Change Order No. KJ-008-007
C H A N G E 0 R D E R
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-008-007
To Contractor: J.F. HOFF ELECTRIC
371 CYPRESS DRIVE
TEQUESTA, FL
Change Order Date: 01/20/93
Architect's Project #:
33460
Contract For:
PRIME ELECTRICAL
Contract Date:
02/19/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 055 - POST BID ADDENDA THRU ADDENDA 9
In accordance with Hoff's written quotation dated September 17, 1992, incorporate the revIsIons to
the Contract Documents detailed in Bid Group 3 Addendums No.5 through No.9 and Architect's
Supplemental Instruction (ASI) No. 13. The issue dates of these documents are as follows: _"_
( )
Addendum No. 5 dated February 18, 1992
Addendum No.6 dated March 4, 1992 ~; ::>
Addendum No. 7 dated March 10, 1992 ., (") ~
Addendum No.8 dated March 25, 1992 C) r .c.
Addendum No. 9 dated Apri l 3, 1992 C) =" -<
ASI No. 13 dated September 3, 1992 So'
This work shall not include the PVC telephone conduits installed in the concrete topping Sl~ ~ ~
Zone A by others, but will include the connection to and continuation of these conduits to the 0 ~"~
designated device and/or panel. --1--; j-.
c.o
C..:>
::3
=0
::!,J
"i
u--;
:-;'J
-0
::3
.....,.....
._....J
rn
C")
o
::0
o
L "
~
C::J
C..:>
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 48,922.76 and 0 days.
The Original Contract Amount was ..... ........... ............ ...... ....... ........................... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Va l ue of th i s Change Order is.................................................................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time will change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
Recommended by Construction Manager:
2-L/~93
Date
Agreed to by Contractor:
Authorized by Owner:
County Commissioners
1,855,491. 00
-854,239.48
1,001,251.52
48,922.76
1,050,174.28
o days
07101/93
Z-' -93
Date
A e : Danny L. Kolhage, Clerk
By .a~c'. Lh A1-~
Deputy C l~rk
Date d ';)..-ID - <13
By
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.