Change Order No. 31-001-001
C H A N G E 0 R D E R
Project: SHERIFF'S BUILDING AT NEW JAIL
To Contractor: D. L. PORTER CONSTRUCTION
1100 GILLESPIE AVE
SARASOTA, FL
Change Order Number: 31-001-001
Change Order Date: 09/26/94
Architect's Project #:
34236
Contract For:
CONSTRUCTION
Contract Date:
06/16/94
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 004 - AWARD DATE TIME EXTENSION
The Milestone Schedule included in the Contract Bid Documents indicated an Award Date for the
Contract of June 16, 1994. The Owner determined to make the Award for this Contract on July 20,
1994, 34 calendar days after the specified date. This Contract Change Order shall revise the
Milestone Schedule Dates as follows at no additional cost to the Owner:
Award Date..................................07/20/94
Notice to Proceed Date......................07/27/94
Building Permit from DCA (Anticipated)......08/08/94
Substantial Completion Date.................08/03/95
-7 """1
U ~
Z "T1
:::t:; -- .,
,-' z
CJ
c:::::
I --'
~ .'
.,--,
::c:::
\.0
Ui -~,l
~
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and all related impacts
due to this contract change for the LUMP SUM AMOUNT of $ 0.00 and 34 days.
The Original Contract Amount was ......... ........ ................. ........ .......................... $
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Va l ue of th i s Change Order is.................................................................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time wi II change by ..................................... ................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
3,514,000.00
0.00
3,514,000.00
0.00
3,514,000.00
34 days
08/03/95
Recommended by Construction Manager:
Approved by Architect:
lo~ 39'1
Date
ONZALEZ ARCHITECTS
14 NORTHSIDE~'
Y WEST, FL ~_3040
Agreed to by Contractor:
D. L. PORTER CONSTRUCTION
1100 GILLESPIE AVE
SARASOTA, FL 34236
lo ^ n~-j,
By
t:t h.7 /'14
Date
Monroe County Board of County Commissioners
500 Whitehead Street
K:;es~~o tJ
By MaYOr~o Tern Date
By
At':" ~ L. rKOlh.... ~'~k 9P~
Deputy Clerk
Approved As
Date
Date
October 20, 1994
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.