Change Order No. 01-017-009
CHAN.,.E ORDER
Project: KJ - NEW DETENTION FACILITY
Change Order Number: 01-017-009
Change Order Date: 11/17/93
To Contractor: D.L. PORTER CONSTRUCTION, INC.
1100 GILLESPIE AVE
SARASOTA, FL
34236
Architect's Project #:
Contract For:
CONCRETE
Contract Date:
06/10/92
You are directed to make the following changes in this contract; all other provisions of the contract shall, except as
specifically changed herein, remain in full force and effect.
Issue: 272 - RELOCATE FIRE HYDRANT
At the request of the City of Key West Fire Department, relocate the fire hydrant adjacent to
column G2 to 15 feet from column line G and 15 feet from column line 2. The work shall include but
not be limited to excavation, dewatering, concrete demolition, offsite disposal, backfill, thrust
blocks and testing. The piping material shall match that currently installed. All of the work
included in this change order shall be completed prior to December 10, 1993, and the contractor
shall furnish all labor and/or services such as overtime as may be necessary to meet this milestone
date.
-" -r--.
\C5
0 VJ
:z , ,
AJ
---, ~_. 0
rr-I
r.:l
- A
Contractor agrees to accept this LlJ4P SUM CHANGE ORDER as FINAL SETTLEMENT for this extra war~: and all related i~cts
due to this contract change for the LUMP SUM AMOUNT of $ 3,400.00 and 0 days. ~
o
The Original Contract Amount was .................................................................... La
Net Change by Previously Authorized Change Orders .................................................... $
The Contract Amount prior to this Change was ......................................................... $
The Va l ue of th i s Change Order is.................................................................... $
The New Contract Amount including this Change Order will be .......................................... $
The Contract Time wi II change by .....................................................................
The Date of Substantial Completion as of the Date of this Change Order is ............................
1,079,410.00
-21,725.00
1,057,685.00
3,400.00
1,061,085.00
o days
12/09/93
Recommended by Construction Manager:
Approved by Architect:
Morrison-Knudsen/Gerrits
5090 College Road
Key West, 3304
Agreed to by Contractor:
Authorized by Owner:
D.L. PORTER CONSTRUCTION, INC.
1100 GILLESPIE AVE
en:A'~L ,3;t.Q~
By
Itf g/9~
ate /
County Commissioners
By
Attest: Danny L. Kolhage, Clerk
By ~~<.4)~~~)
Deput lerk
DatejJO\/~bM 30, '00 3
,
Approved As To
Date
Not valid unless signed by the Owner, the Architect, and the Construction Manager. Signature of the Contractor
indicates agreement herewith, including any and all adjustments in Contract Sum and/or Contract Time.