 1 Rev 02/07/92
10.14 HVAC Plan Second Floor Zone B 1 Rev 12/20/91
10.15 HVAC Plan Second Floor Zone C 1 Rev 01/09/92
10.16 HVAC Plan Mezzanine Level Zone D Housing BG3 10/15/91
10.17 HVAC Plan Mezzanine Level Zone E Housing BG3 10/15/91
10.18 HVAC Plan Mezzanine Level Zone F Housing BG3 10/15/91
Alternate
10.19 HVAC Plenum Plan Zone D Housing BG3 10/15/91
10.20 HVAC Plenum Plan Zone E Housing BG3 10/15/91
10.21 HVAC Plenum Plan Zone F Housing Alternate BG3 10/15/91
10.22 Not Used
10.23 Not Used
10.24 HVAC Plan Roof Level Zone C 1 Rev 01/09/92
10.25 Not Used
10.26 Not Used
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 13
10.27
Not Used
10.28
Enlarged Mechanical Room Plan
10.29 HVAC Details
10.30 HVAC Details
10.31 HVAC Details
10.32 HVAC Schedules
10.33 HVAC Schedules
10.34 HVAC Schedules
10.35 Central Plant Control Diagrams
10.36 HVAC Temperature Control
10.37 HVAC Smoke control
11.00 Electrical Symbols and Notes
11.00A Electrical site Lighting Plan
11.01 power and Lighting Plan Ground Floor
Zone A
11.02 power and Lighting Plan Ground Floor
Zone B
11.03 power and Lighting Plan Ground Floor
Zone C
11.04 Power and Lighting Plan Ground Floor
Zone D Housing
11.05 power and Lighting Plan Ground Floor
Zone E Housing
11.06 Power and Lighting Plan Ground Floor
Zone F Housing Alternate
11.07 power Plan First Floor Zone A
11.08 Lighting Plan First Floor Zone A
11.09 Power Plan First Floor Zone B
11.10 Lighting Plan First Floor Zone B
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
.
1 Rev 11/11/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
1 Rev 02/07/92
BG3 10/15/91
1 Rev 01/02/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 03/04/92
BG3 10/15/91
2 Rev 03/04/92
BG3 10/15/91
00993 - 14
11.11
11.12
11.13
11.14
11. 15
11. 16
11. 17
11.18
11.19
11.20
11.21
11.22
11.23
11.24
11. 25
11. 26
11.27
11.28
11.29
11.30
power Plan First Floor Zone C
Lighting Plan First Floor Zone C
Power Plan First Floor Zone D Housing
Lighting Plan First Floor Zone D Housing
power Plan First Floor Zone E Housing
Lighting Plan First Floor Zone E Housing
Power Plan First Floor Zone F Housing
Alternate
Lighting plan First Floor Zone F Housing
Alternate
Power Plan Second Floor Zone A
Lighting Plan Second Floor Zone A
power Plan Second Floor Zone B
Lighting Plan Second Floor Zone B
Power Plan Second Floor Zone C
Lighting Plan Second Floor Zone C
Power Plan Mezzanine Level Zone D Housing
2 Rev 03/04/92
BG3 10/15/91
3 Rev 03/04/92
BG3 10/15/91
3 Rev 03/04/92
BG3 10/15/91
2 Rev 01/02/92
BG 3 10 / 15/91
1 Rev 03/04/92
BG 3 10/ 15/91
2 Rev 03/04/92
1 Rev 12/20/91
1 Rev 03/04/92
BG3 10/15/91
2 Rev 03/04/92
Power Plan Mezzanine Level Zone E Housing
Lighting Plan Mezzanine Level Zone D Housing BG3 10/15/91
2 Rev 03/04/92
Lighting Plan Mezzanine Level Zone E Housing BG3 10/15/91
Power Plan Mezzanine Level Zone F Housing
Alternate
1 Rev 12/20/91
Lighting Plan Mezzanine Level Zone F Housing BG3 10/15/91
Alternate
11.31 Power and Lighting Plan Plenum Plan Zone D BG3 10/15/91
Housing
11.32 Power and Lighting Plan Plenum Plan Zone E BG3 10/15/91
Housing
11.33 Power and Lighting Plan Plenum Plan Zone F BG3 10/15/91
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 15
11.34
11.35
11.36
11.37
11. 38
11.39
11.40
11. 41
11.42
11.43
11.44
11. 45
11. 46
11.47
11.48
11. 49
11.50
11.51
11.52
Housing Alternate
Power plan Roof Level Zone A
Power Plan Roof Level Zone B
Power Plan Roof Level Zone C
Power Plan Roof Level Zone D
Power Plan Roof Level Zone E
Power Plan Roof Level Zone F Alternate
Electrical Enlarged Kitchen Plan
Electrical Enlarged Laundry Plan
Lightning Protection Plan
Lightning Protection Plan Details
Electrical Riser Diagram Part 1
Electrical Riser Diagram Part 2
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Electrical Schedules and Details
Not Used
12.01 Communications Plan Ground Floor Zone A
12.02 communications Plan Ground Floor Zone B
12.03 communications Plan Ground Floor Zone C
12.04 communications Plan Ground Floor Zone D
Housing
12.05 communications Plan Ground Floor Zone E
Housing
05/02/92 BG-3 SCHEDGLE OF DRAWINGS (ADD. 11)
BG 3 1 0/ 15 r
BG3 10/15/91
1 Rev 01/09/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
2 Rev 01/02/92
1 Rev 11/11/91
BG3 10/15/91
5 Rev 03/0.,92
1 Rev 11/11/91
2 Rev 01/09/92
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
BG3 10/15/91
1 Rev 03/04/92
BG3 10/15/91
BG3 10/15/91
00993 - 1\
12.06
12.07
12.08
12.09
12.10
12.11
12.12
12.13
12.14
12.15
12.16
12.17
12.18
12.19
12.20
12.21
12.22
12.23
12.24
12.25
12.26
12.27
Communications Plan Ground Floor Zone F
Housing Alternate
Communications Plan First Floor Zone A
communications Plan First Floor Zone B
communications Plan First Floor Zone C
Communications Plan First Floor Zone D
Housing
Communications Plan First Floor Zone E
Housing
Communications Plan First Floor Zone F
Housing Alternate
Communications Plan Second Floor Zone A
Communications Plan Second Floor Zone B
Communications Plan Second Floor Zone C
communications Plan Mezzanine Level Zone D
Housing
Communications Plan Mezzanine Level Zone E
Housing
Communications Plan Mezzanine Level Zone F
Housing Alternate
Fire Alarm Riser Diagram
Telephone Riser Diagram and Elevator
Fire Alarm System
Not Used
Not Used
Not Used
Security Plan Ground Floor Zone A
Security Plan Ground Floor Zone B
security Plan Ground Floor Zone C
Security plan Ground Floor Zone D Housing
BG3 10/15/91
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
BG3 10/15/91
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
1 Rev 03/04/92
BG3 10/15/91
BG3 10/15/91
1 Rev 12/20/91
1 Rev 12/20/91
1 Rev 12/20/91
1 Rev 12/20/91
1 Rev 12/20/91
05/02/92
00993 - 17
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
12.28 Security Plan Ground Floor Zone E Housing 1 Rev 12/20/91
12.29 Security Plan Ground Floor Zone F Housing 1 Rev 12/20'~1
Alternate
12.30 Security Plan First Floor Zone A 3 Rev 03/04/92
12.31 Security Plan First Floor Zone B 3 Rev 03/04/92
12.32 Security Plan First Floor Zone C 2 Rev 03/04/92
12.33 security Plan First Floor Zone D Housing 3 Rev 03/04/92
12.34 security plan First Floor Zone E Housing 3 Rev 03/04/92
12.35 Security Plan First Floor Zone F Housing BG3 10/15/91
Alternate
12.36 Security Plan Second Floor Zone A 5 Rev 03/04/92
12.37 Security plan Second Floor Zone B 1 Rev 12/20/91
12.38 security Plan Second Floor Zone C 3 Rev 03/04/92
12.39 Security Plan Mezzanine Level Zone D 3 Rev 03/04/92
Housing
12.40 Security Plan Mezzanine Level Zone E 3 Rev 03/0~ 'Q2
Housing
12.41 Security Plan Mezzanin Level Zone F 1 Rev 12/20/91
Housing Alternate
12.42 Security systems Riser Diagram 2 Rev 02/07/92
12.43 Details 1 Rev 02/07/92
12.44 Details 1 Rev 12/20/91
13.01 Fire Protection Ground Floor Zone A BG3 10/15/91
13.02 Fire Protection Ground Floor Zone B BG3 10/15/91
13.03 Fire Protection Ground Floor Zone C BG3 10/15/91
13.04 Fire Protection Ground Floor Zone D Housing BG3 10/15/91
13.05 Fire Protection Ground Floor Zone E Housing BG3 10/15/91
13.06 Fire Protection Ground Floor Zone F Housing BG3 10/15/91
Alternate
05/02/92 BG-3 SCHEDULE OF DRAWINGS (ADD. 11) 00993 - 18
13.07 Fire Protection First Floor Zone A BG3 10/15/91
13.08 Fire Protection First Floor Zone B BG3 10/15/91
13.09 Fire Protection First Floor Zone C BG3 10/15/91
13.10 Fire Protection First Floor Zone D Housing BG3 10/15/91
13.11 Fire Protection First Floor Zone E Housing BG3 10/15/91
13.12 Fire Protection First Floor Zone F Housing BG3 10/15/91
Alternate
13.13 Fire Protection Second Floor Zone A BG3 10/15/91
13.14 Fire Protection Second Floor Zone B BG3 10/15/91
13.15 Fire Protection Second Floor Zone C BG3 10/15/91
13.16 Fire Protection Mezz. Level Zone D Housing BG3 10/15/91
13.17 Fire Protection Mezz. Level Zone E Housing BG3 10/15/91
13.18 Fire Protection Mezz. Level Zone F Housing BG3 10/15/91
Alternate
13.19 Not Used
13.20 Not Used
13.21 Not Used
13.22 Not Used
13.23 Not Used
13.24 Not Used
13.25 Not Used
13.26 Not Used
13.27 Not Used
13.28 Fire Protection Details BG3 10/15/91
13.29 Fire Protection Details BG3 10/15/91
05/02/92
BG-3 SCHEDULE OF DRAWINGS (ADD. 11)
00993 - 19
SECTION OO;)~S
SCOPE OF woaK
Bid Package No. 35
Carpentry , General Works
1.1 General Scope
Provide all labor, supervision, engineering, materials,
supplies, equipment, tools, transportation, surveying and
layout, and protection, to install complete operating
systems, and proper execution and completion of all Work
specified on the drawings, in the bid package, and the
sections of the specifications, which include, but are not
limited to the listing that follows. The bidder shall review
all drawings, and specification sections that are not
specifically listed, for any additional requirements in order
to complete the scope of work described herein.
specifications sections and Descriptions
\
05810
06100
06200
08300
10100
10160
10350
10500
10520
10550
10800
10900
11480
13090
Expansion Joint Cover Assemblies
Rough Carpentry
Finish Carpentry
Special Doors
Chalkboards and Tackboards
Solid Plastic Toilet Partitions
Flagpole
Steel Lockers
Fire Extinguisher Cabinets
postal Specialties
Toilet Accessories
Miscellaneous Specialties
Athletic Equipment
Radiatioft rrotectioft
1.2 special provisions
The following special provisions are intended to clarify the
scope of work, or highlight features of the work, or modify,
change, add to, or delete from the General Scope of this Bid
Package.
.1 All licenses required in order to perform the scope of
work in the specified location, shall be procured and
maintained by the contractor and his subcontractors.
Contractor shall submit copies to the Construction
Manager. Contractor shall be responsible for applying
for, and procuring the construction permit as required by
04/30/92
CARPENTRY SCOPE OF WORK (ADD. 11)
00335 - 1
the City of Kay West; however, the Owner shall literally
pay the fee for the permit.
.2 Contractor shall maintain As-Built drawings~ (Record
Drawings per section 01720), of his work progression. A
50% progress of field work submittal, will be required.
.3 Provide, replace, and maintain any safety rails and
barricades as necessary during the process of work, or
during deliveries of materials or equipment.
.4 Contractor is to review Division 1 General Requirements
for additional responsibilities required in order to
perform the work under this Bid Package.
Contractor shall pay particular attention to section
01710 Final Cleaning, which shall be performed as
scheduled by the CM, which will be at or near the
completion of the project.
utility Routing and Coordination of the Work
(
(
.5
This contractor shall be responsible to coordinate his
work with other multiple prime contractors both in the
scheduling of field work activities and in the
integration of individually furnished items into final
composite installations. Coordination drawings
procedures shall consist of, but are not limited to, Base
Trade Installers Drawings.
.6
All unfinished surfaces of materials or equipment
furnished or installed by this contractor, shall be
inspected for readiness by follow-on contractors and the
eM, prior to installation of follow-on work. This would
include bringing back to original condition, surfaces
disturbed by welding, burning, or other disfigurement,
which will need to be made ready for finish painting, or
other work. The Masonry Contractor shall pay particular
attention to protect and clean flooring surfaces in
compliance with floor covering installation.
Materials and Equipment Furnished bv Others All
materials furnished by the Owner, other contractors for
the Owner, or by the CM for the Owner, for installation
by this contractor shall upon delivery, be unloaded,
transferred, stored and fully protected by the contractor
until installed. Any demurrage or similar charge
incurred due to failure of the contractor to promptly
unload the materials and equipment shall be the
responstbility of the contractor.
.7
04/30/92
00335 - 2
CARPENTRY SCOPE OF WORK (ADD. 11)
The contractor shall carefully examine all materials and
equipment furnished by the Owner, or any of his
designees, (other contractors or the CM). The contractor
shall complete receiving reports describing the quantity
and condition of the materials or equipment. The
contractor shall be responsible for subsequent damage or
loss until installation is completed and accepted by the
Owner.
Should the contractor fail to report any visible signs of
damage in the receiving report as indicated above, then
all parties may assume that the damage occurred while the
materials and equipment were in the care, custody and
control of the receiving contractor.
Any material furnished by the Owner, at an off-site
location, on other than a charge basis in connection with
the contract, shall be deemed as held by the contractor
on consignment. All such materials not used in the
fabrication of materials or equipment required under the
contract shall be returned to the applicable party, as
directed, at their expense; and, if not accounted for or
so returned, shall be paid for by the contractor.
.8 All incoming materials and equipment shall be coordinated
with other trades and the CM is to be notified, in order
that proper lavdown. staging and stockina areas are
developed, prior to release for shipping. within the
building, areas shall be restricted and stocking areas
will be authorized in writing.
.9 If in the event of conflicting, or overlapping
requirements in any area of the bidding documents,
technical specifications, or drawings, the most stringent
condition shall be bid and constructed. Notify the CM in
any event, in order to not compromise the Owner's right
to make appropriate decisions.
.10 This contractor is reminded of inmate contact areas and
perimeters, and of the requirement for security devices,
fasteners, connectors, and any other work associated with
this bid package scope of work, in order that proper care
and construction is performed in accordance with the
standards and guidelines set forth by the regulatory
agencies governing jails.
.11 Furnish and install all plywood backing panels for
telephones and telephone boards, in accordance with
section 06100 Rouqh Carpentry.
Furnish and install wood blocking, furring, grounds,
04/30/92
CARPENTRY SCOPE OF WORK (ADD. 11)
00335 - 3
curbs, nailers and ~tber rough wood items, for the work
of this bid package, and all other trades. Roof
carpentry is by others, as is cast- in-place concrete
formwork.
Furnish and install all concealed wood blocking at
drywall partitions to fully support cabinetwork prior to
the installation of drywall.
Provide shop drawings detailing wood blocking required
for installation of cabinetwork.
.12 Furnish and install Flagpole, in accordance with section
10350, including foundation.
.13 Furnish and install Fire Extinguisher Cabinets and Fire
Extinguisher Wall Brackets, in accordance with section
10520. Fire Hose Cabinets are by others.
.14 Furnioh and inotall Lcad Lined Film CasDcttc Cabincto and
Desi9natin~ Plaque, in accordance '",rith section 130'0
Radiation Protcction.
(
All other radiation protection matcrialo arc furniahed
and inotalled by others. Testing is by others.
.15 Furnish and install all expansion joints, that are for
precast concrete or masonry. For example, but not
limited to, see detail 4/4.41a. Follow section 05810.
.16 Contractor shall provide an allowance, and as a part of
his base bid, the equivalent of (240) manhours, which
shall include mobilization, labor, equipment, materials,
taxes, incidentals, overhead and profit, for the purpose
of performing work similar to that in this bid package.
.17
Furnish and install
with section 06200.
Contractor who will
control rooms.
all Finish Carpentry in accordance
Coordinate with security Systems
provide information for layout of
.18 Owner option No. 35-01: Zone 'F' CarpentrY
At the option of the Owner, furnish and install Zone 'F'
Carpentry, similar to Zones 'D' and 'E'.
This area is defined as the area bound by column lines G
to La, and 17 line to 24 line, as well as column lines 37
to X, and U line to 42 line.
(
04/30/92
CARPENTRY SCOPE OF WORK (ADD. 11)
00335 - 4
.19 Final Cleaning
This contractor shall be responsible for final cleaning
program, which will be conducted beginning at completion
of prefinal inspection, and continuing through final
punchlist execution.
All surfaces shall be cleaned with appropriate cleansers
as directed by the Owner's representative. Vacuum all
dust accumulations and clean all accessible areas.
Review. other trade contractors scopes of work for
specific exclusions. This Contractor shall be
responsible for all other general cleaning, in order to
make ready for final inspection, and satisfaction of
final inspection.
~~()':~~~~P~!1:9:::'S?!\P?~~?:':':'~:~!!"fi:~~.:!ti:::.:.:~.!:~~+"t:~~~~!'#.g
Ifiz._.iiAll1IiilII16Iilll
1.3 By Others
(
.1
Fire Hose Cabinets in section 10520, are by Fire
Protection Contractor.
.2 Lc~d lincd wall systcms, X r~y view yindows/lcnd lined
fr~lftes, utility shiclding, ~nd pcnetr~tion shiclding, ~rc
by othcr tradc contr~ctors, ~3 rcl~teG to Scction 13090
R~di~tion rrotection. Testing is by others.
.3 Roofing, and roof rough carpentry.
.4 Cast-in-place concrete formwork.
04/30/92
CARPENTRY SCOPE OF WORK (ADD. 11)
00335 - 5
SBCTION 00337
SCOPB OF WORK
Bid Paokage No. 37
Aooess Flooring, Resilient Flooring , carpet
1.1 General Scope
Provide all labor, supervision, engineering, materials,
supplies, equipment, tools, transportation, surveying and
layout, and protection, to install complete operating systems,
and proper execution and completion of all Work specified on
the drawings, in the bid package, and the sections of the
specifications, which include, but are not limited to the
listing that follows. The bidder shall review all drawings,
and specification sections that are not specifically listed,
for any additional requirements in order to complete the scope
of work described herein.
sections and Descriptions of the Work
09650
09680
10270
Resilient Flooring
carpet
Access Flooring
\
1.2 Special provisions
The following Special provisions are intended to clarify the
scope of work, or highlight features of the work, or modify,
change, add to, or delete from the General Scope of this Bid
Package.
.1 All licenses required in order to perform the scope of
work in the specified location, shall be procured and
maintained by the contractor and his subcontractors.
Contractor shall submit copies to the Construction
Manager. Contractor shall be responsible for applying
for, and procuring the construction permit as required by
the city of Key West; however, the Owner shall literally
pay the fee for the permit.
.2 Contractor shall maintain As-Built drawings. (Record
Drawings per section 01720), of his work progression. A
50% progress of field work submittal, will be required.
.3 Provide, replace, and maintain any safety rails and
barricades as necessary during the process of work, or
during deliveries of materials or equipment.
\
03/25/92
FLOORING SCOPE OF WORK (ADD. 8)
00337 - 1
.4 Contractor is to review Division 1 General Requirements
for additional responsibilities required in order to
perform the work under this Bid Package.
Contractor shall pay particular attention to section
01710 Final Cleaning, which shall be performed as
scheduled by the CM, which will be at or near the
completion of the project.
.5 Materials and Equipment Furnished by Others All
materials furnished by the Owner, other contractors for
the Owner, or by the CM for the Owner, for installation
by this contractor shall upon delivery, be unloaded,
transferred, stored and fully protected by the contractor
until installed. Any demurrage or similar charge
incurred due to failure of the contractor to promptly
unload the materials and equipment shall be the
responsibility of the contractor.
The contractor shall carefully examine all materials and
equipment furnished by the Owner, or any of his
designees, (other contractors or the CM). The contractor
shall complete receiving reports describing the quantity
and condition of the materials or equipment. The
contractor shall be responsible for subsequent damage or
loss until installation is completed and accepted by the
Owner.
I
Should the contractor fail to report any visible signs of
damage in the receiving report as indicated above, then
all parties may assume that the damage occurred while the
materials and equipment were in the care, custody and
control of the receiving contractor.
Any material furnished by the Owner, at an off-site
location, on other than a charge basis in connection with
the contract, shall be deemed as held by the contractor
on consignment. All such materials not used in the
fabrication of materials or equipment required under the
contract shall be returned to the applicable party, as
directed, at their expense; and, if not accounted for or
so returned, shall be paid for by the contractor.
.6 Coordination of the Work
This contractor shall be responsible to coordinate his
work with other multiple prime contractors both in the
scheduling of field work activities and in the
integration of individually furnished items into final
composite installations.
03/25/92
FLOORING SCOPE OF WORK (ADD. 8)
00337 - 2
.7 Contractor shall perform and/or coordinate all required
testing and provide adequate personnel in order to
facilitate all testing to the requirements of the
contract documents.
(
.8 All incoming materials and equipment shall be coordinated
with other trades and the eM is to be notified, in order
that proper laydown. stag ing and stocking areas are
developed, prior to release for shipping. Within the
building, areas shall be restricted and stocking areas
will be authorized in writing.
.9 If in the event of conflicting, or overlapping
requirements in any area of the bidding documents,
technical specifications, or drawings, the most stringent
condition shall be bid and constructed. Notify the CM in
any event, in order to not compromise the Owner's right
to make appropriate decisions.
.10 This contractor is reminded of inmate contact areas and
perimeters, and of the requirement for security devices,
fasteners, connectors, and any other work associated with
this bid package scope of work, in order that proper care
and construction is performed in accordance with the
standards and guidelines set forth by the regulatory
agencies governing jails.
.11 Furnish and install Resilient Floorinq, in accordance
with Section 09650, including vinyl composition tile,
vinyl base, rubber tile, and adhesives and miscellaneous
materials required for installation. This shall also
include base around access flooring.
Xllil:r_l1;tt.I~I:l!;l:::!1i@.~I:E!ll~+~.:'::~p:~:~:'''l:)P:l?1:i
Upon installation of resilient flooring, place two (2)
coats of wax, and then provide temporary protection.
When directed by the CM, remove temporary floor
protection, and strip, wax, and buff out.
.12
Furnish and install Direct
accordance with Section 09680,
protection.
Glue-Down Carpet, in
including clean-up and
.13 Furnish and install access flooring in accordance with
Section 10270, including grounding connectors, cable cut-
out protection, panel lifting devices, and aluminum
grilles with dampers. Provide for all transitions to
dissimilar flooring system. Provide for temporary floor
protection, after installation.
(
04/03/92
FLOORING SCOPE OF WORK (ADD. 9 )
00337 - 3
This contractor ,:;hall furnish a set of reproducible
drawings, which will be routed to the Electrical
Contractor, Mechanical Contractor, and security Systems
Contractor, in order for utility routing, cut-outs, and
pedestal location verification, to be scheduled and
coordinated.
Note: Grounding connectors shall be taken to (1) point,
for termination.
Extra stock shall be provided by contractor, consisting
of (5) each panels.
.14 Perform all floor preparations, to include all sanding,
levelling, and defect repair, and be responsible for the
cleanliness of existing concrete, which is to receive
flooring.
sixty (60) calendar days prior to installation, inspect
existing floors which are to receive flooring finish, and
follow up with a (14) day, prior to mobilization
inspection.
.15 Provide final cleaning of all types of flooring in this
bid package, upon substantial completion, as directed by
the CM.
.16 Contractor shall provide the CM the results of moisture (
testinq, and other tests as suggested by manufacturer.
.17 Provide for ventilation for safety and drying as
necessary.
.18 Owner Option No. 37-01: Zone IF' Resilient Flooring and
Carpet:
At the option of the Owner, furnish and install Zone 'F'
Resilient Flooring and Carpet, similar to Zones '0' and
, E I .
This area is defined as the area bound by column lines G
to La, and 17 line to 24 line, as well as column lines 37
to X, and U line to 42 line.
03/25/92
FLOORING SCOPE OF WORK (ADD. 8)
00337 - 4
SECTION 00339
SCOPE OF WORK
Bid Package No. 39
Acoustical ceilings
1.1 General Scope
Provide all labor, supervision, engineering, materials,
supplies, equipment, tools, transportation, surveying and
layout, and protection, to install complete operating
systems, and proper execution and completion of all Work
specified on the drawings, in the bid package, and the
sections of the Specifications, which include, but are not
limited to the listing that follows. The bidder shall review
all drawings, and specification sections that are not
specifically listed, for any additional requirements in order
to complete the scope of work described herein.
specifications sections and Descriptions
05810
09510
13090
Expansion Joint Cover Assemblies
Acoustical Ceilings
Radiation Protection
l
1.2 Special provisions
The following Special provisions are intended to clarify the
scope of work, or highlight features of the work, or modify,
change, add to, or delete from the General Scope of this Bid
Package.
.1 All licenses required in order to perform the scope of
work in the specified location, shall be procured and
maintained by the contractor and his subcontractors.
Contractor shall submit copies to the Construction
Manager. Contractor shall be responsible for applying
for, and procuring the construction permit as required by
the City of Key West; however, the Owner shall literally
pay the fee for the permit.
.
.2 Contractor shall maintain As-Built drawinqs, (Record
Drawings per section 01720), of his work progression. A
50% progress of field work submittal, will be required.
.3 Provide, replace, and maintain any safety rails and
barricades as necessary during the process of work, or
,
03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8)
00339 - 1
during deliveries of materials or equipment.
.4 Contractor is to review Division 1 General Requirements
for additional responsibilities required in order to
perform the work under this Bid Package.
Contractor shall pay particular attention to section
01710 Final Cleaning, which shall be performed as
scheduled by the CM, which will be at or near the
completion of the project.
.5 Access Panels and Doors - Install all access panels and
doors that are required to be installed in acoustical
ceilinqs. Coordinate with other trade contractors for
locations. Access panels and doors will be furnished by
others.
The Access Panels and Doors Schedule, attached and
labelled Attachment 'B', represents those access panels
and doors that are not shown on the plans, but which are
required by other trade contractors. The schedule shows
several types, and that they are to be installed in
various substrates. This schedule is to be used as a
guide, in order for this contractor to bid and understand
the requirements of this scope of work item. The
quantities are not absolute, and contractor shall be
required to make installations of all quantities that are I
to be installed in acoustical ceilings.
.6 Materials and Eauipment Furnished bv others All
materials furnished by the Owner, other contractors for
the Owner, or by the CM for the Owner, for installation
by this contractor shall upon delivery, be unloaded,
transferred, stored and fully protected by the contractor
until installed. Any demurrage or similar charge
incurred due to failure of the contractor to promptly
unload the materials and equipment shall be the
responsibility of the contractor.
The contractor shall carefully examine all materials and
equipment furnished by the Owner, or any of his
designees, (other contractors or the CM). The contractor
shall complete receiving reports describing the quantity
and condition of the materials or equipment. The
contractor shall be responsible for subsequent damage or
loss until installation is completed and accepted by the
Owner.
Should the contractor fail to report any visible signs of
damage in the receiving report as indicated above, then
all parties may assume that the damage occurred while the
03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8)
00339 - 2
materials and equipment were in the care, custody and
control of the receiving contractor.
Any material furnished by the Owner, at an off-site
location, on other than a charge basis in connection with
the contract, shall be deemed as held by the contractor
on consignment. All such materials not used in the
fabrication of materials or equipment required under the
contract shall be returned to the applicable party, as
directed, at their expense; and, if not accounted for or
so returned, shall be paid for by the contractor.
.7 Coordination of the Work
This contractor shall be responsible to coordinate his
work with other multiple prime contractors both in the
scheduling of field work activities and in the
integration of individually furnished items into final
composite installations.
.8 All incoming materials and equipment shall be coordinated
with other trades and the CM is to be notified, in order
that proper lavdown. staqing and stockinq areas are
developed, prior to release for shipping. within the
building, areas shall be restricted and stocking areas
will be authorized in writing.
\,
.9
If in the event of conflicting, or overlapping
requirements in any area of the bidding documents,
technical specifications, or drawings, the most strinqent
condition shall be bid and constructed. Notify the eM in
any event, in order to not compromise the Owner's right
to make appropriate decisions.
.10 This contractor is reminded of inmate contact areas and
perimeters, and of the requirement for security devices,
fasteners, connectors, and any other work associated with
this bid package scope of work, in order that proper care
and construction is performed in accordance with the
standards and guidelines set forth by the regulatory
agencies governing jails.
.11 Furnish and install expansion ioint cover assemblies in
accordance with section 05810, which are to be installed
in the work of this contractor.
.12 Furnish and install Acoustical Ceilings, which includes
mineral fiber ceiling with revealed edge with suspension
system and related items. This shall also include
acoustical ceiling tile adhered to substrate.
\
03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8)
00339 - 3
.13 Provide for additional suspension wires as necessary to
limit ceiling deflection to 1/360 of span. Provide
background drawings as necessary to facilitate
coordination of suspension wires. Coordinate with
mechanical and electrical contractors, and their
fixtures/devices which are to be supported by the ceiling
system.
.14 Provide other trades the finished ceiling elevation, and
assist with other trades in the installation of their
fixtures and devices.
.15 Pre-measure all rooms and adjust patterns as necessary,
and as approved by Owner's representative.
.16 Coordinate with other trades, and with the rough-in
installation of their work.
.17 Coordinate and provide fixture hanqers for lay-in
suspended fixtures and devices.
.18 Provide all hold-down clips as required by applicable
building codes.
.19 Owner Option No. 39-01: Zone 'F' Acoustical Ceilings:
At the option of the Owner, furnish and install Zone 'F'
Acoustical Ceilings, similar to Zones 'DI and IE'.
This area is defined as the area bound by column lines G
to La, and 17 line to 24 line, as well as column lines 37
to X, and U line to 42 line.
1.3 By Others
.1 Sprayed Insulation, paragraph 2.1 D., Sprayed Acoustical
Treatment, is by others.
03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8)
00339 - 4
ATTACHMENT 'B'
ACCESS PANELS AND DOORS
Gypsum w/Standard Lock
Size Quantity
1- 12" x 12" 25
2. 18" x 18" 0
3. 18" x 24" 1
4. 24" x 24" 0
5. 24" x 36" 2
Gypsum wI Standard Lock. Fire-Rated Panels
Size Quantity
6. 12" x 12" 45
7. 18" x 18" 51
(
8. 18" x 24" 0
9. 24" x 24" 0
10. 24" x 36" 0
Plaster wI Standard Lock
Size Quantity
11. 12" x 12" 4
12. 18" x 18" 0
13. 18" x 24" 0
14. 24" x 24" 0
15. 24" x 36" 0
,
03/11/92 ACOUSTICAL CEILING SCOPE OF WORK (ADD. 8)
00339 - 5
Plaster w/Standard Lock, Fire-Rated Panels
size Quantity
16. 12" x 12" 4
17. 18" x 18" 16
18. 18" x 24" 0
19. 24" x 24" 0
20. 24" x 36" 0
Security Plaster w/security Lock
Size Quantity
21- 12" x 12" 245
22. 18" x 18" 4
23. 18" x 24" 0
24. 24" x 24" 24
25. 24" x 36" 0
security Plaster w/Security Lock, Fire-Rated Panels
size Quantity
26. 12" x 12" 66
27. 18" x 18" 0
28. 18" x 24" 0
29. 24" x 24" 0
30. 24" x 36" 0
security Masonry w/Security Lock
size Quantity
31. 24" x 24"
32. 24" x 36"
o
o
03/11/92 ACOUSTICAL CEILING SCQPE OF WORK (ADD. 8)
00339 - 6
SBCTION 00353
MILESTONE scaEDULE
The bar chart and associated activity listing presented in
this section depicts the approximate du~ation, sequence, and
flow of work of major work groups. Not all activities are
shown and groupings are subjective. Logic diagrams
generating the presented document are available for bidder
review in the office of the Construction Manager.
Contractors will be required to submit construction
schedules to meet the requirements of the presented
milestones and in accordance with the Master Project
Schedule.
The Contractors are to note the following special milestone
dates required for the Project.
a. Building Temperature and Humidity
Controlled for Finishes , Follow-on
Work. . . . . . . . . . . . . . . . . .11/15/92
b. Start Contractor Completion Inspections.01/11/93
c.
Start Prefinal Inspections . .
Project Completion . . . .
. .03/02/93
. .07/01/93
d.
03/16/92
MILESTONE SCHEDULE (ADD. 8)
00353 - 1
(
IT 1iI : I .
ioi I ~.
I E
~ , I i
J
g~ j I
i
~ ~
I
.
I i~
f- -
-
ii: 0 i~
-
...
~ ~ ; I ! i~
)1 j j
~
1 >-
<IJ
~ ....
......
.... UJ
Ii] IOU=l
"0 10
= l .... u. 0
c... UJ
I J 0e::I:
...... O<...J
U. .- (/)
J <IJ
~=. I j . e: 0
>- QI .....
<IJ <IJ IX)
e: QI
II ::;,Of")
0
~ <...J~~
I) Qle:
J II o::;,a:
c...o~
~ e:<...J
I j 0 0
::It QI .....
o IX)
c...
! e:
0
::It
I!
J5
~ ~~
II
~ H
f0- il l
~
~ I I
..II i
~ il
t- 1 I , ila ~
! . .111 i
~ i I
I i I . j~~i j
~ I I Ii . J .
I I ! e I
iii i 1 l k
...
(
.........................~.........................................................................................................
~ CcM\ty, Florldl ,.IMAVERA PROJECT PLAIINEI
(
IT DATE 19DEC91 IMI NO. 50 Monroe CcM\ty Detention feelllty
16:28
sce IEPOltT . line skip br ectlvlty code
Monroe CcM\ty Detention Fectl Ity
STAlT DATI 1MJG91 FlI DATI l.IUL93-
DATA DATE 18N0V91 PAGE NO. 1
..-.. ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ .....
ACTIVln ORIG IEJI ACTIVITY DESClIPTlClI SCHEDUlED
II DUI DUI I STAlT FlIISH
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ .....
Site Utllt~l..
5 1 0 100 _ 0:' ITP . lite Utll Itf.. 9OCT91A 9OCT91A
1325 5 5 0 , IW . Zone C . ,,-Sl_ s.nltary . Loedl,. Dock 4MAI92 10MA192
1330 5 5 0 IW . Zone C . ItOl"ll Drain (.II 28-0 & Upat...-) 4MAI92 10MA192
1340 5 5 0 IW . Zone C , ItOl"ll Dr.ln Unlet 1.12 & Upatr.. 4MAI92 10M192
2000 30 5 a sw . Utllltl.. . ~.round SUbaltt.l. 13SEP91A 22IIOV91
2005 10 10 0 sw . Utllltl.. . AlE ~l of U'G SUbalttels 25N0V91 9DEC91
2010 15 15 0 IW . Utllftl.. . Install Outfall Itructures 1ODEC91 31DEC91
2015 5 5 0 sw . UtH Itl.. . Instl U/G TelIpOf'ary Pwr & Tala 1ODEC91 16DEC91
2020 5 5 0 sw . Utfl Itl.. . lenftary TNit LIne . L. Dock 1ODEC91 16DEC91
2OZ5 10 10 0 sw . Utllttt.. . 1_lndar of Senltery Trri Lln 11DEC91 31DEC91
2030 10 10 0 sw . Utllttl.. . Electrical Iul:tbenk end Tela 17DEC91 31DEC91
2035 15 15 0 IW . Utfl Itl.. . Instl Creywat... Une 2JAN9Z 22.1AN92
Z040 15 15 0 sw . Utfl Itf.. . Instl ~tlc Watar Line 2JAN9Z 22.1A119Z
2045 15 15 0 sw . Uti lltl.. . Instl Efflwnt LIne 2JAN9Z 22.1AN92
2050 15 15 0 sw . Utfl Itl.. . Instl Cas LIne 2JAN9Z 22.1A119Z
( 3005 10 10 0 sw . Ent.-.nce toed . Eff lwnt Une 13JAN9Z 24.1AN9Z
3010 10 10 0 IW . Entrance loed . ~tlC/N "'In 13JAN9Z 24.IAN9Z
3015 10 10 0 IW . Ent.-.nce loed . T..t/FlUIh/Dlslnfect DW/AI 27JA1192 7FEB92
3020 5 . 5 0 sw . Ent.-.nce 10IId . Tie- In DW/N LIne to FIM 10fE192 14'E192
3050 15 15 0 IW . Utfl Itl.. . 0YerMad Pwar/Tal.p,ona Line 13JAN9Z 31.1A119Z
3055 5 5 0 IW . Utfl It I.. . TllIpOI'ary "'rlTala St.rtt4>> 3'E192 7FEB92
5000 15 15 0 sw. UtHltl.. . Storti D...ln TNit Linea 17 JUII92 &lUt.92
5005 15 15 0 IW . Utllltl.. - ID L.t...l.ls & Trench Drain 17 JUN92 8JUt. 92
S010 15 15 0 IW - Utllltl.. - Sanitary L.t....l. 17 JUN92 I.IUt. 92
c:.t uana
1025 10 0 100 SW . c:.faon Load Teat 7OCT91A 17OCT91A
1030 10 0 100 SW . AlE levlew of Catuon Loed T..t Data 18OCT91A 6IIOV91A
1035 40 0 100 SW . c:.faon lebar SUbatttals - Itart 13AUG91A 6OCT91A
1040 15 0 100 SW . Cat..on lebar SUbattt.l. . C~lete 7OCT91A 290CT91A
1045 5 0 100 SW - AlE levlew of Catuon leber SUbatttal. 300CT91 A 6ilN91A
1050 10 9 10 SW . 'ebrlcate & DellVel' Calaaon leber 13N0V91A 29IIOV91
1055 25 0 100 IV . "Indloed IIocItffcatton Prich" 6OCT91A 1311OV91A
1060 1 1 0 SW . IOCC Apvl of "tndloed Ch.... 20N0V91- 2OIIOV91
1100 15 15 0 SW . Zone A . Cat ssons 2DEC91 2ODEC91
1150 15 15 0 SW . Zone D . Catuona 23DEC91 14JAN9Z
1 ZOO 10 10 0 SW . Zone . - Catssons 15JAN92 28.1AN92
1250 15 15 0 IV . Zone E . Catssons 29JA1192 18FEI92
1300 10 10 0 SW . Zone C . c:.fssons 19FE192 3MAR92
Colu.w
1105 15 15 0 IV . Zone A . Colu.w & IUse Concrete 23DEC91 14JAII92.
( 1110 5 5 0 IV . Zone A . V...lfy Locations of Colu.w 15JAN92 Z1JA1192
1115 20 20 0 IV . Zone A . Col,--, Concrete CW'e Period 15JA1192 11FEI92
11S5 15 15 0 IV . Zone D . Colu.w IIUec Concrete 15JA1192 4FE892
...................................................................................................................................
MorV'Oe Ccu\ty, Florldl
PllMVERA PIOJECT PWIIEI
Monroe ~ty Det.,Uon Fec:1lfty
W'OIT DATI 19OEt91 IMI 110. SO
":21
SC1IED ItEPOIlT . line Iklp by IlCtlvlty code
Monroe Cowlty Det.,tlon FIlCH Ity
'TART DATI 1AUG91 fll DATI
.f
DATA DATE 1811OV91 PAGE 10.
2
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ .....
..... .-..- .... .... . ... ..--...... ................................................ ........ ........ ........ ........ .....
ACTIVln . OItIG REM
II DUI DUI
ACTIVITY DlICIIPTICII
SCIIEOUlED
START FIIISH
I
Colu.1l
1160 5 5 0 SW . Zone 0 . verify locatfen of Colu.1l 5FE192 " FEI92
"65 20 20 0 . - SW . ZoneD . Coluw. Concrete CUre Period .. 5FE192 3MAR92
1205 10 10 . SW . Zone . . COll..._ & .n se COncrete 29JM92 " FEB92
1210 5 5 0 IW . Zone . . verify Locatlen of Colu.1l 12FE19Z 1lfE192
1215 20 20 0 SW . Zone . . Coluw. Concrete CUre Period 12FE19Z 10MAl92
1255 15 15 0 SW . Zone E . Cob... & Mise Concrete 19FE192 10MAl92
1260 5 5 0 SW . Zone E . verify locatlone of Colwna 11MAl92 17MAR92
1265 20 20 0 SW . Zone E . Coh... Concrete CUre Period 11MAl92 7AP192
1305 10 10 0 SW . Zone C . CoI~ & Mise COncrete 4MAR92 17MAR92
1310 5 5 0 IU . ZonI C . Verify Locatlen of Colu.1l 18MAR92 24MR92
1315 20 20 0 SW . Zone C . Coluw. Concrete CUre Period 18MAR92 1WR92
1320 20 20 0 SW . Zone C . f/IIPIC Concrete Loedf~ Dock 4MAR92 31MAR9Z
Erection Drewlngs
7020 15 15 0 Pr~t . Coluw. Interfeee Detal Is 2111OV91 12DEt91
7'030 15 15 0 Precalt . ArM A . fr_l~ Dr..,lngs 2111OV9'1 12OEC91
7040 10 10 0 Pr~t . A.... A . All Apvl of fr_l~ Drawings 1]OEC91 21DEt91
7100 15 15 0 Prec.lt . A..... . & I . fr_f~ Drawings 13DEC91 6JAN92
7110 10 10 0 Precalt - AreM . & D . All Aptl of fr_l~ .. 7,1A192 2O.1A1192
7200 15 15 0 P.....t . Areea C & I . f.....~ o......ngs 7.1A192 27 .IAII92
n10 10 10 0 Precalt . Areas C & I . All .,. of F.....,. .. 2IJA192 10FE192
UtHltf../precest Coordlrwtlon Effort
7005 10 0 100 Coordfrwtlon Method Declafan 111OV91A 1511O'/91A
7050 20 20 0 P~t . ArM A . UtllPc:lt Coordfrwtfan ''''''' 16DEt91
7120 20 20 0 Precalt . Ar... . I D . UtllPc:lt Coordfrwtfan 11DEC91 15.1A1192
7220 15 15 0 Prec.lt . AreM C & I . UtI/PCSt Coordlrwtfan 16JA192 5FE192
Detan Drawings
7'060 15 15 0 Precalt - ArM A . Detaf I 0....1. 3ODEC91 2OJA1192
7070 10 10 0 Pr~t . A.... A . All Apv. of Detan orawf. 21.1A192 3FE892
7130 15 15 0 Precalt . AreeI' & D . Deten or..,l. 21.1A192 10FEB92
7140 10 10 0 P~t - AreM . & D . AllAlHI of Detaf I .. 11 FEI92 24FE892
7Z3O 15 15 0 Precelt . A..... C & I . Detan Drewl. 11FE192 2MAR92
n40 10 10 0 PrecMt . Ar... C & E . All Aptl of Detal I Dwp 3MAR92 16MAR92
Flbrlcatfan
7OlSO 20 20 0 PrecMt . A.... A - Fabrfcatlan 4FEB92 2MAR92
7090 5 5 0 PrecMt . Ar.. A . legln Shlppl,. to Sft. 3MAR92 9MAR92
7150 20 20 0 Precalt . ArH . - Fabrication 25 FEB92 23MAR92
7160 10 10 0 PrecMt . ArH . . legfn Shlppf,. to Sit. 2WR92 6APR92
7170 40 40 0 Precast . A.... 0 - Fabrfcatfon 25FEB92 2OAPR92
7110 10 10 0 Precelt . Ar.. D . legln Shfpplng to Sit. 21APR92 4MAY92
7250 25 25 0 Precast . A.... C - Fabrication 25MAR92 28APR92
7260 5 5 0 Precast .0 A.... C - legln Shipping to 1ft. 29API92 5MAY92
7270 40 40 0 Precalt . A.... E - 'abrlcatlon 18MAR92 12MAY92
7280 5 5 0 Precalt . Ar.. E - legln Shlppf,. to 1ft. . 13MAY92 19MAY92
. {
{
...............................................................................................................-....-..............
Ronroe Cculty. 'lor f cia PlIMAVEItA PROJECT PLAMI Monroe Cowlty DetentIon ,ectt It)'
IllT DATI 19DEC91 RUN NO. 50 Monroe Coc.my Detent'on FIlCH It)' STAltT DATI 1AUG9'f fllDATI UUl93*
16:28
SOlED ItEPOItT . lIne ak'p by IICtfvfty code DATA DATI 18NCN91 PAGE *t. S
..... ..... .... .... . ... .......... ...........--....-.............................. ........ ........ ........ ..-.-... .....
ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCHEDUlED
ID OUI DUI I STAltT FIIISH
..... ..... .... .... . ... -......... ..........--....-...................-........... ........ ........ .......- ...-.--- -.--.
PrecMt lrectfon
10000 40 40 0 Precest . A.... A . lrectlon 10MAR92 4MAY92
20000 30 30 0 Precut . ArM . - lrectfon 5MAY92 16JU1192
30000 30 30 0 preceat ~ A.... C . lrectlon 17 JUII92 29M.92
40000 30 30 0 precest . A.... D . ErllCtfon 5MAY92 16JU1192
50000 30 30 0 Precut - Area I . Erect'on 17JUN92 29JUl92
Roof
10050 10 10 0 Are. A . loof . looffng 3JUN92 16JU1192
20050 10 10 0 Area . - Roon~ 9JUl92 22JUl92
30050 10 10 0 Area C - Roofl~ 2OAUG92 2SEP92
40050 10 10 0 Area D - loofl~ 9M.92 22M.92
50050 10 10 0 Ar.. E - Roofl~ 2OAUG92 2SEP92
St.l,..
10010 5 5 0 Area A - T8IIIpOf'ary Acceu St.f,.. 5MAY92 11RAY92
20120 10 10 0 Ar.. . . Ir<<t Sta'", 16JUl92 29JUl92
30080 10 10 0 Ar.. C . Erect Stal,.. 27AUG92 10SEP92
( 40120 10 10 0 A.... D - Erect Ital,.. 16JUl92 29JUl92
43050 15 15 0 Ar.. D - 2nd Fl ~ Rezz Handralla 6NJG92 26MJG92
43060 10 10 0 Ar.. D . 1at Pl . Interior St.l,.. 6NJG92 19MJG92
50080 10 10 0 A.... E - Erect Stal,.. 27AUG92 10SEP92
53050 15 15 0 A.... I - 2nd II . Meu "__.1 la 11SEP92 IOCT92
53060 10 10 0 Ar.. I . 1st Pi - Intarlor Ita',.. 1asEP92 10em
Elwators
10100 15 15 0 A.... A - Elwators - lough-In , 9JUL 92 29JUl92
10110 5 5 0 A.... A - Elwators . Car & Pl.tf~ 3OJUL92 5MJG92
10120 5 5 0 Ar.. A - Elwators . Doors & Fr_ 6NJG92 12MJG92
10130 20 20 0 A.... A - Ilevators . Conatruct Cabs & Trf..out 13AUG92 10SEP92
Illb EIIbedI
11000 15 15 0 A.... A - 1st Pl - "lEIP/S Sllb EIIbeds 12MY92 2.u92
12000 20 20 0 A.... A - 2nd Pl - MlEIP/I Illb EIIbeds 12M Y92 9Jl1192
21000 10 10 0 Ar.. . . 1st fl - "lEIP/I Sllb E.Itleda 17 MI92 3O.UI92
22000 15 15 0 Ar.. . - 2nd Fl - "lEIP/I Ilab EIIbeds 17 JUI92 8JUL92
31000 10 10 0 A.... C - 1st Fl - MlEIP II Sllb EIIbeds 3OJUl92 12AUG92
32000 15 15 0 ArM C - 2nd fl - MJE/P/S Slab E.Itleda 22JUl92 11AUG92
41000 15 15 0 Area D - 1at FI - RlEIP/I Slab E.Itleda 17 J\II9Z IJUL 92
42000 20 20 0 ArM D . 2nd Fl - MlElP/I Sllb E.Itleda 17 J\II9Z 15JUL92
51000 15 15 0 Area I - 1at Fl - MlE/P/I Illb E.Itleda 3OJUL92 19MJG92
52000 20 20 0 Ar.. I - 2nd fl - t4/E1P/S Illb EIIbeda 3OJUL92 26AUG92
II'"
10030 5 5 0 Ar.. A - loof - TOPP'ng 19MAY92 2MAY92
11010 10 10 0 A.... A - 1at Fl.- FIR/PIC Sllb 3J\119Z 16JU1192
"- 12010 10 10 0 Ar.. A - 2nd FI - F/RIP/C Sllb 17 JUII92 3O.UI92
20020 5 5 0 A.... . . Roof Toppfng 24J\119Z 3O.IUII92
21010 10 10 0 Are. . - 1at Fl - FIRIPIC Sllb 1 JUL 92 15JUL92
------..................-.....................................................................-....................................
McllYOe Ccu\ty, flori. PttIMAVERA PRO.IECT PI.AIIMEI Monroe CoLf1ty Detention '1CIlIey
IEPClIT DATI 1ac:91 lUll 110. 50 Monroe ~ty Detention FIeHlty START DATI 1AUG91 FIN DATI ,l
16:21
SCIIED ItEPOIT . line .klp by ICtlvtty code DATA DATI 1811OW1 PAGE 11). 4
..... ..... .... .... . .-. .......... ................................................ ........ ........ .....-.. ........ .....
ACTIYln OR I G ItSt ACTIYln DESCRIPTIOI SCHEDUlED
ID OUR OUR I START FINISH
--... ..... .... .... . ... -........- ...-.--......................................... ..-..... ~.._.... ........ ........ ...-.
II'"
22010 10 10 0 A.... . . 2nd Fl - fJI/PIC Illb 16.IUL 92 29JUL92
22200 10 10 0 AI''' . . 2nd Fl - flllPIC .1.... & ~t. 3OJUL92 12AUG92
22JOO 10 10 0 AI''' . . 2nd Fl - lneulatlon brei & Illb . cvr 160CT92 29OCT92
30020 5 5 0 A.... C . Roof TClIlPlne .,-- 6MJG92 12AU892
31010 10 10 0 AI''' C . 1st Fl . FJl/PIC Illb 13AUG92 26MJG92
32010 10 10 0 AI''' C . 2nd Fl - fJI/P/C Sllb 3SEJl92 11SEP92
40020 5 5 0 AI''' - Roof TClIlPlne 24.1U192 3OAJN92
41010 10 10 0 Ar.. . 1at Fl . f~ & Rebar for Sllb 17.1U192 3OAJN92
41020 10 10 0 Ar.. - 1st Fl . Pour/Cur. Sllb 9JUl92 22.1Ul92
42010 10 10 0 A.... . 2nd '1 - F~ & ....1' for Sllb 11.1U192 3O.1U192
42020 10 10 0 Ar.. . 2nd fl - POA/I' /OIft S 1 Ib 23JUl92 5Al1G92
42040 5 5 0 A.... . 2nd Fl . Pour Ecf.II p peds 13AUG92 19AUG92
50020 5 5 0 AI''' - Roof Tapplne 6MJG92 12AUG92
51010 10 10 0 ArM . 1st fl - ,~ & .eber for ~llb 30JUL 92 12AUG92
51020 10 10 0 A.... . 1st Fl - Pour/Olft Illb 2OMJG92 2SEP9Z
52010 10 10 0 A.... . 2nd fl . f~ & ..... for Sllb 3OJUL92 12AUG92 I
52020 10 10 0 A.... . 2nd Fl - Pour/Oln Illb 3SEP92 17SEP92 -.
52040 5 5 0 Are. . 2nd Fl . Pour Equip peds 25SEP92 10CT9Z
JIesonry
11020 5 5 0 AI''' A . 1st fl . L.,out 'art/Set 'r_1Vnd U.l 17.A1192 23.1U192 .'
11040 15 15 0 AI''' A . 1st fl . ....llfIo'l . letll~ 16.IUL92 5AUG92
11050 35 35 0 A.... A . 1st fl - lethrooa & ShaMel' TH. 6AUG92 24SEP9Z
11070 20 20 0 AI''' A . 1st fl - ....Cfli'Y . Offices & DonI ArMs 24.U192 22JUL92'
12020 5 5 0 A.... A . 2nd fl . L.,out 'artltled/Set Fr_IV 1 JUL92 1JUL92
12050 15 15 . A.... A - 2nd FI. - FIlII . 'I 9JUL92 29JUL92
12210 15 15 0 AI''' A . 2nd Fl - eer.tc Tt 1. 9OCT92 29OCT92
20100 10 10 0 AI''' . . ....onry . Stal ra 11.A1192 5O.IUI92
20110 10 10 0 Ar.. . - CUre ....llII. 'I' Sulra 1 JUl92 15JUL92
21020 5 5 0 Aru . . 1st fl .. L-rout Part/Set Fr_1Vnd U.l 16.IUL92 22JUL92
21040 10 10 0 AI''' . . 1st Fl . ReaonrY . . 6MJG92 19AUG92
21050 10 10 0 Ar.. . . 1st .1 . c:er.fc Tt le . . 2OAlJG92 ZSEP92
21070 20 20 0 Ar.. . . 1st '1 . ....llfIo~ 23JUL92 19MJG92
22020 5 5 0 Ar.. . . 2nd fl - uv-out Part/Set Door Fr.-s/V 3OJUL92 5MJG92
22040 10 10 0 Area . . 2nd Fl - .... anry . . 2OAUG92 2SEP92
22050 15 15 0 Are. . - 2nd fl. IIMonI"Y Support Syst_ .ough' 6AUG92 26MJG92
22060 15 15 0 Are. . . 2nd fl- IIMonI"Y 6AUG92 26AUG92 -
22280 10 10 0 Ar.. . . 2nd fl - CaIplete Exterior Masonry 1asEP92 10CT9Z
30060 10 10 0 Ar.. C . MasonrY . Stalra 3OJUL92 12AUG92
30070 10 10 0 Ar.. C . Cure "-onI'Y . St. I ra 13AUG92 26AUCi9Z .
31020 5 5 0 AI''' C . 1st Fl - t.ar-out 'art/Set Dr Fr..-JWII 27AUG9Z 2SEP92
31040 15 15 0 Ar.. C . 1st Fl - ..........., 3SEP92 24SEP9Z
32020 5 5 0 Area C . 2nd Fl . l-rout Part/Set Fr_1Vnd U.l 1asEP92 24SEP9Z
32040 15 15 0 Are. C . 2nd fl - IIMonI"Y 25SEP92 1socm
..............................................................................................................~....................
Monroe CoI.nty Detention FeclUty
"'":~ Cowlty, Flor'. PRIMAVERA PRO.IECT PlAIIIIEl
IT DATE 19DEC91 RUN 110. 50 Monroe CCUIty Detention Fecfllty
":21
SC'!fD IEPOIT - line Iklp by ect'v'ty code
STAlT DATI 1AUG91 FUI DATE 1MO-
DATA DATI 1811OV91 PAGE 110. 5
..... ..... .... .... . ... .......... ....................~........................... ----.... ----...- -..-.... ..-..... .....
ACTIVITY ORIG REM ACTIVITY DESCRIPTION SCIIEDtA.ED
II DUI DUI I STAlT FlMISH
..... ..... .... .... . ... .......... .........................~...............-.....- ......~. .......~ ........ ........ .....
Ruorvy
40100 10 10 0 Area D - Muonry' Ital... . 17.1U1192 3O.U92
40110 10 10 0 Area D - CUre RasonrY . Sta'rs , 1.IUL 92 15M.92
41030 5 5 0 Ar.. D . 1at Fl - L~ Part/Set F.--J\h:I WlI 2S.IUL92 29.IUL92
41050 15 15 0 A.... D - 1at Fl - ....llhi7 - 1at lewl ..Ua . 3O.IUL 92 19MJG92
41010 10 10 0 A.... D - 1at Fl - MaaoIV'Ya - 2OAUG92 2StP92
42030 5 5 0 ArM D - 2nd Fl - L~ Part/Set Fr_JUnd WIt 6AUG92 12AUG92
43010 10 10 0 Area D - 2nd Fl - Masonry - 2nd lewl 3SEP92 17SEP92
43020 25 25 0 Ar.. D - 1at FI - ..'" lay Masonry Wall. 6AUG92 10SEP92
50060 10 10 0 Ar.. E . MMorwy . Sta'ra 3OJUl92 12MJG92
50010 10 10 0 Area I - CUre w..onry - Stl'ra 13AUG9Z 26MJG92
51030 5 5 0 Ar.. I - 1.t Fl - L~ Part/Set f.--J\h:l Wll 3SEP92 10SEP92
51040 15 15 0 Ar.. I - 1at Fl - ~ ~t Sysu. III 11SEP92 1OCT92
51050 15 15 0 Area E - 11t .1 - IIUonrY - 11t lewl ..Ua n SEP92 10CT92
51010 10 10 0 Ar.. I . 1st Fl - Reaonry a . 25SEP92 IOCT92
52030 5 5 0 Area I - 2nd .l - L~ Part/Set fr_JUnd Wll 1~ 2UEP92
( 53010 10 10 0 Areal - 2nd FI I MeIdnry - 2nd lewl 9OCT9Z ~tR
53020 25 25 0 Ar.. I . 1.t fl - MI", lay Maaonry Will. 18SEP92 Z20CJ92
Drywall
12030 25 25 0 A.... A . 2nd Fl - DrywaU fr.',. 9JUL92 12MJG92
12200 15 15 0 Area A - 2nd fl - Drywall/Ttpe/Pl_ter Willa 18SEP92 IOCT92
Spray-on INUlatlon
12070 10 10 0 Area A - 2nd fl - Spray-on lnaulltlon . Prap 3OJUL92 12AUG92
120lIO 5 5 0 Ar.. A - 2nd 'l - Spnron lnaulatlon - Spray 13AU&92 19MJG92
22080 10 10 0 A.... . - 2nd Fl - ......,.on lnaulatlon - Prap 6MJli92 19MJG92
22090 5 5 0 ArM' . 2nd Fl - ......,.on lnaulltlon 27NJG92 2SEP92
32060 5 5 0 Area C - 2nd fl - Spray-on InlUlltlon Pnp 9OCT9Z 150CT92
32070 5 5 . Area C - 2nd Fl - Spray'on lnaulltlon - Spray 160CT92 za,cJR
43010 10 10 0 Area D . 2nd Fl - lpI".ay-on lnaulatlon 2OCT9Z 15OCl92
53010 10 10 0 Area I - 2nd fl- Spray-on lI.ulatlon 6NCN92 19MDV92
Utility lough-In ; ..
c
10020 5 5 0 Area A - loof - hnetrltlona & loof Accessorl. 12MAY92 18Mm
10040 5 5 0 Area A - loof - CUrbs ~ 21MAY92 UJI92
10060 10 10 0 Area A - Roof -.aoof.Dr.',.ge 19MY92 2.u92
11030 15 15 0 Ar.. A - 1at Fl - I?\Ullbh'lJ III II ..th~ 24Jt1192 15JUL92
11060 20 20 0 A.... A - 11t Fl - ,Muonry 1/1 SUpport (M/EIPIS) 24Jt1192 22JUl92
12040 25 25 0 Area A - 2nd fl,- "-onlY III SUpport (MlElPIS) 9JUl92 12AUG92
12060 15 15 0 " A.... A . 2nd flc-J;eU!.", Anchors & ....,.. 9JUL92 Z9JUl92
20010 5 5 0 ArM . -Roof -. ~t...tlona & loof aee.sorl. 11.AJ19Z 23.UI92
20030 5 5 0 ArM' - Roof ~. r'.'", 1 JUL92 ~92
20040 10 10 0 ~ Aree . - Roof Dtaf~ ~ - 24.U192 I.IUL 92
( 21030 10 10 0 Area . - 1st Ft - P\.I,.~ I~- ~n II . 23JUL92 5AUG92
21060 20 20 0 A.... . - 1st 'J - ~ 1uFPort, SyIt_ III 23JUL92 19MJG92
22030 10 10 0 . - Area' - 2nd .t - Ph.pl", I~-In II . 6AUG92 19MJG92 .
...................................................................................................................................
IEP<lIT DATI 1CJDEC91 lUll NO. 50 . Monroe Cou1ty Detentfon Facfl fty
16:21
SCItED IEPOIT - tfne slcfp by actfyfty code
Nontoe C<<Mrty Detentfon Facltfty
STAlT DATI 1AUG91 Fill DATI . (
Monrol.' Cou1ty, Flor-lde PRIMAVERA PROJICT PUllllEI
DATA DATI 18NOY91 PAGE.. 6
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ .....
ACTlVln OIIG 10
ID OUR OUR
ACTIVln DEICIIPTIOI
SCHEDUlED
STAlT FIIIIII II- ..
I
..... ..... .... .... . ... ......~... ................................................ ........ ........ ........ ........ .....
UtfUty lOUIh-fn
30010 5 5 0 ArM C . loof . PenetratIon & loof Accessorf.. 30JUL 92 5MJ892 -
30030 5 5 0 Ar.. C . loof CUrbI 13AUG92 19MJ892 "
30040 10 10 e' ArM C - loof Dr.'...... t' 6MJG92 19MJG92 .
'.
31030 15 15 0 ArM C - 1st Ft - IIIsonry ~t - Syst_ III 3IEP92 24SEP92
31070 15 15 0 Area C - 1st Ft - Ph_fl'll lOUIh-fn a II 3SEP92 24SEP92
32030 15 15 0 Ar.. C - 2nd Fl - RMGnry'~t . Syst_ III 25SEP92 150CT92
32050 10 10 0 Area C - 2nd Ft . eell1,.Anchon & Hengers 25SEP92 8OCT92
32100 10 10 0 Area C - 2nd fl .,.tUlbll'll lOUIh-fn a sa 25SEP92 8OCT92
40010 5 5 0 Area . loof . Penetratlona & loof Accessorl.. 17.ll1192 23JU1192
40030 5 5 0 Area - loof CUrbI . ,'" ~~' 1.1Ul92 8JUL92
40040 10 10 0 Area - loof Dnl,... ., - 24.ll1192 8JUL92
41040 15 15 0 ArM - 1at Ft .- ....on;y SUpport Syst_ III 3OJUL92 19AUG92
41060 10 10 0 Area - 1st 'l - PlUlbfl'lllough'ln' Ir 3OJUL92 12AUG92
43000 10 10 0 Ar.. . 2nd Fl - IIuonry SUpport Syst_ III 3IEP92 17SEP92
43030 10 10 0 Area . 2nd Ft . eel t Il'lIIPl... H.,..rs & Sprts 11SEP92 10CT92
.
s0010 5 5 0 Ar.. - loof . Penetr.tlona & loof Ace..sorl.. 3OJUL92 5MJ892 /
50030 5 5 0 Ar.. . Roof CUrbI . 13AUG92 19AUG92
50040 10 10 0 ArM - loof Drsl,... 6MJG92 19M11i92
51060 10 10 0 Ar.. . 1at ft- PlUlbfl'lllough'in a "r 11SEP92 24SEP92
53000 10 10 0 Ar.. - 2nd'l - RMonry SUpport Syst_ III 9OCT92 22OCT92
53030 10 10 0 ArM . 2nd ft . cell Il'lIIPt... Ilan8ers & SprU 23OCT92 5IIOV92
lult Inst.ll.tion of Utilitl..
". 25 25 0 Ar.. A . 1at ft - IMlC Ductwork lult Instl 23.IUl92 26MJG92
'''00 25 25 0 ArM A . 1at ft - IMC Pipll'll lult Instl 23.IUl92 26MJG92
11120 25 25 0 ArM A . 1at ft . PlUlbfl'lll<k Instl 23.IUl92 26MJG92
'''40 25 25 0 Ar.. A . 1st ft - Pw/UI Cardlft lult Inst 23.IUl92 26MJG92
1 "60 25 25 0 ArM A . 1at ,l _.~ Ccinll.Ift lult Inst.ll 23.IUl92 26IlUG92
",ao 25 25 0 Ar.. A . 1at 'l - -ffre "Prohctlon lult Instl 23.1UL92 26IlUG92
12090 20 20 0 Ar.. A - 2nd ft - WAC Ductwork lult Instl 2OAUG92 17SEP92
12100 15 15 0 Ar.. A - 2nd Ft - WAC Plpll'll lult Instl 2OAUG92 10SEP92
12110 15 15 0 ArM A . 2nd fl . PlUlbfl'lllult Instl 2OAUG92 10SEP92
12120 15 15 0 A.... A - 2nd Ft . Pw/UI eonc..lt lult Instl 2OAUG92 10SEP92
12130 15 15 0 ArM A - 2nd ft - SecUrltj~ Conci.Ift lult Ins 2OAUG92' 10SEP92
12140 15 15 0 Area A - 2nd Fi - FIre .PrOtectlon lult Instl 2OAUG92 10SEP92
21<<110 15 15 0 ArM I - 1at fl ."WAC Ductwoi1t . lult Install- . 2OMJG92 10SEP92
21090 5 5 0 Ar.. 1-.' 1at"t -WAC Plpfriii' - lult lnet.ll-- 2OMJG92 26MJG92
21100 10 10 0 Ar.. I - 1st 'F;~Ptuibt,.:~..lult IniitaU 2OAUG92 2SEP92
21110 15 15 0 ArM I ,""t h . Pwlltt Cardlft . Bult Instell 2OMJG92 10SEP92
21120 10 10 O. Ar.. . . 1at Fl . Sec~ CcriIUft . lult Instal 2OAUG92 2SEP92
21130 10 10 0 Ar.. . - 1at Fl - Fire protection' lult Install 2OMJG92 2SEP92
22100 10 10 0 Ar.. I -'2ncI Ft >>"WACCDUR.ort -'ilult Inst.U' 3SEP92 17SEP92
22110 15 15 0 ArM I - 2nd fl....~lIVAC ,tift.. - ....tt Inst.ll 3IEP92 24SEP92
22120 10 10 0 ArM . . 2nd Fl" ;':-'lUlbll'll. lult lnstallatton 3SEP92 1 tsEP92
....................................-._......_~....................................................................................
NclnrOe Ccurty, Florlde PlIMVEIA PltOJECT Pt.ANIIEI
Monroe County Detention 'ecH fty
d DATE 190EC91 lUll 10. 50 Monroe Coc.Irty Detention FecH Ity
16:21
SCIIED REPORT . line sltfp by ectfvtty code
START DATI 1NJG91 fll DATE 1JUl93*
DATA DATI 18NOV9t PAGE 10. 7
..... ..... .... .... . ... .......... .........................~~..................... ........ ........ ........ ........ .....
ACTIYln ORIG REM ACfIVln DESCRIPTIOI SCHEDULED or
ID M M I STAlT FlIIII
..... ..... ......... . ... .......... ............-.......~..~........................ ........ ........ ..~..... ........ .....
"'lit lnatallatlon of Utll Itl.
22130 " " 0 Ar.. . .. ,Zrld Fl . PwlU, CorQIft . "'lit InataU 3SEP92 24SEP92
22140 10 10 0 Ar.. . . Zrld Fl . seycc. CorQIft . lullt lnatal 3SEP92 17SEP92
22150 10 10 0 Area' . Zrld Fl t fI... protectfon . lult lnatall 3SEP92 17SEP92
m10 15 15 0 ArM . . Zrld 'I . Ancfllfery Pipe 16OCT92 5NCJII92
31OS0 15 15 0 Ar.a C . 1st 'I . IIYAC Ductworlt lullt lnatall 25SEP92 15OCT92
31060 5 5 0 Ar.. C . 1st Fl . IVAC Plplne . lullt lnatall 25SEP92 10em
310e0 15 15 0 Ar.a C . 1st '1 . Plu.bfne . Butlt lnatall 25SEP92 1socm
31090 20 20 0 Ar.. C . 1st Fl . Pwr/Ltl CordJlt . Built lnat.ll 25SEP92 . 22OCI92
31100 20 20 0 Ar.. C . 1st Fl . See/eo. CordJft . lult lnatal 25SEP92 22OCT92
31110 15 15 0 Ar.a C . tst Fl . '1... protec:Uon . lullt lnatall 25SEP92 1socm
:szoeo 15 15 0 Ar.. C . Zrld Fl . IVAI: Ductwork . lullt lnatall 230CT92 1211CW92
32090 10 10 0 Ar.. C . Zrld Fl . IVAC Plpfne . "'It lnatall 230CT92 511M2
32110 10 10 0 Ar.. C . Zrld Fl . Plu.bfne . "'It lnatall 230CT92 511M2
32120 15 15 0 ArM C . Zrld Fl . Pw/Lt, CorQIft . lult lnatall 230CT92 1211CW92
32130 10 10 0 ArM C . Zrld Fl . see/eo. CordJlt . "'It lnatal 230CT92 51OV92
( 32140 10 10 0 . ArM C . Zrld Fl . FI... protectfon . lult lnatall 23OCT92 51OV92
43100 15 15 0 ArM D . 1st '1 . 11.1 1 If de A . vert ch... uti 160CT92 51OV92
43110 15 15 0 . ArM D . 1st Fl . 11.1 1 Ifde . . vert chase uti 6IIOV92 3OIiICW92
43120 15 15 0 Ar.. D . Zrld Fl . 11.1 1 Ifde A . hortz chaM uti 6IIOV92 3OIiICW92
43130 15 15 0 ArM D . Zrld Fl . 11.1 1 If de . . hortz chaM uti 10EC92 Z1DEC92 r
43200 15 15 0 ArM D . 1st Fl . .. 2 Ifde C . vert chaM uti 16OCT92 51OV92
43210 15 15 0 A.... D . 1st Fl . 11.1 2 If de D . vert chaM uti 6IIOV92 3OIiICW92
43220 15 15 0 ArM D . Zrld Fl . .. Z ..de C . hortz chaM uti 6IIOV92 3OIiICW92
43230 15 15 0 Ar. D . Zrld Fl . .. ~ If de D . hortz ell... uti 10EC92 Z1DEC92
43300 30 30 0 A.... D . Zrld,l . IIedlanfcal Iocla Utf lltf.. 160CT92 3OIiICW92
4mO 20 20 0 Ar. D . ~OffICl Utflltf. 160CT92 1211OV92
53100 15 15 0 A.... E . 1st Fl . .. 3 Ifde E . vert chaM uti 2OIOV92 14DEC92
53110 15 15 0 Ar.. E . 1st Fl . 11.1 3 If de , . vert chaM uti 15OEC92 6.IM93
"'20 15 15 0 Ar.. E . Zrld Fl . III 3 Ifde E . horll chaM uti 15DEC92 6.IM93
53130 15 15 0 ArM E . 2nd Fl . III 3 If de , . hortz ell... uti 7JA1193 27 .IM93
53200 15 15 0 Ar.. E . 1st Fl . III 4 Sfde G . vert chaM uti 2OIOV92 14DEC92
53210 15 15 0 Ar.. E . 1st Fl . III 4 Sfde I . vert chase uti 15DEC92 6.IAII93
53220 15 15 0 Area E . 2nd Fl . III 4 Sfde G . horfl ell... uti 1SDEC92 6.IAII93
53230 15 15 0 Area E . 2nd Fl . III 4 Sfde I . horfl chase uti 7JA1193 27.1M93
53300 30 30 0 ArM E . 2nd fl . Mec:henfcal R~ UtU W.. 2ONOV92 6.IM93
5l33O 20 20 0 Ar.. E . ~ffca Utf I 2OIOV92 Z1DEC92
Ceu lne Fr_I",
11200 5 5 0 Ar.. A . 1st Fl . Cel lIne Fr.lne In A1000 27AUG92 2SEP92
11210 5 5 0 Area A . 1st Fl . Cel t lne Fr.lne In A1029 3SEP92 10SEP92
11 220 5 5 0 Area A . 1st Fl ~ eel I fne Fr.fne In A1039 11 SEP92 11SEP92
( 11230 5 5 0 ArM A . 1stF' . Cetllne F~tne In A1049 18SEP92 24SEP92
12150 15 15 0 Area A . 2nd Fl . Ceu lne Fr.tne 18SEP92 8OCT92
~ 21140 10 10 0 ArM . . 1st Fl . Cell lne Fr.fne 11 SEP92 24SEP92
...................................................................................................................................
Monroe Ccurty, , lorl de
PRIMAVERA PROJECT PI.AMEI
Nonroe ~ty Detention 'acllfty
REPORT DATE 19OEC91 RUN NO. 50 Monroe Cowlty Detention FecH Ity
16:21
SCHED REPORT. line skIp by activIty code
STAlT DATI 1MJCi91 fll DATE
DATA DATE UI..0\I91 PAGE 10. a
ACTIVln ORIS Rat
ID DUI M
C'
ACTlvsn -DlSCltIPTlOI
SCHEDULED
ITAll fllllI
I
. . ---
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ ....-
Cel II.. Fr.lng c~ "'.'
22070 10 10 0 Are.' . 2nd Fl . Cell f.. AnChors & hngers 6MIG92 19AiJG92 ,"
22160 5 5 0' Ar.. . . 2nd Fl '.. Celllri.1r..... 25SEP92 10Cm [;
31130 5 5 . ' Area C . 1st ,. .:cifllrii ,,..Ing . Stert 2lOCT92 29OCT92
31140 5 5 . Aree C . 1st Fl . "Celllne '~Ine . Calplete 300CT92 5IOV92
32160 10 10 0 Area C . 2nd Fl . Cell fne '....Ing 1311OV92 3OIIOV92
43340 10 10 0 Area D . Cel I Ing Fri..... 1311OV92 3OIIOV92
53340 10 10 0 Ar.. E . Celli.. Fr.... ; 22DEC92 6.IA1193
Syat_ Dropa I T..tlne / P\n:h.out
11240 10 10 0 Area A . 1st Fl . Syatlllil Dropa . Stert 3SEP92 11SEP92
11250 5 5 0 Area A . 1st Fl - Syat_ Dropa . Calplete Z5SEP92 1OCT92
11260 5 5 0 Ar.. A . 1st '1 . T..t 'UtU fty PIpIng Syst_ 2OCT92 aocm
11270 5 5 0 Area A . 1st PI .. lVIdl.out Above Cell Ing UorIt 9OCT92 1SOCm
1Z160 15 15 0 Ar.. A . 2nd PI . Utflfty Syat_ Dropa . Start 18SEP92 aocm
12170 5 5 0 Area A . 2nd Fl .. "Utfltty Iyst_ Dropa . Cpt 9OCT92 15DCT92
12180 5 5 0 A.... A . 2nd Fl . T..t Uti I Ity PipIng Syat_ 160CT92 22OCT92
12190 5 5 0 Area A . 2nd Fl : pya-out Above Cel I Ing Yortt 2lOCT92 29OCT92
21150 10 10 0 Ar.. . . 1st tl . Sya~ Dropa . Start 11SEP92 24seP92 \
21160 5 5 0 Ar.. . . 1st Fl . Syat_ Dropa . Calplete 25SEP92 10Cm
21170 5 5 0 A.... . . 1st '1 . Syat_ T..t 2OCT92 aocm
21180 5 5 0 A.... . . 1st F\ . P\n:It-out 9OCT92 150CT92
22170 5 5 0 ArM . . 2nd Fa . Sya~ ~ 2OCT92 aocm
22400 10 10 -0 A.... . . 2nd Ft . Syau. T_t 6IDI92 1911OV92
22410 5 5 0 A.... . . 2nd Fl . Ilva-out 2OIOV92 3OIOV92
31150 5 5 0 A.... C . 1st Fl . Sya~ Dropa . Start 3OOCT92 5IIOV92
31160 5 5 0 A.... C . 1st Fl . Ivs~''''' . Calplete 6IDI92 1211OV92
31170 5 5 0 A.... C . 1st '1 . Ivst- Teet 1311OV92 1911OV92
31110 5 5 0 A.... C . 1st 'I . Sya~ "",,.out 2OIOV92 3OIOV92
32170 5 5 0 A.... C . 2nd '1 . Sya~ Oropa . Start 1311OV92 1911OV92
32110 5 5 0 A.... C . 2nd Fl . Syat_ 'DrOp. . Calplete 10EC92 7DEC92
32190 5 5 0 ArM C . 2nd Fl . Syat_ t..t &>>EC92 14DEC92
32200 5 5 0 Area C . 2nd fl . ","".out 15DEC92 21DEC92
43310 5 5 0 ArM D . 2nd Fl . T..t Syst_ 22DEC92 29DEC92
43320 5 5 0 Ar.. D . 2nd Fl . PWd.out 3CIlEC92 6.IA193
43350 5 5 0 ArM D . Syst_ D~". both floors 10EC92 7DEC92
43360 5 5 0 ArM D . Syat_ T..t . ~Off . both floors 1DEC92 14DEC92
43370 5 5 0 ArM D . P\n:II-out . ~f . both floors 15DEC92 21DEC92
53110 5 5 0 Ar.. E . 2nd Fl . T..t Syat_ 28.WI93 3FEa93
53320 5 5 0 Ar.. E '. 2rid Fl . ~.out 4fE893 10FE1193
53350 5 5 0 ArM E . Syat_ -'rcipa . both floors 7.1M93 13JA193
53360 5 5 0 Ar.. E . Syat_ Teet . ~f . both floors 14.1A1193 2O.IA193
53370 5 5 0 ArM E . P\R:h-out . DaYrWOff - both floors 21.1M93 27 JA1193
Cell I "IS '.'
11280 20 20 0 Area A . 1st Fl . Cell Ing loard!TaptlPl..ter 160CT92 1211OV92
...................................................................................................................................
tIonroe CowIty, Florlde PtIMAVERA PROJECT PLAlllER Monroe CowIty DetentIon FecH Ity
( lilT DATI 190EC91 llIt NO. 50 Jbv'oe Cou'tty Detention Facility STAlT DATI ,MIG9t "I DATI 1.IUL93*
16.21
tCIIED REPORT . line skip by actfvlty code DATA DATI ,.."." PAGE 10. 9
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ .....
ACTIVln ORIG REM ACTIVln DESCRIPTIOI SCHEDUlED It. .':'"
.D M M I START ,..1. ~
..... ...-. .... .... . ... .-........ ................................................ ........ .....~.. ........ ........ .....
Celli...
12220 15 15 0 ArM A . 2nd Fl . Drywll/Tape/Pl..ter Cell I... 300CT92 1911DV92
21_ 15 15 .0 ArM . . 1at ,t Cel I Ing 1oardIT.,./Pl..ter 16OCT92 51OV92
22UO 10 10 0 ArM . . 2nd Fl . Df'YMIlllTape/Pl..ter Cen I... 'DEC92 14DEC92
31_ 15 15 0 Ar.. C . 1st Fl . Cel t 11'11 Ioarel Tape & Pleeter 1DEC92 21DEC92
32410 15 15 0 Ar.. C . 2nd Fl . Cell I "IS 14JA1193 3FE193
43380 15 15 0 Ar.. D . DrywelllTape/Pl..ter Celli... . both fl 22DEC92 13.1M93
53380 15 15 0 Ar.. E . DrywlllTape/pt..ter Clp . both floors 28JA1193 17FE193
"Ire Pulls
11300 10 10 0 Ar.. A . 1st Fl . Wire Pulls 13N0V92 3OIIOV92
12240 10 10 0 Ar_ A . 2nd Fl . \ltre Pull. 2ONOV92 7DEC92
21220 15 15 0 ArM . . 1st '1 WIre Pull 6IIOV92 3OIIDV92
22450 20 20 0 Ar.. . . 2nd Fl . Wf... Pull 15DEC92 13.1A1193
31220 15 15 0 Area C . 1st Fl . Wire Pull 22DEC92 13.1A1193
32400 15 15 - ,0 Ar.. C . 2nd Fl . WI r. Pull 22DEC92 13.1A1193 ,
43420 10 10 0 Ar.. D . Wire Pull . start. both floors 3ODEC92 11.1M9J
( 43430 5 5. 0 Ar_ D . Wf... Pull . CCllIIPlete - both floors 14JA1193 20JAIIri
53420 10 10 0 Ar.. E . VI re Pull . etart . both floors 4FEm 17FE193
53430 5 5 0 ArM E . Wi... Pull . CCllIIPlete . both floors 1aFEm 24FE193
Trllrout Utflltl..
11no 15 15 0 ArM A . 1st Fl . J4/EIP/I TrIa-out 15DEC92 6.IAII9S
12210 15 15 0 ArM A . 2nd Fl . t4IElP/I TrIa-out 22DEC92 13.1A1195
21_ 15 15 0 Ar.. . . 1st Fl . M/ElP/I Tria-out 15DEC92 6.IAII93
22480 10 10 0 Area . . 2nd Fl . tVEIP/I Tr la-out 28JA1193 10fU93
31_ 10 10 0 Area C . 1st Fl . tVEIP/I Tria-out 28JA1193 10fU93
32470 10 10 0 ArM C . 2nd Fl . t4IEIP/l Trllrout 4MAl93 11MM93
43470 15 15 0 Area D . M/EIP/S trllrout . both floors 4FEm 24FE193
53470 15 15 0 Area E . M/EIP/I tria-out --,both floors 11MAR93 311N93
Paintfl'll
11310 10 10 0 Aree A . 1et Fl . Prep for lullt Painting 13N0V92 3OIIDV92
11320 10 10 0 Area A . 1st Fl . tulk Palnti", 1DEC92 14DEC92
12250 10 10 0 Area A . 2nd Fl . Prep for "'lit Painting . 2ONOV92 711EC92
12260 10 10 0 Area A . 2nd Fl . lullt Painting 8OEC92 21DEC92
21230 10 10 . Area . . 1st Fl . PaInting Prep 6IlOV92 1911DV92
21240 10 10 0 Area . . 1st Fl . lult Paintfng 1DEC92 14DEC92
22460 10 10 0 Area . . 2nd Fl . Pafntlng Prep 1SOEC92 29DEC92
22470 10 10 0 Area . . 2nd Fl . lul\( Painting 14JA1193 27.1M93
31230 10 10 0 ArM C . 1st Fl.. ,.Intlne Prep 22DEC92 6.IAII9S
31240 10 10 . 0 Area C . 1st Fl . lulk PaInting 14JA1193 27 .IAII93
32430 10 10 0 ArM C . 2nd Fl . P.lnt Prep 14JAN93 27~
32440 10 10 0 ArM C . 2nd Fl . "'Lit Palntfng 4FEm 1~
( 43450 10 10 0 Area D . PaInt prep . both floors 22DEC92 6.IM9J (: ~.
43460 10 10 0 Area D . lullt Paint. both floors 21 JAN93 3FEI93 ,
53450 10 10 0 Area E . Paint prep . both floors 2IJAN93 10FB95
...............................................................................................-................................-.-
Monroe Ccurty, Florlde PttlMAVERA PItO.IIC1' .u.a Monroe Ccu\ty Detent I on 'ac It I ty
REPORT DATI 19DEC91 RUI NO. 50 tIonroe Cowlty Detention 'ecfllty STAlT DATI 1AUQ91 nlDATI
16:21
SCHED REPOIT . Une skip by activity code DATA DATI 1eNOV9t PAGE ID. 10
..... ..... .... .... . ... .......... ................................................ ........ ................. ........ .....
ACTIVln 011 G REM ACTIVln DEICRIPTIOI SCIIEDULED
ID DUI DUI I STAlT FlIIII A.'
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ -.-..
Palnttng
53460 10 10 , A.... E . Butt Paint. botlt floors 25FEI93 1ClMA19J
77'020 30 30 . Painting - Inter'..... Touch... (sUM:) 18MAR93 2IAPI93 0(1
77U3O 10 10 , PaInt tng . Intertor Touch... lCClllpl) 13M Y9S 26MY9S
77040 60 60 . p.tntlng - Exterior aut ldtlll 5FE193 29API9J 0<.
FInIsh..
11290 10 10 . A.... A - 1st ,l . lnatall Doors & Grills 13NO\192 3ONCN92 ,.
11340 15 15 0 ArM A - 1at Fl . CaNwort 15DEC92 6.IAN93
11350 15 15 0 Ar.. A - 1st '1 - Gl.ztng 15OEC92 6JAI9J
11360 15 15 0 ArM A - 1at Fl . Door 1Iardwe... 15DEC92 6.IAN93 1,
11m 10 10 0 A.... A - 1st Fl - Floor & vall CoYerI. 7JA1193 2OJA1193
12230 10 10 . Ar.. A - 2nd Fl - lnatl Doors & Grit Is 2ONOV92 7DEC92
12270 10 10 . ArM A - 2nd Fl - C.....-t 22DEC92 6JAII93
12290 15 15 '" ArM A - 2nd Fl - ~ttcal TIle 22DEC92 13JA119.S
1ZSOO 15 15 . ArM A - 2nd Fl - Door ~ 22DEC92 13JA119.S C
12310 15 15 . ArM A - 2nd Fl - Glul", 22DEC92 13M1193 r
12320 15 15 . A.... A . 2nd Ft - Floor & Ulll Coverf. 14.1A1193 ,]FE193 {
21190 10 10 . A.... . - 1st '1 - ,loor Pr8p 160CT92 29OCT92
21210 15 15 0 ArM . - 1st 'I - Doors & Irlt lee 6IICN92 3C*DV92
21250 15 15 0 Ar.. . - 1at Fl - ~tlcal Ttle 15DEC92 6JAII93
21m 10 10 0 A.... . - 1st Fl . Door ......... 15OEC92 29DEC92
21_ 10 10 . A.... . - 1st Fl - Glul"'.. 15DEC92 29DEC92
21290 15 15 0 A.... . - 1at Fl . Floor & Vallcovwf. 7.1A1193 27 MI9J
22420 10 10 0 Ar.. . - 2nd Fl . floor Prep 10EC92 14DEC92
22440 10 10 0 ArM . - 2nd Fl . Doors & .,.fU.. . lnat.ll 15OEC92 29DEC92 "
22490 5 , 0 A.... . - 2nd Fl . Door .......... 2IJA119S 3f093 ~'
Z2500 5 5 0 Ar.. . - 2nd Fl - Gl.ll", 2IJAII93 3FEI93
22510 5 5 . ArM . - 2nd Fl . Acouatlcal Tile 2IJA1193 3f093
22520 5 ~ 0 A.... . - 2nd Fl - Floor & UlllCCNWtngs 11 F09J 17F093
31120 10 10 . ArM C - 1st Fl . cw.fc TIle 25SEP92 8OCT92
31190 10 10 0 Ar.. C - 1at Fl - Floor Prep 1DEC92 14DEC92
31210 10 10 . A.... C - 1st Fl - Doors & .,.111.. 22DEC92 6.IM93
31250 5 5 0 ArM C - 1at Fl - ~t'cal Tile 2IJAII93 3F093 r '
31270 10 10 . ArM C - 1st Fl - Door ........ 2IJA1193 1GfEI9J r,-
31_ 10 10 0 Ar.. C - 1st Fl - Glul", 2IJA193 10f093
31290 10 10 0 A.... C - 1st Fl -"Floor Covering 11 FEI93 24fE893 ';:
32420 10 10 0 ArM C - 2nd Fl . lnataU Doors & Grill.. 14JAII9J 2'1.1A1193 '
32450 10 10 . ,- ArM C - 2nd Fl - ....l... floors 1aFE193 3MAI93
32490 10 10 . Area C - 2nd Fl -' Othef-' ,loorlng 4MAl93 11MA1t93
43040 15 15 . ArM D - 1st Fl - Celt furniture 2OAUG92 101EP92
43045 10 10 > 0 A.... D - 2nd Fl . Cell fUmt ture ;. 11SEP92 241EP92 "
43400 20 . ' 0 Area D - Cell Doors &.ooot Fr_ - , 160CT92 121OV92 : '
2D
43410 10 10 ,,' 0 . , Area D . Grout Cen Door ,~ .. both floors 131OV92 ~,,' ( ~ "
43440 5 5 -' 0 Area 0 - Doors & ern l..'~ both floors 14JAII9J ZCWlII93
...................................................................................................................................
IIonrOe C<<.I\ty, norl. PlIMAVERA PltOJECT PLAllNU Monroe ~ty Detentfon 'actl Ity
I UUCl91' 'II DATI
..T DATI 190EC91 lUll 10. SO Monroe Cow\ty Detention Fecit fty START DATI ,.W
16:21 t.
SC1IED ItEPORT . line skip by ectfvlty code DATA DATI 18N01191 PAGE 10. U
..... ..... .... .... . ... .....-.... ................................................ .......- ........ ......... ........ .....
ACTIYln ORIG REM ACTIVITY DESCRIPTIOl SCHEDULED ~"'. '
ID M M I STAlT ,.11111
..-.. -.... .... .... . --. .........- ........................--...................... .......- ........ ........ ........ .....
"nl..... : ,--. .... -
43410 15 15 0 ArM D . CaMwort . botll floors 4FE193 24FE19S f'~
43490 15 1S . Ar.. D . Gluf", . both floors 4FEI93 24FE19S C'~ ~' (,
43500 1S 1S 0 ArM D . Door Hardwe... . both floors 4FE193 24FE19S
43510 15 15 . ArM D . Accgtlcal Cetll", . both floors 4FE193 Z4FE893
43520 10 10 0 Ar.. D . Floor prep . both floors 4FEB93 17fU9J
43530 10 10 . Ar.. D . Floor coverl", . both floors 25FEI93 10MAR93
53040 15 15 0 Area E . 1st Fl . Cell furniture 2OCT92 22OCT92
53045 10 10 0 Ar.. E . 2nd Fl . Cell Furniture 230CT92 5IIH92
53400 20 20 0 Ar.. E . Cell Doors & Door Fr_ . both Floors 2OIOV92 21DEC92
53410 10 10 0 ArM E . Grout Cell Door fr_ . both floors 22DEC92 6.Wt9S
53440 5 , 1>> Ar.. E . DoorS & Grin.. - both floors 1IFE193 24FE193
S3480 15 15 0 Area E . Casework . both floors 111Wt93 311N93
53490 15 15 0 Ar.. E . stulng . both floors 111Wt93 311N93
53500 15 15 0 Ar.. E . Door llardwer. ,- both floors 11MAR93 311N93
53510 15 15 0 Ar.. E . Accgtfcal Cefl f", . both floors 111Wt93 31MAR93
( 53520 10 10 0 Ar.. E . floor prep . both floors 11MAR93 24MA193
53530 10 10 0 ArM E . Floor cowrfne . botll floors 1AP1l93 14AP193
Electrical Equt~t
20350 15 15 0 Area' . svttchgeer . ~.ta P.O. 13JA1192 31 JAII92
20360 5 5 0 ArM' . SWftcheur . Select Vendor 3FE192 7FEI92
20370 1 1 0 ArM . . SWltchteer . I.- PO 10FE192 10fE192
20380 70 70 0 Area' . SWftc:heMr . 'lib & DeiWI' 11FEI92 ,..m
20400 15 15 0 ArM . . ...... &en . ......t. '.0. 13.lA1192 3UA1192
20410 5 5 0 Ar.. . . ...... .. . Select Vendor 3fE192 7FEI92
20420 1 1 0 ArM . . ...... &en . lnue PO 10FE192 10FE192
20430 120 120 0 Ar.. . . ...... &en . 'lib & Del fWl' 11FE192 29JUL92
20450 15 15 0 Aree . . tI'I Syst_ . Generat. p.o. 13JA1192 31.1AII92
20460 5 5 0 Ar.. . . tI'I Syst_ . Select Vendor 3FE192 7FEI92
20470 1 1 0 Aree' . tI'I Syst_ ..Issue PO 10FE192 10fE192
20410 145 145 0 ArM . . tI'I Syst. . FIIb & Del iver 11 FEm 2SEP92
Mec:Mnfcal Equfpltnt
20200 15 15 0 Area . . cur - Generate ,.0. 13JAN92 31.lA1192
20210 5 5 0 Area . . cur ....lect Vendor 3FEB92 7FEI92
20220 1 1 . Area' . cur . Issue PO 10FEB92 10FE892
20230 70 70 0 Ar.. . . cur . .flb & Del Iv., 11 FEB92 ,..m
20250 15 15 0 Area' . Chillers. o.nerat. P.o. 13JA1192 31.M1192
20260 5 , . ArM . . Chi n.... . Select Vendor 3FEB92 7fEI92
20270 1 1 0 ArM . . Chin.... . lnue PO 10fEB92 1Oft192
20280 110 110.. 0 ArM . . Chfll.... - FIIb' Oellver 11FEB92 15.IUL92
20300 15 15 0 Area' . AW . Generate P.O. 13.1A1192 31JAN92
20310 5 5 0 ArM . . AHU . Select Vendor 3FQ92 .7FE192
"- 20320 1 1 . 0 Aree . . AIlI . I ssue fIG.. " ". ~ ? 10FE192 10fE192 ..
20330 eo eo! 0 ArM . . AHU . Fib , Del I WI" 11FEI92 2.UI92 -
..~....................................._..........................................................................................
~ Cculty, 'lorl.
"JMAVERA PIO.IIC'f PI.AMI
Monroe eou,ty Detention lecUltr
IEJUT DATE 19OEC91 lUll 10. 50
16:21
SCHED IlEPClIT . line Hip by activity code
Monroe Cou'Ity Detention Fec III ty
START DATI 1AUGt1 FIN DATI
(
DATA DATE 18N0\/91 PAGE 10.
12
..... ..... .... .... . ... .......... ...................................-............ ........ ..-..... .--..... .....-.. .....
ACTIVln ORIG REM ,< ACTIVln DEICIIPTlOI SC1IEDUlED
ID DUI M I IT AlT Fill.. I', " >
..... ..... .... .... . ... .......... ...........................-.......-........-.-. ........ ..--...- .....-.. ..---... .....
MedlInlcal Equl...,t ,
22290 10 10 . Area . . 2nd Fl . II'IICt all 2OCT92 150CT92 - ~t >>,
32300 10 10 0 1 A.... C . 2nd Fl . COOl.. 'loon ....Inat.ll 160CT92 29OCT92 ?' .0,-', '
32310 10 10 0 A.... C . 2nd '1 .cure,loon ' 3OOCT92 121Ol192
32320 10 10 0 ArM C . 2nd n . COOL.. '....1'" 1311GY92 ~ ,J,;,
32330 10 10 0 Area C . 2nd Fl . COOL.. "'ls ..Inatlll 1oeC92 14OEC92
32340 5 , 0 Area C . 2nd Fl .' Cooler Yrl. .out 15DfC92 Z1DEC92
40500 15 " . ArM D . AIlJ'. . Generate P.O. 13JAN92 31.1A1192
40510 5 5 0 ArM D . AIlJ's . Select Yendor 3FE892 7FEI92
40520 1 1 0 Area D . AIIU'. . Jsaue PO lOFE892 10FE192
40530 40 40 0 Area D . AIIU'. . ,., DeliWI' " FEI92 WIl92
50500 " 15 0 Area E . AIIU'. . lIner.te '.0. 13JA1192 31.1A1192
50510 , , 0 ArM E . AIlJ's . Select v.ndor 3FE192 7FEI92
50520 1 1 . Area E . AIIU's . I... PO 10FE192 10FE892
50530 40 40 0 Area E . AIIU'. . ,. & DeliWI' 11FE192 WR92
Lantry Equl...,t
20500 15 " 0 ArM . . L..ay E",lp . Gener.te '.0. 13JAN92 3UAl192 t'
. ~,'
20510 5 , 0 Area . . L..ay EcJ.rlp . Select Vendor 3FE892 7FEI92 " ,
20520 5 5 0 Area . . L..ay Equip. lsaue PO 10FE892 14FE192
20530 15 15 0 Area . . L..ay Equip . F. & DelIver 17FE192 15.u192
KItchen Equl~
30100 25 25 0 Area C . Kitchen Equfp . Generate P.O. 13JAN92 14FE192
30110 5 5 0 Area C . Kitchen Equip. Staff IwI_ 17FE192 21 FEI92
3011' 5 , 0 ArM C . KItchen Equfp . Allard '.0. ZitFE192 2IFEI92
30120 50 50 0 Area C . Kitchen Equip . .. Ir..l.. 2MAI92 Mlm
30130 15 15 0 ArM C . Kitchen .... . AlE 1..,1_ & AFProval 11MAm 1&W92
30140 35 35 . ArM C . Kitchen Equip. fnl Coord WI oth.... 2.UI92 21....92
30150 150 150 . Area C . KItchen Equip. ,. & Delfver 2.UI92 5.IM93
32150 5 , 0 ArM C . 2nd Fl . InataU ICltdlen IoocIa 23OCT92 29OCT92
32410 5 5 0 ArM C . 2nd Fl . ICltdlln Equl~ Trl.-out 25MAI93 311tAR93
Set Equt s-ent .
m10 10 10 0 Ar.. . . 2nd Fl . Set an' E",Is-ent 13AUG92 26MJG92
22220 10 10 0 Ar.. . . 2nd Fl . Set C2lfller Equl~ ; 13AUG92 26MJG92
22230 10 10 . ArM . . 2nd Fl . Set AlII EqulpMnt 13AUG92 26MJ892
22240 10 10 0 ArM . . 2nd Fl . Set ....tc:htMr . . 13AUG92 2MUG92
22250 10 10 0 Area . . 2nd Fl. Set' .....eencv Genentor 13AUG92 26MJG92 ~-
22260 10 10 0 Area . . 2nd Fl . Set lJIIlyst_ ' 3SEP92 17SEP92
22210 10 ;0 0 Area . . 2nd Fl . Set LanIry Equi...,t 13AUG92 26MJG92
32460 15 .15 0 Area C . 2nd Fl . Set Kitchen Equl~ Wl93 2Wl9J
42050 5 5 0 Area D . 2nd Fl . let AlII'. - D1 and D2 2OMJG92 26MJliI92 _,;
52050 , 5 0 Area E . 2nd Fl . let .... · E1 and E2 2OCT92 IOCT92 ~'
Mech..lcal Syst_ Cbeclt.out & "lancing .,,'. '!':li:'\
71005 20 20 0 A.... A . Mec:h Syat. TI,,'ft & Inltl.l IVAC TU ' 14JA1193 10fU93 ' ~;>.
72005 20 20 0 Area 8 . Mec:h Syat_ 'TI..ln & Inltfal WAC TU " FEI93 1l1Wt9J : .
".
...................................................................................................................................
Monroe Cculty Detention 'acll Ity
~ Cowlty, Florlde PRIMAVERA PROJECT PLANMEl
lCT DATE 19OEC91 IMI NO. 50 Monroe Ccgrty Detention FacUlty
16:21
ICIIED REPORT. line Iltlp by ectlvlty code
START DATI 1AUQ91 '111 DATI 1.IUL93.
DATA DATE 1811OV91 PAGe 10. 13
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ........ .....
ACTIVITY ORIG IEJI ACTIVITY OESCRIPTlOI SCHEDUlED
ID M DUI I START FlIIS"
..... ..... .... .... . ... .......... ................................................ ........ ........ ........ ..-..... .....
I
Rechenlcal Syat_ Chec:k.out & lalMCI",
73005 2D 20 0 Area D . RedlSyst_ Tle.ln & Inltl.l IVAC TU 25FE193 24MR93
74005 2D 20 0 Area C . RedlSyst_ Tla.ln & Initial WAC TU 18MAR93 1W193
7'5005 2D 2D 0 Area E . Redl Syst_ Tle.ln & Initial WAC TII 1APR93 28API93
75500 10 10 0 IVAC Syst_ . Ftnal Tnt & lal....:e 29APm 12Mm
75600 10 10 0 Building 0 & .. Syst_ . VerificatIon / Checltout 13MA Y93 26MY93
77010 10 10 0 ChlorInate & FlUlh Drinking Water linN 29APR93 12Mm
Electrical/Security Device Verification
71020 15 15 0 Ar.. A - Point to Point DevIce VerifIcatIon 14JAN93 3FE193
72010 15 15 0 Area' . Point to.polnt Device VerifIcatIon 11FEI93 3MAR93
73010 15 15 0 Ar.. D . PoInt to Point Device Verification 25FEB93 17MAR93
74010 15 15 0 A.... C . Point to Point Devlca Verification 18MAR93 7APR93
75010 " 15 0 Area E . Point to Point Device VerifIcation 1APR93 21APR93
FI... Protection Syst_ Flnel Test
757'00 2D 20 0 Fire Protection Syst. . Flnel T..Un. 29APR93 26Mm
r ",Ity Syst_ Operational Tests
( 71010 5 5 0 Instl Security .Syst_ CClIIIpJter Equip a Ctl R~ 11FE193 17FE193
71015 , 5 0 load Security Syst_ PrOllr_ 1SFE193 24FE193
71025 15 15 0 Ar.. A . Saarlty Syst_ Oper.tlonal T..ts 25FE193 11MA193
no15 15 15 0 A.... . . Sacurlty Syst. Operational T..ts 4MAR93 24IWt93
7301' 15 15 0 Ar.. D . Sacurlty Syst_ OperatIonal T..ts 18MAR93 1APR93
74015 15 15 0 Area C . Security Syat_ Oper.tlonal Tests WR93 2IAPR93
7501 , 15 15 0 Ar.. E . Security Syat_ Operational Tests 22APR93 12MAm
Security Syst_ Intllr.tad Tnts
76000 10 10 0 security Syst_ . Integrated T..t (st.rt) 13MAm 26MY93
76010 20 20 0 security Syst. . Integr.ted Teat (c~l) 27MAY93 24JUN93
Flnel P\n:h
77050 15 " 0 AlE lulldlng CclIIpOnInt PwdIout 27MAY93 17 JUN93
Otntr/ M o.onstrltlona\
aoooo , 5 0 rNnerlAE. D....tr.tlona & Final Wllkthru 25JUN93 1.lUl93
(
~
I
SECTION 00135
PROPOSAL FORM
Bid Package No. 35
Carpentry & General Works
BID TO
MONROE COUNTY PURCHASING DEPARTMENT
PUBLIC SERVICE BUILDING, CROSS WING,
ROOM 002, 5100 COLLEGE ROAD, STOCK
ISLAND, KEY WEST, FLORIDA 33040
BID FROM:
R.J.C. & Associates, Inc.
5611 Dewey Street
Hollywood,
Florida 33023
The undersigned, having carefully examined the Work and Drawings,
Specifications, Proposal, and Addenda thereto and other Contract
Documents for the construction of:
Bid Package No. 35 Carpentry
and having carefully examined the site where the Work is to be
performed, having become familiar with all local conditions
including labor affecting the cost thereof, and having
familiarized himself with material availability, Federal, state,
and Local laws, ordinances, rules and regulations affecting
performance of the Work, does hereby propose to furnish all
labor; mechanics, superintendents, tools, material, equipment,
transportation services, engineering support, and all incidentals
necessary to perform and complete said Work and work incidental
hereto, in a workman-like manner, in conformance with said
Drawings, Specifications, and other Contract Documents including
Addenda issued thereto.
The undersigned further certifies that he has personally
inspected the actual location of where the Work is to be
performed, together with the local sources of supply and that he
understands the conditions under which the Work is to be
performed. The successful bidder shall assume the risk of any
and all costs and delays arising from the existence of any
subsurface or other latent physical condition which could be
reasonably anticipated by reference to documentary information
provided and made available, and from inspection and examination
of the site.
05/19/92
CARPENTRY PROPOSAL FORM (ADD. 12)
00135- 1
:2IiTh.L LLb..
-
...---- ,~~=
.,-- , J.\. ". ~ A.
_.....1....- __........~tj
RIC & ASSOCIATES, IHe
5611 DEWEY STREET
HOl t YWOO[l, FLORIDA 33023
PROPO~A:r,. FORM
Lt.1JTIlL Sum Base Bid
Note:
Items are 'furnish and install' where
as specified in the Scope of Work.
1. Mobilization
2 . Bond
3. Sales Tax
4 . Submittals
5. Section 05810 Expansion Joint Cover Assemblies
6. Section 06100 Rough carpentry
7. Section 06200 Finish carpentry
-(.,
"
~
,
,.
\:
';, '>,
applicable,
$ 5,000.00
$ 2,980.00
$ 11,840.00
$ 2,500.00
$ 25,956.00
$ 5,040.00_
$ 144,810.00
7A. s~ctiori OBj06t~&~i~1
8. Section 10100 Chalkboards and Tackboards
9. Section 10160 Solid Plastic Toilet Partitions
$ 8,820.00
$ 14,629.00
$
$ 2,924.00
$ 24,570.00
$ 2,218.00
$ 2,662.00
$ 30,154.00
$ 1,512.00
$ 6,615.00
$
10. Section 1027~eess Flooring
11. ,section 10350 Flagpole
12. Section 10500 Steel Lockers
13. Section 10520 Fire Extinguisher Cabinets
14. Section 10550 Postal Specialties
15. section 10800 Toilet Accessories
16. Section 10900 Miscellaneous Specialties
17. Section 11480 Athletic Equipment
tB--.--&eet ion 1.3 09-e-RtJ d i tJ t i oR-P-l:'~t-eeHen
05/19/92
CARPENTRY PROPOSAL FORM (ADD. 12)
00135 - 2
. --..- ,.,.-.....=~~~
f
19. Miscellaneous Items (use if work items
cannot be categorized in items 1-18 above)
$_N.C..
20. Allowance - (240) manhours
6,480.00
21.
Final Cleaning
$
$
4,000.00
TOTAL BASE BID, Items 1-21, (figures)
$ 329,800.00
----------
----------
TOTAL BASE BID, (words) Tht:"ee Hundt:"ed Twenty-Nine Thousand
Eight Hundced -------------------------------------00/100
DOLLARS
22. Owner option 35-01: Zone F Carpentry
~/ DEDUCT (Circle One)
-------------------------------------------00/100
DOLLARS
Owner Option 35-01, (figures)
$ 39,000.00
----------
----------
Owner option 35-01, (words)
Thit:"ty Nine Thousand ---------------
05/19/92
CARPENTRY PROPOSAL FORM (ADD. 12)
00135 - 3
I acknowledge receipt of Addenda No. (s)
1 thcough 12 C
I have included pages 1-4 of the Proposal Form X , and attached
the required Bid Security X , Lobbying and Conflict of Interest
Clause X , Sworn Statement of Public Entity crimes_~, and Non-
Collusion Affidavit
~heck mark items above, as ~~eminde~ that th~are included~
Mailing Address:
R.J.C. & Associates, Inc.
5611 Dewey Stceet
Hollywood, Flocida 33023
/
Phone Number:
Date: 8 June 1992
Signed:
pcesident
witness:
l6f~
~ (Seal)
00135 - 4
05/19/92
CARPENTRY PROPOSAL FORM (ADD. 12)
THE AMERICAN INSTITUTE OF ARCHITECTS
I
RECEIVED
AlA Document A310
"PR ? 7 1(lqi
rl,f.C It ASSOflATFS, 'NI
Bid Bond
KNOW All MEN BY THESE PRESENTS,
that we
'H~,. insert full n.m~ .nd .dd,~" 0' l~g.1 titl~ of Conl,octo')
R.J.C. & Associates, Inc.
as Principal, hereinafter called the Principal, and
IH~,~ ins~'t full n.m~ and .dd,~" or l~g.1 I;II~ of Su'~tyl
Employers Insurance of Wausau
a corporation duly orgcll1!zcd under the laws of the State of Wisconsin
as Surety, hereinafter called the Surety, are held and firmly bound unto
(Here in~ert full name .and .1dd,e5~ or legoll .,tle of Owner)
Board of County Commissioners of Monroe County, Florida
as Obligee, hereinafter called the Obligee, in the sum of
-----------Five Percent of Amount Bid------------------ Dollars ($ 5% ),
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by
these presents.
WHEREAS, the Principal has submitted a bid for
(H~r(' insert full name, .lddrelil) and description of projectl
Bid Package No. 35 - Carpentry
N~w Detention Facility on Stock Island, Key West, Florida
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract
with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding
or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt
payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter
such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty
hereof between the amount specified in said bid and such larger amount for which the Obligee may in good faith contract
with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain
in full force and effect.
Signed and sealed this
25th
day of
April
19 92
_fUHI"I' ;\l\ (~\H(,i/(
(Wit ess)
I
Associates Inc.
(Principal)
~
mt/e) .
(Seal)
IJffll1/ t/ iWd'r.d
, (Witness)
ura e of Wausau
(Surety)
~'~G.1~
mt/e)
Jack E. Fowler, Attorney-in-Fact
(Seal)
AlA DOCUMENT A310 . 810 BOND. ^'^ e . FEBRU^RY 1970 ED . THE ^MERIC^N
INSTITUTE OF ^RCHITECTS, 1735 N,Y. ^VE" NW., WMHINGTON, D. C. 20006
1
~
z
o
w
a:
Z
a:
lii
Cl.
Cl.
<(
r-
o
z
(f)
w
o
o
r-
z
w
2
w
,,~
Z(f)
- (f)
7:;:
D.~
~~
a:
o
~
LL
o
a:
w
~
o
Cl.
o
:J
~
<(
r-
o
z
~
~
I
r-
EMPlOYERS INSURANCE OF WAUSAlJ A Mutual Company
POWER OF ATTORNEY
(FOR BID BONDS ONLY)
KNOW ALL MEN BY THESE PHESENTS:
That the EMPLOYERS INSURANCE OF WAUSAI J A Mutual ('ompan.v. a corporation dul~' organizpd and l'xisting undf'r
the laws of the State of Wisconsin, and having its principal officI' in thp Cit.\' of \Vausau, ('ount~' of l\brathon, State of
Wisconsin, has made, constituted and appointed. and does h~' thpsp pn'sents makp, constitutl' and appoint ____.,.__
CHARLES J. NIELSON~ JACK E~-EOWLER~ MARY c. ACEVFS~ JOHN S. HARRIS
its true and lawful a ttorn Py in-fact, with full powpr and authorit~, Iwrehy conferred in its name, plan' and stead, to pxecute.
seal. acknowledge and deliver ANY AND ALL Bill BONDS OR WRITTEN DOCUMENTS INVOLVIN(; Bill GITARAN
TEES OR IN THE NATURE THEREAFTER __ _ _ _ _ _ _ __
and to hind the corporation thprehy as full~' and to thl' saml' extl'nt as if such honds Werl' sigl1f'd hy thl' President, sealed with
the corporate seal of the corporation and dul.\' attpsted hy its spnetarv hpn.h~' ratif~'ing and confirming all that the said
attorney-in-fact may do in the premises.
This power of attorney is granted pursuant to thp following rpsolution adopted hy thp Board of Dirpctors of said Compan.v at a
meeting duly called and hpld on thp IRth day of May, 197:l, which rpsolution is still in effpct:
"RESOLVED, that the Presidpnt and any Vice Presir/pnt - eJpctivl' or appointivp - of EMPLOYEHS INSURANCE OF
W AUSAU A Mutual Company hI', and that ench of them herphv is, authorized to execute powers of nttorney qualifying
the attorney nnmpd in the given powpr ofattornl'~' to expcutl' on Iwhalf of EMPLOYERS INSURANCE OF W AUSAI) A
Mutual Company bonds, undertakings and all contrncts of sllrl'lyship; and that any sperptary' or assistant seCTptary he,
and that each or any of thpm hereby is, authorized to attest the eXl'clltion of an.v such powpr of nttorney'. and to nhach
thereto the spal of EMPLOYERS INSURANCE OF WAITSAU A Mlltllal Company"
"FURTHER RESOLVED, thnt tll(' signatuH's ofsllch officers and Ill(' sl'al of EMPLOYERS INSUHANCE OF W Al rSAtI
A Mutual Company may be nffixed to any such powpr of attorrll'Y or to an~' cf'rtificate relating IIll'reto hy facsimile, and
any such power of attorney or certificntp bparing such facsimile signatun's and facsimill' spal shallllP valid and binding
upon the EMPLOYERS INSURANCE OF W AUSAU A Mutual Compr.n~' whl'n so affixpd and in tIll' futtHP with resppct
to any bond. undertaking or contract of suretyship to which it is attachpd"
IN WITNESS WHEREOF, EMPLOYERS INSUHANCE OF W AIISAI J A Mutual Company has caused these presents to bp
signed hy the senior vice president and attestcd hy its assistant secretary. and its corporate seal to he hereto affixed this IS T day
of ~<::~____.. 19__9.1
,~-;-:.:~~-
d':'o"o",;~ FMPLOYFRS INSURANCE OF WAUSAU A Mutual Company
\\SE'Al)/ R ~ ~,~~~
x:'. ;;,,~, ~
Au.., A l~ Rill n. wym:
R, J, Besteman ", Assistant Secretary
STATE OF WISCONSIN )
) ss.
COUN1Y OF MARATHON)
Executive Vice President
On this 1 S T day of MARrH , 19 .elL , hefore l11e personally came
- Bill D. Wymore . to me known. who heing hy me duly sworn, did depose
and say that he is an executive vice president of the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company. the corporation descrihed in
and which executed the above instrument; that he knows the seal of said corporation: that the seal affixed to said instrument is such corporate
seal and that it was so affixed by order of the Hoard of Directors of said corporation and that he signed his name thereto hy like order.
IN WITNESS WHEREOF. I have hereunto set my hand and affixed my official seal the day and year herein first ahove written.
~.a.~
Patricia A. Kleman
NOTARY PUBLIC
STATE OF WISCONSIN
MY COMMISSION EXPIRES MAY 29, 1994
CERTIFICATE
Notary Public
/::~~.~';'.'.;".'.f{~;;\
{~/ 1I~'.~~ y)
'~~:~::,;,:;~~li
STATE OF WISCONSIN
CITYOFWAUSAU )ss
COUNTY OF MARATHON)
I. the undersigned, assistant secretary of EMPLOYEHS INSURANCE OF WAUSAU A Mutual Companv. a Wisconsin
corporation, do hereby certify that the foregoing and attached power of attorney. WHICH Ml1STCONT AIN'A V ALlDAT-
ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK. remains in full force and has not heen
rpvoked; and furthermore that the resolution of the Hoard of Dirpctors spt forth in the powpr of attorney is still in force.
Signed and sealed in the City of Wausau, Marathon County, State of Wisconsin, this 25 th
of April ___ . 19_9~. A. d 4-L
t-;--:::-""'~ ~
{<<::.~~:.;;~ R. J, Besteman / l' '
\,~SEAl ~I
~~I
day
Assistant Secretary
NOTE: IF YOU Ht\VE ANY QUESTIONS REGARIHNG THE VALIDITY OR WORlHNG OF THIS POWER OF
ATTOHNE\. CALL TOLL FREE (ROO) R2fl-lflf11 <IN WISCONSIN. CALL (ROO) 472-004\}
RJ5-4n2-1 990
.~
l'jl
,
".
~
"
11
LOBBYING AND CONFLICT Of~R'L~!<ES'L CLAUS~
S~9~N ST~TEMENT U~DER ORDINANCE NO. 010-1990
MON-FJ2~~OUNT~~_LXLORI DA
" RJC & ASSOCIATES, I INC.
(Company)
ff
If warrants that it has not employed, retained or otherwise had
act on its behalf any former County officer or employee subject
to the prohibition of section 2 of Ordinance No. 010-1990 or any
County officer or employee in violation of section J of Ordinance
No. 010-1990. For breach or violation of this provision the
County may, in its discretion, terminate this contract without
liability and may also, in its discretion, deduct from the
contract or purchase price, or otherwise recover, the full anount
of any fee, commission, percentage, gift, or consid ration paid
to the former County officer or em 'lee".
Date:
STATE OF
FLORIDA
COUNTY OF
,
BROWARD
PERSONALLY APPEARED BEFORE
J. TAYLOR who,
his/her signature (name of
provided above on this 23
HE, the undersigned authority, RICHARD
after first being sworn by me, affixed
individual signing) in the space '
day of ~_, 1992-.
~~~~
NOTARY PUBLIC
Hy commlSSlon explres:
PAMELA FRAZIER McRAE
My Comm. Exp. 5-13-94
Bonded Thru SeMc:e Ins. Co.
07/25/91 LOBBYING AND CONFLICT OF INTEREST CLAUSE
00425 - 1
,-' :.,~ ....
.._......'---~----,..,..,..-
--> ~!-~_.'.' ~~..::. :..'}~.~~.~'.'_~~'-t~J~:~~~~~~.:~~~;fr{c.~~~'~~~'..~~T~~~'''~!?!.~~~~~f_
--
.
.
,tigJ2 .::~r;gJcj~\,l'~l..SJJ~\Jj i cJ~~I_ iJ:~
"
I , RICHARD J. TAYLOR
according to law on my o~th,
and say that;
__ of the city of HOLLYWOOD
and under penalty of perjury, depose
1. ) I am RTCHARf)~. 'PAYLOR of the firm of
& ASSOCIATES, INC. , the bidder r:laking the Proposed
project described in the notice for calling for bids for
COUNTY DETENTION CENTE~ and that I executed the said proposal
full authority to do so;
RJC
for the
MONROE
Hi'.::h
2.) the pr~ces in this bid have been arrived at
independently without collusion, consultation, communication or
agreement for the purpose of restricting competition, as to any
matter relating to such proces with any other bidder or with any
competitor;
J.) unless otherwise required by law, the prlces which have
been quoted in this bid have not been knowingly disclosed by the
bidder and will not knowingly be disclosed by the bidder and will
not be knowingly disclosed by the bidder prior to bid opening,
directly or indirectly, to any other bidder or to any competitor;
and
4.) no attempt has been made or will be made by the bidder
to induce any other person, partnership or corporation to submit,
or not to submit, a bid for the purpose of restricting
competition;
5. )
correct,
upon the
a'.varding
the statements contained in this affidavit are true and
and made with full knowledge that Monroe County relies
truth of the statements contai ed in this affidavit in
contracts for said project.
STATE OF
COUNTY OF
FLORIDA
BROWARD
PERSONALLY APPEARED BEFORE ME, the undersigned authority, _
RICHARD J. TAYLOR Vlho, after first being SI-lOrn by me,
(name of individual signing)
affixed his/her signature in the space provided above on this
23 ________ day of APRIL I932~
..,......~ ~~R-;~~tc'7l~
(~,.@.. PAMElA FRAZIEIl MeftAE
Hy commission explres: :.: f'\JBUC e My Camm. Exp. 6-13-94
\~ ott: Bonded Thru ServIce Ins. Co.
......?!: f'"
11/20/91
NON-COLLUSION AFFIDAVIT
00430 - 1
... ' _.::~i\Qc"!f""~'.''''!;~'' ~.?~~~~"",~:il7~~~L"~":.'~'~"l'y"""""lI~,,,,:-=-t'!,.~~i""V!':~~:"'1t1I~ ~:'!:';f"\r~'!"~,""""~'?"i":JI..'?ft~~..,.~~:.:."",,,."'{~~, ~~c'":":"'~
-t
"
..
,
SWORN STATEMENT PURSUANT TO SECTION 287.133(3) (a),
FLORIDA ~T~TYTEQ, ON PUBLIC ENTITY CRIMES
THIS FORM MUST BE SIGNED AND SWORN TO IN THE PRESENCE O? A NOTARY
PUBLIC OR OTHER OFFICIAL AUTHORIZED TO ADMINISTER OATHS.
1. This sworn statement is submitted to:
MONROE COUNTY PURCHASING DEPARTMENT
[print name of the public entity]
-,
by RICHARD J. TAYLOR, PRESIDENT
[print individual's name and title]
for RJC & ASSOCIATES, INC.
[print name of entity submitting sworn statement)
vlhose business address is 5611 DEWEY STREET, HOLLYWOOD, FL 33023
Employer Identification Number
(If the entity has no
Number of the individual
) .
and (if applicable) its Federal
(FEIN) is_ 59-1867103
FEIN, include the Social Securit:i
signing this sworn statement:
2.
I understand that a "publ ic ent i ty cr ime" a s de: ined in
paragraph 287.133 (1) (g), Florida Statutes, means a ';iolation
of any state or federal law by a person with respect to and
directly related to the transaction of bus iness ',.;i th any
public entity or with an agency or political subdi~ision of
any other state or of the united States, including, but not
limited to, any bid or contract for goods or services to be
provided to any public entity or an agency or political
subdivision of any other st.ate or of the united States and
involving antitrust, fraud, theft, bribery, collusion,
racketeering, conspiracy, or material misrepresentation.
3. I understand that "convicted" or "conviction" as defined In
Paragraph 287.133(1) (b), Florida Sta~utes, means a finding of
guilt or a conviction of a public entity crime, viith or
without an adjudication of guilt, in any federal or state
trial court of record relating to charges brought by
indictment or information after July 1, 1989, as a result of
a jury verdict, nonjury trial, or entry of a plea of guilty or
nolo contendere.
4. I understand that an "affiliate" as defined In Paragraph
287.133 (1) (a), Florida Statutes, means:
03/02/92
PUBLIC ENTITY CRIMES (ADD. 6)
00420 - 1
'~~'~'\lrlr;jf~,~~,~;.....
*'Tl"'~~ -1ft..' "'";"~?\;4;_"'.ITl,~""'l.~~r:.....I.;.t~,tI,.~\l~~"
5.
1.
A predecessor or successor of a person convicted of a
public entity crime: or
An entity under the control of any natural person who is
active in the management of the entity and who has been
convicted of a public entity crime. The term "affiliate"
includes those off icers, directors , executives, partners,
shareholders, employees, members, and agents '.,;ho are
active in the management of an affiliate. The ownership
by one person of shares constituting a controlling
interest in another person, or a pooling of equip~ent or
income among persons when not for fair market value under
an arm's length agreement, shall be a prima facie case
that one person controls another person. A person ',.;ho
knowingly enters into a joint venture with a person who
has been convicted of a public entity crime in Florida
during the preceding 36 months shall be considered an
affiliate.
2.
I understand that a "person" as defined in Paragraph
287.133(1) (e), Florida statutes, means any natural person or
entity organized under the laws of any state or of the united
states with the legal power to enter into a binding contract
and which bids or applies to bid on contracts for the
provision of goods or services let by a public entity, or
which otherwise transacts or applies to transact business with
a public entity. The term "Person'! includes those officers,
directors, executives, partners, shareholders, employees,
members, and agents who are active in management of an entity.
6. Based on information and belief, the statement whibh I have
marked below is true in relation to the entity submitting this
sworn statement. [indicate which statement applies.]
X Neittler the entity submitting this sworn statement, nor
any officers, directors, executives, partners, shareholders,
employees, members, or agents who are active in the manage~ent
of the entity, nor any affiliate of the entity has been
charged with and convicted of a public entity crime subsequent
to July I, 1989.
__ The entity submitting this S\'iorn statement, or one or
more of its officers, directors, executives, partners,
shareholders, employees, members, or agents who are active in
the management of the entity, or an affiliate of the entity
has b~en charged with and convicted of a public entity crime
subsequent to July I, 1989.
The entity submitting this sworn statement, or one or
.
(I
03/02/92
.
PUBLIC ENTITY CRIMES (ADD. 6)
00420 - 2
~ 'of' " . /'" _,'. lJJ.....J~..~:'t).~I,:.~,~..'I.<~,.M..l' I,..~.~~.l... \""..~'~ ~. .
/';'
,)
(.
1 ~'
gf
~:::.
r~ ..
~~ ..."
r
.
.
more of its officers, directors, executives, partne~s,
shareholders, employees, members, or agents who are active in
the management of the entity, or an affiliate of the entity
has been charged v!ith and convicted of a public entity criffie
subsequent to July I, 1989. Hm.,rever there has been a
subsequent proceeding before a Hearing Officer of the State of
F lor ida, Di'v is ion of Admini stra t i ve Hear ings and the F ina 1
Order entered by the Hearing Officer determined that it was
not in the public interest to place the entity submitting this
sworn statement on the convicted vendor list. [attach a COp!
of the final order]
I UNDERSTAND THAT 'THE SUBHISSION OF THIS FORH TO THE COiiTR..;CTIHG
OFFICER FOR THE PUBLIC ENTITY IDENTIFIED IN PARAGRAPH 1 (ONE) ABOVE
IS FOR THAT PUBLIC ENTITY ONLY AND, THAT THIS FORM IS VALID THROuGH
DECEMBER 31 OF THE CALENDAR YEAR IN WHICH IT IS FILED. I ALSO
UNDERSTAND THAT I AN REQUIEED TO INFORl1 THE PUBLIC ENTITY PRIOR TO
ENTERING INTO A CONTR1\CT IN EXCESS OF THE THRESHOLD AHOUNT PROVIDED
IN SECTION 287.017, FLOR_IDA STATUTES FO~CATEGORY TWO F !I.NY CHANGE
IN THE INFORMATION CONTAINED IN THIS rfoRM.
.... J
[Signatu\e1
Da te : k I
\
STATE OF
FLORIDA
COUNTY OF
BROWARD
PERSONALLY APPEARED BEFORE ME, the undersigned authority,
RICHARD J. TAYLOR
[name of individual signing]
who, after first being sworn by me,
affixed his/her signature in the space provided above on this
23
day of
APRIL , 19 92
___~~~~ Yl/a&r.
NOTARY PUBL'I:C
Form PUR 7068 (Rev.
~--
04/10/9
My commission expires:
PUBLIC ENTITY CRIMES (ADD. 6)
00420 - 3
03/02/92
:,. c J'~-"=_"" c'._."'!:L,',. '.", _.,. ..... . c. . .".c-:..." ...
_ ' ~;t . . '"._ ,,':.~. '.
~. ._\ ....-~..:, .. '~~"J!~_~~~~~~~~~~~~f~~~~~~~:~~~_~~~~
SECTION 00137
PROPOSAL FORM
Bid package No. 37
Access Floo'ring, Resilient Flooring & Carpet
j
BID TO
MONROE COUNTY PURCHASING DEPARTMENT
PUBLIC SERVICE BUILDING, CROSS WING,
ROOM 002, 5100 COLLEGE ROAD, STOCK
ISLAND, KEY WEST, FLORIDA 33040
BID FROM:
RJC & ASSOCIATES, INC.
~l DEWEY STREET
HOLLYWOOD, FL 33023
(305) 987~8301 FAX (305) 985-8796
The undersigned, having carefully examined the Work and Drawings,
Specifications, Proposal, and Addenda thereto and other Contract
Documents for the construction of:
Bid Package No. 37 Access Flooring, Resilient Flooring & Carpet
and having carefully examined the site where the Work is to be
performed, having become familiar with all local conditions
including labor affecting the cost thereof, and having
familiarized himself with material availability, Federal, State,
and Local laws, ordinances, rules and regulations affecting
performance of the Work, does her~by propose to furnish all
labor, mechanics, superintendents, tools, material, equipment,
transportation services, engineering support, and all incidentals
necessary to perform and complete said Work and work incidental
hereto, in a workman-like manner, in conformance with said
Drawings, Specifications, and other Contract Documents including
Addenda issued thereto.
The undersigned further certifies that he has personally
inspected the actual loc~tion of where the Work is to be
performed, together with the local sources of supply and that he
understands the conditions under which the Work is to be
performed. The successful bidder shall assume the risk of any
and all costs and delays arising from the existence of any
subsurface or other latent physical condition which could be
reasonably ant~cipated by reference to documentary information
provided and made available, and from inspection and examination
of the site.
03/11/92 RESILIENT FLOORING PROPOSAL FORM (ADD. 8)
00137 - 1
~.i.==-::..__.
flIG 8. AS.SOCIATES. INC.
5511 DlWFY STREET
. jOllY/Non!, FLORIDA 33023
LumIL.l)um ease_Bid
PROPOSAL_Y_9RM
t
Note:
Items are 'furnish and install' where
as specified in the Scope of Work.
applicable,
I
$ 3, OCJtJ . _ I
$ I, )D O. ---
.
$ 31 tJoo . .-:- i
I
I
$ I,OOCJ.--
,
$ , 1., 5"'08. -
,
$ q 2., ta1 . --
.
$ Z2.j oot!>. -
$ -r9-
l
1. Hobilization
2. Bond
3. Sales Tax
4. Submittals
5. Access Flooring
6. Resilient' Flooring
7. Carpet
8.
Miscellaneous Items (use if work items
cannot be categorized in items 1-7 above)
...,
TOTAL BASE BID, Items 1-8, (figures)
$ 135 O~.-
====~=====
TOTAL BASE BID, (~ords)
_Ql-.l~ H~"'i)R.--'=~ AN~ ""HIQ.~ 1="lvF; -IHa.s~/~o
DOLL~RS
9. OWllS!X--9'p~;ion 37-01:. Zone F Resilient Flooring & Carpet
~ DEDUCT (Circle One)
Owner Option 37-01/ (figures)
$201oOD. -
====-========
O'lmer Option 37-01/ (words) Ilu~Nry THouc:;.A,.JO
DOLLARS
03/11/92 RESILIENT FLOORING PROPOSAL FOru1 (ADD. 8)
00137 - 2
,~ '
..
\ .
,
"
il
. ,
"'\ ~
\
\
(
I J
~ I.
I
I
.
l
.
i
\
\
A,: > .
't:~;~... ~
~, 'j,
I acknow ledge rece ipt of Addenda No. (s) 0"-' ~ 1T-n..'-1.. \ S
I have included pages 1-3 of the Proposal Form____, and attached
the required Bid Security , Lobbying and Conflict of Interest
Clause , swor,n Statement of Public Entity Crimes and Non-
Collusion Affida'vit
(Chgck m.ar~ i t~rn~_above_-,-_~!:!_~min_der tha t theY-2re included.)
Mailing Address:
Phone Number:
Date:
4/23/92
Signed:
i
\
RJC & ASSOCIATES, INC.
5611 DEWEY STREET
HOLLYWOOD, FL 33023
(305) 987-8301 FAX (305) 985-8796
J. TAYLOR
(Name)
witness:
03/11/92 RESILIENT FLOORING PROPOSAL FORM (ADD. 8)
00137 - 3
THE AMERICAN INSTITUTE OF ARCHITECTS
I
RECEIVEr)
AlA Document A310
^PR ~ 7 19CJ/
PJ.c. & ASSOCIATES. iNf
Bid Bond
KNOW All MEN BY THESE PRESENTS,
that we
IHe-re inSf"rt full n,me and ~ddress or IIPg,' title of (ontuctor)
R.J.C. & Associates, Inc.
as Principal, hereinafter called the Principal, and
IHt"re in\~rt full n,me and ..dd'E"H or leg,1 title of SUff"tyJ
Employers Insurance of Wausau
a corporation duly organ!~cd iJjider the laws of the State of Wisconsin
as Surety, hereinafter called the Surety, are held and firmly bound unto
(Here InSf'" full iiolme and address or le-g.J1 tille of Ownrr)
Board of County Commissioners of Monroe County, Florida
as Obligee, hereinafter called the Obligee, in the sum of
-----------Five Percent of Amount Bid------------------ Dollars ($ 5% ),
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by
these presents.
WHErUAS, the Principal has submitted a bid for
(Here insert lull name, address and description of project)
Bid Package No. 37 - Access Flooring, Resilient Flooring and Carpet
Ne~ Detention Facility on Stock Island, Key West, Florida
NOW, THE R EF 0 R E, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract
with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding
or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt
payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter
such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty
hereof between the amount specified in said bid and such larger lImount for which the Obligee may in good faith contract
with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain
in full force and effecl.
Signed and sealed this
25th
day of
April
19 92
Inc.
- r Iii 11 R I , \ I ) dill I I f ,It
(Withess)
(Seal)
,), ')'
fr/dj /" I //'1t f.(jf
(Witness)
I 10, s Insurance of Wausau
(Surety)
. ~~ f. '1-~
(Title) I
Jack E. Fowler, Attorney-in-Fact
(Seal)
AlA DOCUM(NT A31' . BID BOND. ^'^ ~. FEBRU^RY 1970 ED . THE ^MERIC^N
INSTITUTE OF ^RCHITECT5, 1735 N.Y, ^VE" NW" WMHlNGTON, O. C. 20006
1
~
z
o
w
cr
Z
cr
~
a...
a...
<(
I-
a
z
en
w
a
o
I-
Z
w
2
w
C)~
Zt0
- en
.......~. -
III '[
Q..LL
~~
cr
a
~
LL
a
a:
w
~
a
a...
o
:::::i
~
<(
I-
a
z
~
~
I
I-
EMPlOYERS INSURANCE OF WAUSAlJ A Mutual Company
POWER OF ATTOHNEY
(FOR BID BONDS ONLY)
KNOW ALL MEN BY THESE PRESENTS:
That thf' EMPLOYERS INSURANCE OF WA! 'SAil A l\1utual ('ompan~', a corporation dul.\' organizNI and existing unner
thp laws of thp Statp of Wisconsin, and having its principal officf' in till' Citv of Wausau. Count\' of Marathon, Statf' of
Wisconsin, has madp, constitutf'd and appointf'd, and dol'S 1J\' thf'se prf'sl'nts makl'. constitute and appoint .,..__...~.
---.C.HARLES J. NIELSON.. JACK.. E. FOWL ER.. ~R.LL........AC.E\l.Es.........JQHN S. HARR I S
its trul' and lawful attornl'y.in.fact, with full pOWl'r and authorit~, hl'rl'hy confl'rrf'd in its twml', placf' and stf'ad, to I'Xl'cutl',
seal, acknowledge and delivl'r ANY AND ALL BIll BONIlS (>R WRITTEN DOCllMENTS INVOIXIN(; Bill (;UARAN.
TEES OR IN THE NATtTRE TI/EREAF1'ER _ _ . _ _ _ __
and to bind the corporation thereby as full~' and to tI", sam!' I'xtl'nt as if such honds WI'rf' signpd hy till' l'rpsidpnt, seall'd with
the corporate spa] of thl' corporation and dulv attf'stpo h~' its sl'crP(ar~' Ill'n'h~' ratif~'ing and confirming all that thl' said
attorney.in.fact may do in the premises.
This power of attorney is granted pursuant to tlw following resolution adoptl'd h~' the Roard of Directors of said Compan~' at a
meeting duly caliI'd and hl'ld on thl' lRth day of May, 197:\, which rpsolution is still in pffect:
"RESOLVED, that the Prl'sident and any Vice Presidpnt - l'll'ctivl' or appointivl' - of EMPLOYERS INSURANCE OF
W AlJSAU A Mutual Company be, and that each of them hl'rl'hy is. authorizl'd to I'xecute powers of attorney qualifying
the aUorney named in thl' givl'n power of aUornl'Y to l',(l'cutl' on I'l'half of EMPLOYERS INSURANCE OF WAlJSAU A
Mutual Company honds, undertakings and all contracts of surl'tyship: and that any sl'crptar~' or assistant secretary bl',
and that pach or any of thl'm herl'by is, authorizl'd to aUl'st thl' l'xpcution of any such powpr of attornp~', and to altach
therl'to thl' sl'al of EMPLOYERS INSURANCE OF WAllSAU A Mutual Compnny:'
"FURTI/ER RESOLVED, that tlll'signaturps of such officl'rs and till' spal of EMPLOYERS INSUHANCE OF W AllSAll
A Mutual Company may bl' affixl'd to an,\' such powpr of aUOrlll'V or to any' cprtificatl' rplating thl'rpto Irv facsimile, and
any such power of attorney or cl'rtificatl' hl'aring such f,lcsimill' signaturl's and facsimill' spa! shall hl' valid [lnd hinding
upon the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company whpn so affixl'rl anrl in thl' futurp with rpspl'ct
to any bond. undertaking or contract of surf'lyship to which it is attach"d."
IN WITNESS WHEHEOF. EMPLOYEHS INSUHANCE OF W AUSAU A Mutual Compnn~' has causpd tlll'sl' prl'sl'nts to bl'
signed h\' the senior vice president nnn nttested hv its nssistant secretary, and its corporate seal to he hereto affixed this __~ day
of ____~t18RCIj~______, 19----.91
l::'~~;'-"~::"~
~i roll'Olf." t~
\' SE"AL // ~ '-
'\':'.. ~" Ry ~
AU"t ,A: l~ 1';11 D. W,":
R. J, Besleman ,/ Assistant Secretary
FMPLOYFRS INSURANCE OF WAUSAU A Mutual Compnny
~'~~
Executive Vice President
STATE OF WISCONSIN )
) sS.
COUNTY OF MARATHON)
On this 1 S T day llf MARrH , 19 .9..L . hefore me personnlly carne
Bill D. Wymore , 10 me known, who heing hy me duly sworn. did depose
and sny lhal he is an execulive vice president of the El\lPLOYERS INSURANCE OF WAUSAU A Mutual Company. the corporation descrihed in
and which executed thc ahove instrument: that he knows the seal of said corporation; thaI the seal affixed 10 said instrument is such corporate
seal and that il was so al"fixed hy order of the Rllard of Direclors of said corporation and thaI he signed his nmne Ihereto hy like order.
IN WITNESS WHEREOF, I have hereunto set my hand and nffixed my official seal the dav and year herein first ahove written.
~.t1.,~
Patricia A. Kleman
NOTARY PUBLIC
STATE OF WISCONSIN
MY COMMISSION EXPIRES MAY 29, 1994
CERTIFICATE
Notary Public
_.<<;~~~~'.':t'~{~~;\
l~~?;;~~:~~!; j
STATE OF WISCONSIN
CITY OF WAlJSAlI ) ss
COUNTY OF MARATHON)
I. thl.' undl.'rsigned, assistant sl.'cretary of EMPLOYERS INSURANCE OF WAUSAlI A Mutual Company. a Wisconsin
corporation, do hl.'rebycertify that the foregoing and attachl'd powerofattornl'Y, WHICH MUST CO NT AIN'A V ALlDAT-
ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK, rl'mains in full force and has not bl.'en
revoked; and furthl.'rmorl' that the rl'solution of thp Roard of Dirl'ctors set forth in the powpr of attornl'Y is still in forpp.
Siltned and sealed in the City of Wausau. Marathon County. Statl' of Wisconsin, this __~~.
of April . Hl~. A. d ~ ~
/ 'j<< ~
R, J. Besteman
day
Assistant Secretary
NOTE: IF 'lOll HAVE ANY QUESTIONS HE(;AHIHN(~ THE VALIDITY OH WORIHNG OF TillS POWER OF
ATTORNEY, CALL TOLL FREE (ROO) ~2hI6f)lliN WISCONSiN, CALL (R0014720041) , ,
RI.'i.4222.1 990
~
;J ~
r
--
.
;.-'
}:oO'JB.Y HIGj\ND CONfLICT_OF Hi:t~"Rr:.:ST_~J:JMLE:"E
Bji91UL~1'A T~tl.~li'!'._.lLNJ.l"EB__Q R PLHI\BQP,-.J.LQ_"--. --.9.1 0 - 122. Q
tiQliRQ~_c::'9In{,L'( ,.JJ~9.BJJ2~
"
RJC & ASSOCIATES, INC.
"
(Company)
11 ~;2rrants that it has not employed, retair1ed or otllerwise 112d
act on i t.s behC1l f any [ ormer Coun t '{ of f icer or emp levee subj ect.
to the prohibition of ::;c,ct.ion :~ or Ordinance 1'10.010--1990 or C\ny
Count~y officer or emplo'./e0 in vlolClU.on of section J of Ordin,.'~ncl::
Po. 010-1990. For brcclch or violitLic'n of this provision the
County may, in l.ts discr.ctioll, terminate t.his c:ont.r,:.ct. ,-,'ithout
1 .i 2 b i 1 i t Y an cl m i1 y a 1:~ () , i nil: :; d i 0:: C r p t ion, ,:1 e cl u c t f rem the
con tract or pureh:1 ,:;? pr ice, cr ot hcr'-';.i s c rl?covcr, th e full ClnClU r,t
of any [0"", commi.~;sion, percC'nLJcjc, qift., or consicler.i1tion p,~id
tn the former county of r j ,'0' or e,," o\'''e'<~ure)__'''___~''_
STATE OF __FLoRIQ!L_.______
COUNTY OF
BROWARD
PERSOn,\LLY APPE1,PED BEFORE l-lS, thc~ undersi{Jnecl i:\uthority, RlCHARn_.
_~'!',~~{LOR.._.___.._m._..___ ',.;ho, after first bei.nq SHorn by me, affixed
hisjht"r siqnature (name of inclivic1uill signing) in the ~3pace
prov ided obove on t~h i s~~_.._. day 0 f_.l\.J::'..RIJ~___._m_n ' J 9.92..
:f~~Cffl~...._,__..
NOTAPY PUBLIC
PH comml.SSlon explres:
PAMELA FRAZIER McRAE
My Comm. up, 6-13-94
Bonded ThnJ Serva Ins. eo,
07/25/91
LOBBYIJ1G AND CONFLICT OF IN'I'EPE's1' CLAUSE
00<',25 - 1
f.:'~~~."'Pfl~" ...." ..... .~.~._r.~~f~:~-..,__:~~. ..~.;'....:.y;'}'7"T.,. .";7.~.i'Tn;r"r~.-:".'....--i~tl.~.:'.,;,y~'.~H:,'";~f'~~,~' I :--lI~~'~~-::""rl'''-'-f''
. ;--,!., ,"-1 ,.;.. .,,_;' ", .~.,;......~.:.":"....,."r-~.:!..I.-:.T:'!'ll''P,~:r~ '~""i...~:m~;.nr.,..',
~
--
.
H9_I"l_~_~ gJ l1J~i9_n__l\f U._cl c.yj t:
I, RICHARD J. TAYLOH_______ of U1e city of ___HO~YW~~______
according to la;..; on my oatJ" and under penalty of perjury, depose
and Si",y tha t;
1 . ) I a m __~J~[~R!?__~"__'!'f\J'LQ~__~________ 0 f the f j nn 0 [ _RJ~______
_~_A~OCIATES, INC._______, the bic1cler making the Proposal for the
pro j e c t de s c r i be din the not ice for call in g for bid s for N-';;~J1QNJ~QE__
~~UNT~ DETENr!'};O~__F~~~_J;.;rT'p,nd th,-:'\t I executed the said proposal \,;i ~_h
full authority to do so;
2. ) the pr ices in this bid have bE'en arr i ved at
independently without collusion, consultation, commtlnjcation or
agreement for t.he p~lrpose of restr ictinq competi tion, as to un}'
matter relating to such proces with any other bidder or with al1Y
competitor;
3.) unless otherdise required by law, the prices 'dhich have
been quoted in th is bid ba ve not_ been knov! ing 11' eli sc losed by the>
bidder and 'd ill not kno1,./ i ng 1 y be disc losed by the bidder and I,; i lJ
not be knO'.,lingly disclosed by t.he bidder prior to bid openinq,
directly or indirectly, to any other bidder or to any competitor;
and
4.) no attempt has been made or 'dill be made by the bidder
to induce any other person, partnership or corporation to submit,
or not. to submit, a bid [or ~-_he P'Xl:-pO~,C of restrictin,!
competition;
5. )
correct,
upon the
a'darding
the statements contained in this
and made with full knowledge 1t
truth of the statements conta'n d
contracts for said project.
affidavit are true and
/Vlonroe County relics
in_hZid~nt "'~
ratu e of Bidder)
STATE OF
COUNTY OF
FLORIDA
-------- --_.__._~-_._-_.'--'---'------
BROWARD
RIL 3, 1992
._--_._-------_._-------~---
DATE
PERSONALLY APPEARED BEFORE ME, the undersigned authority,
RI<~ttARQ__~ TA1.LOR______________.___. 'd h 0 , aft e r fir s t be in q s \--to r n by 1" e ,
(name of individual signing)
affixed hiS/her signature in the space provided above on this
_~~________ day of ___ APIli~___________, 19__9-_2-.
_~ ~4Ln~~/rz~
NOTP~~IC
My commJ.SSlon
PAMELA fRAZIER McRAE
My Comm. Exp. 6-13-94
Bonded Tllru ServIce Ins. 00.
11/20/91
NON-COLLUSION AFFIDAVIT
004]0 - 1
. :j,l!"."'i!'~~~~.~~~~lf~~~~,'r,~':U......'""Yl"ii,l'..~.,.:-,..".,., '. "l;f' 17':-:~'i~l~,"':"_~....~:-:'tfr-":'.~,.: ';'"'~f"'.~VN,".r::-\": ~...:ow:-~"'G=-'''i'1 ~"".i,~~':;""~.qr~:,:, ":~_' ,~.". ~':?r. 7r'-':..~~~...,~~:r~~~i~I!...:tt~
~
t
.
~
SWORN STATEMENT PURSUANT TO SECTION 287.133 (3) (a) /
FLORIDA STA-'ITJTES / ON PUBLIC ENTI'l'Y CRIl1ES
,.
~
THIS FORM MUST BE SIGNED AND SWORN TO IN THE PRESENCE O? A NOTARY
PUBLIC OR OTHER OFFICIAL AUTHORIZED TO AmUNISTER OATES.
1. This sworn statement is submitted to:
NEW MONROE COUNTY DETENTION FACILITY
[print name of the public entity)
i;<
by
RICHARD J. TAYLOR, PRESIDENT
[print individual's name and title]
for RJC & ASSOCIATES, INC. ______
[print name of entity submitting sworn statement}
whose business address 1S
HOLLYWOOD, FL 33023
~~----
and (if applicable) its
(FEIN) is 59-1867103
FEIN, include the 50,-::ia1 Sccl:rit}'
signing this sworn statement:
5611 DEWEY STREET,
Federa 1 Emp lcyer I den t i fica t iOi: ?iu::;t::er
(If the entity has no
Number of the individual
) .
.
2 .
I un d erst and t hat a " pub lie en tit Y c 2.- i me" a s de fin e din
Pare,graph 287.133 (1) (g), Il.Qrid~J!,j'l.tjdtes, means a '/io::'e..tion
of any state or federe..l law by a person with respe=t to and
cl i rect 11' re 1 a ted to the transact ion 0 f bus i :.e ss ',.; i '-:, c. ny
public entity or with an agency or political subdivisi6n of
any other state or of th~ United states, including, but not
li~ited to, any bid or contract for goods or services to be
provided to any public entity or an agency or political
subcli v is ion of any other state or of the Un i ted States and
involving antitrust, fraud, theft, bribery, collusion,
racketeering, conspiracy, or material misrepresentation.
3. I understand that "convicted" or "conviction" as defined i..
Paragraph 287.133 (1) (b), f~orida--"C;tat1d.tes, mea..s a. finding of
g u i 1 tor a con vi c t ion 0 f a pub 1 ice n tit l' c rim e , ;'i i the r
Hit.hout an adjudication of guilt, In any federa] or state
trial court of record relating to charges brought by
indictment or infor~ation after July 1, 1989, as a result of
a jury verdict, nonjury trial, o~ entry of a ple~ of guilty or
nolo contendere.
4 .
I unc1e'rstand
287.133(1) (a),
that an "affiliate" as defined
Florida statute~, means:
in
Pa!"2ql.-2.ph
.
03/02/92
PUBLIC ENTITY CRIMES (ADD. G)
G0420 - 1
,;.J~w...j5] -; An;.':.~:~~:~.~~-' ':;~~.~'. "?::r:::.::":~~;-rt.'~ ~~;;[ ~':~.;.~ I~~':~7.~ ~: ~;:.~::-~..-::::_:: ~:'-., _'.~ --;;;:.7~~:':~-':7~~~= '.7:~:~:::/:-,~?_~7:r:.:',:;::i :::;?::~~;7:;;S::", ': 1f;;T-~~'"1;~r:~:.~~7;;::;,~.~~~~~j
,
J
I
1
5.
RJC & !iSSOCtAlES, INC.
56! 1 DElVfY STREET
HOLLYWOOD, n.OIlHlA 33023
1.
A predecessor or successor of a person convicted of a
public entity crime: or
An entity under the control of any natural person ~ho is
active in the management of the entity and who has been
convicted of a public: entity crime. The t~erm "affili2te"
includes those officers, directors, executives, partners,
shareho Jders, employees, mer:bers, and agen t S "';:10 are
active in the management of an affiliate. The c~~ershi2
by one person of shares constituting a cantroiling
interest in another person, or a pooling of equi~nent or
income a~ons persons when not for fair market va~ue under
all a~mls le~gttl agreement, sh~ll be a prima fa=ie case
t h 2.. ton e per son con t r.- 0 1 S 2. not h e:- pel'" S 0 rl . .~ De :- S 0 T1 \-: II e,
knowingly e~ters into a joint venture with a pers~n ~hc
has been convicted of a public entity crime in Florida
dUl'ing the ;:receding 36 months shall be cons_~dereci a:t
affiliate.
tit
2.
I understand that a "person" as defined in ?aragc.Gph
2 8 7 . 1 J J ( 1) (e), :" 1.9);" i d a_3 tat u_t e s, r,', e a n san y n a t u r i1 1 P e :::- son 0:-
en tit y 0 r 9 ani zed II n de r the 1 a','; s 0 f a li ~r S tat e 0 r 0 f the (j nit e ;~:
states with the legal power to enter into a binding contract
and which bids or applies to bid on contracts ~u~ the
provision of CjGc:1s cr services let by a public e;--!tic.y, c:-
~;hich ot_her;'Jise tr2nsacts or applies to transact busi~sss ~~.~t~~
a pub lie en tit), . The t e::: n:1 11 P e 2__ S 0 i1 !l i Y': C 1 u des tho s e c f f '. c'= "l,':3 ,
directcrs, executives, partne~s, shareholders, e~plcyee5,
members, and age n t s \,:ho are act i ve in Pc. nagement. c fan en t i t~. .
~
t;::~
,~~
6. Based on information and belief, the statement which I have
marked below is true in relation to the entity submitting this
sworn statement. [indicate which statement applies.]
03/02/92
'.
:...
~"'~~'I\'..~l;:,~'_~'='~;J.'Y""" ;'.' ,. ..".....~ --, .1'-.= -~.:-"'..",..,....I'Iii"l<'f".... ~
~...~ ~: ,.,.,._'~fT);i ~;.' , ...1'~, Ie;! ,:r\(I;:J:j~'~'iJ",_ -':';'~?;f'!.; ,,/ Jl'~~~~.. :~i~~~r'!~; #if'{:;.~~'~~,~.::.Jii~;..I;~_..7:.~~;t"$~.~~'t-.~:-f~~ti-:P~\.- ;~';'~'I'Zf1~J~i~~~~~~*r~.;~,;1~
.-X__ He i tiler t:--,e ent i ty submi tt ing th i s s'.!orn sta tellent, nor
any officers, di:-ectors, executives, partners, shareholders,
employees, members, or agents ~ho are active in the n2~agerre~t
of the entity, nor any affiliate of the entity has !-:ee:i
charged with and convicted of a public entity crimes~tsequent
to July 1, 1989.
The entity subrr;itting this S','io-::n statement, or ene or
more of its officers, directors, executives, partners,
shareholders, eDployees, members, or agents who are ective i~
the management of the entity, or en affiliate of the entity
has been cha:-ged with and convicted of a public eGtity cr12e
subsequent to July 1, 1989.
The entity submitting this sworn statement, er cne::: 0:-
I
Pl.:SLIC
ENTITY C~nt-1ES (?,DD. 6)
0')420 - 2
~ }
:-,:i
:. ,
:'-i
~<
1.<
;:~
~
RJC 3. ASSOCIATES. INC
5611 OrWEY SlRf.El
HOlLYWOOD rtORIlJi'. 13023
~
more of its officers, directors, executives, pa~t~e~s
shareholders, employees, me~be~s, O~ agents wt18 are 2cti~.:e i~
the management of the entity, or an affiliate of t~e e~city
has bee n c h Cl. ::: 9 e d vI i t h and con v i c t e ci 0 f a pub 1 ice n t i. ::. y' c::: i::-. ,2
5 II b s e (1 u e n t t 0 J u 1 y 1 , 1 9 8 9 . E 0 \',1 eve r the 1:.- e r. 2. :; t E: e ~1 .J.
subse:::lue:!t proceeding befo:::e a Heari:!; Officer of tr:e State of
F 1 or ida, D i'v- is ion of i'.dmin is t:::a t ive Hear ings and ::;,e F i.na J
Order entered by the Hearing Officer determined t~a::' i::. was
not ill the pllblic interes~ to place t!1G entity SUbDi~~i~g ~his
s~orn state~ent en the CC~~!~cted ve~dor lj_st. [a~t2=~ a CCC\:
of the final order]
..
.,
f
t'f
I UllDEPST.'\UO TI!.\T 'I;n:: SUBlUSSIOU OF THIS FORr1 TO THE CC:;-=-?.\CT:!:~;G
OFFICt:R FOR THE PL;rL~C FtiTIT"{ ID:::tHIF'ISD III P.~..p.AGH!\r:I 1 (':::::::: .".:=C;i:=:
IS fOR TfIt\T pueu:c ;:~,:'ITTi Ot:LY ;,tlD,-~'::-".T TE:l.S FOPJ.l IS '::..::"=-~'~';:~.:::"::::::-:
DECS;,:t3ER 31 Oi" THE C!\L>:~;ml\R YEi'.? Pi i'!:lICE IT IS FILS]. .:',::":;0
U,mERST;'..~m TEi'-.T I .'\?; RLQUIF.FD TO HiI"OR;'! THE PUBLIC EIIT:;:~":- ??:::O? TO
ENTERIJlG INTO P. Cm';T?.~,CT IN EXCESS OF TEE TnRESHOLD l..HOl'::'.:' r?O-':I~ED
IN SECTIOU 287.017, n=0RJDL_.$T.?l.TU'I' __ FO? c.".T:::GORY
IN THE INFOPJ'IJ1.TIOtl conTAINED IN ,-!I' f'Ol
fib
1992-_~__
STATE OF FLORIDA
t.
COUNTY OF BROWARD
PERSONALLY APP2.11.::<.ED BEFORE: 112, the \..:ndersigned aut:1C:!:ity,
RICHARD J. TAYLOR
[name of individual signing]
v,ho, a:ter first being s';,'c~n ty Tle,
affixed his/her signature in the space provided above on t~is
~3____day of _~RIL 19 92
~~~i3LJ7~
My commission explres:
PAMELA FRAZIEPt McRAE
My Comm. Exp. 6.13.94
Bonded Thru Service Ins. Co.
;
Form PUR 7068 (Rev. 04/10/91)
.
03/02/92
Pu3LIC ENTITY CRH:~S (ADD. 6)
00420 - 3
~
~..:, 'f;:'" "~:~"";7,~~of",~:,,,'..-r-:~.'\~;--'11;';:;I """1 "f-~~~i1~r~;":~7,- ~:.~ ',~,.l."," 1~~;~~,i7!Y7'';''~-:~;y7~.''''''!'r!7':'''7,~'t~7'~~7T,,'
. '~-:-':TT!~~"P:.~'3.'.<~~~l''T.''G';
o
SECTION 00139
PROPOSAL FORM
Bid Package No. 39
Acoustical ceilings
: i
BID TO MONROE COUNTY PURCHASING DEPARTMENT
PUBLIC SERVICE BUILDING, CROSS WING,
ROOM 002, 5100 COLLEGE ROAD, STOCK
ISLAND, KEY WEST, FLORIDA 33040
BID FROM: RJC & ASSOCIATES, INC.
5611 DEWEY STREET
HOLLYWOOD, FL 33023
(305) 987-8301 FAX (305) 985-8796
The undersigned, having carefully examined the Work and Drawings,
specifications, Proposal, and Addenda thereto and other Contract
Documents for the construction of:
Bid Package No. 39, Acoustical Ceilings
;
\
'."
and having carefully examined the site where the Work is to be
performed, having become familiar with all local conditions
including labor affecting the cost thereof, and having
familiarized himself with material availability, Federal, State,
and Local laws, ordinances, rules and regulations affecting
performance of the Work, does hereby propose to furnish all
labor, mechanics, superintendents, tools, material, equipment,
t~ansportation services, engineering support, and all incidentals
necessary to perform and complete said Work and work incidental
hereto, in a workman-like manner, in conformance with said
Drawings, Specifications, and other Contract Documents including
Addenda issued thereto.
The undersigned further certifies that he .has personally
inspected the actual location of where the Work is to be
performed, together with the local sources of supply and that he
understands the conditions under which the Work is to be
performed. The successful bidder shall assume the risk of any
and all costs and delays arising from the existence of any
subsurface or other latent physical condition which could be
reasonably anticipated by reference to documentary information
provided and made available, and from inspection and examination
of the site.
(
03/11/92
ACOUSTICAL PROPOSAL FORM (ADD. 8)
00139 - 1
RJC & ASSOCIATES. INC
5611 DEWEY STREET
llOLLYWOOD. FLORIDA 330?3
i
I
~
,;
,
~
"
PROPOSAL FORM
Lump Sum Base Bid
,1
j
1
Note:
Items are 'furnish and install' where applicable,
as specified in the Scope of Work.
6.
Miscellaneous Items (use if work items
cannot be categorized in items 1-5 above)
$ 3,000.-
$ \. OOD. -
.
$ I. 5o~.-
.
$ Soo.-
$ "'I, 4d". -
$ ~
.i
1.
Mobilization:
J
2. Bond
"
3. Sales Tax
4. Submittals
5. Acoustical Ceilings
:!
.1
TOTAL BASE BID, Items 1-5, (figures)
:=~~~~~~::,;-
;
.1
TOTAL BASE BID, (words) ::::>e\lG,...,+) 'Fl VE
'.i
7 . Owner option 39-01: Zone F Acoustical Ceilinqs
@)/ DEDUCT (circle One)
Owner Option 39-01, (figures)
:J:-l:~~~~~
Owner option 39-01, (words) ~\~\E:E:,...a. ~~4:11'\'~~
DOLLARS
03/11/92
ACOUSTICAL PROPOSAL FOm1 (ADD. 8)
00139 - 2
, '
"
f7\
\~-~::)
~--
'1
A
'..0..
'j
:i
1
I
.;
"
-j
,
I
;.;
-1
,
,
.1
" {--
, \'
, -,
.'i
.1
.' j
,
"j
1
:t
1
.~ !
: I
" J
.: I
. I
!
/"
I acknowledge receipt of Addenda No. (s) D t-.\" ---r14~~ ,~
I have included pages 1-3 of the Proposal Form ,and attached
the required Bid Security____, Lobbying and Conflict of Interest
clause ,Sworn Statement of Public Entity Crimes ,and Non-
Collusion Affidavit____
I
(Check mark items above, as a reminder that they are included.)
Mailing Address:
RJC & ASSOCIATES, INC.
5611 DEWEY STREET
HOLLY~OOD, FL 33023
Phone Number:
(305) 987-8301
FAX (305) 985-8796
Date: 4/28/92
Signed:
PRESIDENT
witness:
(T~
le'A;;.
/ (Seal)
03/11/92
ACOUSTICAL PROPOSAL FORM (ADD. 8)
00139 - 3
THE AMERICAN INSTITUTE OF ARCHITECTS
I
AlA Document A310
Bid Bond
KNOW ALL MEN BY THESE PRESENTS,
R.J.C. & ASSOCIATES, INC.
that we
fH~re insert full n.ame and ,dd'e-S5 or legal ti,te of Contrictor)
as Principal, hereinafter called the Principal, and
Employers Insurance of Wausau
(Here inserl full name and address or lega' litle of Su,ety)
Wisconsin
a corporation duly orgim!~cd under the laws of the State of
as Surety, hereinafter called the Surety, are held and firmly bound unto
(Here IOserl full name and address 0' legal tille of Owne,)
Board of County Commissioners of Monroe County, Florida
as Obligee, hereinafter called the Obligee, in the sum of
---------Fi ve Percent of Amount Bid---------- Dollars ($ ---5%--- l,
for the payment of which sum well and truly to be made, the said Principal and the said Surety, bind
ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by
these presents.
WHEREAS, the Principal has submitted a bid for
(He,e insert full name, add,ess and description of projecll
NEW DETENTION FACILITY ON STOCK ISLAND, KEY WEST,
FLORIDA, BID PACKAGE 39 - ACOUSTICAL CEILINGS
NOW, THEREFORE, if the Obligee shall accept the bid of the Principal and the Principal shall enter into a Contract
with the Obligee in accordance with the terms of such bid, and give such bond or bonds as may be specified in the bidding
or Contract Documents with good and sufficient surety for the faithful performance of such Contract and for the prompt
payment of labor and material furnished in the prosecution thereof, or in the !!vent of the failure of the Principal to enter
such Contract and give such bond or bonds, if the Principal shall pay to the Obligee the difference not to exceed the penalty
hereof between the amount specified in said bid and such larger ilmount for which the Obligee may in good faith contrilct
with another party to perform the Work covered by said bid, then this obligation shall be null and void, otherwise to remain
in full force and effect
Signed and sealed this
1st
day of
May
19 92
(Witness)
(Seal)
/~))
I~ ~{el I: (tel (;t.fA
/ (Witness)
Wausau
(Seal)
AlA DOCUMENT All. . BID BONO. AlA ~ . FEBRUARY 1970 ED . THE AMERICAN
INSTITUTE OF ARCHITECTS, 173S N,Y. AVE" N.W" WASHINGTON, O. C 20006
1
:i
z
0
w
a:
Z
a:
Lfj
0..
0..
<{
~
0
z
(/)
w
0
0
~
z
w
2
w
C) ~
~
Z (/)
- en
OZ. I
C. .L.
~ >-
W
z
a:
0
~
LL
0
a:
w
~
0
0..
0
:i
~
<{
~
0
Z
~
~
I
~
EMPIOVERS INSURANCE OF WAUSAlJ A Mutual Company
POWER OF ATTORNEY
(FOR BID BONDS ONLY)
KNOW ALL MEN BY THESE PRESENTS:
That the EMPLOYERS INSURANCE OF WAt~SAU A Mutual Compan~', a corporation dul~. organized <lnd existing under
the laws of the St<lte of Wisconsin, and having its principal office in thp Cit~. of Wausau. Count~' of Marathon, State of
Wisconsin, has made, constituted and appointed, and does hv thpsp prpsents make, ronstitute and <lppoint ____.
CHARLES J. NIELSON, JACK E. FOWlER, MARY c. ACEVES, JOHN S. HARRIS
its true and lawful attorney-in-fact, with full power and authority hereby conferred in its name, place and stead, to execute.
seal, acknowledge and deliver ANY AND ALL HID HONDS OR WRITTEN DOCtJMENTS INVOLVING BID GUARAN-
TEES OR IN THE NATURE THEREAFTER _ _ _ _ _ _ _ _ _ _ _ _ __
and to bind the corporation thereby as fully and to the same extent as if such bonds were signed by the President, seah'd with
the corporate seal of the corporation and duly attested by its serretary hereb~' ratifying and confirming all that the said
attorney-in-fact may do in the premises.
This power of attorney is granted pursuant to the following resolution adopted b~' the Hoard of Directors of said Company at a
meeting duly called and held on the 18th day of May. J 97:3. which resolution is still in effect:
"RESOLVED. that the President and any Vice President - eledive or appointive - of EMPLOYF:RS INSURANCE OF
W AUSAU A Mutual Company be, and that each of them hereby is. authorized to execute powers of attorney qualifying
the attorney named in the given power of attorney to execute on behalf of EMPLOYERS INStJRANCF: OF W AUSAU A
Mutual Company bonds, undertakings and all contrarts of suretyship: "nd that any secretar~' or assistant secretary be.
and that each or any of them hereby is, authorized to attest the execution of any such power of attorney. and to attach
thereto the seal of EMPLOYERS INSURANCE OF WAUSAU A Mutual Company."
"FURTHER RESOLVED, that the signatures of such officers and the seal of EMPLOYERS INSURANCE OFWAUSAU
A Mutual Company may be affixed to any such power of attorney or to any certificate relating thereto by facsimile. and
any such power of attorney or cE'rti fica te bearing such facsimile signatures and facsimile seal shall be valid and binding
upon the EMPLOYERS INSURANCE OF W AUSAU A Mutual Company when so affixed and in thE' future with respect
to any bond, undertaking or contract of suretyship to which it is attached:'
IN WITNESS WHEREOF, EMPLOYERS INSURANCE OF W AtJSAU A Mutual Company has caused these presents to he
signed hy the senior vice president and attested hy its assistant secretary. and its corporate seal to he hereto affixed this 1ST day
of MARCH . 19--.9.1
r:~~~';'-";;::-"'..
I.. ~\
I: (Olll'0Ito41, t.\ ~
l. -'- '. .
\\ SEAli/ H '
~... :;1 y
AU,,,, ~ 1 ~ BOIl D. wym:
R. J. Besteman -" Assistant Secretary
EMPLOYERS INSURANCE OF WAUSAU A Mutual Company
~'~~
Executive Vice President
STATE OF WISCONSIN )
) ss.
COUNTY OF MARATHON)
On this 1 S T day of MARrH . 19 .9..L . hefore me personally came
Bill D, Wymore , to me known. who heing by me duly sworn. did depose
and say that he is an executive vice president of the EMPLOYERS INSURANCE OF WAUSAU A Mutual Company. the corporation described in
and which executed the ahove instrumeot; that he knows the seal of said corporation: thai the seal affixed to said instrument is such corporate
seal and that it was so affixed hy order of the Hoard of Directors of said corporation and that he signed his name thereto by like order.
IN WITNESS WHEREOF. I have hereunto set my hand and affixed my official seal the day and year herein first above written.
~a..~
Patricia A. Kleman
NOTARY PUBLIC
STATE OF WISCONSIN
MY COMMISSION EXPIRES MAY 29.1994
CERTIFICATE
Notary Public
/~~~~:;':~:':.!~-~;;\
(~:~~:.:~~i~~~~)
STATE OF WISCONSIN
CITY OF W AUSAU ) ss.
COUNTY OF MARATHDN )
I, the undersigned. assistant secretary of EMPLOYERS INSURANCF: OF WAUSAU A Mutual Company, a Wisconsin
corporation, do hereby certify that the foregoing and attached powerof attorney, WHICH MUST CONTAIN A V ALIDA T-
ING STATEMENT PRINTED IN THE MARGIN THEREOF IN RED INK, remains in full force and has not been
revoked; and furthermore that the resolution of the Board of Directors set forth in the power of attorney is still in force,
Signed and sealed in the City of Wausau, Marathon County, State of Wisconsin. this Is t
of May __ .19~? . A d ~L
.p~'i:: 'j ~
f'C'.:'~"'~ R. J. Besteman ;- ,
\ SEAL ,I
~, ,~I
day
Assistant Secretary
NOTE: IF YOU HAVE ANY QUESTIONS REGARDING THE VALIDITY OR WORDING OF THIS POWER OF
ATTORNEY, CALL TOLL FREE (800) R2h-lhhL (IN WISCONSIN. CALL (800) 472-0(41)
RI5-4222-1 990
l
:',}'
M
~. ,
).,
:,1
~
."'..
R'
. ;>t.
I)
1.
I)
;:-!_C}])J i J. ~_; G l~~~i__~_~_~I_~~-~_=~_-_~ ~_l~~_k~_l- ~; T Ll~~J::.) J_C j.J ~_\.:d~.,-- ~
S "li.!2JW S TAT E):(,1:l:L't.-_ll.t:_Q~E_QR DIN AN C E NO. 0 1 0 - 1 9 9 0
HONRQ~__COUNTY, FLORIDA
"
RJC & ASSOCIArES, INC.
(Company)
"
" ~arrants that it has not e~ployed, retained or othe~~ise had
act on its behalf any for~e~ Co~~ty officer or employee s~bject
to the prohibition of Section 2 of Ordinance ~o. 010-~990 o~ a~v
County ;fficer or e~?loyee i~ violation of section J of C~dina~~e
No. 010-1990. For b~each or violation of this provisio~ t~e
County may, in~its discretion, terminate this contract ~it~out
liability and may also, in its discretion, deduct fro~ the
contract or purchase price, cr other~:ise recover, ttle fc~l 2~c~~t
of any fee, commissio~, percentage, gift, or considera~ion aaid
to the former County 0= fieee c" "plcyee" /
Signature)
STATS Ot
FLORIDA
COUl'ITY O? _t1R<;MAlliL-----------
PERSONALLY APPEARED SE?OaE M~, the undersigned :authority,
RICHARD J. TA.YLQR ,,:ho, after first being SHorn by ,,'2, af:ixed
his/her signature (naDe of individual signing) in the s~a=e
provided above on this 28TH day of APRIL 19 92.
----- WnLI.. .../~~ ~(!&-.
NOTARY PUBLI
My co~rn~SSlon exp~res:
07/25/91
LOBBYHJG ;'_~;D COlifLICl' OF IN'!"'EEEST CLl-.USE
c' () :, 2 S - 1
~:.~__~:t!_ ~:_~~~ _~!d~:~~~.~~~~4~T~~ ~~fI~t~~'?"..~~;~~ ~/~}:'I~ ~~.~' ~';.'f~t::~ ~.. '?:'..~~}~:.,;...-~~:?!.:~'~~:.>.~":;?~~;.~.~F~~..r~~~.::~~!2~~~~: ~Jo:;~~ :~ :."::.5_~;'~?-'~~/
~'l
':".,.
"1
, ~
:'i
1~
~
~
~
t
(
!
"
.
j
i;
11
SWORN STATE~ENT UNDER ORD~NANCE NO. 010-1990
HO~~OE COUNTY, FLORIDA
RJC & ASSOCIA~ES, INC.
(COmpany)
I
" warrants that it has not e~ployed, retained or other~ise had
act on its behalf any forDer County officer or employee s~bject
to the prohibition of section 2 of Ordinance ~o. 010-1990 or a~y
County officer or e~?loyee i~ violation of Section J of Crdinance
No. 010-1990: ~or ~~each ~r viclat~on of t~is provisicn,tte
County may, In?lts Clscretlc~, cerrnlnate thIS contract ~lt~ou~
liability and may alse, in its discretion, deduct frc~ t~e
contract or purchase price, cr other~ise recover, the f~:l a~c~~t
of anv fee, commission, perce~t2ge, gift, or considera~io~ aaid
t t.;;, r- r m p y- CO" ,.., ~ -J 0 ~ f' i ,- -'" ,- 0 ~ ' D 1 C \' ""' e 11
o n_ 0 '._ ~..c" _u~-_ - ......' /
Signature)
11
11
IL 28, 1992
STi\TS Of'
FLORIDA
COUNTY OF __BROWARD
PERSO!.JALLY APPEARSJ S::::rO:?E HS, the unders gned ~2.uthor it::', ---
RICHARD J. TAY1QR ,,:ho, efter first be ng S'dorn b'l "e, af:i>:ec.
his/her signature (na~e of individual signing) in th~ s~ace
provided above on this 28TH da'! of APRIL '9 92.
-- c/l,~ J~:" '-h;~
tWTARY PUBLI
My co~rnlsslon explres:
07/25/91
LOBBYI:iG P;O CON?LI':::i' OF Hi'!:EEEST CLf..USE
C. G ~ 2 5 - 1
~~~_ ~~~~~ .~1t.:~_t4~_~~'4["~~T:T'=;~:~-j.~~:~~-::~~ ~~?~;-::'~~l~~ ?:'..::?~:.::!~~?I.:~'~~:~'-~=~~~'~~~:'~~~~:}?:,:~~ 5~?-~:~.::: ~:5:':, :~::~:_:;,.~~~
.
.,
(I)
I I RICHARD J. TAYLOR
according to law on my oath,
and say that;
of the city of HOLLYWOOD
and under penalty of perJury, depose
1. ) I am RICHARD J. TAYLOR of the f irn e: RJC
& ASSOCIATES, INC. , the bidder making the Propos=.l for the
.fyro~ ect descr ibed in the not ice for ca 11 ing for b ids fer NEW MONROE
COUN D TENTION FACILITY Cl"d that I executed the sa id proposel ',.: i th
full authority to do so;
2.) the pr~ces in this bid have been arrived at
independently \vithout collusion, consultation, co~nunic2~ie:t or
agreement for the p~rpose of restricting co~petition, as to any
matter relating to such proces with any other bidder or w~t~ any
competitor;
3.) unless otherwise required by law, the prices wnlcn have
been quoted in this bid 11ave not been knowingly disclcse~ ~'.' t~1e
bidder and will not knowingly be disclosed by the bidder end will
not be knowingly disclcsed by the bidder prior to bid c;en:~g,
directly or indirectly, to any other bidder or to any cc~petitor;
and
4.) no attempt has been made or will be made by t~e bidder
to induce any other person, partnership or corporation ~~ S~b2it,
or not to subrni t, a b:c for tl:'2 p'Jrpose of res tr lct i ng
competition;
5. )
correct,
upon the
a'.vard ing
the staterne~ts contained in
and 'made ~ith full kno~lejge
truth of the statements cont
contracts for said project.
this affidavit are tr~e and
tha t Honroe Cour,~ ': r s: =- i es
in this affi-:e:.';i~ 2-~:
STATE OF
COUNTY OF
FLORIDA
BROWARD
of Bic'c'2r)
PERSONALLY A?P~ARED BEFORE MS, the undersigned a~~~ority, _
RICHARD J. TAYLOR "lho, after first being s'..:crr: ty ?e,
(name of individucl signing)
provided above O~ t~is
19 92 .
~~~~
PAMELA fRAIlER McRAE NOT AR Y ;,; g L.L C
My Comm. Exp. 6-13-94
Bonded Thru SeIvIce Ins. (h,
affixed his/her signature in the soace
28TH day of APRIL
My commlss~on expl~es:
11/20/91
NON-COLLUSION AFFIDAVIT
C'J<;]O - 1
r.:~ .: _~_ ":"~~~~r:!_"3!_~r.~~~~>~-:V!.:~!~~'J?:~~~:~~'~~~r:~~'~.'""~:'--_T-??:-~~'~~~~ -~'_' :\~ ',r: .~~~~~_'t:~~~:~~/:_~2~~~,~~~t~'~::'?:.'!'!~:~~~!~~.!?:::E::~?~~~'~-Y-~:-2~~~
-
.
.
SWORN STATE1-1ENT PURSUANT TO SECTION 287. 133 (3) (a) ,
FL9RIDELJ?_Tj\..J'~-LTES, ON PUBLIC ENTITY CRDiES
THIS FOR...'{ MUST BE SIGNED AND SWORN TO IN THE PRESENCE Or' A }10TARY
PUBLIC OR OTHER OFFICli\L AUTHORIZED TO ADHINISTER Ol\'rES.
1. This sworn state~ent is submitted to:
_M~ COUNTY PURCHASING DEPARTMENT
[print name of the public entity]
by 8lQ[ARD ~. TAYLOR, PRESIDENT
[print individual's na~e and title]
for RJC & ASSOCIATES, INC.
(print name of entity submitting sworn state~e~tJ
whose business address is
HOLLYWOOD, FLORIDA 33023 -
5611 DEWEY STREET,
ancl (if applicable) it.s Federal Elnployer Idelltificatic:-:. ~i~~ce:-
( FE IN) is _-59=18fi11Q3_______________ . ( 1ft he en t i :. y :-, a 0;, no
F2IN, include ~he Soci.al SecLl'i.tj' Number of the ir:ci.:':i:::L':21
signing this s~orn state~ent: ) .
2.
I understand that a "publ ic ent i ty C1- ime" as ce f i :--,s::: .:..n
Paragraph 227. 2-JJ (1) (g), I')-,-ol'id~9.tCl!utg..?" means a ';ic:'?tio!",
of any state or federal law by a person with res~e=t ~o a~j
c1 i rect ly re 12 ted to the t r 2.!tsact ion 0 f bus i !',e s s ,,~~.. z: ny
public entity or with an age~cy or political subdivision of
~I1Y other state or of the u~ited states, includi~g ~~t not
li~ited to, ~r~ bid or contract for goods O~ services tc be
pr-ovic1ed to any public er.tit:l ::Jr an agency or pe,l:':::i.cal
subdivision of"' any other state or of the United S~2tes and
involving antitrust, fraud, th€~ft, bribery, cO}_~']5:Ci1,
racketeering, conspiracy, or ~aterial misrepresentatio~.
3. I understand that "convicted" or "con\(iction" as def::--,ed In
Paragraph 287.133(1) (b), Florida statutes, means a fir.ding of
gu i 1 t or a COil.v ict ion of a ptlbl ic entity cr irne, !...~ i:.h C~
Hit_hout an adjudication of guilt, in ar;y federal- o~ state
trial court of record relating to charges br::Jug~t bv
indictment or- infor-~ation after July 1, 1989, as a r-es~lt a~
a jury verdict, nonjury trial, or entry of a plea of g~iltj or
nolo contenc1e~e.
4 . I c. n d e,r s tan d t 11 a tan " a f f i 1 i ate" as de fin e d l n ? a ~ 2, ~ r 2. ~ h
287 . 13 J ( 1) (a), flor..lda__St_a tutes, :.,eans:
03/02/92
PUBLIC ENTITY CRIMES (ADD. G)
C,Ct,2J - ~
, :':1~~_'?~ -; J?7_:.:.:.~~,'""r;'1":: ;~~::'_ :r;:r::;.:'.';:_r:::-~:;~'~ :'"..i;r ~:~~~ .-:~ ...~,~; - . .__;-r:::~-:..-:yo."'(:_:: :~h. - ..7:'-:~;.~-..~~,=.:.-~~;_~.=:~.-~;;~;..-~.~72;7;:-:...:<i._:...~:Z;:::-~.~:T.=::~~. ~;;T~~; ~ ~ ~~i~ .f~~7~;:::~~~'.~-~;:~~
1
1
~
5.
R.lC &. ASSOCIAit\ IliC
5611 DEWEY SIfI[ET
HOlLYWOOD, FlORIDA 33023
1.
A predecessor or successor of a person convic~ej of a
public entity crime: or
An entity under the control of any natural person ~ho is
active in the rnanag~ment of the entity and who ~as been
convicted of a public entity crime. The terii1 "a.::ili~te"
includes those officers, directors, e>::ecutives, ~;:::rtn€rs,
sharehqlders, employees, neDbers, and c.gent.s "';,10 ere
active in the manage~ent o~ an affiliate. The c~nership
by one person of shal-es constituting a co:',t:::-::llling
interest in ano~her person, or a pooling of eq~i;sent or
income aDong persons when not for fair market va~~e under
an arm's length agreement, shall be a prima facie case
tJ,a ton e per son con t r- 0 1 S 2. Ii 0 the r per s O;l , .'^.. ':: e :- so:: i'; h 0
k n 0\-1 i n -j 1 Y '=, n t e r sin t 0 2. j 0 i n t v e n t u r e \y i t h a r:- e :- S 0;l T..; h 0
has been convicted of a p~blic entity crlme in Flc:-id2.
during th~ t")!~ec:~c1Lng 36 months shall be consiie:-ecl a,l
affiliate.
.
2.
I understand that a "p.??:'son" as defined in =='a:-ag:.i:\ph
2 8 7 . 1 3 3 ( 1) (e), 1"LQ_r i d a 0 t d_l!..J::_e s, n e a n san y n a t 1..1 r a 1 != e r- son 0 r
entity organized under the la~s of any state or of ~he united
states with the legal power to enter into a binding contr-act
and which bids or applies ~a bid on contracts -~- the
provision of goods or sc::r'Jic'2s let by a public e;-,=--=-ty, or
which other~is'2 transacts or a~~lies to transact b~sin~5s ~ith
a publil~ ent.it':l. The t<:::nl "Person" ipcludes those =:=~cers,
directors, executives, pa:-tne~s, shareholders, e~~lcyees,
members, and agents who are active in man~gement c: an entity.
~
_Oll'
6. Based on information and belief, the statement whic~ I have
marked below is true in relation to the entity submit~ing this
S',-lOrn state:t,ent. [inc:icClte ,,-,hich st.atement applies. J
03/02/92
,
...... "", ~ _.r.l..
-\,. . .... ., ....~.~f .
~_ Neither the entit_y submitting this s'...'orn state:c:e!lt, nor
a!lY officers, di:-ectors, exec~ti~es, partners, sh2re~olders,
employees, members, or agents who are active in the ~anage~ent
of the entity, nor any cif;::iliate of the entity n2S tee:l
charged with and convicted of a public entity crimes~t5equent
to July 1, 1989.
__ The entity subrr;itting this S','lOrn statement, 0:- one or
more of its officers, directors, executives, par-tners,
shar-eholders, employees, members, or agents who are aC~lve in
the management of the entity, or an affiliate of the entity
has been char-ged with and convicted of a public enti~y crime
subsequent to July 1, 1989.
The entity submitting this sworn statement, ~- one or
<<I
PUGLIC ENT2:T'{
c!UI-ms
U~DD .
6)
O':;~20 - 2
":\~'n~('.>j:,,,,:'-"irjr.:?':;r.::l"";'iiir.;(':.,:._""~ ."'F""'==~.~':~' , .l\~~~
('..,et,.~in:..1:....'f;.'.<,I.~;I,~'~'~'fl'....:i;~!',"(,~!,'f..tt-.xfJ0!.i:.~~~,,1...:,~.tl,,;~f~ ,.:f.,1'j,-.~..\o., "i1,....} ,\ ......, ~ ~'. ..,..,.tr!!'S'mY.l.. .,~. ~..., "~f,'t'~
. .,_, ..' _ ." '-r , . " '1 Ir- y ."(' ..,' ... .~,,"Y' H'.~t. ,-.:-;~P'J'ii~~.l>'f.:;'~~-).,<,,;'ir~.,it:
- ,
~ ~.
('.
I_:~
RJC & ASSOCIATES. INC,
5611 DEWEY STREET
HQLLYWOOO. FLORIDA 33023
"
more of its officers, directors, executives, ;a=tners,
shareholders, emplojees, ~e~bers, or agents who a=e 2cti~.:e in
the management of the entity, or an affiliate of ~~e encity
has bee n c 11 a r 9 ed"" i t h and con vie t e d 0 f a pub 1 ice n ::: i ": Y c r i;.. e
sub s e que n t to J u 1 y 1 , l ') S 9 , H 01" eve r the 1" e r.2. :=: :c E e n a
subsequent proceeding befo=e a Hearing Officer of the State of
F lor ida I D i~v' is ion of ,z'.d",ir, is tra t i ve Hear ings and ~,:e F ':.na 1
Order entered by the Hearing Officer determined t~a::: it was
not in the public intercs~ to place t110 entity sct~i~~i~g this
s:{or~ statemeT1t Cf1 the cC~~.I~cted vendor li.st. [2~~~=~ a cop~~
cf the final crde~J
.
I UNDEP.STA~ro THXr THE SUDl-!ISSIOi'l OF THIS FOPJ1 TO TH:': CC:;;:-?'.:'..CTI;rG
OFFICi::? FOR THE FC;B::.oIC EUTIT'L ~=:;::::irTIFIED HI F!..FJ\G!D\PH 1 (=::;:::) r.3C'~::::
IS FO? TH1.T PIJBLIC E:::TIT'i O:!L'i i,i:Q ,T!Li\T THIS FOPJ.j IS ...._~.,~:::= '-Ti-:~~00G;:
DECE1'12ER 31 Of' THE C.'\LSim!'-.R Y:E>? It1 \'lH:!:CH IT IS FI LE~, _ .;:C.LSO
UNDERST.;',.:'JD THAT I ~'1 REQUIPED TO IHF0R11 THE PUBLIC ENTl:T'~' ?RIOR TO
ENTERn~G INTO 1\ C01:--:'?~'\CT IN E;~CESS OF THE THRESHOLD P.._l~Ol'!;'.:' P?D\~IDED
IN SECTION 2 S 7 " 017, F!ol2RIJ)I._,'2-'I2J----'-!.'l~~ FOR CAT:Lr.:.GORY 'n:-::-' CF .:'.::',: C~L'..~lGE
IN THE INFORHATIOIl CO!:';.'iU:iED r:~ 1'1-< _ FOR!'.
-----------
2
STAYE: OF FLORIDA
COUNTY OF BROWARD
PLRSONALLY APPE.;:'SED BEFOR:~ ;.;S, the undersigned au'.::.hc:city,
RICHARD J. TAYLOR
[name of individual signing]
,,:ho I aftF~r first be ing s',:srn by De,
affixed his/her signature In the space provided above on '.::.his
28TH day of
APRIL
Yne&
My commlSSlon expIres:
PAMELA FRAZIER McRAE
My Comm. Exp. 6-13-94
Bonded Thru ServIce ,... Cll.
t\;
,
Form PUR 7068 (Rev. 04/10/91)
.
03/02/92
PU3LIC ENTIT"::' CRIHES (fI.DD, 6)
(-::;';20 - 3
~
:~. .~w..;_.~..~. ...r:.~~...::?]f.~l:e<;:r;.-r.~~fTV~, :......1. J!;'~~.t ~-'TJ".;~t~~~..:r~~~::-.~;:~mY7t.~"!""" ...-:.1-~'3, }~.:.rl.r,,~.;;"'1~'~tr8~1-IJ:'::':'~.~;'?f.ii'7:~:.'-:O~.~!':!~~,lj~~:~ t'f.l'.~l': ..~~.~ .~ - ::~;:~ :;~~-?;~P:_~7;:~~tr~i'~
~ ,;;r.....Jt..".,~~l\';V,...~~W---',
,r~"'\I..,,",....,r'i.,~..
~.~,::Ji4,)~",-.., _ ,,';ti_,,:....
,.J t.....~~...J~~=>>tt;tii~~t~...
RJC & ASSOCIATES. IHC,
5611 OEWEY STREET
11(11' YWOOO, FLORIDA 33023
VOLUNTAR\ ALTERNATE BID REVISED (ADD. 12)
[lEDUCTIVE PROPOSAL FORM
10: Monroe Coulty Purchasing Department
Attn: Mr. D~ck Ccfnr, Director of Purchasing
Bidder hereby states tllat separate, distinct and stand-alone bids
have been submitted rr the following bid packages:
1 .
B id Packa9-e_N~
--1iUWl~~ 1t 3i__ ___
__~~fL~ :?25"' _________
-!)~~~-~l- ------
k11V\~t:~ '* .3 ~
Qe~cription
4-W<'v.v'\ ~lC\~ I ~ Ar0:/1 ~~
CA~6N~t f\Nfj ~SpJl'A.,I\L. WoR.ks
~S~ Jl.llQf1;'1' 1(E~: Levrr- A...;! CA~
AC..o\1 f,.~ utl\L.. 0;; I ~~j
l1;::eI1}
2 .
3 .
4 .
5.
6.
7.
8 .
9.
A t the option of the O,mer, and if the bidder is awarded more than
(1) bid package, bidder hereby offers the following DEDUCT proposal
peree-R-t=-a~prices, for the Owner's benefit.
-t f.--4:--h e O'.JfieF tWares--e.i:-d s-eft----:i:-to em s
dedB€-'I=eEi-4rom the base--lr.i:-as--eF- enoh
.:l bev-e, "6- m.:lY be
bid p.:lcJc.:lge.
-a-eave, % Ill.:l y---be
bid p~e-:-
.:lbove, ~ m.:lY be
bid p.:lcJc.:lge.-
~e, "6- m.:lY be
bid p.:lcJc.:lge.
.:lbove, "6- m.:lY be
bid p.:lcJc.:lge-:-
I- f--4:.}:}.c QT,;n C F .:l V.:lres--e 1:-4 s-en--i--t:-ems
lie4uet:e-4---E-rom the base--hids of eaoh
-f+-t,he---ewn e r .:l \/.:l res- -b Hi ~T--t) IT-it:em s
d-(~a-ucted frem the ba-se-l:r.i:B:s 0 f eaoh
~t-~ the Owner .:lW.:lros--b.i:-ds-ef'l~ffiS
deduet:€l---4rom the ba-s-e-hMs-e-:f-e-aoh
:[€--t:-he-Gw-ne r .:l wa-ra-s--bi.d-=-.---eft---i-:E-ems
d"'~due-t:e-€l-----f-re~l:s~-b-ias- 0 f ea eh
__ * -lkJ'~~lO"';~ ~,(),. I~"I~ 15.f.)~ ~l
OS/21/92 I - ADDENDUM NO. 12
p.../J
:;~ fJ!
PAGE - 5
I f the Owner awards bids on items _2.AAi"-.:L____ (from 1 isting above),
;;~9~ 1)0LLl~R~ may be deducted from the sum total of -the base
bids of the listed items.
If the Owner ay;ards bids on items Z+-~A"d '1--(from listing above),
gS:mO. ~ . DOI"L~BB. may be deduct_ed from the sum total of 1::.he base
bids of the listed items.
If the Owner awards bids on items ~ 2.+1,tw~(from listing above),
;;~AOO 'DOL~M-l? may be deducted from the sum total of the base
bids. of the Tisted items.
If the ownerawarc1Sbids on ifems. (fromlistThgab6ve),
.s.___-'-__--------'DOt.k~9. maybe deducted from the si.llT\total>ofthe base
bids of the'listedjtems.
If the Oymer aYlards bids on items (from 1 istingabove) ,
.s. DQL.LA~maybe deducted from the sumdtotalofthe ,base
bids of the listed items.
If the o...,11er awards bids on items (fr()mli~.tiI1gabove) ,
$ --J2QJ;..LARSmaybe deducted fron) the sum. tota lof dtlie base
bidsof<the>listeditefus.
Bidder/Company
RJC & ASSOCIATES. INC.
51111 OEWE Y :mm. r
HOLtYWOOn, FLORIDA 33023
Mailing Address:
------.-.---.-------
-----------
Phone Number:
305 - "ttp')-~'3tJl
Date'_~/~L-.
signed:
Viitness:
?J2. rsl 'H~,-r-r
-1-~
(Seal)
OS/21/92
ADDENDUM NO. 12
PAGE - 6
THE AMERICAN INSTITUTE OF ARCHITECTS
.
AlA Document A201/CM
CONSTRUCTION MANAGEMENT EDITION
General Conditions of the Contract
for Construction
THIS DOCUMENT HAS IMPORTANT LEGAL CONSEQUENCES; CONSULTATION
WITH AN ATTORNEY IS ENCOURAGED.
1980 EDITION
TABLE OF ARTICLES
1. CONTRACT DOCUMENTS
8. TIME
3. OWNER
9. PAYMENTS AND COMPLETION
10. PROTECTION OF PERSONS AND
PROPERTY
2. ADMINISTRATION OF THE
CONTRACT
4. CONTRACTOR
5. SUBCONTRACTORS
11. INSURANCE
6. WORK BY OWNER OR BY
SEPARATE CONTRACTORS
12. CHANGES IN THE WORK
13. UNCOVERING AND CORRECTION
OF WORK
7. MISCELLANEOUS PROVISIONS 14. TERMINATION OF THE CONTRACT
~ CAUTION: You should use an original AlA document which has this caution printed In red.
w.IiI An original assures that changes will not be obscured as may occur when documents are reproduced.
Copyright 1975, Cl 1980, by The American Institute of Architects, 1735 New York Avenue, N.W.. Washington, D.C. 20006.
Reproduction of the material herein or substantial quotation of its provisions without wrillen permission of the AlA violates
the copyright laws of the U:lited States and wiu be subject to legal prosecution.
AlA DOCUMENT A2t1/CM . GH':ERAl CO~DITIONS OF THE CONTRACT FOR CONSTRUCTION
CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION · AlA- . @ 1980 · THE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE.. N.W., WASHINGTON, D.C. 20006
A201/CM - 1980 1
'..l ._._ __J:._,_.L..',..~I._'_-,.....~l~_~e""'..:r'"
Acceptance of Defective of Non-Conforming Work. .6.2.2, 13.3
Acceptance of Work. . ., . . . . . ., . . . . . . .9.5.5, 9,8.1, 9.9.1, 9.9.3
Acce~~ to Work. . . . . . . . , . . . . . . . ... . . . . . . . . . . . . . .2.3.6, 6.2.1
Accident Prevention. ....... ., . ..... .. . . . . . . . . . .,. .2.3.5, 10
Act~ and Omi~~ions ............. .4.18.3, 7.4, 7,6.2, 8.3.1, 10.5
Addenda, Definition of .............................. .1.1.1
Additional Co~ts, C1aim~ for .......................... .12.3
ADMINISTRATION OF THE CONTRACT............. .2,4.3.3
Agreement, Extent of .............................. .1.1, 1.2
All Risk Insurance .................................. .11.3.1
Allowances .......................................... .4.8
Applications for Payment, Contractor's.. . . . . .2.3.8, 9.2.1, 9.3.1,
9,3,3.,9.5.3,9.7.1,9.8.2,9.9.1,9.9.3,9.9.5, 11.3.1, 14.2.2
Applications for Payment, H'
Project................ .2,3.8,2.3.9,9.3.1,9.4,9.6.1,9.7.1
Approvals.... . .. .......... .... .2,3.18, 3.4, 4,3,3,4.5, 4,12.4,
4.12.5,4.12.6,4,12.8,4.13.2,7.7,9.3.2
Arbitration. . .. . ., .2.3.15,2.3.23,6.2.5,7,9, 8.3.1, 11.3.7, 11.3.8
Architect, Definition of ................ ... ............. .2.1
Architect, Extent of Authority....... .2.3.3.4,4.12.8,5,2,7.7.2,
8.1.3,8.1.4,8.3.1,9.2,9,3.1,9.4,9.5.3,9.6,9.8, 9.9.1, 9.9.3,
12.1.1,12.1.4,12.3.1,12.4.1,13.1,13.2.1,13.2.5,14.2
Architect, limitations of Authority and Responsibility. . . . .2.3.2
through 2.3.5, 2.3.13 through 2.3.18, 2.3.22,4.12.6,
5.2.1,9.4.2,9.5.4,9.5.5,12.4
Architect's Additional Services.. .3.4,7.7.2,13.2,1,13.2.5,14.2.2
Architect's Approvals. .., . .2.3.18, 3.4,4.5, 4.12.6, 4.12.8, 4.18.3
Architect's Authority to Reject Work... .2.3,16,4.5,13.1.2,13.2
Architect's Copyright. .. . . . . .. . .... .. . . . .. . . .. . .. .:. . ...1.3
Architect's Decisions. . . . . . . .. ... ..2.3.10 through 2.3.16, 7.7.2,
7.9.1,9.2,9.4,9,6.2,9.8.1,12.1.4,12.3.1
Architect's Inspections. .... . . . .2.3.16, 2.3.21, 9.4.2, 9,8,1,9.9.1
Architect's Instructions. . . . . . .. . .2.3.16, 2.3.19, 7.7.2,12.4,13..
Architect's Interpretations. .... . .. .2.3.10 through 2.3.13, 12.3.2
Architect's On-Site Ob~ervations ...... .2.3.4, 2.3.6, 2.3.9, 7.7.1,
7.7.4,9.4.2, 9.6.1,9.9,1
Architect's Relationship with Contrador ..... .1.1.2, 2.3.5, 2.3.6,
2.3.13,2.3.16,4.3.3,4.5,4.7.3,4.12.6,4.18,11.3.6
Architect's Relationship with
Subcontractors. ...... . . .... .. . . .1.1.2, 2.3,16, 9.5,3, 9.5.4
Architect's Representations .................9.4.2, 9,6.1, 9.9.1
Artistic Effect... .... ............... .1.2,3,2.3.14,2.3.15,7.9.1
Attorneys' fees.......... .............. .. .4.18.1,6.2.5,9.9.2
Award of Separate Contracts. .. .. . .... . . . . . . . . . . . ., . .. .6.1.1
Award of Subcontracts and Other Contracts for
Portions of the Work. . .. . .. . ., . .. . . . ... . . . . .. . . . .. .5.2
Boiler and Machinery Insurance.. ... . . . . . . . . . . . . . . . .. .11.3.2
Bonds, lien ....................................9.3.3, 9.9.2
Bonds, Performance, labor and Material Payment. . .. .7.5,9.9.3
Building Permit. . ..... .. .., . ............ . . . . .. . .. . . .. . .4.7
Certificate of Substantial Completion... .9.8.1,9.8.2,9.8,3,9.8.4
Certificates of Inspection, Te~ting or Approval. .. ........ .7.7.3
Certificates of In~urance ...,................... .9.3.2,11.1.4
Certificates for Payment, Projed ....... .2.3.9,2.3.21,9.4,9.5.1,
9.5.5,9.6.1,9.7.1,9.8.2,9.9.1,9.9.3,12.1.4,14.1.1,14.2.2
Change Orders .............. .1.1.1, 2.3.19, 3.4, 4.8.2.3,4.11.1,
5.2.3,7.7.2,8.3.1,9.7,9.9.3,11.3.1,11.3.5,11.3.7, .
12.1,12.2.1,12.3.1,13.1.2,13.2.5,13.3.1
Change Orders, Definition of ............. . . .. . . . .. ., .12.1.1
CHANGES IN THE WORK................. .2.3.19,4.11.1, 12
INDEX
Claims for Additional Cost or Time. . . . .8.3.2,8.3.3, 12.2.1, 12.3
Claims for Damages.............. .6,1,1, 6.2,5, 7.4, 8.3, 9,6.1.2
Claims and Disputes Between Contractor
and Owner............. .2.3,12,23,15,2.3.23,4,18,2, 7,9
Cleaning Up . . ... .... . . .. . . . . . . . . . . . . . . . .. . . .. . .. .4.15, 6.3
Commencement of the Work, Conditions Relating to .3.2.1,4.2,
4.7.1,4.10,5.2.1,6.2,2,7.5,9.2,11.1,11.3.4
Communications..... ........ ....... . .2.3.2, 3.2.6,4.9,1,4.16
Completion,
Conditions Relating to.. .2.3.21, 4.11, -4.15,9.4.2,9.9,13.2.2
COMPLETION, PAYMENTS AND ..........................9
Completion of the Project, Substantial.. .... .8,1.4,9.8.3,9.8.4,
9.9.4,9.9.5,9.9.6,13.2.1,13.2.2
Completion of the Work, Substantial... .... .23.21, 8.1.1, 8.1.3,
8.2.2,9,8,9.4.2,9.9.3,11.3.9
Compliance with Laws ....... ... . .1.3,2.1.1,4.6.4.7,4.13,7.1,
7.6.1, 7.7.1,10.2.2,14.2.1
Concealed Conditions ..... . . . . . . . . . . . . . . . . . . . . . . . . . . . .12.2
Consent, Written ....................2.3.22,4.14.2,7,2,7.6.2,
9.8.1,9.9.2,9,9,3,11.3.9
Construction Manager, Definition of .................... .2.2
Construction Manager's Approval .............. .4.10.1, 4.13.2
Construdion Manager's
Additional Services........ .3.4,7.7.2,13.2.1,13.2.5,14.2.2
Construction Manager's Authority and Responsibility... . .2.3.3,
23.5,2.3.16,2.3.10, 2.3.22,4.8.1,4.17.1,4.18.3,
7.7.4,9.2,10.2.5,11.3.6,12.1.4,14.1.1
Construction Manager's Confirmation ...................9.9,3
Construdion Manager's Consultation with the Architect .2.3-
2.3.16,2.3.19,2.3.21,3.4.1,9,6.1.9.8.1,12.1.4,12.3.1,14.
Construction Manager's Coordination and Scheduling.. . .2.3.7,
2.3.17,4.3.1,4.10.1, 4.12.4
Construction Manager's Decisions. . . . . . . . . .. ..... . .6.3, 8,3.1
Construction Manager's Determinations. .2.3.3. 6.3.1, 7.7.2,8.3.1
Construdion Manager's Interests................ 11.3.1,11.3.2
Construction Manager's Recommendations... .2.3.8, 2.3.9, 9.3.1,
9.4,1,9.7.1,9,9.1, 12.1.1
Construdion Manager's Relationship
with Architect.......... .... ... . .1.1.2, 2,3.1, 2.3.3, 2.3.21
Construction Manager's Relationship with Contrador .....1.1.2,
2.3.15,23.16,3.2,6,4.2.1,43.3,4.5,4.7.3,4.11.1, 4.12.4, 4.12.6,
4.16.1,4.17.1,4.18,5.2,6,2.1,6.2.2,7.6.2,7.7, 7.9.1,7.9.2,
8.3.1,8.3.2,9.4.1,9.5.4,9.8.1,9.9.1,10.2.6,11.1.4,11.3.6
Construdion Manager's Relationship
with Subcontractors.......... .... .. .. .1.1.2,2.3.16,5.3.1
Construdion Manager's Review..........,. .2.3.8, 2.3.17,5.2.1
Construction Schedule, Contrictor's .. . . . .. ... ... ... . .. . .4.10
Contrad, Definition of ............. . . . . . . . . . . . . . . . . . . .1.1,2
Contract Administration........ ..... . ............ .2.3,4.3.3
Contrad Award ilnd Execution,
Conditions Relating to..... .4.7.1, 4.10, 5.2, 7.5,11.1,11,3.4
CONTRACT DOCUMENTS ..........;....................1
Contrad Documents,
Copies Furnished and Use of ... . ~. . . . .. . ., .1.3, 3.2.5, 5.3
Contract Documents, Definition of .....................1.1.1
Contract Modifications............. ... ............. 1.1.1,12
Contrad Sum, Definition of ...........................9.9.1
Contract Termination ...................................14
Contrad Time, Definition of .. .. .... . " .. ... ......... . .8.1.1
CONTRACTOR ..................................,......4
Contractor, Definition of ........ ... .. ............ .4.1, 6.1.2
Contractor's Construction Schedule .................... .4.1r)
2 A201/CM-1980
AlA DOCUMENT A2ft/CM . GENERAl CONDITIONS Of THE CONTRACT fOR CONSTRUCTION
CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlA. . ~ 1980 . THE
AMERICAN INSTITUTE Of ARCHITECTS. 1735 NEW YORK AVE., N.W., WASHI!'/GTON, D.C. 20006
WAR~I!NG: Unlicensed photocopying \~ol.tes U.S. copyright leNS ~ Is euIljee! to!~1 rmeecutlon.
Contractor's Employees. . . . . .4.3.2, 4.4.2, 4.8.1, 4.9, 4.18, 10,2.1
through 10.2.4, 10.2.6, 10.3, 11,1.1
Contractor's liability Insurance.. .. . ., . . . . . . . . . . . . . . . . . .11.1
Contractor's Relationship with Architect ..... .1.1.2, 2.3,5, 2.3.6,
2.3.13,2.3.16,4.3.3,4,5,4.7,3,4.12.6,4.18,11.3.6
Contractor's Relationship with Construction Manager. .. . .1.1.2,
2.3.15,2,3.16,3.2.6,4.2,1,4,3.3,4.5,4.7.2, 4.11.1, 4.12.4,
4.12.6,4.16.1,4.17.1,4.18,5.2,6.2.1,6,2.2,7.6.2, 7.7, 7.9.1,
7.9.2,8.3.1,8.3.2,9.4.1,9.5.4,9.8.1,9.9.1,10.2.6, 11.1.4, 11.3.6
Contractor's Relationship with Separate Contractors
and Owner's Forces.... .., ......... . . . ... . . .,. .3,2.7, 6
Contractor's Relationship with
Subcontractors..... .,. . .1.2.4, 5.2, 5.3, 9.5.2, 113.3, 11.3.6
Contractor's Representations .......... .1.2.2, 4,5, 4.12.5, 9.3.3
Contractor's Responsibility for Those
Performing the Work.. .. .,. .. ...... . . . ., .4.3,2, 4.18, 10
~ontractor's Review of Contract Documents ....1,2.2, 4.2, 4.73
Contractor's Right to Stop the Work .....................9.7
Contractor's Right to Terminate the Contract. . . . . . . . . . .. .14.1
Contractor's Submittals. .... ...... ... .2.3.18, 4.10, 4.12, 5.2.1,
5.2.3,9.2,9.3.1,9,8.1,9.9.2,9.9.3
Contractor's Superintendent. . .. . ., . . . . . . . . . . . . . . . .4.9, 10.2.6
Contractor's Supervision and
Construction Procedures. . . . . . . . . .1.2.4, 2,3.5, 4.3, 4.4, 10
Contractual liability Insurance.... ...... . .. . .. . .. . ... .11.1.3
Coordination and Correlation...... ...1.2,2,1.2.4,4.3.1,4,10.1,
4.12.5,6.1.3,6.2.1
Copies Furnished of Drawings and Specifications. .1.3, 3,2.5, 5.3
Correction of Work.................... .3.3,3.4,10,2,5,132
Cost, Definition of ................................. .12.1.4
Costs...... .3.4,4,8.2,4.15.2,5,2,3,6.1.1,6.2.3,6,2.5,6,3,7.7.1,
7.7.2,9.7,11.3.1,11.3.5,12.1,3,12.1.4,12.3,13.1.2,13,2,14.2.2
Cutting and Patching of Work. ., . ., . . . . . . . . . . . . . ... .. . .4.14
Damage to the Work........... .4.14.2,10.2.1.2,10.2.7,11.3.1
Damage to Work. . . ..... ... . .4.14,2,4.18.1,6.2.4,6.2.5,9.6.15,
10.2.1.3,10.2,2,10.2.5,10.3,13.2.6
Damages, Claims for.. ..... .......... .6.1.1,6.2.5, 7.4,9.6.1.2
Damages for Delay. . '" ., ...... ;....... . ... .6.1.1,8.3.4,9.7
Day, Definition of ................................... .8.1.5
Decisions of the Architect........ .2.3.10 through 2.3.16, 7.7.2.
7.9.1,9,2,9.4,9.6.1,9.8,1,12,1.4,12.3.1
Decisions of the Construction Manager. . . . . .. . . . .. . .6,3, 8,3.1
Defective or Son.Conforming Work, Acceptance,
Rejection and Correction of . . .. . .2.3.4, 2.3.16, 3.3, 3.4, 4.5,
6.2.2,6.2.3,9.6.1.1,9,9,4.2,13
Definitions. . . . . . . . ... .. . .1.1, 2.1, 2.2, 3.1, 4.1, 4.12.1 through
4.12.3,5.1,6.1.2,8,1,9,1.1,12.1.1,12.1.4
Delays and Extensions of Time. ... . . . . . . . . . . . . . . . . ..... .8.3
Disputes. . . . . . . . . . . . ... . .2.3.12, 2.3.15, 23.23, 6.2.5, 6.3, 7.9.1
Documents and Samples at the Site.. .. . . . . . . . . . . . . . .. . .4.11
Drawings and Specifications,
Use and Ownership of ............. . . .1.3, 3.2.5, 4.11, 5.3
Easements. . .. ... ... .... ., ............ . . . .,. ........ .3.2.3
Emergencies ........................................ .10.3
Employees, Contractor's .......... .4.3.2, 4.4.4, 4.8.1, 4.9, 4.18,
10.2.1 through 10.2.4, 10,2.6,10.3,11.1.1
Equipment, labor, Materials and...... 1.1.1,4.4,4.5,4.12,4.13,
4.15.1,6.2.1,9.3.2,93.3,9,6.1.3,9.9,2,
10.2.1.2,11.3.1,12.1.4,13.2.2,13.2.5,14
Execution and Progress of the Work. . .. . . . . .1.1.3, 1.2.3, 2.3.4,
2.3.5,23.11,4.2,4.4,1,4.5,4.7.1,6.2.2,7,9.3,
8.2.2,8.3,1,8.3.2,9.6.1,10.2.3,10.2.4,14.2
Execution, Correlation and Intent of
the Contract Documents ......................1.2,4.7.1
Extensions of Time... .......... ...... .... .8,3,12.1.1,12.1.2
Failure of Payment by Owner. . . . . . . . . . . . . . . . . . . . . . .9.7, 14.1
Failure of Payment of Subcontractors ......9,6.1.3, 9.9.2, 14.2.1
Failure to earry out the Wort.. .. . . . .. . .. . . ...... . .. . . .2.3.5
Final Completion and Final Payment. . .2.3.15,2.3.21,9.9,13.3.1
Financial Arrangements, O.....-ner's .... ...... ........... . .3.2.1
Fire and Extended Coverage Insurance. . . . . ... ... .. . ., .11.3.1
Governing law.. .............. ... . ................... .7.1
Indemnification.. . .. . . . ....... . . . . .. .. .4.17, 4.18, 6,2.5, 9.9.2
Identification of Contract Documents .................. .1.2.1
Identification of Subcontractors and Suppliers........ ... .5.2.1
Information and Services Required of
the Owner. . . . . .. . . . .... . . . . . . . . . . .3.2, 6.1, 9, 11.2,11.3
Inspections... . .. ...... . .2.3.16,2.3.21,4,3.3,7.7,12.1.2,9.9.1
Instructions to Bidders. . . .... . . . . . . . . . . . . ....... ... . . .1.1.1
Instructions to the Contractor.... . . . .. .2.3.2, 3.2.6, 4.8.1,7.7.2,
12.1.2,12.1.4
INSURANCE. .. ................. . ....... ......... .9.8.1,11
Insurance, Contractor's liability ....................... .11.1
Insurance, loss of Use . . ... ,. ... . . . . .. . . . . ., . .. . . ... .. .11.4
Insurance, Owner's liability..... . .. . .... ........ ...... .11.2
Insurance, Property ...................................11.3
Insurance, Boiler and Machinery. . .. .. . .......... .... .11.3.2
Insurance, Special Hazards.......... .... . ...... ... ...11.3.5
Insurance, Stored Materials.... . .. . . . . .. . . .......9.3.2,11.3.1
Insurance Companies, Conse:!t to Partial Occupancy.... .11.3.9
Insurance Companies, Settle::1ent With. . ., . ..... . . . . .. .11.3.8
Intent of the Contract
Documents...... ........1.2.3, 2.3.10, 2.3.13, 2.3.14,12.4
Interest ............................................. .7.8
Interpretations, Written. ..... . .1.1.1, 2.3.11, 2.3.12, 2.3.13, 12.4
labor, Materials and Equipment.. . . . . .1.1.3, 4.4, 4.5, 4.12, 4.13,
4.15.1,62.1,9.3.2,9.3.3,9.6.1.3,9.2.2,10,2.1.2,
11.3.1,12.1.4,13.2.2,13.2.5,14
labor and Material Payment Bond...................... .7.5
labor Disputes. . . . . . . . . . ... .. . . . . . . . . . . . .... .. . . ., . . .8.3.1
laws and Regulations. . . ..... . . . . .1.3, 2.1.1, 4.6, 4.7, 4.13, 7.1,
, 7.6.1,7.7.1,10.2.2,14
lIens...... ......... ........... ........ .9.3.3, 9.9.2, 9.9.4.1
limitations of Authority.... ... . . . . .. . .. . .2.3.2, 11.3.8, 12.4.1
limitations of liability. . .... . . . . .2.3,13, 23.16, 2.3.18, 3.3,4.2,
4.7.3,4.12.6,4.17,4.18,6.2.2,7.6.2,9.4.2,
9.5.4,9.9.4,9.9.5,10.2.5,11.1.2,11.3.6
limitations of Time, Genera~ ...... . .2.3.11,2.3.18, 3.2.1, 3.2.4,
4.2,4.7.1,4.7.3,4.12.4,4.15.1,5.2.1,5.2.3,6.2.2,7.4,
7.7,7.9.2,8.2,9.5.2,9.6,1,9.8,9.9,11.3.1,11.3.4,
. .. . 1.:1.3.9,12.1.4, 12.4,13.2.1,13.2.2,13.2.5
llmltallons of TIme, Specific....... . .3.4, 4.10, 7.9.2, 8.2, 8.3.2,
8.3.3, 9.~. 9.3.1, 9.4.1, 9.5.1, 9.7, 11.1.4, 11.3.8,
, . . 12.2,12.3.1,13.2.2,13.2.7,14.1,14.2.1
lImItatIons, Statutes of .................. .7.9.2, 13.2.2, 13.2J
loss of Use Insurance. . .. ... . .. . . . . . . . . . ... ... . .. . ... .11.4
AlA DOCUMENT A201/CM . GENERAL CONDIlIONS OF THE CONTRACT FOR CONSTRUCTION
CONSTRUCTION M^N^GE,I.\ENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE
^MERICAN INSTITUTE OF ^RCHITECTS, 1735 NEW YORK ^VE.. N,W., WMHINGTON, D.C. 2OOll6
A201/CM-1980 3
'_l.-_,_~._ _ "__ ._t...._~ 'IC=: f""""'" .~:...I-..~..c::::."..,ir.;~ubi~r:-tt('ll~:"~.""'"':JsecuHon.
Materials, labor and Equipment...... .1.1.3, 4,4, 4,5, 4.12, 4,13,
4.15,1,6,2,1,9.3.2,9.3.3,9.6,1.3,9.9,2,
10.2.1.2,11,3,1,12.1,4,13.2.2,13.2.5,14
Material Suppliers....................... .4.12.1, 5.2.1, 9.3.3
Means, Methods, Techniques, Sequences and
and Procedures of Construction........ .2.3,5,4.3,1,9,4.2
Minor Changes in the Work............... .1.1,1,2.3.19,12.4
MISCELLANEOUS PROVISIONS ...........................7
Modifications, Definition of ...........................1.1.1
Modifications to the Contract.. . . . ., .1.1.1, 1.1.2, 2.3.2, 2.3,22,
4.11.1,4.7.3,12
Mutual Responsibility................................. .6.2
Non-Conforming Work, Acceptance of Defective or .... . . .13.3
Notice, Written. . . ........ .2.3.11,2.3,15,4.2, 4.7.3, 4.7.4, 4.9.
4.12,6,4.12.7,5.2.1,7.3,7,4,7.9.2,8.1.2,8.3.2,8.3.3,
9,4,1,9,6.1,9.7,9.9,1,9,9.5,10.2.6,11,1,4,11.3.1,
11.3.5,11.3.7,11.3,8,12.2,12.3,13.2.2,13,2.5,14
Notices, Permits, Fees and. . ........ .. .2.3.2, 4.7, 4.13,1, 10.2.2
Notice of Testing and Inspections... ....... . . . .......... .7.7
Notice to Proceed................................... .8.1.2
Observations, Contractor's....... . . ........ . . .,. .1,2.2, 4.7.3
Occupancy. . .. ... ... ..... ......... .8.1.3, 8,1,4,9.5.5, 11.3.9
On-Site Inspections
by the Architect........., .2.3.16,2,3.21,9.4.2,9.8.1,9.9,1
On-Site Observations by the Architect. . . . . . ..2.3,4,2.3.6,2.3.9,
7.7.1,7.7,4,9.4,2,9.6.1,9.9.1
Orders. Written................. .3.3,4.9,12.1,4,12.4,1,13 1
OWNER ...............................................3
Owner, Definition. ................................... .3.1
Owner, Information and Services
Required of the.. ....... .3,2,4.7.1,6,1.3,6.2,9,11.2,11.3
Oy.ner's Authority. ...... . .,. ...... .2.3.21, 7.7.2,9.3.1, 9.3.2,
9.8.1,11.3.8,12.1.2,12.1.4
Owner's Financial Capability......................... .3.2.1
Owner's liability Insurance ..,........................ .11.2
Owner's Relationship with Subcontractors... .. .. . . .1.1.2,9.5,4
Owner's Right to Carry Out the Work..... ... . .... .3.4,13.2.4
Owner's Right to Clean Up ...................... .4,15.2, 6.3
Owner's Right to Perform Work and to
Award Separate Contracts.......... .. ., . ...... . . . .. .6.1
Owner's Right to Terminate the Contract, .... .. .....' . . . .14.2
Owner's Right to Stop the Work........................ .3.3
Ownership and Use of Documents.. .. .. ..... .. .1.3,3.2.5,5.3
Patching of Work, Cutting and......... . . .., ... ... .. . . .4,14
Patents, Royalties and. ... . ...,. .. . ... .,. .. .......... .4,17.1
Payment Bond, labor and Material. . .. . . . . . . . . . . ., . . . . . . .7.5
Payment, Contractor's Applications for .... , .2.3.8, 9,2, 9.3, 9.4,
9.5.3,9.6,1,9.7.1,9.8.2,9.9,1,9.9.5,14.2.2
Payment, Project Certificates for..... ,. .2.3,9,2.3.21,9,4,9.5.1,
9.5.5,9.6.1,9.7.1,9.8.2,9.9.1,9.9.3,12.1,4,14,1.1,14.2.2
Payment, Failure of ..........,.....9.5.2, 9.6.1.3, 9.7, 9.9.2, 14
Payment, Final. .. . . ............... 2.3.15, 2.3.21, 9.9, 13.3,1
Payments, Progress. . . ..... . ,i.8, 7.9.3, 9.5.5, 9.8.2,9,9.3,12.1.4
PAYMENTS AND COMPlETION..........................9
Payments to Subcontractors ..........9,5.2,9.5.3,9.5,4,9,6.1.3,
11.3.3,14.2.1
Payments Withheld ....................................9.6
Performance Bond and labor and Material Payment Bond. . .7.5
Permits, Fees and Notices. . . .. . . . . . . . . .3.2,3, 4.7, 4,13. 10.2,2
PERSONS AND PROPERTY, PROTECTION OF . . . . . . . . . . . . . .10
Product Data, Definition of ..................,...... .14.2,2
Product Data, Shop Drawings, Samples and. . .2.3.18,4.2.1,4.12
Progress and Completion ....................2.3.4, 7.9.3, 8,2
Progress Payments....... ...7,8, 7,9.3,9.5.5,9.8,2.9.9.3, 12.1.4
Project, Definition of ............................... .1.1.4
Project Construction Schedule..... .... . .. ., . .,. .. . ., .. .4.10
Property Insurance. .. . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . .. .11.3
PROTECTION OF PERSONS AND PROPERTY ............. .10
Record Documents .................................. .4.11
Regulations and laws... ...... . . ... .1.3,2.1.1,4.6,4.7,4.13.1,
7.1, 10,2,2, 14
Rejection of Work......,................ .2.3,16,4,5.1,13,2
Releases of Waivers and liens .......... . . . . , . . . . ,9,9.2, 9,9,4
Representations.. ....... .. .1,2,2, 4,5, 4.12,5, 9.4,2, 9,6.1, 9.9.1
Representatives. . . .2.1, 2.2, 2.3,2, 2.3.22, 3.1,4.1,4.9,5.1,9.3.3
Responsibility for Those Performing the Work. . .. .2.3.5, 4.3.2,
6.1.3, 6.2, 9.8.1
Retainage ......................9.3.1, 9.5.2, 9,8.2, 9.9.2, 9.9.3
Review of Contract Documents by the Contractor... ... .1.2.2,
4.2,4.7.3
Reviews of Contractor's Submittals by Owner and
Architect... ...... . . . , . .2,3.18, 4.10, 4,12, 5,2.1, 5,2.3, 9.2
Rights and Remedies. . . . . . . . . . . . .1.1.2, 2,3.15, 2.3,16, 3,3, 3.4,
5.3,6.1,6.3,7.6,7,9,8.3.1,9,6.1,9.7,
10,3,12.1.2,12.2.13.2,2,14
Royalties and Patents ................................ .4.17
Safety of Persons and Property ........,............... .10,2
Safety Precautions and Programs.. . .. . . . . , . . . .... .2,3.5, 10,1
Samples. Definition of .. . . . , . . . . , . . . . . . . . . . . . . . . . . . . .4,12.3
Samples, Shop Drawings, Product Data and. . . . . .2.3.17,2.3.18,
4,2, 4.12
Samples at the Site, Documents and. . . . . . . . . ..... . ., .. .4.11
Schedule, Contractor's Construction. . . . . . . . . . . . . . . . . . ., .4.10
Schedule, Project Construction. ... . . . . . ... .. . ., ....... .4.10
Schedule of Values ....................,...............9.2
Separate Contracts and Contractors.... .4.14,2,6,11.3.6,13.1.2
Shop Drawings, Definition..... . . . . .. , , , . . . , .. , .' . .. .4.12.1
Shop Drawings, Product Data and Samples. . , . . ..,. . .. .2.3.17,
2.3,18,4,2,4.12
Site, Use of . . . . . . .... . . . . . . . . . . . . . . . . . . . , . . . ... .4.13, 6,2.1
Site Inspections........... .1.2,2,2.3,4,2.3.21,7.7,9.8.1,9,9.1
Site Visits. Architect's..........,..... ,2.3.4, 2.3,6, 2,3.9, 7.7.1,
7.7.4,9,4,2,9.6.1,9,9.1
Special Inspection and Testing...........,',..... .2,3,16,7.7
SpeCial Hazards Insurance........................... .11,3.5
Specifications.............................. .1.1.1, 1.2.4, 1.3
Statutes oi limitations. . . . . . . , . . . . . . . . . , . .7.9.2, 13.2.2, 13.2.7
Stopping the Work. . . . . . . . . . . . . . . . . . . . . .3.3, 9.7.1, 10.3, 14.1
Stored Materials........... .6.2.1,9.3.2,10.2,1.2,11.3.1,13.2,5
SUBCONTRACTORS ....................................5
Subcontractors, Definition of ...............,......... .5.1.1
Subcontractors, Work by .......... . . . .1.2.4, 2.3.5, 4.3.1, 4.3.2
Subcontractual Relations .................,............ .5.3
Submittals.. ........... .... .1.3,2.3.18,4,10,4.12,5.2.1,5.2.3,
9,2,9.3.1, 9.8.1, 9.9.1,9,9.3
4 A201/CM-1980
AlA DOCUMENT A201/CM . GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
CO'STRUCTION MANAGEMENT EDITION . JUNE 19l1O EDITION . AlA@> . @ 1980 . THE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D,C. ~0006
WARNI'IC, Unlicensed o~ ~C'c",~v:~c v;cl"'es U S copvriQhl law', A"'-! .,
t 10 I..~_.-..r -'''l"")!I;er-:~I'n 'v.
Subrogation, Waiver of ............................. .11.3,6
Substantial Completion of the Project... .... .8.1.4, 9.8.3, 9.8.4,
9,9.4,9.9.5,9.9.6,13,2.1,13,2.2
Substantial Completion of the Project, Definition of ..... .8.1.4
Substantial Completion of the Work....... .2.3.21,8.1.1,8.1.3,
8.2.2,9.4.2,9.8,9.9.3,11.3.9
Substantial Completion of the Work, Definition of ....... .8.1.3
Substitution of Subcontractors ............. . . . . . . .5,2.3, 5.2.4
Substitution of the Architect. ... . . . . . . . . . . . . . . . . . . . .. .2.3.23
Substitution of the Construction Manager. . . .. . ... ... . .2.3.23
Substitutions of Materials ....................... ,4,5, 12.1.4
Sub-subcontractors, Definition oj .... ... .. .. ........... .5.1.2
Subsurface Conditions.. . . . ...... . . .. . . . . . . . . . .. . . . . .12.1.1
Successors and Assigns. . ................... . . ... .. .... .7.2
Supervision and Construction Procedures. . . . . .. .. .1.2.4, 2.3.5,
4.3, 4.4, 10
Superintendent, Contractor's...... .. ... . ., . . . . ... .4.9,10.2.6
Suret}', Consent of ...........,..................9.9.2, 9.9.3
Surveys. . . . . , . . . . . . . . . . . . . .. . . . . . . . . . . . . . . . . . .3.2.2, 4,18,3
Taxes ............................................... .4.6
Termination by the Contractor.... '" . . . .. .. . . ., . ..... .14.1
Termination by the Owner....... .. . . . .. . . . . . ... .. . . .. .14.2
Termination of the Architect ...,.....................2.3.23
Termination of the Construction \tanager ... .. . . .. .... .2.3.23
TERMINATION OF THE CONTRACT..... ... ... .......... .14
Tests............................... .2.3.16,4.3.3,7.7,9.4.2
TIME................................................. .8
Time, Definition of ................................... .8.1
Time, Dela}'s and Extensions of .,....... .8,3, 12,1, 12.3, 13.2.7
Time Limits, Specific ...............3,4, 4.10, 7.9,2, 8.2, 8.3.2,
8.3,3,9.2,9,3,1,9,4,1,9.5.1,9.7,11.1.4,
11.3.8,12,2,12.3,1,13,2.2,13.2.7,14.1,14.2.1
Title to Work ..................................9.3.2, 9.3.3
UNCOVERING AND CORRECTION OF WORK. . . . . . . . . . . . .13
Uncovering of Work ................................. .13.1
Unforseen Conditions.... . . . . . . . . ............. .. .8.3.1,12.2
Unit Prices..... ........ ... .. ............. ..12.1.3.2, 12.1.5
Use of Documents. . . .. . . . . . . . . . . . . . ... .. . . .. .1.3, 3.2.5, 5.3
Use of Site. . . . . . . . . .. . . . . . . .. . . . . . . .. . .. . .. . . . .4.13, 6.2.1
Values, Schedule of ....................................9.2
Waiver of Claims by the Contractor. . . .7.6.2,8.3.2,9.9.5,11.3.6
Waiver of Claims by the Owner..... .7.6.2, 9.9.4, 11.3.6, 11.4.1
Waiver of Liens ................,.....................9.9.2
Warranty and Warranties. . . . . . . . . . . . . .2.3.21, 4.5, 9.3,3, 9.8.4,
9.9.4, 13.2.2, 13.2.7
Weather Delays. . . . . . . . . . . . . . . . . . . . ... . . . . . . . .. . . .. . .8.3.1
Words, Recognized Meaning of ........................1.2.3
Work, Definition of ..................................1.1.3
WORK BY OWNER OR BY SEPARATE CONTRACTORS.......6
Wrillen Consent......... .2.3.22,4.14.1,7.1,7,6,2,9.8.1,9.9.3
Written Interpretations... . .. . . .. .........1,1.1,1.3.11, 11.3.1
Written Notice...... .2.3.11,2.3,15,4.2,4.7.3,4.7.4,4.9,4.12.6,
4,11.7,5,2.1,7.3,7.4,7.7.2,7.9.2,8.1,1,8.3.2,8,3.3,9.4.1,
9.6.1,9.7,9,9.1,10,2.6,11.1.4,11.3.1,11.3.5,11.3.7,
11.3,8, 122, 12.3, 13.2,2, 13.2.5, 14
Wrillen Orders. .. . . .. .. . . . . .. .. . ,3.3,4.9, 12.1.4, 12.4.1, 13.1
AlA DOCUMENT A201/CM . GENERAL Cmml1l0NS OF THE CONTRAG fOR CONSTRUGION
CONSTRUCTION MANAGEMENT EDIT'O-': . JUNE 1980 EDITION . AlA- . @ 1980 . THE
AMERICAN INSTITUTE OF ARCHITEGS 1~35 NEW YORK AVE.. N,W., WASHINGTON, D.C. 20006
A201/C~--1980 5
WAqt.llt.l~' Unlic~nsed ohotocopying vlolat~s U.S. cOpyright laws and Is subject to l~gal proseeutle>r.
GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
ARTICLE 1
CONTRACT DOCUMENTS
1.1 DEFINITIONS
1.1.1 THE CONTRACT DOCUMENTS
The Contract Documents consist of the Owner-Contractor
Agreement, the Conditions of the Contract (General, Sup-
plementary and other Conditions), the Drawings, the
Specifications, and all Addenda issued prior to and all
Modifications issued after execution of the Contract. A
Modification is (1) a written amendment to the Contract
signed by both parties, (2) a Change Order, (3) a written
interpretation issued by the Architect pursuant to Sub-
paragraph 2.3.11, or (4) a written order for a minor
change in the Work issued by the Architect pursuant to
Paragraph 12.4. The Contract Documents do not include
Bidding Documents such as the Advertisement or Invita-
tion to Bid, the Instructions to Bidders, sample forms, the
Contractor's Bid or portions of Addenda relating to any
of these. or any other documents unless specifically enu-
merated in the Owner-Contractor Agreement.
1.1.2 THE CONTRACT
The Contract Documents form the Contract for Construc-
tion. This Contract represents the entire and integrated
agreement between the parties hereto and supersedes all
prior negotiations, representations or agreements, either
written or oral. The Contract may be amended or modi-
fied only by a Modification as defined in Subparagraph
1.1.1. The Contract Documents shall not be construed to
create any contractual relationship of any kind between
the Architect and the Contractor, between the Construc-
tion Manager and the Contractor or between the Archi-
tect and the Construction Manager, but the Architect and
the Construction Manager shall be entitled to perform-
ance of the obligations of the Contractor intended for
their benefit and to enforcement thereof. Nothing con-
tained in the Contract Documents shall create any con-
tractual relationship between the Owner, the Construc-
tion Manager or the Architect and any Subcontractor or
Sub-subcontractor.
1.1.3 THE WORK
The Work comprises the completed construction required
of the Contractor by the Contract Documents, and in-
cludes all labor necessary to produce such construction,
and all materials and equipment incorporated or to be
incorporated in such construction.
1.1.4 THE PROJECT
The Project, as defined in the Owner-Contractor Agree-
ment, is the total construction of which the Work per-
formed under the Contract Documents is a part.
1.2 EXECUTION, CORRELATION AND INTENT
1.2.1 The Contract Documents shall be signed in not
less than quadruplicate by the Owner and the Contractor.
If either the Owner or the Contractor or both do not sign
the Conditions o{ the Contract, Drawings, Specifications
or any of the other Contract Documents, the Architect
shall identify such Documents.
1.2.2 Execution of the Contract by the Contractor is a
representation that the Contractor has visited the site, be-
come familiar with the local conditions under which the
Work is to be performed, and has correlated personal
observations with the requirements of the Contract Docu-
ments.
1.2.3 The intent of the Contract Documents is to include
all items necessary for the proper execution and comple-
tion of the Work. The Contract Documents are comple-
mentary, and what is required by anyone shall be as
binding as if required by all. Work not covered in the
Contract Documents will not be requ;red unless it is con-
sistent therewith and is reasonably inferable therefrom as
being necessary to produce the intended results. Words
and abbreviations which have well-known technical or
trade meanings are used in the Contract Documents in
accordance with such recognized meanings.
1.2.4 The organization of the Specifications into divi-
sions, sections and articles, and the arrangement of Draw-
ings shall not control the Contractor in dividing the Work
among Subcontractors or in establishing the extent of
Work to be performed by any trade.
1.3 OWNERSHIP AND USE OF DOCUMENTS
1.3.1 All Drawings, Specifications and copies thereof
furnished by the Architect are and shJII remain the prop-
erty of the Architect. They are to be used only with re-
spe~t to th~s Project and are not to be used on any other
prOJect. With the exception of one contract set for each
party to the Contract, such documents are to be returned
or suitably accounted for to the Architect on request at
the completion of the Work, Submission or distribution
to meet official regulatory requirements or for other pur-
poses in connection with the Project is not to be con-
strued as publication in derogation of the Architect's
common law copyright or other reserved rights.
ARTICLE 2
ADMINISTRATION OF THE CONTRACT
2.1 THE ARCHITECT
2.1.1 The Architect is the person lawfully licensed to
practice architecture. or an entity lawfully practicing ar-
chitecture, identified as such in the Owner-Contractor
Agreement. The term Architect means the Architect or
the Architect's authorized representative.
2.2 THE CONSTRUCTION MANAGER
~.2.1 , ,The Construction Manager is the person or entity
Identified as such in the Owner-Contractor Agreement.
The term Construction Manager means the Construction
Manager or the Construction Manager's authorized
representative.
2.3 ADMINISTRATION OF THE CONTRACT
2.3.1 The Architect and the Construction Manager will
AlA DOCUMENT A20lICM . GENERAL CONDITIONS OF THE CONTRACT FOR CONSTRUCTION
CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlAe . @ 1980 . niE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE., N.W., WASHINGTON, D.C. 20006
:. ._._ - 'I ~ __
A201/CM -1980 6
. l_., '.... ........04 :r r..h,;c ~, 0_ I...,... ",:. _
provide administration of the Contract as hereinafter
described.
2.3.2 The Architect and the Construction Manager will
be the Owner's representatives during construction and
until final payment to all contractors is due, The Archi-
tect and the Construction Manager will advise and con-
sult with the Owner. All instructions to the Contractor
shall be forwarded through the Construction Manager.
The Arshitect and the Construction Manager will have
authority to act on behalf of the Owner only to the extent
provided in the Contract Documents, unless otherwise
modified by written instrument in accordance with Sub-
paragraph 2.3.22.
2.3.3 The Construction Manager will determine in gen-
eral that the Work of the Contractor is being performed
in accordance with the Contract Documents, and will en-
deavor to guard the Owner against defects and deficien-
cies in the Work of the Contractor.
2.3.4 The Architect will visit the site at intervals appro-
priate to the stage of construction to become generally
familiar with the progress and quality of the \Vork and to
determine in general if the \\lork is proceeding in accord-
ance with the Contract Documents. However, the Archi-
tect will not be required to make exhaustive or con-
tinuous on-site inspections to check the quality or quan-
tity of the Work. On the basis of on-site observations as
an architect. the Architect will keep the Owner informed
of the progress of the Work, and will endeavor to guard
the Owner against defects and deficiencies in the Work
of the Contractor.
2.3.5 Neither the Architect nor the Construction Man-
ager will be responsible for or have control or charge of
construction means, methods, techniques, sequences or
procedures, or for safety precautions and programs in
connection with the Work, and neither will be respon-
sible for the Contractor's failure to carry out the Work in
accordance with the Contract Documents. Neither the
Architect nor the Construction Manager will be respon-
sible for or have control or charge over the acts or omis-
sions of the Contractor, Subcontractors, or any of their
agents or employees, or any other persons performing any
of the Work.
2.3.6 The Architect and the Construction Manager shall
at all times have access to the \'\'ork wherever it is in
preparation and progress. The Contractor shall prO\ ide
facilities for such access so that the Architect and the
Construction Manager may perform their functions under
the Contract Documents.
2.3.7 The Construction Manager will schedule and coor-
dinate the \,\'ork of all contractors on the Project includ-
ing their use of the site. The Construction Manager will
keep the Contractor informed of the Project Construction
Schedule to enable the Contractor to plan and perform
the Work properly.
2.3.8 The Construction Manager will review all Applica-
tions for Payment by the Contractor, including final pay-
ment, and will assemble them with similar applications
from other contractors on the Project into a combined
Project Application for Payment. The Construction Man-
ager will then make recommendations to the Architect
for certification for payment.
2.3.9 Based on the Architect's observations, the recom-
mendations of the Construction Manager and an evalua-
tion of the Project Application for Payment, the Architect
\,vill determine the amount owing to the Contractor and
will issue a Project Certificate for Payment incorporating
such amount, as provided in Paragraph 9.4.
2.3.10 The Architect will be the interpreter of the re-
quirements of the Contract Documents and the judge of
the performance thereunder by both the Owner and the
Contractor.
2.3.11 The Architect will render interpretations neces-
sary for the proper execution or progress of the Work,
with reasonable promptness and in accordance with
agreed upon time limits. Either party to the Contract may
make written request to the Architect for such interpreta-
tions.
2.3.12 Claims, disputes and other matters in question
between the Contractor and the Owner relating to the
execution or progress of the Work or the interpretation
of the Contract Documents shall be referred initially to
the Architect for decision. After consultation with the
Construction Manager, the Architect will render a deci-
sion in writing within a reasonable time.
2.3.13 All interpretations and decisions of the Architect
shall be consistent with the intent of and reasonably in-
ferable from the Contract Documents and will be in writ-
ing or in graphic form. In this capacity as interpreter and
judge, the Architect will endeavor to secure faithful per-
formance by both the Owner and the Contractor, will not
show partiality to either, and will not be liable for the
result of any interpretation or decision rendered in good
faith in such capacity.
2.3.14 The Architect's decisions in matters relating to
artistic effect will be final if consistent with the intent of
the Contract Documents.
2.3.15 Any claim, dispute or other matter in question
between the Contractor and the Owner referred to the
Architect through the Construction Manager, except those
relating to artistic effect as provided in Subparagraph
2.3.14 and those which have been waived by the making
or acceptance of final payment as provided in Subpara-
graphs 9.9.4 through 9.9.6, inclusive, shall be subject to
arbitration upon the written demand of either party,
However, no demand for arbitration of any such claim,
dispute or other matter may be made until the earlier of
(1) the date on which the Architect has rendered a writ-
ten decision, or (2) the tenth day after the parties have
presented their evidence to the Architect or have been
given a reasonable opportunity to do so, if the Architect
has not rendered a written decision by that date. When
such a written decision of the Architect states (1) that the
decision is final but subject to appeal, and (2) that any
demand for arbitration of a claim, dispute or other matter
covered by such decision must be made within thirty days
after the date on which the party making the demand re-
ceives the written decision, failure to demand arbitration
within said thirty day period will result in the Architect's
decision becoming final and binding upon the Owner
and the Contractor. If the Architect renders a decision
after arbitration proceedings have been initiated, such
decision may be entered as evidence but will not super-
sede any arbitration proceedings unless the decision is
acceptable to al,l parties concerned.
7 A201/CM - 1980
AlA DOCUMENT A20l/CM . GENERAL CONDITIONS OF THE CONTRACT fOR CONSTRUCTION
CONSTRLCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlAe . @ 1980 . THE
AMERICA'l INSTITUTE Of ARCHITECTS, 1735 NEW YORK AVE., N,W" WASHINGTON, D.C. 20006
WARNING: Unlicensed pholocopying violates U.S. copyright IlIWS ..nd Is sublecl~o legal prosecutl'!n.
V~
2.3.16 The Architect will have authority to reject Work
which does not conform to the Contract'Documents, and
to require special inspection or testing, but will take such
action only after consultation with the Construction .'v1an-
ager. Subject to review by the Architect, the Construction
Manager will have the authority to reject Work which
does not conform to the Contract Documents. Whenever,
in the Construction Manager's opinion. it is considered
necessary or advisable for the implementation of the in-
tent of the Contract Documents, the Construction .\1an-
ager will have authority to require special inspection or
testing of the Work in accordance with Subparagraph
7.7.2 whether or not such Work be then fabricated, in-
stalled or completed. The foregoing authority of the Con-
struction Manager will be subject to the provisions of
Subparagraphs 2.3.10 through 2.3.16, inclusive, with re-
spect to interpretations and decisions of the Architect.
However, neither the Architect's nor the Construction
Manager's authority to act under this Subparagraph 2.3.16.
nor any decision made by them in good faith either to
exercise or not to exercise such authority shall give rise
to anv duty or responsibility of the Architect or the Con-
struction Manager to the Contractor, any Subcontractor,
any of their agents or employees, or anv other person
performing any of the Work.
2.3.17 The Construction Manager will receive from the
Contractor and review all Shop Drawings. Product Data
and Samples, coordinate them with information contained
in related documents, and transmit to the Architect those
recommended for approval.
2.3.18 The Architect will review and approve or take
other appropriate action upon the Contractor's submittals
such as Shop Drawings, Product Data and Samples, but
only for conformance with the design concept of the
Work and the information given in the Contract Docu-
ments. Such action shall be taken with reasonable prompt-
ness so as to cause no delay. The Architect's approval of
a specific item shall not indicate approval of an assembly
of which the item is a component.
2.3.19 Following consultation with the Construction
Manager, the Architect will take appropriate action on
Change Orders in accordance with Article 12, and will
have authority to order minor changes in the Work as
provided in Subparagraph 12.4.1.
2.3.20 The Construction Manager will maintain at the
Project site one record copy of all Contracts, Drawings,
Specifications, Addenda, Change Orders and other Modi-
fications pertaining to the Project, in good order and
marked currently to record all changes made during
construction, and approved Shop Drawings, Product
Data and Samples. These shall be available to the Archi-
tect and the Contractor, and shall be delivered to the
Architect for the Owner upon completion of the Project.
2.3.21 The Construction Manager will assist the Archi-
tect in conducting inspections to determine the dates of
Substantial Completion and final completion, and will
receive and forward to the Owner for the Owner's review
written warranties and related documents required by the
Contract and assembled by the Contractor. The Architect
will issue a final Project Certificate for Payment upon
compliance with the requirements of Paragraph 9.9.
2.3.22 The duties, responsibilities and limitations of
authority of the Architect and the Construction Manager
as the Owner's representatives during construction as set
forth in the Contract Documents, will not be modiiied or
extended without written consent of the Owner, the Con-
tractor, the Architect and the Construction Manager,
which consent shall not be unreasonably withheld. Failure
of the Contractor to respond within ten days to a wrillen
request shall constitute consent by the Contractor.
2.3.23 In case of the termination of the employment of
the Architect or the Construction Manager, the Owner
shall appoint an architect or a construction manager
against whom the Contractor makes no reasonable objec-
tion and whose status under the Contract Documents
shall be that of the former architect or construction man-
ager, respectively. Any dispute in connection with such
appointments shall be subject to arbitration.
ARTICLE 3
OWNER
3.1 DEFINITION
3.1.1 The Owner is the person or entity identiiied as
such in the Owner-Contractor Agreement. The term
Owner means the Owner or the Owner's authorized
representative.
3.2 INfORMATION AND SERVICES REQUIRED OF
THE OWNER
3.2.1 The Owner shall, at the request of the Contractor,
at the time of execution of the Owner-Contractor Agree-
ment furnish to the Contractor reasonable evidence that
the Owner has made financial arrangements to fultill the
Owner's obligations under the Contract. Unless such
reasonable evidence is furnished, the Contractor is not
required to execute the Owner-Contractor Agreement or
to commence the Work.
3.2.2 The Owner shall furnish all surveys describing the
physical characteristics, legal limitations and utilih loca-
tions for the site of the Project, and a legal descrip!;on of
the site.
3.2.3 Except as provided in Subparagraph 4.7.1. the
Owner shall secure and pay for necessary approvals. ease-
ments, assessments and charges required for the construc-
tion, use or occupancy of permanent structures or for
permanent changes in existing facilities.
3.2.4 Information or services under the Owner's control
shall be furnished by the Owner with reasonable prompt-
ness to avoid delay in the orderly progress of the Work.
3.2.5 Unless otherwise provided in the Contract Docu-
ments, the Contractor will be furnished. free of d:arge,
all copies of Drawings and Specifications reasonabh nec-
essary for the execution of the Work.
3.2.6 The Owner shall forward all instructions to the
Contractor through the Construction Manager, with simul-
taneous notification to the Architect.
3.2.7 The foregoing are in addition to other duties and
responsibilities of the Owner enumerated herein and es-
pecially those in respect to Work By Owner or By Sepa-
rate Contractors, Payments and Completion, and Insur-
ance in Articles 6, 9 and 11, respectively.
AlA DOCUMENT A201/CM . GENERAL CONDITIONS OF THE CO!'llTRACT FOR CONSTRUCTION
CO:>;STRUCTION MANAGEMENT EDITION . JUNE 19&:l EDITION . AlA. . ~ 1980 . THE
A'IERlCAN INSTITUTE OF ARCHITECTS, 1735 'EW VORl.: AVE., N.W., WASHIr-.:GTON, D.C. 20006
A201/CM -1980 8
3.3 OWNER'S RIGHT TO STOP THE WORK
3.3.1 If the Contractor fails to correct defective Work as
required by Paragraph 13.2, or persistently fails to carry
out the Work in accordance with the Contract Docu-
ments, the Owner, by a written order signed personally or
by an agent specifically so empowered by the Owner in
writing, may order the Contractor to stop the Work, or
any portion thereof, until the cause for such order has
been eliminated; however, this right of the Owner to stop
the Work shall not give rise to any duty on the part of the
Owner to exercise this right for the benefit of the Con-
tractor or any other person or entity, except to the extent
required by Subparagraph 6.1.3.
3.4 OWNER'S RIGHT TO CARRY OUT THE WORK
3.4.1. If the Contractor defaults or neglects to carry out
the Work in accordance with the Contract Documents,
and fails within seven days after receipt of written notice
from the Owner to commence and continue correction of
such default or neglect with diligence and promptness,
the Owner may, after seven days following receipt by the
Contractor of an additional written notice and without
prejudice to any other remedy the Owner may have,
make good such deficiencies. In such case an appropriate
Change Order shall be issued deducting from the pay-
ments then or thereafter due the Contractor the cost of
correcting such deficiencies, including compensation for
the Architect's and the Construction Manager's additional
services made necessary by such default, neglect or fail-
ure. Such action by the Owner and the amount charged
to the Contractor are both subject to the prior approval
of the Architect, after consultation with the Construction
Manager. Ii the payments then or thereafter due the Con-
tractor are not sufficient to cover such amount, the Con-
tractor shall pay the difference to the Owner.
ARTICLE 4
CONTRACTOR
4.1 DEfINITION
4.1.1 The Contractor is the person or entity identified as
such in the Owner-Contractor Agreement. The term Con-
tractor means the Contractor or the Contractor'S author-
ized representative.
4.2 REVIEW OF CONTRACT DOCUMENTS
4.2.1 The Contractor shall carefully study and compare
the Conlract Documents and shall at once report to the
Architect and the Construction Manager any error, incon-
sistency or omission that may be discovered. The Con-
tractor shall not be liable to the Owner, the Architect or
the Construction Manager for any damage resulting from
any such errors. inconsistencies or omissions in the Con-
tract Documents, The Contractor shall perform no portion
of the \A;ork at any time ,\'ithout Contract Documents or,
where required, approved Shop Drawings, Product Data
or Samples for sllch portion of the Work.
4.3 SUPERVISION AND CONSTRUCTION
PROCEDURES
4.3.1 The Contractor shall supervise and direct the
Work, using the Contractor's best skill and attention. The
Contractor shall be solely responsible for all construction
means, methods, techniques, sequences and procedures;
and shall coordinate all portions of the Work under the
Contract, subject to the overall coordination of the COII-
struction Manager.
4.3.2 The Contractor shall be responsible to the Owne,
for the acts and omissions of the Contractor's employees,
Subcontractors and their agents and employees, and any
other persons performing any of the Work under a con-
tract with the Contractor.
4.3.3 The Contractor shall not be relieved from the
Contractor's obligations to perform the Work in accord-
ance with the Contract Documents either by the activities
or duties of the Construction Manager or the Architect
in their administration of the Contract, or by inspections,
tests or approvals required or performed under Paragraph
7.7 by persons other than the Contractor.
4.4 LABOR AND MATERIALS
4.4.1 Unless otherwise provided in the Contract Docu-
ments, the Contractor shall provide and pay for all labor,
materials, equipment, tools, construction equipment and
machinery, water, heat, utilities, transportation, and other
facilities and services necessary for the proper execution
and completion of the Work, whether temporary or per-
manent and whether or not incorporated or to be incor-
porated in the Work.
4.4.2 The Contractor shall at all times enforce strict dis-
cipline and good order among the Contractor's em-
ployees and shall not employ on the Work any unfit per-
son or anyone not skilled in the task assigned them.
4.5 WARRANTY
4.5.1 The Contractor warrants to the Owner, the Archi-
tect and the Construction Manager that all materials and
equipment furnished under this Contract will be new U!
less otherwise specified, and that all Work will be of gOOl.
quality, free from faults and defects and in conformance
with the Contract Documents. All Work not conforming
to these requirements, including substitutions not prop-
erly approved and authorized, may be considered defec-
tive. If required by the Architect or the Construction Man-
ager, the Contractor shall furnish satisfactory evidence as
to the kind and quality of materials and equipment. This
warranty is not limited bv the provisions of Paragraph
13.2.
4.6 TAXES
4.6.1 The Contractor shall pay all sales. consumer, use
and other similar taxes for the Work or portions thereof
provided by the Contractor which are legally enacted at
the time bids are received, whether or not yet effective.
4.7 PERMITS, FEES AND NOTICES
4.7.1 Unless otherwise provided in the Contract Docu-
ments, the Owner shall secure and pay for the building
permit and the Contractor shall secure and pay for all
other permits and governmental fees. licenses and inspec-
tions necessary for the proper execution and completion
of the Work which are customarily secured after execu-
tion of the Contract and which are legally required at the
time bids are received.
4.7.2 The Contractor shall give all notices and comply
with all laws, ordinances. rules, regulations and lawful
orders of any public authority bearing on the perform-
ance of the Work.
9 A201iCM -1980
AlA DOCUMEST A201/CM . GENERAL COPOo/OlTIONS OF THE CONTRACT FOR CONSTRUCTlO:-'
CONSTRUCTIO, MANAGEMENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE
AMERICAS I'STITUTE OF ARCHITECTS. 1735 NEW YORK AVE.. N.W.. WASHINGTON, D.C. 2{)(}()o
L . ,_ _ _..... .~..... .:.....,...... _ I' e ...,......,.;;,.,kf 1~..~ ~nrt :t;. ~l.I'<P('t 10 'et!{~! ')~S{'{.' .'
4.7.3 It is not the responsibility of the Contractor to
make certain that the Contract Documents are in accord-
ance with applicable laws, statutes, building codes and
regulations. If the Contractor observes that any of the
Contract Documents are at variance therewith in any re-
spect, the Contractor shall promptly notify the Architect
and the Construction Manager in writing, and any neces-
sary changes shall be accomplished by appropriate
Modification.
4.7.4 If the Contractor performs any Work knowing it
to be contrary to such laws, ordinances, rules and regula-
tions, and without such notice to the Architect and the
Construction Manager, the Contractor shall assume full
responsibility therefor and shall bear all costs attributable
thereto.
4.8 ALLOWANCES
4.8.1 The Contractor shall include in the Contract Sum
all allowances stated in the Contract Documents. Items
covered by these allowances shall be supplied for such
amounts and by such persons as the Construction Man-
ager may direct, but the Contractor will not be required
to employ persons against whom the Contractor makes a
reasonable obj-:?ction.
4.8.2 Unless otherwise provided in the Contract Docu-
ments:
.1 these allowances shall cover the cost to the
Contractor, Jess any applicable trade discount,
of the materials and equipment required by the
allowance, delivered at the site, and all appli-
cable taxes;
.2 the Contractor's costs for unloading and han-
dling on the site, labor, installation costs, over-
head, profit and other expenses contemplated
{or the original allowance shall be included in
the Contract Sum and not in the allowance;
.3 whenever the cost is more or less than the
allowance, the Contract Sum shall be adjusted
accordingly by Change Order. the amount of
which will recognize changes, if any. in han-
dling costs on the site, labor, installation costs,
overhead, profit and other expenses.
4.9 SUPERINTENDENT
4.9.1 The Contractor shall employ a competent superin-
tendent and necessary assistants who shall be in attend-
ance at the Project site during the progress of the Work.
The superintendent shall represent the Contractor and all
communications given to the superintendent shall be as
binding as if given to the Contractor. Important commu-
nications shall be confirmed in writing. Other communi-
cations shall be so confirmed on written request in each
case.
4.10 CONTRACTOR'S CONSTRUCTION SCHEDULE
4.10.1 The Contractor, immediately after being awarded
the Contract, shall prepare and submit for the Construc-
tion Manager's approval a Contractor's Construction
Schedule for the Work which shall provide {or expedi-
tious and practicable execution of the Work. This sched-
ule shall be coordinated by the Construction .\1anager
with the Project Construction Schedule. The Contractor's
Construction Schedule shall be revised as required by the
conditions of the Work and the Project, subject to the
Construction Manager's approval.
4.11 DOCUMENTS AND SAMPLES AT THE SITE
4.11.1 The Contractor shall maintain at the Project sile,
on a current basis, one record copy of all Drawings,
Specifications, Addenda, Change Orders and other Modi-
fications, in good order and marked currently to record
all changes made during construction, and approved Shop
Drawings, Product Data and Samples. These shall be
available to the Architect and the Construction Manager.
The Contractor shall advise the Construction Manager on
a current basis of all changes in the Work made during
construction.
4.12 SHOP DRAWINGS, PRODUCT DATA AND
SAMPLES
4.12.1 Shop Drawings are drawings, diagrams, schedules
and other data specially prepared {or the Work by the
Contractor or any Subcontractor, manufacturer, supplier
or distributor to illustrate some portion of the Work.
4.12.2 Product Data are illustrations, standard schedules,
performance charts, instructions, brochures, diagrams and
other information furnished by the Contractor to illustrate
a material, product or system for some portion of the
Work.
4.12.3 Samples are physical examples which illustrate
materials, equipment or workmanship, and establish
standards by which the Work will be judged.
4.12.4 The Contractor shall prepare, review, approve and
submit through the Construction Manager, with reason-
able promptness and in such sequence as to cause no de-
lay in the Work or in the work of the Owner or any sepa-
rate contractor, all Shop Drawings, Product Data and
Samples required by the Contract Documents. The Con-
tractor shall cooperate with the Construction Manager in
the Construction Manager's coordination of the Contrac-
tor's Shop Drawings, Product Data and Samples with
those of other separate contractors.
4.12.5 By preparing, approving and submitting Shop
Drawings, Product Data and Samples, the Contractor rep-
resents that the Contractor has determined and verified
all materials, field measurements and field construction
criteria related thereto, or will do 50 with reasonable
promptness, and has checked and coordinated the infor-
mation contained within such submittals with the require-
ments of the Work, the Project and the Contract Docu-
ments.
4.12.6 The Contractor shall not be relieved of responsibil-
ity for any deviation from the requirements of the Con-
tract Documents by the Architect's approval of Shop
Drawings, Product Data or Samples under Subparagraph
2.3.18, unless the Contractor has specifically informed the
Architect and the Construction Manager in writing of
such deviation at the time of submission and the Archi-
tect has given written approval to the specific devialion.
The Contractor shall not be relieved {rom responsibility
for errors or omissions in the Shop Drawings, Product
Data or Samples by the Architect's approval of them.
4.12.7 The Contractor shall direct specific attention, in
writing or on resubmitted Shop Drawings, Product Data
or Samples, to revisions other than those requested by the
Architect on previous submittals.
"I" DOCUMENT A.101/CM . GENERAL CONDITIONS OF THE co~'nRACT FOR CO~STRUCT'ON
CONSTRUCTION MAN."GEMENT EDITION . JUNE 1980 EDmON . AlA" . ~ 1980 . THE
A'URICAN "STITUTE OF ARCHITECTS, 1735 NEW YORK AVE.. 'W.. WASHINGTON, D.C. ;!OO(lo.
A201/CM -1980 10
".;,'~~; t'.;c-t!_ 'I'>~::::-'........-;:,;.. .",~'i....,.,
4.12.8 No portion of the \^.'ork requiring submission of a
Shop Drawing, Product Data or Sample shall be com-
menced until the submittal has been approved by the
Architect as provided in Subparagraph 2.3.18. All such
portions of the Work shall be in accordance with ap-
proved submittals.
4.13 USE OF SITE
4.13.1 The Contractor shall confine operations at the site
to areas permitted by law, ordinances, permits and the
Contract Documents, and shall not unreasonably encum-
ber the site with any materials or equipment.
4.13.2 The Contractor shall coordinate all of the Contrac-
tor's operations with, and secure approval from, the Con-
struction Manager before using any portion of the site.
4.14 CUTTING AND PATCHING OF WORK
4.14.1 The Contractor shall be responsible for all cutting,
fitting or patching that may be required to complete the
\Vork or to make its several parts fit together properly.
4.14.2 The Contractor shall not damage or endanger any
portion of the Work or the work of the Ov.mer or any
separate contractors by cutting, patching or otherwise
altering any work, or by excavation. The Contractor shall
not cut or otherwise alter the work of the Owner or any
separate contractor except with the written consent of the
Owner and of such separate con\ractor. The Contractor
shall not unreasonabl\' withhold from the Owner or any
separate contractor consent to cutting or otherwise alter-
ing the'Work.
4.15 CLEANING UP
4.15.1 The Contractor shall at all times keep the premises
free from accumulation of waste materials or rubbish
caused by the Contractor's operations. At the completion
of the Work, the Contractor shall remove all the Contrac-
tor's waste materials and rubbish from and about the
Project as well as all the Contractor's tools, construction
equipment. machinery and surplus materials.
4.15.2 If the Contractor fails to clean up at the comple-
tion of the Work, the Owner may do so as provided in
Paragraph 3.4 and the cost thereof shall be charged to the
Contractor.
4.16 COMMUNICATIONS
4.16.1 The Contractor shall forward all communications
to the Owner and the Architect through the Construction
Manager.
4.17 ROYALTIES AND PATENTS
4.17.1 The Contractor shall pay all royalties and license
fees, shall defend all suits or claims for infringement of
any patent rights and shall save the Owner and the Con-
struction Manager harmless from loss on account thereof,
except that the Owner, or the Construction Manager as
the case may be, shall be responsible for all such loss
when a particular design, process or the product of a par-
ticular manufacturer or manufacturers is selected by such
person or such person's agent. If the Contractor, or the
Construction Manager as the case may be, has reason to
believe that the design, process or product selected is an
infringement of a patent, that party shall be responsible
for such loss unless such information is promptly given to
the others and also to the Architect.
4.18 INDEMNIFICATION
4.18.1 To the fuilest extent permitted by law, the Con-
tractor shall indemnify and hold harmless the Owner, thl
Architect. the Construction Manager, and their agents ana
employees from and against all claims, damages, losses
and expenses, including, but not limited to, attorneys'
fees arising out of or resulting from the performance of
the Work, provided that any such claim, damage, loss or
expense (1) is attributable to bodily injury, sickness, dis-
ease or death, or to injury to or destruction oi tangible
property (other than the Work itself) including the loss of
use resulting therefrom, and (2) is caused in whole or in
part by any negligent act or omission oi the Contractor,
any Subcontractor. anyone directly or indirectly employed
by any of them or anyone for whose acts any of them
may be liable, regardless of whether or not it is caused
in part by a party indemnified hereur.der. Such obligation
shall not be construed to negate, abridge or otherwise
reduce any other right or obligation of indemnity which
would othen,vise exist as to any party or person described
in this Paragraph 4.18.
4.18.2 In any and all claims against the Owner, the Archi-
tect, the Construction Manager or any of their agents or
employees by any employee of the Contractor, any Sub-
contractor, anyone directly or indirectly employed by any
of them or anyone for whose acts any of them may be
liable, the indemnification obligation under this Para-
graph 4.18 shall not be limited in any way by any limita-
tion on the amount or type of damages, compensation or
beneiits payable by or for the Contractor or any Sub-
contractor under workers' or workmen's compensation
acts, disability benefit acts or other employee benefit acts.
4.18.3 The obligations of the Contractor under this Para
graph 4.18 shall not extend to the liability of the Architec,
or the Construction Manager, their agents or employees,
arising out of (1 j the preparation or approval of maps,
drawings, opinions, reports, surveys, Change Orders, de-
signs or specifications, or (2) the giving of or the failure to
give directions or instructions by the Architect or the
Construction Manager, their agents or employees, pro-
vided such giving or failure to give is the primary cause
of the injury or damage.
ARTICLE 5
SUBCONTRACTORS
5.1 DEFINITION
5.1.1 A Subcontractor is a person or entity who has a
direct contract with the Contractor to perform any of the
Work at the site. The term Subcontractor means a Sub-
contractor or a Subcontractor's authorized representative.
The term Subcontractor does not include any sepa rate
contractor or any separate contractor's subcontractors,
5.1.2 A Sub-subcontractor is a person or entity who has
a direct or indirect contract with a Subcontractor to per-
form any of the Work at the site, The term Sub-subcon-
tractor means a Sub-subcontractor or an authorized rep-
resen ta tive thereof.
5.2 AWARDS OF SUBCONTRACTS AND OTHER
CONTRAaS FOR PORTIONS OF THE WORK
5.2.1 Unless otherwise required by the Contract Docu
11 A201/CM - 1980
,\IA OOCUMENT A201/CM . GESERAL CosDITIONS OF THE COSTR,\CT FOR COSSTRUCTlO~
CONSTRUCTION M."NAGEME~T EDITION . JUNE 1980 EDITION . AlAe . @ 1980 . THE
AMERICA~ INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE" N,W., WASHINGTOS, o,c. 2000&
\)0" cu ""1~. I t,..,li....,.,....c..:..4 ... 1~""'.n('l"\l"l"in,., \,h'~'~c:. tIC:; ~rv'vr;~ht 12W$ 2,,(1 i5 SUb:K1 to::- lpo~l orosecution
ments Or the Bidding Documents, the Contractor, as soon
as practicable after the award of the Contract, shall fur-
nish to the Construction Manager in writing for review
by the Owner, the Architect and the Construction Man-
ager, the names of the persons or entities (including those
who are to furnish materials or equipment fabricated to
a special design) proposed for each of the principal por-
tions of the Work. The Construction Manager will
promptly reply to the Contractor in writing stating
whether or not the Owner, the Architect or the Con-
struction Manager, after due investigation, has reasonable
objection to any such proposed person or entity. Failure
of the Construction Manager to reply promptly shall con-
stitute notice of no reasonable objection.
5.2.2 The Contractor shall not contract with any such
proposed person or entity to whom the Owner, the Ar-
chitect or the Construction Manager has made reasonable
objection under the provisions of Subparagraph 5.2.1. The
Contractor shall not be required to contract with anyone
to whom the Contractor has a reasonable objection.
5.2.3 If the Owner, the Architect or the Construction
Manager has reasonable objection to any such proposed
person or entity, the Contractor shall submit a substitute
to whom the Owner, the Architect and the Construction
Manager have no reasonable objection, and the Contract
Sum shall be increased or decreased by the difference in
cost occasioned by such substitution and an appropriate
Change Order shall be issued; however, no increase in
the Contract Sum shall be allowed for any such substitu-
tion unless the Contractor has acted promptly and re-
sponsively in submitting names as required by Subpara-
graph 5.2.1.
5.2.4 The Contractor shall make no substitution for any
Subcontractor, person or entity previously selected if the
Owner, the Architect or the Construction Manager makes
reasonable objection to such substitution.
5.3 SUBCONTRACTUAl RELATIONS
5.3.1 By an appropriate agreement, written where legally
required for validity, the Contractor shall require each
Subcontractor, to the extent of the Work to be performed
by the Subcontractor, to be bound to the Contractor by
the terms of the Contract Documents, and to assume to-
ward the Contractor all the obligations and responsibili-
ties which the Contractor. by these Documents, assumes
toward the Owner, the Architect and the Construction
Manager. Said agreement shall preserve and protect the
rights of the Owner, the Architect and the Construction
Manager under the Contract Documents with respect to
the Work to be performed by the Subcontractor so that
the subcontracting thereof will not prejudice such rights,
and shall allow to the Subcontractor, unless specifically
provided otherwise in the Contractor-Subcontractor
Agreement. the benefit of all rights, remedies and redress
against the Contractor that the Contractor, by these Docu-
ments, has against the Owner. Where appropriate, the
Contractor shall require each Subcontractor to enter into
similar agreements with their Sub-subcontractors. The
Contractor shall make available to each proposed Sub-
contractor, prior to the execution of the Subcontract,
copies of the Contract Documents to which the Subcon-
tractor will be bound by this Paragraph 5.3, and identify
to the Subcontractor any terms and conditions of the pro-
posed Subcontract which may be at variance ",,;;11 the
Contract Documents. Each Subcontractor shall similarly
make copies of such Documents available to their Sub-
subcontractors.
ARTICLE 6
WORK BY OWNER OR BY
SEPARATE CONTRACTORS
6.1 OWNER'S RIGHT TO PERfORM WORK AND TO
AWARD SEPARATE CONTRACTS
6.1.1 The Owner reserves the right to perform work re-
lated to the Project with the Owner's own forces, and to
award separate contracts in connection with other por-
tions of the Project or other work on the site under these
or similar Conditions of the Contract. If the Contractor
claims that delay, damage or additional cost is involved
because of such action by the Owner, the Contractor shall
make such claim as provided elsewhere in the Contract
Documents.
6.1.2 When separate contracts are awarded for different
portions of the Project or other work on the site, the term
Contractor in the Contract Documents in each case shall
mean the Contractor who executes each separate Owner-
Contractor Agreement.
6.1.3 The Owner will provide for the coordination of the
work of the Owner's own forces and of each separate
contractor with the Work of the Contractor, who shall
cooperate therewith as provided in Paragraph 6.2.
6.2 MUTUAL RESPONSIBILITY
6.2.1 The Contractor shall afford the Owner, the Con-
struction Manager and separate contractors reasonable
opportunity for the introduction and storage of their ma-
terials and equipment and the execution of their work,
and shall connect and coordinate the Work with theirs
as required by the Contract Documents.
6.2.2 If any part of the Contractor's Work depends for
proper execution or results upon the work of the Owner
or any separate contractor, the Contractor shall, prior to
proceeding with the Work, promptly report to the Con-
struction Manager any apparent discrepancies or defects
in such other work that render it unsuitable for such
proper execution and results. Failure of the Contractor so
to report shall constitute an acceptance of the Owner's
or separate contractor's work as fit and proper to receive
the Work, except as to defects which may subsequently
become apparent in such work by others.
6.2.3 Any costs caused by defective or ill-timed work
shall be borne by the party responsible therefor.
6.2.4 Should the Contractor wrongfully cause damage to
the work or property of the Owner, or to other work or
property on the site, the Contractor shall promptly rem-
edy such damage as provided in Subparagraph 10.2.5.
6.2.5 Should the Contractor wrongfully delay or cause
damage to the work or property of any separate contrac-
tor, the Contractor shall, upon due notice. promptly at-
tempt to settle with such other contractor by agreement,
or otherwise to resolve the dispute. If such separate con-
tractor sues or initiates an arbitration proceeding against
the Owner on account of any delay or damage alleged to
have been caused by the Contractor, the Owner shall
AlA DOCUMENT A201/CM . GENERAL CONDITIONS Of THE CO!>;TRACT fOR CONSTRUCTION
COr-;STRUCTIO:-.: /l.1ANAGEMENT EDITION . JUNE 1980 EDITIO!l: . AlAe . @ 1980 . THE
AMERICAN I'STITUTE Of ARCHITECTS, 173S NEW YORK AVE" N.W., WASHINGTON, D.C. 20006
A201/CM - 1980 12
notify the Contractor who sh,,11 defend such proceedings
at the Owner's expense, and if any judgment or award
against the Owner arises therefrom, the Contractor shall
payor satisfy it and shall reimburse the Owner for all
attorneys' fees and court or arbitration costs which the
Owner has incurred,
6.3 OWNER'S RIGHT TO CLEAN UP
6.3.1 If a dispute arises between the Contractor and
separate contractors as to their responsibility for cleaning
up as required by Paragraph 4.15, the Owner may clean
up and charge the cost thereof to the contractors respon-
sible therefor as the Construction Manager shall deter-
mine to be just.
ARTICLE 7
MISCELLANEOUS PROVISIONS
7.1 GOVERNING lAW
7.1.1 The Contract shall be governed by the law of the
place where the Project is located.
7.2 SUCCESSORS AND ASSIGNS
7.2.1 The Owner and the Contractor, respectively, bind
themselves, their partners, successors, assigns and legal
representatives to the other party hereto and to the part-
ners, successors, assigns and legal representatives of such
other party with respect to all covenants, agreements and
obligations contained in the Contract Documents. Neither
party to the Contract shall assign the Contract or sublet it
as a whole without the written consent of the other.
7.3 WRITTEN NOTICE
7.3.1 Written notice shall be deemed to have been duly
served if delivered in person to the individual or mem-
ber of the firm or entity or to an officer of the corpora-
tion for whom it was intended, or if delivered at or sent
by registered or certified mail to the last business address
known to the party giving the notice.
7.4 CLAIMS FOR DAMAGES
7.4.1 Should either party to the Contract suffer injury or
damage to person or property because of any act or omis-
sion of the other party or of any of the other party's
employees, agents or others for whose acts such party is
legally liable, claim shall be made in writing to such
other party within a reasonable time after the first observ-
ance of such injul) or damage.
7.5 PERFORMANCE BOND AND LABOR AND
MATERIAL PAYMENT BOND
7.5.1 The Owner shall have the right to requi re the
Contractor to furnish bonds covering the faithful perform-
ance of the Contract and the payment of all obligations
arising thereunder if and as required in the Bidding Doc-
uments or the Contract Documents.
7.6 RIGHTS AND REMEDtES
7.6.1 The duties and obligations imposed by the Con-
tract Documents and the rights and remedies available
thereunder shall be in addition to, and not a limitation of,
any duties, obligations, rights and remedies otherwise im-
posed or available by law,
7.6.2 No action or failure to act by the Owner, the Ar-
chitect, the Comtruction Manager or the Contractor shall
constitute a waiver of any right or duty afforded any of
them under the Contract, nor shall any such action or
failure to act constitute an approval of or acquiescence in
any breach thereunder, except as may be specifically
agreed in writing.
7.7 TESTS
7.7.1 If the Contract Documents, laws, ordinances, rules,
regulations or orders of any public authority having juris-
diction require any portion of the Work to be inspected,
tested or approved, the Contractor shall give the Architect
and the Construction Manager timely notice of its readi-
ness so the Architect and the Construction Manager may
observe such inspection, testmg or approval. The Con-
tractor shall bear all costs of such inspections, tests or
approvals conducted by public authorities. Unless other-
wise provided, the Owner shall bear all costs of other in-
spections, tests or approvals.
7.7.2 If the Architect or the Construction Manager deter-
mines that any Work requires special inspection, testing
or approval which Subparagraph 7.7.1 does not include,
the Construction Manager will, upon written authoriza-
tion from the Owner, instruct the Contractor to order
such special impection, testing or approval, and the Con-
tractor shall give notice as provided in Subparagraph
7.7.1. If such special inspection or testing reveals a failure
of the Work to compiy with the requirements of the Con-
tract Documents, the Contractor shall bear all costs
thereof, including compensation for the Architect's and
the Construction Manager's additional services made nec-
essary by such failure; otherwise the O\\ner shall bear
such costs, and an c: ppropriate Change Order shall be
issued.
7.7.3 Required certiiicates of inspection, testing or ap-
proval shall be secu'ed by the Contractor and the Con-
tractor shall promptly deliver them to the Construction
Manager iar transmi::al to the Architect.
7.7.4 If the Architect or the Construction Manager wishes
to observe the inspections, tests or approvals required by
the Contract Documents. they will do so promptly and,
where practicable, at the source of supply.
7.8 INTEREST
7.8.1 Payments due and unpaid under the Contract Doc-
uments shall bear interest from the date pavment is due
at such ra:e as the parties may agree upor in writing or,
in the absence thereof, at the legal rate prevailing at the
place of the Project.
7.9 ARBITRA TION
7.9.1 All claims, di;putes and other matters in question
between the Contractor and the Owner ari;ing out of or
relating to the Contrc:ct Documents or the breach thereof.
except as prO\ided ;:"1 Subparagraph 2.3.14 with respect
to the Architect's decisions on matters relating to artistic
effect, and except for claims which have been waived by
the making or accep~ance of iinal payment as provided
by Subparagraphs 9.?A through 9,9.6. inclusive, shall be
decided bv arbitration in accordance with the Construc-
tion Industry Arbitration Rules of the American Arbitra-
tion Association then obtaining unless the parties mutually
13 A201/CM - 1980
AlA DOCUMENT A201/CM . GE,,~>'L CO-':DIT"O-':S OF THE CONTRACT FOt CO:-':SHL'CTlON
CONSTRUCTlOS MANAGEMEST ,:J1TI0" . l"_"E 1980 EDITION . AlAe . ~ 1980 . THE
AMERICAN INSTITUTE OF ARCH1;ECTS. ,;35 :-'E",\' YORK AVE., N.W" WASH1'GTON, D.C. 2()()()b
"" ~,,".l""'. 11...1._...__. "" _...,....,.........~_..;...._ :^I~fDc:':! c:: ....",..\.'.,,-...,4 I;3VJ~ ~...,:-' ic: ~ _:hiect.: 'co~f (H'O'.:iecufion.
agree otherwise. No arbitration arising out of or relating
to the Contract Documents shall include, by consolida-
tion, jOinder or in any other manner, the Architect, the
Construction Manager, their employees or consultants
except by written consent containing a specific reference
to the Owner-Contractor Agreement and signed by the
Architect, the Construction Manager, the Owner, the
Contractor and any other person sought to be joined. No
arbitration shall include by consolidation, joinder or in
any other manner, parties other than the Owner, the
Contractor and any other persons substantially involved
in a common question of fact or law, whose presence is
required if complete relief is to be accorded in the arbi-
tration. No person other than the Owner or the Contrac-
tor shall be included as an original third party or addi-
tional third party to an arbitration whose interest or re-
sponsibility is insubstantial. Any consent to arbitration
involving an additional person or persons shall not con-
stitute consent to arbitration of any dispute not described
therein or with any person not named or described
therein. The foregoing a&"eement to arbitrate and any
other agreement to arbitrate with an additional person or
persons duly consented to by the parties to the Owner-
Contractor Agreement shall be specifically enforceable
under the prevailing arbitration law. The award rendered
by the arbitrators shall be final. and judgment ma~ be en-
tered upon it in accordance with applicable la\\ in any
court having jurisdiction thereof.
7.9.2 Notice of the demand for arbitration shall be filed
in writing with the other party to the Owner-Contractor
Agreement and with the American Arbitration Associa-
tion, and a copy shall be filed with the Architect and the
Construction Manager. The demand for arbitration shall
be made within the time limits specified in Subparagraph
2.3.15 where applicable. and in all other cases within a
reasonable time after the claim. dispute or other matter
in question has arisen; and in no event shall it be made
after the date when institution of legal or equitable pro-
ceedings based on such claim. dispute or other matter in
question \,vould be barred by the applicable statute of
limitations.
7.9.3 Unless otherwise agreed in writing. the Contractor
shall carry on the Work and maintain its progres~ during
any arbitration proceedings. and the Owner shall con-
tinue to make payments to the Contractor in accordance
with the Contract Documents.
ARTICLE 8
TIME
8.1 DEFINITIONS
8.1.1 Unless otherwise provided, the Contract Time is
the period of time allotted in the Contract Docurr.ents for
Substantial Completion of the Work as defined in Sub-
paragraph 8.1.3, including authorized adjustments :hereto.
8.1.2 The date of commencement of the War:' is the
date e~tablished in a notice to proceed. If there is no no-
tice to proceed. it shall be such other date a~ may be
established in the Owner-Contractor Agreement or else-
where in the Contract Document~.
8.1.3 The Date of Substantial Completion of the Work
or designated portion thereof is the Date certified by the
Architect when construction is sufficiently complete, in
accordance with the Contract Documents, so that the
Owner or separate contracto~s c~n occupy or utilize the
Work or a designated portion thereof lbr the use (or
which it is intended.
8.1.4 The Date of Substantial Completion of the Project
or designated portion thereof is the Date certified by the
Architect when construction is sufficiently complete so
the Owner can occupy or utilize the Project or designated
portion thereof for the use for which it was intended.
8.1.5 The term day as used in the Contract Documents
shall mean calendar day unless specifically designated
otherwise.
8.2 PROGRESS AND COMPLETION
8.2.1 All time limits stated in the Contract Documents
are of the essence of the Contract.
8.2.2 The Contractor shall begin the Work on the date
of commencement as defined in Subparagraph 8.1.2. The
Contractor shall carry the Work forward expeditiously
with adequate forces and shall achieve Substantial Com-
pletion of the Work within the Contract Time.
8.3 DELAYS AND EXTENSIONS OF TIME
8.3.1 If the Contractor is delayed at any time in the
progress of the Work by any act or neglect of the Owner,
the Architect, the Construction Manager, any of their em-
ployees. any separate contractor employed by the Owner,
or by changes ordered in the Work, labor disputes, fire.
unusual delay in transportation. adverse weather condi-
tions not reasonably anticipatable, unavoidable casualties,
any causes beyond the Contractor's control, delay author-
ized by the Owner pending arbitration. or by any other
cause which the Construction Manager determines may
justify the delay, then the Contract Time shall be ex-
tended by Change Order for such reasonable time as the
Construction Manager may determine.
8.3.2 Any claim for extension of time shall be made in
writing to the Construction Manager not more than
twenty days after the commencement of the delay; other-
wise it shall be waived. In the case of J continuing dela\
only one claim is necessary. The Contractor shall provide
an estimate of the probable efiect of such delay on the
progress of the Work.
8.3.3 If no agreement is made stating the dates upon
which interpretations as provided in Subparagraph 2.3,11
shall be furnished. then no c1,lim for delay shall be
allowed on account of failure to furnish such interpreta-
tions until iifteen da~ s after \\ ritten request is made for
them. and not then unless such claim is reasonable,
8.3.4 This Paragraph 8.3 does not exclude the recoverv
of damages for delay by either party under other provi-
sions of the Contract Document<,
ARTICLE 9
PAYMENTS AND COMPLETION
9.1 CONTRACT SUM
9.1.1 The Contract Sum is qaled in the Owner-Contrac-
tor Agreement and, including authorized adjustment~
thereto. is the total amount payable by the Owner to the
Contractor for the performance of the Work under the
Contract Documents.
A'A DOCUMENT A201iCM . GE~ERAl CO:-;DITIO'-'S OF THE CC'TRACT FOR C01'STRUCTIO:-;
COSSTRLCTIO~ .\IA:-':AGEME1'T EDITION . ILSE 1980 EDIlIO"" . AI^~ . @ 1980 . THE
AMERICA" INSTITUE OF ARCHITECTS, 1i3; 'E\\' YORK AVE.. "W., WASHINGTON, D.C. ~ A201/CM -1980 14
~-~:,... .- ~~. '.....~....~- --,
9.2 SCHEDULE OF VALUES
9.2.1 Before the firq Application for Payment. the Con-
tractor shall submit to the Construction Manager a
schedule of values allocated to the various portions of the
Work, prepared in such form and supported by such data
to substantiate its accuracy as the Architect and the Con-
struction Manager may require, This schedule, unless
objected to by the Construction Manager or the Architect,
shall be used only as a basis for the Contractor's Applica-
tions for Payment.
9.3 APPLICATIONS FOR PAYMENT
9.3.1 At least fifteen days before the date for each
progress payment established in the Owner-Contractor
Agreement, the Contractor shall submit to the Construc-
tion Manager an itemized Application for Payment, notar-
ized if required, supported by such data substantiating
the Contractor's right to payment as the Owner, the Ar-
chitect or the Construction Manager may require, and re-
flecting retainage, if any, as provided elsewhere in the
Contract Documents, The Construction Manager will as-
~emble the Application with similar applications from
other contractors on the Project into a combined Project
Application for Payment and forward it with recommen-
dations to the Architect within seven days.
9.3.2 Unless otherwise provided in the Contract Docu-
ments, payments will be made on account of materials or
equipment not incorporated in the Work but delivered
and suitably stored at the site and, if approved in advance
by the Owner, payments may similarly be made for mate-
rials or equipment suitably stored at some other loca-
tion agreed upon in writing. Payments for materials or
equipment stored on or off the site shall be conditioned
upon submission by the Contractor of bills of sale or
such other procedures satisfactory to the Owner to estab-
lish the Owner's title to such materials or equipment or
otherwise protect the Owner's interest, including applica-
ble insurance and transportation to the site for those
materials and equipment stored on the site.
9.3.3 The Contractor warrants that title to all Work,
materials and equipment covered by an Application for
Payment will pass to the Owner either by incorporation
in the construction or upon receipt of payment by the
Contractor, whichever occurs first. free and clear of all
liens, claims, security interests or encumbrances, herein-
aiter referred to in this Article 9 as "liens"; and that no
\\lork, materials or equipment covered by an Application
for Payment will have been acquired by the Contractor,
or by any other person performing Work at the site or
furnishing materials and equipment for the Project, sub-
ject to an agreement under which an interest therein or
an encumbrance thereon is retained by the seller or oth-
erwise imposed by the Contractor or such other person,
9.4 CERTIFICATES FOR PAYMENT
9.4.1 The Architect will, within seven days after the re-
ceipt of the Project Application for Payment with the rec-
ommendations of the Construction Manager, review the
Project Application for Payment and either issue a Project
Certificate for Payment to the Owner with a copy to the
Construction Manager for distribution to the Contractor
for such amounts as the Architect determines are prop-
erly due, or notify the Construction Manager in writing of
the reasons for withholding a Certificate as provided in
Subparagraph 9.6.1, Such notification will be forwarded
to the Contractor by the Construction Manager.
9.4.2 The issuance of a Project Certificate for Pa)'ment
will constitute a representation by the Architect to the
Owner that, based on the Architect's observations at the
site as provided in Subparagraph 2.3.4 and the data com-
prising the Project Application for Payment, the Work has
progressed to the point indicated; that, to the best of the
Architect's knowledge, information and belief, the quality
of the Work is in accordance with the Contract Docu-
ments (subject to an evaluation of the Work for conform-
ance with the Contract Documents upon Substantial
Completion of the Work, to the results of any subsequent
tests required by or performed under the Contract Docu-
ments, to minor deviations from the Contract Documents
correctable prior to completion, and to any specific quali-
fications stated in the Certificate); and that the Contrac-
tor is entitled to payment in the amount certified. How-
ever, by issuing a Project Certificate for Pa\ment. the Ar-
chitect shall not thereby be deemed to rep'resent that the
Architect has made exhaustive or continuous on-site in-
spections to check the quality or quantity of the Work,
has reviewed the construction means, methods, tech-
niques, sequences or procedures, or has made any exam-
ination to ascertain how or for what purpose the Contrac-
tor has used the monies previously paid on account of the
Contract Sum.
9.5 PROGRESS PAYMENTS
9.5.1 After the Architect has issued a Project Certificate
for Payment, the Owner shall make payment in the man-
ner and within the time provided in the Contract Docu-
ments.
9.5.2 The Contractor shall promptly pay each Subcon-
tractor upon receipt of payment from the Owner, out of
the amount paid to the Contractor on account of such
Subcontractor's Work, the amount to which said Subcon-
tractor is entitled, reflecting the percentage actually re-
tained, if any, from payments to the Contractor on ac-
count of such Subcontractor's Work. The Contractor shall,
by an appropriate agreement with each Subcontractor,
require each Subcontractor to make payments to their
Sub-subcontractors in similar manner.
9.5.3 The Architect may, on request and at the Archi-
tect's discretion, furnish to any Subcontractor, if prac-
ticable, information regarding the percentages of com-
pletion or the amount, applied for by the Contractor and
the action taken thereon by the Architect on account of
Work done by such Subcontractor.
9.5.4 Neither the Owner, the Architect nor the Construc-
tion I\1anager shall have any obligation to payor to see to
the payment of any monies to any Subcontractor except
as may otherwise be required by law.
9.5.5 No certification of a progress payment, any prog-
ress payment, or any partial or entire use or occupancy
oi the Project by the Owner, shall constitute an accept-
ance of any Work not in accordance with the Contract
Documents.
9.6 PAYMENTS WITHHELD
9.6.1 The Architect, following consultation with the
Construction Manager, may decline to certify payment
15 A201/CM -1960
AlA DOCUMENT A201/CM . GENERAL CO~DITIO"S OF THE CONTRACT FOIt CONSTRl'CTION
COSSTRUCTION MAt\AGEMENT EDITION . jU"'E 1980 EDITION . AlA- . @ 1980 . THE
AMERICAN INSTITUTE OF ARCHITECTS, 1735 NEW YORK AVE.. N.W., WASHI"'GTON, D.C. 20006
'.'~D'."Ur:. 11....f;,-"'...t:-c..t'..... .....tr -'''''''''''t!"'n ,.;.....l'::l.t',~ 11 ~ ,.."n\f~;...t-.t '~.ws and i~ subll?c. tt"\ I~";!il o"O~p~utlo".
and may withhold the Certificate in whole or in part to
the extent necessary to reasonably protect the 0" ner, if,
in the Architect's opinion, the Architect is unable to make
representations to the Owner as provided in Subpara-
graph 9.4.2. If the Architect is unable to make representa-
tions to the Owner as provided in Subparagraph 9.4.2,
and to certify payment in the amount of the Project Ap-
plication, the Architect will notify the Construction Man-
ager as provided in Subparagraph 9.4.1, If the Contractor
and the Architect cannot agree on a revised amount, the
Architect will promptly issue a Project Certificate for Pay-
ment for the amount for which the Architect is able to
make such representations to the Owner. The Architect
may also decline to certify payment or, because of subse-
quently discovered evidence or subsequent observations,
the Architect may nullify the whole or any part of any
Project Certificate for Payment previously issued to such
extent as may be necessary, in the Architect's opinion, to
protect the Owner from loss because of:
.1 defective Work not remedied;
.2 third party claims filed or reasonable evidence in-
dicating probable filing of such claims;
.3 failure of the Contractor to make payments prop-
erly to Subcontractors, or for labor, materials or
equipment;
.4 reasonable evidence that the Work cannot be com-
pleted for the unpaid balance of the Contract Sum;
.5 damage to the Owner or another contractor;
.6 reasonable evidence that the Work will not be
completed within the Contract Time; or
.7 persistent failure to carry out the Work in accord-
ance with the Contract Documents.
9.6.2 When the grounds in Subparagraph 9.6.1 above
are removed, payment shall be made for amounts with-
held because of them.
9.7 FAILURE OF PAYMENT
9.7.1 If the Construction Manager should fail to issue
recommendations within seven days of receipt of the
Contractor's Application for Payment, or if, through no
fault of the Contractor, the Architect does not issue a
Project Certificate for Payment within seven days after
the Architect's receipt of the Project Application for Pay-
ment, or if the Owner does not pay the Contractor within
seven days after the date established in the Contract Doc-
uments any amount certified by the Architect or awarded
by arbitration, then the Contractor may, upon seven addi-
tional days' written notice to the Owner, the Architect
and the Construction Manager, stop the Work until pay-
ment of the amount owing has been received. The Con-
tract Sum shall be increased by the amount of the Con-
tractor's reasonable costs of shut-down, delay and start-
up, which shall be effected by appropriate Change Order
in accordance with Paragraph 12.3.
9.8 SUBSTANTIAL COMPLETION
9.8.1 When the Contractor considers that the Work, or a
designated portion thereof which is acceptable to the
Owner, is substantially complete as defined in Subpara-
graph 8.1.3, the Contractor shall prepare for the Construc-
tion Manager a list of items to be completed or cor-
rected. The failure to include any items on such list does
not alter the responsibility of the Contractor to complete
all Work in accordance with the Contract Documents.
When the Architect, on the basis of inspection and con-
sultation with the Construction Manager, determines that
the Work or designated portion thereof is substantially
complete, the Architect will then prepare a Certificate of
Substantial Completion of the Work which shall establish
the Date of Substantial Completion of the Work, shall
state the responsibilities of the Owner and the Contractor
for security, maintenance, heat, utilities. damage to the
Work and insurance, and shall fix the time within which
the Contractor shall complete the items listed therein.
The Certificate of Substantial Completion of the Work
shall be submitted to the Owner and the Contractor for
their written acceptance of the responsibilities assigned to
them in such Certificate.
9.8.2 Upon Substantial Completion of the Work or desig-
nated portion thereof, and upon application by the Con-
tractor and certification by the Architect. the Owner shall
make payment, reilecting adjustment in retainage, if any,
for such Work or portion thereof as provided in the Con-
tract Documents.
9.8.3 When the Architect, on the basis of inspections,
delermines that the Project or designated portion thereof
is substantially complete, the Architect will then prepare
a Certificate of Substantial Completion of the Project
which shall establish the Date of Substantial Completion
ot the Project and fix the time within which the Contrac-
tor shall complete any uncompleted items on the Certif-
icate of Substantial Completion of the Work.
9.8.4 Warranties required by the Contract Documents
shall commence on the Date ot Substantial Completion of
the Project or designated portion thereof unless other-
wise provided in the Certificate of Substantial Comple-
tion of the \Vork or designated portion thereof.
9.9 FINAL COMPLETION AND FINAL PAYMENT
9.9.1 Following the Architect's issuance of the Certiiicate
of Substantial Completion of the Work or designated por-
tion thereof, and the Contractor's completion of the
Work, the Contractor shall forward to the Construction
Manager a written notice that the Work is ready for final
inspection and acceptance, and shall also forward to the
Construction Manager a final Application for Payment.
Upon receipt, the Construction .\\anager will make the
necessary evaluations and forward recommendations to
the Architect who will promptly make such inspection.
When the Architect finds the Work acceptable under
the Contract Documents and the Contract fully per-
formed, the Architect will issue a Project Certificate for
Payment which will approve the iinal payment due the
Contractor. This approval will constitute a representation
that, to the best of the Architect's knowledge, informa-
tion and belief, and on the basis of observations and in-
spections, the Work has been completed in accordance
with the Terms and Conditions of the Contract Docu-
ments and that the entire balance found to be due the
Contractor, and noted in said Certificate, is due and pay-
able. The Architect's approval of said Project Certificate
for Payment will constitute a further representation that
the conditions precedent to the Contractor's being en-
titled to final payment as set forth in Subparagraph 9.9.2
have been fulfilled.
All. DOCUMENT A201/CM . GENERAL CONDITlO....S OF THE CO!'.iTRACT FOR CONSTRUCTION
CO,,"'STRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE
AMERICAN INSTITUTE OF ARCHITECTS. 173S NEW YORK AVE.. KW.. WASHI!'GTON, D.C 20006
A201/CM -1980 16
V/" PN,...,r:. ! 'f"'ltr....pnct:l.~ I""lh,...,fl""\('("trr'/i,,-::; vi~l("~('~ I." S CC'::J\'''~O'''1 fEW.>"; ;incf ic; ~; 'biecf '(' ie-gaf oro~ecution.
9.9.2 Neither the final payment nor the remaining retain-
age shall become due until the Contractor submits to the
Architect, through the Construction Manager, (1) an affi-
davit that all payrolls, bills for materials and equipment,
and other indebtedness connected with the Work for
which the 6wner or the Owner's property might in any
way be responsible, have been paid or otherwise satis-
fied, (2) consent of surety, if any, to final payment, and
(3) if required by the Owner, other data establishing pay-
ment or satisfaction of all such obligations, such as re-
ceipts, releases and waivers of liens arising out of the
Contract. to the extent and in such form as may be desig-
nated by the Owner. If any Subcontractor refuses to fur-
nish a release or waiver required by the Owner, the Con-
tractor may furnish a bond satisfactory to the Owner to
indemnify the Owner against any such lien. If any such
lien remains unsatisfied after all payments are made, the
Contractor shall refund to the Owner all monies that the
latter may be compelled to pay in discharging such lien,
including all costs and reasonable attorneys' fees.
9.9.3 If, after Substantial Completion of the Work, final
completion thereof is materially delayed through no fault
of the Contractor or by the issuance of Change Orders
affecting final completion, and the Construction Manager
so confirms, the Owner shall, upon application by the
Contractor and certification by the Architect and without
terminating the Contract, make payment of the balance
due for that portion of the Work fully completed and
accepted. If the remaining balance for Work not fully
completed or corrected is less than the retainage stipu-
lated in the Contract Documents, and if bonds have been
furnished as provided in Paragraph 7.5, the written con-
sent of the surety to the payment of the balance due for
that portion of the Work fully completed and accepted
shall be submitted by the Contractor to the Construction
Manager prior to certification of such payment. Such pay-
ment shall be made under the Terms and Conditions gov-
erning final payments, except that it shall not constitute a
waiver of claims.
9.9.4 The making of final payment shall, after the Date
of Substantial Completion of the Project, constitute a
waiver of all claims by the Owner except those arising
from:
.1 unsettled liens;
.2 faulty or defective Work appearing after Substan-
tial Completion of the Work;
.3 failure of the Work to comply with the require-
ments of the Contract Documents; or
.4 terms of any special warranties required by the
Contract Documents.
'9.9.5 The acceptance of final payment shall, after the
Date of Substantial Completion of the Project, constitute
a waiver of all claims by the Contractor except those
pre\ iously made in writing and identified by the Contrac-
tor as unsettled at the time of the final Application for
Payment.
9.9.6 All provisions of this Agreement. including with-
out limitation those establishing obligations and proce-
dures, shall remain in full force and effect notwithstand-
ing the making or acceptance of final payment prior to
the Date of Substantial Completion of the Project.
ARTICLE 10
PROTECTION OF PERSONS AND PROPERTY
10.1 SAFETY PRECAUTIONS AND PROGRAMS
10.1.1 The Contractor shall be responsible for initiating,
mainlaining and supervising all safety precautions and
programs in connection with the Work.
10.2 SAFETY OF PERSONS AND PROPERTY
10.2.1 The Contractor shall take all reasonable precau-
tions for the safety of, and shall provide all reasonable
protection to prevent damage, injury or loss to:
.1 all employees on the Work and all other persons
who may be affected thereby;
.2 all the Work and all materials and equipment to
be incorporated therein, whether in storage on or
off the site, under the care, custody or control of
the Contractor or any of the Contractor's Subcon-
tractors or Sub-subcontractors;
.3 other property at the site or adjacent thereto, in-
cluding trees, shrubs, lawns, walks, pavements,
roadways, structures and utilities not designated
for removal, relocation or replacement in the
course of construction; and
.4 the work of the Owner or other separate contrac-
tors.
10.2.2 The Contractor shalf give all notices and comply
with all applicable laws, ordinances, rules, regulations
and lawful orders of any public authority bearing on the
safety of persons or property or their protection from
damage, injury or loss.
10.2.3 The Contractor shall erect and maintain, as re-
quired by existing conditions and the progress of the
Work, all reasonable safeguards for safety and protection,
including posting danger signs and other warnings against
hazards, promulgating safety regulations and notifying
owners and users of adjacent utilities.
10.2.4 When the use or storage of explosives or other
hazardous materials or equipment is necessary for the
execution of the Work, the Contractor shall exercise the
utmost care and shall carry on such activities under the
supervision of properly qualified personnel.
10.2.5 The Contractor shall promptly remedy all damage
or loss (other than damage or loss insured under Para-
graph 11.3) to any property referred to in Clauses 10.2.1.2
and 10.2.1.3 caused in whole or in part by the Contrac-
tor. anv Subcontractor, any Sub-subcontractor, anyone di-
rectly or indirectly employed by any of them, or by any-
one for whose acts any of them may be liable, and for
which the Contractor is responsible under Clauses 10.2.1.2
and 10.2.1.3, except damage or loss attributable to the
acts or omissions of the Owner, the Architect, the Con-
struction Manager or anyone directly or indirectly em-
ployed by any of them, or by anyone for whose acts any
of them may be liable, and not attributable to the fault
or negligence of the Contractor. The foregoing obliga-
tions of the Contractor are in addition to the Contractor's
obligations under Paragraph 4.18.
10.2.6 The Contractor shalf designate a responsible
member of the Contractor's organization at the site
whose duty 'shall be the prevention of accidents. This
person shalf be the Contractor's superintendent unless
17 A201/CM -1980
AlA DOCUMENT A201/CM . GENERAL CONDITIONS Of THE CONTRACT fOR CONSTRUCTION
CONSTRUCTION MANACEMENT EDITION . JUNE 1980 EDITION . AlA_ . @ 1980 . THE
AMERICA" INSTITUTE OF ARCHITECTS, 173S NEW YORK AVE., N.W.. WASHINGTON. D.C 2OOOf,
WARNING: Unlicensed ph:>tocopylng v101atM U.S. copyright IllW!l and Is subject to legal prosecution.
otherwise designated by the Contractor in writing to the
Owner and the Construction Manager.
10.2.7 The Contractor shall not load or permit any part
of the Work to be loaded so as to endanger its safety.
10.3 EMERGENCIES
10.3.1 In any emergency affecting the safety of persons
or properly Ihe Contractor shall act, at the Contractor's
discretion, to prevent threatened damage, injury or loss.
Any additional compensation or extension of time
claimed by the Contractor on account of emergency
work shall be determined as provided in Article 12 for
Changes in the Work.
ARTICLE 11
INSURANCE
11.1 CONTRACTOR'S L1ABtLlTY INSURANCE
11.1.1 The Contractor shall purchase and maintain insur-
ance for protection from the claims set forth below which
may arise out of or result from the Contractor's opera-
tions under the Contract, whether such operations be-by
the Contractor or by any Subcontractor, or by anyone di-
rectly or indirectly employed by any of them, or by any-
one for whose acts any of them may be liable:
.1 claims under workers' or workmen's compensa-
tion, disability benefit and other similar employee
benefit acts;
.2 claims for damages because of bodily injury, occu-
pational sickness or disease, or death of the Con-
tractor's employees;
.3 claims for damages because of bodily injury, sick-
ness or disease, or death of any person other than
the Contractor's employees;
.4 claims for damages insured by usual personal in-
jury liability coverage which are sustained (1) by
any person as a result of an offense directly or
indirectly related to the employment of such per-
son by the Contractor, or (2) by any other person;
.s claims for damages, other than to the Work itself,
because of injury to or destruction of tangible
property, including loss of use resulting therefrom;
and
.6 claims for damages because of bodily injury or
death of any person or property damage arising
out of the ownership. maintenance or use of any
motor vehicle.
11.1.2 The insurance required by Subparagraph 11.1.1
shall be written for not less than any limits of liability
specified in the Contract Documents or required by law,
whichever is greater.
11.1.3 The insurance required by Subparagraph 11.1.1
shall include contractual liability insurance applicable to
the Contractor's obligations under Paragraph 4,18.
11.1.4 Certificates of Insurance acceptable to the Owner
shall be submitted to the Construction Manager for trans-
mittal to the Owner prior to commencement of the Work.
These Certificates shall contain a provision that coverages
afforded under the policies will not be canceled until at
least thirty days' prior written notice has been given to
the Owner.
11.2 OWNER'S LIABILITY INSURANCE
11.2.1 The Owner shall be responsible for purchasing
and maintaining Owner's liability in5urance and, at the
Owner's option, may purchase and maintain imurance
for protection against claims which may arise' from
operations under the Contract.
11.3 PROPERTY INSURANCE
11.3.1 Unless otherwise provided, the Owner shall pur-
chase and maintain property insurance upon the entire
Work at the site to the full insurable value thereof. This
insurance shall include the interests of the Owner, the
Construction Manager, the Contractor, Subcontractors
and Sub-subcontractors in the Work, and shall insure
against the perils of fire and extended coverage and shall
include "all risk" insurance for physical loss or damage
including, without duplication of coverage, theft, van-
dalism and malicious mischief. If the Owner does not
intend to purchase such insurance for the full insurable
value of the entire Work, the Owner shall inform the
Contractor in writing prior to commencement of the
Work. The Contractor may then effect insurance which
will protect the interests of the Contractor, the Contrac-
tor's Subcontractors and the Sub-subcontractors In the
Work, and by appropriate Change Order the cost thereof
shall be charged to the Owner. If the Contractor is dam-
aged by failure of the Owner to purchase or maintain
such insurance and to so notify the Contractor, then the
Owner shall bear all reasonable costs properly attributa-
ble thereto, If not covered under the all risk insurance
or otherwise provided in the Contract Documents. the
Contractor shall effect and maintain similar property in-
surance on portions of the Work stored off the site or in
transit when such portions of the V'/ork are to be in-
cluded in an Application for Payment under Subpara-
graph 9.3.2.
11.3.2 The Owner shall purchase and maintain such
boiler and machinery insurance as may be required by
the Contract Documents or by law. This insurance shall
include the interests of the Owner, the Construction Man-
ager, the Contractor. Subcontractors and Sub-subcontrac-
tors in the Work.
11.3.3 Any loss insured under Subparagraph 11.3.1 is to
be adjusted with the Owner and made payable to the
Owner as trustee for the insureds, as their interests may
appear, subject to the requirements of any applicable
mortgagee clause and of Subparagraph 11.3.8. The Con-
tractor shall pay each Subcontractor a just share of any
insurance monies received by the Contractor, and by ap-
propriate agreement, written where legally required for
validity, shall require each Subcontractor to make pay-
ments to their Sub-5ubcontractors in similar manner.
11.3.4 The Owner shall file a copy of all policies with
the Contractor before an exposure to loss may occur.
11.3.5 If the Contractor requests in writing that insur-
ance for risks other than those described in Subpara-
graphs 11.3.1 and 11.3.2, or other special hazards, be
included in the property insurance policy, the Owner
shall. if possible, include such insurance. and the cost
thereof shall be charged to the Contractor by appropriate
Change Order.
AlA OOCUMENT A201/CM . GENERAL CONOITIONS OF THE CONTRACT FOR CONSTRUCTION
CO"'STRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlA- . @ 1980 . THE
AMERICAN INSTITUTE OF ARCHITECTS. 173S NEW YORK AVE.. NW., WASHINGTON, D.c. :!0006
A201/CM - 1980 18
WI\R'<"-lG' lJ"';"""ed ""c,t"c~,,\"- 0 vlolat"s l' ~, copyrlc"t laws ar>tl is subject 't) lege; prosecution,
11.3.6 The Owner and the Contractor waive all rights
against (1) each other and the Subcontractors, Sub-sub.
contractors, agents and employees of each other, and (2)
the Architect, the Construction Manager and separate con-
tractors, if any, and their subcontractors, sub-subcontrac-
tors, agents and employees, for damages caused by fire or
other perils to the extent covered by insurance obtained
pursuant to this Paragraph 11.3 or any other property in-
~urance applicable to the Work, except such rights as
they may have to the proceeds of ~uch insurance held
by the Owner as trustee. The foregoing waiver afforded
the Architect. the Construction Manager, their agents and
employees shall not extend to the liability imposed by
Subparagraph 4.18.3. The Owner or the Contractor, as
appropriate, shall require of the Architect, the Construc-
tion Manager, separate contractors, Subcontractors and
Sub-subcontractors by appropriate agreements, written
where legally required for validity, similar waivers each
in favor of all other parties enumerated in this Sub-
paragraph 11.3.6.
11.3.7 If required in writing by any party in interest, the
Owner as trustee shall, upon the occurrence of an in-
~ured loss, give bond for the proper performance of the
Owner's duties. The Owner shall deposit in a separate
account any money so received, and shall distribute it in
accordance with such agreement as the parties in interest
may reach, or in accordance with an award by arbitration
in which case the procedure shall be as provided in Para-
graph 7.9, If after such loss no other special agreement
is made, replacement of damaged Work shall be covered
bv an appropriate Change Order.
11.3.8 The Owner, as trustee, shall have power to adjust
and settle any loss with the insurers unless one of the
parties in interest shall object, in writing within five days
after the occurrence of loss, to the Owner's exercise of
this power, and if such objection be made, arbitrators
shall be chosen as provided in Paragraph 7.9. The Owner
as trustee shall, in that case, make settlement with the
insurers in accordance with the directions of such arbi-
trators. If distribution of the insurance proceeds by arbi-
tration is required, the arbitrators will direct such dis-
tribution.
11.3.9 If the Owner finds it necessary to occupy or use
a portion or portions of the Work prior to Substantial
Completion thereof, such occupancy shall not commence
prior to a time mutually agreed to by the Owner and the
Contractor and to which the insurance company or com-
panies providing the property insurance have consented
by endorsement to the policy or policies. This insurance
shall not be canceled or lapsed on account of such partial
occupancy. Consent of the Contractor and of the insur-
ance company or companies to such occupancy or use
shall not be unreasonably withheld.
11.4 LOSS OF USE INSURANCE
11.4.1 The Owner, at the Owner's option, may purchase
and maintain insurance for protection against loss of use
of the Owner's property due to fire or other hazards,
however caused. The Owner waives all rights of action
against the Contractor for loss of use of the Owner's
property, including consequential losses due to fire or
other hazards however caused, to the extent covered by
insurance under this Paragraph 11.4.
ARTICLE 12
CHANGES IN THE WORK
12.1 CHANGE ORDERS
12.1.1 A Change Order is a written order to the Con-
tractor signed to show the recommendation of the Con-
struction Managf~, the approval of the Architect and the
authorization oj t~e Owner, issued after execution of the
Contract, authorizing a change in the Work or an adjust-
ment in the Contract Sum or the Contract Time. The
Contract Sum and the Contract Time may be changed
only by Change Order. A Change Order signed by the
Contractor indicates the Contractor's agreement there-
with, including the adjustment in the Contract Sum or
the Contract Time,
12.1.2 The Ow ner, without invalidating the Contract,
may order changes in the Work within the general scope
of the Contract consisting of additions, deletions or other
revisiom, the Contract Sum and the Contract Time being
adjusted accordingly, All such changes in the Work shall
be authorized bv Change Order, and shall be performed
under the applicable conditions of the Contract Docu-
ments.
12.1.3 The cost or credit to the Owner resulting from a
change in the Work shall be determined in one or more
of the following ways:
.1 by mutual acceptance of a lump sum properly
itemized and supported by sufficient substantiating
data to pe~mit evaluation;
.2 by unit prices stated in the Contract Documents or
subsequently agreed upon;
.3 by cost to be determined in a manner agreed upon
by the pa~ties and a mutually acceptable fixed or
percentage fee; or
.4 by the method provided in Subparagraph 12.1.4.
12.1.4 If none of the methods set forth in Clauses
12.1.3.1,12.1.3.2 or 12.1.3.3 is agreed upon, the Contrac-
tor, provided a written order signed by the Owner is re-
ceived, shall promptly proceed with the Work involved.
The cost of such Work shall then be determined bv the
Architect, after consultation with the Construction ~1an-
ager, on the basis of the reasonable expenditures and
savings of those performing the Work attributable to the
change, including, in the case of an1ncrease in the Con-
tract Sum, a reasonable allowance for overhead and
profit. In such case, and also under Clauses 12.1.3.3 and
12,13.4 above, :~e Contractor shall keep and present. in
such form as the Owner, the Architect or the Construc-
tion Manager may prescribe. an itemized accounting to-
gether with apvopriate supporting data for inclusion in
a Change Order, Unless otherwise provided in the Con-
tract Documents cost shall be limited to the follow ing:
cost of materials, including sales tax and cost of delhery;
cost of labor. including social security, old age and
unemployment insurance, and fringe benefits required by
agreement or custom; workers' or workmen's compensa-
tion insurance; bond premiums; rental value of equip-
ment and machinery; and the additional costs of super-
vision and field office personnel directly attributable to
the change. Pending final determination of cost to the
Owner, payments on account shall be made on the Ar-
chitect's apprO\'al of a Project Certificate for Payment.
19 A201/CM -1980
AlA DOCUMENT A201/CM . GENERAL CO'DITIONS OF THE CONTRACT FOR CONSTRUCTION
CONSTRUCTION MANAGEMENT EDIlIO'- . JUNE 1980 EDITION · AlAe . ~ 1980 . THE
A~ERICAN INSTITUTE OF ARCHIlECTS, -'-j; Io;EW YORK AVE.. N.W" WASHINGTON. D.C 20006
WARNING: Unlicensed photocopying violates U.S. copyright laws and Is subject to legal prosecution.
The amount of credit to be allowed by the Contractor to
the Owner for any deletion or change which results in a
net decrease in the Contract Sum will be the amount of
the actual net cost as confirmed by the Architect after
consultation with the Construction Manager. When both
additions and credits covering related Work or substitu-
tions are involved in anyone change, the allowance for
overhead and profit shall be figured on the basis of the
net increase, if any, with respect to that change.
12.1.5 If unit prices are stated in the Contract Docu-
ments or subsequently agreed upon, and if the quantities
originally contemplated are so changed in a p~op~sed
Change Order that application of the agreed unit pnc.es
to the quantities of Work proposed will cause subs~antlal
inequity to the Owner or the Contractor, the applicable
unit prices shall be equitably adjusted.
12.2 CONCEALED CONDITIONS
12.2.1 Should concealed conditions encountered in the
performance of the Work below the surface of the ground
or should concealed or unknown conditions in an existing
structure be at variance with the conditions indicated by
the Contract Documents, or should unknown physical
conditions below the surface of the ground or should
concealed or unknown conditions in' an existing struc-
ture of an unusual nature, differing materially from those
ordinarily encountered and generally recognized as in-
herent in work of the character provided for in this Con-
tract, be encountered, the Contract Sum shall be equita-
bly adjusted by Change Order upon claim by either party
made within twenty days after the first observance of the
conditions.
12.3 CLAIMS FOR ADDITIONAL COST
12.3.1 If the Contractor wishes to make a claim for an
increase in the Contract Sum, the Contractor shall give
the Architect and the Construction Manager written no-
tice thereof within twenty days after the occurrence of
the event giving rise to such claim. This notice shall be
given by the Contractor before proceedin.g to .execute the
\\lork. except in an emergency endangermg hfe or prop-
erty in which case the Contractor shall proceed in ac-
cordance with Paragraph 10.3. No such claim shall be
valid unless so made. Ii the Owner and the Contractor
cannot agree on the amount of the adjustment in, the
Contract Sum, it shall be determined by the Architect
after consultation with the Construction Manager. Any
change in the Contract Sum resulting from such claim
shall be authorized by Change Order.
12.3.2 If the Contractor claims that additional cost is in-
volved because of, but not limited to. (1) any written in-
terpretation pursuant to Subparagraph 2.3.11, (2) any or-
der by the Owner to stop the Work pursuant to Para-
graph 3.3 where the Contractor was not at fault, or any
such order by the Construction Manager as the Owner's
agent. (3) any written order for a minor change in the
Work issued pursuant to Paragraph 12.4, or (4) failure of
payment by the Owner pursuant to Paragraph 9.7. the
Contractor shall make such claim as provided in Sub-
paragraph 12.3.1.
12.4 MINOR CHANGES IN THE WORK
12.4.1 The Architect will have authority to order minor
changes in the Work not involving an adjustment in the
Contract Sum or extension of the Contract Time and not
inconsistent with the intent of the Contract Documents.
Such changes shall be effected by written order issued
through the Construction Manager, and shall be binding
on the Owner and the Contractor. The Contractor shall
carry out such written orders promptly.
ARTICLE 13
UNCOVERING AND CORRECTION OF WORK
13.1 UNCOVERING OF WORK
13.1.1 If any portion of the Work should be covered
contrary to the request of the Architect Or the Construc-
tion Manager, or to requirements specifically expressed in
the Contract Documents, it must, if required in writing by
either, be uncovered for their observation and shall be
replaced at the Contractor's expense.
13.1.2 If any other portion of the Work has been cov-
ered which the Architect or the Construction Manager
has not specifically requested to observe prior to its being
covered, either may request to see such Work and it shall
be uncovered by the Contractor. If such Work be found
in accordance with the Contract Documents, the cost of
uncovering and replacement shall, by appropriate Change
Order, be charged to the Owner. If such Work be found
not in accordance with the Contract Documents, the
Contractor shall pay such costs unless it be found that
this condition was caused by the Owner or a separate
contractor as provided in Article 6, in which event the
Owner shall be responsible for the payment of such costs.
13.2 CORREalON OF WORK
13.2.1 The Contractor shall promptly correct all Work
rejected by the Architect or the Construction Manager as
defective or as failing to conform to the Contract Docu-
ments whether observed before or after Substantial Com-
pletion of the Project and whether or not fabricated, in-
stalled or completed. The Contractor shall bear all costs
of correcting such rejected Work, including compensa-
tion for the Architect's and the Construction Manager's
additional services made necessary thereby.
13.2.2 Ii, within one year after the Date of Substantial
Completion of the Project or designated portion thereof,
or within one year after acceptance by the Owner of
designated equipment, or within such longer period of
time as may be prescribed by law or by the terms of any
applicable special warranty required by the Contract Docu-
ments, any of the Work is found to be defective or not in
accordance with the Contract Documents, the Contractor
shall correct it promptly after receipt of a written notice
from the Owner to do so unless the Owner has previ-
ously given the Contractor a wrillen acceptance of such
condition. This obligation shall survive both final pavment
for the Work or designated portion thereof and termina-
tion of the Contract. The Owner shall give such notice
promptly after discovery of the condition.
13.2.3 The Contractor shall remove from the site all
portions of the Work which are defective or nonconform-
ing and which have not been corrected under Subpara-
graphs 4.5.1, 13.2.1 and 13.2,2, unless removal is waived
by the Owner.
13.2.4 If the Contractor fails to correct defective or non-
conforming Work as provided in Subparagraphs 4.5.1,
AlA DOCUMENT A201/CM . GENERAL CONDITIO~S OF THE CONTRACT FOR CONSTRUCTION
CONSTRUCTION MANAGEMENT EDITION . JUNE 1980 EDITION . AlAe . @1980 . THE
,.....\ERIC..'1 INSTITUTE OF ARCHITECTS. 173S NEW YORK AVE" N,\\'.. WASHINGTON. D.C 20006
A201/CM - 1980 20
We.t:F::NC' \""l("l?n~pd nh~,tocC"nv;"''''' vir"t~.,c.t:' us ("o"vrict)t law~ ?...,~ i~ ~~'I:-;F-t::t tf"l !:>...~, proseC'(I.r,...~
13.2.1 and 13.2.2, the Owner may correct it in accordance
with Paragraph 3.4.
13.2.5 If the Contractor does not proceed with the cor-
rection of such defective or nonconforming Work within
a reasonable time fixed by written notice from the Archi-
tect issued through the Construction Manager, the Owner
may remove it and may store the materials or equipment
at the expense of the Contractor. If the Contractor does
not pay the cost of such removal and storage within ten
days thereafter, the Owner may, upon ten additional
days' written notice, sell such Work at auction or at pri-
vate sale and shall account for the net proceeds thereof,
after deducting all the costs that should have been borne
by the Contractor, including compensation for the Archi-
tect's and the Construction Manager's additional services
made necessary thereby. If such proceeds of sale do not
cover all costs which the Contractor should have borne,
the difference shall be charged to the Contractor and an
appropriate Change Order shall be issued. If the payments
then or thereafter due the Contractor are not sufficient to
cover such amount, the Contractor shall pay the differ-
ence to the Owner.
13.2.6 The Contractor shall bear the cost of making
good all work of the Owner or separate contractors de-
stroyed or damaged by such correction or removal.
13.2.7 Nothing contained in this Paragraph 13,2 shall be
construed to establish a period of limitation with respect
to any other obligation which the Contractor might have
under the Contract Documents, including Paragraph 4.5
hereof. The establishment of the time periods noted in
Subparagraph 13.2,2, or such longer period of time as
may be prescribed by law or by the terms of any warranty
required by the Contract Documents, relates only to the
specific obligation of the Contractor to correct the Work,
and has no relationship to the time within which the
Contractor's obligation to comply with the Contract Doc-
uments may be sought to be enforced, nor to the time
within which proceedings may be commenced to estab-
lish the Contractor's liability with respect to the Contrac-
tor's obligations other than specifically to correct the
Work.
13.3 ACCEPTANCE OF DEFEOIVE OR
NONCONFORMING WORK
13.3.1 If the Owner prefers to accept defective or non-
conforming Work, the Owner may do so instead of requir-
ing its removal and correction. in which case a Change
Order will be issued to reflect a reduction in the Contract
Sum ",'here appropriate and equitable. Such adjustment
shall be effected whether or not final payment has been
made.
ARTICLE 14
TERMINATION OF THE CONTRACT
14.1 TERMINATION BY THE CONTRACTOR
14.1.1 If the Work is stopped for a period of thirty days
under an order of any court or other public authority
having jurisdiction, or as a result of an act of government
such as a declaration of a national emergency making
materials unavailable, through no act or fault of the Con-
tractor or a Subcontractor or their agents or employees or
any other persons performing any of the Work under a
contract with the Contractor, or if the Work should be
stopped for a period of thirty days by the Contractor be-
cause of the Construction Manager's failure to recom-
mend or the Architect's failure to issue a Project Certifi-
cate for Payment as provided in Paragraph 9.7 or because
the Owner has not made payment thereon as provided in
Paragraph 9.7, then the Contractor may, upon seven addi-
tional days' written notice to the Owner, the Architect
and the Construction Manager, terminate the Contract and
recover from the Owner payment for all Work executed
and for any proven loss sustained upon any materials,
equipment, tools, construction equipment and machinery,
including reasonable profit and damages.
14.2 TERMINATION BY THE OWNER
14.2.1 If the Contractor is adjudged a bankrupt, or
makes a general assignment for the benefit of creditors,
or jf a receiver is appointed on account of the Contrac-
tor's insolvency, or if the Contractor persistently or re-
peatedly refuses or fails, except in cases for which exten-
sion of time is provided, to supply enough properly
skilled workers or proper materials, or fails to make
prompt payment to Subcontractors or for materials or
labor, or persistently disregards laws, ordinances, rules,
regulations or orders of any public authority having juris-
tion, or otherwise is guilty of a substantial violation of a
provision of the Contract Documents, and fails within
seven days after receipt of written notice to commence
and continue correction of such default, neglect or viola-
tion with diligence and promptness. the Owner, upon
certification by the Architect after consultation with the
Construction Manager that sufficient cause exists to justify
such action, may, after seven days following receipt by
the Contractor of an additional written notice and with-
out prejudice to any other remedy the Owner may have,
terminate the employment of the Contractor and take
possession of the site and of all materials, equipment,
lools, construction equipment and machinery thereon
owned by the Contractor and may finish the Work by
whatever methods the Owner may deem expedient. In
~uch case the Contractor shall not be entitled to receive
any further payment until the Work is finished.
14.2.2 If the unpaid balance of the Contract Sum ex-
ceeds the costs of finishing the Work, including compen-
sation for the Architect's and the Construction Manager's
additional services made necessary thereby, such excess
shall be paid to the Contractor. If such costs exceed the
unpaid balance, the Contractor shall pay the difference
to the Owner. The amount to be paid to the Contractor
or to the Owner. as the case may be. shall be certified by
the Architect, upon application, in the manner provided
in Paragraph 9.4, and this obligation for payment shall
survive lhe termination of the Contract.
21 A201/CM -1980
AlA DOCUMENT A2t1/CM . GENERAL CONDIlIO~S Of THE CONTRACT fOR CONSTRUCTION
CONSTRUCTION ,\V."IAGEMENT EDITION . JU~E 1980 EDITION . AlAe · Cll980 · THE
,,,\[RICA" INSTilL TE Of ARCHIlECTS.I;35 NEW YORK AVE.. NW., WASHlsGTON, D,C. 20006
". ,~..",..... "_~"~_'~_ .....t..r. ~....r ~"'v;"""'-.I">~tl~ _'""'~''';Qh~I'''').'sP!''diS~,\lbjecttoleQalpro'5ecution.
SECTION 00805
SUPPLEMENTARY GENERAL CONDITIONS
Information contained in this Supplementary Conditions amends,
supplements or clarifies the "General Conditions of the Contract
for Construction, Construction Management Edition, AlA Document
A201/CM dated June 1980 Edition.
In cases of conflict between the General Conditions and these
Supplementary Conditions, wording of this section shall govern.
ARTICLE 1
1. Subparagraph 1.1.3 - third line-after the word
"construction," delete the remaining words and insert the
following:
"and all supplies, tools, construction equipment and
machinery, water, heat, utilities, transportation, and other
facilities, services, and incidentals necessary for the
proper execution and completion of such construction; except
as expressly noted in the Scope of Work or the General
Requirements of the Contract."
2. Subparagraph 1.2.1 - delete in its entirety.
3. Subparagraph 1. 2.3 - after the last word "meanings" in the
paragraph add the following sentence:
"In case of discrepancy or disagreement in the contract
documents, specifications, and/or drawings, the ORDER OF
PRECEDENCE shall be:
Contract Agreement
The addenda as issued
The Supplementary General Conditions
General Conditions
The General Requirements
The Technical Specifications
The Drawings (Large scale detail drawings take
precedence over smaller scale general drawings).
Note: Do not rely on scaled dimensions on drawings,
and any discrepancies found shall be brought to the
attention of the AlE through the CM.
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 1
4. Add new subparagraph 1.2.5 as follows:
"'i\'here on any of the drawings a portion of the h'ork is drawn
out and the remainder is indicated in outline, the parts
drawn out shall also apply to all other like portions of the
Work."
5. Add new subparagraph 1.3.2 as follows:
"Unless otherwise provided in the Contract Documents, the
Trade Contractor will be furnished, free of charge, all
copies of Drawings and Specifications reasonably necessary
for the execution of the Work."
ARTICLE 2
1. Subparagraph 2.2.1 - after the word "representative", add:
liThe Construction Manager is not the General Contractor and,
unless otherwise expressly provided in the Contract
Documents, does not assume any of the traditional duties of
a General Contractor. The term Construction Manager means
the Construction Manager acting through his authorized
representative."
2. Subparagraph 2.3.4 - first sentence after the word
"Architect," add "along with the Construction Manager."
3. subparagraph 2.3.7 - after the word "properly," add:
"It is the intent of the Contract Documents to allow the
Construction Manager to schedule the performance of all Work
and the contractors are expected to follow all such schedule
direction. Should a contractor, either in person or through
his subcontractor, supplier, or vendor, fail to maintain
progress according to the Project Schedule and approved
Contractor's Schedule, or cause delay to another Contractor:
De shall furnish additional labor and/or services such as
overtime as may be necessary to brinq his operations up to
schedule, all at no additional cost to the Owner."
4. Subparagraph 2.3.15 - delete in its entirety.
5. subparagraph 2.3.18 - delete the word "reasonable" in the
sixth (6th) line. After the word "promptness", add
"consistent with the constraints of the project schedule so
as to cause no delay."
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 2
6. Subparagraph 2.3.23 - delete the phrase "against whom the
Contractor makes no reasonable objection and." Also, delete
the last sentence in the subparagraph in its entirety.
ARTICLE 3
1. Subparagraph 3.3.1 - delete from the last sentence the
phrase, ". .., except to the extent required by Subparagraph
6.1.3"
2. Subparagraph 3.4.1 - substitute three (3) days notice in
each case for the seven (7) day notices stipulated. Add at
end of subparagraph the following: "In the event of clean-
up issues, Owner has right to provide a minimum of 24 hours
notice. In the event of safety issues determined to be of a
serious nature, as determined by the CM, notice will given,
and contractor is required to rectify deficiency
immediately."
3. Subparagraph 3.2.1 - delete in its entirety.
ARTICLE 4
1. Subparagraph 4.1.1 - delete in its entirety and insert the
following:
liThe Contractor is the same person or entity identified as
the Trade Contractor. A Trade Contractor is the person or
entity identified as such in the Agreement between the Owner
or Construction Manager and a Trade Contractor. The term
Trade Contractor includes one who furnishes material worked
to a special design but does not include one who furnishes
material not so worked and is referred to throughout the
Contract Documents as if singular in number and masculine in
gender. The term Trade Contractor means the Trade
Contractor or his authorized representative."
2. Add new subparagraph 4.4.3 as follows:
"The Contractor is responsible for the conduct of his
employees at all times. Misconduct, destruction of
property, unsafe practices, or violation of any Federal or
state regulations including abuse of alcohol or drugs, will
be cause for permanent dismissal from the project. If any
Contractor employee is determined to be detrimental to the
Project, as deemed by the Construction Manager, the
Contractor will remove and/or replace the employee at the
01/06/92 SUPPLEMENTARY GEN~RAL CONDITIONS (ADD. 2)
00805 - 3
request of the Construction Manager. Employees dismissed
from the project will be transported from the jobsite at the
Contractor's expense.1I
3. Add new subparagraph 4.4.4 as follows:
"The Trade Contractor shall be totally responsible for the
security of his work, materials, equipment, supplies, tools,
machinery, and construction equipment.1I
4. Add new subparagraph 4.4.5 as follows:
liThe Trade Contractor shall be responsible for complete,
timely and accurate field measurements as necessary for
proper coordination, fabrication and installation of his
materials and equipment. The Trade Contractor agrees to
cooperate with the Construction Manager, if required, to
accommodate any discovered variations or deviations from the
Drawings and Specifications so that the progress of the Work
is not adversely affected. II
5. Subparagraph 4.9.1 - add the following sentence:
liThe superintendent shall be satisfactory to the
Construction Manager and shall not be changed except with
the consent of the Construction Manager, unless the
superintendent proves to be unsatisfactory to the Trade
Contractor or ceases to be in his employ.1I
6. Subparagraph 4.10.1 - add the following sentence:
"This schedule, to be submitted within three (3) days after
Contract Award, shall indicate the dates for the starting
and completion of the various stages of construction, shall
be-revised as required by the conditions of the Work, and
shall be subject to the Construction Manager's approval."
7. Add new subparagraph 4.10.2:
liThe Construction Manager will conduct a weekly scheduling
meeting which the Contractor shall attend. At this meeting,
the parties can discuss jointly such matters as progress,
scheduling, and problems. II
8. Add new subparagraph 4.12.9:
"If materials specified in the Contract Documents are not
available on the present market, the Trade Contractor may
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 4
submit data on substitute materials through the Construction
Manager to the Architect/Engineer for approval by the
Owner."
9. Subparagraph 4.14.1 - add at line 3 after "properly":
"He shall also provide protection of existing work as
required."
10. Subparagraph 4.14.2 - at end of paragraph, add:
"When structural members are involved, the written consent
of the Architect/Engineer shall also be required. The Trade
Contractor shall not unreasonably withhold from the
Construction Manager or any separate contractor his consent
to cutting or otherwise altering the Work."
11. Add new subparagraph 4.14.3:
"The Trade Contractor shall arrange for any blockouts,
cutouts, or opening required for the installation of his
materials and equipment and the execution of his work,
whether or not shown or indicated on the Drawings. The
Trade Contractor shall be further responsible for sealing
and/or finishing, in an acceptable fashion and meeting any
applicable code requirements, any such blockout, cutout
opening, or other hole in any fire-rated floor, ceiling,
wall, security wall, or any other finished surface".
12. Subparagraph 4.15.1 - at end of paragraph, add:
"Clean up shall be performed to the satisfaction of the
Owner or Construction Manager."
13. Add new subparagraph 4.16.2:
"The Trade Contractor shall promptly return telephone calls
or respond to any other form of communication initiated by
the Construction Manager. Failure to promptly do so shall
be considered a lack of performance on the part of the Trade
Contractor, and may be considered grounds for replacement of
site personnel."
14. Add new Subparagraph 4.16.3:
"All written correspondence to the Construction Manager
shall be serialized, dated, and signed by an authorized
representative of the Trade Contractor. The correspondence
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 5
15. Subparagraph 4.2.1 - at the end of the paragraph, add the
following:
liThe Owner and the Architect have acknowledged that
nothing in the Architect's engagement implies any
undertaking by the Architect for the benefit of or
which may be enforced by the Contractor, its
subcontractors, or the surety of any of them; it being
understood that the Architect's obligations are to the
Owner and that, in performing such obligations, the
Architect may increase the burdens and expenses of the
Contractor, its subcontractors, or the surety of any of
them. Neither the Contractor, any Subcontractor, nor
the surety of any of them shall bring any civil suit or
other legal action against the Architect arising out of
or in connection with the Project."
03/02/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 6)
00805 -5a
16. Subparagraph 4.18.1 - delete from the loth line, the phrase,
II... (other than the Work itself)...1I
At the end of the paragraph add the following paragraph:
liThe first ten dollars ($10) of remuneration paid to the
CONTRACTOR is for the indemnification provided for above.1I
04/16/92
SUPPLEMENTARY GENERAL CONDITIONS(ADD. 10) 00805 -SB
shall be directed to:
Morrison-Knudsen/Gerrits
P.O. Box 5283
Key West, Florida 33040
Attn: Doug Fuller
or hand delivered to Morrison-Knudsen/Gerrits. office
located at 5090 Junior College Road, stock Island, Florida
33040.
Serialization procedures will be provided to the Trade
Contractor in the pre-construction meeting."
Each trade contractor shall be required to check his
designated mailbox regularly. This mailbox will be made
available, and located by the Construction Manager.
ARTICLE 5
1. Subparagraph 5.2.3 - delete in its entirety and insert the
following:
IIIf the Owner or Construction Manager refuses to accept any
person or entity on a list submitted by the Trade Contractor
in response to the requirements of the Contract Documents,
the Trade Contractor shall submit an acceptable substitute;
however, no increase in the Contract Sum shall be allowed
for any such substitution.1I
ARTICLE 6
1. Subparagraph 6.1.1 - delete the last sentence.
2. Subparagraph 6.1.3 - delete in its entirety, and insert the
following:
lilt shall be the responsibility of each contractor to
coordinate his work with the work of other contractors
on the site. The Owner, A/E and Construction Manager
shall be held harmless of any and all costs associated
with improper coordination.1I
3. Subparagraph 6.2.5 - sixth line, after the word "initiates,1I
delete the words "an arbitration proceedingll and substitute
"a claim;1I tenth line, delete the words "at the Owner.s
expense, and"; thirteenth line, after the words "and court
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 6
or," delete the word "arbitration" and substitute "claim."
4. Add new subparagraph 6.2.6:
"Should the Contractor contend that he is entitled to
an extension of time for completion of any portion or
portions of the work, he shall, within (72) hours of
the occurrence of the cause of the delay, notify the
Construction Manager in writing, of his contention:
setting forth (A) The cause for the delay, (B) A
description of the portion or portions of work affected
thereby, and (C) all details pertinent thereto. A
subsequent written application for the specific number
of days of extension of time requested shall be made by
the Contractor to the Construction Manager within (72)
hours after the delay has ceased to exist.
It is a condition precedent to the consideration or
prosecution of any claim for an extension of time that
the foregoing provisions be strictly adhered to in each
instance and, if the Contractor fails to comply, he
shall be deemed to have waived the claim.
The Contractor agrees that whether or not any delay,
regardless of cause, shall be the basis for an
extension of time he shall have no claim against the
Owner, A/E or Construction Manager for an increase in
the contract price, nor a claim against the Owner, A/E
or Construction Manager for a payment or allowance of
any kind for damage, loss or expense resulting from
delays: Nor shall the Contractor have any claim for
damage, loss or expense resulting from interruptions
to, or suspension of, his work to enable other
contractors to perform their work. The only remedy
available to the Contractor shall be an extension of
time. II
ARTICLE 7
1. subparagraph 7.1.1 - delete in its entirety and insert the
following:
"The contract shall be governed by the laws of the State of
Florida. Venue for any claims or disputes arising under
this contract shall be in the Circuit Court of the 16th
Judicial Circuit of the State of Florida."
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 7
2. Subparagraph 7.2.1 - delete in its entirety and insert the
following:
"The Owner or Construction Manager (as the case may be) and
the Trade Contractor each binds himself, his partners,
successors, assigns, and legal representatives of such other
party in respect to all covenants, agreements, and
obligations contained in the Contract Documents. Neither
party to the Contract shall assign the Contract or sublet it
as a whole without the written consent of the other."
3. Add new Subparagraph 7.2.2:
"The Trade Contractor shall not assign any monies due or to
become due under this Contract without prior written consent
of the Owner or Construction Manager."
4. subparagraph 7.8.1 - delete in its entirety.
5. Paragraph 7.9 'Arbitration' and all associated subparagraphs
7.9.1, 7.9.2, & 7.9.3 - delete in their entirety.
ARTICLE 8
1. Subparagraph 8.3.1 - delete in its entirety and insert the
following:
"If the Trade Contractor is delayed, at any time, in the
progress of the Work, by any act or neglect of the Owner,
Construction Manager, or the Architect/Engineer, or by any
employee of either, or by any separate contractor employed
by the Owner, or by changes ordered in the Work, or by fire,
unusual delay in transportation, adverse weather conditions
not reasonably anticipatable, unavoidable casualties or any
causes beyond the Trade Contractor's control, or by delay
authorized by the Owner, Construction Manager, or by any
other cause which the Construction Manager determines may
justify the delay, then the Contract Time shall be extended
by no cost Change Order for such reasonable time as the
Construction Manager may determine, in accordance with
subparagraph 6.2.6.11
2. Subparagraph 8.3.2 - replace the remainder of the Paragraph
after the word "waived" in line 4 with the following:
"Any claim for extension of time shall state the cause of
the delay and the number of days of extension requested. If
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 8
the cause of the delay is continuing, only one claim is
necessary, but the Trade Contractor shall report the
termination of the cause for the delay within twenty (20)
days after such termination; otherwise, any claim for
extension of time based upon that cause shall be waived. II
3. Subparagraph 8.3.4 - delete in its entirety and insert the
following:
"It shall be recognized by the Trade Contractor that he may
reasonably anticipate that as the job progresses, the
Construction Manager will be making changes in, and updating
Construction Schedules. No claim for an increase in the
Contract Sum for either acceleration or delay will be
allowed for extensions of time pursuant to this Paragraph
8.3 or for other changes in the Construction Schedules which
are of the type ordinarily experienced in projects of
similar size and complexity."
4. Add new subparagraph 8.3.5:
"If the Project is delayed as a result of the Trade
Contractor's refusal or failure to begin the Work on the
date of commencement as defined in paragraph 8.1.2, or his
refusal or failure to carry the Work forward expeditiously
with adequate forces, the Trade Contractor causing the delay
shall be liable, but not limited to, delay claims from other
Trade Contractors which are affected."
ARTICLE 9
1. Subparagraph 9.3.3 - add at line 14 after the word "person":
"All Trade Subcontractors and Trade Subsubcontractors shall
execute an agreement stating that title will so pass, upon
their receipt of payment from the Trade Contractor."
2. Subparagraph 9.5.1 - add:
"From the total of the amount determined to be payable on a
progress payment, 10 percent of such total amount will be
deducted and retained by the Owner until final payment is
made. The balance (90 percent) of the amount payable, less
all previous payments, shall be certified for payment. When
not less than 95 percent of the work has been completed, the
Owner may, at his/her discretion (and with the consent of
the surety), prepare an estimate from which will be retained
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 9
an amount not less than twice the contract value or
estimated cost, (whichever is greater), of the work
remaining to be done. The remainder, less all previous
payments and deductions, will then be certified for payment
to the Contractor.
It is understood and agreed that the Contractor shall not be
entitled to demand or receive progress payment based on
quantities of work in excess of those provided in the
proposal or covered by approved change orders, except when
such excess quantities have been determined by the
Construction Manager to be a part of the final quantity for
the item of work in question.
No progress payment shall bind the Owner to the acceptance
of any materials or work in place, as to quality or
quantity. All progress payments are subject to correction
at the time of final payments.
3. Add new subparagraph 9.5.6:
"All material and work covered by partial payments made
shall thereupon become the sole property of the Owner, and
by this provision shall not be construed as relieving the
Trade Contractor from the sole responsibility for the
materials and work upon which payments have been made or the
restoration for any damaged material, or as a waiver to the
right of the Owner or Construction Manager to require the
fulfillment of all the terms of the Contract."
4. Add new subparagraph 9.5.7:
"Except in case of bona fide disputes, or where the Trade
Contractor has some other justifiable reason for delay, the
Trade Contractor shall pay for all transportation and
utility services not later than the end of the calendar
month following that in which services are rendered and for
all materials, tools, and other expendable equipment which
are delivered at the site of the Project. The Trade
Contractor shall pay, to each of his Trade Subcontractors,
not later than the end of the calendar month in which each
payment is made to the Trade Contractor, the representative
2TI10unt allowed the Trade Contractor on account of the work
performed by his Trade Subcontractor interest therein. The
Trade Contractor shall, by an appropriate agreement with
each Trade Subcontractor, also require each Trade
Subcontractor to make payments to his suppliers and Trade
Subsubcontractors in a similar manner."
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 10
5. Subparagraph 9.6.1 - delete in its entirety and insert the
following:
"The Construction Manager/Architect may decline to approve
an Application for Payment if, in his opinion, the
application is not adequately supported. If the Trade
Contractor and Construction Manager cannot agree on a
revised amount, the Construction Manager shall process the
Application for the amount he deems appropriate. The
Construction Manager may also decline to approve any
Applications for Payment or, because of subsequently
discovered evidence or subsequent inspections, he may
nullify, in whole or part, any approval previously made to
such extent as may be necessary in his opinion because of:
(1) defective work not remedied; (2) third party claims
filed or reasonable evidence indicating probable filing of
such claims; (3) failure of the Trade contractor to make
payments properly to Trade Subcontractors or for labor,
materials, or equipment; (4) reasonable evidence that the
work cannot be completed for the unpaid balance of the
Contract Sum; (5) damage to the Construction Manager, the
Owner, or another contractor working at the project; (6)
reasonable evidence that the Work will not be completed
within the contract time; (7) persistent failure to carry
out the Work in accordance with the Contract Documents.
9.6.1.1 No payment shall be made to the Trade
Contractor until certificates of insurance or other
evidence of compliance by the Trade Contractor, within
all the requirements of Article 12, have been filed
with the Owner and Construction Manager. Further, no
payments on the basis of work performed by a Trade
Subcontractor shall be paid until copies of all bonds
required by Paragraph 7.5 and any certificates of
insurance required of the Trade Subcontractors under
Article 12 have been filed with the Owner."
6. Subparagraph 9.7 - delete in its entirety.
ARTICLE 11
1. Add new subparagraph 11.1.2.1:
The following coverages are required to be maintained by all
Trade Contractors and subcontractors in any tier throughout
the entire length of the contract and any extensions
thereof.
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 11
1. Premises and Operation Liability Insurance:
commercial General Liability Insurance shall be
obtained in amounts of not less than $1,000,000 each
occurrence.
Coverage shall specifically include:
a. Bodily injury and property damage liability
coverage for premises and operations.
b. Products and completed operations.
c. Independent contractor's exposures.
d. Property damage resulting from explosion,
collapse, or underground (x/c,u) exposures.
e. Blanket contractual liability covering this
contract.
f. Personal injury liability.
g. Broad form property damage liability.
2. Automobile Liability Insurance:
Comprehensive automobile liability insurance shall
include coverage for bodily injury and property damage
liability for a minimum limit of $1,000,000 each
occurrence and shall cover use of owned, non-owned, and
hired vehicles, and include employers' non-ownership
liability coverage.
3. Workers Compensation and Employers Liability Insurance:
statutory Workers' Compensation coverage including
Employers Liability coverage with limits of not less
than $100,000 per person per accident and $500,000 per
person per occurrence for disease. Coverage shall be
provided to cover operations in the state of Florida
and the Voluntary Compensation endorsement shall be
provided. Coverage for deferally enacted benefits
shall be provided where applicable.
All insurance policies except the Workers Compensation and
Employers Liability Insurance policy, are required in the
name of Monroe County Board of County Commissioners and
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 12
Morrison-Knudsen/Gerrits as Additional Insured, and provide
a ~inimum of sixty (60) days notice in the event of
termination, non-renewal or reduction in coverage. Policy
language shall be modified to provide liability coverage for
Cross Liability suits between insureds ~ithout increasing
the total policy limits. Monroe County reserves the right
to require additional insurance as may be deemed necessary
for any specific project or work.
Insurers providing coverage(s) must be financially stable
and authorized to do business in the state of Florida. The
Monroe County Board of County Commissioners reserves the
right to reject any insurer that it belie~es to be
unacceptable.
Failure to maintain required insurance coverage in effect
will provide Monroe County, Florida with the option of
terminating the contract upon written notice to the
Construction Manager.
certificates expiring during the term of the contract shall
be replaced with new certificates prior to the expiration of
the original certificates.
Complete and certified copies of all insurance contracts
shall be furnished to The Monroe County Board of County
Commissioners if requEsted.
The certificate Holder on all insurance policies is required
to be as follows:
}~onroe County Board of County Commi ss ioners, or Monroe
County,
c/o Morrison-Knudsen/Gerrits
P.O. Box 5283
Key West, FL 33040
2. Subparagraph 11.3.7 - second sentence, delete the phrase,
"..., or in accordance with an award by arbitration in which
case the procedure shall be as provided in Paragraph 7.9"
3. Subparagraph 11.3.8 - first sentence, delete the phrase,
II.. .arbitrators shall be chosen as provided in Paragraph
7.9"
01/06/92 SUPPLEMENTARY GE1;ERAL CONDI'rrONS U..::m. 2)
00805 - 13
4. Subparagraph 11.3.1 - delete in its entirety, and insert the
follO\.Jing:
11 Throughout the term of the CONTRACT, the o\'iNER shall
purchase and maintain property insurance on the
completed value of the perr::anent facility only. The
completed value is defined as all material, labor,
supplies, and equipment intended to be incorporated in
and to become a permanent part of the completed
facility. Such insurance shall include perils of fire,
lightning, and extended perils. The facility as
defined for 11.3.1 includes structures as defined in
the contract drawings and specifications.
Notwithstanding any provisions contained in this
paragraph, the CONTRACTOR shall be responsible for the
first $10,000 on any loss governed by this section.
The CONTRACTOR understands that the o\'iNER I S property
insurance policy contains certain exclusions which are
available upon request from the CONSTRUCTION l'-1ANAGER.1I
04/16/92
SUPPLU1ENTARY GENERAL CO~;DITIONS (ADD. 10) 00805 -13A
ARTICLE 12
1. Subparagraph 12.1.3 - under item .1, add the following at
the end of the sentence, II, as set forth in subparagraph
12.1.611
2. Subparagraph 12.1.4 - replace the remainder of the
paragraph, after the word IIchangell in line 25, with the
following:
IIpending final determination of cost, payments on account
shall be made as determined by the Construction Manager.
The amount of credit to be allowed by the Trade Contractor
for any deletion or change, which results in a net decrease
in the Contract Sum, will be the amount of the actual net
cost as confirmed by the Construction Manager. When both
additions and credits covering related Work or substitutions
are involved in anyone change, the allowance for overhead
and profit shall be figured on the basis of the net
increase, if any, with respect to that change.1I
3. Add new subparagraph 12.1.6:
"The actual cost of Changes in the Work may include all
items of labor or material, power tools, and equipment
actually used, utilities, pro rata charges for foreman, and
all payroll charges such as Public Liability and Workman's
Compensation Insurance. No percentage for overhead and
profit shall be allowed on items of Social Security and
Sales Tax. If deductions are ordered, the credit shall be
the net cost. Items considered as overhead shall include
insurance other than that mentioned above, bond or bonds,
superintendent, timekeeper, clerks, watchmen, use of small
tools, incidental job costs, and general office expenses.
The actual cost of Changes in the Work (other than those
covered by unit prices set forth in the Contract Documents)
shall be computed as follows:
12.1.6.1 If the Trade Contractor performs the actual
Work, the percentage mark-up for overhead and profit
shall be a maximun addition of fifteen percent (15%).
12.1.6.2 If the Trade Subcontractor performs the
actual Work, the percentage mark-up for overhead and
profit shall be a maximum addition of fifteen percent
(15%). If the Trade Contractor does not enter into the
Work, the maximum mark up for managing this work will
be ten percent (10%).
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 14
12.1.6.3 If the Trade Subcontractor performs part of
the actual work, his percentage mark-up for overhead
and profit shall be a maximum addition of fifteen
percent (15%) on his direct work only. If the Trade
Contractor performs part of the actual work, his
percentage mark-up for overhead and profit shall be a
maximum addition of fifteen percent (15%) on his direct
work only.
4. Add new subparagraph 12.1.7:
liThe Trade Contractor shall furnish to the Owner through the
Construction Manager, an itemized breakdown of the
quantities and prices used in computing the value of any
change that might be ordered."
5. Subparagraph 12.3.1 - delete in its entirety and insert the
following:
IIIf the Trade Contractor claims that any instructions given
to him by the Construction Manager, by drawings or
otherwise, .involve extra work not covered by the Contract,
he shall give the Construction Manager written notice
thereof within three (3) days after the receipt of such
instructions and before proceeding to execute the work,
except in emergencies endangering life or property, in which
case the Trade Contractor shall proceed in accordance with
Paragraph 10.3."
Should it not be clear to the Trade Contractor that a change
will involve extra work, written notice given within three
(3) days that the change may involve extra work will be
sufficient notice. If it is later determined that the work
involved in such instruction shall be recognized as an
extra, the amounts of additional compensation to be paid
therefore should be determined in accordance with Paragraph
13.1.
Except as otherwise specifically provided, no claim for
additional cost shall be allowed unless the notice specified
by this Subparagraph is given by the Trade Contractor. If
the Contractor considers that the changed work involves
extra costs, the costs shall be accounted for, and presented
in accordance with subparagraph 12.1.3. All claims shall be
submitted to the Owner through the Construction Manager. II
6. Subparagraph 12.3.2 - change the word 'agent' in the 7th
line, to 'representative'. Also, delete item (4).
01/06/92 SUPPLEMENTARY GE~ERAL CONDITIONS (ADD. 2)
oose5 - 15
7. Add new subparagraph 12.3.3:
"Unless otherwise agreed in writing, the Contractor
shall carryon the Work and maintain its progress
during any dispute or claim proceeding, and Owner shall
continue to make payments to the Contractor in
accordance with the Contract Documents. Disputes
unresolved shall be settled in accordance with
subparagraph 7.1.1."
ARTICLE 14
1. Subparagraph 14.1.1 - starting at the 8th line, delete the
phrase, "..., or if the Work should be stopped for a period
of thirty days by the CONTRACTOR because of the CONSTRUCTION
MANAGER's failure to recommend or the ARCHITECT's failure to
issue a Project certificate for Payment as provided in
Paragraph 9.7 or because the OWNER has not made payment
thereon as provided in Paragraph 9.7"
2. Subparagraph 14.2.1 - change the words 'seven days' in the
13th and 18th line, to '72 hours'.
01/06/92 SUPPLEMENTARY GENERAL CONDITIONS (ADD. 2)
00805 - 16
SECTION 00970
PROJECT SAFETY AND HEALTH PLAN
1.1
REGULATIONS AND POLICIES
1.1.1
1.2
1.2.1
Every Trade Contractor and Trade Subcontractor employed
on the Project shall comply with all applicable local,
State, and Federal safety and health regulations and
with Morrison-Knudsen Company, Inc. safety and health
policies as described herein.
PROJECT SAFETY AND HEALTH REQUIREMENTS
It is recognized that it is good business and evidence
of competent leadership to prevent the occurrence of
incidents that lead to occupational injuries or
illnesses. Safety and health requirements on this
project include, but are not limited to, the following:
.1 In general, this accident prevention policy is
based on a sincere desire to eliminate personal
injuries, occupational illnesses, and equipment
and property damage; and to protect the general
public exposed to or associated with the work.
.2 The importance of the safety of all workers on the
project shall be recognized and accident
prevention shall be an integral part of all
operations.
.3 Each Trade Contractor and Trade Subcontractor
shall conduct work in a safe and practical manner
in conformance with the OSHA Safety and Health
Regulations and the latest edition of the Manual
of Accident Prevention, Associated General
Contractors of America.
.4 Each Trade Contractor and Trade Subcontractor
shall observe all applicable Federal, State, local
and project laws and regulations pertaining to
safety and health, pollution control, water
supply, fire protection, sanitation facilities,
waste disposal and other related items.
.5 The Mandatory Safety and Health Rules shall be
posted in a conspicuous location along with the
OSHA and Emergency Phone Number posters.
11/21/91
00970 - 1
PROJECT SAFETY AND HEALTH PLAN
.6 A record of all occupational injuries and
illnesses shall be maintained. Medical and lost
time cases shall be properly recorded on the OSHA
log, and reported to MORRISON-KNUDSEN/GERRITS. A
copy of the insurance report for workmen
compensation cases shall be provided to MORRISON-
KNUDSEN/GERRITS.
.7 Each Trade Contractor and Trade Subcontractor
shall provide or arrange for adequate first aid
facilities, emergency transportation and persons
qualified in first aid.
.8 Each Trade contractor and Trade Subcontractor
shall cooperate fully with all other contractors
in their respective safety and health programs.
.9 Good housekeeping shall be observed at all times.
Waste, debris, and garbage shall be removed daily
or placed in appropriate waste containers. All
materials, tools, and equipment shall be stored in
a safe and orderly fashion. Each contractor shall
donate 10% of their staff to a crew that will
convene every Friday at 1:00pm for a joint site
clean-up effort not to exceed a duration of three
hours.
In summary, there will be a 3-part clean-up plan.
The first part consists of the contractor cleaning
up on a daily basis, his workstations, and his
trade work. The second part consists of the
general clean-up, the concerted effort by all
trade contractors working on the project. A
minimum of (1) crew is to be utilized by each
contractor, or 10%, whichever is more. The third
part consists of the Owner cleaning up for a
particular trade contractor should adequate notice
not compel him to clean up his work. In this
case, the appropriate contractors will be
backcharged.
.10 This project shall be a Hard Hat job and all
supervisors, employees and visitors shall be
required to wear a suitable hard hat while on the
project site.
.11 other appropriate personal protective equipment
shall be provided and worn as required including
11/21/91
PROJECT SAFETY AND HEALTH PLAN
00970 - 2
but not limited to long pants, shirts with sleeves
and appropriate leather work boots.
.12 Temporary construction aids such as ladders,
scaffolds, stairs, railings, etc. shall be
provided to facilitate access or working
conditions in a manner that shall conform to the
safety standards specified by Federal, state,
Local or manufacturer's recommendations or
stipulations.
.13 Each Trade Contractor and Trade Subcontractor
shall be expected to indoctrinate his employees as
to the safety and health requirements of this
project and to enforce adherence to safe work
procedures.
.14 If MORRISON-KNUDSEN/GERRITS notifies any Trade
Contractor of any noncompliance with the
provisions of this program, the Trade Contractor
shall make all reasonable efforts to immediately
correct the unsafe conditions or acts.
Satisfactory corrective action shall be taken
within the specified time. If a Trade Contractor
or Trade Subcontractor refuse to correct unsafe or
unhealthy conditions or acts, MORRISON-
KNUDSEN/GERRITS shall take one or more of the
following steps:
a. Cease the operation or a portion thereof.
b. stop payment for the work being performed.
c. Correct the situation using other forces and
back charge the Trade Contractor expenses
incurred.
d. Increase withholding in proportional
increments for that given pay period.
.15 All Trade Contractor's Superintendents shall be
required to attend and participate in all general
project safety meetings. These meetings will be
included in the weekly coordination meetings as
previously specified or on an as needed basis.
.16 All Trade Contractors shall conduct Weekly Tool
Box Safety Training Meetings, and shall document
11/21/91
00970 - 3
PROJECT SAFETY AND HEALTH PLAN
the minutes on the forms provided. These forms
are to be transmitted to Morrison-Knudsen/Gerrits
on a weekly basis. All employees working at the
project site shall be required to attend and
participate in the meetings.
.17 Shortly after the award of the contract and prior
to the beginning of work, an Activity Hazard
Analysis (phase plan) shall be prepared by the
contractor and submitted to Morrison-
Knudsen/Gerrits for approval. The analysis will
address the hazards for each activity to be
performed in that phase and will present the
procedures and safeguards necessary to eliminate
the hazards or reduce the risk to an acceptable
level. A phase is defined as an operation
involving a type of work presenting hazards not
experienced in previous operations or where a new
subcontractor or work crew is to perform work.
The analysis will be discussed by the contractor
and Morrison-Knudsen/Gerrits on-site
representatives at the Preparatory Inspection
Meeting. Work will not proceed on that phase
until the Activity Hazard Analysis (phase plan)
has been accepted by Morrison-Knudsen/Gerrits.
.18 No personal radios or stereos will be allowed on
the job-site.
1.3
FIRE PROTECTION
1. 3.1
Every Trade Contractor and Trade Subcontractor employed
on the Project shall exercise good construction
practices to prevent fire. It shall be the
responsibility of the Trade Contractor to insure that
general fire protection facilities are adequate for his
work and to provide additional fire protection
facilities and devices, including fire extinguishers as
required by their scope of work.
1.4
WORK NEAR ENERGIZED ELECTRICAL LINES OR OTHER UTILITIES
1. 4.1
It shall be the Trade Contractor's sole and exclusive
responsibility (a) to provide personnel capable of
working adjacent to energized electrical lines or other
utilities; (b) to provide adequate, safe and properly
maintained equipment; (c) to conduct all of his work in
accordance with the safety rules and regulations
11/21/91
PROJECT SAFETY k~D HEALTH PLAN
00970 - 4
1.5
1. 5.1
1. 5.2
1. 5.3
prescribed by the National Electric Code, National
Electric Safety Code, H30, and Safety Rules for
Installation and Maintenance of Electrical supply and
Communication Lines Hand Book 81, Occupational Safety
and Health Act of 1970, as well as other safety codes
in effect at the site of construction and as specified
elsewhere herein, or as are generally applicable to the
type of work being performed; and (d) to continuously
supervise and inspect the work being performed to
assure that the requirements of (a), (b), and (c) above
are complied with and nothing in these Contract
Documents shall be held to mean that any such
responsibility is the obligation of the Owner or the
Architect or the Construction Manager.
BARRICADES, WARNING DEVICES AND LIGHTING
The Trade Contractor shall be solely responsible for
providing temporary ladders, guard rails, warning
signs, barricades, night guard lights, and deck or
floor closures required in connection with his work to
comply with Federal, State and local safety
requirements. The Trade Contractor shall be solely and
exclusively responsible for the design, construction,
inspection and maintenance of such facilities at all
times.
It shall be the responsibility of the Trade Contractor
to provide additional temporary lighting, if needed to
maintain safe conditions.
It shall be the sole and exclusive responsibility of
the Trade Contractor to provide a safe place to work
for all laborers and mechanics and other persons
employed on or in connection with the project, and
nothing in these Contract Documents shall be construed
to give any of such responsibility to the Owner, the
Architect, or the Construction Manager.
11/21/91
PROJECT SAFETY AND HEALTH PLAN
00970 - 5
SECTION 00980
CONTRACTOR QUALITY CONTROL PLAN
1.1
1.1.1
1.2
1.2.1
1.2.2
1. 2.3
1. 2.4
MORRISON-KNUDSEN/GERRITS' DUTIES AND RESPONSIBILITIES
The Morrison-Knudsen/Gerrits' superintendent will
monitor all work performed by the Trade Contractor and
assist the Trade Contractor with his conformance of the
work to the Contract Drawings and Specifications.
TRADE CONTRACTOR'S DUTIES AND RESPONSIBILITIES
The Trade Contractor is responsible for the quality of
the work performed by his work force on this project as
well as the quality of the material, equipment and
supplies furnished by him to be incorporated into the
work.
The Trade Contractor will designate a Quality Control
Representative who will be on site at all times while
the respective Trade Contractor's work is in progress
and will have the authority and responsibility to
accept or reject items of work. The Trade Contractor's
Quality Control Representative may delegate his duties
but the primary responsibility and authority will rest
on him.
The Trade Contractor's Quality Control Representative
will coordinate the submittal of all shop drawings,
product data and samples to Morrison-Knudsen/Gerrits.
Any submittal that is a variance to the contract
requirements must be identified as such and transmitted
to the Construction Manager for submittal and approval
by the Architect/Engineer or Owner. No work requiring
submittal of a shop drawing, product data or sample
shall commence until the submittal has been reviewed
and approved by the Architect/Engineer.
The Trade Contractor will bear the responsibility of
notifying the designated material-testing laboratory,
whether Monroe County or Contractor is required to
perform testing of materials as required by the
contract drawings and specifications in a timely
fashion to prevent needless cancellations and delays of
work activities. Any costs caused by untimely
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
00980 - 1
1. 2.5
1. 2.6
1.3
1. 3.1
notification shall be borne by the Contractor.
The Trade Contractor's Quality Control Representative
will review his drawings, procurement documents and
contracts to insure that the technical information
provided and all work performed is in accordance with
the latest revisions of the Contract Drawings and
Specifications.
The Trade Contractor's Quality Control Representative
will perform an inspection upon receipt at the site of
the work of all materials, equipment and supplies
including those furnished to him by the Owner. Notes
from this inspection will be filled out on the
appropriate form and included with the Contractor Daily
Quality Control Report. Items which are damaged or not
in conformance with the respective submittals, quality
standards, contract drawings and specifications shall
be brought to the attention of Morrison-
Knudsen/Gerrits' representative on site and then will
be identified and segregated from accepted items.
Items thus identified will not be incorporated into the
work until corrective action acceptable to Morrison-
Knudsen/Gerrits is completed. Items determined
unsalvageable will be removed from the job site. These
items shall be noted as deficient in the applicable
section of the Contractor Daily Quality Control Report.
INSPECTION AND TESTING
INSPECTION PLAN
Morrison-Knudsen/Gerrits utilizes a multi-point
inspection plan for each separate feature of work to be
performed under this Trade Contract, i.e., work
described by each division of the technical provision
section of the contract specifications. This plan
consists of the following:
.1 Preparatory Inspection - Prior to commencing the
work, the Trade Contractor's Quality Control
Representative will meet with Morrison-
Knudsen/Gerrits' Superintendent and the
Architect's representative if he so desires to
attend and check the following items at a minimum
for conformance:
(a) Approval of shop drawings and submittals.
00980 - 2
11/21/91 CONTRACTOR QUALITY CONTROL PLAN ~~D. 3)
(b) Approval of inspection and test reports of
materials and equipment to be utilized.
(c) Completion of previous operations of
preliminary work.
(d) Availability of materials and equipment
required.
(e) Potential utility outages.
(f) Any other preparatory steps dependent upon
the particular operation.
(g) Quality standards.
(h) Safety or environmental precautions to be
observed. (Phase Hazard)
Note:
Morrison-Knudsen/Gerrits will record the minutes
to this inspection meeting and distribute
accordingly.
.2
Initial inspection - Upon completion of a
representative sample of a given feature of the
work, the Trade Contractor's Quality Control
Representative will meet with the Morrison-
Knudsen/Gerrits superintendent and the Architect's
representative if he so desires to attend and
check the following items at a minimum for
conformance:
(a) Workmanship to established quality standards.
(b) Configuration to contract drawings and
specifications.
(c) Construction methods, equipment and tools
utilized.
(d) Materials and articles utilized.
(e) Adequacy of testing methods.
(f) Adequacy of shop drawings.
(g) Adequacy of safety or environmental
precautions.
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
00980 - 3
Note:
.3
Note:
Note:
Morrison-Knudsen/Gerrits will record the minutes
to this inspection meeting and distribute
accordingly.
Follow-up Inspections - The Trade Contractor's
Quality Control Representative will inspect the
work daily to assure the continuing conformance of
the work to the workmanship standards established
during the preparatory and initial inspections.
Additionally, as a part of the follow-up
inspection, sign-off sheets will be utilized as
often as possible. The intent of these sheets is
to achieve concurrence from other trade
contractors and responsible parties that ensuing
work can indeed commence over underlying work.
This will prevent oversights and omissions which
could elevate costs. Sign-off sheets shall be
used for, but not be limited to, concrete,
drywall, ceilings, painting, roofing substrates
and flooring. These reports are to be generated
by the applicable Trade Contractor and submitted
to Morrison-Knudsen/Gerrits' superintendent for
approval prior to the start-up of work.
Failure to generate a sign-off sheet or to attain
proper signatures prior to covering up underlying
work may affect payment for that piece of work if
ensuing problems are detected or not. This
disciplinary action shall be carried out via the
Nonconformance Report. (See section 1.4.2 of this
plan. )
The Trade Contractor shall be responsible to
record these inspections and all other project
related activities encountered throughout the day
on the Contractor Daily Quality Control Report.
. 4
Completion Inspections - Upon completion of a
given feature of the work, the Trade Contractor's
Quality Control Representative will meet with
Morrison-Knudsen/Gerrits' Superintendent, if he so
desires to attend, to perform an inspection of the
completed work. Non-conforming items will be
identified and corrected prior to commencement of
the next operation.
The Trade Contractor shall conduct and report
00980 - 4
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
1.3.1.5
1.3.1.6
1. 3.2
1.3.3
corrections of this inspection which shall be a
required submittal.
Follow-On Inspections - Upon execution of the
contractor's completion inspection in elements of the
work which result in concealment; such as, ceiling and
drywall installations, MK/G shall schedule and conduct
multi-trade or singular inspections prior to covering
installation.
Note:
MK/G will record the minutes to this
inspection meeting.
Pre-Final Inspection - Upon substantial completion of
the project work MK/G shall coordinate and conduct a
universal inspection of all areas and elements of the
work. The Architect/Engineer may be represented if he
so desires. This inspection shall be completed at
least (15) days prior to the final substantial
completion inspection which shall be conducted by the
AlE. All deficiencies and incomplete work should be
completed prior to the final substantial completion
inspection.
OPERATION AND CHECK OUT TESTING
The Trade Contractor will provide personnel and
equipment to perform the operational tests and checkout
of the equipment, facilities or equipment constructed,
fabricated or installed under this Trade Contract.
Morrison-Knudsen/Gerrits' Superintendent will
coordinate and witness all such tests. Notification
should be given at least ten (10) days in advance of
the scheduled tests.
FINAL INSPECTION and issuance of the AlE CERTIFICATE OF
SUBSTANTIAL COMPLETION
Morrison-Knudsen/Gerrits' Superintendent will
coordinate and attend all final inspections of the work
by the Architect/Engineer. Prior to requesting a final
inspection, all tests for the equipment and systems
must be completed.
Upon completion of the AlE's inspection, the A/E will
publish outstanding items and issue a Project
Certificate of Substantial Completion, which will
define the date of 'Turn-Over' to the Owner the care,
11/21/91 CONTRACTOR QUALITY CONTROL PLAN {ADD. 3)
00980 - 5
control and custody. Reference section 00800,
Substantial Completion.
1.4
REPORTING
Maintaining accurate and retrievable records is
extremely important in the Quality Assurance Program.
These records will act as a main source of information
in the present and in the future for the entire project
management team. The main report that will be utilized
to provide this information is the Daily Quality
Control Report. Nonconformance Reports may also be
issued.
1. 4.1
DAILY QUALITY CONTROL REPORT
The Daily Quality Control Report shall be used to
document the summary of daily inspection activities
performed by the Trade Contractor's designated Quality
Control Representative. It shall include any of the
steps of inspection that are performed that day, all
test monitoring and any rework of nonconforming items.
The daily Quality Control Report section of the Daily
superintendent's Report will be routinely used for
daily reporting requirements. When the magnitude or
complexity necessitates such, a more separate and
comprehensive form will be used. Reference
Contractor's Daily Report, and as needed Contractor
Daily Quality Control Report, section 01385.
1. 4.2
NONCONFORMANCE REPORT
Nonconformance Reports will be issued for work that is
found to be in nonconformance with the contract
documents or the referenced quality standards. The
report will be issued by Morrison-Knudsen/Gerrits.
It is not the intent to routinely and repeatedly issue
nonconformance reports, but to issue them only after
normal enforcement standards have been exhausted, or if
the work performed is a detriment to the project.
A copy of the Nonconformance Report will be forwarded
to the Project Manager for his information and/or
action. It should also be included in the Trade
Contractor's Daily Quality Report package for general
review.
11/21/91 CONTRACTOR QUALITY CONTROL PIAN (ADD. 3)
00980 - 6
Nonconformance Reports will be signed off once the
deficient item or items have adequately been corrected.
This will be done by the issuing Superintendent and
Project Manager. These sign-offs will be included with
a corresponding corrective action taken. Significant
nonconformances need to be addressed to prevent
recurrence. The signed-off report will also be
submitted for review.
Work activities affected by a Nonconformance Report
will proportionally counteraffect payments. Whether
that be partial or full retainage will be left up to
the discretion of Morrison-Knudsen/Gerrits' management
team.
1.5
NOT USED
1.6
AUDITS
1. 6.1
Morrison-Knudsen/Gerrits may choose at its option to
perform Trade Contractor audits of their Contractor
Quality Control Plan at any time. Reports of these
audit results will be forwarded to the Project Manager
for his action. Any action items noted during an audit
for the Trade Contractor will be followed up and
documented to insure compliance and avoid recurrence.
1.7
SUMMARY
The intention of this plan is to create a system of
checks and balances that will minimize delays caused by
rework and a lack of planning and maximize production
and insure that the finished product is one that the
entire construction team can pride themselves in.
These goals can be achieved by giving the Owner exactly
what he has bought. The owner will expect no more and
through Quality Assurance, the construction team will
provide no less.
11/21/91 CONTRACTOR QUALITY CONTROL PLAN (ADD. 3)
00980 - 7
SECTION 00800
SUBSTANTIAL COMPLETION AND OWNER ACCEPTANCE
Bid Group 2, and Bid Group 3 Contractors shall turn over care,
custody and control of their work to the Owner as defined in the
issuance of the A/E's certificate of Substantial Completion of the
Project. All contracts in these bid groups shall exchange as a
group and in unison, possession, maintenance and security
responsibilities with the Monroe County Officials. Any portion of
the work which is in non-conformance with the contract documents or
elements which prevent the Owner's use of the facilities for its
intended use shall be excluded from acceptance. The contractor
shall be responsible for all work performed, equipment, and
materials furnished to, or by the contractor under this contract
until the contractors work is completed and has been accepted by
the Owner as stated in the Certificate of Substantial Completion.
In the event of loss, damage or destruction of such work,
equipment, or materials, the contractor at his sole expense shall
promptly repair, restore, or replace such, to the conditions
required by the contract documents.
All warranties and guarantees shall commence as stated on the A/E's
certificate of Substantial Completion.
Substantial Completion certificates for portions of the project or
portions of the work may be used to reduce retention. This partial
certification shall only be used for the purpose of reducing
retention. The implementation and amounts of reduction shall be at
the Owner's sole discretion.
In the event of discrepancy or disagreement in the contract
documents, specifications, and/or drawings, this section will take
precedence over the Supplementary General Conditions, General
Conditions, General Requirements, technical specif ications and
drawings.
OWNER ACCEPTANCE
00800 - 1
11/20/91
- - _. . -. -. --"' -~~ ---........
--
SECTION 01027
APPLICATION FOR PAYMENT
PART 1 - GENERAL
1..1 SUMMARY
A.
section includes:
1. Procedures for preparation and submittal
Applications for Payment.
of
B. Related sections
1. section 00750 - General Conditions
2. section 00900 - AlA G702/G703
2. section 01370 - Schedule of Values
1. .2 FORMAT
A. AlA G702 Application and Certificate for Payment
including continuation sheets when required.
1..3 PREPARATION OF APPLICATIONS
A. Present required information in typewritten form.
B.
Execute certification
authorized officer.
by
notarized
signature
of
C. List each authorized Change Order on the form, including
change order number, date and dollar amount.
D. Prepare Application for Final Payment as specified in
section 01700.
1..4 SUBMITTAL PROCEDURES
A. The initial Application for Payment will not be processed
until the construction schedule, the schedule of values,
and the initial submittal schedule have been received by
the Construction Manager, reviewed and approved by the
Architect.
B. Submi t an updated construction and submittal schedule
with each Application for Payment.
C. Payment Period: submit once per month, during the last
OS/20/91
APPLICATION FOR PAYMENT
01027 - 1
week of the month. Payment will be made by the Owner
within (30) days thereafter.
D. Work Item Update Listing - this work sheet, prepared by
the Construction Manager, shows the work items which are
being considered for progress payments. It is to be
billed from the Contractor's approved schedule of values
and approved changes only. The Contractor must fill in
percentages of work completed on each line item or total
dollar amount of Original Suppliers Invoices. Suppliers
Invoices are then attached for payments on materials
stored.
E. status Meeting - The Contractor's representative and the
Construction Manager review the Contractor's Work Item
Update Listing. Upon agreement between the two parties,
both the Contractor and Construction Manager will sign
off on the form.
F. Estimate Voucher - The Construction Manager will input
the progress into the computer from the work Item Update
Listing, and will issue the Estimate Voucher to the
Contractor.
G. Submit waivers as required.
H. Submit three (3) copies of each Application for Payment.
1..5 SUBSTANTIATING DATA
A. When the Construction Manager and/or Architect requires
substantiating information, submit data justifying dollar
amounts in question.
B. Provide one copy of data with cover letter for each copy
of submittal. Indicate Application number and date, and
line item by number and description.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01027
APPLICATION FOR PAYMENT
01027 - 2
OS/20/91
SECTION 01028
CHANGE ORDER PROCEDURES
PART 1 - GENERAL
1. .1 SUMl1ARY
A. section includes:
1. Promptly implement change order procedures.
a. Provide full written data required to evaluate
changes.
b. Maintain detailed records of the work done on
a time and material/force account basis.
c. Provide full documentation to the Construction
Manager with each request.
2. Designate in writing the member of the Contractor's
organization authorized to accept changes in the
Work.
3. The Owner will designate in writing the person who
is authorized to execute Change Orders.
B. Related requirements:
1. Agreement: The amounts of established unit prices.
2. Agreement: The amounts of established allowances.
3. Conditions of the Contract, Article 12 of the
General Conditions:
a. Methods of determining cost or credit to the
Owner resulting from changes in the Work made
on a time and material basis.
b. The Contractor's claims for additional costs.
1..2 DEFINITIONS
A. Change Order, AlA Document G701/CM: Refer to the General
Conditions.
B. Construction Change Directive: A written order to the
Contractor, signed by the Owner, MK/Gerr i ts and the
Architect, which amends the Contract Documents as
described, and authorizes the Contractor to proceed with
a change which affects the Contract Sum or the Contract
time, for inclusion in a subsequent Change Order.
1..3 PRELIMINARY PROCEDURES
A. A change may be initiated by submitting a Proposal
Request to the Contractor. Request will include:
1. Detailed description of the change, products and
04/30/91
CHANGE ORDER PROCEDu~ES
01028 - 1
location of the change in the Project.
2. Supplementary or revised Drawings and
Specifications.
3. The projected time span for making the change, and
a specif ic statement as to whether overtime work
is, or is not, authorized.
4. A specific period of time during which the
requested price will be considered valid.
5. Such request is for information only, and is not an
instruction to execute the changes, nor to stop the
Work in progress.
B. The Contractor may initiate changes by submitting a
written notice to the Construction Manager containing:
1. Description of the proposed changes.
2. Statement of the reason for making the changes.
3. Statement of the effect on the Contract Sum and the
Contract Time.
4. statement of the effect on the Work of separate
contractors.
5. Documentation supporting change in the Contract Sum
or the Contract Time, as appropriate.
1..4 CONSTRUCTION CHANGE DIRECTIVE
A. In I ieu of Proposal Request, a Construction Change
Directive may be issued for Contractor to proceed with a
change for subsequent inclusion in a Change Order.
B. The Construction Change Directive will describe changes
in the Work, both additions and deletions, with
attachments of revised Contract Documents to def ine
details of the change, and will designate the method of
determining a change in the Contract Sum and change in
the Contract Time.
C. The Owner, Construction Manager, and the Architect will
sign and date the Construction Change Directive as
authorization for the Contractor to proceed with changes.
D. At completion of the change, submit itemized accounting
and supporting data as provided in the Article
"Documentation of Proposals and Claims" of this section.
E. The allowable costs of such work will be determined as
provided in the General Conditions and Supplementary
Conditions.
F. The Owner, Construction Manager and Architect will sign
and date the Change Order to establish the change in the
Contract Sum and in the Contract Time.
04/30/91
CHANGE ORDER PROCEDURES
01028 - 2
G. The Owner and the Contractor will sign and date the
Change Order to indicate their agreement.
1..5 DOCUMENTATION OF PROPOSALS AND CLAIMS
A. Support each quotation for a lump-sum proposal, and for
each unit price which has not previously been
established, with sufficient substantiating data to allow
evaluation of the quotation.
B. On request provide additional data to support time and
cost computations:
1. Labor required.
2. Equipment required.
3. Products required.
a. Recommended source of purchase and unit cost.
b. Quantities required.
4. Taxes, insurance and bonds.
5 . Credit for the work deleted from the Contract,
similarly documented.
6. Overhead and profit.
If the Trade Contractor performs the actual
Work, the percentage mark-up for overhead and
profit shall be a maximum addition of fifteen
percent (15%).
If the Trade Subcontractor performs the actual
Work, the percentage mark-up for overhead and
profit shall be a maximum addition of fifteen
percent (15%). If the Trade Contractor does
not enter into the Work, the maximum mark-up
for managing this work will be ten percent
(10%).
If the Trade Subcontractor performs part of
the actual Work, his percentage mark-up for
overhead and profit shall be a maximum
addition of fifteen percent (15%) on his
direct work only. If the Trade Contractor
performs part of the actual work, his
percentage mark-up for overhead and prof it
shall be a maximum addition of fifteen percent
(15%) on his direct work only.
7. Justification for change in the Contract Time.
C.
Support each claim for additional costs, and for the
done on a time-and-material/force account basis,
documentation as required for a lump-sum proposal,
additional information:
work
with
plus
04/30/91
CHANGE ORDER PROCEDURES
01028 - 3
1. Name of the Owner's authorized agent who ordered
the work, and date of the order.
2. Dates and times the work was performed, and by
whom.
3. Time record, summary of hours worked, and hourly
rates paid.
4. Receipts and invoices for:
a. Equipment used, listing dates and times of
use.
b. Products used, listing of quantities.
c. Subcontracts.
5. signature of Construction Manager's superintendent,
concurring with quantities.
1..6 PREPARATION OF CHANGE ORDERS
A. The Construction Manager will prepare each Change Order.
B. Change Order form: AlA Document G701/CM.
C. Change Order will describe changes in the Work, both
additions and deletions, with attachments of revised
Contract Documents to define details of the change.
D. Change Order will provide an accounting of the adjustment
in the Contract Sum and in the Contract Time.
1..7 LUMP-SUM/FIXED PRICE CHANGE ORDERS
A. Content of Change Orders will be based on either:
1. The Proposal Request and the Contractor's
responsive proposal as mutually agreed between the
Owner and the Contractor.
2. The Contractor's Proposal for a change, as
recommended by the Architect or Construction
Manager.
B. The Owner, Construction Manager and the Architect will
sign and date the Change Order as authorization for the
Contractor to proceed with the changes.
C. The Contractor may sign and date the Change Order to
indicate agreement with the terms therein.
1..8 UNIT PRICE CHANGE ORDER
A.
The
1.
content of the Change Orders will be based on either:
The definition of the scope of the required
changes.
The Contractor's Proposal for a change, as
recommended by the Architect, or Construction
2.
04/30/91
CHANGE ORDER PROCEDURES
01028 - 4
Manager.
3. Survey of completed work.
B.
The
1.
2.
amounts of the unit prices to be:
Those stated in the Agreement.
Those mutually agreed upon between
Architect and the Contractor.
the
Owner,
C. When quanti ties of each of the items affected by the
Change Order be determined prior to start of the Work:
1. The Owner, Construction Manager and the Architect
will sign and date the Change Order as
authorization for the Contractor to proceed with
the changes.
2. The Contractor may sign and date the Change Order
to indicate agreement with the terms therein.
D. When quantities of the items cannot be determined prior
to start of the Work:
1. A Construction Change Directive will be issued
directing the Contractor to proceed with the change
on the basis of unit prices, and will cite the
applicable unit prices.
2. At completion of the change, the cost of such work
will be determined based on the unit prices and
quantities used.
3. The Owner, Construction Manager and the Architect
will sign and date the Change Order to establish
the change in the Contract Sum and in the Contract
Time.
4. The Contractor will sign and date the Change Order
to indicate their agreement with the terms therein.
1..9 CORRELATION WITH THE CONTRACTOR'S SUBMITTALS
A. Revise Schedule of Values and Request for Payment forms
monthly to record each change as a separate item of the
Work, and to record the adjusted Contract Sum prior to
submission of Application for Payment.
B. Revise the Construction Schedule to reflect each change
in the Contract Time prior to monthly submissions.
Revise subschedules to show changes for other items of
work affected by the changes.
C. Upon completion of the Work under a Change Order, enter
pertinent changes in Record Documents.
04/30/91
CHANGE ORDER PROCEDURES
01028 - 5
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
****************
END OF SECTION 01028
-
04/30/91
CHANGE ORDER PROCEDURES
01028 - 6
SECURITY PROJECT PROCEDURES
PART 1 - GEl;ERAL
1.1 SUMMARY
A. section Includes
1. Electronic automated computerized security
management system.
2. Provide a complete enclosed raceway system for all
wiring for security devices and controls in
compliance with NEC, NFPA-70 1990 and in accordance
with 16050 and 16111.
3. Drawings for this work are diagrammatic, intended
to convey the extent, general arrangement and
locations of the work. Because of the scale of the
drawings, certain basic items such as conduit
fittings, access panels, cabinet sizes, sleeves,
pull and junction boxes may not be shown. Include
such items where required by code, other sections,
and for proper installation of the work.
4. Equipment specifications may not deal individually
with every part, control, or device which may be
required to produce the equipment warranties.
5. Coordinate with other trades in submittal of shop
drawings. Shop drawings shall detail space
conditions to the satisfaction of concerned trades
and is subject to final review by the Architect.
If installation of equipment, raceways, cable trays
or conduit is performed prior to coordination with
other trades and interferes with work of other
trades, make necessary changes to correct the
condition at no additional cost to the Owner.
6. Provide required integration of components to
create an operational computerized security
management system providing control and monitoring
from a touchscreen CRT.
1.2 TESTS
A. Notify Architect and Owner's representative in writing,
1~ days in advance of testing to prevent delays in
construction schedules.
B. Test systems and place in proper and specified working
order prior to demonstration of the systems.
C. 'Test system grounds to demonstrate that the ground
resistance does not exceed the requirements of the
transient voltage surge suppression (TVSS) or the
National Electric Codes (NEC).
D. Perform tests required by authorities having jurisdiction
11/18/91
SECURITY PROJECT PROCEDURES
01130-1
over the site.
E. Testing shall be in the presence of the Owner's
designated representatives, Contractor and Architect.
1.3 DEMONSTRATION
A. Pr ior to acceptance of the work, the Security System
Installer shall demonstrate to the Owner, designated
representatives, Contractor and Architect, the features
and functions of the system, and all subsystems and shall
instruct the Owner in the proper operation and event
sequences of the system.
B. Demonstrate each system and subsystem. The demonstration
is to consist of not less than the following:
1. Designate actual location of each component of a
system or subsystem and demonstrate its function
and its relationship to other components within the
system.
2. Demonstrate the systems and subsystems operations
by actual "START-STOP/ON-OFF" cycling showing how
to work controls, reset devices, replace fuses and
conduct emergency operating/operations procedures.
3. Demonstrate communication, signaling and security
equipment/devices by actual operation of such
devices.
c. Demonstration of systems are to include, but not be
limited to the following:
1. UPS Power and Distribution system
2. Touchscreen CRT Operations .
3. Alarm Detection and signalling Equipment
4. Door Control/Monitoring System
5. Access Control System
6. situation Alarms (Hardwire)
7. Man-Down Alarms (Wireless)
8. CCTV System
9. Intercom Systems
10. Telephone Systems (Inmate/Attorney/Visitor)
11. Lighting Control
12. Fire Alarm Interface
13. Cable Supervision System (Random Points to be
Selected by Architect)
D. Security System Installer/Integrator shall furnish the
necessary trained personnel to perform the demonstration
and instructions and shall arrange to have the
manufacturer's representatives present to assist with the
demonstrations. The Security System Installer shall
allow a minimum of one week for performing the prescribed
demonstrations.
E. Security systems Installer/Integrator shall arrange with
the Owner the date and times for performing the
demonstration. The Owner will select date and time for
11/18/91
SECURITY PROJECT PROCEDURES
01130-2
- .- -----_.~-~.....,-
demonstration.
F. Comply with requirements of Section 01670 SYSTEMS
DEMONSTRATIONS.
1. security System Installer/Integrator shall video
tape in high speed, high quality, VHS format the
demonstration of systems listed.
1.4 QUALIFICATIONS
A. Manufacturer Qualifications: Company specializing in
electronic automated computerized security management
systems of the same type, scope, operation and magnitude
for a minimum of five years. Documented experience shall
include the following:
1. List at least 10 facilities of equal size and
technical requirements utilizing the equipment
submitted.
2. For each facility, list:
a. Name and location of facility
b. Date of occupancy by Owner
c. Owner's representative to contact and
telephone number
d. Construction Manager and/or General Contractor
e. Architect
B. Use the products of a single manufacturer for similar
type equipment, i.e., motion detectors, magnetic
contacts.
C. Use products made by companies regularly engaged in the
manufacture of the type equipment specified.
1.5 IDENTIFICATION
A. Identify control and sub-control, motor and equipment
controls, remote relay cabinets, address panels, system
interface cabinets, and similar equipment with 1/211 red
lettering or as specified for individual piece of
equipment.
B. Identify pull and junction boxes in service areas,
tunnels, above accessible ceilings, and in accessible
chases with 1/2" red lettering indicating the circuit and
system. Example: Secur i ty Alarms "SY", Fire Alarms
"FA", Circuit Number "SY-126".
C. Engraved laminated plastic tags may be used for
identification in lieu of painted lettering.
D. Provide typewritten circuit directories installed in 3
ring binders with transparent page protectors in each
control and sub-control cabinet.
1.6 RECORD DOCUMENTS
A. Provide complete schematic drawings depicting location of
interface, number of conductors, types of connectors,
circuit requirements, and type of enclosure.
11/18/91
SECURITY PROJECT PROCEDURES
01130-3
1.7 PROTECTION OF EQUIPMENT
A. Protect mater ials stored on the job site. Protect
materials during construction and after installation.
B. Provide and apply protective material immediately upon
receiving the products and maintain throughout the
construction process.
C. Keep products clean and dry or by elevating equipment
above ground and floor.
D. Take precautions to protect apparatus and materials from
damage. Failure to protect materials constitutes
sufficient cause for rejection of the apparatus or
material.
E. Protect equipment and factory finish from damage during
construction operations and until final acceptance.
Restore finishes that become stained, scratched, or
damaged.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
NOT USED
********************
END OF SECTION 01130
SECURITY PROJECT PROCEDURES
01130-4
11/18/91
SECTION 01200
PROJECT MEETINGS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Project meetings
1..2 The CONSTRUCTION MANAGER'S RESPONSIBILITY
A. Construction Manager shall schedule and administer pre-
construction meeting, periodic progress meetings, and
specially called meetings throughout progress of the
Work.
1. Prepare agenda for meetings.
2. Provide notice of each meeting four days in advance
of meeting date, or provide as much advance notice
as possible.
3. Make physical arrangements for meetings.
4. Preside at meetings.
5. Record the minutes; include significant proceedings
and decisions.
6. Reproduce and distribute copies of minutes.
a. To participants in the meeting.
b. To parties affected by decisions made at the
meeting.
c. Furnish three copies of minutes to the
Architect.
B.
Representatives of the Contractors,
suppliers attending meetings shall
authorized to act on behalf of
represents.
subcontractors and
be qualified and
the entity each
C. The Architect and the Owner's Representative may attend
meetings to ascertain that the Work lS expedited
consistent with the Contract Documents and construction
schedules.
1..3 PRE-CONSTRUCTION MEETING
A. Location: A central site designated by the Construction
Manager.
B. Attendance:
1. The Owner's Representative.
11/21/91
PROJECT MEETINGS
01200 - 1
2. The Architect and his professional consultants (as
required) .
3. Construction Manager.
4. The Contractor's Superintendent.
5. Major subcontractors.
6. Major suppliers.
7. others as appropriate.
c. suggested Agenda:
1. Distribution and discussion of:
a. List of major subcontractors and suppliers.
b. Projected Construction Schedules.
2. critical Work sequencing.
3. Major equipment deliveries and priorities.
4. Project Coordination.
a. Designation of responsible personnel.
5. Procedures and processing of:
a. Field decisions.
b. Proposal requests.
c. Submittals.
d. Change Orders.
e. Applications for Payment.
6. Adequacy of distribution of the Contract Documents.
7. Procedures for maintaining Record Documents.
8. Use of premises:
a. Office, work and storage areas.
b. The Owner's requirements.
9. Construction facilities, controls and construction
aids.
10. Temporary utilities.
11. Safety and first-aid procedures.
12. Security procedures.
13. Housekeeping procedures.
14. Distribute meeting minutes within (3) days.
1..4 WEEKLY PROGRESS MEETINGS
A. The Contractor's Project Manager and/or Superintendent
shall be required to attend a weekly scheduling meeting.
B.
Location of the meetings:
Manager.
Office of the Construction
C. Attendance:
1. The Architect and his professional consultants as
needed.
2. Contractors as appropriate to the agenda.
3. suppliers as appropriate to the agenda.
4. others.
D. suggested Agenda:
11/21/91
PROJECT MEETINGS
01200 - 2
1. Review of Work progress since previous meeting.
2. Field observations, problems, conflicts.
3. Problems which impede Construction Schedule.
4. Review of off-site fabrication, delivery schedules.
5. Corrective measures and procedures to regain
projected schedule.
6. Revisions to Construction Schedule.
7. Progress, schedule, during succeeding Work period.
8. Coordination of schedules.
9. Review submittal schedules.
10. Maintenance of quality standards.
11. Pending changes and substitutions.
12. Review proposed changes for:
a. Effect on Construction Schedule and on
completion date.
b. Effect on other contracts of the Project.
13. Other business.
14. Distribute meeting minutes.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01200
11/21/91
PROJECT MEETINGS
01200 - 3
SECTION 01301
SUBMITTALS
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Submit to the Construction Manager, shop drawings,
product data, certifications and samples required
by the technical sections.
2. Prepare and submit a separate schedule listing
dates for submission and dates for review.
B. Related Sections:
1. Section 00750 - GENERAL CONDITIONS
2 . Individual submittals required: refer to each
specific section, for certifications, shop
drawings, product data and sample requirements.
1.2 SUBMITTAL TRANSMITTAL FORM
A. Attached, and made a part of this section 01301, is a
copy of the submittal Transmittal Form, which shall be
filled out by the contractor and submitted with each and
every submittal. Follow the instruction sheet, also
attached, for directions on this procedure. It is
essential that the submittal Transmittal Forms are filled
out in their entirety for the system to function
properly.
B. Transmittal Form, originals for contractors use, will be
supplied by the Construction Manager, and is a 6-part
form.
1.3 SUBMITTAL SCHEDULE
A. The Contractor shall submit within seven (7) days of
award of the Contract a preliminary "Submittal Schedule"
to the Construction Manager for review, modification and
response. No payment applications will be processed
prior to finalizing the submittal schedule. The
"Submittal Schedule" shall contain the following
information:
1. Specification Section number and name.
2. Specification Section paragraph identification
which describes submittal requirement.
3. Submittal information required, (i.e., sample, test
data, shop drawing, etc.).
08/20/91
SUBMITTALS (ADD.l)
01301 - 1
B. The Contractor shall also supply the following dates in
order to meet the project schedule.
1.
Date submittal is scheduled to be submitted and
received by the Construction Manager.
Date contractor has scheduled to order material or
equipment or the submittal item.
Date contractor has scheduled delivery to job-site
equipment or the submittal item.
Add any remarks or unique items that the CM or A/E
should be aware of.
2.
3 .
of material or
4 .
C. The Contractor shall allow a minimum of (2) weeks for
review of submittal by A/E (in calendar days) .
D. The submittal master record will then be used to track
submittals within the process.
1.4 SHOP DRAWINGS
A. Submi t legible shop drawings in the form of posi ti ve
pr inting reproducible transparencies, commonly ca lled
sepia prints, suitable for reproduction use on dry print
diazo type machines. Sepia prints which cannot be
reproduced will be returned to the Contractor for
resubmittal.
B. Provide shop drawings as complete submittals (no partial
sets) on original drawings or information prepared solely
by the fabricator or supplier. Deviation from complete
submittals will only be allowed by pre-arranged method.
C. Do not reproduce the Contract Drawings for shop drawing
submittals.
D. Sheet sizes shall not exceed the size of the Contract
Drawings.
E. Each sepia print shall have blank spaces large enough to
accept 4" x 4" review stamps of the Architect and the
Contractor.
F.
Each
1.
2.
3.
sepia print shall carry the following
Project name and contract number.
Date.
Names of:
a. The Architect
b. The Construction Manager
c. The Contractor
d. Supplier
e. Manufacturer
information:
08/20/91
SUBMITTALS (ADD.l)
01301 - 2
4. Identification of product or material.
5. Relation to adjacent structure or materials.
6. Field dimensions, clearly stated as such.
7. Specification section number.
8. Applicable standards such as ASTM or Federal
Specification.
9. Identification of deviations from Contract
Documents.
10. Reference to construction drawings by drawing
number and/or detain number.
G. Submit sepia prints without folds either as flat sheets
if size permits, or rolled in tubes.
H. The contractor shall submit (2) reproducibles and (4)
blueline or blackline sets to the CM. The CM will return
(1) reproducible to the contractor after review/return
from the A/E.
1.5 PRODUCT DATA
A. Product data such as catalog cuts, brochures or
manufacturer's sheets may be submitted in lieu of sepia
prints if adequately identified. Submit seven copies of
product data to the Construction Manager.
B. Modify product data sheets to delete information which is
not applicable to the Project. Provide additional
information if necessary to supplement standard
information.
C. Product data sheets that are submitted with extraneous
information not deleted and/or modified will be returned
without review to the Contractor for resubmittal.
D. The contractor shall submit at a minimum, (1) original
and (6) copies to the CM. The CM will return (2) copies
to the contractor after review/return by the A/E.
1.6 SAMPLES
A. Provide samples to illustrate materials, equipment or
workmanship, and to establish standards by which
completed work may be judged.
B. Construct mock-ups as required by the technical sections,
at the Project site in a location designated by the
Construction Manager. Construct mock-ups, including
adjacent work required, to demonstrate the final
appearance of the Work.
08/20/91
SUBMITTALS (ADD.l)
01301 - 3
C. 'The contractor shall submit (3) samples to the CM, and
(1) will be returned to the contractor after
review/return from the A/E.
1.7 CERTIFICATIONS
A. Provide certifications as required by various technical
sections on the Contractor's letterhead stationary.
certifications shall be identified to this Project, dated
and bear Contractor's signature in the same format used
for the Owner/Contractor agreement.
B. Clearly identify the materials referenced and state that
the material and the intended installation methods, where
appl icable, are in compl iance with the Contract
Documents. Attach manufacturer's affidavits where
applicable.
C. The contractor shall submit (1) original and (6) copies
to the CM. The CM will return (2) sets to the contractor
after review/return from the AlE.
1.8 THE CONTRACTOR'S RESPONSIBILITIES
A. Before making submittals to the Construction Manager,
review each submittal, make changes or notations as
necessary to conform to the Contract Documents, identify
such review with review stamp and forward reviewed
submittal with comments to the Construction Manager for
review. Return submittals not meeting Contract
requirements to subcontractors and do not forward such
submittals to the Construction Manager.
B. Submit catalog sheets, product data, shop drawings and
where specified, submit calculations, material samples,
color chips or charts, test data, warranties and
guarantees all at the same time for each submittal item.
C. verify field measurements and product catalog numbers or
similar data.
D.
clearly identify on the
Construction Manager
submittals from the
Documents.
submittal a~d transmittal to the
in writing of deviations in
requirements of the Contract
E. After the Construction Manager's and the Archi tect' s
review, distribute copies with one copy to be maintained
at the Project site for reference use and other copies
distributed to suppliers and fabricators.
SUBMITTALS {ADD.1}
01301 - 4
08/20/91
F.
Do not begin the Work which requires submittals until
return of submittals with the Construction Manager's and
the Architect's stamp and initials indicating review.
G.
The Contractor's responsibility for errors and omissions
in submittals is not relieved by the Construction
Manager's or the Architect's review of submittals.
H.
The Contractor's responsibility for deviations in
submi ttals from requirements of the Contract Documents is
not relieved by the Construction Manager's or the
Architect's review of submittals unless the Architect
gives written acceptance of specific deviations.
1.9 THE CONSTRUCTION MANAGER'S RESPONSIBILITIES
A. The Construction Manager will return to the Contractor,
without review, all submittals not bearing the
Contractor's review stamp or not showing it has been
reviewed by the Contractor.
B. After the Architect's review, the Construction Manager
will forward submittals to the Contractor and retain one
copy for the Owner. The Contractor shall distribute
copies including other copies distributed to suppliers
and fabricators. The Contractor shall supply copies of
reviewed submittals to the Construction Manager in
sufficient quantity to allow proper coordination of the
Contract.
1.10 THE ARCHITECT'S RESPONSIBILITIES
A. The Architect will review submittals with reasonable
promptness, checking only for conformance with the design
compliance of the Project and compliance with information
given in the Contract Documents.
B. The Architect will make changes or notations directly on
the submittal, identify such review with his review
stamp, obtain and record the Architect file copy and
return the submittal to the Construction Manager.
****************
END OF SECTION 01301
08/20/91
SUBMITTALS {ADD.1)
01301 - 5
b
Z
w
:2:
:::l
... U
0
~ ~ 0
C:l w
~ ~ U
;- ~ v Z
0::
~ 0 - UJ
u ;: ct;
" ~
'" cL.
0 " w
I I z c C1:
~ G
<: <
~ , ~ 0:
~ ::i ::;: b
~ E '" ~ z
z z
"" ::;: ~ < 0
::> {: ":l U
Vl '" "
~ ::> Vl ~
In ;;
L!J L!J ~ ::> ~
z 0:: Vl 0 -
g ;; "
I I L!J ;;
a:
....
;:J
,....
<
C
Vl
f--
Z
u.l
::'E
u.l
>
a
g: ~
6 a
....J""u..
<<....J
f--",,<
P.:Gf--
<at:
uo::~
rp..Vl
f-- ~
Z 0::
6 f--
U
u.J
o
0::
Z
o
~
7-
i
o
.."
G:
00
~~
6...;
c.; ,
-
t, ~
Q~3
::2?~
::;: .7:. ~
o
f-
~~_. =
h
<
'J
z
<
'"
<
>
>
'"
'"
c
z
<:>
~
Q -
o
z
~
<
..
V')
,. L!J
0 <5
>lo U
~ ~
E' ;;:
I -,
v ,....
>
~ -- -
~
c5
z
g 0
<: 2
u
3 ~ ~ ~
.;
I ~ ::> u
- Vl ".
I ,.... := ~ -.:;
~
.~ ~ t: ~
<-. E
;, ~ " (5 ,;
'"
~ -, z ";;'
" ~ i
~ - 5
C
- '-'
0
'"
c:J
... 0
c
,.: ~
Z <::
c:
0. c
u
V') .~
z
g -,
"
<: ~ ..
u ;;
\J
\J ::;:
~ :,: E
~
::;.
-
-- ;===
---
~
L!J
;;
uJ
0::
In
f..
z
L!J
o
Z
~
0:
L!J
....
:J
Vl
~
::;:
~
o
~
~
::>
..
c
."
Vi
~
j!
IS
oj
E
:2 "
'" ~ ~
~ ~
;:1 ~C~
r "-i ~ (; r; :/: n :/: -l
o -> ov-<
-;I
l-1
nl)V;(jCF()
.. r. ::; ^' :T 0
:::"~:J~G~
2 ::.-.0 ::.-.:J v
_:::-o~t':1
~~!J~U:l1
~.::.. c..=:
:J ~ :.; ~
:;. z
-V':.r'.
--'"
3~~i~
n .- r-1' ~ ....,
n n (t '1
C. :l. .., O;:l
c:: PJ ~ ,. ::J
~~(t~G
:r-t:~"'n
o~
c::
::.
:=--:
n
;::
o.
::J
:Il
~~~t,;::::~
oo~>o~
~ =- ~:g ::. :::
E.~~~~~
~ ...... ..., :,; ... c.:
!;l > n - " .,.
=,tn9.,Y3i
~ :~ ~ ~ ~. ~
~l~ ~.~
~. i
0;;
'"
s
5
-<
.,. ::l
cr.
:r-
'T1CJonc::J> >
-;I
~O;;.;:%);o>-;I
n~r.o-.:J-.:J::O
<:T<....-.:J-.:JO
(1;. (t ",. PJ '1 .., <:
~'1(t-.:J~~>
n ~-.:J n r, t""
P- (30.c.
~<PJPJ()
(\ n :Il tr. 0
'" 0. ::l tr. C1
if OC::tT1
:3 oerC/)
_. 0. :3
" ~.
n
c.
::l
o
PJ
'U
'U
'1
o
<
e:.
'1
(t
..D
c::
::;.
n
0.
\>
~
~
~~l~i
c..:.: ." C"-
~- ~ a
~ 3
~
;:,
~
~
~.
!~- - -~T - u--- ~rr I ~r-Jnll-rl!I--: -~i~ ~~: f:= C~=7~1~
I Jj" ; 1 I 'I ~ ~ ~ !: ~ ;- z
: 1- -I t i <-- 1 iFJ, ~ ~ ; ~ ~
\K r'l' ' i ii, \ ii, ~ < ~ ~ ;
~ '.:::/ ' i II II , ' I ' ~ ~ -;; -<
, , ~ ~~- ~T ~ ~ ~
, 1/ ~z ~t ~; f _>~>>=1
< ~!t\.1 ~ = -
,-W' s - ~ ~ ~
'~i\ '! : ; U\ i i
i V 3:
I . ~
I I Zi.
i .
.:
,;:s..
',t' ;
I
I ;?'\
'~; -
~~~--
~ ~\, ~ ~ I, ;
I~ ~ '~
'>
C8~
x ~ (0.
~ ~. ~ !
" ~
i ~ ~
>
z ~
! ~ :;
., ~
~ 0
~-
~ ~ ~
~
:J
@)
~,
~
z
~
---'~=:"-~
2
J
x
<:
@~
,.
:: t..,)
N N t"'.-'.................-
~:--F-.":;:X:-J.~~
_ X....
-~. .
~
~ ~ :~t.J:-~
n
~~ ~ i [ [ ~ !
~ ? ~ ::: Q Q n .
-' =:~nn~^.-
~.-._~-- -
, c- g ~ ~_ ; ""
;-~E......:;.~~
~~~~~;[
j :.. ~ ~, 3 ~
~::..~~~
'- n ~:r, - 3
ngt~~
.. ~ :; F."..:s '0
f~: !f;
~ C:or. ~!.l
r. 3 c' :II C
Hi l(
~. ~ ~ ;"
~ :;. ;.
(r; ~ n
n
!2.,
~.
~~i~~~~i~j~~~~[]~t~~~~~6
_ _ <; =_ ~' ~ ri. 3 X 1") ~ ]. 3 ~ =:' ?: __ ~ if :;f =- n
~=r.~~.~.?~ao~'~c~~~~~;_~;3~X
~ :.. ::'... ......' r. ~ ~ ::> -. -., -- ... L.:
_ ,,~= ~ g ~.' : ;. =- ~ =- ~_' ~_ ~ '1 - - .... ~
~ "V-:o -co -- ;;;; 5~
!illl! o-~" ~~6?~~~~~ ~~
t ~- S" :;- :::.; 3
g'"::Sc'~~"l
""' _ c. 3 '"'0 ""'I
~~~!~
"'Q )0( ::l _ (')
'<~35
f";. ('; ;II
1; ::l ~
= .~. 5-
~ ::l ""
;; :;.~
~ n C'.
.....n .2 _'7~;?:;Ij... ~
-~ ~ ~ "" ~ - ~ ~ ~ -
:; g ~ ~ ~ :_r;' .<i
i:"[ ~ V) ~
it; 0 ~;;~. s
g? ~B K~
::l ~ ~' ?
-, "8.:; 3'"
2~
'r,'
!:':. .
~~
~
~
..
z-;;:.;
r. ""\
:;
~
:?
.,
~
-;;
;'(5
~ x
..
c
..
g
=- x
8
"
;;:x
n
S.
l
z
~
:;.
n
'-'
"
;;
?
:;
~
SECTION 01310
PROGRESS SCHEDULES
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Progress schedules
2. Revisions to schedules
B. Related sections:
1. SCOPE OF WORK
c. Description:
1. Progress Schedules:
Promptly after award of the Contract, prepare and
submi t to the Construction Manager, construction
progress schedules for the work, with subschedules
of related activities which are essential to its
progress. Also incorporate manpower loading
related to each activity on the construction
schedule.
2. Revisions to Schedule:
Submit revised/updated progress schedules with each
payment application..
1. .2 FORMAT
A. Prepare Progress Schedules as a hor i zonta 1 bar chart with
separate bar for each major portion of Work or operation,
identifying the first work day of each week.
B. Include numeric manpower loading associated with each
horizontal bar, clearly defined.
C.
Scale and spacing:
revisions.
to provide space for notations and
D. Sheet size: minimum 8 1/2" x 11".
1..3 CONTENT
A. Indicate complete sequence of construction by activity,
with dates for beginning and completion of each element
of construction.
OS/20/91
PROGRESS SCHEDULES
01310 - 1
B. Show the manpower loading for each activity.
c. Identify each item by specification section number.
D. Identify work of separate stages and other log ically
grouped activities.
E. Identify work of separate floors and other logically
grouped activities.
F. Provide sub-schedules to define critical portions of the
entire schedule.
G. Indicate accumulated percentage of completion of each
item and total percentage of Work completed, as of the
first day of each month.
H. Submit separate schedule of submittal dates for shop
drawings, product data, and samples, including the Owner
furnished products and products identified under
allowances and dates reviewed submittals will be required
from the Architect. Reference section 01301
Submittals.
I. Indicate delivery dates for the Owner furnished products.
J. Coordinate content with Schedule of Values specified in
Section 01370.
1..4 REVISIONS TO SCHEDULES
A. Indicate progress of each activity to date of submittal,
and projected completion date of each activity.
B. Identify activities modified since previous submittal,
major changes in scope, and other identifiable changes.
1. Major changes in scope.
2. Activities modified since previous submission.
3. Revised projections of progress and completion.
4. other identifiable changes.
c. Provide a narrative report as needed to define:
1. Problem areas, anticipated delays and the impact on
the schedule.
2. Corrective action recommended and its effect.
3. The effect of changes on schedules of other prime
contractors.
PROGRESS SCHEDULES
01310 - 2
OS/20/91
1..5 SUBMITTALS
A. Submit initial schedules within (3) days after award of
Contract.
1. The Construction Manager will review schedules and
return review copy within ten (10) days after
receipt.
2. If required, re-submit within seven (7) days after
return of review copy.
3. Submit revised Progress Schedules with each
Application for Payment.
1..6 DISTRIBUTION
A. Distribute copies of the reviewed schedules to:
1. Job site file.
2. Subcontractors.
3. other concerned parties.
B. Instruct recipients to report promptly to the Contractor,
in writing, any problems anticipated by the projections
shown in the schedules.
Note~ It is not incumbent upon the Construction Manager
to notify the Trade Contractor when to begin, to
cease, or to resume work nor to give early notice
of faulty or defective work, nor in any way to
superintend so as to relieve the Trade Contractor
of responsibility or of any consequence of neglect
or carelessness.
**************
END OF SECTION 01310
OS/20/91
PROGRESS SCHEDULES
01310 - 3
SECTION 01370
SCHEDULE OF VALUES
PART 1 - GENERAL
1..1 SUMMARY
A. Section includes:
1. Schedule of Values allocated to the various
portions of the Work, submitted within three (3)
days after award of the Contract.
2. Upon request of the Construction Manager, support
the values with data which will substantiate their
correctness.
3. The Schedule of Values, unless objected to by the
Construction Manager, forms the basis for the
Contractor's Applications for Payment.
1..2 FORM AND CONTENT OF SCHEDULE OF VALUES
A. Type schedule on AlA G703 Form; the Contractor's standard
forms and automated printout will be considered by the
Construction Manager upon the Contractor's request.
Identify schedule with:
1. Title of Project and location.
2. The Architect and Construction Manager.
3. Name and Address of the Contractor.
4. Contract designation.
5. Date of submission.
B. List the installed value of the component parts of the
Work (broken down into labor and material and physical
location) in sufficient detail to serve as a basis for
computing values for progress paYments during
construction.
C. Follow the Specifications as the format for listing
component items.
1. Identify each line item with the number and title
of the respective major section of the
Specifications.
D. Itemize separate line item cost for each of the following
general cost items:
1. Mobilization.
2. Bonds, Insurance and Permits.
3. General Conditions spread over project duration on
monthly basis.
04/30/91
SCHEDULE OF VALUES
01370 - 1
4. Clean-up.
5. Submittals.
6. Safety.
E. For each major line item list sub-values of major
products or operations under the item.
2.
the various portions of the Work:
Include a directly proportional amount
Contractor's overhead and profit for each
For items on which progress payments
requested for stored materials, break
value into:
a. The cost of the materials, delivered and
unloaded, with taxes paid.
b. The total installed value.
Submit a subschedule for each separate stage of
work specified in section 00300.
of the
item.
will be
down the
F.
For
1.
3 .
G. The sum of values listed in the schedule shall equal the
total Contract Sum.
1..3 SUBSCHEDULE OF UNIT MATERIAL VALUES
A. Submit a subschedule of unit costs and quantities for:
1. Products on which progress payments will be
requested for stored products.
B. The form of submittal shall parallel that of the Schedule
of Values, with each item identified the same as the line
item in the Schedule of Values.
C. The unit quantity for bulk materials shall include an
allowance for normal waste.
D. Provide unit values for the materials as follows:
1. Cost of the material, delivered and unloaded at the
Site, with taxes paid.
2. Installation costs, including the Contractor's
overhead and profit.
E. The installed unit value multiplied by the quantity
listed shall equal the cost of that item in the Schedule
of Values.
1..4 REVIEW AND SUBMITTAL
A. After review by Construction Manager, revise and resubmit
schedule (and Schedule of Material Values) as required.
04/30/91
SCHEDULE OF VALUES
01370 - 2
B. Resubmit revised schedule in same manner.
*************
END OF SECTION 1370
04/30/91
SCHEDULE OF VALUES
01370 - 3
SECTION 01385
DAILY CONSTRUCTION REPORTS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Requirement for Daily Construction Reports by each
Trade Contractor.
2. Scheduled submission times for Daily Construction
Reports.
1..2 FORM AND CONTENT OF DAILY CONSTRUCTION REPORTS
A. Daily Construction Reports shall be submitted by each and
every Contractor performing work on the project. Forms
to be used will be furnished by the Construction Manager.
Items to be addressed on the Report are:
1. Title of Project
2. Name of Trade Contractor
3. Date and day of Report information. For example,
you performed work on Thursday, April 18, 1991, so
you would therefore use "Thursday, 4 / 18 / 91. " This
holds true even if you did not complete filling out
the Report until Friday, 4/19/91.
4. Contract designation.
5. Note any major Shipments received on that
particular day.
6. Note major equipment used that day.
7. Note manpower used, and designate what trades. For
example, if you were the mechanical contractor, you
would also list how many insulators, pipefitters,
etc. that you were also managing, even if they were
subcontractors. In addition, list the names of the
subcontractors that were on-site that day.
8. Note any deficiencies in your work, and corrective
actions taken to resolve the deficiencies.
9. Note any safety violations discovered, whether or
not caused by your forces.
10. Provide a full description of work performed that
day, and any problems or unusual conditions
discovered.
11. Report is to be signed by the al1thorized
representati ve of the contractor, and should the
signature not be legible, print the name of the
signer next to the signature.
11/21/91
DAILY CONSTRUCTION REPORTS
01385 - 1
1..3 SCHEDULE OF SUBMITTING DAILY REPORTS
A. Daily Reports are to be submitted at the designated
location described in the pre-construction meeting.
Contractors are to submit the original of their report,
and should keep a copy for their records. The
Construction Manager's photocopy ing faci 1 i ties are not to
be used in the reproduction for submission of the
reports.
B. Submit Daily Reports no later than 9:00am the day
following the day of the work described in that
particular report. No exceptions to this rule will be
accepted. Should contractor fail to comply with these
instructions, the contractor's payment application for
the following month will be held in abeyance until such
time the contractor properly- submits the delinquent
reports.
*************
END OF SECTION 1385
DAILY CONSTRUCTION REPORTS
01385 - 2
11/21/91
- -.,.-- '_'4 ...... _ ..--'-'-iO.__.:.~_._.,..,..".~ -..- "_..~___'_"'- _,..-. _~ __.. _'_. :_._
=
i\IONROE COUNTY CAPITAL Il\lPROVE,\lENT PROJECTS
CONTRACTOR'S DAILY REPORT
PROJ ECT:
DATE:
SHEET
OF
~~')-~~~~..~~r-
II!
~~..u
~ ".it .l11:\.>S"-e...~~ 'l'l'f:WWi~~--
CONTRACTOR:
~"..>S..~~~~~.:r=~
M..\JOR SH1PMENTS RECEIVED TODAY
CONTRACRO.:
::s:~~.,..~~~~~~
!\t~OR EQUIPMENT USED
~~~~.~~~~~g...:J"
.~~,-' --'-'-~,-~~~-
NUMBER OF PERSONNEL O~SITE
LlST SUBCONTRACTORS Ol\:SITE
OFC
C
C
C
C
C
C
SC SC
T
o
T
A
L
~~~-c,~~__"",...~~_...,
.".~~~~~J:
DEFICIEJ\CIES NOTED/CORRECrED; INSPECTIONS ~iADE; TESTS CONDUCTED:
QC REPRESEl\:TATIVE:
S:\FETY V]OLATIO~S NOTEDiCORRECTED:
-- ~---_.
FULL DESCRIPTION OF WORK PERFOR~1ED BY AREA; INCLUDE ANY PROBLB1S:
--~----
.-----
SITE R.EPRESE';T.h.TIVE:
=.
.h. I J ACH ;>"-1) ::.:1EET1Fl\t:.J:1Jt:1J
2~D SHEET
r==---~---~~=~- CO~;~ACTO;S DA~;~EPORT -----~- SHE;;~_~~:~~;:~-~_:=c~~l
\~~~"'<...._...."'-.& R .__~--,..,.~~ ---------.------------
I PROJECT: WORK DAY:
~~-~~------ ------
CO'.;TRACT ~O.: DA TE:
,.~~~.~Ii\'t(~~...~ "-"'ilJii.~~~~:;'~
DESCR1PTJON OF WORK PERFORMED Liq a(livilic~ ~lar1l'd, 8Cli\.ilic~ cumrlclc<J, d('la)'~, rC~l~ons for dcl:j)'s, and
r(,.J~ons for po"iblc future dc\3ys.
~1:;iii4:~~..JtI'L...- I ...;;u.......&::l'''''''~--- -1....t..........r.'""-"'-ffr~~.4i"t.~~=__..~~~~.......--.."'.
--
--
--
.--
--
--
---------
--
--
-~
--
--
-~
.----------.----
-
--------
-----
L
-----~
=====_=~==_c=
SECTION 01395
DOCUMENT CLARIFICATION REQUESTS (DCR)
PART 1 - GENERAL
1.1 SUMMARY
A. Section includes:
1. Notification of Construction Manager in the event
errors, field conflicts, and omissions are found in
the Contract Documents, or clarifications are
necessary.
2. utilization of DCR form.
B. Related Sections:
1. General Conditions Article 2.3
2. General Conditions Article 8.3.2
3. General Conditions Article 12.3
1.2 FORM AND CONTENT OF DOCUMENT CLARIFICATION REPORTS
A. All errors, field conflicts, and omissions in the
Contract Documents shall be brought to the attention of
the Construction Manager immediately. If clarifications
are necessary, the request is to be conveyed to the CM.
The DCR is a tool established to provide expedient
clarifications of contract drawings, specifications or
field conflicts. It is not meant to be a substitute for
good communication.
B. The DCR is not meant for formal notification of extra
work. Reference General Conditions paragraph 8.3.2 and
12.3, when formal correspondence is required for formal
notif ication of time extensions, and for cost change
notifications.
C. The contractor should propose a solution, and enter on
the form in sufficient detail necessary for the A/E or CM
to confirm the contractor's proposed solution.
D. The contractor is also required to mention all other
trade work which is affected by the problem, and all
trade work which will be affected by the proposed
solution.
11/21/91
DOCUMENT CLARIFICATION REQUESTS
01395 - 1
1.3 UTILIZATION OF DCR FORM
A. The CM will make available the DCR forms for the
contractors use. Attached is a copy of the DCR form, and
the instruction sheet.
*************
END OF SECTION 1395
11/21/91
DOCUMENT CLARIFICATION REQUESTS
01395 - 2
..<< -~-. .,--.-......- --...._,--- -...
DOCUMENT CL<\RIFICATlON REQUEST No.
From: To: Morrison- Knudse n/G errits Contract )\0.
P. O. Box 5283
Key West, FL 33045 Receipt
(305) 292-7S45 Lqgged:
Problem By: DwglSpec No./Revision/Detail/Sect No.
AlE Project No.
Civil Siructural Architectural Se.curity PLB HVAC Electrical S~.
Subject: .
~'W -- - .it.
Problem & suggested solution: ..,
-
-
--
I \IK'G Rc\icw:
Solution:
--
Solulion bv: I Dale: I MI</G: I Dale:
')CROl
, DOCUMU.' UARJnCA no' llQl'IST 1'0. (5)
From: r M~KJ)IXbCn.'Vemtl (.or.ullnf'o. C~'
._@-- ,. o. >> ~1A.\ --
).;.("'0 ~ot. FL ))04~ ReceIpt CD
(~)~:.m~ Lou'.
prrt-km By: 12. ' Dwa.'Sfu p.;vJ1l.....R~lail.&>n ,,"u
A'l: P'n'f<<1 p...... \10' ,"l' __
.~ eMl s.\rvo.r~ AJo..Ie('\W" So.~"" ,LJj HVAC f.jox'lr.cal ''''
....,.., i'" )
I"wbkrr...lI.I"d-....:!~.~
-_..~
:'1 .-
--
--.- -
---
.----- -
I "H:<. !<.....--- ~'
""~~ --
-~--
~ ----
.-
.-
----
~ ('\5 1_ i1J,' 119& (11- ltlfl :,.~
=
~. By Contractor:
1. From: The OCR ~ill al~ays be froffi the Fri~e contractor.
subcontractors to the prire contrbctor Shlloll submit OCR's
through their prime contractor.
2.
Problem By: This
contractor, or
representative,
representative..
can be the subcontractor, or the prime
the establ ished prime contractor
or the established subcontractor
3. Contract No.: This is the approved contract, contract
nun-iller.
4. Drli....ing No.: Here insert as Dluch infonr.ation as possible
to d€:scribe the locatior. in the contract documents of the
particular problem you are asking clarification. Include
revision level of drawings, and date. Include detail
numbers, include section nun~ers, include specification
section nurr~ers, paragraph locations, all as applicable.
5. civil, structural, etC.: Here note the particular
division of ~ork the DC~ app~ies to.
6. subject: Here insert brief, clear, concise caption
subject, ,,'rdch is representative of problt=.m area.
7. Problem' suggested Solution: Describe in as much detail
as necessary, t.he problem to~which clarification 1s
needed. If additional space is needed, add extra sheets
to back, and reference attachments in this area no. 7.
Dra.. sketches if necessary. Make photocopy of particular
dra~inq detail and attach if necessary.
B. By Morrison-Knudsen/Gerrits:
8. DCR No.: Nurriliers ~ill be assigned bS fol1o~s:
xx-
Project
xxx-
Contractor }oIo.
XXX
Seq..Jential No.
For instance, the first OCR from t.he contr~ctor of
Contract No. 001 on the NeY Detention Facility, ~ould be:
KJ-{'01-00l
~s another exa~ple: The seventh consecutive OCR logged
on the New Detention Facility, \"as rece i ved fro. the
contractor of Contract No. 005, ~ould be:
KJ-005-007
9. ~eceipt Ifl9ged: This will be the date received by the
eM from the cont.ractor, and ....ill s~rve as the reference
date.
10. AlE Project No.: The AlE's project nu:::ber ,.'ill be
insErted here, ~here and ~ht=.n applicable.
11. Y.K/G Revie...': Tt.is ...:ill bE the signature or initials of
the Constructien ~~n~qer, upon revie.. of t.he prcbleJt,
kith the date of ~ign-off.
12. MK/G ~evie*: ~tis _ill be the signature cr initials of
the Construction Manager, upon revie.... of the solution.
13. Date: This ...dll be the date of ~K/G review and sign-
oft.
c. By Architect/Engineer:
14. Solutic~: The hiE .i11 here inSErt the solution to the
probler., or o;)s""er lr. some ot.her fashion the
clllriflcation being requested. The AlE roay herein
confint the 'contract.or's fToposed solution.
15. Solution By: The entity providing the solution is to
sign here. This rr.ay be the Construction Manager ....hen
particular c1arifications are being requested that can
be ansl,."ered ty the CY.. Othendse, it ....il1 be the 1-./E
representative.
16. Date: This )o.'i11 be the date of sign-off, or ans...:ering
the DCR by the AlE.
D. Part-By-Part oistri~ution of ~-part OCR ror~:
a. "'''hen the co.Jtractor sub;:its DCR, he .....ill retain gQ1..denrod
copy.
b. ~"hen received by the contractor, CM ""ill retain fiD.ls.
copy.
c. The DCR then is sub~itted to the ^/E. Once ans.ered, the
AlE returns to eM, but retains Can~ copy.
d. eM revie~s a~s~er, and sends Green copy back to
contractor. Cl'. ",'ill retain original !5.hite copy for
office files, and !Uue copy will go to the job-site.
SECTION 01410
TESTING LABORATORY SERVICES
PART 1 - GENERAL
1..1 SUMMARY
A. Section includes:
1. Selection and payment
2. The Contractor submittals
3. Testing laboratory responsibilities
4. Testing laboratory reports
5. Limits on testing laboratory authority
6. The Contractor responsibilities
7. Schedule of inspections and tests
B.
1.
2 .
3 .
section 00750 - GENERAL CONDITIONS
section 01700 - CONTRACT CLOSEOUT
Individual Specification sections: inspections and
tests required, and standards for testing.
1..2 REFERENCES
A.
ASTM D-3740 -
Practice for Evaluation of Agencies
in Testing and/or Inspection of Soil
and Rock as Used in Engineering
Design and Construction.
B.
ASTM E-329 -
Recommended Practice for Inspection
and Testing Agencies for Concrete,
Steel, and Bituminous Materials as
used in Construction.
1..3 SELECTION AND PAYMENT
A. The Owner will employ and pay for services of an
independent testing laboratory to perform specified
inspection and testing where so indicated to be performed
by the Owner in technical Specification Sections.
B. Employment of testing laboratory shall in no way relieve
the Contractor of obI igation to perform the Work in
accordance with requirements of the Contract Documents.
11/21/91
TESTING LABORATORY SERVICES
01410 - 1
1..4 QUALITY ASSURANCE
A. Comply with requirements of ASTM E-329 and ASTM D-3740.
B. Testing laboratory: authorized to operate in the state
of Florida.
C. Testing laboratory staff: maintain a full time
registered Engineer on staff to review services.
D. Testing Equipment: calibrated at reasonable intervals
with devices of an accuracy traceable to either National
Bureau of standards (NBS) ~tandards or accepted values of
natural physical constants.
E. Meet "Recommended Requirements for Independent Laboratory
Qualification", published by American council of
Independent Laboratories.
1..5 TESTING LABORATORY RESPONSIBILITIES
A. Test samples of mixes.
B. Provide qualified personnel at the site. Cooperate with
the Architect, Construction Manager and the Contractor in
performance of services.
C. Perform specified inspection, sampling, and testing of
Products in accordance with specified standards.
D. Ascertain compliance of materials and mixes with
requirements of the Contract Documents.
E. Promptly notify the Construction Manager and the
contractor of observed irregularities or non-conformance
of the Work or products.
F. Perform additional inspections and tests required by the
A/E and Construction Manager.
1..7 TESTING LABORATORY REPORTS
A. After each inspection and test, promptly submit three
copies of testing laboratory report to the Construction
Manager.
B. Include:
1. Date issued
2. Project title and number
3. Name of inspector
4. Date and time of sampling or inspection
TESTING LABORATORY SERVICES
01410 - 2
11/21/91
5. Identif ication of product and Specifications
section
6. Location in the Project
7. Type of inspection or test
8. Date of test
9. Results of test
10. Conformance with the Contract Documents
C. When requested by the Construction Manager or A/E,
provide interpretation of test results.
1..8 LIMITS ON TESTING LABORATORY AUTHORITY
A. The testing laboratory may not release, revoke, alter, or
enlarge on requirements of the Contract Documents.
B. The testing laboratory may not approve or accept any
portion of the Work.
C. The testing laboratory may not assume any duties of the
Contractor.
D. The testing laboratory has no author i ty to stop the Work.
1..9 THE CONTRACTOR RESPONSIBILITIES
A.
B.
C.
D.
E.
1. .10
A.
Deliver to the testing laboratory at designated location,
adequate samples of materials proposed to be used which
require testing, along with proposed mix designs.
Cooperate with testing laboratory personnel, and provide
access to the Work and to the manufacturer's facilities.
Provide incidental labor and facilities to provide access
to the Work to be tested, to obtain and handle samples at
the site or at source of products to be tested, to
facilitate tests and inspections, storage and curing of
test samples.
Notify the Construction Manager and the testing
laboratory 48 hours prior to expected time for operations
requiring inspection and testing services.
Employ services of a separate qualified testing
laboratory and pay for additional samples and tests which
are beyond the specified requirements.
RETEST RESPONSIBILITY
Where the results of required inspections, tests, or
similar services prove unsatisfactory and do not indicate
11/21/91
01410 - 3
TESTING LABORATORY SERVICES
compliance with the requirements of the Contract
Documents, the retests shall be the responsibility of the
Contractor regardless of whether the original test was
the Contractor's responsibility.
B. Retesting of the work revised or replaced by the
Contractor is the Contractor's responsibility where
required tests were performed on original work. Costs
and fees for retesting shall be paid by the Contractor.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01410
11/21/91
TESTING LABORATORY SERVICES
01410 - 4
-.. --"'~--.T--'.'--.-'.-----~'-"-"'---.'- -"';:.". -'"--.--.' ,.., -,."
SECTION 01510
TEMPORARY UTILITIES
PART 1 - GENERAL
1.1
SUMMARY
A.
section includes:
1. Temporary utilities required for construction.
PART 2 - PRODUCTS
2.1
MATERIALS-- GENERAL
A.
Materials shall be new, adequate in capacity for the
required usage, not create unsafe conditions, not violate
requirements of applicable codes and standards, and
comply with NEe Art. 305 - Temporary Wiring.
2.2
TEMPORARY ELECTRICITY
A.
The Temporary Power Contractor shall furnish, install and
maintain, temporary electric. power service for
construction needs throughout the construction period and
shall remove such service on completion of the work.
1. Primary temporary electrical underground feeder
will be provided and installed by temporary power
contractor under Bid Group 1, per drawing 1510- TP.
2. At Front Gate transformer location, the temporary
power contractor under Bid Group 1 has installed a
meter, mast, and main breaker panel Nema 3R, per
Detail "A" attached. The final location of each
panel shall be approved by the Construction
Manager.
3. Distribution panels have been provided by the Bid
Group 1 temporary power contractor per drawing 1510
- TP, and Details A, B, C and D, and as follows:
a. Front gate area serving the construction
manager trailer, guard shack and area lights.
(20 ckt. min.)
4.
Power centers for miscellaneous tools and
used in the Work will be provided by the
1 Temporary Power Contractor as follows:
a. distribution boxes with minimum
equipment
Bid Group
of four
11/21/91
TEMPORARY UTILITIES
01510 - 1
double-duplex 15 Amp, 120-Volt grounded
outlets, with GFCI Protection for personnel.
See Detail "B".
b. located so that power is available at any
point of use with not more than 100 ft. power
cords.
c. minimum: one power center on each floor.
d. circuit-breaker protection for each outlet.
e. One panel each for Building Areas
A,B,C,D,E,F,K,L,M,N,O,P and Q.
5. The capacity of each power center in 4. above~shall
be 120/240 volts single phase, minimum 50 Amps.
6. The Trade Contractors shall notify the Temporary
Power Contractor when unusually heavy loads, such
as for welding and other equipment with special
power requirements, will be connected so that the
Bid Group 3 Temporary Power Contractor can notify
the power company.
7. Any Trade Contractor requiring service of capacity
or characteristics other than that specified shall
arrange and pay for the additional service.
8.
The Temporary
install, and
required to
including the
Power Contractor shall furnish,
maintain all equipment and wiring
distribute the power, up to and
power services.
9. The Temporary Power Contractor shall pay all costs
of installation, maintenance, and removal of
temporary services.
10. The Construction Manager will pay the costs of
power needed, including deposits and fees
associated with city Electric except as outlined in
item 13 below
11. Materials shall be new, and r:mst be adequate in
capacity for required usage, and must not violate
the requirements of applicable codes and standards.
Materials used for temporary service shall not be
reused in the permanent system.
12. The Temporary Power Contractor shall comply with
all applicable requirements specified in National
Electr ic Code Art. 305 when insta II ing the
temporary electr ic power service, sha II rna inta in
the system to provide continuous service and shall
modify and extend the service as the progress of
11/21/91
TEMPORARY UTILITIES
01510 - 2
the Work requires.
13. wiring for Trade Contractor field offices and sheds
shall be installed by the Temporary Po.....er
Contractor and paid for by the Trade Contractor
requiring the service.
14. The Temporary Power Contractor shall completely
remove all temporary materials and equipment at
Project Completion. Underground lines may be
disconnected and abandoned in place with approval
of the Construction Manager. The temporary shed as
shown in Detail "e" shall remain the property of
Benson Electric.
15. Feeders to distribution panels from distribution
shed shall be 400 feet maximum length, with two hot
legs and one neutral of the same size as per NEC
Table 310-16 and Article 210-19a FPN.
16. Circuits to Power Centers from Distribution Panels
shall be installed per NEC Art. 305.
17. Feeders and Branch Circuits in 15. and 16. above
shall be protected from physical damage.
18. See Detail "C" for temporary power shed
requirements. This shall remain the property of
Benson Electric.
2.3
TEMPORARY SITE LIGHTING
The Temporary Power Contractor shall install and maintain area
lights on the meter poles as shown in Detail "A", 2 lights total.
Temporary Lighting power will be fed from the panels and power
centers covered under Section 2.2 TEMPORARY ELECTRICITY.
2.4
TEMPORARY TELEPHONE SERVICE
A.
Each Trade Contractor shall be responsible for arranging
with the local telephone service company to provide
telephone service at the construction site for the use of
his personnel and employees. The Trade Contractor shall
pay all costs for installation, maintenance, removal and
service charges for such service. The Construction
Manager will not act as an answering service for Trade
Contractor's personnel and employees, and Trade
Contractor's personnel and employees will not be
permitted to utilize the Construction Manager's phones
except in cases of an emergency.
11/21/91
TL~PORARY UTILITIES
01510 - 3
2.5
CONTINUING TEMPORARY ELECTRICITY MAINTENANCE
At the option of the Owner, the Temporary Power
Contractor shall provide a minimum of 1 person full time
for the duration of the construction, estimated to be 18
months. This person will maintain, relocate and repair
the temporary utilities covered under Articles 2.2, 2.3
and 2.4. The bid for this work shall be based on an
hourly rate for licensed electrician.
2.6 TEMPORARY LIGHTING
A. The Electrical Trade Contractor will be responsible for
the installation of the permanent electrical system and
shall also furnish, install and maintain temporary
lighting for construction needs throughout the
construction period and shall remove such temporary
lighting on completion of the Work.
1. Temporary artificial lighting shall be provided in
enclosed Work areas and all other work areas when
natural lighting does not meet minimum
requirements. Temporary artif icial lighting in
Work areas shall produce uniform illumination of
20-foot candles.
2. Any Trade Contractor requiring temporary lighting
in addition to that specified, including lighting
for security, temporary offices, storage, shops and
other construction buildings, shall arrange and pay
for such additional temporary lighting.
3. Power requirements and source will be coordinated
with Article 2.2 above.
4. The Electrical Contractor shall comply with the
applicable requirements specified in sections of
Division 16 - Electrical. Materials shall be new,
and must be adequate for required usage, and must
not violate requirements of applicable codes and
standards.
5. Receptacles, fixtures and controls shall be
standard products, meeting UL standards.
6. The Electrical Contractor shall comply with all
applicable requirements specified in sections of
Division 16 Electrical, when installing the
temporary lighting, shall locate fixtures to
provide full illumination of required areas, shall
maintain the system to provide continuous service,
and shall modify and extend the service as the
progress of the Work requires.
7. The Electrical Contractor shall completely remove
temporary materials and equipment at Project
Completion, except for high voltage underground.
11/21/91
TEMPORARY UTILITIES
01510 - 4
2.7
A.
B.
C.
D.
E.
2.8
TEMPORARY WATER
site Plumbing Contractor will arrange
service company, to provide water for
purposes.
with utility
construction
site Plumbing Contractor will provide temporary water at
locations of two (2) fire hydrants on fire. water loop as
directed by Construction Manager; fire water loop will
be charged to provide construction water.
The Construction Manager will pay for water used for
temporary construction purposes.
Building Plumbing Contractor will maintain temporary
water systems, and will remove temporary water
appurtenances at completion of project.
Each Trade Contractor shall be responsible for providing
any additional water (if needed) for construction
purposes. In addition, each Trade Contractor is
responsible for providing potable drinking water for his
personnel and employees, as well as suitable containers,
ice and salt tablets in sufficient quantity to meet the
needs of his labor force.
TEMPORARY HEATING, COOLING AND VENTILATING
Each Trade Contractor shall be responsible for providing, and
operating and maintaining temporary heating, cooling and
ventilating, as required, to maintain adequate environmental
conditions to facilitate the progress of his Work; to meet
minimum condition for the installation of materials; and to
protect materials and finishes from damage due to temperature
or humidity. Each Trade Contractor, subject to the approval
and direction of the Construction Manager, shall:
1. Provide adequate forced ventilation of enclosed
areas for curing of installed materials, to
disperse humidity, and to prevent hazardous
accumulations of dust, fumes, vapors, or gases.
2. If portable heaters are required, utilize only UL
approved units complete with controls.
3. Insure that all safety devices specified for
operation of equipment are functioning properly.
4. Pay all costs of providing, operating, maintaining,
and removing such temporary heating, cooling, and
ventilating equipment as may be required.
11/21/91
01510 - 5
TEMPORARY UTILITIES
The foregoing obligations of the Trade Contractor are in
addition to his obligations under Article 10 of the General
Conditions.
2.9
A.
B.
2.10
TEMPORARY SANITARY FACILITIES
The Owner will provide sanitary facilities in compliance
with laws and regulations.
The Owner will service, clean and maintain facilities and
enclosures.
TEMPORARY FIRE PROTECTION
The Trade Contractor responsible for the installation of the
permanent fire protection system shall furnish, install and
maintain temporary fire protection equipment, materials,
supplies and service within the buildings throughout the
construction period in accordance with the requirements of all
applicable codes and standards. Each floor shall have a
temporary fire protection system. Each Trade Contractor will
be responsible for fire protection required for his own work.
2.11
A.
B.
REMOVAL
Completely remove temporary materials and equipment when
their use is no longer required.
Clean and repair damage caused by temporary installations
or use of temporary facilities.
c.
Restore permanent facilities used for temporary services
to specified condition.
1. Prior to final painting, the
responsible for the permanent
system, shall remove temporary
Trade Contractor
building lighting
lamps and install
new lamps.
2 .
Pr ior to final inspection, the Trade Contractor
responsible for the building mechanical system
shall replace filters and worn or consumed parts of
mechanical equipment.
***************
END OF SECTION 01510
11/21/91
TEMPORARY UTILITIES
01510 - 6
SECTION 01520
CONSTRUCTION AIDS
PART 1 - GENERAL
1.1 SUl1MARY
A. section includes:
1. Construction aids
2. Temporary enclosures
1.2 REQUIREMENTS OF REGULATORY AGENCIES
B.
Comply with Federal,
regulations.
state and local codes and
PART 2 - PRODUCTS
2..1 MATERIALS - GENERAL
A. Materials may be new or used, suitable for the intended
use and shall not violate requirements of applicable
codes and standards.
2..2 CONSTRUCTION AIDS
A. Each Trade Contractor shall be responsible for
furnishing, installing, maintaining, and removing on
completion of the Work all scaffolds, staging, ladders,
stairs, ramps, runways, platforms, railings, chutes, and
other such facilities and equipment required by his
personnel to insure their safety and faci li tate the
execution of the Work.
1. Each Trade Contractor shall comply with all
Federal, State and local codes, laws and
regulations governing such construction aids.
2. Each Trade Contractor shall relocate such
construction aids as required by the progress of
construction, by storage or work requirements, and
to accommodate the legitimate requirements of the
Owner or Construction Manager or other separate
contractors employed at the site.
3. Each Trade Contractor shall completely remove
temporary scaffolds, access, platforms, and other
such materials, facilities, and equipment, at the
completion of the Work or when construction needs
can be met by the use of the permanent
construction, provided the Construction Manager has
04/09/91
CONSTRUCTION AIDS
01520 - 1
approved and authorized such use. Each Trade
Contractor shall clean up and shall repair any
damage caused by the installation or by the use of
such temporary construction aids. Each Trade
Contractor shall restore any permanent facilities
used for temporary purposes to their specif ied
condition.
The foregoing obligations of the Trade Contractor are in
addition to his obligations under Article 10 of the General
Conditions.
2..3 TEMPORARY ENCLOSURES
A. The Trade Contractor responsible for installing the
permanent closure in an opening in an exterior wall shall
be responsible for installing, maintaining, and removing,
as the Work progresses, a temporary weather-tight
enclosure for that opening as necessary to provide
acceptable working conditions, to provide weather
protection for interior materials, to allow for effective
temporary heating, and to prevent entry of unauthorized
persons.
1. Each Trade Contractor shall install such temporary
enclosures as soon as is practical after the
opening is constructed or as directed by the
Construction Manager.
2. Temporary enclosures shall be removable as
necessary for the Work and for handling of
materials.
3. Temporary enclosures shall be completely removed
when construction needs can be met by the use of
the permanent closures.
4. The Trade Contractor responsible for providing,
maintaining, and removing the temporary enclosure
shall clean and shall repair any damage caused by
the installation of such enclosure.
5. Each Trade Contractor shall remain responsible for
insuring that his work, material, equipment,
supplies, tools, machinery, and construction
equipment is adequately protected from damage or
theft and shall provide, maintain and remove such
additional temporary enclosures as may be deemed
necessary.
The foregoing obligations of the Trade Contractor are in addition
to his obligations under Article 10 of the General Conditions.
****************
END OF SECTION 01520
04/09/91
CONSTRUCTION AIDS
01520 - 2
SECTION 01550
ACCESS ROADS AND PARKING AREAS
A. Each Trade Contractor shall be responsible for installing
and maintaining, until the completion of his Work any
temporary access roads or parking facilities required by
his Work, other than that which has been provided by the
Owner.
B. Any Trade Contractor excavating across an access road or
parking area shall backfill and compact his excavation
and resurface the road or parking area to match the
existing surface. The Trade Contractor shall comply with
all applicable Specifications when so doing.
*********************
END OF SECTION 01550
04/09/91
ACCESS ROADS AND PARKING AREAS
01550 - 1
SECTION 01560
TEMPORARY CONTROLS
PART 1 - GENERAL
1..1 SUMMARY
A. Section Includes:
1. Water control
2. Dust control
3. Erosion and sediment control
4. Pollution control
B. Related sections:
1. SCOPES OF WORK
1..2 WATER CONTROL
A. site Grading Contractor shall grade site to drain.
B.
Protect site from puddling or running water.
water barriers to protect site from soil
Maintain excavations free of water. Provide,
and maintain pumping equipment.
Provide
erosion.
operate,
1..3 DUST CONTROL
A. Execute the Work by methods to minimize raising dust from
construction operations.
B. Provide positive means to prevent airborne dust from
dispersing into atmosphere.
1..4 EROSION AND SEDIMENT CONTROL
A. Plan and execute construction by methods to control
surface drainage from cuts and fills, from borrow and
waste disposal areas. Prevent erosion and sedimentation.
B. Minimize amount of bare soil exposed at one time.
C. Provide temporary Deasures such as berms, dikes, and
drains, to prevent water flow.
D. Construct fill and waste areas by selective placement to
avoid erosive surface silts or clays.
E. Inspect earthwork to detect evidence of erosion and
OS/20/91
TEMPORARY CONTROLS
01560 - 1
sedimentation; promptly apply corrective measures.
1..5 POLLUTION CONTROL
A. Provide methods, means, and facilities to prevent
contamination of soil, water, and atmosphere from
discharge of noxious, toxic substances, and pollutants
produced by construction operations.
Two (2) 30 c.y. trash containers will be provided by the Owner.
The Masonry Contractor shall be responsible to -provide his own
trash dumpsters for masonry waste disposal. Tr~shcontainers shall
be located in trash accumulation areas designated by the
Construction Manager. Each Contractor each day shall collect and
deposit in the containers, all rubbish, wast~ materials, debris,
and other trash from his operations, (excluding masonry), including
any trash generated by his employees during lunch periods or coffee
breaks. Shipping dunnage is to be removed by the receiving
contractor. Paper, boxes and bulk packaging shall be folded or cut
into reasonable sizes and shapes and confined to prevent lost of
trash container volume or wind relocation.
***************
END OF SECTION 01560
OS/20/91
TEMPORARY CONTROLS
01560 - 2
- .~- -<olr--"~,~' 'f't.,~~--..-..~---.-._,~-",.~-o--.'[..:..~-~.......", ~ ~_'_'."__'_'.. _ ___'__."'. ~
SECTION 01580
PROJECT IDENTIFICATION AND SIGNS
Trade Contractors informational signs on the site shall be limited
to those designating their tenporary field offices and sheds. All
such informational signs shall be subject to approval by the
Construction Manager.
*************************
END OF SECTION 01580
11/21/91
PROJECT IDENTIFICATION AND SIGNS
01580 - 1
SECTION 01590
FIELD OFFICES AND SHEDS
A. The Trade Contractor, if he~_ deems it necessary I may
furnish, install, and maintain a temporary field office
for his use and the use of his employees during the
construction period.
B. The Trade Contractor shall furnish, install, and maintain
temporary storage and work sheds to adequately protect
his work, materials, equipment, supplies, tools,
machinery, and construction equipment from damage and
theft.
C. The Trade Contractor shall arrange his field office and
sheds so as not to interfere with the construction. The
locations of field offices and sheds shall be coordinated
with the Construction Manager. The type, size and
location of field offices and sheds is subject to
approval by the Construction Manager.
D. The Trade Contractor shall arrange and pay for temporary
electricity and telephone service for his field office
and sheds, if he should require such services.
E. The Trade Contractor shall relocate his field office and
sheds as directed by the Construction Manager, at no
additional cost to the Owner or Construction Manager.
F. The Trade Contractor shall completely remove his field
off ice and sheds on completion of the Work or when
directed by the Construction Manager. The Trade
Contractor shall remove all debris and rubbish and shall
place the area in a clean and orderly condition.
G. The Construction Manager as soon as reasonably possible
will establish a field office on the site and will
maintain such an office during the entire construction
period. The Construction Manager's field office will not
be used as field office by the Trade Contractor or his
employees.
**************
END OF SECTION 01590
04/09/91
FIELD OFFICES AND SHEDS
01590 - 1
SECTION 01595
CONSTRUCTION CLEANING
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Cleaning during progress of work.
1..2 DISPOSAL REQUIREMENTS
: ~.
A. Conduct cleaning and disposal operations to comply with
codes, ordinances, regulations, and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on
Project site.
2. Do not dispose of volatile wastes such as mineral
spirits, oil or paint thinner in storm or sanitary
drains.
PART 2 - PRODUCTS
2..1 MATERIALS
A. Use only those cleaning materials which will not create
hazards to health or property and which will not damage
surfaces.
B. Use only those cleaning materials and methods recommended
by manufacturer of the surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by
cleaning material manufacturer.
D. Sweeping compounds used in cleaning operations shall
leave no residue on concrete floor surfaces that may
affect installation of finish flooring materials.
PART 3 - EXECUTION
3..1 DL~ING CONSTRUCTION
A. Execute cleaning to keep the Work, the site and adjacent
properties free from accumulations of waste materials,
rubbish and windblown debris, resulting from construction
operations.
B. Provide on-site containers for the collection of waste
04/09/91
CONSTRUCTION CLEANING
01595 - 1
materials, debris, and rubbish.
C. Dispose of waste materials, debris and rubbish off the
site.
3..2 DUST CONTROL
A. Clean interior spaces prior to the start of the finish
painting and continue cleaning on an as-needed basis
until painting is finished.
B. Schedule operations so that dust and other contaminants
resulting from cleaning process will not fall on wet or
newly-coated surfaces.
C. Handle materials in a controlled manner with as little
handling as possible; do not drop or throw materials
form heights.
************
END OF SECTION 01595
04/09/91
CONSTRUCTION CLEANING
01595 - 2
SECTION 01600
MATERIAL AND EQUIPMENT
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1 . Products
2. Transportation and handling
3. storage and protection
4. Security
1..2 PRODUCTS
A. Products: means new material, machinery, components,
equipment, fixtures, and systems forming the Work. Does
not include machinery and equipment used for preparation,
fabrication, conveying and erection of the Work.
Products may also include existing materials or
components required for reuse.
B. Do not use materials and equipment removed from existing
premises, except as specifically permitted by the
Contract Documents.
C.
Provide interchangeable components
manufacturer, for similar components.
of
the
same
1..3 TRANSPORTATION AND HANDLING
A. The Trade Contractor shall be responsible for the
transportation of all materials and equipment furnished
under this contract. The Trade Contractor shall also be
responsible for loading, receiving and off-loading at the
site all material and equipment installed un der this
Contract, whether furnished by the Trade Contractor or
the Owner. Unless otherwise provided, the Construction
Manager will not accept delivery on behalf of the Trade
Contractor for his materials and equipment. The Trade
Contractor shall be responsible for coordinating the
installation within the buildings of equipment that is
too large to pass through finished openings.
B. Transport and handle products in accordance with
manufacturer's instructions.
C. Promptly inspect shipments to assure that products comply
04/09/91
MATERIAL AND EQUIPMENT
01600 - 1
with requirements, quantities are correct, and products
are undamaged.
D. Provide equipment and personnel to handle products by
methods to prevent soiling, disfigurement, or damage.
1..4 STORAGE AND PROTECTION
The Trade Contractor shall be responsible for the proper
storage of all materials, supplies, and equipment to be
installed under this Contract. Materials stored on site but
not adequately protected will not be included in estimates for
payment. Except for materials stored ~lthin designated and
approved storage sheds, vans, or .1:railers, the Trade
Contractor shall not bring onto nor store in any manner at the
site any materials and equipment which will not be
incorporated into the permanent Work within seven (7) days
from the delivery date. The Trade Contractor shall be
responsible for arranging and paying for the use of property
off the site for storage of materials and equipment as may be
required.
1..5 SECURITY
A. Each Trade Contractor shall be totally responsible for
the security of his work, materials, equipment, supplies,
tools, machinery, and construction equipment.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
*************
END OF SECTION 01600
04/09/91
MATERIAL fu~D EQUIPMENT
01600 - 2
SECTION 01630
POST-BID SUBSTITUTIONS
PART 1 - GENERAL
1.1 SUMMARY
A.
section includes:
1. Post-bid substitutions
1.2 SUBSTITUTIONS
A. Base Bid shall be in accordance with the Contract
Documents.
B.
After the end of the bidding
requests will be considered only
1. Product unavailability
2. Other conditions beyond
Contractor.
period, substitution
in the case of:
the control of the
C. Submit a separate request for each substitution. Support
each request with the following information:
1. Complete data substantiating compliance of proposed
substitution with requirements stated in Contract
Documents:
a. Product identification, including
manufacturer's name and address.
b. Manufacturer's literature, identifying:
1) Product description.
2) Reference standards.
3) Performance and test data.
c. samples, as applicable.
d. Name and address of similar projects on which
product has been used and date of each
installation.
2. Itemized compar ison of the proposed substitution
with product specified, listing significant
variations.
3. Data relating to changes in construction schedule.
4. Effects of substitution on separate contracts.
5. List of changes required in other work or products.
6. Accurate cost data comparing proposed substitution
with product specified.
a. Amount of net change to Contract Sum.
7. Designation of required license fees or royalties.
8. Designation of availability of maintenance
services, sources of replacement materials.
04/09/91
POST-BID SUBSTITUTIONS
01630 - 1
D. Substitutions will not be considered for acceptance when:
1. A substitution is indicated or implied on shop
drawings or product data submittals without a
formal request from Bidder.
2. Acceptance will require substantial revision of
Contract Documents.
3. In judgement of Architect or Construction Manager,
the substitution request does not include adequate
information necessary for a complete evaluation.
4. Requested directly by a subcontractor or supplier.
E. Do not order or install substitute products without
written acceptance of Construction Manager.
F. Architect will determine acceptability of proposed
substitutions.
G. No verbal or written approvals other than by Change Order
will be valid.
1..3 CONTRACTOR'S REPRESENTATION
A. In making formal request for substitution the Contractor
represents that:
1. The proposed product has been investigated and it
has been determined that it is equivalent to or
superior in all respects to the product specified.
2. The same warranties or bonds will be provided for
the substitute product as for the product
specified.
3. Coordination and installation of the accepted
substitution into the Work will be accomplished and
changes as may be required for the Work to be
complete will be accomplished.
4. Claims for additional costs caused by substitution
which may subsequently become apparent will be
waived by the Contractor.
5. Complete cost data is attached and includes related
costs under the Contract, but not:
a. Costs under separate contracts.
b. Architect's costs for redesign or revision of
Contract Documents.
1..4 POST-BID SUBSTITUTION FORM
A. The form is attached to this section.
B. Substitutions will be considered only when the attached
form is completed and included with the submittal with
back-up data.
04/09/91
POST-BID SUBSTITUTIONS
01630 - 2
-.-. --- '~.' "". --~-~'>'-"''---~.''''r''V-,"".',,",,"---'.''.'-..-~~-~>.'''':r'~ 'f:<-'--:--,' ~',..~- -"'-- '~
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
04/09/91
POST-BID SUBSTITUTIONS
01630 - 3
TO: Project Architect
HANSEN LIND MEYER INC.
c/o Morrison-Knudsen/Gerrits
P.O. Box 5283 5090 Jr. College Road, Key West, Fl. 33040
(305)292-7845 FAX (305)292-9697
We hereby submit for your consideration the following product instL~d c
the specified item for the above project:
DRAWING NO.
DRAWING NAME
SPEC. SEC.
SPEC. NAME
PARAGRAPH
SPECIFIED ITEM
Proposed Substitution:
Attach complete information on changes to Drawings and/or Specificatio~
which proposed substitution will require for its proper installation.
Submit with request necessary samples and substantiating data to pro~
equal quality and performance to that which is specified. Clearly mal
manufacturer's literature to indicate equality in performance.
The undersigned certifies that the function, appearance and quality al
of equal performance and assumes liability for equal performance, equc
design and compatibility with adjacent materials.
Submitted By:
Signature
Title
Firm
Address
Telephone
Date
signature shall be by person having authority to legally bind his firm t
the above terms. Failure to provide legally binding signature will resu=
in retraction of approval.
For use by the Architect:
____Recommended ____Recommended as noted
____Not Recommended ____Received too late
Insufficient data received
By
Date
Fill in Blanks Below:
A. Does the substitution affect dimensions shown on Drawings?
Yes
No
If yes, clearly indicate changes.
B. will the undersigned pay for changes to the building design
including engineering and detailing costs caused by the requestec
substitution?
Yes
No
If no, fully explain:
C. What effect does substitution have on other Contracts or othel
trades?
D. What effect does substitution have on construction schedule?
E. Manufacturer's warranties of the proposed and specified items are:
Same
Different. Explain:
F. Reason for Request:
G.
Itemized comparison of specified item(s)
substitution; list significant variations:
with the proposec
H. This substitution will amount to a credit or extra cost to the Ownel
of: dollars ($ ).
I. Designation of maintenance services and sources:
(Attach additional sheets if required.)
****************
END OF DOCUMENT 01630
SECTION 01650
STARTING OF SYSTEMS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. starting systems
2. Demonstration and instructions
3. Testing, adjusting, and balancing
B. Related sections:
1. SECTION 01700 - CONTRACT CLOSEOUT
1..2 STARTING SYSTEMS
A. Coordinate schedule for start-up of various equipment and
systems.
B. Notify the Construction Manager seven days pr ior to
start-up of each item.
C. verify that each piece of equipment or system has been
checked for proper lubrication, drive rotation, belt
tension, control sequence, or other conditions which may
cause damage.
D. Verify that tests, meter readings, and specified
electrical characteristics agree with those required by
the equipment or system manufacturer.
E. Verify wiring and support components for equipment are
complete and tested.
F.
Execute start-up under supervision
manufacturer's representative in
manufacturer's instructions.
of responsible
accordance with
G. Execute start-up under supervision of the responsible
Contractors' personnel in accordance with manufacturer's
instructions. All in-line and interface trades shall
cooperatively support and coordinate individual
components and systems to facilitate start-up activities.
H. When specified in individual Specif ication sections,
require manufacturer to provide authorized representative
to be present at the site to inspect, check and approve
11/21/91
STARTING OF SYSTEMS
01650 - 1
equipment or system installation prior to start-up, and
to supervise placing equipment or system in operation.
I. Submit a certified written report that equipment or
system has been properly installed and is functioning
correctly.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01650
11/21/91
STARTING OF SYSTEMS
01650 - 2
SECTION 01670
SYSTEMS DEMONSTRATIONS
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Procedures for demonstration of equipment operation
and instruction of the Owner's personnel.
1..2 QUALITY ASSURANCE
A. When specified in individual Sections, provide
manufacturer's authorized representative to demonstrate
operation of equipment and systems, instruct the Owner's
personnel and provide written report that demonstrations
and instructions have been completed.
B. The Owner will provide list of personnel to receive
instructions, and will coordinate their attendance at
agreed-upon times.
1. .3 SUBMITTALS
A. Submit preliminary schedule for the Owner's approval,
listing times and date for demonstration of each item of
equipment and each system, two weeks prior to proposed
dates.
B. Provide operating and maintenance manuals to owner (4)
weeks prior to demonstrations.
C. Submi t reports wi thin one week after completion of
demonstrations, that demonstrations and instructions have
been satisfactorily completed. Give time and date of
each demonstration, and hours devoted to demonstration,
with a list of persons present.
PART 2 - PRODUCTS
NOT USED
PART 3 - EXECUTION
3..1 PREPARATION
A. Verify equipment has been inspected and put into
04/30/91
SYSTEMS DEMONSTRATIONS
01670 - 1
operation;
performed;
operational.
testing, adjusting, and balancing has been
and equipment and systems are fully
B.
Have copies
manuals at
instructions.
of completed operation and maintenance
hand for use in demonstrations and
3..2 DEMONSTRATION AND INSTRUCTIONS
A. Demonstrate operation and maintenance of equipment and
systems to the Owner's personnel two weeks prior to date
of final inspection. For equipment requiring seasonal
operation, perform instructions for other seasons within
six months.
B. Use operation and maintenance manuals as basis of
instruction. Review contents of manual with personnel in
detail to explain aspects of operation and maintenance.
C.
Demonstrate start-up, operation, control,
maintenance, servicing, trouble-shooting and
each item of equipment at agreed-upon
designated location.
adjustment,
shutdown of
times, at
D. Prepare and insert additional data in operations and
maintenance manuals when need for additional data becomes
apparent during instructions.
3..3 TIME ALLOCATED FOR INSTRUCTIONS
A. The amount of time required for instruction on each item
of equipment and system is specified in individual
Sections.
**************
END OF SECTION 01670
04/30/91
SYSTEMS DEMONSTRATIONS
o 1 67 0 .- 2
- , ..~. .._c,_ ~..." ~_' .._, _... ,_, ''',__ __ .~_'''', ~__- . ':"'_
SECTION 01700
CONTRACT CLOSEOUT
PART 1 - GENERAL
1. . 1 SUMYiARY
A. section includes:
1. Closeout p~ocedures
2. Adjusting
B. Related sections:
1. SECTION 01027 - APPLICATION FOR PAYMENT
2. SECTION 01650 - STARTING OF SYSTEMS
3. SECTION 01730 - OPERATION AND MAINTENANCE DATA
4. SECTION 01740 - WARRANTIES AND BONDS
5. SECTION 08710 - FINISH HARDWARE
6. SECTION 11196 - SECURITY HARDWARE
1..2 PROJECT TERMINATION
A. the Contract requirements are met when construction
acti vi ties have successfully produced, in this order,
these three terminal activities:
1. Substantial Completion
2. Final Completion
3. Final Payment
1..3 SUBSTANTIAL COMPLETION
A. Submit to the Construction Manager when the Work is
substantially complete:
1. A written notice that the Work, or designated
portion thereof, is substantially complete.
2. A list of items to be completed or corrected (Punch
List) .
3. Request Substantial Completion Observation at a
mutually agreeable date.
4. certifications of systems and testing/balancing
final reports.
5. Submit evidence of compliance with requirements of
governing authorities:
a. certificate of Occupancy
b. certificates of Inspection:
1) Elevators
2) Mechanical systems
3) Electrical systems
4) Kitchen equipment
04/09/91
CONTRACT CLOSEOUT
01700 - 1
5) Fire protection system
6) Security system
B. within a reasonable time after receipt of such notice,
the Architect, the Construction Manager, the
Contractor,and the Owner, will make an observation to
determine the status of completion.
C. Should the work be determined to not be substantially
complete the following will occur:
1. The Construction Manager will promptly notify the
Contractor in writing, giving the reasons.
2. The Contractor shall remedy the deficiencies in the
Work, and send a second written notice of
substantial completion.
3. The Work will be reobserved.
D. When the Work is considered substantially complete, the
following will occur:
1. The Construction Manager will prepare a certificate
of Substantial Completion on AlA Form G704,
accompanied by the Contractor's Punch List of items
to be completed or corrected, as verified and
amended. Contract responsibilities are not altered
by inclusion or omission of required Work from the
punch list.
2. The certificate will be executed by all parties and
distribution made.
E. Complete or correct items identified on the punch list
and required by the Contract requirements wi thin time
limit established by the certificate.
1..4 FINAL COMPLETION
A. To attain final completion, the Contractor shall complete
activities pertaining to substantial completion, complete
Work on punch list items and submit written request to
the Construction Manager for final inspection.
B. When the Work is complete, the Contractor shall submit
written certification that:
1. The Contract Documents have been reviewed.
2. Work has been inspected for compliance with the
Contract Documents.
3. Work has been completed in accordance with the
Contract Documents.
4. Equipment and systems have been tested in the
presence of the Owner's representative and are
operational.
5. Work is completed and ready for final observation.
CONTRACT CLOSEOUT
01700 - 2
04/09/91
C.
D.
The Architect, the Construction Manager, the Contractor
and the Owner will make an inspection to verify the
status of completion with reasonable promptness after
receipt of such certification.
Should the Work be considered incomplete or defective:
1. The Construction Manager will promptly notify the
Contractor in writing, listing the incomplete or
defective work.
2. The Contractor shall take immediate steps to remedy
the stated deficiencies and send a second written
certification to the Construction Manager that the
Work is Complete.
3. The Work will be reinspected.
E.
When the Work is acceptable under the Contract Documents
the Contractor shall make closeout submittals.
1..5 THE CONTRACTOR'S CLOSEOUT SUBMITTALS TO THE ARCHITECT
to requirements of SECTION
A.
Project Record Documents:
01720.
B. Operating and maintenance data, instructions to the
Owner's personnel: to requirements of SECTION 01730.
C.
Keys and keying schedule:
08710 & 11196.
to requirements of SECTION
D. Spare parts and maintenance materials: to requirements
of individual sections.
E. Evidence of payment and release of liens: to
requirements of General and Supplementary Conditions.
1..6 FINAL ADJUSTMENT OF ACCOUNTS
A. Submit a final statement of accounting to the Architect.
B. Statement shall reflect adjustments to the Contract Sum:
1. The original Contract Sum
2. Additions and deductions resulting from:
a. Previous Change Orders
b. Allowances
c. Unit Prices
d. Deductions for uncorrected Work
e. Penalties and bonuses
f. Deductions for liquidated damages
g. Deductions for reinspection payments
h. Other adjustments
3. Total Contract Sum, as adjusted
04/09/91
CONTRACT CLOSEOUT
01700 - 3
4. Previous payments
5. Sum re~aining due
C. The Construction Manager will prepare a final Change
Order, reflecting adjustments to the Contract Sum which
were not previously made by Change Orders.
1..7 FINAL APPLICATION FOR PAYMENT
A. The Contractor shall submit the final Application for
Payment in accordance with procedures and requirements
stated in the Conditions of the Contract.
PART 2 - PRODUCTS
Not used
PART 3 - EXECUTION
Not used
*****************
END OF SECTION 01700
04/09/91
CONTRACT CLOSEOUT
01700 - 4
SECTION 01710
FINAL CLEANING
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Cleaning at completion of Work
1..2 DISPOSAL REQUIREMENTS
A. Conduct cleaning and disposal operations to comply with
codes, ordinances, regulations, and anti-pollution laws.
1. Do not burn or bury rubbish and waste materials on
the Project site.
2. Do not dispose of volatile wastes such as mineral
spirits, oil or paint thinner in storm or sanitary
drains.
PART 2 - PRODUCTS
2..1 MATERIALS
A. Use only those cleaning materials which will not create
hazards to health or property and which will not damage
surfaces.
B. Use only those cleaning materials and methods recommended
by manufacturer on the surface material to be cleaned.
C. Use cleaning materials only on surfaces recommended by
cleaning material manufacturer.
PART 3 - EXECUTION
3..1 DUST CONTROL
A. Handle materials in a controlled manner with as little
handling as possible.
3..2 FINAL CLEANING
A. Employ skilled workmen for final cleaning.
B. Remove grease, mastic, adhesives, dust, dirt, stains,
fingerprints, labels, and other foreign materials form
sight-exposed interior and exterior surfaces.
04/09/91
FINAL CLEANING
01710 - 1
C. Wash and shine glazing and mirrors.
D. Polish glossy surfaces to a clear shine.
E. Dust cabinetwork and remove markings.
F. Vacuum as needed.
G.
Broom clean exterior paved surfaces;
surfaces of the grounds.
rake clean other
H. Prior to final completion, or the . Owner occupancy,
conduct an inspection of sight-exposed ~nterior surfaces,
exterior surfaces and work ~areas, to verify that the
entire Work is clean.
I. Clean tunnels and closed" off spaces of packing boxes,
wood frame members and other waste materials used in the
Construction.
J. Internally clean the entire system of piping and
equipment. Open dirt pockets and strainers, completely
blowing down as required and clean strainer screens of
accumulated debris.
K. Drain tanks, fixtures and pumps to be free of sludge and
accumulated matter.
L. Remove temporary labels and stickers from fixtures and
equipment. Do not remove permanent name plates,
equipment model numbers and ratings.
M. Thoroughly clean heating and air conditioning equipment,
tanks, pumps and traps. Install or thoroughly clean
filters or filter media, including:
1. The cleaning of permanent filters and the
replacement of disposable f il ters if units were
operated during construction.
2. The cleaning of ducts, blowers, and coi ls if the
units were operated during construction.
N. Remove from the site all facilities of items installed or
used for temporary purposes during construction.
O. Restore all adjoining areas to their original or
specified condition.
****************
END OF SECTION 01710
04/09/91
FINAL CLEANING
01710 - 2
SECTION 01720
PROJECT RECORD DOCUMENTS
PART 1 - GENERAL
1..1 SUMMARY
A. Section includes:
1. Maintain at the job site one copy of:
a. Record Contract Drawings
b. Record Project Manual
c. Coordination drawings
d. Addenda
e. Reviewed shop drawings
f. Change Orders
g. Other modifications to the Contract
h. Field test records
1. .2 GENERAL
A. Store documents in cabinets in temporary field office,
apart from documents used for construction.
B. Maintain documents in clean, dry, legible condition.
C. Do not use Project Record Documents for construction
purposes.
D. Make documents avai lable for inspection by the
Construction Manager, the Architect and the Owner.
E. Failure to maintain documents up-to-date will be cause
for withholding payments.
F. Obtain from the Construction Manager (at no charge) two
sets of the Contract Documents for Project Record
Documents including:
1-
2.
Specifications with
Two complete sets
Drawings.
One complete set of
all addenda.
of black line prints of all
3 .
mylar prints of all Drawings.
1. .3 RECORDING
A. Label each document "Project Record".
B. Keep record documents current.
01/06/92
PROJECT RECORD DOCUMENTS (ADD. 2)
01720 - 1
C. Do not permanently conceal any work until required
information has been recorded.
D. Contract Drawings:
1. Required information may, as an option, be entered
on a "working set" and then at completion of
project transfer the information to final submitted
IIproject Record" set.
2. Legibly mark to record actual construction:
a. Depths of various elements of foundation in
relation to survey data.
b. Horizontal and vertical location of
underground utilities and appurtenances
referenced to permanent surface improvements.
c. Location of internal utilities and
appurtenances concealed in construction
referenced to visible and accessible features
of structure.
d. Field changes of dimension and detail.
e. Changes made by Change Order or Construction
Change Directive.
f. Details not on original Contract Drawings.
E. Specifications and Addenda:
1. Legibly mark up each section to record:
a. Manufacturer, trade name, catalog number and
supplier of each product and item of equipment
actually installed.
b. Changes made by Change Order or Construction
Change Directive.
c. Other items not originally specified.
F. Conversion of schematic layouts:
1. Arrangement of conduits , circuits, piping, ducts
and similar items are in most cases shown
schematically on the Drawings.
2. Legibly mark to record actual construction:
a. Dimensions accurate to within 111 on the
centerline of items shown schematically.
b. Identify each item, for example, "cast iron
drain" IIgalvanized water".
c. Identify location of each item, for example,
"under slab", "in ceiling plenum", lIexposedll.
3. The Construction Manager may waive requirements of
schematic layout conversion, when in his opinion,
it serves no beneficial purpose. Do not, however,
rely on waivers being issued except specifically
issued by the Construction Manger in writing.
PROJECT RECORD DOCUMENTS (ADD. 2)
01720 - 2
01/06/92
1. .4 SUBMITTAL
A. At completion of Project, deliver Project Record
Documents as delineated in paragraph 1.2 F. above, to the
Construction Manager prior to request for final payment.
B. Accompany submi ttal with transmi ttal letter, in
duplicate, containing:
1. Date
2. Project title and HLM Project number
3. The Contractor's name and address
4. Title and number of each record document
5. certif ication that each document as submitted is
complete and accurate.
6. signature of the Contractor, or his authorized
representative.
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
***************
END OF SECTION 01720
01/06/92
PROJECT RECORD DOCUMENTS (ADD. 2)
01720 - 3
SECTION 01730
OPERATION AND MAINTENANCE DATA
PART 1 - GENERAL
1..1 SUMMARY
A. section includes:
1. Format and content of manuals
2. Instruction of the Owner's personnel
3. Schedule of submittals
B. Related sections:
1. SECTION 01301 - SUBMITTALS
2. SECTION 01700 - CONTRACT CLOSEOUT
3. Individual specifications sections: specific
requirements for operation and maintenance data.
1..2 QUALITY ASSURANCE
A. Prepare instructions and data by personnel exper ienced in
maintenance and operation of described products.
1. . 3 FORMAT
A. Prepare data in the form of an instructional manual.
B. Binders: commercial quality, 8-1/2" x 11" three-ring
binders with hardback, cleanable, plastic covers; 1-1/2"
maximum ring size. When multiple binders are used,
correlate data into related consistent groupings.
C. Cover: identify each binder with typed or printed title
OPERATION AND MAINTENANCE INSTRUCTIONS; list ti tle of the
Project and separate building; identify subject matter of
contents.
D. Arrange content by systems under section numbers and
sequence of Table of Contents of these Specifications.
E. Provide tabbed fly leaf for each separate product and
system, with typed description of product and major
component parts of equipment.
F. Text: manufacturer's printed data, or typewritten data
on 20 pound paper.
G. Drawings: provide with reinforced punched binder tab.
Bind in with text; fold larger drawings to size of text
OS/20/91
OPERATION AND MAINTENANCE DATA
01730 - 1
pages.
1..4 CONTENTS, EACH VOLUME
A. Table of Contents: provide title of the project; names,
addresses, and telephone numbers of the Construction
Manager, the Architect, consultants, and the Contractor
with name of responsible parties; schedule of products
and systems, indexed to content of the volume.
B. For each product or system: list names, addresses and
telephone numbers of subcontractors ~nd suppliers,
including local source of supplies and replacement parts.
C. Product data: mark each sheet to clearly identify
specific products and component parts, and data
applicable to installation. Delete inapplicable
information.
D. Drawings: supplement product data to illustrate
relations of component parts of equipment and systems, to
indicate control and flow diagrams. Do not use the
Project Record Documents as maintenance drawings.
E. Type text: as required to supplement product data.
Provide logical sequence of instructions for each
procedure, incorporating manufacturer's instructions.
F. Warranties and bonds: bind in copy of each.
1..5 Y~UAL FOR MATERIALS AND FINISHES
A. Building products, applied materials, and finishes:
include product data, with catalog number, size,
composi tion, and color and texture designations. Provide
information for re-ordering custom manufactured products.
B. Instructions for care and maintenance; include
manufacturer's recommendations for cleaning agents and
methods, precautions against detrimental agents and
methods, and recommended schedule for cleaning and
maintenance.
C. Moisture protection and weather exposed products:
include product data listing applicable reference
standards, chemical composition, and details of
installation. Provide recommendations for inspections,
maintenance, and repair.
D. Additional requirements; as specified in individual
product specification sections.
OS/20/91
OPERATION AND }~INTENANCE DATA
01730 - 2
1..6 MANUAL FOR EQUIPMENT AND SYSTEMS
A. Each item of equipment and each system: include
descr iption of unit or system, and component parts.
Identify function, normal operating characteristics, and
limiting conditions. Include performance curves, with
engineer ing data and tests, and complete nomenclature and
commercial number of replaceable parts.
B. Panelboard circuit directories: provide electrical
service characteristics, controls and communications.
.c. Include color coded wiring diagrams as installed.
D. Operating procedures: include start-up, break-in, and
routine normal operating instructions and sequences.
Include regulation, control, stopping, shut-down, and
emergency instructions. Include summer, winter, and
special operating instructions.
E. Maintenance requirements: include routine procedures and
guide for trouble-shooting; disassembly, repair, and
reassembly instructions; and alignment, adjusting,
balancing, and checking instructions.
F. Provide servicing and lubrication schedule, and list of
lubricants required.
G. Include manufacturer's printed operation and maintenance
instructions.
H. Include sequence of operation by controls manufacturer.
I. Provide original manufacturer's parts list,
illustrations, assembly drawings, and diagrams required
for maintenance.
J. Provide control diagrams by controls manufacturer as
installed.
K. Provide the Contractor's coordination draw ings, with
color coded piping diagrams as installed.
L. Provide charts of valve tag numbers, with location and
function of each valve, keyed to flow and control
diagrams.
M. Provide list of original manufacturer's spare parts,
current prices, and recommended quantities to be
maintained in storage.
OS/20/91
OPERATION AND MAINTENANCE DATA
01730 - 3
N. Include test and balancing reports.
o. Additional requirements: as specified in individual
product specification ~ections.
P. Provide a listing in Table of Contents for design data,
with tabbed fly sheet and space for insertion of data.
1..7 INSTRUCTION OF THE OWNER PERSONNEL
A. Before final inspection, instruct the Owner's designated
personnel in operation, adjustment, and maintenance of
products, equipment, and systems, at agreed upon times.
B. For equipment requiring seasonal operation, perform
instructions for other seasons within six months.
C. Use operation and maintenance manuals as basis for
instruction. Review contents of manual with personnel in
detail to explain all aspects of operation and
maintenance.
D.
Prepare and insert additional
Maintenance Manual when need
apparent during instruction.
data in
f or such
Operation and
da ta becomes
1. .8 SUBMITTALS
A. Submit two copies of preliminary draft or proposed
formats and outlines of contents before start of the
Work. The Construction Manager and Architect will review
draft and return one copy with comments.
B. For equipment, or component parts of equipment put into
service during construction and operated by the Owner,
submit documents within ten days after acceptance.
C. Submi t one copy of completed volumes in final form 15
days prior to final inspection. Copy will be returned
after final inspection, with Construction Manager and
Architect comments. Revise content of documents prior to
final submittal.
D. Submi t two copies of revised volumes of data in final
form within ten days after final inspection.
OS/20/91
OPERATION AND MAINTENANCE DATA
01730 - 4
PART 2 - PRODUCTS
Not Used
PART 3 - EXECUTION
Not Used
**************
END OF SECTION 01730
OS/20/91
01730 - 5
OPERATION AND MAINTENANCE DATA