04/05-19
PURCHASE / SERVICE ORDER
FOR
MONROE COUNTY
To: URS
Purchase Service Order No.
04/05-19
Re: PSA Agreement, Dated 1-1-02
Resolution No.
Project Name: Key West Intemational- Hangar Development RPR
Description of Services:
Fees for Resident Inspection for the extended time of the project due to the permit
delays from the Corp. of Engineer and other time extension justifiable by the
Contractor due to plan modifications and construction changes on Hangars 9, 10, 11
and 12.
Multiple of Direct Salaries
Lump Sum
x
Reimbursable Expense
Days to Complete 180
Fee this Service Order $ 59.400.00
Not-to-Exceed
Payment for Services shall be in their entirety as per PSO.
..J~
::>
'Jl
c...
C
r-
N
CD
<-'i'l
~~
,
Milford A. Reisert
o ","
-"P'" ....-'
;0 C"') :.::
orx
f'Tl~-<
. r-
0("')'
c;-o:::::::
';0
~ ("') r- Pi
;< ~ :T.: (.r.) (")
"'T'l' Y .. (:J
r C') W :::J
1- ('1- os-- :> ," CD-"
MONROE COUNTY ATTORNEY
OVED AS 0
o
Prepared by:
....""....
"......,i
Date: t:' ~ 2? -CJ 5
Date:
CM1{i~~
Date: ~ !~/65'
Approved by:
Accepted by:
KEY WEST INTERNATIONAL AIRPORT
HANGAR DEVELOPMENT, TAXILANES, AND APRON
URS CORPORATION
6/15/2005
MAN-HOUR ESTIMATE
DESCRIPTION SUBTOTAL TOTALS
RESIDENT INSPECTION
Based on 125 calendar day contract-time
125 davs*5davs/7davs= 90 days
Labor 90 days*8(hrs.ldav)=720 hours
720 hours* $55/hr= $39,600.00
Sub Total Resident Inspection Cost $39,600.00
Note: -The above estimate covers until May 29,2005
Possible construction time extension until July 31, 2005
Based on 63 additional calendar day contract-time
63 days*5days/7days= 45 days ,
Labor 45 days*8(hrs.lday)=360 hours
360 hours* $55/hr= $19,800.00
i
Sub total additional Resident Inspection Cost $19,800.001
i
Total Resident Ins"ection Cost ! $59,400.00
F\KEYWES1\HANGAR\ T -HANGAR PROJECnPSORPR(6-15-05).xLS
00/30/2005 18:37
3052'338118
KAWA CONST
MEMO
DATE: June 30, 2005
TO: Peter Horton. Airport Manager
FROM: KWIA Hangar Corporation
R E: Key West 'ntern.tlona' Airport
Hangar Dev.lopment. T....an... and Apron
RPR Costa
This I. to Inform you that the KWIA Hangar Owner. haye agr.ed
to pay our ahar. of the Increased RPR cost In the amount of
$23.000.00.
Karl W t...., Tr.asured
KWIA CorporBtlon
PAGE 01