Change Order No. 1 CHANGE ORDER NO. (j) (/ Job No. 401-002.10K Project Title: Renovation and Upgrading of Duck Key Bridge #2 Contractor: Alonzo Cothron. Inc. Contract Date: Ma rch 22. 1982 Alonzo Cothron. Inc. To: Route #1. Box 55B Islamorada. Florida 33036 You are directed to make the changes noted below in the subjec Attest: By: Dept. Da te: APproV~d s To Correctness and Form I By: ~ A ttorney for Monroe County. Nature of the Change: The contractor has requested an additional time extenslon of 120 days to complete the contract. Based on our review of his justification we have determined the following: (A) That inclement weather was a factor in not completing the Bridge on time. (B) That although the Bridge was not completed on time. those items requiring completion were of a minor nature: painting. paving. placement of flower urns. (C) That although not entirely complete. the Bridge was open for beneficial use of the local residents and construction equipment within the alloted contract time. (D) That as mitigation for the claimed oversight. he has verbally agreed to not pursue a claim for additional monies on Duck Key Bridge #1 in the amount of $3.258.90. Based on the above. we recommend that an extension of 120 days be granted. No additional monies are required by the change request. The changes result in the following adjustment of Contract Price and Time: Contract Price Prior to this Change Order: Net Increase Resulting from this Change Order: Current Contract Price Including this Change Order: Contract Time Prior to this Change Order: Net Increase Resulting from this Change Order: Current Contract Time Including this Change Order: Contract completion date is May 10. 1983. Prepared by: Richard C. Peper $194.689.00 -0- $lQ4.figQ nn 240 days 120 days 360 days Date: 'ir. .IJ'!J Th ~'6~ 1/- I1J2;(j Da te: Title: