01st Change Order 03/30/2005 MONROE COUNTY ENGINEERING/CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER PROJECT TITLE: CHANGE ORDER NO: Freeman Justice Center 1 DATE: March 10,2005 Total Previous Change Orders Current Change Order % of Original Contract Amount % of Contract after Prior CIO's Original Contract Amount Revised Contract Amount o ($30.360.00) N/A N/A $13.804.000.00 $13.773,640.00 Detailed description of change order and justification: This DEDUCT chanae order allows the structural inspections to be performed bv the Structural Enaineer thus insurina the structure is built within the design parameters. The amount of $30,360 is for inspections bv the structural enaineer twice a week for 12 weeks. At the end of this 12 week period the inspections will be completed bv MT Causlev for the duration of the proiect. The proiect substantial completion will be extended by 38 days at no additional cost to the owner for overhead and profit. The new substantial completion date will be June 17. 2006 ARCHITECT: CONTRACTOR: CONSTRUCTION MANAGER: COUNTY ENGINEER: COUNTY ADMINISTRATOR David S. Koppel, Thom& r CMD-CHG.l g '14-'2~ Date ,).-l2> - os. Date J'~%:r ., Date j ,03/09/f005 17:48 FAX 954 370 5401 ,~ THE TOWER GROUE. General Contractors Construction Management Construction Design-Build Planning Sife Development Infrastructure Consul1lng EstImating Scheduling Value Engineering Post Construction CGCA38309 UNITED ENGINEERING CORP. @002 March 9, 2005 MeN/WE COUNIY CONSTRUC110fll MANAGEM! MAR~200 l1ME: mtavm f:!}f __ , _ 0417-00506 Larry S. Chalmers Director of Construction & Planning MONROE COUNTY CONSTRUCTION MGMT 1100 Simonton Street Key West, Florida 33040 Fax: 305-295-4321 ROUT ''-['il DL /=" df o o o o RE: Subject: Freeman Justice Center (FJC) Structural Inspections Dear Mr. Chalmers: This letter will address the recent conversations we've been having regarding structural inspections and delayed work progress due to the ongoing conflicts over how those inspections have and will be conducted. As you know, The Tower Group is uncomfortable retaining the Special Inspectors required to perform the structural inspections. While there is a pay item in the Contract Documents for inspections, The Tower Group is uncomfortable with a direct contract with inspectors performing inspections of The Tower Group work. We know you are sympathetic to our viewpoint, but we also recognize that your preference is to have The Tower Group contract inspectors, so that the inspection work does not become a public bid item. In order to accommodate your preference, we previously retained M.T. Causley. However, with regard to structural work, and the safety issues involved, Monroe County has agreed that the preferred approach would be to have the Engineer of Record inspect the structural foundation work. Accordingly, we have agreed to credit the Owner with the amount of $30,000.00. This $30,000.00 credit, as we understand it, will be paid to Gonzalez Architects who in tum will pay the Engineer of Record for the following inspection work: Pistorino and Alam will perform two structural inspections each week for the next three months, or until the foundation steel work and concrete pours are completed, In so doing, The Tower Group's structural foundation work will be reviewed by the Engineer of Record, and not by an inspector being paid by The Tower Group, pursuant to the Contract Documents. 405 S,w, 1 48th Avenue' Suite One - Davie, Florida 33325 . Tel: 954 '476.3200 - Fax: 954-474-3111 7601 S,w, Lost River Road - Stuart. Florida 34497 - Tel: 772-287-7525 - Fax: 772.287-7524 9440 Philips Hiqhwav, Suite#5 - Jacksonville, Florida ,,?? fif, . TAl' <mLl _ ? 0') . 1 All . ~r'tV' on A . "....". A 0' C UNITED ENGINEERING CORP. ,03109/2005 17:48 FAX 954 370 5401 . ..' THE TOWER GRaue. ~ UU;J March 9, 2005 MCCM Page 2 When the structural foundation work is complete and the vertical construction work begins, columns, beams and joists, The Tower Group hopes you will choose to continue with the Engineer of Record for structural inspections. Regarding time, we are aII aware that the work has been slowed over recent weeks over a number of issues, inclusive of structural inspections. In our most recent conversation, The Tower Group proposed a time extension of eight (8) weeks. Mr. Jose Gonzalez of Gonzalez Architects countered with a four (4) week time extension. In order to conclude this time extension issue, The Tower Group has stated that a six (6) week time extension would be acceptable. While Mr. Gonzalez's initial response has been to decline the six week proposal, we hope this matter can be revisited. Finally, let me say that The Tower Group understands that Article 8.3.3 of the General Conditions states: No claim for an increase in the Contract Sum for either acceleration or delay will be allowed for extensions of time pursuant to this Paragraph 8.3 or for other changes in the Construction Schedules, While The Tower Group has reviewed this provision, we are also mindful of the idea that a contractor is entitled to compensation for delay when there has been active interference. As you are aware, this project is in its early state and The Tower Group is not seeking a compensatory change order at this time. However, we hope that our work, as it progresses, will not encounter the kinds of delays which may cause The Tower Group to request delay compensation, In closing, let's get back on track so that The Tower Group can oversee a productive and successful project. Sinr{~ Gregory F. Galmin Vice President CC: Gonzalez Architects File \~3/091?005 17:47 FAX 954 370 5401 UNITED ENGINEERING CORP. If!:I UU-L , ( ., , The Tower Group, Inc. 405 SW 148th Avenue, Suite One ,;,,:j Davie, Plorida 33325 ",:': Phone: 954-476-3200 " THE ~"'I Fu: 954-474-3111 TOWER I GROUP.:, 'llME: Ri:CEIVm RV: -" M To: Monroe County Construction Mgmt From: Gregory F. Galmin If Attn: Larry S. Chalmers Fax: 305-295-4321 Pages: 3 Pl1one: 305-292-4468 Date: March 9. 2005 Re: Freeman Justice Center (FJC) CC: Gonzalez architects 0417 00507 x Urgent x For Review x Please Comment X Please Reply . Comments:, Larry, see attached letter 00506 dated March 9, 2005, regarding Structural Inspections. Please review and respond accordingly. Greg File LETTER OF TRANSMITTAL Date: March 30, 2005 MONROE COUNTY Construction Management 1100 Simonton Street Key West, Florida 33040 (305) 292-4429 Attention: Jackie/Pam Clerks office RE: Freeman Justice Center Change order #1 ENCLOSED PLEASE FIND THE FOLLOWING ITEM(S): NO. DATE COPIES DESCRIPTION 2 3/30/05 2 Chan~e order #1 for your tiles THESE ARE TRANSMITTED AS CHECKED BELOW: X For Your Use o For Review and Comment D Approved as Noted DReturned for Corrections o Copies for Approval REMARKS: CMD025-9/11/95