Change Order No. 01-018-004
-'-'--
C H A N G E 0 R D E R
To Contractor: BIG C STEEL, INC.
13095 49 STREET, N
CLEARWATER, FL
Ohange Order Number: 01-018-004
Change Order Date: 11/03/93
Project: KJ - NEW DETENTION FACILITY
Architect's Project #:
34622
Contract For:
STAIRS & MISCELLANEOUS METALS
Contract Date:
06/10/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 097 - TRANSFORMER VAULT REVISIONS
In accordance with the Architect's Supplemental Instruction No. 24, dated January 22, 1993, supply
and install the pulling eyes and the lifting eye apparatus at the transformer vault~
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 2,765.00 and 0 days.
The Original Contract Amount was. ........... ......... .......... ..... ............................. ... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Va l ue of th i s Change Order is.................................................................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time will change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
280,269.00
-209,736.65
70,532.35 ...
2,765.00 ~
73,297.35
o days
11/01/93
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
Key West, F 33
By
Agreed
Authorized by Owner:
/1 9" .7,.-:>
Date
Attest: Danny L. Kolhage, Clerk
BY~~~~
De Cler
Date--1\10 v' ~ e;( 3D I I eJq 3
,
Approved As To
By
Date
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.
ARCHITECT'S
SUPPLEMENTAL INSTRUCTIONS
otSTRlBUnON: Gonzalez Architects, D. Voda
ew onroe un e n on ael I
PROJECT: Key West, f10rida ARCHITECT'S SUPPLEMENTAL
(name, address) INSTRUCTION N0z4 Bid Group 3
OWNER: Monroe County DATE OF ISSUANCE: JanuaI)' 22, 1993
TO: Morrison Knudsen/Gerrits ARCHITECT: HANSEN LIND MEYER INC.
(Contractor) Post Office Box 5283
Key West, Florida 33045-5283
CONTRACT FOR: All Work
ARCHITECT'S PROJECT NO:
90007,00
The Work shall be carried out in accordance with the following supplemental instructions issued in accord-
ance with the Contract Documents without change in Contract Sum or Contract Time. Prior to proceeding
in accordance with these instructions, indicate your acceptance of these instructions for minor change to
the Work as consistent with the Contract Documents and return a copy to the Architect.
Description:
Install lifting rings. curb and floor-mounted hatch doors in Transformer Room.
Attachments: (HtI. In"" lilli", 01 docum.nu ,",, .upporl MIC/lplion,)
Drawing No. 4.09 - Exterior Building Plan, First Floor, Zone C dated 1/22193
c 7-;5
BY
Date
ay