Change Order No. KJ-008-009 C H A N G E 0 R D E R Project: KJ - NEW DETENTION FACILITY Change Order Number: 01-008-009 Change Order Date: 08/13/93 To Contractor: J.F. HOFF ELECTRIC 371 CYPRESS DRIVE TEQUESTA, FL 33460 Architect's Project #: Contract For: PRIME ELECTRICAL Contract Date: 02/19/92 You are directed to make the fOllowing changes in this contract; all other provisions of the contract shall, except as specifically changed herein, remain in full force and effect. Issue: 081 - ACCESS PANEL P.O. In accordance with Contract Specification Section 00314, Prime Electrical Scope of Work, deduct from the Contract Base Bid Amount, the allowance for others supplying the Contractor's listed~izes and ~ quantities of access panels and doors which were not shown on the Contract Drawings. T~ .. - \...t...I Contractor remains responsible for furnishing access panels and doors required by this seope'~f Work which exceed the quantities listed in the Base Bid. ?Dr ~ f'T1 -0 "'1 rT1 ~ '. ._~.J N CC :;:.::. \0 j:;~ Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts due to this contract change for the LUMP SUM AMOUNT of $ -2,000.00 and 0 days. The Original Contract Amount was .................................................................... $ Net Change by Previously Authorized Change Orders .................................................... $ The Contract Amount prior to this Change was ......................................................... $ The Value of this Change Order is .................................................................... $ The New Contract Amount including this Change Order will be .......................................... $ The Contract Time will change by ........... ..... ...... .......... ..... ................................ The Date of Substantial Completion as of the Date of this Change Order is ............................ 1,855,491.00 -805,316.72 1,050,174.28 -2,000.00 1,048,174.28 o days 11/01/93 Recommended by Construction Manager: Approved by Architect: Morrison-Knudsen/Gerrits 5090 Coli.,. R~ ~~ ~~7 te 93 Agreed to by Contractor: Authorized by Owner: J.F. HOFF ELECTRIC 371 CYPRESS DRIVE EQUESTA, FL 3346~ 'Q't\W ?r-~C,-/" Date County Commissioners .......... By By Kolhage, Clerk -Po~ t. .&.,,~ Deputy Clerk / ~9-t>"'3 Date Date Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.