Change Order No. 01-022-001
C H A N G E 0 R D E R
To Contractor: FIRST CHOICE ROOFING
10267 NW 46 STREET
SUNRISE, FL
Change Order Number: 01-022-001
Change Order Date: 10/30/92
Project: KJ - NEW DETENTION FACILITY
Architects Project #:
33351
Contract For:
ROOFING
Contract Date:
07/15/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 120 - LIGHTWEIGHT CONCRETE SUBSTITUTION
In accordance with First Choice's post-bid substitution request for Elastizell cellular lightweight
concrete, dated July 31, 1992, as approved and noted by the AlE on September 17, 1992, and per
MK/G's letter(Serial No. KJ-OC22-017) of authorization to proceed, dated September 22, 1992, install
the proposed cellular lightweight concrete on the roof, in lieu of the tapered insulation
originally proposed.
..
CD
c:..;) ."
;, ~ c... r--
l,) :z: =:D rrl
r, 0 __ Z ,---,
r- -- '-'
g~~ ~ 6
z ::u
-l?J~ ::D ;U
-~ r- :::::3 rn
-I~::- 0
, . Xc>< ..- 0
, ) C) ..- ::0
Contractor agrees to accept this LUMP SUM CHANGE ORDER as FINAL SETTLEMENT for this extra work and:a'll re[~te~c~
due to this contract change for the LUMP SUM AMOUNT of S 35,000.00 and 0 days. t!J
.:::...
c>
The Origninal Contract Amount was .................................................................... S
Net Change by Previously Authorized Change Orders .................................................... S
The Contract Amount prior to this Change was ......................................................... S
The Value of this Change Order is ....... .................... ...... .......... ......................... S
The New Contract Amount including this Change Order will be .......................................... S
The Contract Time wi II change by .....................................,...............................
The Date of Substantial Completion as of the Date of this Change Order is ............................
345,900.00
0.00
345,900.00
35,000.00
380,900.00
o days
07101/93
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
1JesLFla 33045
~ ). 1JL.
By
".,.,....
Date
Agreed to by Contractor:
Authorized by Owner:
ICE ROOFING
46 STREET
FL 33351
v
est: Danny L. Kolhage, Clerk A .
By A~ C. LO.Jo~~
Depu~k
Date Ii- 0 ,- 9.
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum andlor Contract Time.