06th Change Order 09/02/2005 ~ I MEMORANDUM TO: Board of County Commissioners From: Thomas J. Willi County Administrator Date: September 1, 2005 RE: Change Orders Attached is a proposed change order for The Tower Group, for the Freeman Justice Center. (Change Order #5 is for $73,969.57 for Revised Fire-Rated Walls and the associated Doors, Frames and Hardware.) According to the ordinance adopted by the Board of County Commissioners, proposed change orders are to be presented to members of the Board of County Commissioners prior to approval, assuming they are within the Administrator's prescribed limits. Change orders not within the Administrator's authority are placed on the BOCC agenda. The Administrator intends to approve this change order on Friday, September 2, 2005. ,r---' ;i . f. \, -of l - . /- '. #,._. < _. I" y---.----./'''-----. ;;/-, /{-- '1(' /VI(/ I( !., ~-- >--p__l~.;.. -'I \. I :, Debbie Frederick Deputy County Administrator DF:adc HP Fax Series 900 Plain Paper Fax/Copier Fax History Report for Thomas J Willi Co Admin 305-292-4544 Sep 01 2005 7:57am Last Fax Date Time ~ Identification Duration Pages ~esult Sep 1 7:45am Sent SPEHAR 1:26 4 OK Sep 1 7:47am Sent NEUGENT 2:23 4 OK Sep 1 7:50am Sent McCOY 2:55 4 OK Sep1 7:54am Sent NELSON 1:46 4 OK Sep 1 7:56am Sent RICE 1:26 4 OK Result: OK - black and white fax MoNROE COUNTY / ENGINEERING /FACILITIES DEVELOPMENT CONTRACT CHANGE ORDER PROJECT TITLE: Freeman Justice Center (Name and address) 500 Whitehead St. Key West, FI. 33040 CHANGE ORDER NO: 6 INITIATION DATE: August 29,2005 CONTRACT DATE: June 16, 2004 TO CONTRACTOR: The Tower Group Inc. (Name and address) 405 S.W. 148TH St., Suite 1 Davie, FI. 33325 THE CONTRACT IS CHANGED AS FOLLOWS: See The Tower Group Inc. Proposed Change Order NO.8. Cost to remove decking & depress slab related to prestressed concrete joists and soffit beams. The original (Contract Sum) (Guaranteed Maximum Price) ........................................ $13,804,000.00 Net change by previously authorized Change Orders.... ... . ..... . .. .... . . ... . ..... . . . ... . ...... .... $60,319.40 The (Contract Sum) (Guaranteed Maximum Price) prior to this Change Order was... ...... $13,864,319.40 The (Contract Sum) (Guaranteed Maximum Price) will be (increased) (decreased) (unchanged) by this Change Order ................. $57,737.50 The new (Contract Sum) (Guaranteed Maximum Price) including this Change Order is ... $13,922,056.90 The Contract Time will be (increased) (decreased) (unchanged) by .................. (12) days The date of Substantial Completion as of the date of this Change Order is (June 29,2006) Not valid until siQned bv Owner. Construction ManQer and Contractor ARCHITECT: itects Date 51 c" ~S Date CONTRACTOR: CONSTRUCTION MANAGER: ,-~,-~.s Date 7'- 2 -0:> Date 9/2/uS I I COUNTY ENGINEER: COUNTY ADMINISTRATOR THE TOWER GROUP.c General Contractors Construction Management Construction Design-Build Planning Site Development Infrastructure Consulting Estimating Scheduling Value Engineering Post Construction CGCA38309 August 18, 2005 0417-01035 Jose Gonzalez GONZALEZ ARCHITECTS 32 E. Bay St. Savannah, GA 31401 8 MONROE COUNtY CONSlftUCllON MANAGEMOO f/lU~". n~ .. If{. d ~. ~~~ Fax: 912-201-0240 RE: Freeman Justice Center (FJC) Subject: Requestfor Change Order No.8 Dear Mr. Gonzalez: Attached for your review and approval please find The Tower Group Change Order Request No.8 dated August 18, 2005 in the amount of $57,737.50 for the additional material, labor and extended overhead cost to lower 12 deck panels to accommodate the 1st floor concrete deck design deficiencies. Please be reminded of the chronological sequence of communication regarding this subject as follows: 1. July 20, 2005 TTG submitted RFl No. 00134. (See attached RFI) 2. July 2 1,2005 TTG brought this problem to your attention again in our Weekly Project Meeting. (See attached Meeting Minutes item No. 110) 3. August 8, 2005, TIG sent letter No. 01001 to Gonzalez Architects again requesting a written directive how to proceed. (See attached letter) 4. August 8, 2005, TIG received memorandum from Gonzalez Architects directing TTG to slightly drop panels in conflict. (See attached memo) 5. August 10, 2005, TIG sent letter No. 01011 to Gonzalez Architects indicating receipt of Gonzalez Architects memorandum, and notifYing work is on hold pending receipt of cost from EBG and reserving our rights for a contract time extension. (See attached letter) 6. August II, 2005, TIG received memorandum from Gonzalez Architects, stating "It is the responsibility of the contractor to coordinate their subcontracts, as required, to implant the solution." (See attached memo) 7. August 18, 2005, TTG submitted Request for Change Order No.8, in the amount of $57,737.50. (See attached Change Order) In closing, the critical path progress of this project is on hold, pending the receipt of a fu Ily executed Contract Change Order. Time is of the essence. STffaln,Jfn Gregory F. Galmin Vice President CC: Alan French, MCCM File Encl. 405 SW 1 48th Avenue' Suite One' Davie. Florida 33325 . Tel: 954. 4 76' 3200 . Fax 954' 474' 3111 7601 SW Lost River Road' Stuart Florida 34497 . Tel: 772' 287' 7525 . Fax: 772 -287' 7524 9440 Philips Highway, Suite#5 . Jacksonville, Florida 32256 . Tel: 904' 292' 1811 . Fax: 904. 292' 4865 CHANGE ORDER UWNt::K [] AKt.;HII t::t; I [] CONTRACTOR [] FIELD 0 OTHER 0 AlA DOCUMENT G701 PROJECT: 0 o o CHANGE ORDER NUMBER: DATE: CONTRACTOR PROJECT #: 8 0417 TO CONTRACTOR: The Tower Group, Inc. 405 S.W. 148th Avenue Suite # 1 CONTRACT DATE: 6/16/2004 Davie, Florida 33325 The Contract is changed as follows: (See attached sheet) Subtotal---------________ Contractor Fee - Credits-------___ $ Total.--------___._ $ 57,737.50 Not valid until signed by the Owner and Contractor. The original (Contract Sum) (Gllarantees Maximllm Price) was........................................._....... $ Net change by previously authorized Change Orders................................................................. $ The (Contract Sum) (GllaraAlees MaxiFRllm Price) prior to this Change Order was..................._ $ The (Contract Sum) (Gllaranteed MaxiFRllm Price) will be (increased) (decrea!:ed) (unchanged) by this Change Order in the amount of.........._.........._..................................... $ The new (Contract Sum) (Gllaranloed MaximuFR Price) including this Change Order will be....._ $ $ 13,804,000.00 $ (13,650.17) $ 13,790,349.83 $ 57,737.50 $ 13,848,087.33 The Contract Time will be (increased) (decreased) (llnch:lnged) by The date of Substantial Completion as of the date of this Change Order therefore is 12 Calendar days Gonzalez Architects ARCHITECT 2720A North Roosevelt Blvd. The Tower Group, Inc. CONTRACTOR 405 S.W. 148th Avenue Suite # 1 Monroe County O'NNER 1100 Simonton Street, Address Address Address Key West, Florida 33040 Davie, Florida 33325 Key West, Fl. 33040 BY BY BY DATE DATE DATE CO#8Sht#1 CHANGE ORDER AlA DOCUMENT G701 OVVNER ARCHITECT CONTRACTOR FIELD OTHER Q o Q o Q PROJECT: CONTRACTOR: o o o The Tower Group, Inc. 405 S.W. 148th Avenue Suite # 1 Davie, Florida 33325 Item # The Contract is changed as follows: Description: 1 2 CHANGE ORDER NUMBER: DATE: ARCHITECT'S PROJECT NO: 8 1/011 900 0417 CONTRACT DATE: 6/1 6/2004 C.O. Amount EGB PCO #12 (See attached) TTG Extended Overhead Cost (12day impact @$2,126.67/day) $27,733.16 $25,520.04 1. This proposal excludes all additional permitting costs. 2. This proposal excludes any premium time or accelerated delivery costs. 3. This proposal is valid for (7) Seven days and subject to escalation thereafter. 4. We exclude all costs associated with Electrical, Mechanical, and all other disciplines not specifically identified 5.This lump sum proposal is based on estimated direct costs, such as labor, material, equipment and extended overhead cost. 6. We reserve the right to submit the cost for any and all of the aforementioned, as well as related items of costs including the accumulative of changes and the aggregate prior to the final job closeout. 7. The additional time estimated to complete this sequence of work is approx. 12 Cal. days Your prompt and immediate response is required. If you have any questions or require further clarification, please do not hesitate to contact me. Subtotal $53,253.20 Contractor Fee 5% $ 2,662.66 Bond 1% $ 523.53 Subtotal $56,439.39 Builders Risk Ins. 2.30% $ 1,298.11 Total $57,737.50 CO#8Sht#2 Contractor Name Date: August 17, 2005 The Tower Group Job Name: Freeman Justice Center Greg Galmin Job Location: K~ West, Florida Fax 296-2587, 954-474-3111 PCO # 12 ---.... ~I 11"'\'''\.:11:: u/"'(Ut:K J U GENERAL CONTRACTOR E.G. BRASWELL CONSTRUCTION INC. 5565 SECOND AVENUE KEY WEST, FLORIDA 33040 PHONE 305.296.0305 FAX 305.296.1824 Changes to Project: Cost to remove decking & depress slab related to prestressed concrete joists and soffit beams. SPI Estimate of extra charges Additional concrete, rebar, labor 20,115.79 4,000.00 24,115.79 Sub-Total 3,617.37 Overhead / Profit (15%) 27,733.16 Total Proposed I ncrease to Contract Accepted by Signature Printed Name and Title Approved by: Rene May, Contro E.G. Braswell Construction Inc. ..-- ... ....."'... lr.I,iJ;"r1r1 r~u~~tructural Prlstrlssld Ind. 3055569696 T-OS9 P.OOI/OOI F-9aO CGC # OS820~ - _~I STRUCTURAL PRESTRESSED . INDUSTRIES, INC. SUBCONTRACTOR CHANGE ORDlYf CONTRACI'OR: l. G. BRASWELL DATEI AUGUST 16, 1005 CHANGE ORDER NO. ; 2 KEY WEST, PL. SoP.I. JOB III 04.7% SUBCONTRACTOR I PROJECT I Structural PrestrCllcd Indwtries Freman ]UJtice FaCility 11405 N.W. 138th ST. TRADl: Miami, FL. 33178 PrQStIw8ed COl:lCrele loifta IIId aoffit beams. OESer Of CHANGE ORDER: Cost to remove decklnc:l-& deer... slsb. 1 400 man hours to remove/deck X S27/hr. $10,BOO.00 2 3 rm..X4 nlaht&X$88.09/rm.+ Per DIem Cost $2,057.08 3 Added Coat of Stringers & Ellis Jaek.a. . .- $4,980.00 4 One Truck Load from MiamI to KevWeat. S4e0.OO SUbtotal $18287.08 P A 0 10% $1,628.71 Total $20 115. 7Sl O~~ALSDBCONTRACTAMOUNT '- . . PREVIOUSLY ISSUED CHANGE ORDERS J SUBCONTRACT AMOUNT PRIOR TO THIS C.O. AMOUNT OF THIS CHANGE ORDER NEW SUBCONTRACT AMOUNT{Jneludina this c.o.} ~ . J Please acknOwledge your acceptance and return an executed original to S.P.I.. Contractor Acceptance: Signature: Printed Name: Title; Date : a:'Il~~'~1a,: "Manufacturers and Erectors of Quality Prestressed/Precast Products" 11405 N.W: 138th Str~et · Miami, Florida 33178 · Tel (305) 556-6699 . Fax (305) .556-9696 www.struQuralprestressed.com ..... u\;.; ..I. VYVt:I uroup, Inc. REQUEST FOR INFORMA No. I - 507 Whitehead St Key West, Fl 33040 AiTLE: Phone: 305-296-2521 Fax: 305-296-2587 PPC RFI 50 PROJECT: Freeman Justice Center (FJC) DATE: 7/20/2005 JOB: 0417 TO: Attn: Monica D'Ambra Gonzalez Architects Phone: 954-443-8292 STARTED: COMPLETED: REQUIRED: 7/22/2005 REQUEST: Attached is self-explanatory RFI 50 from Patrick Power Corporation, please review and respond as soon as possible. R,qU"':ttt:P:" Gmup, Inc. Signed: A~ , Tim Clarke Date: 7/7tJ/or , E;(~di!ion:!l .-t.NSWER: Answered By: Gonzalez Architects Date: Signed: Monica D'Ambra FREEMAN JUSTICE CENTER REQUEST FOR INFORMA nON tI,f'S DA TE: 7/20/2005 RF/# PPC# 050 TOWER GROUP # PROJECT: . FREEMAN JUSTICE CENTER FROM: JOSE CLAUSELL /IVAN CASAMAYOR PA TRICK POWER CORP. 5691 NW 14TH AVE. FT LAUD, FLA. 33334 PHONE 305 296 4454 FAX 305 296 4454 CELL 954 325 9890 TO: TOWER GROUP 405 SW 148 AVE. DAVIE. FLORIDA PHONE 954476- 3200 FAX 954 4743111 DESCRIPTION: CAN THE CONDUITS FOR THE SM.RM, SN AND REAL TIME REPORTER BE A 3/4" CONDUIT FOR THE FLOOR BOXES? A 1" CONDUIT WILL NOT FIT IN THE SLAB PLEASE SEE ATTACHED DETAIL AND SPESIFICA TION. ALSO THERE WILL BE CASES I WHICH I WILL ONLY HAVE 1/2" COVER OF CONCRETTE ON MY CONDUITS IS THIS OK? SEE SECOND SKETCH# 2 : CONTRACTOR RECOMMENDATION: COST IMPACT: RESPONSE: NAME: JOSE CLAUSELL : ~ G.A. 9300 1.13 Jackson Square Renovations Monroe County Facilities Freeman Justice Center 09/02 3.1 WIRING METHOD A. Outdoors: Use the following wiring methods: I. Exposed: electrical metallic tubing (EM1) 2. Concealed: electrical metallic tubing (EMT) 3. Underground, Single Run: rigid nonmetallic conduit (PVC). 4. Underground, Grouped: rigid nOnmetallic conduit (PVC). 5. Conn<<ti'" 10 Vib"'ling Eq,ipm,nt fool'ding "=fo"",,, and hydmulie, pneumalie, 0' electric solenoid Or motor-driven equipment: Iiquidtight flexible metal conduit. 6. fndoo" 0' 0",<100", Cona,etion to vib"'ting 'quipment and hYd",lie, pneumatic, 0' el,eleie ,ol'noid 0' mOlo<-driven 'quipm,nt in moi" 0, humid fooation 0' eorro,ive almosphe", 0' where subject to water Spray or dripping oil, grease, or water: liquidtight flexible metal conduit. S. Indoors: Use the following wiring methods: I. Conn,etion to Vib""'ng Equipm,nt fnel'ding """fonn,,, and hyd"',lie, pneumatic 0' eleeleie solenoid or motor-operated equipment: flexible metal conduit 2. Exposed: electrical metallic tubing (EMT) 3. Concealed: electrical metallic tubing(EMT) 3.2 lNST ALLA TION A. Gen,ml, fn"all 'Ieeteieal '""way, in "co,dane, with manufaeru"" w";ll<n installation instrue"o.ns, applicable requirements of NEe, and as follows: B. Conceal COnduit 'nd EMf, ''"'" indieat,d oth"wi", within fini,h,d wal~; e'ilin." and "00". K"p ",e,way, at I,a" 6 inch" 'w'y from P","I,I run, of "," and "earn o. hot W'le, pipes. ''''tall raceways level and square and at proper elevations. C. Elevation of R"""y, Wh... POS,ibfe, install horizontal mceway run, 'hove w.t" >nd '''''un piping. O. Complete in'tall.tion of el<<tri"" "'''w'y, b,fo" miring in'tallation of eond""o,", wiibin """"y,. E. Provide supports for raceways as specified elsewhere in Division 16. F. Prevent foreign matter from entering raceways by using temporary closure protection. G. Protect ,rub-ups f.om d"""", wh,,, eondui~ rise from llco, '1,,,,. Anang, '0 eu",," portion of bends is not visible above the finished slab... _.. . H. Make bends and om,~ so th, inside di_,,, i, nOI 'ff<<tively "due,d. Vnl", orn'nNi" indicat'd, keep the legs of a bend in the same plane and the straight legs of offsets paraJlel. I. Use me,w.y fitting, th,t Me of types 'ompatibl, with th, ",coi'''d "e,w,y and ,uitable fo, th, use "'d loo,.;on. Fo, in"nnedlat, '''01 ,ondui, use Ih",ded rigid "eel ,ond"it fittings ex"p." oth'""ise indicated. J. Run eone"l,d me,,,,,,, with , mini"'"m of b'n'" in lhe 'hort"t pmelioal di"an" eonsid'ring tJ" type of building eoo',,"etioo ""d ob,truetions ex"pt " oth'""i" indie'ted. Thi, does no' 'ppiy to conduits in crawl spaces. K. ",,,w,y, ,mb'dd'd in ,,"", ""'" in middf, thi.d of!h, ,f,b !hi'kn,,, wh", pmeli,,1 and leav, a, I,,,t I inch cone"" 'OV". Ti, "ee",y, to "infonoing 'ods 0' oth'""i" '''u" th,", to p'ovenl '",ging o. ,hifting d"ring 'O'e"" P""m,nt. Sp,e, ""w'y, I"'mlly to P"V,nt void, in th, eOneme. Run 'ond,it I"g" than '-inch "'d, ,i", "",lid with o. ,. right "'gl" 10 Ihe m,in "info.e'm,nt; wh,,, ,. tighl ""g'" to th, "infote,m,n, th, eo,d"" ,h," be dose 10 on, of the supports of the slab. Where nonmetallic conduit or tubing is used, raceways must be converted to Schedule 80 Or rigid steel conduit or tubing IMC before rising abOve floor. L Ins"" 'xposed """'y, p","" and P''Peedlo,,'.. to ne"by ,un,,,, o. "n"'",,1 m'mbe" and follow the surface contours as much as practical. M. R" 'xposed, P'''"e!, 0' bankod ""w'y, tog,,'''. Mok, bend, in p....II'1 o. b'nk'd run, f,"m th, same center line so that the bends are parallel. Factory elbows may be used in banked runs only where th'ye,n b, in'''"'d p",",r. Thl, "qui,,, tho! th", b, ',h,ng, in th, p""" ofth, run 'ueh " rrom w,lIto "ill fig Md thO! th, "'''''y' b, of th, "mosi". 'n oth,,,,,,,, p'ovld, field beeds fo, p...II,1 raceways. RACEWAYS 16110-3 Zll III liz" L{/" ~ IIzI t Ii- ,I z I"~ CtJVE/C.. . 3/'1- (( ~N.D{/IT ,II c-() V &/Z. / j II CI/4-/,e Z- -ri JOB NO.: F:J ( DESCRIPTION: 1 0 ITE M: 5 {,,/Jl3 rZ I! tt./hJ/1 t"L-#/ c<r1 .-. .--....- . '~.. BY: T c.t. AdiCl[ PAGE OF THE TOWER GRaUE 'U--'~ /' --;:Fr ,v It .1 , ,. , · ATTYI rt '" t 1~ <,H~ ~.' l:t2f .;:;-. / to ._;\ ." ... 7 ~ " : ( '(:.. rI ~ I I@ ~C re J/jI>' rB . 10., ~ L :.J 'J r Ll:.. ~10- I -t--u- 4"-0- 11 -. I I , I .\: '7 "V II IUJoa, ';t-I'\.. II " ~ ~~ rl1c y-- I fj'- '~ '\; ( I (')3 II: 1,3 . l:;> " '~~ "1/1 f~. / ~ I <E r ' , ~ ~ V /' / / 'fi I ,./t--r--,....."" ! / (, ~ IV! J I. f rr T.., I ftil if ~.::; " ~. <I I \A.)8 '/1 i ~ w'f-J; ~ ...... ...... .~ \V, -----:: V '-- I ~ Y'-. '~. -; /-l ....... jr~lrv;"j"f __ ~ V V ~ ffj ..."'. ., 1\ ~ I D?'~I ? .. e ~ . I ~ "" r------- /" I:- .-/ :'~; ~ [fi~ ~~ ~ '- / ,./ r ~ !- - .~ ~ ~J J~ ~-J ~ ~ rr '. , i I I I i I ! ! ~/ '~ -- y~.~~ GONZALt~ . ''''''''.l.t:, & C&A ~ lfIrEC!s 303-234-821,7 p, .Jl.ln 13 OS 07:05a Th. To~~~ G~ou~ k.~ w.~~ ~((!l ;. Sf:" ~;'!-f~ .- Po FREEMAN JlISTlce c=. FDo ~o__~ ~ ,,~"~ .OU~ ;;1 DATE: SlfaJ200s R:FCJ PPCIt ~, 'rO~eR GftO\J~. PRoJ~CT: J=R.e~WN JtJSnCf ceNTER __ ~ JOS1: C~lll rvAN Co\s~ ~ TRIC1( PV1"tI:R CO€"-- __ "'., Hw "'" "ve. >7 ~~ p-.~-..... """...2)0.... L""""",_ TO: ~CR ~1.1P ~"'~F'L~~' ---.. --=== PwoHl:.i.S4 ~ 3200 FAl': asc ~4 3111 _ iiil~~i~w- = - - =----. = -~ = = -- =- -- C~~lII/~T1ON: ..::.-. =- =- ---- -- -- -=- ----."'~ .. -----.--. COST '''''~''CT; -- -~._-- ~E:~'JOS~~eu __ -"""''' .. ~~ ~,~. j~ - .~~.~~~~ Lo~.~ ~~_.. ~- ~ ~ -f=- ~ '''':;'. 'q'~ 5ysrBH WffLIs,- JI.JH I D ;'->s ,:.:; The TowerGroui~:ft~_ i ~-_. ,"11N 1 ", :::11.':" ~-;: 'J 1 :~<"I :: ';.; ,.,~ .,~, F:>S 'J .' -.. . """oa rh~ ro~.~ G~gy~ K.M ~..e J05-Z9-f_a,17 p, 405 <:93 ~.,~~ P. FREE.\fAN JUSTICE CENTER BEotrFS'T "'" ~~ OAT~; t:l1l1r'2~ ~ PP-Czo4Q r~~6 ~OJECT; "~NJ~ IIFI'I c~ J"pAcT: - The Tower Group, Jnc. ...rJ:~ l}I~C"ll~ C7:~j :(.) ;;"::'j I;~~'~:" 1""9.;. .j -..--- - . -.... ----- - -. --. -- ._-----~ ----.. -. '. /' ;7 -' u-., I:i n~ WI: (J ~ ~ o.nl;s;rs 30~-29f-8217 p~ Th~ lo~~r Group k~~ u.s~ .~ . :JOS C:~ ~ Ci:!on P. : FREalAN JUSTICE C€~E~ .B......~uSSr.FOIf ~TIQt! "fl'f DATE: 6N~ "'" l'Pc. .,. t Q~ ""':1!:.~ '" _ ~ROJeCT: f:~~US1"JC:e ____ FRo." .100< O~, ~~ ~.AYOft _ E6.n:ucK P co D:; ~~ B!LNW 14TH 4VE. FT '":"FiA: ~ !!<O..~.... F.o.x "'......... CEll: ~~ _ _ TO; TOWl;:R~~_. ____.._ ~ SW ~<U1_.;.;o' ClltV'd; FLO~OA __ !'H~"!L'" Co."". F.u... C.,," __ OE3c~pno," ~~~~.~KOO=~T~_= .~t~~~~.E~~~~= ~!.~J~'~r;:~.~~~ __ ~._._---=- ----- CC>>w"TluCTOR ilt..!!CO.Lf~ENOA T/0N: .....:---- ---... =.= ~=- -------.."----- --: ~~ COST IMPAC't~ -- --- -----.. -- .Jl'l~ I..\.::~l(.~ i.:I:.c; ~I'" ':.1'7 f "'~"..., ..l...:r~.;. J . ....'" "''''111\'-'100 \00.....\01111 I l;111,.f 1f1C:~ 1f111 +3052954321 T-oza P.OI4/019 F-333 FREEMAN JUSTICE CENTER finished mth underground except sally port area. TTG is waiting for GA update on sally port bathroom elimination and floor drain connections. Monica D'Ambra (GA) is on vacation. No other contact (on this issue) with GA since last week's meeting. (8/4/05). TTG win prepare C.D.R. to reflect changes to sally port per GA revisions. (8/1l/05). OPEN 106. Final Count on Security Cameras: P.P needs to know about all additional cameras ASAP. (7/14/05). PP needs final count & locations on cameras. (7/21/05). MCCM response to GA security revisions was faxed to Monica D' Ambra on July 27, '05. MCCM has no objection to the proposed changes other than the comments included on this faxed response. (7/28/05). No response from GA (8/4/05). (8/11/05). OPEN 107. Monolithic Floor Pours: ITG: Floor pours are continuous monolithic pours and will start at 3:00 am. ITG needs permission from Key West Bldg. Dept. to waive noise ordinance and aIJowthis to happen. (7/14/05). Monolithic pours begin August 19th. 'ITG will contact Joe April (Key West Bldg. Dept.) to arrange noise ordinance waiver to allow work after hours, i.e. early AM to late P.M and Sundays. (7/21105). (7/28/05). (8/4/05). TTG will talk to Joe April today to advise him of TTG intent to perform an early a.m. pour. (8/11/05). OPEN 109. Pile Cap Survev & Site Survev: MCCM requestS master sheet of pile cap survey and copy of site survey done last month. Also MCCM requests confirmation tbat there are 5 Pistorino & Alam visits remaining on the llil round of credit to MCCM by way of C.O. #1. (7/14/05). (1/21105). (7/28/05). TTGto verify number ofP&A visits and establish when first found of inspections expires, second round begins. Surveyor O'Flynn will be on site today or tomorrow to work on site survey and to investigate a suspected 4" discrepancy along column line uD" discovered yesterday. (8/4/05). TTG received 3 copies of site survey (up to 1" floor including columns & deck). MCCM will receive 1 copy. TTG: 22 P&A visits have been used so far including today's visit. Two more visits remain on the rIrst round of inspections. Second round will begin when these two are finished. (8/11/05). OPEN 110. Conduit Interference in 1st FIr. Slab: J. Clausell (PP) states insufficient concrete clearance when 1 n conduit crosses other conduit in 4 ~" floor slab. He suggests using two %" conduits. GA will look into this. PP states that exterior wall mounted lights shovro at el. 21'-9" are in conflict with post-tensioned beam cable. PP recommends lowering lights 1'-0", GA will look at this_ (7/21/05). PP proposes direct burial flex conduit (MC-EZ-lYK Armor Cable) to minimize clearance problem. GA will verify with P&A (7/28/05). ITG requests immediate direction from GA and P&A as to how to proceed. PP needs to install conduit which allows Meeting No. 36 13 August II, 2005 AUi-15-2005 16:44 From-MONROE COUNTY ENGINERING +3052954321 T-028 P.OI5/0Ie F-333 FREEMAN mSTICE CENTER less than %" concrete coverage. Also, floor boxes will not allow concrete to flow properly between boxes and deck forms. Without immediate response, TTG will be delayed on floor pour scheduled August 19, '05. TTG will produce a model of the problem. rIDS ISSUE IS URGENT. (8/4/05). J. GiJnzalez met with TTG & MCCM on Monday August 8, '05 to discuss this item. GA sent memo directing deck fonns to be dropped. ITG sent letter of response #01001 August 8, '05 stating intent to prepare cost proposal. GA recommends ~S" clips to drop 10 deck form panels. (Neither SPI nOr EGB are aware of these deck support devices.) Can GA advise how they can be installed or even obtained? ptherwise TTG can not utilize this option and will need to shore forms from below. THIS IS MORE COSTL V TO THE OWNER. MCCM requests GA to continue discussion with TTG on this issue by calling J. Gonzalez after the meeting. TTG requests MCCM to authorize a cost account not to exceed $15,000 for lowering and shoring deck panels in the event the method suggested by J. (rl)nzaJcz is not feasible. ITG replaced 20 deck panels identified by MCCM as not acceptable quality. H ITG receives GA directive today stating that lTG will be compensated, work will not be deJayed. S. Coffer will attempt to contact J. Gonzalez by phone after the meeting. [This attempt at contact was not successful.] (8111/05). OPEN 112. Dowels Cut at Post-Tensioned Beam Columns: Six columns (col. 2 ,3, 4,50,5], & 52) at ends of post-tensioned beams are missing 3 dowels (cut by EGB because the bends were improperly oriented). TTG awaiting response from P&A on repairs. (7/28/05). EGB is chipping tops of columns to allow new dowels to be installed. Repairs may be finished in time for Johnny Clavijo (P&A) to inspect next Tuesday. (8/4/05). Columns 20 & 30 are also constructed improperly with vertical dowels not showing correct bends at the lilt to 2aW floor intersection and will be chipped out and re-built. AU six oftbese columns were inspected by Pistorino & AIa.m at the time they were built in February of this year, but no discovery of error occurred until this week (Aug. 10th) when Contractor attempts to tie ground floor columns to In floor columns. [This is another example of the failure of structural inspections to reve3J errors in construction or to identify details which are unclear until after the work is in place and needs to be demolished.] Johnny Clavijo will inspect today. (8/11/05). OPEN 113. Coordination Drawin~: TTGto submit coordination drawings (sheet metal shop drawings as base, sprinkler, electrical, SPI & structural overlays). Must be DWG files, not plOt files, (7/28/05). (8/4/05). lTG will issue in 3-4 weeks. (8/11/05). OPEN Meeting No. 36 14 August 11,2005 THE TOWER GROUP, General Contractors Construction . Management Construction Design-Build Planning Site Development Infrastructure Consulting Estimating Scheduling Value Engineering Post Construction CGCA38309 August 8, 2005 0417-01001 Jose Gonzalez GONZALEZ ARCHITECTS 32 E. Bay St. Savannah, GA 31401 Fax: 912-201-0240 RE: Subject: Freeman Justice Center (FJC) First Floor Concrete Deck Conflicts Dear Mr. Gonzalez: As a follow up to our conversation today regarding the structural and electrical design conflicts associated with the first floor concrete deck, please provide a written directive how we are to proceed with the contract document change in scope of work. Upon receipt of your letter of directive, we will evaluate the cost and time impact to the project critical path and advise you of our findings accordingly. Should additional time and cost be required for this change in scope, then we reserve our right to time extensions and associated costs. Thank you for your attention to this most critical matter. Sincerely, f!~ Gregory F. Galmin Vice President CC: Alan French, MCCM File 405 s,w. 148th Avenue' Suite One. DaVie. Florida 33325 . Tel: 954'476' 3200 . Fox: 954' 474' 31 ) 1 7601 S.w. Lost River Road. Stuart. FlOrida 34497. Tel: 772'287'7525 . Fox: 772'287'7524 9440 Philips Highway. Suite#5 . Jacksonville. Florida 32256 . Tel: 904 '292' 1811 . Fax: 904' 292 '4865 . ,; J8,2005 17:09 GONZALEZ ARCnIrECTS Ine TOWer Group Ke~ West 305-294-8217 305 293 6299 p IE p Pa9~ Gonzalez Architects Architecture * Plannm!: ,. IJlterion MEMORANDUM - Date: August 08, 2005 'i~: . " .. Gr~~lmin. The Tower Group From: Jose A. Gon7a1e7.. NCARB AlA - . ..... ~... .. -. --.-..- Project: FreComan JUStice Building Re; RFT #134 - So'ution ~ .-...,.... . ..---- eel , .any Cha/m..., Pi"",,,,, of C 0""""""00 & Plann;"". Monroe C"un'y ----.....-. .,..- --..-'-'-. .-..... ---. . -.-.. -- ._--..~.._-~ ~. ... ~ -. ~.. . . In resronse to the allove, the solution ;s as foUows: III areas where lbe .I""'rical eooduiLs e,os., and adequa.e enY""'Be cann.t be met, rhe PSI syStem fonnwoa can be dropped .I;gbt/y.t those 10c;Wons with One layer of "".doit onder rhe ..""!. 32 E.., Bay S'mt, Savannah, C...... 3'''1 · (912)20 '-9888,1>.. ("")201-02.0 2720... N....h ll00aevelt Blvd.. Key W"', Florid. 33040 . (305)294-37... Fax (305)294-8217 1602 Alto. R"d,l'MB 503, M....,. Hooch, Florid. 3'1J9 . (305)~72-9tl44. Fax (305)86&-8324 THE TOWER GROUF: General Contractors Construction Management Construction Design-Build Planning Site Development Infrastructure Consulting Estimating Scheduling Value Engineering Post Construction CGCA38309 August 10, 2005 0417-01011 Jose Gonzalez GONZALEZ ARCHITECTS 32 E. Bay 5t. Savannah, GA 31401 Fax: 912-201-0240 RE: Subject: Freema/l Justice Center (FJC) First Floor Concrete Slab CO/ljlicts Dear Mr. Gonzalez: The Tower Group (TTG) is in receipt of your memorandum dated August 8, 2005, responding to the first floor concrete slab structural and electrical design conflicts. Presently our structural subcontractor E.G. Braswell and their pre- cast joist subcontractor SPl are reviewing the areas of concern and are developing their cost and time estimate to solve the problem in the field. As previously stated, all remedial work in the effective areas in conflict are on hold pending our submittal, the owner's approval and TTG receipt of a fully executed contract change order. TTG reserves its rights to claim for delays, time extensions including extended general condition cost and all other additional costs when the full extent of the impact of this change order is known. Thank you for your attention to this matter. Sincerely, II~ Gregory F. Galmin Vice President CC: Alan French MCCM File 405 s.w. 148th Avenue' Suite One. Davie, Florida 33325 . Tel: 954. 476' 3200 . Fox: 954' 474. 3111 7601 S.w. Lost River Rood' Stuart, Florida 34497 . Tel: 772' 28 7. 7525 . Fax: 772' 287. 7524 9440 Philips Highway, Suite#5 . Jacksonville, Florida 32256 . Tel: 904. 292' 1811 . Fox: 904' 292. 4865 "... .. ......"" 1;.1.1,,11,,1 rrom-MONROE COUNTY 2NGINERING +305225432 I T-OI3 P.002/00Z F-31~ III MONROE COUNTr CONSffilJcnON MANAQEMQ AUG Deft Gonzalez Architects Architecture ... lllanning · Interiors MEMORANDUM Dale: August I 1,2005 .' .. ...-..-.. Lury Chalmer::;, Director of Const~~?~. &._~!~~!!lg, Monroe CClunty los~ A. (ionzale7., NCARfi AlA -.- ". Freeman Justice Bltilding -'-- ., ..-........ --.-05 -/'"' I . -.... .:- ~ .., ..........-0 ~ r:r: ~..1 To: From: Project: Re: . .. ......., .... Cc: ConclCtu Slau Atom French .-.... ...........--....... .~ & We have given 'podfl< di...<tion to the ,on""",o,. The: Tow," 01<>"1'. wid, refe,,,,,c. !v "',,'Jvi,,~ thi3 issue of concrete cOv~t~ge. lL is t1a~ I c:spuu.sibiliLy IIf thr; t;lIULI'"~ctur lu c.:ullnJinalc thl:u- subcontractors. alll '\;quil tal., l~, j,"pJt:II/t:llt Lite .'iuJuLiulI. 32 E~J.llt Day Stttltlt, ."lavannlth, Gl'llrgia 31401 .., (912)201-9888, Fax (9 J 2)20 '-02411 2720 A North ROosevelt Dlvd., J'(ey We...t, Florida 33040 '" (305)294-3748. Fax (305)294-82J 7 1602 Arrlln Uuad, PM8 503, Miami Beach, Florida 33139 * (30S)672-9044, jl'u (305)1166-8324