Change Order No. 01-029-001 C H A N G E 0 R D E R Project: KJ - NEW DETENTION FACILITY To Contractor: ALLEN'S ENVIRONMENTAL EQUIPMNT 719 COMMERCE CIRCLE LONGWOOD, FL Change Order Number: 01-029-001 Change Order Date: 08/16/93 32750-3605 Contract For: WWTP FINAL DESIGN & CONSTRUCT Contract Date: 04/14/93 You are directed to make the following changes in this contract; all other provisions of the contract shall, except as specifically changed herein, remain in full force and effect. Issue: 226 - LIFT STATION CONTROL PANEL Deduct for non-submersible control panel remote mount above flood elevation in accordance with AEEI letter of June 1, 1993 (KJ-IC29-015). It is understood and agreed that this adjustment constitutes compensation in full on behalf of the Design/Builder and it's subcontractors and suppliers for all costs and considerations directly or indirectly attributable to the changes listed above. -,. \C5 -Tl W UJ Z ;--, :0 ,--., C/.l ' -' I"Ti ; , -0 ,.J N CC :;::: '-0 -; 1:::: .~ ij --'" The Original Contract Amount was......... ......... .... ............... ..................... .......... $ Net Change by Previously Authorized Change Orders .................................................... $ The Contract Amount prior to this Change was ......................................................... $ The Va l ue of th i s Change Order is.................................................................... $ The New Contract Amount including this Change Order will be .......................................... $ The Contract Time will change by ..................................................................... The Date of Substantial Completion as of the Date of this Change Order is ............................ 580,441.00 0.00 580,441.00 -4,300.00 576,141.00 o days 09/03/93 Recommended by Construction Manager: By Date Agreed/Approved by Design/Builder: Authorized by Owner: ALLEN'S ENVIRONMENTAL EQUIPMNT 719 COM~~A/I~~ LONGWOOD(~U0fP ~ By (-/1-'13- Date County Commissioners By By anny L. Kolhage, Clerk .JJo<<..td. c.. ~ Deputy Cler 09'0/-,/3 I -;t;, . ,.) Approved As To Form County Attorney's Office Date 2Y ~u~ '~ 3 Date Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Design/Builder indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.